Date post: | 06-Apr-2018 |
Category: |
Documents |
Upload: | monik-maru-fakra-he |
View: | 241 times |
Download: | 0 times |
of 25
8/3/2019 5. Facility Layout
1/25
Prof. s. Ganguly
8/3/2019 5. Facility Layout
2/25
2
Facility Layout and Basic Formats
Process Layout
Layout Planning
Assembly Line balancing
Service Layout
OBJECTIVES
2
Prof.S.Ganguly
8/3/2019 5. Facility Layout
3/25
3
FACILITYLAYOUT
Facility layout can be defined as configuration of departments, workcenters and equipment, machinery with focus on flow of materials orwork through production systems.
Factors considered in Plan Layout
Machines.
Equipments.
Work-stations.
Customer service areas.
Tooling.
Rest rooms.
Lunch rooms.
Coffee/tea base.
Toll cribs, ailes. 3
Prof.S.Ganguly
8/3/2019 5. Facility Layout
4/25
4
LAYOUTPLANNING
Involves decisions about physical arrangement ofeconomic activity centers within a facility..
Important things to be taken care are:
Type of Centers.
Space and capacity for each center.
Configuration of each centers space.
Location of each center in terms of Relative andAbsolute location.
4
Prof.S.Ganguly
8/3/2019 5. Facility Layout
5/25
5
NEEDFORLAYOUTDECISIONS.
Layout decisions Need:
To determine long run efficiency in operations.
It establishes organizations competitive priorities in
regards to capacity, flexibility, cost, processes,quality of work life, customer contact and image (incase of service organizations).
To achieve strategic advantage that supports
differentiation, low cost, fast response or flexibility.
5
Prof.S.Ganguly
8/3/2019 5. Facility Layout
6/25
6
OBJECTIVES: GOODPLANTLAYOUT
Higher utilization of space,equipment,flexibility andpeople.
Improved flow of materials, productioncapacity,information,people.
Employee morale and safe working conditions.
Reduced material handling, bottleneck center,health hazards and accidents.
To provide product, volume flexibility, ease ofsupervision, allow ease of maintenance.
To facilitate effective co ordination and face to facecommunication.
6
Prof.S.Ganguly
8/3/2019 5. Facility Layout
7/25
7
FACTORSINFLUENCINGLAYOUTCHOICES
Materials. (Cranes, trolleys, conveyors, pipelines)
Product. (Nature and type)
Workers. (Gender, Position, Facilities)
Machinery and equipments. Type of industry.
Location.
Managerial policies.
7
Prof.S.Ganguly
8/3/2019 5. Facility Layout
8/25
8
PRINCIPLESOFPLANTLAYOUT
1. Principle of minimum travel.
2. Principle of sequence.
3. Principle of Usage.
4. Principle of compactness.5. Principle of safety and satisfaction.
6. Principle of flexibility.
7. Principle of Minimum investment.
8
Prof.S.Gan
guly
8/3/2019 5. Facility Layout
9/25
9
BASIC PRODUCTION LAYOUT FORMATS
Process Layout (also calledjob-shoporfunctional layout)
Product Layout (also called flow-shop layout)
Group Technology (Cellular) Layout
Fixed-Position Layout
Combination or Hybrid Layout9
Prof.S.Gan
guly
8/3/2019 5. Facility Layout
10/25
10
SPECIFICATIONSOFPROCESSLAYOUT.
The raw material flows through differentdepartments wherein the equipments andmachineries are already fixed.
Its also known as functional or batch production
layout.
Distance needs to be short.
Departments should be located in accordance withthe principle sequence of operations.
Convenience for inspection and supervision.
10
Prof.S.Gan
guly
8/3/2019 5. Facility Layout
11/25
11
ADVANTAGESANDDISADVANTAGESPROCESSLAYOUT.
Advantages. Reduced investment on machinery.
Greater flexibility in production.
Greater scope for expansion.
Better utilization of man and machines. Easier to handle breakdown by transferring work to
another department.
Greater incentive to specialized worker to increase hisproductivity
Disadvantages. Difficulty in movement of materials.
Requires More floor space.
Production time increases due to more travelling andaccumulation of work-in-progress.
11
Prof.S.Gan
guly
12
8/3/2019 5. Facility Layout
12/25
12
PRODUCTLAYOUT/STRAIGHTLINELAYOUT
Product moves through a series of special purposemachinery.
Raw Materials fed into the first machine andfinished product comes out of the last.
characteristics:-
Machines and equipments should be placed at the pointdemanded by the sequence.
No line crossing.
All operations included in the line.Materials may be fed where they are required, but notnecessarily all at one point.
12
Prof.S.Gan
guly
13
8/3/2019 5. Facility Layout
13/25
13
ADVANTAGESANDDISADVANTAGES.
Advantages
Reduction in material handling.
Avoids production bottlenecks.
Saves manufacturing time.
Facilitates better production control. Requires less floor area.
Reduced WIP, minimized investment.
Early detection of mistakes is possible.
Greater incentives to a group of workers. Disadvantages.
Inflexible and expensive.
Difficulty in supervision and expansion.
Any Breakdown disrupts the whole system.13
Prof.S.Gan
guly
14
8/3/2019 5. Facility Layout
14/25
14
FIXEDPOSITIONLAYOUT/STATICLAYOUT.
Machines and tools are moved to the product,which in turn remains stationary.
E.G:-
Construction of buildings, Dams, Bridges,
Service industries like hospitals, scan centers etc.
14
Prof.S.Gan
guly
15
8/3/2019 5. Facility Layout
15/25
15
ADVANTAGESANDDISADVANTAGES.
ADVANTAGES
Men and machines can be used for a wide variety ofoperations to produce different products.
Low yearly investment.
Pride for workers.
Avoids high costs, and difficulty in transportations.
DISADVANTAGES.
High initial investment.
Large quantity of production is not possible.
Requires high degree of workers and employeeexpertise.
Time consuming. 15
Prof.S.Gan
guly
16
8/3/2019 5. Facility Layout
16/25
16
CELLULARMANUFACTURINGLAYOUT/GROUPTECHNOLOGYLAYOUT.
Machines are grouped into cells, and they functionlike a product layout with a larger shop or processlayout.
16
Prof.S.Gan
guly
17
8/3/2019 5. Facility Layout
17/25
17
ADVANTAGESANDDISADVANTAGES.
Advantages.
Lower WIP inventory.
Reduced material handling cost.
Shorter flow times in production.
Simplified PPC. Increased operator responsibilities.
Improved visual control.
Fewer tooling changes facilitating quicker setups.
Disadvantages Less flexibility
Increased machine downtime.
Duplicate equipments is essential to avoid transportation ofparts between cells.
17
Prof.S.Gan
guly
18
8/3/2019 5. Facility Layout
18/25
18
COMBINATION/HYBRIDLAYOUT
A combination of product and process layout, withan emphasis on either according to the productproduced.
E.G:-
Soap manufacturing, two wheelers.
ULTIMATELY PROFIT IS WHAT MATTERS.
18
Prof.S.Gan
guly
19
8/3/2019 5. Facility Layout
19/25
19
SERVICE FACILITY LAYOUTS
It is specially designed to bring together servicesand customers.
Provisions of easy entrances, gangways, busytrough fares.
Two types of service facility layouts
Totally designed around customer receiving servicefunction.
Totally designed around technologies and machinery.
19
Prof.S.Gan
guly
20
8/3/2019 5. Facility Layout
20/25
20
PLANTUTILITIES
Plant Lighting.
Characteristics.
Sources.
Natural
Artificial.
Features to be considered.
Type of illumination.
Type of light source.
Quality and intensity of light. Glare and its effects.
Color of walls and ceilings.
Maintenance. 20
Prof.S.Gan
guly
21
8/3/2019 5. Facility Layout
21/25
21
PLANTUTILITIES
Ventilation.
Methods
Importance.
General ventilation.
Local exhaust ventilation.
Sources.
Natural.
Artificial/mechanical.
21
Prof.S.Gan
guly
22
8/3/2019 5. Facility Layout
22/25
22
PLANTUTILITIES
Air conditioning.
Objectives.
Types.Depending on season.
Depending on purpose.
22
Prof.S.Gan
guly
23
8/3/2019 5. Facility Layout
23/25
23
PLANTUTILITIES
Industrial sanitation.
Noise control.
Importance
Methods
Control at source.
Control by enclosures.
Control by absorption.
Control through protection of ears.
23
Prof.S.Gan
guly
24
8/3/2019 5. Facility Layout
24/25
24
ASSEMBLYLINES
It refers to progressive assembly linked by somematerial handling device.
Commonly referred material handling devices:-
Conveyor belts.
Overhead cranes.
24
Prof.S.Gan
guly
25
8/3/2019 5. Facility Layout
25/25
25
ASSEMBLYLINE BALANCING.
Workstation cycle time time between twosuccessive units coming off the end of theassembly line.
C = production time per day / required output per day.
Precedence relationship principle of sequence.
Theoretical min. no. of workstations.
Nt = sum of the task times (T) / cycle time (C)
Efficiency = T / (Na x C).
Na = actual no. of workstations.
If efficiency is unsatisfactory, then rebalance usingdifferent rule.s
25
Prof.S.Gan
guly