+ All Categories
Home > Documents > 4.2 Project Management KAF BDM

4.2 Project Management KAF BDM

Date post: 28-Nov-2015
Category:
Upload: orbind-b-shaikat
View: 31 times
Download: 6 times
Share this document with a friend
Description:
Project Management Business Decision Making( HND Course)
22
PROJECT MANAGEMENT Prepared by Kashfiya Afrin Lecturer School of Business BAC
Transcript
Page 1: 4.2 Project Management KAF BDM

PROJECT MANAGEMENTPrepared by

Kashfiya AfrinLecturer

School of BusinessBAC

Page 2: 4.2 Project Management KAF BDM

What is Project?An undertaking that has a beginning as well

as end and is carried out to meet established goals within cost, schedule and quality objectives

Page 3: 4.2 Project Management KAF BDM

Characteristics of a ProjectSpecific start and end pointWell defined objectiveUnique & non repetitiveCost & time scheduleCross functional team

Page 4: 4.2 Project Management KAF BDM

Unique Features of Project MgtTeam WorkExpected ProblemUnexpected ProblemDelayed BenefitContribution of SpecialistsParties with Different Interest

Page 5: 4.2 Project Management KAF BDM

Why Projects Go Wrong?Difficulty in estimating project durationUnderestimated costsChanges in client specificationLack of coordination and team workDifficulties in managing unexpected problems

Page 6: 4.2 Project Management KAF BDM

Objective of Project MgtQualityBudgetTime Scale

Page 7: 4.2 Project Management KAF BDM

Project Life CycleConceiving & defining projectPlanning the projectProject implementation & controlCompleting & evaluating the project

Page 8: 4.2 Project Management KAF BDM

Project Life CycleConceiving & defining projectPlanning the project Break down into manageable unitsEstimation of resource needed (material,

money, time, labor etc.)Project implementation & controlCompleting & evaluating the project

Page 9: 4.2 Project Management KAF BDM

Work Break Down StructureDiscovering work that must be done in the

projectDetermining resources requiredSequencing work

Page 10: 4.2 Project Management KAF BDM

Estimation“An accurate estimate of project costs provides

a proper basis for management control” -Dennis Lock

Page 11: 4.2 Project Management KAF BDM

Estimation (Cont…)Estimates can be improved byLearning from past mistakesObtaining sufficient design informationEnsuring customer specification as detailed

as possibleAnalyzing properly

Page 12: 4.2 Project Management KAF BDM

Cost EstimationBased on 2 componentsDirect Cost (Labor, material, sub components

etc.)Overhead Cost (Heating, lighting, utilities

etc.)Material requires 2 types of estimationTotal material cost (Design engineers,

procurements etc.)Lead time for receipt

Page 13: 4.2 Project Management KAF BDM

Job Time EstimationEstimated time, te={(to+4tm-tp)/6} Here, to=the most optimistic duration (shortest

time) tm=the most likely duration tp=the most pessimistic duration (Longest

time)

Page 14: 4.2 Project Management KAF BDM

Network AnalysisTechnique for planning & controlling large

projectsConstruction workR&DComputerization of a systemAlso known as Critical Path Analysis (CPA) or

Critical Path Method (CPM)

Page 15: 4.2 Project Management KAF BDM

Advantages of Network AnalysisHelps to plan when to start tasksHelps to allocate resources properlyHelps to monitor progressHelps to control

Page 16: 4.2 Project Management KAF BDM

Network DiagramRepresents events & activities (along with

their sequence) making up a whole projectFlow of activities: Left to rightArrowed lineNode

Page 17: 4.2 Project Management KAF BDM

Critical PathIt is the path through the network with the

greatest total durationActivities on it are called critical activitiesA network can have more than one critical

path.

Page 18: 4.2 Project Management KAF BDM

Example: Critical PathThe following activities comprise a project to

renovate a block of flats.

Page 19: 4.2 Project Management KAF BDM

Example: Critical PathActivities Preceding

ActivityDuration(Weeks)

A: Replace windows in lounges - 5

B: Rewire - 4

C: Re-plaster walls of lounges A 2

D: Fit lights in lounges B 1

E: Decorate the bedrooms B 5

F: Install Plumbing B 5

G: Decorate lounges C, D 4

H: Decorate kitchen F 3

I: Decorate Washroom F 2

Page 20: 4.2 Project Management KAF BDM

Example: Critical PathWhat are the paths through network?What is the critical path and what is its

duration?

Page 21: 4.2 Project Management KAF BDM

TextBusiness Decision Making by Pipa Riley Chapter 10: Project Mangement Tools &

TechniquesProjects: Planning, Analysis, Selection,

Financing, Implementation & Review by Prasanna Chandra

Edition: 7th

Chapter-21: Project Management

Page 22: 4.2 Project Management KAF BDM

Thank You!


Recommended