REMINDER Check in on the COLLABORATE mobile app 4D Scheduling: the Reality and the Hype Prepared by: Charlie Dunn 4D | Project Controls | Scheduling Duke Energy Does 4D deliver? Tales from the biggest projects on the Strip to 72 hours in a power plant outage . . . Session ID#: @charliedunn
Transcript

REMINDER

Check in on the

COLLABORATE mobile app

4D Scheduling: the Reality and the Hype

Prepared by:

Charlie Dunn

4D | Project Controls | Scheduling

Duke Energy

Does 4D deliver? Tales from the biggest projects on the Strip to 72 hours in a power plant outage . . .

Session ID#:

@charliedunn

Some Stuff about Charlie

//storyteller

//21 years Project Controls experience

//successful projects including;

Accenture, Apple, Dell,

Lockheed Martin Aerospace,

Navistar, Primavera, Tishman

and currently Duke Energy

//passionate about communication

About Communication

A Working Definition of Scheduling

the science of defining

activities and

network logic to

track progress and

predict completion

and

//the art of communicating

the schedule to stakeholders

The Challenge

We have tools for the science

but

struggle with tools for the art

So What’s the Problem?

data doesn’t drive project success

//people do

4D and the People Problem

What happens in Vegas . . .

Hype:

1. Excessive publicity and the ensuing commotion:

2. Exaggerated or extravagant claims made especially

in advertising or promotional material:

3. An advertising or promotional ploy:

4. Something deliberately misleading; a deception:

A Tale of Two Projects

Here’s to the British Invasion

a bit of Dickens

It was the best of times,

it was the worst of times,

it was the age of wisdom,

it was the age of foolishness,

it was the epoch of belief,

it was the epoch of incredulity,

it was the season of light,

it was the season of darkness,

it was the spring of hope,

it was the winter of despair . . .

It was Las Vegas, 2008

and just down the street

How to Demobilize a Crane?

The CAD Guys and Jealousy

The Other Project

4.5 weeks to 72 hours?

Huntersville, 2014

//4.5 week duration on other unit in 2012

//12 day duration planned for Spring 2013

//Could it be done in 72 hours?

//11 crews in 15 by 22 by 40 feet of space,

with equipment and scaffolding

What does the Schedule Mean?

What is a Stator?

What is a Schnabel Car?

Where is that Stator Going?

Lessons from Vegas

//Model for the problem you are trying to solve

// Schedule activity for every visible step in the model

// Goal is to increase schedule certainty and decrease risk

// Schedule design is a known workflow,

3D design or acquisition is not

// 4D provides exponential benefits

Building the 4D

//Schedule development (6 weeks)

//Point Cloud field walk down (1 hour)

//Point Cloud field scan (3 hours)

//Point Cloud modeling (2 days)

//Synchro schedule connection (1 day)

//Round trip refinements (4 days)

//Additional Model elements

//Schedule revision

//Synchro “highlights”

Challenge the Concept of a Report

//Phantom

//Ops and GOD

//Vendor SME

The Villains

Where to learn about an Outage?

//where does it look like the water is going?

//where is the water going?

//where does the water want to go?

Lesson from the River

What is an outage like?

What is an outage like?

What is an outage like?

What is an outage like?

What is an outage like?

//the Sky is Falling

//the Mechanical Team

//“We have been here before”

Day Two of The Outage

Right on Schedule

The Last Piece

Reality:

1. The quality or state of being actual or true.

2. One, such as a person, an entity, or an event, that is

actual:

3. The totality of all things possessing actuality,

existence, or essence.

4. That which exists objectively and in fact:

4D Reality

1. 4D Increases Certainty. 2. 4D Decreases Risk. 3. 4D Creates Belief.

People Drive Project Success

4D Hype:

1. 4D takes a long time. 2. 4D is expensive. 3. 4D replaces traditional scheduling.

The Strength of Leverage

Take the bull by the horns

To Turn a Beast

Please complete the session evaluation We appreciate your feedback and insight

You may complete the session evaluation either

on paper or online via the mobile app

■ Our purpose is to inform and educate our members on current and future

functionality of Oracle Primavera products, while offering a forum for peers to

share their experience and knowledge in the use of Primavera.

■ Educational opportunities across the Primavera product suite

■ Online Learning Series August 17th – September 4th

■ Call for presentation opening April 27th

■ Monthly Community Calls

■ 3rd Thursday of the month at 1:00 pm ET

■ Networking with other users within the Primavera community

■ Partnering with Oracle Primavera to meet the needs of our diverse

membership.

■ Membership is open to anyone with an interest in the Oracle Primavera products,

with no dues for membership. All members can vote on matters brought before

the OPSIG. Membership requests may be reviewed by the OPSIG board.

OPSIG is the home for

Primavera Users


Recommended