+ All Categories
Home > Documents > 5. Description of the Proposal - Transport for NSW · The Proposal involves upgrading the power...

5. Description of the Proposal - Transport for NSW · The Proposal involves upgrading the power...

Date post: 19-Jul-2019
Category:
Upload: vudang
View: 218 times
Download: 0 times
Share this document with a friend
17
Strathfield to Hornsby Power Supply Upgrade Review of Environmental Factors EN04405_S2H signal power supply upgrade REF_final © TfNSW 2013 Page 33 of 141 5. Description of the Proposal Chapter 5 describes the Proposal and summarises key design parameters, construction method, and associated infrastructure and activities. The description of the Proposal is based on the AECOM Devlins Creek to Hornsby HV Aerial Lines and Cables Design Plans and GHD Signals Power Supply Upgrade LV Location and Site Layout Design Plans. 5.1. The Proposal As described in Section 1.1 of this REF, the Proposal involves upgrading of the existing 2kV signal power supply from Strathfield to Hornsby with a new 11kV signal power supply as part of the PSU Program. 5.1.1. Design features The Proposal involves upgrading the power supply within the rail corridor between Strathfield Substation and Hornsby Substation and includes the following (see Figure 5-1, Figure 5-2 and Figure 5-3): Upgrade of the existing 2 kV overhead aerial line to an 11kV aerial line from Pole 15, approximately 500 metres north of the Devlins Creek Sectioning Hut at Epping, to Pole 127, approximately 300 metres south of Hornsby Station Refurbishment of the 33kV transmission line poles and accessories along with the 2kV to 11kV line conversion on all common or sharing poles (approximately 115 in total) between Devlins Creek Sectioning Hut and Hornsby Substation Replacement and upgrade of approximately 90 power poles between Devlins Creek and Hornsby Installation of a combination of buried 33kV and 11kV cabling and galvanised steel trough (GST) for approximately 500 metres north and south of Pennant Hills Station Trenching at Normanhurst from the power room, north within the rail corridor, passing underneath Buckingham Avenue bridge to an existing section hut Construction and commissioning of power rooms (see example power room in Plate 5) at Concord West, Rhodes, West Ryde, Eastwood, Beecroft, Pennant Hills and Normanhurst Construction and commissioning of 11kV/415V padmount substations (see example padmount substation in Plate 6) in the vicinity of the proposed power rooms at Rhodes, West Ryde, Eastwood, Beecroft, Pennant Hills and Normanhurst Installation of underline track crossings (ULX) at Normanhurst and Concord West to connect the proposed power room and padmount substation Supply (415V/120V) four to five signal locations from each power room. The distance between power rooms and signal locations vary between approximately 30 metres and 1500 metres Installation of two underground/overhead (UGOH) poles (see example UGOH pole in Plate 7) at each proposed power room to connect cables from the padmount substations to the existing aerial lines. The poles would be a maximum of 70 metres apart
Transcript
Page 1: 5. Description of the Proposal - Transport for NSW · The Proposal involves upgrading the power supply within the rail corridor between Strathfield Substation and Hornsby Substation

Strathfield to Hornsby Power Supply Upgrade Review of Environmental Factors

EN04405_S2H signal power supply upgrade REF_final

© TfNSW 2013 Page 33 of 141

5. Description of the Proposal

Chapter 5 describes the Proposal and summarises key design parameters, construction method, and associated infrastructure and activities. The description of the Proposal is based on the AECOM Devlins Creek to Hornsby HV Aerial Lines and Cables Design Plans and GHD Signals Power Supply Upgrade LV Location and Site Layout Design Plans.

5.1. The Proposal

As described in Section 1.1 of this REF, the Proposal involves upgrading of the existing 2kV

signal power supply from Strathfield to Hornsby with a new 11kV signal power supply as part of the PSU Program.

5.1.1. Design features

The Proposal involves upgrading the power supply within the rail corridor between Strathfield Substation and Hornsby Substation and includes the following (see Figure 5-1, Figure 5-2and Figure 5-3):

Upgrade of the existing 2 kV overhead aerial line to an 11kV aerial line from Pole 15, approximately 500 metres north of the Devlins Creek Sectioning Hut at Epping, to Pole 127, approximately 300 metres south of Hornsby Station

Refurbishment of the 33kV transmission line poles and accessories along with the 2kV to 11kV line conversion on all common or sharing poles (approximately 115 in total) between Devlins Creek Sectioning Hut and Hornsby Substation

Replacement and upgrade of approximately 90 power poles between Devlins Creek and Hornsby

Installation of a combination of buried 33kV and 11kV cabling and galvanised steel trough (GST) for approximately 500 metres north and south of Pennant Hills Station

Trenching at Normanhurst from the power room, north within the rail corridor, passing underneath Buckingham Avenue bridge to an existing section hut

Construction and commissioning of power rooms (see example power room in Plate 5) at Concord West, Rhodes, West Ryde, Eastwood, Beecroft, Pennant Hills and Normanhurst

Construction and commissioning of 11kV/415V padmount substations (see example padmount substation in Plate 6) in the vicinity of the proposed power rooms at Rhodes, West Ryde, Eastwood, Beecroft, Pennant Hills and Normanhurst

Installation of underline track crossings (ULX) at Normanhurst and Concord West to connect the proposed power room and padmount substation

Supply (415V/120V) four to five signal locations from each power room. The distance between power rooms and signal locations vary between approximately 30 metres and 1500 metres

Installation of two underground/overhead (UGOH) poles (see example UGOH pole in Plate 7) at each proposed power room to connect cables from the padmount substations to the existing aerial lines. The poles would be a maximum of 70 metres apart

Page 2: 5. Description of the Proposal - Transport for NSW · The Proposal involves upgrading the power supply within the rail corridor between Strathfield Substation and Hornsby Substation

Strathfield to Hornsby Power Supply Upgrade Review of Environmental Factors

EN04405_S2H signal power supply upgrade REF_final

© TfNSW 2013 Page 34 of 141

Internal renovation to the existing Hornsby and Strathfield signal rooms including the removal of redundant 2kV equipment (i.e. 11kV/2kV transformers, 2kV boards, 2 kV cable etc.)

Decommissioning of approximately 25 kilometres of the 2kV network including existing cables, transformers, regulators, and switchboards at Strathfield Substation, Epping Substation, Hornsby Substation; and reticulated 2kV switchboards at various signal locations.

Construction work is estimated to commence in late 2014 and take about 24 months to complete.

5.1.2. Power rooms

The power rooms would be approximately 5 to 7 metres long, 3.5 metres wide and 3 metres high (see Plate 5 for an example power room). The buildings are of modular design i.e. pre-

cast concrete mono-form. They are manufactured and fitted out off site, then transported to the required locations and placed on a 300 millimetre deep pre-prepared compacted base. Each power room would supply enough power to support 4 to 5 signals located within the surrounding area. The power rooms are all located within the rail corridor. Their internal equipment includes but is not limited to a combination the following items:

415/120V distribution transformers

415V/415V isolation transformer

Electrical switchboards

Uninterruptible Power Supply (UPS) backup supplies

Signalling alarm monitoring systems.

A natural convectional ventilation system would be installed to avoid the need for mechanical ventilation.

Page 3: 5. Description of the Proposal - Transport for NSW · The Proposal involves upgrading the power supply within the rail corridor between Strathfield Substation and Hornsby Substation

Strathfield to Hornsby Power Supply Upgrade Review of Environmental Factors

EN04405_S2H signal power supply upgrade REF_final

© TfNSW 2013 Page 35 of 141

Plate 5: Example size of a power room

Page 4: 5. Description of the Proposal - Transport for NSW · The Proposal involves upgrading the power supply within the rail corridor between Strathfield Substation and Hornsby Substation

Decommissioning Works

Decommissioning Works

Beecroft PowerRoom and Padmount

Normanhurst Power Roomand Padmount Under Level

Crossing Drilling Works

(ULX)

Pennant Hills PowerRoom and Padmount

500 m of Underground

Trenching

CASTLEH

ILL

RO

AD

BEECROFTROAD

BOUNDARY

RO

AD

GE

OR

GE

ST

RE

ET

EDGEWORTH DAVID AVENUE

PACIFICHIGHW

AY

PA

CIF

ICH

IGH

WA

Y

EPPING ROAD EPPING ROA

D

PE

NN

AN

TH

ILL

SR

OA

D

PACIFIC HIGHWAY

PA

CIF

ICM

OT

OR

WA

Y

PEN

NA

NT

HIL

LSROAD

M2 MOTORWAY

M2 MOTORWAY

PA

CIF

I CM

OT

OR

WA

Y

LANECOVE NP

BEECROFT

EPPING

CHELTENHAM

HORNSBY

NORMANHURST

THORNLEIGH

PENNANT HILLS

DEVLINS CREEK LANE COVE RIVER

Figure 5-1 | Location of Aerial and Underground Works

SYDNEY

MASCOT

WOY WOY

WINDSOR

HORNSBY

BLACKTOWN

PARRAMATTA

HURSTVILLE

PALM

BEACH

INGLEBURN

STRATHFIELD

REVIEW OF ENVIRONMENTAL FACTORSStrathfield to Hornsby Signal Power Supply Upgrade

0 1

Kilometres

LEGEND

Power Room andPadmount

Station

Railway

Primary Road

Waterway

National Park

Galvanised steeltrough (GST)

Upgrade of existing2kV overhead line to11kV aerial line

Underground cableinto existing conduit

DATA SOURCESImagery: AUSIMAGE 2011Contextual information: LPMA 2014,Streetworks 2001

16/05/2014 | I:\ENVR\Projects\EN04405\Technical\Spatial\ArcMap\EN04405_REF_F010_CableWorks_r2v1.mxd

Newcastle Spatial Team - Prepared by : ALChecked by : AW

Sinclair Knight Merz does not warrant that this

document is definitive nor free of error and does

not accept liability for any loss caused or arising

from reliance upon information provided herein.

PA

CIF

ICH

IGH

WA

Y

HORNSBY

HORNSBYSUBSTATION

HORNSBYSTATION S.S.

POLE 126

PENNANT HILLS

Page 5: 5. Description of the Proposal - Transport for NSW · The Proposal involves upgrading the power supply within the rail corridor between Strathfield Substation and Hornsby Substation

JER SEY STREET

ST ATI ON STREETJERSEY LANE BEATTIE LANE GE OR GE STREET

HORNSBY

Fig ure 5*2 | Pro posa l Desc ript io n

SYDNEYMASCOTWOY WOYWINDSOR HORNSBYBLACKTOWNPARRAMATTAHURSTVILLE PALMBEACH

INGLEBURN STRATHFIELDREV IEW OF ENV IRONMENTA L FA CTORSStrathfield to Hornsby Signal Power Supply Upgrade0 100MetresLEGENDStationRail Track CentrelineGalvanised steel trough(GST)Upgrade of existing 2kVoverhead line to 11kVaerial lineUnderground cable Power Room (IndicativeLocation)Padmount (IndicativeLocation)Decommissioning Works DATA SOURCESSydney Trains 2014, LPMA 2014,Streetworks 2001

16/05/2014 | I:\ENVR\Projects\EN04405\Technical\Spatial\ArcMap\EN04405_REF_F002_ProjectDescription_part1_r2v2.mxdNewcastle Spatial Team È Prepared by : KMChecked by : AWSinclair Knight Merz does not warrant that thisdocument is definitive nor free of error and doesnot accept liability for any loss caused or arisingfrom reliance upon information provided herein.

MIL SON P AR ADEBUCKINGHAMAVENU E

M AL SBURY R OADEATONAVENUEDENM AN P AR ADE

DENMAN PAR ADEHAMMOND AVENUE

NORMANHURST

PENNANT HILL SROADY ARR AR ARO AD BEE CR OF TROAD COPELAND ROADWONGAL ACRESCENT SUTHERLAND ROADBEECROFT

Ho rns by Decommiss io ning Wo rks No rma nhurst Powe r Room

Pe nna nt Hills Powe r Room Beec roft Powe r Room

Page 6: 5. Description of the Proposal - Transport for NSW · The Proposal involves upgrading the power supply within the rail corridor between Strathfield Substation and Hornsby Substation

MAY STREETETHEL STREETETHEL LANERAILWAY P ARADE

BALL AVENUEMAY LANEHILL VIE WR OAD

RAILWAY AVENUE BALL AVENUE

WE ST P AR ADE

EA STWOOD AVEN UEWINGATEAVENUE DOOMBEN AVENUEEASTWOOD

Figure 5Ø3 | Proposal Description

SYDNEYMASCOTWOY WOYWINDSOR HORNSBYBLACKTOWNPARRAMATTAHURSTVILLE PALMBEACHINGLEBURN STRATHFIELDREVIEW OF ENVIRONMENTAL FACTORSStrathfield to Hornsby Signal Power Supply Upgrade

0 100MetresLEGENDStationRail Track CentrelineGalvanised steel trough(GST)Upgrade of existing 2kVoverhead line to 11kVaerial lineUnderground cable intoexisting conduitPower Room (IndicativeLocation)Padmount (IndicativeLocation) DATA SOURCESSydney Trains 2014, LPMA 2014,Streetworks 2001

16/05/2014 | I:\ENVR\Projects\EN04405\Technical\Spatial\ArcMap\EN04405_REF_F003_ProjectDescription_part2_r2v2.mxdNewcastle Spatial Team v Prepared by : KMChecked by : AWSinclair Knight Merz does not warrant that thisdocument is definitive nor free of error and doesnot accept liability for any loss caused or arisingfrom reliance upon information provided herein.

RYEDALE ROADWEST PAR ADEVICTORIA ROAD

WEST RYDE

MARYSTREETWALKER STREET

MARYSTREETRIDER BOULEVARDBLAXLANDROAD

RHODES KINGSTREETSTU ART STREETQUEEN STREET

VICTORIA AVENUECONCORD WEST

Eastwood Power Room West Ryde Power Room

Rhodes Power Room Concord West Power Room

Page 7: 5. Description of the Proposal - Transport for NSW · The Proposal involves upgrading the power supply within the rail corridor between Strathfield Substation and Hornsby Substation

Strathfield to Hornsby Power Supply Upgrade Review of Environmental Factors

EN04405_S2H signal power supply upgrade REF_final

© TfNSW 2013 Page 39 of 141

5.1.3. Padmount substations

The padmount substations would be approximately 1.2 metres tall and 1 metre wide (see Plate 6). Each padmount would consist of the following equipment:

11kV Ring Main Unit (RMU)

11kV/415V transformer

LV (415V) connection board.

Plate 6: Example Padmount Substation

A padmount substation at Concord West would be installed as part of the North Strathfield Rail Underpass (NSRU) Project. The padmount at this location has not been assessed as part of this REF.

5.1.4. Poles and overhead wiring

Generally, the existing 2kV and 33kV aerial lines share a common pole. However, in some instances (i.e where UGOH poles or lines transitioning between substations), separate poles are used. The Proposal involves the installation of an 11kV aerial line and removal of the

Page 8: 5. Description of the Proposal - Transport for NSW · The Proposal involves upgrading the power supply within the rail corridor between Strathfield Substation and Hornsby Substation

Strathfield to Hornsby Power Supply Upgrade Review of Environmental Factors

EN04405_S2H signal power supply upgrade REF_final

© TfNSW 2013 Page 40 of 141

existing 2kV aerial lines. After construction there would generally be three aerial cables between poles, increasing from two aerial cables provided by the 2kV power supply.

Generally, the poles between Pole 15 (near Devlins Creek Section Hut at Epping) and Pole 127 (approximately 300 metres south of Hornsby Station) would remain in their current locations. Approximately 90 poles would be removed/replaced where required due to ageing, changes in line profiles, pole strength etc. Poles would be removed where the existing poles are not suitable for re-use.

Plate 7 Example Underground Overhead (UGOH) Pole

5.1.5. Signal cables

The installation of 415V cables from each of the power rooms would be undertaken to power the nearby signals. The cables would extend for between approximately 30 and 1600 metres (this would vary for each location) before being connected to the signal power supply.

5.1.6. Sustainability in design

The design of the Proposal has been undertaken in accordance with the project targets identified in TfNSW’s Environmental Management System (EMS) and the Sustainable Design Guidelines (Version 3.0) which groups sustainability into seven themes:

Page 9: 5. Description of the Proposal - Transport for NSW · The Proposal involves upgrading the power supply within the rail corridor between Strathfield Substation and Hornsby Substation

Strathfield to Hornsby Power Supply Upgrade Review of Environmental Factors

EN04405_S2H signal power supply upgrade REF_final

© TfNSW 2013 Page 41 of 141

Energy and greenhouse gases

Climate resilience

Materials and waste

Biodiversity and heritage

Water

Pollution control

Community benefit.

Within each theme, potential initiatives are prioritised into two categories of requirements:

Compulsory – the initiative is required to be implemented when applicable to the

Proposal as they refer to a corporate target, or are fundamental to the delivery of sustainable assets)

Discretionary – the initiative has benefits to be implemented, however may not be

the most appropriate.

The Guidelines also specify a minimum level of compliance within each category: 100 percent of applicable Compulsory initiatives and 50 percent of the applicable Discretionary points are to be adopted on the Proposal.

Further information on the sustainability design initiatives for the Proposal can be found in Section 7.12.

5.2. Construction activities

5.2.1. Construction methodology

Construction works would involve the following:

Site establishment:

Services relocation or protection work for services located on or near the site

Establishment of the construction compounds

Installation of safety fencing around the Proposal where required.

Tree trimming from within the rail corridor where required

Trenching and conduit laying works and galvanised steel trough installation 500 metres north and south of Pennant Hills Station

Directional drilling works for installing an under line crossing adjacent to the rail corridor at Normanhurst and Concord West

Replacement and upgrade of the existing high voltage aerial poles and aerial cables

High voltage (HV) aerial pole and aerial cable installation, including cable jointing

Electrical work and fit out including connection the electrical network

Site clean up.

Page 10: 5. Description of the Proposal - Transport for NSW · The Proposal involves upgrading the power supply within the rail corridor between Strathfield Substation and Hornsby Substation

Strathfield to Hornsby Power Supply Upgrade Review of Environmental Factors

EN04405_S2H signal power supply upgrade REF_final

© TfNSW 2013 Page 42 of 141

5.2.2. Construction workforce

Construction of the Proposal would involve a maximum workforce of approximately 30 people. The Proposal would not be staged but rather when access is permitted into the rail corridor, planned activities would be undertaken to maintain progress.

To complete the padmount substations and power rooms, access to the rail corridor can be granted any time.

It is anticipated that workers would work across the whole Proposal area at any one time rather than starting at one section and moving on.

The work would commence in late 2014 and take about 24 months to complete.

5.2.3. Plant and equipment

Plant and equipment used to construct the Proposal may include, but not be limited to:

Water truck

2-4 hi-rail trucks

Mini excavators

Mini dump trucks

2 concrete booms and 2 concrete trucks

3x16 tonne excavators with augers and a rock breaker

Backhoes

Hand tools

Light commercial and passenger vehicles

2x25 tonne cranes

4 high rail telehandlers

Small site shed

Portaloo

Supersuckers/vacuum trucks

2-6 hi rail elevated work platforms.

5.2.4. Working hours

Construction would generally occur during the standard hours set out in the Interim Construction Noise Guideline (DECC, 2009):

Mondays to Fridays between 7 am and 6 pm

Saturdays between 8 am and 1 pm

No work would occur on Sundays or public holidays.

Some of the proposed works would be carried out during scheduled track possession periods (including work on Sundays). The majority of the overhead cabling would be undertaken outside of possessions and power rooms and padmounts would be installed during daytime hours. Some work would be required during possessions and isolations including signal supply changeovers, commissioning, and cable connections to padmount substations and power rooms where required to maintain network connections and for safety reasons.

For out of hours works, the contractor would obtain permission from TfNSW. All out of hours work would be undertaken in accordance with the Construction Noise Strategy (Transport for

NSW, 2012).

Page 11: 5. Description of the Proposal - Transport for NSW · The Proposal involves upgrading the power supply within the rail corridor between Strathfield Substation and Hornsby Substation

Strathfield to Hornsby Power Supply Upgrade Review of Environmental Factors

EN04405_S2H signal power supply upgrade REF_final

© TfNSW 2013 Page 43 of 141

5.2.5. Earthworks

Seven sites within the rail corridor require excavation as part of the Proposal. The seven sites include the excavation of three trenches (varying from approximately 30 to 500 metres in length, to a depth of between 1 and 1.5 metres below ground level),the construction of seven power rooms, six padmount substations (maximum excavation depth of 1.5 metres below ground level) and associated connections.

The volume of material expected to be removed during trenching works at Pennant Hills would be approximately 750m3. The volume of material for the padmount substation and power room installation is expected to be minimal.

Excavated material would be used to backfill where possible across the Proposal. Excess spoil would be disposed of at an appropriately licensed facility.

5.2.6. Source and quantity of materials

Materials for the Proposal would be sourced from local suppliers where practicable and recycled materials would be used where possible. The power rooms would be constructed in Wollongong and transported to the site via road for installation in the rail corridor.

The source and quantity of materials required for construction would be confirmed during the detailed design of the Proposal.

5.2.7. Vehicle movements

Construction would generate the need for heavy vehicle movements associated with the transportation of construction machinery, equipment and materials to the site. Light vehicle movements would be associated with employees and smaller deliveries.

It is estimated that construction vehicle movements would involve a daily maximum of approximately 15 vehicles per day. This would consist of five light vehicles and 10 construction vehicles across the whole site.

The delivery of some equipment, such as the padmount substations and power rooms, may be considered oversized deliveries. These deliveries would be undertaken in accordance with the requirements of the relevant authorities.

5.2.8. Site access and car parking

Site access would be via existing rail corridor gates and access tracks. To achieve the project objectives. Access to the rail corridor would also be required at:

Pennant Hills adjacent to a car yard

Through the commuter car park at the West Ryde site

Derby Street (public and restricted area access) for the upgrading of the 2kV line to the 11kV line across the M2 Motorway between Beecroft and Eastwood.

Parking of construction and staff vehicles would be on the local road network or within the construction compound area where possible.

It is estimated that 15 vehicles per day transporting employees would be travelling to and from site during construction. These vehicles would have minimal impact to the road network and overall traffic on the surrounding road network.

Page 12: 5. Description of the Proposal - Transport for NSW · The Proposal involves upgrading the power supply within the rail corridor between Strathfield Substation and Hornsby Substation

Strathfield to Hornsby Power Supply Upgrade Review of Environmental Factors

EN04405_S2H signal power supply upgrade REF_final

© TfNSW 2013 Page 44 of 141

Traffic and transport impacts associated with the Proposal are assessed in detail in Section 7.3 of this REF.

5.2.9. Ancillary facilities

Ancillary facilities that include a construction compound area would be located at a central location within the Proposal area as the work moves. This compound location would be located on largely cleared and vacant land where possible and it would not be located within 40 metres of a waterway or within 100 metres of a sensitive receiver where possible. The location and activities proposed for the construction compound are yet to be confirmed.

Potential locations for the construction compound include:

Within the rail corridor at Normanhurst on the same side of the track as the power room

Adjacent to Sutherland Road inside the rail corridor at Beecroft.

Where possible the site shed and ablutions building used by site staff would be moved along the Proposal area. The final location of ancillary facilities would be confirmed during detailed design. In the event that ancillary facilities are required outside of this footprint, further assessment would be undertaken of that specific location.

5.2.10. Public utility adjustments

During the subsequent phases of design, a utility investigation including a Dial Before You Dig (DBYD) enquiry, would be undertaken to identify utilities with the potential to occur within the Proposal area. The following utilities could potentially occur within the Proposal area.

Electricity

Telecommunications

Water and sewerage

Stormwater

Closed circuit TV

Rail signalling.

It is likely some services may require relocation. Such relocation is unlikely to occur outside of the Proposal area footprint assessed in this REF. In the event that construction related works would be required outside of this footprint, further assessment would be undertaken of that specific location.

The appropriate utility providers would be consulted during the detailed design phase.

5.3. Operational management and maintenance

The main function of the Strathfield to Hornsby Power Supply Upgrade would be to convert the existing 2kV signal power supply to an 11kV signal power supply. The 11kV network would operate 24 hours a day to ensure that power supply is provided to the network at all times.

No permanent staff members would be located on site.

Page 13: 5. Description of the Proposal - Transport for NSW · The Proposal involves upgrading the power supply within the rail corridor between Strathfield Substation and Hornsby Substation

Strathfield to Hornsby Power Supply Upgrade Review of Environmental Factors

EN04405_S2H signal power supply upgrade REF_final

© TfNSW 2013 Page 45 of 141

Maintenance activities would be the responsibility of Sydney Trains and would involve approximately one visit each month. These visits would generally consist of one utility vehicle accessing the site. In emergency situations additional vehicles may need to access the site.

The potential impacts of operation are considered in Section 7.

Page 14: 5. Description of the Proposal - Transport for NSW · The Proposal involves upgrading the power supply within the rail corridor between Strathfield Substation and Hornsby Substation

Strathfield to Hornsby Power Supply Upgrade Review of Environmental Factors

EN04405_S2H signal power supply upgrade REF_final

© TfNSW 2013 Page 46 of 141

6. Community and stakeholder consultation

This section summarises the community and stakeholder consultation undertaken as an input to development of the Proposal and the REF.

6.1. Introduction

This chapter summarises TfNSW’s approach to community and stakeholder engagement for the planning approval phase of the Proposal, including the REF public display.

Formal statutory consultation under the Infrastructure SEPP is not required as the Proposal is not likely to have an impact to local heritage that is not minor or inconsequential as per clause 13 of the ISEPP. Also, the Proposal would not have an impact on council-related infrastructure or services as per clause 13(e) and (f). Nevertheless, consultation with Hornsby Shire Council, City of Canada Bay Council, Parramatta City Council and City of Ryde Council has been undertaken to inform them of the Proposal.

6.2. Engagement objectives

Ensuring the community and key stakeholders are fully informed and given the opportunity to provide feedback during the planning process is fundamental to the development of the Proposal.

The objectives of community and stakeholder engagement activities are to:

Provide accurate, accessible and timely information about the Proposal and REF process to relevant stakeholders

Raise awareness of the REF and the opportunity for feedback, particularly residents, businesses and other stakeholders adjoining the rail corridor

Foster a positive two-way dialogue with the community and key stakeholders

Provide opportunities for stakeholders and the community to express their view about the Proposal

Identify, understand and incorporate stakeholder and community views into the planning approval phase of the Proposal.

Page 15: 5. Description of the Proposal - Transport for NSW · The Proposal involves upgrading the power supply within the rail corridor between Strathfield Substation and Hornsby Substation

Strathfield to Hornsby Power Supply Upgrade Review of Environmental Factors

EN04405_S2H signal power supply upgrade REF_final

© TfNSW 2013 Page 47 of 141

6.3. Engagement during REF preparation

Table 6-1 lists the key engagement tools and activities employed during the preparation of

the REF and describes how each tool has been used to engage with the community and stakeholders.

Table 6-1: Engagement activities and tools

Engagement tool Purpose and activity to date

Contact mechanisms A Project Infoline (1800 684 490) and email address ([email protected]) was established to allow all stakeholders to seek information about the Proposal.

A database was also established to manage contacts and record issues and actions.

Project website Information about the Strathfield to Hornsby Signal Power Supply Upgrade was made available on the TfNSW website (www.transport.nsw.gov.au/projects).

Council briefings City of Canada Bay, City of Ryde, Parramatta City and Hornsby Shire Councils were invited to a briefing prior to the public display so TfNSW could provide an overview of the Proposal. City of Canada Bay Council, Hornsby Shire Council and City of Ryde Council were briefed by TfNSW on the Proposal on 14 May, 15 May and16 May 2014 respectively. No issues or concerns were raised by Councils during consultation. Parramatta City Council declined a briefing for the Proposal and would comment during the public display period.

6.4. Engagement during REF public display

This REF would be placed on public display for a period of two weeks from the 13 June to

27 June 2014 during which time written submissions would be accepted.

Table 6-2 lists the key engagement tools and activities that would be employed during the

REF public display and describes how each tool has and would be used to engage with the community and stakeholders.

Page 16: 5. Description of the Proposal - Transport for NSW · The Proposal involves upgrading the power supply within the rail corridor between Strathfield Substation and Hornsby Substation

Strathfield to Hornsby Power Supply Upgrade Review of Environmental Factors

EN04405_S2H signal power supply upgrade REF_final

© TfNSW 2013 Page 48 of 141

Table 6-2: Engagement activities and tools

Engagement tool Purpose and activity to date

Community Update brochure

A Community Update brochure would be distributed to nearby properties and stakeholders to inform of the Proposal, the REF public display, details of public display locations and invite written submissions.

Public display locations The REF would be available for viewing at the following locations:

Transport for NSW Community Information Centre, Ground Floor, 388 George Street, Sydney, Monday to Friday, 9am to 5pm

Hornsby Shire Council Chambers, 296 Pacific Highway, Hornsby, Monday to Friday, 8.30am to 5pm

City of Canada Bay Council Chambers, 1A Marlborough Street, Drummoyne, Monday to Friday, 8.30am to 4pm

City of Ryde Council Chambers, 1 Devlin Street, Ryde, Monday to Friday, 8.30am - 4.30pm (note: second Thursday of each month hours are 10am to 4.30pm)

Parramatta City Council Chambers, 30 Darcy Street, Parramatta, Monday to Friday, 8.30am - 4.30pm

Hornsby Central Library, 28-44 George Street, Hornsby, Monday to Friday, 10am to 9pm, Saturday, 9.30am to 5pm, Sunday 2pm to 5pm

West Ryde Library, 2 Graf Avenue, West Ryde, Monday to Wednesday, 10am to 5pm, Tuesday and Thursday, 10am to 8pm, Saturday, 9.30am to 5pm, Sunday, 12pm to 4pm

Concord Library, Wellbank Street, Concord, Monday to Thursday, 9.30am to 7.30pm, Friday, 9.30am to 5pm, Saturday, 9.30am to 4pm, Sunday 1pm to 5pm

Eastwood Library, Corner Hillview Road and West Parade, Eastwood, Monday to Tuesday, 10am to 5pm, Wednesday to Friday, 10am to 8pm, Saturday, 9.30am to 12pm

Ryde Library, 1 Pope Street, Ryde, Monday to Friday, 10am to 9pm, Saturday 9.30am to 5pm, Sunday 2pm to 5pm

Epping Branch Library, Chambers Court, Epping, Monday to Friday, 10am to 9pm, Saturday, 9.30am to 12pm, Sunday 2pm to 5pm

Pennant Hills Branch Library, Corner Ramsay and Yarrara Roads, Pennant Hills, Monday to Friday, 10am to 9pm, Saturday 10am to 4pm, Sunday 2pm to 5pm.

It would also be available on the project website for the duration of the public display.

Contact mechanisms All communication materials would encourage stakeholders to seek information about the Proposal via the Project Infoline (1800 684 490) and email address ([email protected]).

Project website Updated information about the Strathfield to Hornsby Signal Power Supply Upgrade would be made available on the TfNSW website (www.transport.nsw.gov.au/projects), including the REF and Community

Page 17: 5. Description of the Proposal - Transport for NSW · The Proposal involves upgrading the power supply within the rail corridor between Strathfield Substation and Hornsby Substation

Strathfield to Hornsby Power Supply Upgrade Review of Environmental Factors

EN04405_S2H signal power supply upgrade REF_final

© TfNSW 2013 Page 49 of 141

Engagement tool Purpose and activity to date

Update brochure, public display locations and how to make a submission on

the REF.

Written submissions Written submissions on the REF are encouraged throughout the public display period. Submissions can be emailed to [email protected] or posted to:

PSU Community Relations, Locked Bag 6501, St Leonards, NSW, 2065

Submissions would be accepted no later than 5 pm Friday 27 June 2014. All submissions received during the public display period (13 June to 27 June)would be considered as formal submissions and would be acknowledged by return letter or email (depending on what contact information is provided).

All information in submissions may be published in subsequent assessment documents. If the stakeholder indicates at the time of supply of information that it should be kept confidential, TfNSW would attempt to keep it confidential however there may be legislative or legal justification for release of the information, for example under the Government Information (Public Access) Act 2009 or under subpoena or statutory instrument.

6.5. Post-display engagement activities

TfNSW would accept and acknowledge written submissions throughout the REF public display period.

Following the REF display, TfNSW would prepare a report to summarise issues raised, provide responses to the issues raised, and identify any changes to the Proposal and the potential impacts of those changes.

TfNSW would consider issues raised in submissions prior to determining whether to proceed with the Proposal.

Anyone who makes a submission (and provides their contact details) would be notified when the Proposal's determination report is available for viewing on the TfNSW website.

Should TfNSW proceed with the Proposal, communication and consultation activities would continue, including updates and notifications to residents, businesses and other community members in the lead up to and during construction.

The TfNSW Infoline and email address would continue to be available during the construction phase as would a dedicated 24-hour Construction Information line.


Recommended