+ All Categories
Home > Documents > 40517-013: Annual Environmental and Social Compliance ......Project Type (Operational) HFO fired...

40517-013: Annual Environmental and Social Compliance ......Project Type (Operational) HFO fired...

Date post: 16-Oct-2020
Category:
Upload: others
View: 0 times
Download: 0 times
Share this document with a friend
49
Annual Environmental and Social Compliance Audit Report Project No. 40517-013 Annual Report April 2015 2454-BAN: Public-Private Infrastructure Development Facility Prepared by Infrastructure Development Company Limited for the Asian Development Bank.
Transcript
Page 1: 40517-013: Annual Environmental and Social Compliance ......Project Type (Operational) HFO fired Power Plant to be developed on BOO basis Prect Type (Awarding) oj IPP1 1.2 AREA AND

Annual Environmental and Social Compliance Audit Report Project No. 40517-013 Annual Report April 2015

2454-BAN: Public-Private Infrastructure

Development Facility

Prepared by Infrastructure Development Company Limited for the Asian Development Bank.

Page 2: 40517-013: Annual Environmental and Social Compliance ......Project Type (Operational) HFO fired Power Plant to be developed on BOO basis Prect Type (Awarding) oj IPP1 1.2 AREA AND

This environmental audit report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

Page 3: 40517-013: Annual Environmental and Social Compliance ......Project Type (Operational) HFO fired Power Plant to be developed on BOO basis Prect Type (Awarding) oj IPP1 1.2 AREA AND

Loan No. 2454-BAN-OCR

Public-Private Infrastructure Development Facility

ANNUAL ENVIRONMENTAL AND SOCIAL COMPLIANCE AUDIT REPORT

108 MW Power Project at Kolagaon, Chittagong, Bangladesh

ECPV Chittagong Limited

April, 2015

Prepared by

INFRASTRUCTURE DEVELOPMENT COMPANY LIMITED

Page 4: 40517-013: Annual Environmental and Social Compliance ......Project Type (Operational) HFO fired Power Plant to be developed on BOO basis Prect Type (Awarding) oj IPP1 1.2 AREA AND

2

TABLE OF CONTENTS

Executive Summary…..………………………….…………………………………..……………..6

1. Introduction………..………….………………….……...………………………………………..8

1.1 Project proponent.…….…..……………….…….…….……………...………………………………8

1.2 Area and location of the project…………..…….…………………………………….………..…….8

1.3 Brief description of the project……………..…………….………………………….…….……..…10

1.4 Objectives of environmental and social compliance audit……..…….………….……………….11

1.5 Methodology ….………………………..……………………………………….………...………….11

1.6 Reporting period………………………..……………..………………………….…………………..12

1.7 Changes in project scope……………..……………………………………….………..…………..12

1.8 Environmental monitoring ……………..………………………………….…….…………………..12

2. Regulatory Requirements………………………………………………………….………….…………13

2.1 ECR, 1997 of Bangladesh Government………………………………………………………..… 13

2.3 SPS, 2009 of Asian Development Bank……………...……………….….……………….………13

2.4 ESSF of IDCOL………………………………………………………………….……………………13

3. Status of Project Implementation….....………………..…………...................................................14

3.1 Implementation of electro-mechanical and civil components….…….……….…………….……14

4. Implementation of Environmental Safeguards………………………….……………………………15

4.1 Compliance with ECR, 1997…………………………..…………..…………………….…….……15

4.2 Compliance with EMP……………………………………………………………………….……….15

4.3 Compliance with ADB requirement……………….…………………………………….………..…24

5. Implementation of Social Safeguards…………………………………………………..…………..…26

5.1 Impact on resettlement and livelihood ….…………………………………………………….……26

5.2 Institutional arrangement for social safeguards ………………………………………….……….26

5.2 Impact on indigenous people………………….. ………………………………………….……….27

5.3 Child labour…………………………………..………………………………...………….….………27

5.4 Public consultation and disclosure of information …………...……………...……………………28

6. Corrective Action Plan ………………...……….……………………...…….………………………….29

7. Conclusion…………………………………….…………………………………………………….…..…30

Page 5: 40517-013: Annual Environmental and Social Compliance ......Project Type (Operational) HFO fired Power Plant to be developed on BOO basis Prect Type (Awarding) oj IPP1 1.2 AREA AND

3

Annexure

Annex-1: Environmental Clearance Certificate………...………………………….……..………………...31

Annex-2: Location of the project site……...……………………….…………….…….…….………………32

Annex-3: Project risk rating checklist of ESSF, IDCOL……….………….………….………………….…34

Annex-4: Arrangement of workers’ shed..…….………………….………….………….………………..…35

Annex-5: PPE arrangement and medical check up.…………….………….………….………………..…35

Annex-6: Dust management………….………………….………….………………………….….…………36

Annex-7: Construction of fuel storage tank…………….……………………………………..….…………37

Annex-8: Consultation with local community during construction phase.…….…………..….… ………38

Annex-9: List of some participants in consultation…….……………………………………..….…………39

Annex-10: Fuel treatment process………….…………….……………………………………..…..….……40

Annex-11: Stack….………..………………………………………………………………….…………….…40

Annex-12: Closed oil transportation process.……………………………………………………………….41

Annex-13: PPE arrangement….………………………………………………………………..……….……41

Annex-14: Fire fighting arrangement ….…………………………………………………………….………42

Annex-15: Application of signage….. ….………………………………………………………….…………42

Annex-16: Current status of project (external view)….……………………………………….……………43

Annex-17: Current status of project (internal view)….……………………………………….……….……44

Annex-18: Housekeeping …………………………………………………………………….………………45

Annex-19: List of male respondents during consultation in operation phase……… ……...……………46

Annex-20: Boundary wall……………………………………………………………….… …….……………47

Page 6: 40517-013: Annual Environmental and Social Compliance ......Project Type (Operational) HFO fired Power Plant to be developed on BOO basis Prect Type (Awarding) oj IPP1 1.2 AREA AND

4

List of Abbreviations

ADB Asian Development Bank

CCC Chittagong City Corporation

DOE Department of Environment

ECR Environment Conservation Rules

ECPVCL Energypac-Confidence Power Venture Chittagong Limited

EHS Environmental and Health Safety

EMP Environmental Management Plan

ERP Emergency Response Plan

FGD Focus Group Discussion

IDCOL Infrastructure Development Company Limited

IEE Initial Environmental Examination

PPE Personal Protective Equipment

SPS Safeguards Policy Statement

Page 7: 40517-013: Annual Environmental and Social Compliance ......Project Type (Operational) HFO fired Power Plant to be developed on BOO basis Prect Type (Awarding) oj IPP1 1.2 AREA AND

5

List of Tables

Table 1.1: Project related basic information…………...………….……………….….…..………………...8

Table 1.2: Geographic location of project site……………….…………..…….……..….….………………9

Table 1.3: Distance of project site from major infrastructures.………..…….……..…..….………………9

Table 1.4: List of major equipment……...……………………….…………….….……..….……….………10

Table 1.5: Engine specifications..…….………………….………….……………….….………………...…10

Table 1.6: Generator specifications.…………….………….………….……………….……………..…..…11

Table 3.1: Project progress………….………………….………….…………………….…….….…….……14

Table 4.1: Compliance with ECR, 1997.…….…………..….… ……………………….………………...…15

Table 4.2: Response of ECPVCL on major project activities (construction phase)….…..….……….…16

Table 4.3: Major environmental and social issues and implementation of corrective action plan….…18

Table 4.4: Monitoring parameters and frequency (trial run)…………………….………….….……….…18

Table 4.5: Ambient air quality ……………………………………………………..…….……………..….…19

Table 4.6: Response of ECPVCL on major project activities (operation phase)……..….………...……21

Table 4.7: Monitoring parameters and frequency (operation phase)……..….…………………………..23

Table 4.8: Compliance status on major E&S issues during construction and operation phases…..…24

Table 6.1: Gap between E&S compliance and corrective actions…………………….……………….…29

Page 8: 40517-013: Annual Environmental and Social Compliance ......Project Type (Operational) HFO fired Power Plant to be developed on BOO basis Prect Type (Awarding) oj IPP1 1.2 AREA AND

6

EXECUTIVE SUMMARY

Background

Considering the importance of electricity, the Government of Bangladesh (GOB) has adopted a number of initiatives including implementation of power plant through independent power producer (IPP) modality by private sector. The 108 MW HFO based project of Energypac Confidence Power Venture Chittagong Limited (ECPVCL) is an example of this initiative of Government of Bangladesh.

Through a competitive bidding process Bangladesh Power Development Board (BPDB) has selected ECPVCL to establish and operate an HFO based power plant by using Julda or Shikalbaha sub-station, Chittagong under a 15-year Power Purchase Agreement (PPA). Accordingly ECPVCL has purchased required land at Kolagoan Union of Patiya Thana, Chittagong. The generated electricity will be sold to BPDB.

For financial assistance ECPVCL has approached Infrastructure Development Company

Limited (IDCOL), along with other lenders. Considering the importance of the Project to meet

the national power demand, IDCOL has provided a term loan facility of USD 30 million in

favour of the Project. IDCOL has sourced the required financing from the fund allocated as

ordinary capital resources (OCR) for large infrastructure projects under Public-Private

Infrastructure Development Facility (PPIDF) of Asian Development Bank (ADB).

The project has been classified as B under Safeguards Policy Statement, 2009 of Asian

Development Bank (ADB) in regard of environmental compliance. But in consideration of

Indigenous People (IP) and Involuntary Resettlement (IR) aspects the project has been

classified as C. According to the Environmental Conservation Rules (ECR), 1997 of the

Department of Environment (DOE), Bangladesh the project belongs to Red category. In

addition, the Environmental and Social Safeguards Framework (ESSF) of Infrastructure

Development Company Limited (IDCOL) has categorized the project as High Risk project.

So, a comprehensive Initial Environmental Examination (IEE) Report has been prepared for

the project by Bangladesh Centre of Advanced Studies (BCAS) as ‘Environmental

Consultant’ appointed by ECPVCL.

To assess the actual implementation of environmental management plan and social

safeguards, respective IDCOL official visited the project site during construction and

operation phases. According to the IEE, there is requirement of IDCOL to submit annual

Environmental and Social Compliance Audit Report of this project to ADB. Accordingly, this

audit report has been prepared by IDCOL.

Audit overview and findings

The respective IDCOL official has visited the project during the audit period (July 2014 to

April 2015). He has also reviewed the available relevant documents and clearances. In

addition, there was consultation with senior representatives of adjacent neighborhood. The

audit period encompasses two phases viz. construction (upto December 2014) and

operation (from January 2015). During construction phase, ECPVCL had been found to be

Page 9: 40517-013: Annual Environmental and Social Compliance ......Project Type (Operational) HFO fired Power Plant to be developed on BOO basis Prect Type (Awarding) oj IPP1 1.2 AREA AND

7

satisfactorily responsive in regard of environmental and social safeguards. But during

operation phase they need to consider the following issues with due importance:

Monitoring of air, water and noise quality and adopt required mitigation measures

based on the monitoring data (if required);

Introduce comprehensive EHS guidelines, which will describe the detail procedure

about complying with Environmental Management Plan (EMP);

Develop a competent EHS team with required competence;

Arrange emergency response facility including training on fire-fighting, earthquake

hazard management;

Adopt well-structured Grievance Redress Mechanism.

Page 10: 40517-013: Annual Environmental and Social Compliance ......Project Type (Operational) HFO fired Power Plant to be developed on BOO basis Prect Type (Awarding) oj IPP1 1.2 AREA AND

8

1.0 INTRODUCTION

1.1 PROJECT PROPONENT

Energypac is a reputed name in electro-mechanical sector in Bangladesh. Confidence

Group is a trusted name in cement and ready mixed concrete, lead-acid battery and

electro-mechanical products. The captioned project is a joint initiative of these two well

acknowledged entrepreneurs. As special purpose vehicle, the project proponent has been

jointly named as Energypac Confidence Power Venture Chittagong Limited (ECPV

Chittagong Limited). The project related major information are as follows:

Table 1.1: Project related basic information

Project Company ECPV Chittagong Limited

Date of Incorporation 21 August 2011

Registration Number C-94987/11

Registered Address 79 Shahid Tajuddin Ahmed Sharani, Tejgaon I/A, Dhaka

1208

Trade License Number & Issuer No: 0948634; Dhaka City Corporation

TIN Number 211-202-3847/C 20

Type of Business Power Generation

Project Location Kolagaon, Chittagong

Capacity 108 MW

Fuel Type HFO

GenSet Supplier Rolls-Royce

Off-taker BPDB

Project Tenure 15 Years from the COD

Project Type (Operational) HFO fired Power Plant to be developed on BOO basis

Project Type (Awarding) IPP1

1.2 AREA AND LOCATION OF THE PROJECT

It The project site is located at Kolagoan Union of Patiya Thana under the jurisdiction of

Chittagong City Corporation (CCC). The area of CCC is about 157 sq. kilometres. The land

having an area of about 6 acres has been purchased by ECPVCL. The site is about 9

kilometres away from Shah Amanat International Airport, Chittagong and about 5

kilometres away from the Chittagong Port. The site is about 270 kilometres away from the

capital Dhaka. The location of the project in respect of Chittagong city Corporation area

and adjacent area is presented in Annex-2.

1 IPP means Independent Power Producer

Page 11: 40517-013: Annual Environmental and Social Compliance ......Project Type (Operational) HFO fired Power Plant to be developed on BOO basis Prect Type (Awarding) oj IPP1 1.2 AREA AND

9

A B

D C

Table 1.2: Geographic location of the project site with schematic lay out

Point Latitude Longitude

A 22o20.064/N 91 o 52.510/ E

B 22 o20.013/ N 91 o52.448/ E

C 22 o19.975/ N 91 o52.614/ E

D 22 o20.030/ N 91 o52.625/ E

Source: GPS survey by IDCOL

Along the BC, AB, DA and CD are access road& vacant land, neighborhood, vacant land &

Western Marine Shipyard, and Karnaphuly River respectively.

Table 1.3: Distance of project site from major infrastructures

Major Infrastructure Approx. areal Distance from site

(kilometer)

Julda 132VV Sub-Station 4

Shah Mirpur 132KV sub-Station 9.5

Bangladesh Navy Bases/Jetty 6.5

Chittagong Port 5.5

Shah Amanat Bridge on Karnaphuli River 1.5

Bangladesh Naval Academy 10

Eastern Refinery, & BPC Chittagong Oil Depots 8.5

KAFCO 10

Shah Amanat International Airport 9

Marine Academy 7.5

Shikolbaha 120MW Power Plant 4

Page 12: 40517-013: Annual Environmental and Social Compliance ......Project Type (Operational) HFO fired Power Plant to be developed on BOO basis Prect Type (Awarding) oj IPP1 1.2 AREA AND

10

1.3 BRIEF DESCRIPTION OF THE PROJECT

The technology involves for power generation of ECPVCL108 MW power is mainly based

on reciprocating engines. The primary fuel is HFO. There are 16 (sixteen) reciprocating

engines of 7.2 MW each to be coupled with alternator to generate electricity. The following

Table 1.4 shows list of major equipment as have been used in this power plant.

Table 1.4: List of major equipment

The engine model B32:40V16A manufactured by Rolls-Royce for the 108 MW HFO based

power plant is 4-stroke, turbocharged, inter-cooled. The following Table 1.5 shows detail

technical specifications of the engines.

Table 1.5: Engine specifications

Equipment Unit Country of Origin

Rolls-Royce B32:40V16A 16 Norway

Generator (AvK make DIG 167/d8) 16 Germany

11/132 kV Step-Up Power Transformer 2 Bangladesh

11/ 0.415kV Distribution Transformer 2 Bangladesh

Indoor and outdoor switchgear 21 Bangladesh

Power Transformer Control Panel 2 Bangladesh

Current Transformer (132KV) 2 Bangladesh

Particular Specification

Model B32:40V16A

Number of cylinders 16

Engine speed (rpm) 750

Maximum Continuous Alternator Rating 6984 kW

Cylinder bore 320 mm

Piston stroke 400mm

Mean effective pressure (BMEP) Bar 24.9

Altitude above sea level (max) 100m

Turbocharger air suction temperature (max) +35oC (25oC)

Charge air cooling water inlet temp +42oC (25oC)

Relative humidity 70%@35oC

Page 13: 40517-013: Annual Environmental and Social Compliance ......Project Type (Operational) HFO fired Power Plant to be developed on BOO basis Prect Type (Awarding) oj IPP1 1.2 AREA AND

11

The generators are synchronous, three-phase, brushless, salient pole and marine types. The

generators are designed to operate together with B32:40V16A engines. The following Table

1.6 shows technical specifications of the generators.

Table 1.6: Generator specifications

1.4 OBJECTIVES OF THE ENVIRONMENTAL AND SOCIAL COMPLIANCE AUDIT

The audit has been conducted with the aim to assess the project’s compliance with-

(i) Environment Conservation Rules (ECR)1997 of GOB;

(ii) Environmental and social safeguards according to the Environmental and Social

Safeguard Framework (ESSF) of IDCOL;

(iii) Environmental and social safeguards according the Safeguards Policy Statement

(SPS), 2009 and other relevant standards and guidelines of the ADB;

(iv) Proposed mitigation measures and monitoring procedures according to the

committed environmental management plan (EMP), resettlement action plan (RAP)

as are applicable.

1.5 METHODOLOGY

The audit includes the following steps:

(i) visits the project site and consult with stakeholders especially local people;

(ii) review the environmental and social safeguards documents including environmental impact assessment report, EMP and Resettlement Action Plan (as are relevant) ;

(iii) assess actual implementation of the guidelines/action plan of the safeguard related

documents.

Parameters Description

Make CGT ( AvK)

Type DIG

Construction IM 1101 (B20), Two bearings

Output 6984 kW(e) 8730 kVA

Power Factor 0.80

Voltage 11 kV

Frequency 50Hz

Generator speed 750 rpm

Insulation Class F

Page 14: 40517-013: Annual Environmental and Social Compliance ......Project Type (Operational) HFO fired Power Plant to be developed on BOO basis Prect Type (Awarding) oj IPP1 1.2 AREA AND

12

1.6 REPORTING PERIOD

The reporting period of this Environmental and Social Compliance Audit Report is

July 2014 to April 2015. During this reporting period upto December 2014 was

Construction phase and from January 2015 has been considered as Operation

phase.

1.7 CHANGES IN PROJECT SCOPE

There is no change in the technology and operational process as have been declared

by the respective government and accepted by ECPVCL. So, it can be said that the

Environmental Management Plan of ADB approved Initial Environmental Examination

(IEE) is fully applicable during the reporting period as well.

1.8 ENVIRONMENTAL MONITORING

The parameter, frequency and methodology of environmental monitoring are in

accordance with EMP of ADB approved IEE, as has been detailed in chapter 4 of this

audit report.

Page 15: 40517-013: Annual Environmental and Social Compliance ......Project Type (Operational) HFO fired Power Plant to be developed on BOO basis Prect Type (Awarding) oj IPP1 1.2 AREA AND

13

2.0 REGULATORY REQUIREMENTS

2.1 ENVIRONMENT CONSERVATION RULES, 1997 OF BANGLADESH

The project has to comply with the Environment Conservation Rules (ECR), 1997. According

to the categorization of ECR, 1997, the project has been categorised as Red2 meaning that

it has significant adverse environmental impacts, which are to be mitigated with proper

mitigation measures.

2.2 ENVIRONMENTAL AND SOCIAL COMPLIANCE RELATED STANDARDS AND

GUIDELINES OF ASIAN DEVELOPMENT BANK

The project has to be complied with Safeguards Policy Statement (SPS), 2009 of ADB in

regard of environmental and social (E&S) compliances. Considering the adversity of

environmental impacts, it has been categorized as B from environmental safeguard point of

view. Accordingly an IEE has been prepared, which is already approved by the ADB. As no

record of any indigenous habitat has been found in Kolagaon, the project has been

categorised as C in respect of Indigenous People (IP). In addition, as there was neither any

issue of involuntary resettlement (IR) nor adversely affecting any income generating activity,

the project has been categorised as C from IR perspective.

2.3 ENVIRONMENTAL AND SOCIAL SAFEGUARDS FRAMEWORK OF IDCOL

IDCOL has adopted an Environmental and Social Safeguards Framework (ESSF) in 2011,

which is to be complied with all infrastructure projects as are to be funded IDCOL. According

to the environmental categorization of ESSF, the project has been categorised as High

Risk3 project requiring significant compliance safeguards including comprehensive

environmental impact assessment and regular monitoring. In consideration of social

categorization, the project has been categorised as Low Risk project both for Indigenous

People (IP) and Involuntary Resettlement (IR) perspectives.

2 Schedule-1 of ECR (project no. 6 of Red category), 1997

3 The project risk screening checklist of ESSF, IDCOL is provided in Annex-3

Page 16: 40517-013: Annual Environmental and Social Compliance ......Project Type (Operational) HFO fired Power Plant to be developed on BOO basis Prect Type (Awarding) oj IPP1 1.2 AREA AND

14

3.0 STATUS OF PROJECT IMPLEMENTATION

3.1 STATUS OF IMPLEMENTATION OF VARIOUS ELECTRO-MECHANICAL

COMPONENTS

The status of progress of implementation of major electro-mechanical and civil components upto 15 April 2015 are as follows:

Table 3.1: Progress of implementation of electro-mechanical and civil components

Type of

component

Component Percentage of

accomplishment

Ele

ctr

o-m

ec

ha

nic

al c

om

po

ne

nt

Generator 100

Exhaust gas system 100

Ventilation system 100

Intake air system 100

Lube oil system 100

Cooling water system 100

Electrical works 100

11KV/230 KV sub-station 100

11/0.4 KV auxiliary transformer 100

Gen-set control panel/MCC panel/VCB panel (switch gear) 100

Testing & Commissioning 100

230 KV HT cable terminations and Transmission Towers 100

TBS and RMS 100

Fire Fighting System4 95

Civ

il c

om

po

nen

t

Power house and warehouse 100

Internal and external drainage 100

Road surface 100

Administrative Building 100

Septic tank and soak pit 100

Water reservoir of fire hydrant 100

The photographs of current status of various project components are provided as Annex-15

and 16.

4 The firefighting system is already installed (Annex-14). It is now under the process of testing

Page 17: 40517-013: Annual Environmental and Social Compliance ......Project Type (Operational) HFO fired Power Plant to be developed on BOO basis Prect Type (Awarding) oj IPP1 1.2 AREA AND

15

4.0 IMPLEMENTATION OF ENVIRONMENTAL SAFEGUARDS

4.1 COMPLIANCE WITH ENVIRONMENT CONSERVATION RULES, 1997

ECPVCL has to comply with the requirement of ECR, 1997 of the DOE. In the following

Table 4.1, the compliance status of ECPVCL, in regard of major milestones of ECR, 1997 is

depicted.

Table 4.1: Compliance with the requirement of ECR, 1997

Basic Requirement Compliance Status

Approve IEE Fully complied

Approve EIA Fully complied

Award Site Clearance Certificate Fully complied

Award EIA approval Fully complied

Award Environmental Clearance Certificate Fully complied

4.2 COMPLIANCE WITH ENVIRONMENTAL MANAGEMENT PLAN

4.2.1 COMPLIANCE WITH EMP DURING CONSTRUCTION PHASE

a. Institutional arrangement

ECPVCL had formed an Environmental and Health Safety (EHS) Team comprising three full-

time personnel, to look after the environmental, social and occupational health safety

aspects. The EHS team is led by Mr. Khan Mohammad Mehbub Hossain. He is a graduate

Electrical Engineer having basic orientation on EHS aspect. He was assisted by two diploma

engineers. The overall EHS implementation at Project site was monitored by Mr. Md.

Ashekus Salam. He is a graduate Electrical Engineer having about 15 years’ experience in power sector. He was involved in a number of power projects including 100 MW power

project of Energypac at Gopalganj.

At the corporate level, the EHS aspect was monitored by Mr. Md. Mainuddin. He is an

experienced Mechanical Engineer. He has completed the Lead Auditor Course of ISO

14001:2005 (Environmental Management System).

b. Compliance status

In the IEE, a number of activities having potential adverse environment impacts and

occupational health safety aspects have been identified. In the following Table 4.2, suitable

mitigation measures to address these impacts according to the EMP and responses by

ECPVCL have been given.

Page 18: 40517-013: Annual Environmental and Social Compliance ......Project Type (Operational) HFO fired Power Plant to be developed on BOO basis Prect Type (Awarding) oj IPP1 1.2 AREA AND

Table 4.2: Response of ECPVCL on major activities and potential impacts (construction phase)

Project activity Potential Impacts Proposed mitigation measures as per EMP Actual Implementation Status of

compliance

Influx of workers

Generation of

sewage and solid

waste

Construction of sanitary latrines and septic tank system

Erecting “no litter” sign, provision of waste bins/cans, where appropriate

Proper disposal of solid waste

Sanitary latrines were provided

To ensure proper solid waste disposal, various types of waste bins were found to be practiced.

Fully complied

Possible spread of

disease from

workers

Clean bill of health a condition for employment

Regular medical monitoring of workers

There was a dedicated doctor to conduct weekly medical monitoring of workers (Annex-5)

Fully complied

Transportation of

equipment,

materials `and

personnel; storage

of materials

Deterioration of air

quality from

increased vehicular

movement, affecting

people in the

surrounding areas

Keeping vehicles under good condition, with regular

checking of vehicle condition to ensure compliance with

national standards and EHS guidelines (as applicable)

The available vehicles were found mostly of satisfactory condition, based on visual observation

Partially complied

Wind-blown dust

from material (e.g.

fine aggregate)

storage areas

Watering the access road

Sprinkling and covering stock piles

Covering top of trucks carrying materials to the site and

carrying construction debris away from the site

Access road was found to be watered

Stock piled had been found to be

covered (Annex-6)

Partially complied

HFO Oil storage

tank

Soil contamination Oil storage tank should be well protected against

leakage.

The construction of oil storage tank

has been found as satisfactory

(Annex-7)

Fully complied

Site clearance Topographic change

by cutting existing

trees, shrubs, herbs,

and filling land

Adopt such type design as is required minimum cutting

of trees, shrubs, herbs, and low-land filling

Use waste shrubs, herbs as organic fertilizers

Adopt required measures to prevent waste shrubs,

herbs as fuel to cook or for any localized burning

purpose.

Basic design of the project has been

found as land efficient i.e. ensuring

optimum use of land.

As the project site was a low lying

land having irregular terrain, there

was neither significant shrubs nor

trees.

Partially complied

Page 19: 40517-013: Annual Environmental and Social Compliance ......Project Type (Operational) HFO fired Power Plant to be developed on BOO basis Prect Type (Awarding) oj IPP1 1.2 AREA AND

17

Project activity Potential Impacts Proposed mitigation measures as per EMP Actual Implementation Status of

compliance

Noise from

construction

equipment

operations and

maintenance

Noise could exceed

the allowable limit

and result in hearing

loss

Use of noise suppressors and mufflers in heavy

equipment

Avoiding, as much as possible, construction equipment

producing excessive noise

Avoiding prolonged exposure to noise by workers

Creating a buffer zone by introducing green belt around

the Project site

Follow construction scheduling to avoid evening and

nighttime disruption

Workers were found to be equipped

with required PPE.

Most of the noise intensive work had

been reported to be accomplished

during day time

Partially complied

Dust during

construction and

exhaust gases from

construction

machinery and

vehicles (particulate

matter, NOx, SO2)

Increased SPM,

NOx, SOx levels at

construction sites,

and surrounding

areas

Avoiding equipment usage such as stone crushers at

site, which produces significant amount of particulate

matter

Immediate use of construction spoils as filling materials

Immediate disposal/sale of excavated materials

Continuous watering of bare areas

Ready-made stone chips were used

The evidence of using construction

spoils as filling materials was

observed

Watering was observed in bare areas

(Annex-6)

Partially complied

Fires, explosion and

other occupational

health safety related

issues

Risk of human

health and property

damage

Use of personal protective equipment during construction and maintenance.

Prepare and implement safety and emergency manual.

Regular inspection of lines for faults prone to accidents.

Provision of fire protection equipment.

Provision of Lightening arrestors

Fire extinguishers were found in the site.

Evidence of regular inspection of lines for faults prone to accidents, had been observed.

Partially complied

Page 20: 40517-013: Annual Environmental and Social Compliance ......Project Type (Operational) HFO fired Power Plant to be developed on BOO basis Prect Type (Awarding) oj IPP1 1.2 AREA AND

ECPVCL has been found responsive about satisfactory complying with EMP requirement.

While visit in July 2014, IDCOL had identified some areas requiring corrective actions.

ECPVCL’s response in regard of this proposed corrective actions are documented in Table 4.3.

Table 4.3: Major environmental and social issues and action plan

Issue Required corrective action Status of implementation

of corrective action

House keeping The standard of house-keeping at project site needs to be

improved to minimize the risk of accidents and associated

pollution.

Fully complied

Availability of

PPE

There is scope to increase the number and quality of PPE, in

respect of actual demand.

Fully complied

Documentation The induction training and other relevant issues need to be

more structured. In addition, social safeguards especially

grievances need to be properly documented and duly

resolved.

Partially complied

C. Environmental monitoring

I. Technical approach of environmental monitoring

According to the IEE, no environmental monitoring has been required in the EMP during

construction phase except during trial run. Because usually trial run phase is considered as

the final milestone of construction phase. According to the EMP, the monitoring requirement

during trail run is as follows (Table 4.4):

Table 4.4: Monitoring parameters and frequency of monitoring during trial run

Key parameters to be monitored: (1) Ambient Air Quality

location frequency parameter

At Project site, residential/institutional/commercial

areas within 500m outside from plant boundary

(4 locations)

Once during trial run SOx, NOx and CO

Key parameters to be monitored: (2) Noise

location frequency parameter

At four corners of Project boundary,

residential/institutional /commercial areas within 100m

and 300m outside from plant boundary

Hourly basis for 24

hours during trial run

Limits in dBA

Page 21: 40517-013: Annual Environmental and Social Compliance ......Project Type (Operational) HFO fired Power Plant to be developed on BOO basis Prect Type (Awarding) oj IPP1 1.2 AREA AND

19

Table 4.5: Ambient air quality at project site dated on 4 August 20125 (baseline condition)

Location PM2.5

(µg/m3)

PM10

(µg/m3)

SOx

(µg/m3)

NOx

(µg/m3)

CO

(ug/m3)

At project site from the

Karnaphuli River side

11 18.24 0.85 1.64 0

Standard of DOE 65 150 365 150 10

Figure 4.1: Ambient hourly noise of project site from Karnaphuli River side (4 August 2012)

II. Result of environmental monitoring

There was no air and noise quality monitoring during trial run.

III. Disclosure of environmental monitoring

As disclosure of environmental monitoring, ECPVCL is required to keep monitoring result available at

project site. But neither air nor noise quality was monitored during trial run, no result has been made

available for disclosure purpose.

IV. Monitoring adjustment measure

As there was no monitoring, the requirement of monitoring adjustment was not determined.

5 During IEE preparation phase, the ambient air and noise quality were assessed on 4 August 2012.

Page 22: 40517-013: Annual Environmental and Social Compliance ......Project Type (Operational) HFO fired Power Plant to be developed on BOO basis Prect Type (Awarding) oj IPP1 1.2 AREA AND

20

4.2.2 COMPLIANCE WITH EMP DURING OPERATION PHASE

a. Institutional arrangement

ECPVCL is in the process to form an Environmental and Health Safety (EHS) Team, which

would be headed by Mr. Mostafizur Rahman. Mr. Rahman is serving as Plant Manager. He

is a retired Marine Engineer having orientation on EHS aspect of power project. He is well

conversant with Integrated Management System (ISO 14001, OHSAS 18001, and ISO

9001). Before joining ECPVCL, he was involved with Orion Group for power projects. He is

expected to be assisted by a team of engineers. But the activities has been found as

informal as there is yet any comprehensive EHS implementation plan and systematic

practice of EHS implementation.

At the corporate level, the EHS aspect is expected to be monitored by Mr. Mainuddin. In the

earlier section, his qualification and competence in regard of environment and social (E&S)

safeguards has already been discussed. It is expected that like construction phase, he will

play the leading role in EHS implementation during operation phase as well.

b. Compliance status

In the IEE, a number of activities having potential adverse environment impacts and

occupational health safety aspects during operation phase have been identified. In the

following Table 4.6, suitable mitigation measures to address these impacts according to the

EMP and actual responses by ECPVCL has been given.

Page 23: 40517-013: Annual Environmental and Social Compliance ......Project Type (Operational) HFO fired Power Plant to be developed on BOO basis Prect Type (Awarding) oj IPP1 1.2 AREA AND

Table 4.6: Response of ECPVCL on project activities and mitigation measures during operation phase

Project Activity Potential Impacts Proposed mitigation measures in EMP Actual implementation Compliance

status

Transportation of

HFO oil to the plant

Possible spillage and leakage of oil

during storage

Oil should be stored through close piping system Oil has been found to be

stored through closed piping

system (Annex-12)

Fully complied

Emission from the power plant Using 27 meter tall stack

Installation of stack emission monitoring equipment for major pollutants

Planting of indigenous trees around the Project site

27 meter tall stacks have been installed

Partially complied

Generation of noise from

generators and associated sub-

stations , which could exceed 70

dB(A) at site boundary

Locate facility 70–100 m from nearest receptor;

Use walls, fencing, and/or greenbelt to provide partial noise barrier

Provision of silencers or generators an turbines (if need arises)

Use of ear-muffs and ear-plugs by plant personnel working in the generator and turbine facilities of the plant

The project is about 100 m away from nearest settlement.

Walls are being installed as noise barrier (Annex-20)

Ear plugs were being used as noise barrier.

Partially complied

SO2 generation from the engine,

which has adverse health impact

Use low sulfur (0.5 %) content fuel.

Distillate fuel oil to control SO2;

If the SO2 emission is more than standards, desulfurization measure is to be adopted

ECPVCL has installed fuel treatment plant. So, it can be said that the sulfur content in the fuel is within the limit of acceptable standard (Annex-10)

Fully complied

Suspended particulate matter

(SPM) and PM2.5, PM10 generation

from the engine, which can

adversely affect health

Use fabric bag filter to reduce particulate matter before discharging the emission.

Good combustion control, required stack height

should also be maintained properly

Fabric bag has been introduced.

Partially complied

Page 24: 40517-013: Annual Environmental and Social Compliance ......Project Type (Operational) HFO fired Power Plant to be developed on BOO basis Prect Type (Awarding) oj IPP1 1.2 AREA AND

22

Project Activity Potential Impacts Proposed mitigation measures in EMP Actual implementation Compliance

status

Power generation Electro-magnetic wave or electrical

interference, which may result in

occupational health risk.

All equipment should be grounded earthing with mesh system.

Power plant to sub-station should be connected by HT cable.

Power plant & substation site is away from the settlement.

No house is located in the immediate vicinity of the site.

Relevant equipment have been grounded.

Power plant to sub-station has been connected by HT cable.

Power plant & substation site are away from the settlement.

No house is located in the immediate vicinity of the site.

Fully complied

Heath safety during

operation

Risk of human health and property

damage

All necessary safety equipment should be ready at the plant.

Regular training on safety needs to provide.

PPE were found to be practiced.

Partially complied

Fires, explosion and

other accidents

Risk of human health and property

damage

Use of personal protective equipment during operation and maintenance.

Prepare and implement safety and emergency manual.

Regular inspection of lines for faults prone to accidents.

Provision of fire protection equipment.

Provision of Lightening arrestors

There are fire extinguishers

Automated firefighting system is in the final stage to install (Annex-14).

Partially complied

Domestic wastewater

and sewage

BOD, fecal coliform contamination

in groundwater and surface water

Need to provide septic tank with soak pit for

treatment of sewage.

Septic tank with soak pit for treatment of sewage.

Fully complied

Wastes oil from Plant

(scrap metal, waste,

lube oils, spill oil etc)

Potential soil and groundwater

contamination

Secure on-site storage, waste sell to the DOE authorized vendor for discharge in a safe place.

Used lube oil is being sold to DOE designated vendor.

Fully complied

Page 25: 40517-013: Annual Environmental and Social Compliance ......Project Type (Operational) HFO fired Power Plant to be developed on BOO basis Prect Type (Awarding) oj IPP1 1.2 AREA AND

c. Environmental monitoring

I. Technical approach of environmental monitoring

In the EMP of the IEE, environmental monitoring has been required during operation phase.

The air, water and noise quality monitoring schedule are depicted in Table 4.7.

Table 4.7: Monitoring parameters and frequency of monitoring during operation phase

Key parameters to be monitored: (1) Ambient Air Quality

location frequency parameter

At Project site, residential /institutional

/commercial areas within 500m outside from

plant boundary.

Quarterly (routine) analysis SPM, SOx, NOx

Key parameters to be monitored: (2a) Surface Water

location frequency parameter

Project site at Kolagaon Bi-annual basis in each year (pre-

monsoon and post-monsoon)

pH, Temperature, DO,

BOD, COD, TDS, Oil

and grease

Key parameters to be monitored: (2b) Ground Water

location frequency parameter

Project site at Kolagaon Bi-annual basis in every year (pre-

monsoon and post-monsoon)

pH, Temperature, DO,

BOD, COD, TDS, Oil

and grease

Key parameters to be monitored: (3) Noise

location frequency parameter

At four corners of Project boundary,

residential/institutional /commercial areas

within 100m and 300m outside from plant

Quarterly (routine) analysis (four

times in each year)

Limits in dBA

II. Result of environmental monitoring

ECPVCL is yet to conduct air, water and noise quality monitoring.

III. Disclosure of environmental monitoring

As disclosure of environmental monitoring, ECPVCL is required to keep monitoring result

available at project site. But as there is yet any monitoring result, no result has been made

available for disclosure purpose.

IV. Monitoring adjustment measure

Based on the monitoring result of the project during operation phase, it will be determined

whether there is necessity of any adjustment or mitigation measures.

Page 26: 40517-013: Annual Environmental and Social Compliance ......Project Type (Operational) HFO fired Power Plant to be developed on BOO basis Prect Type (Awarding) oj IPP1 1.2 AREA AND

24

4.3 COMPLIANCE WITH SAFEGUARDS POLICY STATEMENT, 2009 OF ADB

It is already said that the ECPVCL project has to comply with the requirement of SPS, 2009

of ADB. Accordingly, the compliance of this project in regard of major EHS related

requirement are mentioned in Table 4.8, where the gray colored portion represents the

construction phase and colorless portion represents the operation phase.

Table 4.8: Compliance with important EHS aspects during construction and operation phase

ADB

Requirements

Issue and Description of

Observation

Status of

compliance

Recommendation

Environment

Assessment

requirements for

various financing

modalities

The IEE of the project comprehensively

describes the potential environmental,

social and occupational impacts in

compliance with SPS 2009 of ADB, and

IFC EHS guidelines (General and

power plant).

To ensure the implementation of EMP

during construction phase (upto

December 2014) ECPVCL has been

found to adopt specific EHS

Implementation Guidelines, where

induction training and other relevant

issues need to be more structured.

Partially

complied

To revise the EHS

Implementation Guidelines with

focus on induction training and

other relevant issues need to be

more structured.

But during operation phase (from

January 2015), ECPVCL is yet to adopt

any comprehensive EHS

Implementation Guidelines, which

clearly specify the EHS Policy and

Procedure to address the ADB’s Environment Safeguard, EHS

guidelines of IFC (general and power

plant).

Late

complied

ECPVCL has to ensure the

availability of a comprehensive

EHS Implementation Guidelines

for operation phase.

Occupational and

Community

Health and safety

During construction phase the

Occupational and community health

safety measures have been found

satisfactory. Because there were

application of PPE and arrangement of

weekly doctor at plant level. Regular

consultation with community

representative had ensure the

community participation.

Fully

complied

No additional measures were

recommended.

During operation phase, ECPVCL has

to emphasize application of PPE. In

addition, they have to adopt required

mitigation measures to limit the higher

noise level issue.

Partially

complied

ECPVCL has already started to

increase the height of eastern

side boundary wall to serve as

noise barrier. Based on the

noise monitoring result, they

need to go for further

mechanical measures (if

required).

Page 27: 40517-013: Annual Environmental and Social Compliance ......Project Type (Operational) HFO fired Power Plant to be developed on BOO basis Prect Type (Awarding) oj IPP1 1.2 AREA AND

25

ADB

Requirements

Issue and Description of

Observation

Status of

compliance

Recommendation

No documented evidence of any fire or

emergency hazard drill have been

found during operation phase.

Late

complied

To arrange the fire and

associated emergency hazard

drill with proper documentation.

Biodiversity

conservation and

Sustainable

natural resource

Management

The scale and complexity of

construction activities were too limited

to adversely affect local biodiversity and

to appear as detrimental in respect

natural resource management.

Fully

complied

No action was required

The activities in relevant to operation

phase seems to be inadequate to

adversely affect the biodiversity and

natural resource

Fully

complied No action seems to be required

Pollution

prevention and

abatement

During construction phase, the pollution

prevention and abatement process has

been found as satisfactory.

Fully

complied No action was required

To assess the impact of the project to

the ambient air and water quality, there

is necessity to conduct air and water

quality monitoring during operation

phase.

Late

complied To monitor and water quality

During operation phase, the noise level

seems to be higher than the acceptable

limit. So, there is necessity of noise

monitoring to have the actual data and

respond accordingly.

Late

complied

To monitor the noise quality.

There is scope to improve the present

spillage management process.

Partially

complied

ECPVCL should be adequately

careful about satisfactory

spillage management.

Physical Cultural

resources

Kolagaon is a rural area having

dominating agricultural trend. In

addition, it is significantly deprived with

adequate educational and cultural

facility. So, there is no significant

physical cultural resources in close

proximity to this project. So, to affect

the physical cultural resources during

construction phase seemed to be

irrelevant.

Fully

complied

No action was required.

Due to the unavailability of physical

cultural resources within the range of

close distance, the issue of adversely

affecting the physical cultural property

seems not to be relevant with the

project.

Fully

complied

No action is required

Page 28: 40517-013: Annual Environmental and Social Compliance ......Project Type (Operational) HFO fired Power Plant to be developed on BOO basis Prect Type (Awarding) oj IPP1 1.2 AREA AND

26

5.0 IMPLEMENTATION OF SOCIAL SAFEGUARDS

5.1 IMPACT ON RESETTLEMENT OF THE PROJECT AFFECTED PEOPLE AND

LIVELIHOOD

As the project site is a purchased land of ECPVCL from private land-owners through willing

seller-willing buyer arrangement, there is no issue of resettlement. In addition, as the project

site was of a low lying land with dominating water logging trend, there was no significant

economic activity. So, the project is not associated with adversely affecting the livelihood of

any local household.

Photographs 5.1 and 5.2: View of a portion of project site

5.2 INSTITUTIONAL ARRANGEMENT ON SOCIAL SAFEGUARD

Institutional arrangement

During construction phase, although there was no dedicated structural arrangement to

comprehensively look after social safeguards issue, there were several comprehensive

consultations with local people and their views were given due attention. For example, there

were demand for drinking water and job opportunity for local people, which has been

successfully resolved by ECPVCL. In addition, due to initiative of ECPVCL, the local

infrastructures including road has been developed.

But as operation phase comprises a long term period, ECPVCL has to emphasize the social

safeguards issue with due priority and has to designate official with specific responsibility to

ensure social safeguards.

Grievance Redress Mechanism

Although there is no IP and IR issues associated with the project, the project involves

numerous stakeholders resulting the concern of potential grievances. So, there should be

well structured grievance redress mechanism. In this regard, ECPVCL has to make sure the

Page 29: 40517-013: Annual Environmental and Social Compliance ......Project Type (Operational) HFO fired Power Plant to be developed on BOO basis Prect Type (Awarding) oj IPP1 1.2 AREA AND

27

availability of Grievance Box and Grievance Log Book. So, that who does not prefer to put

his grievance in written in Grievance Log Book may prefer Grievance Box. In addition, there

should be a designated cell phone number and e-mail ID facility, where victim can raise his

grievance comprehensively and confidentially.

5.3 IMPACT ON INDIGENOUS PEOPLE

Based on the primary observation during site visit and secondary sources including

Chittagong City Corporation and Chittagong Development Authority, no habitat of any

indigenous community has been reported at Kolagaon. So, the project has been categorized

as C for Indigenous Peoples (IP) safeguards concluding that there is no issue about

adversely affecting IP neither in construction phase nor in operation phase.

ECPVCL has conveyed that they are gender and caste neutral. So, any qualified person

coming from the indigenous community will be equally treated during the recruitment

process, and will be given the same benefits as like as other personnel.

5.4 CHILD LABOUR

The Bangladesh Labour Act 2006 (Act XLII of 2006) also defines the “child” and the “adolescent” on the basis of age. As per section 2(8) of the Act, a person who has attained the age of 14 but below the age of 18 is considered to be an „adolescent‟ and as per section

2(63), a person not attaining the age of 14 is defined as a “child‟.

According to The National Child Labour Elimination Policy 2010, following rights are to be

complied with, in regard of addressing child labour Issue

Employing children according to the age determined by the Acts and not to employ children below 14 years as a regular employee;

Ensuring the children at domestic work not to perform any hazardous work and providing them with proper food and accommodation, education, recreation since they work full time; and

Refraining child workers from physical, mental, sexual persecution and abuse.

ECPVCL has been found to be careful about the child labour issue. So, neither in

construction phase nor in operation phase, no child has been found to be engaged in the

project activities.

Page 30: 40517-013: Annual Environmental and Social Compliance ......Project Type (Operational) HFO fired Power Plant to be developed on BOO basis Prect Type (Awarding) oj IPP1 1.2 AREA AND

28

5.5 PUBLIC CONSULTATION AND DISCLOSURE OF INFORMATION

i. Consultation

From the beginning of the construction phase, IDCOL officials have tried to ensure the

project as socially compliant. In this regard, there were a number of formal consultation

including consultation of 5 May 2014 are worth mentioning (Annex-8). However, four senior

persons were informally consulted on 19 April 2015 to share their views about the potential

environmental and social impacts of the project (Annex-19). They are-

Md. Foujul Haq, son of Md. Badrul Haq

Md. Osman Ali, son of Late. Yakub

Md. Ayub Ali, son of Late. Shamir Ali

Md. Abul Mia, son of Late. Sador Ali

ii. Major findings

They have said that the project is advantageous to them for many reason but also there are few issue to requiring due attention from ECPVCL.

The advantages of the project are:

The project has given them a social identity. Because initially Kolagaon was considered as a backward area struggling with basic infrastructures. But now Kolagaon is informally considered as industrial area.

The land price has increased

There is employment opportunity for the local people.

ECPVCL has provided drinking water facility through connection with its deep tubewell.

The quality of road has been improved.

ECPVCL has made financial contribution in social infrastructure like mosque.

The dis-advantages of the project are:

The noise level of the project has appeared as a concern, especially at night.

iii. Response from ECPVCL

In response, the ECPVCL official has ensured that they are considering the noise issue with

due importance and accordingly they are erecting brick wall on the eastern side of the plant

as is shown in Annex 20.

iv. Disclosure

ECPVCL has to adopt structured approach to disclose the grievance redress aspects,

results of environmental monitoring and any other issue (as seems relevant during operation

phase).

Page 31: 40517-013: Annual Environmental and Social Compliance ......Project Type (Operational) HFO fired Power Plant to be developed on BOO basis Prect Type (Awarding) oj IPP1 1.2 AREA AND

29

6.0 CORRECTIVE ACTION PLAN

6.1 CORRECTIVE ACTION PLAN IN REGARD OF ENVIRONMENTAL AND SOCIAL

SAFEGUARDS

Based on the discussion in earlier chapters, it assumes that the ECPVCL had been found to

be satisfactorily E&S compliant during construction phase. But they are required to focus on

some specific issue to make the project satisfactorily E&S compliant during operation phase

as well. In this regard, the specific E&S issues with potential corrective measures are

depicted in the following Table 6.1.

Table 6.1: Gap between E&S compliances and proposed corrective actions

Aspect Issues Reason of inadequacy Corrective measure Required committed time period

Environmental

EHS

guidelines

Without a documented EHS

guidelines, it seems to be

inconvenient to ensure proper

implementation of EMP.

Adopt an EHS guideline which clearly describes the process of EMP implementation during operation phase.

30 June, 2015

EHS training The officials and workers

have been found to require

comprehensive training on

disaster management

including fire and earth quake

hazard.

Arrangement of firefighting

and earthquake safety drill.

31 July, 2015

Emergency

Response Plan

There is yet any Emergency

Response Plan (ERP) is

required to ensure the proper

management of emergency

condition

Prepare an ERP by detailing out the all relevant hazards, risks and near misses and suitable way to address them.

31 July, 2015

Arrangement

of

Environmental

Monitoring

There is no environmental

monitoring (air, water and

noise) report based on the

current situation.

Conduct environmental

monitoring (air, water and

noise) according to the EMP

30 June, 2015

Noise

The local people raised the

issue of higher noise level

Erection of boundary wall and adopt required mechanical measures to limit noise level.

30 September,

20156

Social Institutional

arrangement

and Grievance

Redress

Mechanism

(GRM)

Due to the close proximity to neighborhood, the project requires structured institutional arrangement to look after social safeguards issues including GRM.

Develop a team to look after social safeguards and adopt GRM in a structured manner.

31 July, 2015

6 To address the noise issue, erection of boundary wall has already been started, which may require upto 30 September 2015.

But ECPVCL has instructed to EPC contractor to accomplish the erection work ever earlier, if possible.

Page 32: 40517-013: Annual Environmental and Social Compliance ......Project Type (Operational) HFO fired Power Plant to be developed on BOO basis Prect Type (Awarding) oj IPP1 1.2 AREA AND

30

7.0 CONCLUSION

Based on the findings of E&S compliance audit, it can be concluded that ECPVCL had been

found adequately responsive in regard of complying with environmental and social

safeguards during construction phase. It is expected that they will show similar type of

commitment during operation phase as well and will ensure the proper implementation of

corrective action plan (Table 6.1).

Page 33: 40517-013: Annual Environmental and Social Compliance ......Project Type (Operational) HFO fired Power Plant to be developed on BOO basis Prect Type (Awarding) oj IPP1 1.2 AREA AND

31

Annex 1: Environmental Clearance Certificate issued by the DOE

Page 34: 40517-013: Annual Environmental and Social Compliance ......Project Type (Operational) HFO fired Power Plant to be developed on BOO basis Prect Type (Awarding) oj IPP1 1.2 AREA AND

32

Annex 2: Location of the project site

Figure : Satellite image of ECPVCL Project site in respect of Chittagong City

Figure : Satellite image of ECPVCL Project site in respect of distant surrounding area

Page 35: 40517-013: Annual Environmental and Social Compliance ......Project Type (Operational) HFO fired Power Plant to be developed on BOO basis Prect Type (Awarding) oj IPP1 1.2 AREA AND

33

Figure : Satellite image of ECPVCL project site in respect of close surrounding area

Figure : Satellite image of a close view of ECPVCL Project site

Page 36: 40517-013: Annual Environmental and Social Compliance ......Project Type (Operational) HFO fired Power Plant to be developed on BOO basis Prect Type (Awarding) oj IPP1 1.2 AREA AND

34

Annex 3: Project risk screening checklist of ESSF, IDCOL

Sl.

no

Env. and scl. risks rating criteria Response Remarks

Yes No

01

For new projects, does the project have any pending compliance such as

Location and Environmental Clearance based on its category (Red,

Orange-A, Orange-B and Green), from the DOE?

02

Is the project located in the immediate vicinity (likely to adverse impact) of

environmentally critical areas (national wetlands, wildlife habitats, important

bird areas, and protected areas)

03 Does the project construction and/or operation lead to environmental

impacts that are diverse, irreversible and/or unprecedented in nature?

04 Does the project require involuntary resettlement that results in loss of land

or livelihoods or physically displaces more than 200 persons?

05

Is the project site on or in immediate vicinity of socially vulnerable or

Indigenous People IP) owned or occupied land and has the potential to

cause an adverse impact on their culture and identity?

06 Is the project vulnerable to climate change related impacts?

07 Does the Borrower have a documented Policy on E&S Performance?

08

Does the Borrower have dedicated human resources to address E&S

performance?

09

Has the Borrower established and implemented Environmental, Health &

Safety Management Systems and Social Accountability Systems for the

Project SPV or in the parent company?

Page 37: 40517-013: Annual Environmental and Social Compliance ......Project Type (Operational) HFO fired Power Plant to be developed on BOO basis Prect Type (Awarding) oj IPP1 1.2 AREA AND

35

Annex 4: Arrangement of workers’ shed and storage shed (construction phase)

Photograph: A view of an storage shed Photograph: A view of an workers’ shed

Annex 5: PPE arrangement and medical check-up (construction phase)

Photograph: Treatment provided by doctor Photograph: Workers with PPE

Photograph: Accident record arrangement

Page 38: 40517-013: Annual Environmental and Social Compliance ......Project Type (Operational) HFO fired Power Plant to be developed on BOO basis Prect Type (Awarding) oj IPP1 1.2 AREA AND

36

Annex 6: Dust management (construction phase)

Photograph: Watering in access road Photograph: Covering of stock piles

Photograph: Watering in bare areas

Page 39: 40517-013: Annual Environmental and Social Compliance ......Project Type (Operational) HFO fired Power Plant to be developed on BOO basis Prect Type (Awarding) oj IPP1 1.2 AREA AND

37

Annex 7: Construction of fuel storage tank (construction phase)

Photograph: Secondary layer of fuel storage tank Photograph: Base piling of fuel storage tank

Page 40: 40517-013: Annual Environmental and Social Compliance ......Project Type (Operational) HFO fired Power Plant to be developed on BOO basis Prect Type (Awarding) oj IPP1 1.2 AREA AND

38

Annex 8: Consultation with local community (construction phase)

Photograph: Representatives of ECPVCL, IDCOL and

Kolagaon Union Parishad at consultation

Photograph: A view of the participants at consultation

Page 41: 40517-013: Annual Environmental and Social Compliance ......Project Type (Operational) HFO fired Power Plant to be developed on BOO basis Prect Type (Awarding) oj IPP1 1.2 AREA AND

39

Annex 9: List of some participants in the consultations (construction phase)

Page 42: 40517-013: Annual Environmental and Social Compliance ......Project Type (Operational) HFO fired Power Plant to be developed on BOO basis Prect Type (Awarding) oj IPP1 1.2 AREA AND

40

Annex 10: Fuel treatment process (operation phase)

Photographs: Fuel Treatment Plant

Annex 11: Stack (operation phase)

Photograph: 27 m tall stack

Page 43: 40517-013: Annual Environmental and Social Compliance ......Project Type (Operational) HFO fired Power Plant to be developed on BOO basis Prect Type (Awarding) oj IPP1 1.2 AREA AND

41

Annex 12: Closed oil transportation process (operation phase)

Photographs: Closed oil transportation system

Annex 13: PPE arrangement (operation phase)

Photograph: Application of PPE

Page 44: 40517-013: Annual Environmental and Social Compliance ......Project Type (Operational) HFO fired Power Plant to be developed on BOO basis Prect Type (Awarding) oj IPP1 1.2 AREA AND

42

Annex 14: Fire-fighting arrangement (operation phase)

Photographs: Firefighting pumps and internal and external fire fighting arrangement

Annex 15: Application of signage

Photographs: Bengali and English signage at project

Page 45: 40517-013: Annual Environmental and Social Compliance ......Project Type (Operational) HFO fired Power Plant to be developed on BOO basis Prect Type (Awarding) oj IPP1 1.2 AREA AND

43

Annex 16: Current status of project (external view)

Photograph: External view of the Plant (partial)

Photograph: Riverside view of the plant

Photograph: Transformer

Page 46: 40517-013: Annual Environmental and Social Compliance ......Project Type (Operational) HFO fired Power Plant to be developed on BOO basis Prect Type (Awarding) oj IPP1 1.2 AREA AND

44

Annex 17: Current status of project (internal view)

Photograph: Internal view of the Plant (production record and gen sets)

Page 47: 40517-013: Annual Environmental and Social Compliance ......Project Type (Operational) HFO fired Power Plant to be developed on BOO basis Prect Type (Awarding) oj IPP1 1.2 AREA AND

45

Annex 18: Housekeeping

Photograph: Status of internal housekeeping

Photograph: Application of different types of dustbin

Page 48: 40517-013: Annual Environmental and Social Compliance ......Project Type (Operational) HFO fired Power Plant to be developed on BOO basis Prect Type (Awarding) oj IPP1 1.2 AREA AND

46

Annex 19: List of male respondents during consultation in operation phase

Photographs: Participants in the consultation process

Page 49: 40517-013: Annual Environmental and Social Compliance ......Project Type (Operational) HFO fired Power Plant to be developed on BOO basis Prect Type (Awarding) oj IPP1 1.2 AREA AND

47

Annex 20: Boundary wall

Photograph: Construction of boundary wall at eastern side

Photograph: Boundary wall at western (river) side


Recommended