+ All Categories
Home > Documents > 42056398-Erection-and-Commissioning-Procedure.pdf

42056398-Erection-and-Commissioning-Procedure.pdf

Date post: 04-Apr-2018
Category:
Upload: shankar-jha
View: 216 times
Download: 0 times
Share this document with a friend

of 94

Transcript
  • 7/29/2019 42056398-Erection-and-Commissioning-Procedure.pdf

    1/94

  • 7/29/2019 42056398-Erection-and-Commissioning-Procedure.pdf

    2/94

  • 7/29/2019 42056398-Erection-and-Commissioning-Procedure.pdf

    3/94

    Kirloskar Oil Engines Ltd.Large Engines Division

    INSTALLATION & COMMISSIONING MANUAL

    Chapter-1 Drawing list

    LIST OF DRAWINGS FOR PROJECT EXECUTION

    (MECHANICAL)SR. NO. DRAWING NO. DESCRIPTION

    CIVIL DRAWINGS

    1 27.827.11.0.00 POWER HOUSE & EQUIPMENT LAYOUT

    2 27.827.16.0.00 DG SET FOUNDATION BLOCK

    BASIC DRAWING

    3 27.828.90.0.02 BASE FRAME FOR ENGINE AND ALTERNATOR

    4 27.815.11.0.00 FLY WHEEL COUPLING ASSLY

    5 74.225.40.0.01 LIMIT OF SUPPLY6 AZ-12832 GA DRG. OF ALTERNATOR

    7 74.640.20.0.00 COUPLING

    HT WATER CIRCUIT

    8 27.809.21.0.00 HT WATER CIRCUIT SCHEMATIC

    9 70.660.10.0.00 EXPANSION WATER TANK

    10 27.706.10.0.00 CHEMICAL MIXING TANK & PUMP

    11 27.833.10.0.00 PRE HEATING MODULE

    12 27.810.11.0.00 HT WATER RADIATOR

    LT WATER CIRCUIT

    13 27.809.20.0.00 LT WATER CIRCUIT SCHEMATIC

    14 27.810.12.0.00 LT WATER RADIATOR

    FUEL CIRCUIT

    15 27.809.25.0.00 FUEL CIRCUIT SCHEMATIC

    16 74.635.10.0.05 GA DRG. OF FUEL DAY TANK 990 LTRS.

    17 79.824.10.0.00 HSD DRIP TANK WITH PUMP ASSLY.

    18 27.692.02.0.00 FUEL FILTER COARSE19 74.649.10.0.00 FINE FUEL FILTER

    LUBE OIL CIRCUIT

    20 27.809.22.0.00 LUBE OIL SCHEMATIC

    21 27.808.10.0.00 LUBE OIL COOLER

    1.1

  • 7/29/2019 42056398-Erection-and-Commissioning-Procedure.pdf

    4/94

    Kirloskar Oil Engines Ltd.Large Engines Division

    INSTALLATION & COMMISSIONING MANUAL

    Chapter-1 Drawing list

    SR. NO. DRAWING NO. DESCRIPTION

    COMPRESSED AIR CIRCUIT

    22 27.809.23.0.00 COMPRESSED AIR CIRCUIT SCHEMATIC

    23 27.689.10.0.00 COMPRESSED AIR MODULE

    24 27.812.11.0.00 COMPRESSED AND AIR BOTTLE

    25 74.632.12.0.00 MOTOR DRIVEN AIR COMPRESSOR

    26 74.632.11.0.00 ENGINE DRIVEN AIR COMPRESSOR

    CHARGE AIR EXHAUST CIRCUIT

    27 27.809.24.0.00 CHARGE AIR & EXHAUST SYSTEM SCHEMATIC

    28 27.650.01.0.03 EXHAUST SILENCER

    MISCELLANCEOUS

    29 XI--08074--M04--01CHIMNEY

    30 27.809.27.0.00 LEGEND AND ABBRIVATION

    31 74.643.10.0.00 WORKING PLATFORM (L.H.)

    32 74.643.11.0.00 WORKING PLATFORM (R.H.)

    33 UTILITY WATER DISTRIBUTION

    1.2

  • 7/29/2019 42056398-Erection-and-Commissioning-Procedure.pdf

    5/94

    Kirloskar Oil Engines Ltd.Large Engines Division

    INSTALLATION & COMMISSIONING MANUAL

    Chapter-1 Drawing list

    LIST OF DRAWINGS FOR

    PROJECT EXECUTION(ELECTRICAL)

    SR. NO. DRAWING NO. DESCRIPTION

    1 SINGLE LINE DIAGRAM

    2 POWER DISTRIBUTION SCHEMATIC OF GCP CUM SYN.

    3 PLC WIRING SCHEMATIC OF GCP CUM SYN.PANEL

    4 PLC INPUT/OUTPUT LIST

    5 SYSTEM ARCHITECTURE OF GCP CUM SYN.PANEL

    6 AVR TERMINAL

    7 LOCAL SENSOR STAND

    8 MOTOR CONTROL CENTRE PANEL

    9 DG BREAKER

    10 NEUTRAL GROUND RESISTOR PANEL

    11 CABEL SCHEDULE

    12 CABEL INTERCONNECTION DETAILS

    13 POWER HOUSE EARTHING LAYOUT

    14 POWER HOUSE CABLE TREY LAYOUT

    16 DG OPERATION PHILOSPHY

    17 ALTERNATOR MANUAL WITH TEST CERTIFICATE18 TEST CERTIFICATE OF ALL PANELS

    1.3

  • 7/29/2019 42056398-Erection-and-Commissioning-Procedure.pdf

    6/94

    Chapter 2 - INSTALLATION

    Technical Specifications forInstallation of DG Set Mechanica/Electrical

    Kirloskar Oil Engines Ltd.Large Engines Division

    INSTALLATION & COMMISSIONING MANUAL

    TECHNICAL SPECIFICATIONS FOR

    INSTALLATION OF DG SET (MECHANICAL)1. UNLOADING OF MATERIAL (Lifting, Leading & Installation)

    We have to use proper tools, adequate manpower & arrangements to unload the materialdepending upon its size and weight to avoid damages.

    For Unloading of engine, alternator and auxiliaries etc., should use hooks which are provided onit for handling with crane otherwise we have to use jacks & sleepers with wrench and wire rope.

    If crane is used to unload, the capacity of crane should be twice the weight of material

    Crane documents should be verified before allowing to work as per RTO.

    Slings of crane should be lubricated and joints of the sling should be examined for perfect fitmentwith clamping.

    While unloading the crane should be supported by jacks on both ends and tyres should be lockedat both end with some media like sleepers to avoid jerking while unloading.

    NOTE : Collect a catalogue from crane manufacturer for more informations.

    No material shall be slinged with any components of machineries like motors, pumps, pipes

    base frame etc.

    No body should step on the components to do any work while unloading, leading or at the time ofinstallation.

    For each sq. mtrs. 4 persons are required for handling of material to avoid any damage tomaterial, what ever may be its weight.

    All glass parts, instrumentation items, pressure gauges etc. should be handled with care andprecautions to avoid damage, no jerks & drops.

    While handling the material top side mark should always be maintained at the top.

    NOTE : Enquire the capacity of winch, pulleys used for leading and lifting of materials dependingupon the weight.

    2. CHECKING OF LAYOUT.

    Civil layout made by customer should be collected from customer and compared with KOELlayout w.r.t. dimensions, if any variation is noticed enquire with Customer.

    Locate the direction of power house & co-relate with drawing, than locate foundation blocks ofengine and its auxiliaries as per drawing.

    2.1

  • 7/29/2019 42056398-Erection-and-Commissioning-Procedure.pdf

    7/94

    Chapter 2 - INSTALLATION

    Technical Specifications forInstallation of DG Set Mechanica/Electrical

    Kirloskar Oil Engines Ltd.Large Engines Division

    INSTALLATION & COMMISSIONING MANUAL

    3. CHECKING OF MATERIAL

    Check the material as per packing sheets and also cross check with application code, if there isany shortage / damage, intimate to KOEL Ofiice immediately.

    Examine the material for its condition frequently during the course of commissioning.

    Inform shortage of material, if any in advance.

    Make a chart for weekly material consumption and cross check the plan with every day actualconsumption.

    Correctness of material should be checked for weekly plan.

    4. PIPING NORMS

    Each pipe should clearly shows the direction of flow of liquids with arrows.

    If any doubt in pipe size of circuit, clarify with KOEL AE.

    5. PIPING SUPPORTS

    The pipe must be supported on both side of bend joints, flange joints and Auxiliaries ends within afeet.

    In every 4 meters of pipeline there should be a support.

    For supports use 50 x 50 x 5 angles or 100 x 50 x 5 C Channel. Use U clamps, washer and nuts forclamping the pipes with angle & channel.

    All supports must be painted by BLACK paint, before clamping the pipes.

    For clamps of pipes to supports, all holes on supports should be drilled and shall not be done bygas cutting.

    All Supports should be horizontal.

    At every 5 mtrs. length there must be flange connection except for Fuel.

    All flange of pipeline should be minimum 100 mm above the trench floor and supports should be300 mm. above floor level of trench.

    The vertical gaps between pipe line supports in double tier should be maintained around 300 mm.

    Lower support should be both side welded in trench and above that, only one support of cantile-ver type and only one side of trench with a gap of 400 mm. from opposite side of trench.

    NOTE : Ensure that the trenches are water proof before laying pipelines.

    2.2

  • 7/29/2019 42056398-Erection-and-Commissioning-Procedure.pdf

    8/94

    Chapter 2 - INSTALLATION

    Technical Specifications forInstallation of DG Set Mechanica/Electrical

    Kirloskar Oil Engines Ltd.Large Engines Division

    INSTALLATION & COMMISSIONING MANUAL

    6. WELDING

    The angle between the two pieces of pipes to be welded should be chamfered.

    The distance between two pipes should be half of the thickness of the pipe, which are to bewelded together.

    Before starting the welding clean the edge to be welded thoroughly and make sure edges are dry.use proper flux for proper welding with correct grade of welding rods.

    Properly chamfer the edges to be welded.

    Remove distance piece used to maintain gap between pipes.

    Root weld and brush it by wire brush before doing 2nd round i.e. there is no any red beed.

    Capacity of welding machine should be as per the welding rod requirement. Keep all welding

    rods packets in a dry container.

    If welding rods are wet they should be kept in a oven for drying before use.Do not use sub-standard, damaged or cracked welding rods.

    Standard welding rods requirement

    Seamless pipe : 6013 - Advani S & 2S or equivalent of reputed make.6010 - Deep penetration rod.7018 - Super therm special

    S.S. Pipe S4E 308 - 16 for ss 304 PipeS4E 308L - 16 for ss 304L Pipe

    Selection of current of welding motor for different size of rods.

    Size of rod Amps

    2.50 x 350 50 - 70

    3.15 x 350 90 - 110

    4.00 x 350 110 - 140

    5.00 x 350 160 - 200

    Welding beed should be uniform and @ 1.5 mm, above the surface of pipe. Chipping and wirebrushing should be done to take out slag, flex and burgs of welding.

    If pipe size is more than 4 use clits in between edges of pipes to be welded to make sure bothpipes are in correct position.

    Size of welding rod selection as per thickness of pipes is as below :-

    Pipe Size (mm) Root Weld (mm) Main Weld (mm)

    15 NB 12 10/8

    20 NB 12 10/8

    25 NB 12 8

    40 NB 12/10 8

    2.3

  • 7/29/2019 42056398-Erection-and-Commissioning-Procedure.pdf

    9/94

    Chapter 2 - INSTALLATION

    Technical Specifications forInstallation of DG Set Mechanica/Electrical

    Kirloskar Oil Engines Ltd.Large Engines Division

    INSTALLATION & COMMISSIONING MANUAL

    50 NB 12/10 8

    65 NB 12/10 880 NB 12/10 8

    100 NB 12/10 8

    150 NB 10 8

    200 NB 10 8

    460 OD 10 8

    560 OD 10 8

    750 OD 10 8

    1000 OD 10 8/6

    Fillet welding should be done for the pipe to the flange and pipe to valves.Gap between pipes and flange face should be minimum 5 mm x 45 Deg.

    Pipe should be horizontal or vertical when it is welded with valve.

    7. WELDING TEST

    Random test of welding joints is to be done by D. P. Test (10%).

    8. HYDRO TEST

    Pipe should be Hydro tested at following pressure:

    Pipe line Pressure

    L. T. Water 10 bar

    H. T. Water 10 bar

    Injector water 10 bar

    Fuel 10 bar

    Lub Oil 10 bar

    Air 45 bar

    (The Hydro test should be carried out by pump which is to be arranged by contractor)

    NOTE : The specifications of hand pump required for Hydro test are to be confirmed.

    Before Hydro test all pipes should be thoroughly cleaned with wire brush chipping at flange end

    and by water flushing.Any leakage found in the Hydro test should be rectified and pipe should be retested for leakage.

    Put a air vent at highest point of pipe line while doing Hydrotest which should withstand therequired pressure.

    After Hydro test no work should be done on the pipe line like gas cutting, drilling, welding etc.

    The pressure should hold, at least for one hour without any leakage.

    For exhaust and air intake ducting there is no Hydro test.

    2.4

  • 7/29/2019 42056398-Erection-and-Commissioning-Procedure.pdf

    10/94

    Chapter 2 - INSTALLATION

    Technical Specifications forInstallation of DG Set Mechanica/Electrical

    Kirloskar Oil Engines Ltd.Large Engines Division

    INSTALLATION & COMMISSIONING MANUAL

    9. ACID CLEANING.

    Acid cleaning should be done immediately after Hydro test within 4 hours.

    NOTE : For More details refer chapter : Chemical Cleaning Procedures for Pipes.

    10. PAINTING.

    Preparation of pipe surface before application of paint.

    a) Remove all oil on pipe surface with the solvent.b) Removal of dirt, loose rust and loose mill scale with scraper or wire brush.

    c) Flame cleaning if necessary.d) Clean and dry pipe surface with cloth.e) Ensure pipes are degreased properly.

    First apply red oxide or Primer.

    After one day apply the 2 coats of paint on pipelines as per following colour codes.

    PIPE LINE PAINTING COLOUR CODE

    Sr. No. System Colour Colour shade as

    Per IS 5

    1. L.T. Water Sea Green 217

    2. H.T. Water & French blue 166

    Injector Water

    3. Lub Oil Golden brown 414

    4 Fuel Post office red 538

    5 Air Canary yellow 309

    6 Exhaust Gas Silicon based heat resistance ----

    Aluminium paint (upto 600 deg.C)7 Supports Bituminous Black ----

    Note: Do not apply red Oxide on exhaust ducting.

    2.5

  • 7/29/2019 42056398-Erection-and-Commissioning-Procedure.pdf

    11/94

    Chapter 2 - INSTALLATION

    Technical Specifications forInstallation of DG Set Mechanica/Electrical

    Kirloskar Oil Engines Ltd.Large Engines Division

    INSTALLATION & COMMISSIONING MANUAL

    TECHNICAL SPECIFICATIONS FOR INSTALLATION

    OF DG SET (ELECTRICAL)1. INSPECTION

    a) Check whether there is no damage to the panel.

    b) Check whether all terminal connections and numbering of ferrules are as per cable

    schedule.

    c) Check the continuity of each terminal.

    d) Check for proper tightness of each connection.

    e) Check for proper earthing of panels.

    f) Check / ensure fuses provided are of correct rating.

    g) If any damage, faulty component found out during testing, inform to KOEL HO and ask for

    replacement.

    h) Check whether all the live connections are properly covered with insulation and earthed.

    2. GENERATOR CUM SYNCHRONISING PANEL

    a) Check whether there is no damage to the panel .

    b) Check / Ensure that output of DC-DC convertor supply to panel is 24 volts.

    c) Switch on PLC and check / ensure its proper working functions.

    d) Check the input and outputs of PLC are as per requirements.

    e) Check all safeties by simulation method.

    f) Check EFMU for proper working condition by simulation method.

    g) Check whether there is no drop of voltage observed across hour meter connections whilehooter is on.

    h) Check starting of lub oil priming pump and preheating module through GCP.

    i) Check whether lub oil priming pump, water pump and heaters are operating as per logic

    i.e. 20 min on and 15 min off. (All the three should run continuously till temp. reaches 50

    deg. C and then the cycle should start) .

    j) Check three attempts start and starting refusal logic functions.

    k) Check proper operation of start, stop and emergency stop.

    l) Check the magnetic pickup resistance is more than 500 ohms. (as per requirement.)

    m) Check whether the over speed safety is operating properly by pressing test push button

    on EFMUn) Check / Ensure all temperature scanners, pressure indicators etc. are showing proper

    readings.

    o) Calibrate all pressure gauges, pressure switches and RTDs installed on GCP &

    LSS and on all auxiliaries.

    p) Test each relay, its settings and record the same.

    q) Check / Ensure operation of breaker through GCP.

    r) Check whether excitation is not permitted without ready for excitation permission from

    GCP.

    2.6

  • 7/29/2019 42056398-Erection-and-Commissioning-Procedure.pdf

    12/94

    Chapter 2 - INSTALLATION

    Technical Specifications forInstallation of DG Set Mechanica/Electrical

    Kirloskar Oil Engines Ltd.Large Engines Division

    INSTALLATION & COMMISSIONING MANUAL

    s) Check the following functions are OK.

    i) Speed raise / Low

    ii) Voltage raise / Lowiii) Manual / auto synchronizing.

    iv) Breaker closing and tripping.

    v) Indication for all these operations.

    vi) Check other functions.

    3. NGR PANEL

    a) Check whether there is no damage to the panel

    b) Ensure whether resistance banks are not damaged.

    c) Check whether required No. and proper ratio of CTs are available.

    d) If possible test the ratio of CTs by injecting primary winding.e) Check whether cables are connected to correct polarity.

    f) Check for proper termination / insulation of HT cables and ensure that proper type of

    cable joint kit is used.

    g) Measure the resistance of whole bank and ensure that it is as per requirement.

    4. BREAKER PANEL

    a) Check whether there is no damage to the panel.

    b) Rack out the breaker and check that all components are OK.

    c) Grease the rack and other components, if required.

    d) Ensure whether breaker can not be operated in half in position

    e) Ensure proper and easy slide of breaker rack.

    f) Push the rack inside and check that limit switch is operating.

    g) Check whether auto and manual charging of spring is proper.

    h) Check whether breaker ON / OFF operation is proper, both by auto and manual method.

    i) Check for breaker closed indication on GCP when it is on.

    j) Ensure tripping of breaker during fault by simulation.

    k) Ensure auto closing of breaker by simulation check.

    5. MCC PANEL

    a) Check whether there is no damage to the panel .

    b) Check whether all OLR, Contactors and fuses fitted are of proper range.c) Check whether all switches and contactors are functioning properly.

    d) Check the interconnection of MCC, ECP and auxiliaries are proper.

    6. EARTHING PITS AND EARTHING GRID.

    a) Check the earthing pit resistance is within limit (Record the same.)

    b) Ensure the proper connections / joint of each grid. (As per drawing)

    2.7

  • 7/29/2019 42056398-Erection-and-Commissioning-Procedure.pdf

    13/94

    Chapter 2 - INSTALLATION

    Technical Specifications forInstallation of DG Set Mechanica/Electrical

    Kirloskar Oil Engines Ltd.Large Engines Division

    INSTALLATION & COMMISSIONING MANUAL

    7. ALTERNATOR.a) Megger the windings. ( Record the same.)

    b) Check the continuity of windings.

    c) Check whether space heater is working properly.

    d) Check whether the diodes are OK.

    e) Check the Lube Oil / Greasing of bearings.

    f) Check the proper air gap of excitation field if it is a separate unit.

    g) Check the CT ratio and polarity. (If applicable)

    h) Check whether RTDs are properly showing readings.

    8.H.T. CABLE

    a) Megger the Cable and record the same.

    b) Take the high potential test.

    c) Check for proper termination.

    d) Ensure whwther cable jointing is done by using std. material and correctly.

    2.8

  • 7/29/2019 42056398-Erection-and-Commissioning-Procedure.pdf

    14/94

    Chapter 3 - INSTALLATIONStatutory Rules & Safety Regulations

    Kirloskar Oil Engines Ltd.Large Engines Division

    INSTALLATION & COMMISSIONING MANUAL

    STATUTORY RULES & SAFETY REGULATIONS

    The details of statutory rules and safety regulations are followed for labour work executionfor KOELs erection and commissioning contractor at L&T-IOCL,Panipat Sites.

    STATUTORY RULES:

    01. This being a labour contract, it is obligatory for contractors employees under PF/ESI/WC,schemes and make compliance under various statutory acts, by contractor applicable. Itclarified that no reimbursement will be made on account of employers share of PF/ESI bythe company.

    02. The contractor shall comply promptly with the provisions of contract labour Act and producethe Licence of the Contract Labour Act if the number of labours exceed 19 on any day during

    contract period.

    03. The contractor shall bring only those labourers at the work site / premises who have beenissued gate passes / identity cards. the contractor agrees that he shall not retain the gatepasses with the labourers engaged by him to restrict unnecessary entries in the premises.The contractor also agrees to return all gate Passes / identity cards to the company as andwhen contract is over.

    04. The contractor will maintain muster roll of his employees engaged in the work site / premisesand update their attendance on day to day basis this should be handedover along with astatement showing the ESI / PF contributions to be recovered from the employees, to KOEL/ Local Labour Officer as and when required.

    05. The contractor will pay wages to the labourers as per rate under the minimum Wages Actnotified from time to time by the Govt. Authority.

    06. The labourers engaged by the contractor will be his employees and KOEL shall be in no wayresponsible or liable for their payment of wages / salaries, bonus, gratuity and otherallowances, if any.

    07. The labourers engaged by the contractor shall abide by all the disciplinary, rules & regulationslaid down by the customer / company / end user from time to time.

    08. In the event of any act committed by contractors laboures against the interest of the company,the company reserves the right to ask the contractor to remove such labourers withoutgiving notice and contractor is bound to do so.

    09. The contractor shall comply with all the rules and regulations under the various Acts applicableto the company. In case he fails to comply with the same and if the company apprehendsany breach thereto his contract is liable for termination fortwith. The company also reservesthe right to withhold the payment of the contractor.

    10. The contractor shall ensure the compliance and provisions of the contract labour Act. TheMinimum Wages Act. The payment of Wages Act, The Employees Provident Fund Act, ESIAct, Factories Act, payment of Wages Act. The payment of Gratuity Act and such labourlegislations applicable at the relevant time.

    3.1

  • 7/29/2019 42056398-Erection-and-Commissioning-Procedure.pdf

    15/94

    Chapter 3 - INSTALLATIONStatutory Rules & Safety Regulations

    Kirloskar Oil Engines Ltd.Large Engines Division

    INSTALLATION & COMMISSIONING MANUAL

    SAFETY REGULATIONS:

    01. The company has set some safety rules to be followed by each person to be employed bythe contractor to take care of the safety of the persons, safety of the other people and toensure the safety of companys properties. These rules are being framed by our safetydepartment and you will follow the same.

    02. While working at height all labour must use P.P.E. (Personal Protective Equipments)

    03. While working at the height on fragile roofs and other delicate areas special equipmentmust be used as directed by Safety Dept. Also you will take special precautions whileworking at height with open busbars open H. T. Lines etc.

    04. You will make use of safety belts wherever required. The healthiness of the safety belts

    should be confirmed.

    05. You will bring machines / equipment such as welding machine, drilling machine, gascutting set, rigging equipment, etc. of proper specifications and safety features. Machines/ equipments without safety features will not be permitted for use.

    06. While carrying out welding / gas cutting or any other fire hazardous works, ensure thatsite is made clear of such materials which can cause fire hazard.

    07. You will depute your supervisor at site to supervise your workers. No work will be permittedin the absence of your supervisor.

    08. You will carry out work against this from 9.00 am to 5.00 pm and weekly work basis. Workafter 5.00 pm or on holidays should be carried out only after getting special permission,depending on the works you are working.

    09. Workers possessing trade certificate for electrician should only allow to work on liveelectrical supply systems. The workers deputed by the contractor, as helper should carryout only the labour work and strictly under the supervision of contractors supervisor.

    10. While carrying out work you will make proper provisions to take care of the safety andcompanys machinery / property. Whenever required you will do the work after providingsuitable barricades / covers. Whenever carrying work, which is likely to lead harm toother persons, you will see that suitable sign / caution boards are displayed.

    11. Whenever working in combined space you will obtained permission from safety department

    12. Whenever working near LT / HT cables prior permission / clearance of concerned electricalmaintenance department should be taken.

    13. All safety rules and codes as applicable to work must be followed without any

    exception.

    3.2

  • 7/29/2019 42056398-Erection-and-Commissioning-Procedure.pdf

    16/94

    Chapter 3 - INSTALLATIONStatutory Rules & Safety Regulations

    Kirloskar Oil Engines Ltd.Large Engines Division

    INSTALLATION & COMMISSIONING MANUAL

    14. All personal protective equipments (safety bolts, hand gloves, aprons, helmets, safety

    shoes, safety belts, shields, goggles etc.) must be used while working at site.

    15. The company may from time to time add, delete, modify or change any rule as and when

    required.

    CONTRACTORS OBLIGATIONS / LIABILITIES:

    Above rules and regulations are to followed to take care of safety of persons employedby you, Other people working in the company and companys property. These rules are to befollowed strictly and wherever in doubt you will clarify with us for the same. Any work carriedout without following above rules and regulations will be considered as illegal. The contractorshall identify the company at all times against all claims for compensation under the provision

    of any law for the time being in force by or in respect of any labours employed by him incarrying out the contract and against all costs and expenditure incurred by the company inconnection therewith.

    It will be contractors responsibility to settle all legal deals of his labourers on theirtermination and will hand over the copy of the receipt obtained from the concerned labour, infull and final settlement of the claims of whatsoever nature, to the company. In case if anylabour engaged by the contractor raises any demand after his termination or after making fulland final settlement by the contractor during the currency or after the expiry of the contract, thecontractor shall settle the same and no liability will rest upon the company.

    3.3

  • 7/29/2019 42056398-Erection-and-Commissioning-Procedure.pdf

    17/94

    Chapter 4 - INSTALLATION

    Tools for Installation of DG Set

    Kirloskar Oil Engines Ltd.Large Engines Division

    INSTALLATION & COMMISSIONING MANUAL

    LIST OF TOOLS REQUIRED FOR

    INSTALLATION OF DG SET

    SR. NO. DESCRIPTION QTYA . TOOLS FOR UNLOADING AND SHIFTING OF DG SET

    AND AUXILIARIES1 MECHANICAL SCREW JACK 20 TON 4 NOS

    2 MECHANICAL SCREW JACK 10 TON 2 NOS

    3 SLING / STEEL ROPE / NYLONE ROPE AS REQD

    4 WOODEN SLEEPER Min. 50 NOS

    5 CHAIN PULLEY BLOCK 20 TON 2 NOS

    6 CHAIN PULLEY BLOCK 5 TON 1 NO

    7 TARPAULIN / PLASTIC SHEET TO PROTECT EQUIPMENTS AS REQD

    B GENERAL TOOLS1 DOUBLE ENDED OPEN SPANNER (10 TO 41 MM) 1 SET

    2 DOUBLE ENDED RING SPANNER (10 TO 32 MM) 1 SET

    3 BOX SPANNER 10 TO 30 MM (1/2 DRIVE) 1 EACH

    4 BOX SPANNER 30,32,36,41,46,50 & 55 MM (3/4 DRIVE) 1 EACH

    5 BOX SPANNER 60 & 65 MM (1 DRIVE) 1 EACH

    6 EXTENSION BAR 6 & 12 LONG (1/2 DRIVE) 1 EACH

    7 TOMMY BAR (1/2 DRIVE) 1 NO

    8 RATCHET (1/2 DRIVE) 1 NO

    9 EXTENSION BAR 8 & 16 LONG (3/4 DRIVE) 1 EACH10 TOMMY BAR (3/4 DRIVE) 1 NO

    11 RATCHET (3/4 DRIVE) 1 NO

    12 REDUCER (1.0 X 3/4 ) 1 NO

    13 REDUCER (3/4 X 1.0 ) 1 NO

    14 ALLEN KEY SET 2 MM TO 19 MM 1 EACH

    15 SCREW DRIVER HEAVY DUTY 2 DIFFERENT SIZE 1 EACH

    16 ADJUSTABLE SPANNER 8.0 & 12.0 1 EACH

    17 CUTTING PLIER 8 1 NO

    18 NOSE PLIER 8 1 NO

    19 CIRCLIP PLIER 8.0 LONG (INTERNAL) 1 NO

    20 CIRCLIP PLIER 8.0 LONG (EXTERNAL) 1 NO21 TAP SET 10,12,16,18,20,& 24 MM 1 EACH

    22 TAP SET WRENCH 1 NO

    23 PIPE WRENCH 12,18 & 24 1 EACH

    24 FILE ROUGH (ROUND, HALF ROUND & FLAT) 12 LONG 1 EACH

    25 FILE SMOOTH (ROUND, HALF ROUND & FLAT) 12 LONG 1 EACH

    26 BENCH VICE (HEAVY DUTY) 1 NO

    27 HAMMER (SMALL & BIG) 1 EACH

    28 CHISEL 6 & 8 1 EACH

    29 HOLE PUNCH 16,18,20,& 24 MM 1 EACH

    30 MALLET / PLASTIC BAR / PLASTIC HAMMER 1 NO

    4.1

  • 7/29/2019 42056398-Erection-and-Commissioning-Procedure.pdf

    18/94

    Chapter 4 - INSTALLATION

    Tools for Installation of DG Set

    Kirloskar Oil Engines Ltd.Large Engines Division

    INSTALLATION & COMMISSIONING MANUAL

    31 TIN CUTTER 12 LONG 1 NO

    32 SINGLE ENDED OPEN SPANNER 46,50,55,60,&65 MM 1 EACH

    33 FLAT RING SPANNER 60 & 65 MM 1 EACH

    34 8 MM PIPE BENDING MACHINE FOR PR GAUGES ETC. 1 NO

    35 CLEANING TRAYS 2 DIFFERENT SIZE 1 EACH

    C TOOLS FOR WELDING & CUTTING1 WELDING TRANSFORMER (ONLY FOR TAG WELDING) 1 NO

    2 WELDING RECTIFIER ROTATING 200 AMPS (FINAL WELDING) 2 NOS

    3 WELDING HELMET / SCREEN 3 NOS

    4 WELDING BRUSH, HAMMER & CHISEL 3 EACH

    5 RIGHT ANGLE 12 LONG 2 NOS

    6 GAS CUTTING TORCH WITH EXTRA NOZZLE 1 SET

    7 FLEX HOSE AND REGULATOR FOR SR. NO. 6 1 SET8 SPANNER FOR GAS CYLINDER 2 NOS

    9 ELECTRICAL ANGLE GRINDER 4.0 WHEEL DIA 2 NOS

    10 ELECTRICAL ANGLE GRINDER 6.0 WHEEL DIA 2 NOS

    11 MEASUREMENT TAPE STEEL 3 MTRS 3 NOS

    12 MEASUREMENT TAPE 15 MTRS 1 NOS

    13 WATER LEVEL MAGNETIC BASE 12 LONG 3 NOS

    14 6/8 MM DIA PLASTIC TUBE 20 MTRS

    15 25 MM DIA PLASTIC TUBE 25 MTRS

    16 NEEDLE PLUM 100 GM WEIGHT 3 NOS

    17 HACK SAW FRAME WITH BLADE 12 2 NOS

    18 CENTRE PUNCH 6 LONG 1 NOS19 CHAIN PULLEY BLOCK 5 & 10 TON 1 EACH

    20 SLING / WIRE ROPE / ENDLESS ROPE (DIFFERENT SIZES) AS REQD

    21 NYLONE ROPE 1/2 AND 1.0 DIA 20 MTRS.

    22 D SHAKLES DIFFERENT SIZE AS REQD

    23 CROW BAR 1.0 MTR LONG 2 NOS.

    24 ELECTRICAL MOTOR DRIVEN PIPE LINE CUTTER WITH 1 NO

    WHEEL 10 TO 12 DIA

    25 DRILL MACHINE WITH DRILL BITS 1 SET

    D PRECISION TOOLS1 DIGITAL VERNIER CALIPER (0 TO 300 MM) 1 NO

    2 MICRO METER OUT SIDE (0 TO 25 MM) 1 NO3 DAIL GAUGE (0.01 MM) 0 TO 10 MM TRAVEL 2 NOS

    4 MAGNETIC BASE FOR DAIL GAUGE 2 NOS

    5 STEEL SCALE 0 TO 1.0 MTRS 1 NO

    6 FEELER GAUGE MM (100 MM BLADE LENGTH) 1 SET

    7 SMALL MIRROR FOR DEFLECTION AND ALIGNMENT WORK 1 NO

    8 TORCH WITH CELL 1 NO

    9 MASTER LEVEL GAUGE 6 LONG 0.025 MM/ MTR ACCURACY 1 NO

    10 REAMER SET (REFER COUPLING DETAILS) 1 SET

    4.2

  • 7/29/2019 42056398-Erection-and-Commissioning-Procedure.pdf

    19/94

    Chapter 4 - INSTALLATION

    Tools for Installation of DG Set

    Kirloskar Oil Engines Ltd.Large Engines Division

    INSTALLATION & COMMISSIONING MANUAL

    E TOOLS FOR HYDRO TESTING AND ACID PICKLING

    1 HYDRAULIC PRESSURE TESTING PUMP WITH CORRECT 1 NO

    END CONNECTION AND FLEX HOSE (CAPACITY 50 BAR)2 PRESSURE GAUGE FOR HYDRO TESTING PUMP UP TO 60 BAR 1 NO

    3 ACID PICKLING PUMP 5.0 HP / 3.5 KW 1 NO

    4 ACID PICKLING TANK (CAN BE FABRICATED AT SITE) 150 LTRS 1 NO

    5 CHEMICALS FOR PICKLING, NEUTRALISING & PASSIVATION AS REQD

    F CONSUMABLES FOR INSTALLATION (MECH)1 GRINDING WHEELS FOR 4.0 GRINDER AS REQD

    2 GRINDING WHEELS FOR 6.0 GRINDER AS REQD

    3 HACK SAW BLADES AS REQD

    4 GLASS FOR WELDING HELMET (WHITE) AS REQD

    5 GLASS FOR WELDING HELMET (BLACK) AS REQD6 WELDING BRUSH AS REQD

    7 WELDING RODS 2.5,3.25,4.0,5 & 6 MM (ADVANI OERLICON / ESAB) AS REQD

    8 LINE DORI 20 MTRS

    9 CHALK / PENCIL (WHITE COLOUR) AS REQD

    10 TEFLON TAPE AS REQD

    11 EMERY PAPER ROUGH 60 TO 100 NUMBER AS REQD

    12 EMERY PAPER MEDIUM 300 TO 400 NUMBER AS REQD

    13 EMERY PAPER FINE 600 NUMBER AS REQD

    14 GRINDING PASTE (ROUGH AND FINE BOTH) AS REQD

    15 EMERY STONE / HONING STICK 10 X10 X100 AS REQD

    16 ORDINARY GREASE AS REQD17 HAND GLOVES (CLOTH, PLASTIC & ASBESTOS ETC.) AS REQD

    18 M SEAL, ARALDITE & FEVIQUICK AS REQD

    19 CTC, PETROL & HSD FOR CLEANING AS REQD

    20 CLEANING CLOTH, MARKING CLOTH & BANIAN CLOTH ETC. AS REQD

    21 CLEANING BRUSH AS REQD

    22 CELLO TAPE, PERMANENT MARKER AS REQD

    23 SPONGE AS REQD

    24 RUSTOLIN AS REQD

    G ELECTRICAL TOOLS1 MEGGER 500 AND 1000 V 1 NO

    2 TONG TESTER 0 TO 200 AMPS DIGITAL 1 NO

    3 MULTIMETER (DIGITAL WITH FREQ. MEASUREMENT UPTO 4 KHz) 1 NO

    4 LINE TESTER 2 NOS

    5 INSULATION PLIER 2 NOS

    6 SCREW DRIVER SET 1 NO

    7 WIRE STRIPPER 2 NOS

    8 CRIMPING TOOL FOR INSULATED AND NON INSULATED 1 NO

    LUGS UPTO 70 SQ.MM

    4.3

  • 7/29/2019 42056398-Erection-and-Commissioning-Procedure.pdf

    20/94

    Chapter 4 - INSTALLATION

    Tools for Installation of DG Set

    Kirloskar Oil Engines Ltd.Large Engines Division

    INSTALLATION & COMMISSIONING MANUAL

    9 EXTENSION BOARD WITH 15 AMPS & 5 AMPS, 5 PIN SOCKETS/ 3 NOS

    SWITCHES

    10 SERIES LAMP 1 NO

    11 SOLDERING IRON, WIRE AND FLUX 1 SET

    12 EARTH RESISTANCE TESTER 1 NO

    13 ELECTRICAL HAND DRILL MACHINE UPTO 15 MM BIT 1 NO

    14 ELECT. DRILL MACHINE WITH MAGNETIC BASE UPTO 30 MM 1 NO

    15 HAND LAMP WITH GUARD AND 20 MTRS CORD 1 NO

    16 NUMBER AND LETTER PUNCH 1 EACH

    17 BLADE / CUTTER AS REQD

    18 IMMERSION HEATER 1 NO

    19 BLOWER 1 NO

    20 RELAY TESTING KIT 1 SET

    21 SET OF SPANNERS FOR DOING ALL ELECTRICAL WORK 1 SET22 PHASE SEQUENCE INDICATOR 1 NO

    H CONSUMABLES FOR INSTALLATION (ELECTRICAL)1 INSULATION TAPE RED, YELLOW, BLUE & BLACK AS REQD

    2 BINDING TAPE AND BUTTONS (BLACK) AS REQD

    3 ELECTRICAL HAND GLOVES AS REQD

    4 CTC AS REQD

    5 ALUMINIUM TAGS (FOR CABLE NUMBERING) AS REQD

    6 CLAMPS FOR CABLE FIXING IN TRAYS AS REQD

    7 BITUMEN PAINT AS REQD

    8 FERRULES NOS 0 TO 9 T TYPE 2.5 SQ.MM AS REQD9 FERRULES NOS A TO Z T TYPE 2.5 SQ.MM AS REQD

    4.4

  • 7/29/2019 42056398-Erection-and-Commissioning-Procedure.pdf

    21/94

    Chapter 5 - PROCEDUREGrouting Procedure

    Kirloskar Oil Engines Ltd.Large Engines Division

    INSTALLATION & COMMISSIONING MANUAL

    Document no.-27.400.85.0.00

    TECHNICAL NOTE

    GROUTING PROCEDURE

    INTRODUCTION

    During installation of DG set on the foundation block, grouting is carried out in order.a) To minimize heat build up on foundation block.b) To assure precise and unsurpassed contact with baseframe.c) To provide a high coefficient of friction to help maintain DG set alignment which

    further reduces possible bearing or crank shaft alternator rotor damage.

    Generally powdered FOSROCK GP2 is used as grouting compound which is mixed withwater along with coarse aggregates or pea gravel of size 6sq.mm. down to obtain free

    flowing grout. ** Aggregates to be used only for pockets.

    1) PREPARATION OF GROUT

    In order to obtain optimum physical properties with grouts, precise mixing and curing ofgrout is necessary.

    A) MATERIAL AND EQUIPMENT REQUIRED FOR PREPARATION OF GROUT

    - FOSROCK GP2 of sufficient quantity.- Crushed aggregates or pea gravels of size 6 sq.mm. down to sufficient quantity.- A 220 lits. drum for stocking water - 4 Nos.- Buckets to carry mixed grout - 6 Nos.

    - Concrete mixer - tilting drum type - 2 Nos.- A water can measuring 4.5 lits. capacity.- A pan with dry FOSROCK GP2 in case of leaks.- Water bath curing compound - 2 Nos.- Hammer, Chisels, nails etc.- Wire Brush.- Sufficient length of MS plates.- Masonry tools like pan, trowel etc.

    B) MIXING OF GROUT- The quantity of grout required is estimated by using the following thumb rule.

    Weight of FOSROCK GP2 required = 2 x vol. of grouting space.- Place about 80% of the water required per batch inside the mixer.- Add bag by bag FOSROCK GP2 with mixer running.- Add balance about 20% water.- Add the crushed aggregates or pea gravel about 50% by wt. of FOSROCK GP2.- Mix for 5 minutes.- Unload into buckets for transporting and placing.

    B.1) PRECAUTIONARY MEASURES TO BE TAKEN DURING MIXING- Do not mix anything else like sand, cement etc. to the grout.- Do not pour more that 4.3 liters of water per bag of FOSROCK GP2 for grouting pockets

    and 4.5 liters. for plain grouting.- Mixed grout should be consumed within 20 minutes after mixing.

    5.1

  • 7/29/2019 42056398-Erection-and-Commissioning-Procedure.pdf

    22/94

    Chapter 5 - PROCEDUREGrouting Procedure

    Kirloskar Oil Engines Ltd.Large Engines Division

    INSTALLATION & COMMISSIONING MANUAL

    - If the ambient temperature is very high (above 40 deg.C) and humidity also is low, thegrout tends to lose moisture fast and thus fluidity is reduced. Under such circumstances,

    mixed grout may have to be consumed immediately after mixing.

    B.2) CHECKS TO BE FOLLOWED BEFORE MIXING- Ensure the FOSROCK GP2 used is well protected from moisture and no damages have

    occurred.- No Vibrators are used as a means of mixing.

    2) PLACING OVER OF GROUT

    C) CHECKS TO BE FOLLOWED BEFORE GROUTING

    - The top surface of foundation block is plane and rigid.- The top surface of foundation and bottom surface of baseframe should be free from oil,

    grease and debris.The foundation block is soaked with water for about 24 hours.

    - Ensure lowering of baseframe and anchor bolts in position.- Sole plates (Reqd. if any in relation to alignment) are well levelled.- Shuttering around the sole plates with MS angle or wooden block is done.

    D) GROUTING PROCEDURE- Grout the sole plates individually upto half their thicknesses.- Use mixed grout for the space in between sole plates and space around the sole plates.- Continue to grout bay after bay in both the sole plates.

    E) CHECKS TO BE FOLLOWED DURING GROUTING

    - Pouring of grout should be continuous and from one side to avoid voids.- Check for leaks. The leakages can be avoided by applying dry FOSROCK GP2.

    F) CURING OF GROUT- After 4 hours of grouting the grout becomes hard so water curing is carried out. Curing

    period should be minimum 6 d

    5.2

  • 7/29/2019 42056398-Erection-and-Commissioning-Procedure.pdf

    23/94

    Chapter 5 - PROCEDUREGrouting Procedure

    Kirloskar Oil Engines Ltd.Large Engines Division

    INSTALLATION & COMMISSIONING MANUAL

    PREPARATION OF FOUNDATION BLOCK

    z A surcharge of 15 mm concrete is provided on the top surface of foundation block.

    z The block surface shall be gently chipped off. There should not be any peak exceeding

    10 mm. The top surface of block shall be perfectly cleaned after chipping.

    z Mark the location of chokes (MS Block) on the foundation block just below the jacking

    bolt location.

    z The bearing area near the chokes to be flattened to the size 250 mm (L) x 150 mm (w).

    Surface shall be cleaned again.

    z Position the chokes such that length of each block gets equally divided at the centre of

    jacking hole. Chokes should be longitudinally parallel to the foundation block.

    z The foundation block and pockets shall be soaked with water for about 24 hrs.

    z Remove all remaining water from the pockets.

    z Place all the foundation bolts in the pockets.

    z Place the baseframe on minimum 200 mm height wooden sleepers and align all base

    frame mounting holes with pocket centres.

    z Clean the alternator mounting pads on the baseframe. Place the alternator on the base

    frame. Loosely connect the mounting bolts with alternator.

    z Clean baseplate bottom so that it is free from oil, debris etc. Insert foundation bolts from

    bottom in the baseframe. Assemble nut and washer with foundation bolt. Ensure that boltprojection is about 20 mm above nut top surface.

    z Ensure all bolts are laying straight in the pockets. The foundation bolt should not remain

    inclined in the pocket.

    z Lower the baseframe (with engine mounted on it) slowly on the choke plates and ensure

    that it rests firmly on all the chokes. While lowering the base frame make sure thatadjacent jacking screws are equally loaded and foundation bolts are in perfect position.

    z Carry out the leveling of baseframe with water level tube and level bottle. The baseframe

    should be leveled within 2 mm of water level.

    Note : Engine is mounted on the baseframe.

    PARTIAL GROUTING OF FOUNDATION BOLT

    z Refer specification No. 27.400.85.0.00 for preparation of grouting material and

    procedure.

    zFill 3/4th portion of pockets by slowly pouring the mixed grout. Ensure that there is no airpocket or cavity (voids) in the pocket after poring of grout.

    z After 4 hrs. of grouting the grout becomes hard, water curing is therefore necessary for

    minimum 6 days.

    z Carry out leveling checks once again before final grouting.

    z Carry out shuttering around the baseframe with MS angle or wooden plate.

    z Fill remaining 1/4th portion of the pocket with mixed grout.

    z Use pure GP2 cement for grouting the space between bottom of baseplate and

    foundation block top surface. Grouting will be done such that GP2 cement is filledsurrounding the baseplate and foundation block top surface. About 150 mm wide layersurrounding the baseplate and 3/4th thickness of bottom plate of baseplate in height will

    5.3

  • 7/29/2019 42056398-Erection-and-Commissioning-Procedure.pdf

    24/94

    Chapter 5 - PROCEDUREGrouting Procedure

    Kirloskar Oil Engines Ltd.Large Engines Division

    INSTALLATION & COMMISSIONING MANUAL

    be filled up with GP2 cement. Grouting should be continuous and from one side to avoidvoids.

    z Check for leaks. The leakage can be avoided by applying dry FOSROCK GP2.

    z After 4 hrs of grouting the grout becomes hard therefore water curing has to be carried

    out. Curing period should be minimum 6 days.

    z During curing period, meanwhile remove shuttering and carry out cementing of portion

    between baseplate and edge of foundation block on all four sides. Provide suitable slopetowards the edge of foundation block.

    TORQUING OF FOUNDATION BOLTS

    z After 6 days of grouting carry out torquing as per sequence given below.

    1) First apply 10 kgm torque on centrally located foundation bolt on both sides.

    2) Continue applying torque 10 kgm on foundation bolts starting from centrally located bolt

    towards engine and alternator and simultaneously on both sides.3) Repeat procedure by increasing torque value by 10 kgm in each step till final torquing of

    95 kgm is achieved.

    5.4

  • 7/29/2019 42056398-Erection-and-Commissioning-Procedure.pdf

    25/94

    Chapter 6 - PROCEDUREAlignment Procedure

    Kirloskar Oil Engines Ltd.Large Engines Division

    INSTALLATION & COMMISSIONING MANUAL

    RELATIVE POSITION OF THE SHAFTS IN THE HORIZONTAL PLANE

    The measurements show that :

    A axis is more at right than B one by = 9

    in the plane of dial gauge C1.

    B axis is more at right than A one by = 47

    in the plane of dial gauge C2

    Then the relative position of the shafts is as follows :

    The experience shows that some erectors prefer to realize an intermediary sketch giving the

    relative position of the traces of the axis A and B in the planes C1 and C2 before carrying out the

    representation of the axis in the vertical plane and the horizontal plane.

    With this operation the operators can probably better figure out the axis in the space, this inter-

    pretation can be considered as good as the one explained in this note.

    Plane C1 Plane C2

    9

    axisB

    axis A

    47

    104 - 862

    164 - 702

    6.3

  • 7/29/2019 42056398-Erection-and-Commissioning-Procedure.pdf

    26/94

    Chapter 7- PROCEDUREChemical Cleaning Procedure for Pipe Line

    INSTALLATION & COMMISSIONING MANUALKirloskar Oil Engines Ltd.Large Engines Division

    CHEMICAL CLEANING PROCEDURE FOR PIPES

    [Chemical Cleaning of the associated piping of DG set subsystem ( Material of constructioncarbon steel - seamless Tube ASTM A 106)]

    1. LOOP FORMATION

    The various pipes are joined together by means of mating flanges and flexible hoses and formedinto a closed loop system alongwith the chemical circulation pump and tank.

    2. PREFLUSH

    The system is filled with water and leak tested, it is then continuously flushed with water into the

    drain gutter. All high points if any are to be vented regularly till system is completely filled.

    3. DEGREASING

    The objective of degreasing is to remove all the dirt, loose rust and mill scale so as to provide anactive surface for acidic solvent treatment.

    The degreasing solvent to be used is proprietary formulation of an Alkali alongwith a Non lonicWetting Agent.

    The degreasing is to be carried out for a period of 2 hrs. at a temp. of 40 Deg. C and flow velocityof 0.2 m/s.

    4. FLUSHINGUse service water to flush the system till pH is neutral.

    5. ACIDIC SOLVENT TREATMENT

    The objective of acidic solvent treatment HCL 50% (strength 30%) + 50% water is to remove allthe rust, mill scale, welding slag and other oxide deposits. The circulation is to be carried out fora period 1-2 hrs. with help of acid circulation pump at flow velocity of 0.3 m/s.During the circula-tion hammer the pipe loop at regular interval so that welding slag,mill scale get removed.

    6. DRAINING & FLUSHING

    The acidic solvent is drained and the system is flushed completely till pH is neutral.

    7. ORGANIC ACID RINSE

    The step involves the circulation of an ammoniated organic acid (10% Caustic Soda + Water)having an alkaline pH to remove all residual matter and neutralize the acid solvent.

    The circulation of this is to be carried out for a period for 1 hr. at ambient temperature.

    7.1

  • 7/29/2019 42056398-Erection-and-Commissioning-Procedure.pdf

    27/94

    Chapter 7- PROCEDUREChemical Cleaning Procedure for Pipe Line

    INSTALLATION & COMMISSIONING MANUALKirloskar Oil Engines Ltd.Large Engines Division

    8. DRAINING & FLUSHINGThe solution is to be drained completely and flushed till pH is neutral.

    9. PASSIVATION

    The objective of passivation is to form a protective film on the freshly cleaned surfaces. Thepassivating solution with a sodium nitrite base is circulated for 4 hrs. at ambient temp. The systemis drained and inspected.

    The above procedure is carried out prior to system start up for the purpose of removing millscale, corrosion and other deposits. The operation provides a thin, uniform protective coating ofiron oxide and removes the loose material that might cause damage to systems down stream of

    piping.

    7.2

  • 7/29/2019 42056398-Erection-and-Commissioning-Procedure.pdf

    28/94

    Chapter 8 - KOELS RECOMMENDATIONSNote on Water Quality & Recommendation

    Kirloskar Oil Engines Ltd.Large Engines Division

    INSTALLATION & COMMISSIONING MANUAL

    QUALITY OF WATER REQUIRED TO PA6 ENGINES

    The raw water available for a cooling tower, could contain following characteristics :

    Hardness < 2500 mg / lit

    Alkalimetric Content (TAC) < 400 ppm

    Silicon < 100 mg / lit

    Suspended Matter < 20 mg / lit

    Chlorine < 300 mg / lit

    Sulphates < 600 ppm

    Ca Concentration Product < 15000 (F)2

    Although chemicals are available to condition such water quality, our experience in the pasthave shown that the problems occurs due to scaling / fouling and corrosion in the raw watersystem These problems occurred either due to incorrect treatment, or bad monitoring. Basedon past experience, KOEL essentially recommends softened water for use on raw watercircuit for PA6 engines, with cooling tower applications.

    The softened water will have the following characteristics :

    pH > 6

    Total hardness < 5 ppm

    Alkalimetic content (TAC) < 400 ppm

    Salinity strength < 300 ppm

    Suspended Matters < 20 ppm

    Please note that it is impossible to one treatment procedure for water at all sites. Werecommend a pre-survey by water treatment experts from M/s Nalco or M/s Ion Exchange fortheir recommendations or economical conditioning of water.

    Si suspended matter concentration, Ca concentration Chlorides + Sulphates will be decidedTOS etc. case to case basis on joint consultation with engine manufacturer & water treatmentexperts.

    A comprehensive TIN will be prepared on the above subject.

    Please note, the softened water outlet must be checked periodically and regularly to ascertainthe correctness of regeneration frequency.

    Use of Nalco / Ion Exchange chemicals must not be avoided to use of softener.

    H. T. Water :

    KOEL essentially recommends the use of DM water for H.T. water circuit with Nalco /Ion Exchange chemicals.

    RE / RAVI / KH -1 / 5516

    Date : 05/06/1999

    8.1

  • 7/29/2019 42056398-Erection-and-Commissioning-Procedure.pdf

    29/94

    Chapter 8 - KOELS RECOMMENDATIONSNote on Water Quality & Recommendation

    Kirloskar Oil Engines Ltd.Large Engines Division

    INSTALLATION & COMMISSIONING MANUAL

    Please note DM water being corrosive in nature must not be used without chemicals in H.T.water circuit as this will cause corrosion

    Before commissioning of DG set, the DM water with chemicals must be kept available soas to ensure their use of correct water quality and chemicals from first instance itself.

    Also ensure availability of softened water for L.T. Circuit and suitable chemicals during startof set. Ensure the availability of the expert from the chemical supplying company (Nalco /Ion Exchange) to stabilize the water chemistry and recommend correct final dosage ofchemicals.

    Maintain a log book of essential water parameters as suggested by the expert on the site.

    8.2

  • 7/29/2019 42056398-Erection-and-Commissioning-Procedure.pdf

    30/94

    Chapter 8 - KOELS RECOMMENDATIONSNote on Water Quality & Recommendation

    Kirloskar Oil Engines Ltd.Large Engines Division

    INSTALLATION & COMMISSIONING MANUAL

    LT , HT COOLING WATERUnsuitable water, results in scaling, pitting or corrosion. Use of very soft water should notdispense with water treatment, since water absorbs Carbon - di - Oxide which renders itcorrosive.

    LT WATER SYSTEM :

    LT WATER system can either be.

    1) Closed

    2) Half Open (for Stationary Plants)

    3) Open : With waste water and sea water. Necessary steps to be taken to avoidcorrosion, Scaling & to eliminate seaweeds & bacteria.

    In open system, precautions to be taken are as follows:

    1) A suction strainer should be provided and maintained in clean condition.

    2) Piping should be reduced so that flow rate should be maintained to avoidtemperature raise above 40 oC in order to avoid salt deposition.

    3) For application with sea water, pipes, Lub oil cooler and charge air cooler to bewaterproof ex. Bronze, Cupro-Nickel.

    Temperature deviation between system inlet and outlet should range from 10 to 12oC at fullload.

    REQUIRED WATER PROPERTIES :

    1) Hardness : Total hydrodynamic hardness should be minimum. Water can besoftened by using Soda.

    2) pH should be more than 6

    3) Chlorine ion content should be minimum (below 100 mg/ lit)

    4) Salinity should be less than 200 mg / lit

    5) Water should be clean at filling. If required can be cleaned by adding chemicals,further rinsing is necessary since these chemicals are acid.

    NECESSITY OF WATER TREATMENT1) To avoid chemical & electrochemical corrosion from different metals which requires

    basicity (pH) level to be maintained between 7.5 to 9.

    2) To avoid scale, liable to reduce wall heat conductivity.

    TYPES OF TREATMENT

    1) CHROMATE:

    Sodium & Potassium Chromate provides protection on Iron. Their efficiency of antiscalingprotection can be increased by addition of organic compounds. For Aluminium and coppersince, it is not compatible, it can be gained by adding Borate compound.

    TIN/COOL/VMK/001-00

    Date : 14/04/1998

    8.3

  • 7/29/2019 42056398-Erection-and-Commissioning-Procedure.pdf

    31/94

    Chapter 8 - KOELS RECOMMENDATIONSNote on Water Quality & Recommendation

    Kirloskar Oil Engines Ltd.Large Engines Division

    INSTALLATION & COMMISSIONING MANUAL

    When Chromate drops below 0.5 gm/lit, it becomes dangerous. They are then capable oforiginating corrosive reaction, chromate level recommended 2.5 to 3 gm/lit. Chromate doesnot deteriorate with time.

    2) BORATE - NITRITE:

    Mixture of sodium Borates & Nitrites with addition of organic compounds ensure efficientantiscaling action and corrosion resistance for ferrous material. But Nitrites in alone attackon welding therefore other components like borate - benzoates are added. 3 to 5 gm / litnitric contain is recommended. Nitrite are toxic from absorption of 4 gm of pure nitrite salts.

    Requirements of Additives :

    1) It must prevent corrosion

    2) It must prevent precipitation of scaling salts.

    3) It should be soluble in water4) It must be compatible with anti - freeze.

    5) It must have suitable pH range . (Stabilising 7.5 to 9)

    ENGINE REQUIREMENT DATA :

    1) FOR HSD

    HT cooling water temperature at engine outlet 80 to 85 oC - for non pressurised circuit

    HT cooling water temperature at engine outlet 95 to 100 oC - for pressurised circuit

    LT cooling water temperature at air cooler inlet 25 to 35 oC.

    2) FOR HFO(applicable only for HFO 0

    HT cooling water temperature

    For 0 to 60% MCR : Normal temperature 90 to 95 oC

    For 60 to 100% MCR : Normal temperature 80 to 85 oC

    LT cooling water temperature

    For 100 to 40% MCR : Normal temperature 40 to 45 oC

    For 40 to 15% MCR : Normal temperature 60 to 70 oC

    Injector Water Cooling : Injector Inlet temperature : 80 to 85 oC

    Injector Outlet Pressure : Normal 250 Kpa.

    QUANTITY OF WATER IN ENGINE (lit)

    No. Of Cylinders 6 8 9 12 16 18

    Quantity of Water (Lit) 260 340 370 520 670 750

    Nominal Recommended flow rate : 7.5 m3 / hr / cyl

    8.4

  • 7/29/2019 42056398-Erection-and-Commissioning-Procedure.pdf

    32/94

    Chapter 8 - KOELS RECOMMENDATIONSNote on Water Quality & Recommendation

    Kirloskar Oil Engines Ltd.Large Engines Division

    INSTALLATION & COMMISSIONING MANUAL

    A) LOW TEMPERATURE WATER FOR HT WATER COOLING AND LUBE OIL COOLING

    SR PROPERTY SPEC.

    NO.

    1. pH 7.5 to 7.8

    2. Total hardness (ppm) 300 max

    3. Alkalinity (ppm) 50-150

    4. TSS (NTU) 25 max

    5. Silica (ppm) 150 max

    6. Chlorides (ppm) 100 max

    7. Iron (ppm) 3.0 max

    8. TDS (ppm) 1000 max

    B) HIGH TEMPERATURE WATER

    SR PROPERTY SPEC.

    NO.

    1. pH 7.1 to 7.8

    2. Nitrite level (ppm) 1000-1200

    C) DEMINERALISED WATER

    1. Conductivity (ms / cm) 30 max

    2. Total Hardness (ppm) Nil

    3. Si O2(ppm) 0.5 max

    4. pH 8 - 9

    RECOMMENDED WATER QUALITY

    8.5

  • 7/29/2019 42056398-Erection-and-Commissioning-Procedure.pdf

    33/94

    Chapter 8 - KOELS RECOMMENDATIONSNote on Water Quality & Recommendation

    Kirloskar Oil Engines Ltd.Large Engines Division

    INSTALLATION & COMMISSIONING MANUAL

    E) INCOMING WATER FOR CPP

    SR PROPERTY SPEC.NO.

    1. Total hardness (ppm) 180 max

    2. Total Alkaline content (ppm) 400 max

    3. Suspended solids (ppm) 20 max

    4. pH 6.5 to 8.5

    5. Chlorides, Phosphates & Sulphates (ppm) 300 max (Total)

    6. Chlorides (ppm) 100 max

    7. Turbidity (NTU) 25 max.

    8.6

  • 7/29/2019 42056398-Erection-and-Commissioning-Procedure.pdf

    34/94

    Chapter 8 - KOELS RECOMMENDATIONSNote on Water Quality & Recommendation

    Kirloskar Oil Engines Ltd.Large Engines Division

    INSTALLATION & COMMISSIONING MANUAL

    E) INCOMING WATER FOR CPP

    SR PROPERTY SPEC.NO.

    1. Total hardness (ppm) 180 max

    2. Total Alkaline content (ppm) 400 max

    3. Suspended solids (ppm) 20 max

    4. pH 6.5 to 8.5

    5. Chlorides, Phosphates & Sulphates (ppm) 300 max (Total)

    6. Chlorides (ppm) 100 max

    7. Turbidity (NTU) 25 max.

    8.6

  • 7/29/2019 42056398-Erection-and-Commissioning-Procedure.pdf

    35/943 - 1

    Chapter 9- KOELS RECOMMENDATIONSNote on Lub Oil Quality & Recommendation

    Kirloskar Oil Engines Ltd.Large Engines Division

    INSTALLATION & COMMISSIONING MANUAL

    LUBRICATING OIL FOR PA-6 ENGINES

    High speed diesel engine of our range needs specially tailored lub oil, catering to following

    conditions:

    1) High firing pressure

    2) Mean Piston Speed

    3) High combustion temperature

    The above factors results in high stress on mechanical components and lubricating oil

    SEMT Pielstick has an elaborate approval procedure of lubricating oil for their engines. After

    through tests on chemical and physical characteristics of lubricating oil. It is subjected to rigerous

    on field trials, before a certain lubricating oil brand is approved for a specific engine series.

    IMPORTANT CHARACTERISTICS OF LUBRICATING OIL :

    A) VISCOSITY :

    To avoid metal to metal contact, it is mandatory to have stable and sufficient thick oil film

    between cylinder liner and piston ring. Oil from this region is high temperature thereby lower

    viscosity than when entering in the engine. The viscosity index expressing the temperature

    dependent of the viscosity is of importance to protect engine components.

    Lubricating oil viscosity has been chosen as being defined by SAE 40 grade that is between 12.5

    to 16.3 cSt at 100 Deg C. In this range, correct lubricating oil film and flow will be made through

    engine.

    If the viscosity changes, film thickness and flow will trend towards the values which can be

    dangerous to the engine.

    CAUSE OF DROP IN VISCOSITY :

    a) Diesel dilution coming from pump leakage (HSD)

    b) Unburnt diesel in fuel chamber.

    c) Leakages through injection pump.

    CAUSE OF RAISE IN VISCOSITY :

    a) Oxidation,

    b) Presence of insolubles

    c) Raw Fuel Dilution

    Alarm Limit : 2/3 SAE grade Variation (18%)

    Rejection Limit : One grade of SAE (25% variation of viscosity)

    B) TOTAL BASE NO (TBN) :

    This value defines the resistance value of lub oil against the corrosion (Mainly sulphuric, generated

    from Sulphur in Fuel)

    9.1

    TIN No. : TIN/LO/VMK/001/00

    Date : 19/06/1999

  • 7/29/2019 42056398-Erection-and-Commissioning-Procedure.pdf

    36/943 - 2

    Chapter 9- KOELS RECOMMENDATIONSNote on Lub Oil Quality & Recommendation

    Kirloskar Oil Engines Ltd.Large Engines Division

    INSTALLATION & COMMISSIONING MANUAL

    Other than Sulphur, Other engine running condition have an effect on this value. A too cold

    water will lead to temperature on liner walls lower than dew point of Sulphuric Acid.

    CAUSE OF DROP IN TBN1) High Sulphur Content

    2) Bad Adjustment of HT water Circuit

    3) Precipitation of additives due to water presence.

    LIMITS FOR TBN FOR LUB OIL :

    Fuel Gas Oil Gas Oil Distillates Interediates HFO

    % Sulphur < 0.1 < 1 < 1.8 0.3 - 1.8 1.8 - 3.0 3 - 4 < 5

    Mn TBN 5 10 16 16 20 20 25 - 28

    To keep cold corrosion rate low, neutralisation capacity of lub oil must be sufficiently high. Therefore

    TBN 40 oil is recommended for HFO Operation.

    C) WATER CONTENT :

    Presence of water in lub oil is the risk of major break down of engine. The water elimination

    will be made by centrifuges adjusted as purifier.

    Normal water content : 0.1 %

    Alarm Limit : 0.2 %

    Rejection Limit : 0.5 %

    In case of excessive wear, the water content, TBN & lub oil additives must be controlled. (Lub

    Oil additives trend is to react with water and disappear with it)

    CAUSES OF WATER CONTENT IN LUB OIL :

    a) Condensation of crankcase wall in humid and tropical zones.

    b) Engine Leakages

    c) Leakages in lub oil cooler

    d) Bad running of centrifuge.

    D) FLASH POINT :It is the temperature at which mist and product are ignited with a flame- hot point (In

    case of engines) like cylinder and crankshaft or by flame generated by blowby owing to bad

    tightness of rings.

    Flash point for new oil : 235 to 240 Deg C

    Alarm Level : 50 Deg C less than new oils flash point (Higher than 190 Deg C)

    Rejection Limit : 150 Deg C risk of self ignition and bursting of crankcase.

    9.2

  • 7/29/2019 42056398-Erection-and-Commissioning-Procedure.pdf

    37/943 - 3

    Chapter 9- KOELS RECOMMENDATIONSNote on Lub Oil Quality & Recommendation

    Kirloskar Oil Engines Ltd.Large Engines Division

    INSTALLATION & COMMISSIONING MANUAL

    E) DETERGENCY / DISPERSANCY :

    Oil has to keep clean the liners, pistons, piston Rings, and ring grooves from thecombustion products, This property is called as high temperature detergency.

    After lubricating the piston and liner, oil returns to sump during which it cleans crankcase walls

    connecting rods, Crankshafts. This effect is known as low temperature detergency.

    DISPERSANCY : Ability of oil to maintain in suspension all particles and unburnt components

    picked by oil in piston, liners etc. All the impurities must be transported to the purifier where

    most are removed. Dispersancy determined by visual inspection and automatic analysis of a

    spot.

    These values allow to define if the lub oil is still capable to clean and maintain the material in

    suspension.

    F) ANTIWEAR AND EXTREME PRESSURE:

    Whenever the oil film gets interrupted from or in insufficient quantity, the tribological

    characteristics have to be supported by antiwear and extreme pressure additives to reduce

    abrasive and adhesive wear.

    G) THERMAL STABILITY :

    Oil is exposed to long period of high temperature. Adequate thermal stability is therefore

    vital.

    H) OXIDATION STABILITY :

    Oxidation stability is required to prevent oxidation of oil due to high temperature and

    oxygen surplus in blow by gases and trapped air.

    I) LUBRICITY :

    Lubricant must be capable of covering surfaces to be protected. Therefore good

    spreadablity and reliability cohesion to the mettalic surfaces are required.

    J) ALKALINITY :

    The property permits the oil to react against corrosive wear by neutralising acidic

    combustion products from fuel sulphur.

    K) COMPATIBILITY WITH HEAVY FUEL :

    The lubricating oil and fuel should be compatible at prevailing temperature. Otherwise

    plunger sticking by deposit formation in fuel pump initiated by asphanates drop out from fuel

    may take place.

    9.3

  • 7/29/2019 42056398-Erection-and-Commissioning-Procedure.pdf

    38/943 - 4

    Chapter 9- KOELS RECOMMENDATIONSNote on Lub Oil Quality & Recommendation

    Kirloskar Oil Engines Ltd.Large Engines Division

    INSTALLATION & COMMISSIONING MANUAL

    L ) ANTIFOAMING :Oil circulation in engine is continuous. During the circulation, air gets mixed with oil

    intensively. Antifoaming capacity of lubricating oil should be high otherwise which is dangerous

    for bearing.

    FUNCTION OF LUBRICATING OIL.

    1) Lubrication

    2) Cooling

    3) Anticorrosion

    4) Antiwear

    LUBRICATION SYSTEMI) BEARING LUBRICATION

    Between crankshaft journal and bearing there must be an oil film of a defined thickness.

    By considering engine characteristics and temperature requirements, viscosity grade should

    be selected and specified viscosity grade shall be used.

    The oil is circulated in crankshaft to reach big end bearing of connecting rod. Here the

    oil film has to provide an oil film to resist the impact resulting from combustion pressure on

    piston head.

    The oil passes towards small end (through connecting rod holes) bearing of gudgeon

    pin where again oil film is required. A important task of lubricating oil is to cool the bearings

    (removing frictional heat)

    II) PISTON COOLING

    After gudgeon pin, oil enters in the interior as a coolant medium (cooling the piston

    head). For this oil must have good resistance against deterioration at high temperature which

    is known as Oxidation Stability.

    III) OUR LUB OIL CONSUMPTION :

    Recommended lub oil consumption is 0.8 to 1.2 gm / kwh. optimisation of Piston ring

    set, piston clearance, liner temperature and its ability to retain the shape and liner surface are

    prerequisites of lub oil consumption, this rate includes losses in separators / filters.

    Oil change is required when lub oil consumption gets decreased. reduced oil

    consumption results in stress on oil, as oil volume will be replenished to lesser degrees by

    fresh oil. Therefore will require frequent oil changes. It could also indicate a trend of external

    contamination etc. (Fuel dilution into lub oil or water contamination in lub oil through improper

    9.4

  • 7/29/2019 42056398-Erection-and-Commissioning-Procedure.pdf

    39/943 - 5

    Chapter 9- KOELS RECOMMENDATIONSNote on Lub Oil Quality & Recommendation

    Kirloskar Oil Engines Ltd.Large Engines Division

    INSTALLATION & COMMISSIONING MANUAL

    centrifuge settings.)

    LUB OIL PARAMETERS RECOMMENDED DURING THE ENGINE RUNNING

    CONDITION :

    Oil temperature at engine inlet : 59 to 61 oC

    Filtering : 30 m max. and is being changed to 20 m through main filter Glacier

    for HSD and Alfa - Laval centrifuge for HFO

    Flow Rate : 5 m3 / Hr - for L engines

    10 m3 / Hr - for V engines

    VOLUME OF LUB OIL IN THE SUMP (Wet Sump)

    For PA6 L and PA6 V st. engines (running on HSD)

    No. of cylinders 6 8 9 12 16 18

    Max level (Lit) 660 860 960 920 1200 1340

    Min Level (Lit) 560 730 810 770 1000 1115

    Flow rate through 75 75 75 100 110 120

    oil pumps m3 / Hr

    PE-LUBRICATION PUMP PRESSURE: 6 bar for engine and motor driven pump

    Volume of lub oil in the sump of PA6V CL Engine : 7,600 Lit (Engine running on HFO with

    external / dry sump)

    Volume of lub oil in the sump of PA6L CL Engine : 4,200 Lit (Engine running on HFO with

    external / dry sump)

    VOLUME OF LUB OIL IN THE SUMP (Wet Sump)For PA6 L CL and PA6V CL engines (running on HSD)

    No. of cylinders 6 8 9 12 16 18

    Max level (Lit) 700 910 1020 1500 1980 2200

    Min Level (Lit) 600 780 880 1350 1780 1980

    Engine Inlet pressure : 6 to 6.5 bar

    Engine outlet temperature : 73 oC

    9.5

  • 7/29/2019 42056398-Erection-and-Commissioning-Procedure.pdf

    40/94

    Chapter 10- ELECTRICAL SYSTEM

    Kirloskar Oil Engines Ltd.

    Large Engines Division

    INSTALLATION & COMMISSIONING MANUAL

    CONTROL PANELS

    Following control panels are suppliedalong with the DG set.

    Generator Control Panel (GCP)

    Local Sensor Stand (LSS)

    Motor Control Centers (MCC)

    Neutral Grounding Resistor (NGR)

    Breaker Panel.

    GENERATOR CUM SYNCHRONISING PANEL

    Function

    Synchronization, Protection, Control

    and Monitoring of DG SET.

    Features

    Suitable for Auto/Manual operation.

    Major Components

    Programmable Logic Controller.Operator Terminal (Panel View).Protection Relay.

    Power Meters i.e. KW, KVA, PF, A,V etc.Engine RPM Meter.Turbo charger RPM Meter.Excitation Voltmeter and Ammeter.

    Engine Frequency Monitoring Unit.Turbo. Frequency Monitoring Unit.Push Buttons and Selector Switches .

    PROGRAMMABLE LOGIC CONTROLLER

    Major ItemsCentral Processing Unit.

    Power Supply.

    Digital Input Modules.Digital Output Modules.RTD Modules

  • 7/29/2019 42056398-Erection-and-Commissioning-Procedure.pdf

    41/94

    Chapter 10- ELECTRICAL SYSTEM

    Kirloskar Oil Engines Ltd.

    Large Engines Division

    INSTALLATION & COMMISSIONING MANUAL

    Thermocouple Modules .Analog (4-20mA) Modules.Panel View ( HMI ).

    Functions of the PLC.

    Monitoring of the operating parameters.Operation logic execution.Auto synchronization and load sharing.

    STARTING INTERLOCK

    Manual mode

    Fuel Control Handle should be unlocked.Turning Gear to be disengaged.Level of Water Expansion Tank should be more than low level.

    Starting Air Pressure should be more than 16 bar.No Safety Stop should be operated.DG Breaker should be in off condition.Lube Oil Priming pressure should be more than 0.5 bar.

    Engine should not be in running condition.

    Auto mode

    HT Water Engine Inlet Temp. should be more than 40 Deg.

    PRE HEATING AND PRIMING MOUDLE

    Ability of an engine to take the load rapidly after a standstill period depends essentially on theambient conditions.More precisely on HT water and Lube oil temperature at the time of starting.DG set is equipped with Pre Heating and Priming module, which maintains a reduced flow of

    HT water and lube oil in the engine.

    This equipment allows maintaining water temp. between 40 to 50 deg. in the cylinders andcylinder heads, decreasing the lube oil viscosity and thus avoid the over pressure on starting,ensures an adequate lubrication of all the moving components.

    Power supply to this module is fed from alternate supply source.

    MODE OF OPERATION

    There are three modes to start the DG set.

    Auto mode :

    Start of the engine shall be through AMF operation.

    Engine will be start after checking the following condition.Under voltage relays on GCP/Customer panel senses the bus supply.In AMF mode these Under voltage relays will give command for starting the DG set

  • 7/29/2019 42056398-Erection-and-Commissioning-Procedure.pdf

    42/94

    Chapter 10- ELECTRICAL SYSTEM

    Kirloskar Oil Engines Ltd.

    Large Engines Division

    INSTALLATION & COMMISSIONING MANUAL

    MANUAL MODE-

    In Manual mode Starting of Engine, Closingof the DG Breaker manual.

    Closing of breaker may be Either dead bus orlive bus.

    In case of live bus of closing DG Breaker can

    be momentary paralleled With either of normalincomer.In this Engine starting can only be done After

    checking all necessary process Permissive.

    TEST MODE-

    In Test mode operation is similar to AUTOoperationGrid supply fail signal is given to PLC by simulation.

    ALTERNATORBasic Operating Principle

    Exciting current Ie(dc current from AVR)flows through exciter Stator.

    It induces emf in exciter rotor(3 Ph).Then It is rectified by rotating diode and field current flowsthrough main rotor winding.

    The flux due to this current induces an alternating emf in main stator winding.

    GENERATOR PROTECTION RELAY

    Combined numerical relayFunction

    REM 543 of ABB make is used for following abnormal protection conditions

    -Differential-Under Voltage-Over Voltage

    -Under Frequency-Over Frequency-Earth Fault-Over Current etc.

    -Reverse Power.-Breaker trip command and Engine Stop command will execute through GPR under the aboveabnormal conditions.

  • 7/29/2019 42056398-Erection-and-Commissioning-Procedure.pdf

    43/94

    Chapter 10- ELECTRICAL SYSTEM

    Kirloskar Oil Engines Ltd.

    Large Engines Division

    INSTALLATION & COMMISSIONING MANUAL

    AUTO SYNCHRONISATION RELAY

    Function

    To check following conditions for paralleloperation

    FREQUENCY DIFF. WITHIN SET LIMITVOLATAGE DIFF WITHIN SET LIMIT.PHASE ANGLE DIFF. WITHIN SET LIMIT

    If all above conditions are fulfilled it givesClosing command to the circuit breaker ofWhich is to be synchronized.

    GOVERNOR CONTROL UNIT

    Function

    To control Speed/frequency of the prime mover (Engine).

    AUTOMATIC VOLTAGE REGULATOR

    Function :

    To regulate the alternator voltage.

    Operation of AVR

    AVR senses the voltage signal Um from main stator and adjusts the field Current Ie, as per

    the set value to regulate the stator voltage.

    FREQUENCY MOINTERING UNIT

    FUNCTION

    Monitoring the speed of engine.It receives following inputs,24V DC supply.Magnetic RPM pickup input from pickup fitted on the Fly wheel of engineIt gives following outputs,RPM>170 (PF output) Threshold 1.

    RPM>300 (PF output) Threshold 2.RPM>550 (PF output) Threshold 3.RPM>700 (PF output) Threshold 4.

    RPM>840 (PF output) Engine over speed.Fault (PF output) Speed Sensing Failure.

  • 7/29/2019 42056398-Erection-and-Commissioning-Procedure.pdf

    44/94

    Chapter 10- ELECTRICAL SYSTEM

    Kirloskar Oil Engines Ltd.

    Large Engines Division

    INSTALLATION & COMMISSIONING MANUAL

    Following indications are used,Thresholds i.e. TH1 to TH4, Over speed .In working order In healthy condition, this indication should be always present. If thisindication is not there, either RPM pickup input has failed or connection to the over speed

    solenoid on compressed air module is loose or broken.

    Following controls are possible,

    Test This facility is to be used only when engine is in stopped condition. By pressing this button,engine RPM meter will reach up to 1000RPM and over speed solenoid valve on the air

    module is operated.

    Half speed test This facility is used to check OSPD safety when engine is running at speed of 840/2=420RPM. Bring speed about 400 RPM and press Half Speed Test button. Slowly startincreasing thespeed. When indication on RPM meter will cross 840 (actual engine speed420), OSPD safety should be operate as mentioned above.After operating above tests or in case over speed condition are rectified, press reset pushbutton.In case Engine over speed safety operates, with pressing reset button. Engine cannot be

    started again.EFMU also gives 4-20 mA output corresponding to engine speed. This output is connectedto engine RPM meter on ECP, engine RPM meter on LSS and to 4-20 mA input module ofPLC.

    THERMOCOUPLE

    Engine is equipped with temperature sensors, to show the temperature of exhaust gas from

    the respective cylinder heads and the temperature of turbo charger. The thermocouple isused as a sensor.

    The thermocouple operates on the principle of Seebeck effect, when two dissimilar metals/alloys are joined together to form a closed circuit and the two junctions are held at differenttemperatures, then a voltage is generated. This voltage is due to the temperature differencebetween the two junction. The voltage generated is proportional to temperature.

    The range of temperature measurement is from room temperature to 600 Deg. C, for alltypes of engines. Considering the temperature ranges & other factors like,

    We uses K-type thermocouple as a sensor for exhaust gas temperature and turbo charger

    temperature measurement. the typical range of K-type temperature sensor is -150 Deg. C.to 1400 Deg. C.

    TEMPERATURE SENSOR RTD-PT100

  • 7/29/2019 42056398-Erection-and-Commissioning-Procedure.pdf

    45/94

    Chapter 10- ELECTRICAL SYSTEM

    Kirloskar Oil Engines Ltd.

    Large Engines Division

    INSTALLATION & COMMISSIONING MANUAL

    DG Set is equipped with temperature sensor, to show the temperature lub oil, fuel oil, LTwater, HT water temperature, charge air cooler inlet and outlet temperature etc.

    The resistance temperature detector (RTD) PT 100 is used as a sensor. The RTDoperates on the principle of change in the electrical resistance of a conductor takes placewhen there is change in temperature. The PT 100 is a positive temperaturecoefficient type RTD, means when temperature increases the resistance of the

    conductor also increases. The output of the PT 100 is resistance, corresponding totemperature. The PT 100 sensor consist of 3 wires at the output. At 0 deg its resistance is100 ohm,the resistance increases by 4 ohm for every increase by 10 deg.

    MAGNETIC PICK UP( SPEED SENSOR )

    The magnetic pickup is used to detect the speed of the prime mover. Engine FrequencyMonitoring Unit (EFMU) which is mounted in the GCP is needed to convert thepickups output signal to one usable by the governor amplifier. The magnetic pickup

    will produce a voltage output , when any magnetic material moves through themagnetic field. Most engines have flywheels or other large gears made up ofmagnetic material ( usually iron or steel). Magnetic pickups can usually be installed

    without adding attachments to a gear or shaft. Non-magnetic materials, such asaluminum, brass and some stainless, will not excite the magnetic pickup. Anydevice which produces a dynamic discontinuity of magnetic material in the field of thepickup will produce an electrical voltage.

    LOCAL SENSOR STAND

    FunctionMonitoring of pressure parameters.

    Features

    Located near DG set for easy monitoringRemote control of engine possible.

    Major ComponentsPressure Gauges.Pressure Transmitters.Push Buttons.

    Indicating Lamps.

  • 7/29/2019 42056398-Erection-and-Commissioning-Procedure.pdf

    46/94

    Chapter 10- ELECTRICAL SYSTEM

    Kirloskar Oil Engines Ltd.

    Large Engines Division

    INSTALLATION & COMMISSIONING MANUAL

    INDICATIONS1. HT water Pressure 0-6 Bar (pump outlet)

    2. LT water Pressure 0-6 Bar (pump outlet)

    3. Lub oil Pressure 0-10 Bar (engine inlet)

    4. Injector Water Pressure 0- 6 Bar

    5. Fuel Pressure 0-10 Bar (engine inlet)

    6. Engine Speed 0-1000 RPM

    7. Local control Lamp

    8. Remote control Lamp

    9. Engine start permission Lamp

    10. Engine trip Lamp

    Switches

    1) Low lube oil priming pressure switchAlarm & Start interlock

    2) Low/ Very low lube oil pressure switch Alarm/Stop

    3) Low HT water pressure Alarm

    4) Low LT water pressure Alarm

    5) Low fuel pressure switch Alarm

    6) Turbocharger lube oil inlet pressure Low Alarm

    MCC PANEL

    Provide the supply to the auxiliaries

    1. LT RADIATOR.

    2. HT RADIATOR.3. EMD COMPRESSOR.4. L.OIL PRIMING PUMP.

    5. DRIP TRANSFER PUMP.6. TURNING GEAR.7. PREHEATING HEATER.

  • 7/29/2019 42056398-Erection-and-Commissioning-Procedure.pdf

    47/94

    Chapter 10- ELECTRICAL SYSTEM

    Kirloskar Oil Engines Ltd.

    Large Engines Division

    INSTALLATION & COMMISSIONING MANUAL

    BREAKER PANEL

    FUNCTION

    Vacuum circuit breaker is used to deliver the generated output power to the

    consumer.

    MAJOR COMPONENTS

    VCB trolley rated for 13.1 KA.

    Metering / Protection CTs and PTs

    Meters, indicators

    METERING DEVICE

    Ammeter with selector switch

    Voltmeter with selector switch

    INDICATIONS

    VCB ON

    VCB OFF

    Auto trip

    Spring charged

    CONTROLS POSSIBLE

    Local / Remote control selection

    VCB ON/OFF

  • 7/29/2019 42056398-Erection-and-Commissioning-Procedure.pdf

    48/94

    INSTALLATION & COMMISSIONING MANUAL

    Chapter 11- ELECTRICAL SYSTEMThermocouple / RTD Calibration Chat

    Kirloskar Oil Engines Ltd.

    Large Engines Division

    Date :

    THERMOCOUPLE CALIBRATION REPORT FORMAT

    StandardObserved ReadingSr.No

    Reading

    Temp. oC mV. Output Temp oC mV.Output

    01 0 oC 002 30 oC 1.2

    03 50 oC 2.02

    04 75 oC 3.058

    05 100 oC 4.1

    06 150 oC 6.14

    07 200 oC 8.14

    08 300o

    C 12.2109 400 oC 16.4

    10 500 oC 20.64

    11 600 oC 24.9

    REMARK :

  • 7/29/2019 42056398-Erection-and-Commissioning-Procedure.pdf

    49/94

    INSTALLATION & COMMISSIONING MANUAL

    Chapter 11- ELECTRICAL SYSTEMThermocouple / RTD Calibration Chat

    Kirloskar Oil Engines Ltd.

    Large Engines Division

    TEMPERATURE V/S OUTPUTCHARACTERISTICS OF K- TYPE THERMOCOUPLE

    Sr.No Temperature (oC) Output (mV)

    01 - 150 - 4.921

    02 - 100 - 3.553

    03 - 50 - 1.889

    04 - 25 - 0.368

    05 0 006 10 0.397

    07 20 0.798

    08 30 1.203

    09 40 1.611

    10 50 2.022

    11 60 2.436

    12 70 2.850

    13 80 3.266

    14 90 3.68115 100 4.095

    16 120 4.919

    17 140 5.733

    18 160 6.539

    19 180 7.338

    20 200 8.137

    21 250 10.151

    22 300 12.207

    23 350 14.292

    24 400 16.395

    25 500 20.640

    26 600 24.902

    27 700 29.128

    28 800 33.277

    29 900 37.325

    30 1000 41.269

    31 1100 45.108

    32 1200 48.828

    NOTE : Add Ambient Temperature.

  • 7/29/2019 42056398-Erection-and-Commissioning-Procedure.pdf

    50/94

    INSTALLATION & COMMISSIONING MANUAL

    Chapter 11- ELECTRICAL SYSTEMThermocouple / RTD Calibration Chat

    Kirloskar Oil Engines Ltd.

    Large Engines Division

    TEMPERATURE V/S OUTPUTCHARACTERISTICS OF RTD PT - 100

    Sr.No Temperature (oC) Output (ohm)

    01 - 150 39.71

    02 - 100 60.25

    03 - 50 80.31

    04 - 25 90.13

    05 0 100.0006 10 103.90

    07 20 107.79

    08 30 111.67

    09 40 115.54

    10 50 119.40

    11 60 123.24

    12 70 127.07

    13 80 130.89

    14 90 134.70

    15 100 138.50

    16 120 146.06

    17 140 153.58

    18 160 161.04

    19 180 168.46

    20 200 175.84

    21 250 194.07

    22 300 212.02

    23 350 229.67

    24 400 247.04

    25 500 280.90

    26 600 313.59

    27 700 345.13

  • 7/29/2019 42056398-Erection-and-Commissioning-Procedure.pdf

    51/94

    Kirloskar Oil Engines Ltd.Large Engines Division

    INSTALLATION & COMMISSIONING MANUAL

    CHAPTER-12 HANDING OVER

    COMMISSIONING REPORTS

  • 7/29/2019 42056398-Erection-and-Commissioning-Procedure.pdf

    52/94

    ENGINE DETAILS

    Engine Make :

    Engine Modle :

    Engine Sr. No. :

    Year of Mfg. :

    Speed / MHP :

    Firing order :

    Lube oil :

    Fuel :

    Direction of Rotation :

    ALTERNATOR DETAILS

    Make :

    Type :

    Sr.No.

    KW :

    K.V.A :

    Voltage :Current :

    Speed :

    Duty :

    AVR :

    Year of Mfg. :

    Frequency :

    Power factor :

    Excitation Voltage :

    Excitation Current :

    Insulation Class :

    Grease type :

    DE Bearing NDE Bearing

    Type : Type :

    KIRLOSKAR OIL ENGINES LTD.Large Engines Division

    4 MW EMERGENCY DG SET COMMISSIONING REPORTS

    Project :PANIPAT NAPHTHA CRACKER PROJECT CAPTIVE POWER PLANT

    Format No. : KOEL/L&T/EPCC-4/6556/Engine-Alter details/01

  • 7/29/2019 42056398-Erection-and-Commissioning-Procedure.pdf

    53/94

    Format No. : KOEL/L&T/EPCC-4/6556/DG Base frame levelling/01

    mm 0 Reference set

    mm mm

    mm mm

    mm mm

    KOEL L&T EIL

    Sign:

    Name:

    ENGINE

    ALTERNATOR

    Priming Pump SideGovernor Side

    Phase side NGR Side

    Remarks - DG Baseframe levelling done with water tube column and reading found within limit

    DG SET BASE FRAME LEVELLING

    KIRLOSKAR OIL ENGINES LTD. LargeEngines Division

    4 MW EMERGENCY DG SET COMMISSIONING REPOR

    Project : PANIPAT NAPHTHA CRACKER PROJECT CAPTIVE POWER PLANT

    Date :

  • 7/29/2019 42056398-Erection-and-Commissioning-Procedure.pdf

    54/94

    Engine No.- Alternator No.-

    ( B ) ( D ) ( F ) ( H )

    GOV SIDE LOP SIDE GOV SIDE LOP SIDE

    Gauge Position

    If DV OR DH IS -VE PLOT BELOW ENGINE AXIS.

    LOP Side

    DV DH

    C2 C2

    KOEL L&T EIL

    SIGN.:

    NAME:

    DATE:

    DIAL ON ENGINE ( C1 ) DIAL ON ALTERNATOR (C2)

    C1 Down C1 GOV Side

    UP

    Engine Axis Engine Axis

    DH=F-H/2

    DV=C-A/ 2 DV=A-C/2

    DH=D-B/2 DH=B-D/2

    DV=E-G/2

    If Dial on

    Inner of

    If Dial on Inner side of

    Flywheel

    If Dial on outer

    side of Flyheel

    CALCULATIONS

    C 1 C1

    BOTTOM SIDE

    (Indicator is 1/100 of millimeter )

    A

    D H

    B F

    C G

    E

    Gauge PositionDial on Engine

    C2

    ENGINE AND ALTERNATOR ALIGNMENT

    TOP SIDE TOP SIDE

    500 ( A ) ( E )

    ( C ) 500 ( G )

    BOTTOM SIDE

    KIRLOSKAR OIL ENGINES LTD.Large Engines Division

    4 MW EMERGENCY DG SET COMMISSIONING REPORTS

    Project : PANIPAT NAPTHA CRACKER PROJECT CAPTIVE POWER PLANTDATE-Format No. :KOEL/L&T/EPCC-4/6554/DG Alignment/01

    Dial on Alternator

  • 7/29/2019 42056398-Erection-and-Commissioning-Procedure.pdf

    55/94

    Format No. :KOEL/L&T/EPCC-4/6554/Web deflection/01

    Engine No.- Alternator No.-

    Coupled / Uncoupled

    1 Gauge on balance weight2 Insure dial when plunger seeezess reading

    increases3 Read the reading on dial( Bold & Big)

    (Upper scale reading )

    4 1 Unit =0.01mm

    Gov. SideC

    1 2 3 4 5 6 7 8

    A

    B

    C

    D

    E

    DV=[A+E/2-C]/100

    DH=B-D

    INSTRUMENTS USED ( TYPE,MAKE,SL.NO.):

    KOEL L& T EIL

    Sign :

    Name :

    Date:

    Page 1 of 1

    KIRLOSKAR OIL ENGINES LTD.Large Engines Division

    4 MW EMERGENCY DG SET COMMISSIONING REPORTS

    Project : PANIPAT NAPTHA CRACKER PROJECT CAPTIVE POWER PLANTDate :

    CRANKSHAFT WEB DEFLECTION MEASUREMENT

    A E

    B D

    LOP Side

    Guage PositionCylinder No.

  • 7/29/2019 42056398-Erection-and-Commissioning-Procedure.pdf

    56/94

    Format No :KOEL/L&T/EPCC-4/6554/Shim report/01 Date :

    Engine No.- Alternator No.-

    A B C D

    KOEL L&T EIL

    SIGN.:

    NAME:

    DATE:

    Page 1 of 1

    KIRLOSKAR OIL ENGINES LTD.Large Engines Division

    4 MW EMERGENCY DG SET COMMISSIONING REPORTS

    Project : PANIPAT NAPTHA CRACKER PROJECT CAPTIVE POWER PLANT

    DG SHIM REPORT

    Lube Oil Priming Pump Side

    B C

    Drive End side Non Drive side

    A D

    Governor side

    Position

    Shim thickness in mm

    Torquing on bolts

  • 7/29/2019 42056398-Erection-and-Commissioning-Procedure.pdf

    57/94

    SR.NO.

    1

    2

    3

    4

    5

    6

    7

    8

    9

    10

    11

    12

    13

    14

    15

    16 Acid Water Air

    17 Acid Water Air

    18 Acid Water Air

    19 Acid Water Air

    20 Acid Water Air

    Note: Confirm the Torque Values as per Drawing.


Recommended