Semiannual Social Monitoring Report
Project No: 42378-016 Loan No- BAN: 3087 December 2018
Power System Expansion and Efficiency Improvement Investment Program - Tranche 2
Construction of Five 132/33/11kV Substations in DESCO Area
This Semiannual Social Monitoring Report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature.
In preparing any country program or strategy, financing any project, or by making any
designation of or reference to a particular territory or geographic area in this document, the
Asian Development Bank does not intend to make any judgments as to the legal or other status
of any territory or area.
ii
Table of Content
DHAKA ELECTRIC SUPPLY COMPANY LIMITED (DESCO)
MINISTRY OF POWER, ENERGY & MINERAL RESOURCES
GOVERNMENT OF THE PEOPLE’S REPUBLIC OF BANGLADESH
4thSocial Safeguard Monitoring Report
on
Construction of Five 132/33/11kV Substations in DESCO Area
Period: July-December 2018
Dhaka
December, 2018
iii
List of Tables .......................................................................................... iv
List of Figures ........................................................................................ iv
Abbreviations and Acronyms ................................................................... v
Units of Measurement ............................................................................ vi
1. Introduction ...................................................................................... 1
1.1 Background ................................................................................... 1
1.2 Broad Objective ............................................................................. 1
1.3 Specific Objectives .......................................................................... 1
1.4 Project Location ............................................................................. 2
1.5 Scope of the Study ......................................................................... 4
1.6 Monitoring Law and Policy Standard .................................................. 4
1.6.1 ADB Safeguard Policy ............................................................... 4
1.6.2 ADB loan covenants with the DESCO ........................................... 4
2. Approach and Methodology ............................................................... 8
2.1 Overall Approach of Safeguard Monitoring .......................................... 8
2.2 Study Mobilization .......................................................................... 8
2.3 Study Team Mobilization .................................................................. 8
2.4 Data Collection Methods .................................................................. 9
3. Monitoring Results........................................................................... 10
3.1 Social Safeguard Compliance Status ................................................ 12
3.1.1 Compensation ....................................................................... 12
3.1.2 Livelihoods and employment .................................................... 13
3.1.3 Occupational Health, Safety and Security ................................... 13
3.1.4 Labor and Working Condition. .................................................. 13
3.2 Compliance status with ADB loan covenants ..................................... 14
4. Stakeholder Consultations ............................................................... 19
5. Conclusions and Recommendations ................................................. 21
Appendix 1: Monitoring Checklist .......................................................... 22
Appendix 2: Composition of the Team ................................................... 32
Appendix 3: Participant List of Stakeholder Consultation ...................... 33
Appendix 4: Photographs of Project Sites ............................................ 35
Appendix 5: Photo of Stakeholder Consultation ................................... 43
iv
List of Tables
Table 1.1: Location of the Sub-stations .................................................................... 2
Table 2.1: Variables and Indicators for Social Safeguard Monitoring ............................ 8
Table 3.1: Project Implementation Status .............................................................. 10
Table 3.2: Protective Equipment of Risky Limb in Human Body ................................. 14
Table 3.3: Summary of Compliance Status with ADB Loan Covenants ........................ 14
Table 3.4: Corrective Action Plan for Non-Complaince Status .................................... 17
Table 4.1: Location of Consultation meeting during Field Visit ................................... 19
Source: Field survey July – December 2018............................................................ 19
Table 4.2: Consultation Findings ........................................................................... 20
List of Figures
Figure 1.1: Map of DESCODistribution Area of Proposed 132/33/11kV SSs ................... 3
v
Abbreviations and Acronyms
ADB Asian Development Bank
CEGIS Center for Environmental and Geographic Information Services
DESCO Dhaka Electric Supply Company Limited
DoE Department of Environment
DPDC Dhaka Power Distribution Company
EIA Environmental Impact Assessment
EHS Environment, Health and Safety
EMP Environmental Management Plan
EMR Environmental Monitoring Report
EPC Engineering, Procurement and Construction
HR Human Resources
HSE Health, Safety and Environment
GoB Government of Bangladesh
kV kilo Volt
PAM Project Administration Manual
PPE Personal Protection Equipment
RAJUK RajdhaniUnnyanKartipakkho
RP Resettlement Plan
SSP Social Safeguard Policy
ToR Terms of Reference
1
1. Introduction
1.1 Background
Dhaka Electric Supply Company (DESCO) has taken initiatives to modernize the existing old
distribution system through renovation and with the construction offive 132/33/11kV new
substations at Aftabnagar, Banani, Uttara, Purbachal, and Tongi in Dhaka, Narayanganj and
Gazipur Districts respectively in relation to the increased demand within the circle of DESCO
area. However, construction of five (5) grid substation is ongoing whereas HYOSUNG
Corporation has been appointed and started the construction works. At this stage, the
construction activities of three (3) substaions out of 5 has already been completed and rest
of the sites (i.e. Banani and Tongi) have achieved 50% status of construction completion.
As this project is financed by Asian Development Bank (ADB), therefore, it is required to
implement this project in compliance with ADB’s social safeguard policy and the loan
covenants between ADB and Bangladesh Govt. There is a provision to monitor the social
safeguard compliance in accordance with the Bangladesh and loan covenant between
Bangladesh Govt and Asian Development Bank (ADB).
In this aspect, social safeguard compliance monitoring is conducted by CEGIS to monitor
social safeguard status during the project implementation at the five substation locations.
Based on the prepared checklist, social safeguard monitoring (4thphase) completed through
monthly field visit considering the social safeguard indicators likecompensation status,
livelihood and living condition, community health, safety and security and labor and working
condition following the Bangladesh National Policy Standard and Social Safeguard Policy
(SSP).
1.2 Broad Objective
The broad objective of the safeguard monitoring is to monitor the social safeguard
components (i.e.occupational health and safety, social issues)and Environmental
Management Plan (EMP) in relation to Asian Development Bank’s (ADB) safeguard policy
and Bangladesh and ADB loan covenants.
1.3 Specific Objectives
In relation to broad objective, there are some specific objectives of this study. The specific
objectives of the social safeguard compliance monitoring are to:
i. Analyze the Environmental and Social Safeguarding laws and policies of
Bangladesh and ADB
ii. Monitor working condition and occupational health safety during project
implementation phase
iii. Provide suggestion and measure addressing the Non compliance issues.
Introduction
2
1.4 Project Location
The location of the project is shown in Figure 1.1. The proposed 132/33/11kV Sub-Stations
and connected transmission lines will be constructed from different location in DESCO area
such as Dhaka North,Tongi under Gazipur and Purbachal under Narayanganj districts. The
locations of Sub-stations are given in the Table 1.1 below:
Table 1.1: Location of the Sub-stations
SI. No
Proposed grid name
Location description and address
Land area (decimal)
Remarks
1
Aftabnagar
132/33/11 kV
sub-station
Plot no -32/M, Road no -17,
Avenue-13, Sectoe-3, Jahurul
Islam City, Aftabnagar, Dhaka
GPS: N- 23°46’11.65’’
E- 90°27’24.02.’’
60
- Jahurul Islam City
(Aftabnagar) project
authority handover the
land to DESCO
authority. - -
Coonstruction work
has already been
completed
2
Tongi 132/33/11
kV sub-station
(Mill gate)
Tongi-3, Sub-station area, Mill
gate, Tongi, Gazipur
GPS: N- 23°53’47.22’’
E- 90°23’48.23.’’
82 (about)
*DESCO area (Tongi-3,
33/11kV Old sub-station)
*Old sub-station Site
cleaning work is going on,
New Sub station’s
Construction work has
already been started
3
Purbachal
132/33/11kV
sub-station
Purbachal New city project area,
Sector-2, Road no 210 and
305(close to corner plot),
Rupganj, Narayanganj
GPS: N- 23°49’57.01’’
E- 90°30’23.49.’’
103.3
*RAJUK handover the
land to DESCO Authority.
- Coonstruction work has
already been completed
4
Uttara third
phase 132/33/11
kV sub-station
Plot no 103, Avenue-3 and West
avenue, Sector-18, Uttara third
phase, Uttara, Dhaka
GPS: N- 23°51’31.53’’
E- 90°20’59.23.’’
198
*RAJUK handover the
land to DESCO Authority.
*Coonstruction work has
already been completed
5
Banani
132/33/11kV
sub-station
Plot no 31, Road no 5, Block – I,
Banani, Dhaka
GPS: N- 23°47’18.8’’
E- 90°24’17.97.’’
46.26
*DPDC handover the land
to DESCO authority and
DESCO handover to
HYOSUNG Corporation.
*The Site cleaning work
has done.
*Construction work
hasalready been started.
Source: Field visit 2018 and consultation with PD office, DESCO
Introduction
4
1.5 Scope of the Study
In line with the aforementioned objectives the scope of the services regarding the social
safeguard issues would cover the following:
• Review of social management and monitoring plan suggested in the EIA report in
line with the action plan proposed by ADB.
• Monthly monitoring of construction activities to overview their compliance with
national environmental and social regulations, and ADB’s performance standards
on social issues regarding sustainability.
• Monthly monitoring for the implementation of environmental monitoring activities
as specified in the environmental monitoring plan.
• Monthly monitoring of socio-economic issues like community safeguard due to
pollution, hazards and employment opportunity.
• Suggestion of pollution prevention and mitigation measures to ensure social
safeguard, to ensure compliance with national standard.
• Keeping close liaison with the project implementation office (Project Director),
and Engineering, Procurement and Construction (EPC) contractor.
• Providing a monitoring report at the end of every six (6) months in line with the
reporting requirement of ADB satisfying equator principles.
1.6 Monitoring Law and Policy Standard
1.6.1 ADB Safeguard Policy
The Safeguard Policy Statement (SPS) of Asian Development Bank reviewed to understand
the compliance and terms of partnership with the Bangladesh GoB. Presently,the
BangaldeshGovt amended the ECA 1995 tookthe construction of substation is under the
Orange B category (as like as ADB categorization) under the social safeguard policy.
In this social safeguard monitoring follow the Environmental Management Plan (EMP)
prepared during the period EIA study. In addition, the standards determined by this policy
are followed during this study. The standards for social safeguard issues identified in which
as all construction activities can continue taking care all social issues around the project
area. For this reason, this monitoring considers the risk of electrocution, safety measures
within the construction site, emergency plan, livelihood challenges, restoration process,
compensation process as any complaints from affected people can be noted with necessary
measures at the construction phase of the project.
1.6.2 ADB loan covenants with the DESCO
According to the Loan Covenant Article (II), section 2.01, DESCO should carry out the
project, with the due diligence and efficiency and in conformity with sound administrative,
financial, engineering, environmental and power sector practices. For the execution of
project following criteria should be followed. In this respect, social safeguard standard would
be maintained in terms of occupational health safety, employment opportunity, and
community social safety due to the project implementation.
Introduction
5
Implementation Arrangement
DESCO should ensure the project implementation in accordance with the detailed
arrangements set forth in the PAM. Besides, it is the responsibility of DESCO to ensure their
project management staff that has the qualification to undertake necessary tasks of
procurement, construction, supervision, inspection, and testing of equipment, payments to
contractors, monitoring, environmental and social safeguards due diligence and reporting of
progress relevant to the components under their responsibility.
Environment
DESCO should ensure that the preparation, design, construction, implementation, operation,
and decommissioning of the project and all project facilities comply with;
• All applicable laws and regulations of the relating to environment, health and
safety
• The environmental safeguard
• The EARF
• All measures and requirements set forth in the respective IEE and EMP and
any corrective or preventive actions set forth in a safeguard monitoring report
• Land Acquisition and Involuntary Resettlement1
• All land acquisition and resettlement activities are implemented in compliance
with
• Compensation and other entitlements have been provided to affected people
in accordance with the RP (if required).
• A comprehensive income and livelihood restoration program has been
established in accordance with the RP (if required).
Human and financial Resources to implement Safeguards Requirements
The DESCO should make available, or cause the project executing agency to make
available, necessary budgetary and human resources to fully implement the EMP, the RP
and any small ethnic community peoples planning framework.
Safeguards-related provisions in bidding documents and works and work contracts
The DESCO should ensure the following compliance in relation to contract or bidding during
the project implementation.
• Comply with the measures and requirements relevant to the contractor set
forth in the IEE, EMP and RP (if required) any small ethnic community
peoples plan and any corrective or preventive actions set out in a safeguard
monitoring report.
1There is no land acquisition and RP related activities that have been found in EIA study report under
this project.
Introduction
6
• Make available a budget for all such environmental and social measures
• Provide the borrower with a written notice of any unanticipated environmental,
resettlement or small ethnic community peoples plan.
• Adequately record the condition of roads, agricultural land, and other
infrastructure prior to starting to transport materials and construction
• Fully reinstate pathways other local infrastructure and agricultural land to at
least their pre-project condition upon the completion of construction.
Safeguard Monitoring and Reporting
The DESCO should comply the following section:
• Submit semiannual safeguards monitoring reports to ADB and disclose
relevant information from such reports to the affected person
• Any anticipated environmental and social as well as impacts arise during the
construction, implementation, or operation of the project that were not
considered in the IEE, the EMP or the RP promptly inform ADB of the
occurrence of such risks and impacts with detailed description of the events
and proposed corrective action plans.
• The Monitoring process should be verified by the external experts
• Reporting would be completed based on the any potential beach of
compliance with the measures and requirements set forth in the EMP
Labor standards
Following labor standards should be followed as per loan covenants:
• Comply with all applicable labor law and related international treaty
obligations of the borrower and do not employ child labor as defined under
the Bangladesh law
• Provide Safe working condition for male and female workers
• Carry out HIV/Aids and human trafficking prevention and awareness
campaigns in the campsites and corridor of influence
• Engage women workers as wage laborers depending on their skill and
• Provide equal wage for equal work between men and women.
Project Reviews
• The project progress would be reviewed by the ADB with necessary
midcourse corrections
• The Assistance should be provided by the Executing Agency (i.e. DESCO).
The environmental monitoring will assess the compliance that has been suggested under the
Bangladesh Govt. laws, policies and national standards (i.e. air, noise and water quality) and
ADB loan covenants. As there is no involuntary resettlement and ethnic minority issues,
Introduction
7
therefore, this monitoring assess the environmental and social safeguard issues in
accordance with the Govt. laws and ADB loan covenants like the above mentioned ways.
The Social Safeguard compliance monitoring has been conducted based on the above
mentioned national and international policy and compliance status have been mentioned
accordingly.
8
2. Approach and Methodology
2.1 Overall Approach of Safeguard Monitoring
The mixed (quantitative and qualitative approach) and interdisciplinary approaches
followedfor conducting this study. The locations of five (5) substations visited monthly and
analyzedwith the compliance status applying different social tools (i.e. Questionnaire Survey,
Observation, Group Discussion) considering construction activities, Impacts, safeguard
policies, and Bangladesh and ADB’s loan covenants.
2.2 Study Mobilization
A comprehensive checklist on environmental and social compliance was prepared. A
preliminary checklist (Appendix B) prepared based on the suggested recommendations
incorporated in the Environmental Management Plan (EMP) of EIA for the construction offive
132/33/11kV new substations in DESCO area.
In this way, study team for this study mobilized and visited five (5) grid substations where
constructions activities are ongoing. Based on the observation, this social safeguard
monitoring has been conducted and whole study mobilized according to the plan and the
prepared methodology.
2.3 Study Team Mobilization
Based on the contract agreement between DESCO and CEGIS (the Monitoring Consultant)
a multidisciplinary team was mobilized targeting the work plan to monitor the social
issuesfollowing the social safeguard policy and other selected social indicators.
The consultant (CEGIS) started work under the overall supervision of the Project Director,
maintaining close liaison with DESCO offices (both field and head office) and EPC contractor
(HYOSUNG ). The supervision got from the study team and guided the multidisciplinary
team for achieving the goal of the study, in relation to the study objectives. The progress of
the study was reviewed in weekly progress review meeting held in CEGIS. TheComposition
of the teammembers list presented in Appendix 2.
Table 2.1: Variables and Indicators for Social Safeguard Monitoring
Variables Indicators
a) Compensation Compensation for Land Acquisition (if required)
b) Livelihoods and Employment Employment opportunity, Occupational Status
APs (If required), Income, Wage
c) Community Health, Safety and Security Community health condition, Safety and Security
Status, Threats for Community health and safety
d) Occupational Health and Safety Status of Labor Health, Accidental status,
Monitoring Results
9
Variables Indicators
Mitigation measure (i.e. First Aid Box,
Ambulance), Status of Safety Tools and
Instruments (i.e. Gumboots, Earmuffs, Helmet,
Gloves etc)
e) Labor and Working Condition Labor Shed, Condition of Kitchen, Status of Food,
Sanitation and Drinking Water, Status of Waste
management (i.e. Kitchen Waste).
2.4 Data Collection Methods
Physical Observation
The Site specific physical observation occurred during the field work at the five (5)
Substations. With the physical observation, working condition, use of safety tools, sanitation
and drinking water status, labor shed condition, kitchen waste management status, food
quality, status of pollution monitored understood the site specific compliance status. The Non
complaiance issues also identified based on the physical observation and these issues
discussed with the relevant stakeholders during the KII and Group Discussions.
Key Informant Interview (KII)
During the project implementation, some key personnel from DESCO and HYOSUNG
corporationwere responsible to monitor the work progress. The site engineers from
HYOSUNG considered as the Key Informants (from each site) interviewed for understanding
the work progress and status of different social safeguard issues during the project
implementation.
Group Discussion (GD)
During the field visit, group discussion held with labours, site engineers, supervisors,
concerned personnel from DESCO to be updated with the construction status and
compliance status of relevant issues. During the consultation, Non-compliance issues also
identified and discussed how to address them within the duration of project implementation.
Consultation with relevant Stakeholders
The project director and concerned personnel from DESCO consulted regarding several
issues. The Non compliance issues addressed during the field visit shared with the project
directors and concerned personnel and outlined the guidelines based on their suggestion for
implementation. In addition, any difficulties related to the study addressed through such
consultation and relate them with the study findings.
Monitoring Results
10
3. Monitoring Results
This chapter provided the monitoring results based on monthly field visits at five project sites
in DESCO Area. The monitoring result addressed the social safeguard issues related
ongoing project activities from July–December 2018. Based on the prepared checklist, a
comprehensiveresult (July 2018 to December 2018)has beenprovided here considering the
field findings through monthly field visit.
Based on the following activities and implementation status of these 5 projects sites, all
activities 2 related to the construction observed and the findings of social safeguard
monitoring compiled following the ADB social safeguard policy and ADB –Bangladesh loan
covenants.
Table 3.1: Project Implementation Status
Substations Name Activity details Status
Aftabnagar Sub-station
� Installation the Gas
Insulated Switchgear (GIS)
� Done
� MV cable termination work
and AC DC cable laying
and termination work
� Done
� Roof slab and Column
casting
� Done
� Transformation bushing
installation
� Done
� GIS monitor installation � Done
� Civil work for installation of
electrical components like
transformer.
� Done
� Other civil works including
Building construction,
boundary construction
activities etc.
� Done
� Setup transformer inside
the substation
� 132/33 kV transformer
installation
work is complete
� Copping work � Done
Purbachal Sub-station
� Installation the Gas
Insulated Switchgear (GIS)
� Done
� MV cable termination work
and AC DC cable laying
and termination work
� Done
� Roof slab and Column � Done
2Piling, Electrical Works (i.e. Earth work),Transformer Foundation,RCC Works, Fellow Casting
Monitoring Results
11
Substations Name Activity details Status
casting
� Transformation bushing
installation
� Done
� GIS monitor installation � Done
� Civil work for installation of
electrical components like
transformer.
� Done
� Other civil works including
Building construction,
boundary construction
activities etc.
� Done
� Setup transformer inside
the substation
� 132/33kV transformer
installation
work is complete
Uttara 3rd phase Sub-station
� Copping work � Done
� Installation the Gas
Insulated Switchgear (GIS)
� Done
�
� Civil work for installation of
electrical components like
transformer
� Done
� MV cable termination work
and AC DC cable laying
and termination work
Done
� Other civil works including
Building construction,
boundary construction
activities etc.
� Done
� Setup transformer inside
the substation
� 132/33kV transformer
installation
� work is complete
� Installation the Gas
Insulated Switchgear (GIS)
� Done
� Roof slab binding � Done
Banani Sub-station
� Civil work for installation of
electrical components like
transformer
� The Earth Work is Ongoing
� Other civil works including
Building construction,
boundary construction
activities etc.
� Ongoing other civil works
� Column and Beam slab and
carpeting
� On going
� Piling � Completed
� Basement preparation and
casting work
� Completed
� RCC mat casting and 33/11
kV wall casting work
� Ongoing
� In the project area, the
safety activities
� Ongoing.
� Construction of boundary
wall around project site.
� The boundary wall at north-
west and southern part will
Monitoring Results
12
Substations Name Activity details Status
be reconstructed
� The eastern part of
boundary will be remaining
as usual
� Temporary fence is built in
the two site (north and
south) by tin and iron.
Tongi Sub-station
� Civil work for installation of
electrical components like
transformer
� The Earth Work is Ongoing
� Other civil works including
Building construction,
boundary construction
activities etc.
� Ongoing other civil works
� Column and Beam slab and
carpeting � On going
� Piling � Completed
� Basement preparation and
casting work � Completed
� RCC mat casting and 33/11
kV wall casting work � Ongoing
� In the project area, the
safety activities
� Ongoing.
� Construction of boundary
wall around project site.
� Existing boundary wall is
using now, the boundary
will be will re-construction
after the construction work.
Source: Monthly field visit from July-December 2018
3.1 Social Safeguard Compliance Status
3.1.1 Compensation
During the site visit the study team did not encounter any compensation related dispute in
the study area as no land acquired for the construction of any project. All project activities
are ongoing within demarcated land boundary owned by DESCO. In this consideration, there
is no compensation related issue found during this phase of study.
Monitoring Results
13
3.1.2 Livelihoods and employment
Local people stated that the Project has no threat for the existing livelihoods.At the same
time people of this area consider this project as the generation of working opportunities for
labours within the DESCO circle area.
As a follow up study, as the findings of monitoring ,it is found that a number of workers
(5%)from the localitygot the chance for working and rest of the workers joined as the
workforce from different districts for the construction of watch tower, cline the Sub Station
yard, color the building, GIS setup, testing and commissioning, RCC road construction work
and other minor activities were observed to be initiated in the project sites.
According to a working laborer, at present about 140 laborers are working in the five sites
whereas about ninety (95%) laborersare from Kurigram, Joypurhat, Tangail, Rangpur,
Gaibanda, Dinajpur, Netrokona, Jamalpur and Barisal districts. The labors of the
construction area are satisfied by their wages in comparison to the wage rate of project
surroundings. The wage rate of unskilled/semiskilled labors varies from BDT 400 to BDT 500
in the project site while for the skilled workers it is up to BDT 750 for the respective works.
3.1.3 Occupational Health, Safety and Security
HYOSUNG Corporationis aware to ensure the health, safety and security of the labourers at
all project sites. They have the provision to manage any accidental case through written
agreements with the adjacent hospitals. The ambulance service will be available if any
accidental case occurred during the project implementation.Still, there is no major accidental
case reported except 2 minor accidents at Banani and Tongi sub stations (CEGIS,
December 2018).
Based on the findings, three substations have enough first aid set up for primary treatment
but the facilities of first Aid Box for the Banani and Tongi sites is not found as in satisfactory
level. All emergency numbers were pasted around the project sitesto call and carry injured
patient at the adjacent local hospitals.
3.1.4 Labor and Working Condition.
adequatesafety equipment for laborers (like helmet, shoes, gown and other safety
equipment) are provided by the EPC contractor but the utilization of the safety tools is not
fully complied due to the habitual condition of labors.
In some cases, it is found that the availability and use of earmuff is not sufficient in relation
to the number of workers working during the construction.
There are fourteen (14) toilets (Aftabnagar2, Uttara third phase 2 and Purbachal2, tongi 4,
Banani 4)and 6 kitchens facilities in the three sub-stations (Uttara third phase 1,
whilePurbachal,Aftabnagar, Banani and Tongi each have one (1) kitchen. Site specific
photographs regarding the working condition is presented at the appendix 4.
In case of the use of PPE, it is required to improve the status of PPE in which the working
environment will comply in relation to ADB social safeguard policy and ADB and Bangladesh
government loan covenants. Exisiitng practiceof PPE use is specified in the following table
3.2.
Monitoring Results
14
Table 3.2: Protective Equipment of Risky Limb in Human Body
Risky limbs of human body Protective Equipment Practice in
project site Remarks
Eye Safety spectacles/goggles � Partially complied
Ear Earplugs X Not Complied
Head and Neck Safety helmets � Partially complied
Hands and Arms Gloves, gauntlets and
sleeves that covers part or all
of the arm
� Partially complied
Legs and Feet Safety boots and shoes � Partially complied
Lungs Half and full masks filtering
dust
� Partially complied
Source: Personal Protective Equipment at Work Regulations 1992 (as amended)
Due to the lack of labor shed, presently, the migrated laborers are living with poor
accommodation facilities. According to the findings, there is a need to improve the labor
shed quality and increase the number of toilet facilities.
According to the present study fidings, it is essential to draw the attention for ensuring
adequate accommodation facilities using standard materials. Besides, safe drinking water,
hygienic sanitation and proper medical facilities for the labourers needs to be complied fully
within the next phase of monitoring.
The project authority stated earlier that all these facilities will be improved before starting the
work in construction phase. At present some activities in construction phase has already
been started but scenario of the above mentioned facilities remain unchanged. So, it is a
matter of concern for the project authority to pursue the EPC contractor as well as
subcontractors to ensure standard accommodation facilities for alllaborers.
3.2 Compliance status with ADB loan covenants
The compliance status with the ADB loan covenants have been monitored based on
indicators provided in the ADB loan covenants. The summary of the findings for compliance
status with is presented in the following table 3.3
Table 3.3: Summary of Compliance Status with ADB Loan Covenants
Indicators Issues Activities
Compliance Status
Complied Not
Complied Remarks
Human and
financial
Resources to
implement
safeguards
requirements
� DESCO should
make available,
or cause the
project executing
agency to make
available,
necessary
� DESCO
made
contract with
HYOSUNG
which have
available
manpower,
Fully
Complied
Human and
financial
resources
management
follows the
ADB and
Monitoring Results
15
Indicators Issues Activities
Compliance Status
Complied Not
Complied Remarks
budgetary and
human resources
to fully implement
the EMP
budget and
other
resources
for the
implementati
on of EMP.
safeguard
requirements.
Safeguards-
related
provisions in
bidding
documents
and works
and work
contracts
� Comply with the
measures and
requirements
relevant to the
contractor set
forth in the EIA
and EMP.
� Make available
budget for all
such
environmental
and social
measures
� The
Environment
al consultant
and DESCO
monitor
through
monthly visit
where the
construction
activities
started.
Fully
Complied
All safeguard
related
provisions
incorporated in
bidding
documents,
works and
work contracts.
Safeguard
Monitoring
and
Reporting
� Any anticipate
results that were
not considered in
the EIA and the
EMP promptly
inform ADB and
proposed for
mitigation in
corrective action
plans.
� The Monitoring
process should
be verified by the
external experts
� Reporting would
be completed
based on the any
potential beach of
compliance with
the measures
and requirements
set forth in the
EMP.
� Reviewed
the EMP
provided in
the EIA
� A Review
team formed
and
reviewed
after the
submission
of
monitoring
report.
� All
compliance
status
prepared
based on
selected
indicators
provided in
the
checklist.
Fully
Complied
Safeguard
Monitoring and
Reporting
completed (1st,
2nd and 3rd
EMR)
And rests of
the reporting
are ongoing
with the close
interaction
between
DESCO and
Environmental
consultant.
Monitoring Results
16
Indicators Issues Activities
Compliance Status
Complied Not
Complied Remarks
Labor
standards
� Comply with all
applicable labor
law, treaty
obligations of the
borrower and
child labor law of
Bangladesh
� Provide Safe
working condition
for male and
female workers
Carry out
HIV/Aids and
human trafficking
prevention and
awareness
campaigns in the
campsites and
corridor of
influence
� Compliance
status
monitored
through site
specific visit
and
consultation
with the
respective
stakeholders
by DESCO
and
Environment
al
Consultant.
Partially
Complied
(80%)
Suggestions
for achieving
full compliance
suggested in
the CAP.
� Evaluation for
risks and impacts
on health and
safety during
preconstruction,
construction,
operation and
decommissioning
of the project
Partially
Complied
(30%)
Suggestions
for achieving
full compliance
suggested in
the CAP.
� Engage women
workers as wage
laborers
depending on
their skill
� Provide equal
wage for equal
work between
men and women.
Monitoring Results
17
Indicators Issues Activities
Compliance Status
Complied Not
Complied Remarks
Project
Reviews
� The project
progress would
be reviewed by
the ADB with
necessary
midcourse
correction
� All
Submitted
Report
reviewed by
ADB
Fully
Complied
All comments
(1st , 2nd and
3rd Monitoring
report) from
the ADB
incorporated
and submitted
to DESCO.
Source: EMR findings from July 2018 to Dewcember 2018.
Table3.4: Corrective Action Plan for Non-Complaince Status
Indicators Status Corrective Action Plan (CAP)
Labor standards Partially Complied (75%)
� All applicable labor laws,
treaty obligations of the
borrowers and child labor law
of Bangladesh should be
followed strictly
� Increase safe working
improving labor shed
� Awarness on Health Safety
Issue (i.e. HIV AIDS) would
be increased through regular
tool box trainng
Working Condition Partially Complied (70%)
� - The habit of the use of
PPE for labors should be
increased
� Sanitation facilities should
adequate in comparison
with the total labor force
� Faciltiies of labor shed
shuld be improved
�
Monitoring Results
18
Occupational Health and Safety
(OHS) In average 70% complied
� The decision during the tool
box meeting for the use of
PPE should be followed
and monitored during the
construction.
� Ensure available PPE
instrucment (i.e. Safety
shoes and socks) against
the number of labor force.
19
4. Stakeholder Consultations
Several stakeholder consultations were held in the study area. These consultations were held
comprising of different stakeholders such as project affected people (PAPs, local DESCO officials,
representatives from HYOSUNG and other local concerned people). These stakeholders were
brought together through prior contacts. Several issues were discussed in the meeting regarding the
project. In consultation meetings, the participants expressed their opinion spontaneously, and the
monitoring team recorded all the information delivered in the meeting. Participants list presented in
Appendix 3 and Photos added in Appendix4.
Table 4.1: Location of Consultation meeting during Field Visit
District Upazila/Thana Consultation Place Date Number of
Participants
Dhaka
Uttara Uttara third phase Sub-
Station area
31.07.2018 2
29.08.2018 2
06.09.2018 2
04.10.2018 4
12.12.2018 2
Aftabnagar Aftabnagar Sub-Station
area
15.01.2018 6
29.08.2018 2
28.09.2018 4
04.10.2018 4
13.012.2018 2
Banani Banani Sub Station area
03.07.2018 11
28.08.2018 2
04.09.2018 7
02.10.2018 12
25.11.2018 12
20.012.2018 3
Narayanganj Rupganj Purbachal Sub-Station
area
29.07.2018 8
28.08.2018 2
04.09.2018 10
07.10.2018 4
05.11.2018 5
13.12.2018 2
Gazipur Tongi Tongi Sub-Station Area
31.07.2018 10
28.08.2018 3
06.09.2018 9
03.10.2018 10
06.11.2018 12
18.12.2018 12
Total 164
Source: Field survey July – December 2018
Stakeholder Consultations
20
Table 4.2: Consultation Findings
Stakeholders Outputs
Sub-assistant Engineer
and officials of the project
- Banani Site about 46.26 decimals which was previously used as
store and Tongi site about 82 decimals of land which was
previously used for 33/11kV Sub-Stations.
- Shortage of space at the Substations (i.e.Banani and Tongi) made
difficulty for the construction of labor shed, toilets and keeping
construction materials .
- About 5 % labors from the nearest locality.
- Mobile toilet will be set up at Banani Site.
Safety manager of
HYOSUNG
- Safety, Security and Health Services are available for the workers
- Tool Box Training is ongoing according to the provision
- Have a good concern for the use of PPE by workers and trying for
100 percent compliance
-
Local (affected)
stakeholders
- No complain adreesed by the local people regarding any
compensation issue
- Avoid construction work at night.
Engagement of local labors - Needs to increase labors from adjacent project location (i.e Karwail
Slum)
Source: EMR findings from July 2018 to Dewcember 2018.
21
5. Conclusions and Recommendations
This social safeguard monitoring was conducted at the five (5) sites and observed the
compliance status based on ADB safeguard policy, EMP provided in the EIA, Government of
Bangladesh (GoB) and ADB loan covenant. For the social safeguard monitoring,
occupational health and safety, and workers’ wellbeing, impacts and benifits of community
people due to construction have been observedand site specific compliance provided
through monthly field visit based on prepared selected variables and indicators. In addition, a
corrective action plan has been prepared for non-complaince issues addressed during the
field visit.
To make the process more smooth and efficient, the following recommendations are
proposed by the study team should be followed to address the non –complaince issues at
this stage of project implementation.
• More awareness is to be created among the workers and community dwellers
regarding the health and safety risks associated with the construction phase of
the project. Besides, one paramedic doctors, and an ambulance need to be made
available for the labors in case of any injury and accident.
• Weekly toolbox meetings on health and safety, as well as the other governing
environmental and social issues should be initiated.
• Increased awareness on child labor; confining the involvements of labors below
18 years of age to light works (works not connected with heavy loads).
• Emergency preparedness and response plan; fire prevention, protection and
control plan;
• Though construction materials like sand and soil were not covered with polythene
at any site. This might cause dust pollution in dry condition. Hence, it is required
to cover the construction materials properly;
• It is obligatory to provide hearing protection equipment to the employees who are
exposed to loud noise;
• Separate dustbins used for both disposal and non disposal waste during
construction;it should be maintained.
• The level of safety for workers must be enhanced with comprehensive
enforcement on PPE usage, and regular (at least four times a day) health and
safety supervision should be carried out;
• Workers working condition i.e. accommodation, drinking water, sanitation and
medical facilities has remained same as it was in earlier phase of monitoring;
• The sanitation system for labor must be improved up to a healthy and desirable
level;
• The labor sheds must be improved up to a comfortable, useable and desirable
level for construction workers and security force;
• Recruitment of more local labor in the newly constructed sites would certainly
improve the economic condition of local people; Rationalized work permit system
and enhanced medical support at site should be maintained.
22
Appendix 1: Monitoring Checklist
Category Description of potential
impact
Measures/Indicators
Substations Name
Uttara Purbachal Aftabnagar Banani Tongi
Co
mp
lied
No
t
Co
mp
lied
Rem
ark
s
Co
mp
lied
No
t
Co
mp
lied
Rem
ark
s
Co
mp
lied
No
t
Co
mp
lied
Rem
ark
s
Co
mp
lied
No
t C
om
pli
ed
Rem
ark
s
Co
mp
lied
No
t C
om
pli
ed
Rem
ark
s
Socio-Economic Environment
Land Acquisition
There is no impact
because Land is not acquisied.
Not Applicable. ✓ ✓ ✓ ✓ ✓
Livelihood and living condition
Livelihood and living system may be disturbed due to the development activities
Causing no threat to the livelihood of local people
✓ ✓ ✓ ✓ ✓
Prioritize local labors in employment
Not applicable for the project
site
Not applicable for
the project
site
Not applicab
le for the
project site
Partially
10%
Partially
10%
Develop a separate road network during construction
NA Existing road used
for the sub
station
NA Existing road used
for the sub
station
NA Existing road used
for the sub
station
NA
Existing road used
for the sub
station
NA
Existing road
used for the sub station
23
Category Description of potential
impact
Measures/Indicators
Substations Name
Uttara Purbachal Aftabnagar Banani Tongi
Co
mp
lied
No
t
Co
mp
lied
Rem
ark
s
Co
mp
lied
No
t
Co
mp
lied
Rem
ark
s
Co
mp
lied
No
t
Co
mp
lied
Rem
ark
s
Co
mp
lied
No
t C
om
pli
ed
Rem
ark
s
Co
mp
lied
No
t C
om
pli
ed
Rem
ark
s
Separate water facilities for workers
Partially
80%
Partially
80%
Partially
80%
Partially
80%
Partially
80%
Community Health, Safety and Security
Health, safety and security would be affected during pre, construction, operation and decommissioning phases of the project.
Construction of Fence around project area
✓ ✓ ✓ ✓ ✓
No settlem
ent found
adjacent to the project
site
Evaluation for risks and impacts on health and safety during preconstruction, construction, operation and decommissioning of the project
Partially
60%
Partially
60%
Partially
60%
Partially
70%
Partially
70%
Involve Community in Risk Assessment Process
Not app
licable for the project
site
Not applicable for
the project
site
Not applicable
for the project
site
Partially
70%
Partially
65%
Consider Community Health and Safety in Designing infrastructure and equipment
✓
The
project
almost
complet
ed
without
causing
any
risks on
commu
nity
health
✓
The
project
almost
complet
ed
without
causing
any
risks on
commu
nity
health
✓
The project almost completed
without
causing any risks on
community
health Safety
Partially
70%
Partially
60%
24
Category Description of potential
impact
Measures/Indicators
Substations Name
Uttara Purbachal Aftabnagar Banani Tongi
Co
mp
lied
No
t
Co
mp
lied
Rem
ark
s
Co
mp
lied
No
t
Co
mp
lied
Rem
ark
s
Co
mp
lied
No
t
Co
mp
lied
Rem
ark
s
Co
mp
lied
No
t C
om
pli
ed
Rem
ark
s
Co
mp
lied
No
t C
om
pli
ed
Rem
ark
s
Safety
issue
Safety
issue
issue
Practicing safe management for hazardous materials which may pose threat to the community
✓ ✓ ✓ ✓ ✓
Availability of plan for natural hazards
Not applicable for
the project
site
Not applicable for
the project
site
Not applicable
for the project
site
Partially
60%
Partially
60%
Develop and Implement an Emergency Response Plan
✓
✓
✓
✓
✓
Training and instruction to the security personnel about their behavior and communication with the local people
✓
✓
✓
Partially
75%
Partially
75%
Practice of Tool box meeting and reporting
✓ ✓ ✓ ✓ ✓
Establishing a grievance mechanism for the community dwellers
Not applicable for
the project
Not applicable for
the project
Not applicable
for the project
Partially
60%
Partially
60%
25
Category Description of potential
impact
Measures/Indicators
Substations Name
Uttara Purbachal Aftabnagar Banani Tongi
Co
mp
lied
No
t
Co
mp
lied
Rem
ark
s
Co
mp
lied
No
t
Co
mp
lied
Rem
ark
s
Co
mp
lied
No
t
Co
mp
lied
Rem
ark
s
Co
mp
lied
No
t C
om
pli
ed
Rem
ark
s
Co
mp
lied
No
t C
om
pli
ed
Rem
ark
s
site site site
Provision of health service facilities to community
Not applicable for
the project
site
Not applicable for
the project
site
Partially
60%
Partially
50%
Safety trainings for workers (i.e. fire control, working at height, working in heat, first aid etc.)
✓ ✓ ✓ Partially
70%
Partially
70%
Increase awareness amongst the workers and employees and conduct health awareness drivers and medical camps in the neighboring areas (HSBC)
Not applicable for
the project
site
Not applicable for
the project
site
Not applicable
for the project
site Partially
70%
Partially
70%
Causing no disturbance on locally or culturally important sites
✓ ✓ ✓
✓ ✓
Ensure no use of Polychlorinated Biphenyls (PCB) in transformers
✓ ✓ ✓
✓ ✓
26
Category Description of potential
impact
Measures/Indicators
Substations Name
Uttara Purbachal Aftabnagar Banani Tongi
Co
mp
lied
No
t
Co
mp
lied
Rem
ark
s
Co
mp
lied
No
t
Co
mp
lied
Rem
ark
s
Co
mp
lied
No
t
Co
mp
lied
Rem
ark
s
Co
mp
lied
No
t C
om
pli
ed
Rem
ark
s
Co
mp
lied
No
t C
om
pli
ed
Rem
ark
s
The workers’ camps should be located away from residents and sensitive receptors schools, health centers etc.
✓ ✓ ✓
✓ ✓
All vehicles exit points from the construction site shall have a wash down or shakedown area where mud and earth can be removed from the vehicles before it enters the public road system. All wash down areas are to drain to a sedimentation basin.
Not
applica
ble for
the
project
site
Not
applica
ble for
the
project
site
Not
applic
able
for the
project
site
Partially
50%
Partially
50%
Information disseminati
on
Disputes may arise in the nearby community if public consultation meeting is not held.
Disclosure of EIA Report and sharing project information
Partially
90%
Partially
90%
Partially
90% Partially
80%
Partially
60%
Arranging public consultation meeting
Partially
90%
Partially
90% Partially
90%
Partially
80%
Partially
70%
Quality of consultation
Partially
Partially
Partially Partially Partially
27
Category Description of potential
impact
Measures/Indicators
Substations Name
Uttara Purbachal Aftabnagar Banani Tongi
Co
mp
lied
No
t
Co
mp
lied
Rem
ark
s
Co
mp
lied
No
t
Co
mp
lied
Rem
ark
s
Co
mp
lied
No
t
Co
mp
lied
Rem
ark
s
Co
mp
lied
No
t C
om
pli
ed
Rem
ark
s
Co
mp
lied
No
t C
om
pli
ed
Rem
ark
s
and disclosure 90% 90% 90% 70% 70%
Working Condition
Community dwellers may feel that they are not giving substantial share in project related job opportunity
Adequate fire precautions in place (for example, fire extinguishers, escape routes)
Partially
90%
Partially
90%
Partially
90%
Partially
80%
Partially
80%
Documentation and reporting of occupational accidents, diseases, and incidents
Partially
85%
Partially
85%
Partially
85%
Partially
70%
Partially
70%
Ensuring fair treatment, non-discrimination and equal opportunity
Partially
85%
Partially
80%
Partially
80%
Partially
70%
Partially
70%
Compliance of project’s labor policy with the national labor law
✓ ✓ ✓ ✓ ✓
No Child Labor ✓ ✓ ✓ ✓ ✓
No incident of forced labor
✓ ✓ ✓ ✓ ✓
Conduct regular third party audits during construction phase of the project to assess the contractors
✓ ✓ ✓
✓ ✓
28
Category Description of potential
impact
Measures/Indicators
Substations Name
Uttara Purbachal Aftabnagar Banani Tongi
Co
mp
lied
No
t
Co
mp
lied
Rem
ark
s
Co
mp
lied
No
t
Co
mp
lied
Rem
ark
s
Co
mp
lied
No
t
Co
mp
lied
Rem
ark
s
Co
mp
lied
No
t C
om
pli
ed
Rem
ark
s
Co
mp
lied
No
t C
om
pli
ed
Rem
ark
s
compliance levels in meeting the statutory and ADB requirements
Develop a site specific safety plan including standard operating procedures (SOPs) and work permits required to protect employees (both full-time employees and contractors) from injuries
Partially
90%
Partially
80%
Partially
80%
Partially
80%
Partially
80%
Working Condition
Provide adequate provision of drainage and access to toilets
Partially
85%
Partially
80%
Partially
80%
Partially
70%
Partially
65%
Cleanup litters and other wastes regularly
Partially
80%
Partially
80%
Partially
80%
Partially
75%
Partially
70%
Provide secure containers for disposal at designated area
Partially
80%
Partially
80%
Partially
80%
Partially
60%
Partially
50%
Properties Partially Partially Partially Partially Partially
29
Category Description of potential
impact
Measures/Indicators
Substations Name
Uttara Purbachal Aftabnagar Banani Tongi
Co
mp
lied
No
t
Co
mp
lied
Rem
ark
s
Co
mp
lied
No
t
Co
mp
lied
Rem
ark
s
Co
mp
lied
No
t
Co
mp
lied
Rem
ark
s
Co
mp
lied
No
t C
om
pli
ed
Rem
ark
s
Co
mp
lied
No
t C
om
pli
ed
Rem
ark
s
safety on site, and illuminate well if work at night
80% 80% 80% 75% 75%
Provision of PPE for workers and maintenance of work safety procedure
Partially
80%
Partially
80%
Partially
80%
Partially
75%
Partially
75%
Regular safety checks and maintenance
Partially
80%
Partially
80%
Partially
80%
Partially
70%
Partially
70%
Emergency response plan for events such as accidents, spillage of hazardous materials etc.
Partially
80%
Partially
75%
Partially
75%
Partially
70%
Partially
60%
Employment
Without the involvement of local labor, Social unrest will be held among the local people
Local Labor (technical and non-technical) should be recruited.
Partially
10%
Partially
10%
Partially
10%
Partially
15%
Partially
10%
Site Closure
Environmental and social safety can be hampered without completion of site works and
At the completion of work at a particular site, or when the construction program as a whole is
Partially
80%
Partially
80%
Partially
80%
Partially
70%
Partially
70%
30
Category Description of potential
impact
Measures/Indicators
Substations Name
Uttara Purbachal Aftabnagar Banani Tongi
Co
mp
lied
No
t
Co
mp
lied
Rem
ark
s
Co
mp
lied
No
t
Co
mp
lied
Rem
ark
s
Co
mp
lied
No
t
Co
mp
lied
Rem
ark
s
Co
mp
lied
No
t C
om
pli
ed
Rem
ark
s
Co
mp
lied
No
t C
om
pli
ed
Rem
ark
s
restoration properly
completed, the contractor will be responsible for removing all equipment and structures, cleaning up and disposing all waste materials, and rehabilitating all construction sites and work areas so that these can be returned as much as possible to their previous use.
There must be a stabilization of all project construction sites, roads, and tracks (where batters and embankment fill must be stabilized, and road drainage stabilized as well). All borrow pits and quarries are to be rehabilitated; all fuel and oil depots closed;
Partially
80%
All project constru
ction and
others activities are
almost finished
Partially
80%
All project constru
ction and
others activities are not
finished
Partially
80%
All project construction and
others activities are
not finishe
d
Partially
50%
All project construction and
others activities are
not finishe
d
Partially
60%
All project constru
ction and
others activities are not
finished
31
Category Description of potential
impact
Measures/Indicators
Substations Name
Uttara Purbachal Aftabnagar Banani Tongi
Co
mp
lied
No
t
Co
mp
lied
Rem
ark
s
Co
mp
lied
No
t
Co
mp
lied
Rem
ark
s
Co
mp
lied
No
t
Co
mp
lied
Rem
ark
s
Co
mp
lied
No
t C
om
pli
ed
Rem
ark
s
Co
mp
lied
No
t C
om
pli
ed
Rem
ark
s
any contaminated soil removed; and the areas restored. All spoil heaps must be reshaped and revegetated.
All work sites must be rehabilitated as per needs. Areas where topsoil has been removed will require a reapplication of topsoil, and revegetation as required.
Partially
80%
All project constru
ction and
others activities are
almost finished
Partially
80%
All project constru
ction and
others activities are
almost finished
Partially
80%
All project construction and
others activiti
es
Partially
50%
All project construction and
others activities are
not finishe
d
Partially
60%
All project constru
ction and
others activities are not
finished
Care must be taken to ensure that the sites are adequately restored. This will require adequate time to ensure that the sites are effectively reestablished.
Partially
85%
All project constru
ction and
others activities are
almost finished
Partially
85%
All project constru
ction and
others activities are
almost finished
Partially
85%
All project construction and
others activiti
es
Partially
60%
All project construction and
others activities are
not finishe
d
Partially
60%
All project constru
ction and
others activities are not
finished
LEGENDS:
Complied = ✓ Partially complied= ✓ Not complied= ✓
32
Appendix2: Composition of the Team
Sl.No. Name of Professional Position Assigned
1. Engr.JalalAhmed Chowdhury Environmental Expert/Transmission Line (TL)/
Power Plant Expert
2. Dr. Dilruba Ahmed Socio-economic an livelihood expert
3. Mr. Subrata Kumar Mondal Economist
4. Md. Maqb –E- Elahi Geology Specialist
5. Md. Mushfiq Ahmed Ecology Specialist
6. AnushilaMazumder Expert of Environmental Policy and Management
7. Md. Shofiqul Islam Sociologist, Socio-economic Division
8. Md. NazmulKabir Water Resource Engineer
9. Uzzal Kumar Saha Ecologist
10. Bilkish Sultana Electrical Engineer
33
Appendix 3: Participant List of Stakeholder Consultation
Sl. Name Occupation/designation Contact no.
1 Engr. Md. Rashidur Rahman Superintending Engineer and Project
Director, DESCO 01713038386
2 Engr. Md. Abdul Latif Miah Deputy Project Director (Grid), DESCO 01713443039
3 Engr. Md. Golam Faruk Sub Divisional Engr. (Grid Project), DESCO 01755637531
4 Engr. Md. Shahin Ibne Rafiq Sub Divisional Engr. (Grid Project),DESCO 01755637542
5 Engr. Md. Golam Mostofa Assistant Engr. (Grid Project), DESCO 01755637585
6 Engr. Mahadi Hasan Rana Assistant Engr. (Grid Project), DESCO 01755637602
7 Engr. Md. Mazedur Rahman Sub Assistant Engr. (Grid Project),DESCO. 01777739220
8 Md. Imrul Ansari Sub Assistant Engr. (Grid Project) 01787680515
9 Md. Atiur Rahman Sub Asst. Engr. HYOSUNG, Tongi, Gazipur 01714909429
10 Md. Atiqur Rahman Mollah Sub Manager. HYOSUNG, Dhaka 01730452981
11 Engr. BasirAhammad Site Manager, HYOSUNG, Dhaka 01777666778
12 Md. Saidul Islam Site In charge, HYOSUNG, Dhaka 01957981063
13 Abdul MatinAkondo O/C Manager, , HYOSUNG, Dhaka 01745361208
14 Syed Rafiqul Islam Site Manager, HYOSUNG, Dhaka 01715785644
15 Md. Istiak Habib Site Manager, HYOSUNG, Dhaka 01766388135
16 Md. Mostafizur Rahman Site Engr. HYOSUNG, Dhaka 01721331021
17 Md. Shahin Site Engr. HYOSUNG, Dhaka 01739514303
18 Md. Jahidur Rahman Admin, HYOSUNG, Dhaka 01723626535
19 Md. Ashraful Kabie Cite Engineer, Purbachal.HYOSUNG, Dhaka 01791261897
20 Md. Abdul Baker Hyosung, Uttata 01710054037
21 Md. Abdul Alim Safety Manager,Uttara 01990391453
22 Md. Rashid Roma Tongi Sub Station 01937236336
23 Zihad Uddin Morshed Site Manager, Uttara 01708642607
24 Md. SoukhinShaik Worker, Purbachal Site. 01768280624
25 Md. Nurul Huda Guard, Banani 01767766635
26 Farhad Hossain Worker, Purbachal Site 01980246449
27 Mst. SumiKhatun Woman Cook, Uttara 01938975007
28 Md. Moffazal Hossain Security gurd, Banani 01636717810
29 Ealius Uddin Worker, Uttatal Site. 019125875
30 Md. Solaiman Ali Worker, Uttatal Site. 01776161688
31 Mst. JahuraKhatun Woman Cook, Uttara -
32 Mst. SuchunaKhatun Woman Cook, Uttara 01709076015
33 Mst. AsmaKhatun Woman Cook, Uttara
34 Md. Rofiqul Islam Head Mistry,Purbachal 01927044121
35 Md. Moktar Hossain Worker, Aftabnagar Site. 01700632530
36 Sona Miah Worker, Aftabnagar Site. 01777111995
37 Quddus Miah Worker, Uttara Site. 01925552698
38 SreeProvus Worker, Uttara Site 01701489465
39 Rubel Worker, Aftabnagar Site 01792004265
40 Monowar Worker, Aftabnagar Site 01770869682
41 Raihan Worker, Aftabnagar Site 01708044647
42 Alamgir Worker, Aftabnagar Site
43 Abu Sayed Worker, Aftabnagar Site 01726516546
44 Shahin Worker, Aftabnagar Site 01917454232
45 Mofazzol Worker, Aftabnagar Site 01798110675
46 Al Amin Worker, Aftabnagar Site 01932804016
47 Rahen Worker, Aftabnagar Site 01740857308
34
Sl. Name Occupation/designation Contact no.
48 Moktar Worker, Aftabnagar Site 01700632530
49 Monir Worker, Aftabnagar Site
50 Sentu Worker, Aftabnagar Site 01947201516
51 Md. Mamunur Rashid Worker, Uttara Site 01726960006
52 Nasir Worker, Uttara Site 01756030053
53 Md. Imran Worker, Uttara Site 01717753053
54 Md. NurAlam Worker, Uttara Site 01785900487
55 Raihan Worker, Uttara Site 01864615504
56 Md. Mehedi Worker, Uttara Site 01782231727
57 Bablu Worker, Uttara Site 01738794506
58 Md. Nazrul Worker, Uttara Site 01733435505
59 Md. Saju Worker, Uttara Site 01863104803
60 Sujan Mia Worker, Uttara Site 01933531443
61 Md Hassan Worker, Uttara Site -
35
Appendix 4: Photographs of Project Sites
Photo: Purbachal 132/33/11 kV Sub-Station in the study area.