Date post: | 02-Jun-2018 |
Category: |
Documents |
Upload: | rkraghuram007 |
View: | 213 times |
Download: | 0 times |
of 28
8/10/2019 5 MRP.ppt
1/28
8/10/2019 5 MRP.ppt
2/28
MRP 2
E n
d i t e m
C o m p o n e n
t
R a w
m a
t e r i a
l
RTime
LTLT
RTime
LT
R
TimeLT
Order point system with dependent demand
8/10/2019 5 MRP.ppt
3/28
MRP 3
E n
d i t e m
C o m p o n e n
t
R a w m a
t e r i a
l
R
Time
Time
Time
The MRP approach
8/10/2019 5 MRP.ppt
4/28
MRP 4
The simultaneous probabilityproblem
When components are ordered independently with an order pointsystem, the probability that all will be in stock at the same time ismuch lower than the probabilities for individual components
Computation:Let P n = Prob. that n components arein stock simultaneously
Si = Prob. of stockout on oneorder cycle for component i
ThenPn = S 1 x S 2 x S 3 Sn
8/10/2019 5 MRP.ppt
5/28
MRP 5
The simultaneous probabilityproblem (cont.)
Example:
End Item
S1 = .9 S 2 = .9 S 3 = .9
P3 = .9 x .9 x .9 =
= Prob. that all 3 components will be available at any given time tobuild the end item
1 2 3
.729
8/10/2019 5 MRP.ppt
6/28
MRP 6
Probabilities of simultaneousavailability of components
Number of Service levelcomponent items 90% 95%
1 .900 .9502 .810 .9023 .729 .857
4 .656 .8145 .590 .7746 .531 .7357 .478 .6988 .430 .6639 .387 .63010 .348 .59915 .206 .46320 .121 .35825 .071 .277
8/10/2019 5 MRP.ppt
7/28
MRP 7
Mfg. orders
Demandforecasts and
customer orders
Aggregateplanning/
masterscheduling
Productdesign
changesInventory
transactions
Bill
ofmaterials
MRPsystem
Inventoryrecords
Purchaseorders
Capacity report
Performance/exceptions
Detailedscheduling
system
Purchasingdept.
MRP inputs and outputs
8/10/2019 5 MRP.ppt
8/28
MRP 8
Product tree vs. indented parts list
Product tree
A Level 0
B(2) C(4) Level 1
D(1) E(3) D(2) F(1) G(3) Level 2
8/10/2019 5 MRP.ppt
9/28
MRP 9
Product tree vs. indented parts list(cont.)
Indented parts list
A B(2)
D(1) E(3)
C(4) D(2) F(1)
G(3)
8/10/2019 5 MRP.ppt
10/28
MRP 10
WeekLead
1 2 3 4 5 6 7 8 9 time
Quiz: MRP plan to produce 10 unitsof A due in week 9
Gross Rqmts.
Planned order rls.1
Gross Rqmts.Planned order rls. 2
Gross Rqmts.Planned order rls.
3
Gross Rqmts.Planned order rls. 3
Gross Rqmts.Planned order rls. 2
Gross Rqmts.Planned order rls. 3
Gross Rqmts.Planned order rls.
4
A
B
C
G
F
E
D
8/10/2019 5 MRP.ppt
11/28
MRP 11
Problems in requirementscomputations
Product structure
Recurring requirements within the planninghorizon
Multilevel items
Rescheduling open orders
8/10/2019 5 MRP.ppt
12/28
MRP 12
Product structure
Bills of material are hierarchical with distinct levels
To compute requirements, always proceed down bill ofmaterials, processing all requirements at one level beforestarting another
8/10/2019 5 MRP.ppt
13/28
MRP 13
Product structure (cont.)
Example:Level Inventory O.H.
Truck 0 0
A. Transmission (1) 1 2
B. Gearbox (1) 2 15
C. Gear (1) 3 7
D. Forging Blank (1) 4 46
Suppose we are to produce 100 trucks. What are the netrequirements for each component?
8/10/2019 5 MRP.ppt
14/28
MRP 14
Recurrence of requirements withinthe planning horizon The same item may be required for several different lots within
the planning horizon always process one lot entirely, level bylevel, before starting the next.
Example: One lot of 12 trucks, followed by 2nd lot of 100Lot 1 Lot 2
Level 1: Gross requirements 12 100
8/10/2019 5 MRP.ppt
15/28
MRP 15
Multilevel itemsThe same item may appear at different levels on one or more BOMs result is multiple retrievals of same record to update system.
Examples:
1
2
3
4
X
A
Y
A
Z
A
A
8/10/2019 5 MRP.ppt
16/28
MRP 16
Multilevel items (cont.)
Solution: Low-level coding. Lowest level an item appears is codedon inv. record. Processing delayed until that level reached .
1
2
3
4
X
A
Y
A
Z
A A
8/10/2019 5 MRP.ppt
17/28
8/10/2019 5 MRP.ppt
18/28
MRP 18
Rescheduling open orders (cont.)
Example:Week
1 2 3 4 5 6
Most MRP systems make such schedule changes automatically.
Gross requirements 30 5 10 10 10
Scheduled receipts 20 20
On hand 27 -3 12 12 22 12 2
8/10/2019 5 MRP.ppt
19/28
MRP 19
Tactical questions in MRP
Regeneration vs. net change
Lot sizing
Safety stocks
8/10/2019 5 MRP.ppt
20/28
MRP 20
Regeneration vs. net change
Regeneration Complete replanning of requirements and update of inventory
status for all items
High data processing efficiency
Usually initiated by weekly update of master schedule
Net change Daily update based on inventory transactions
More responsive to changing conditions
Requires more discipline in file maintenance
8/10/2019 5 MRP.ppt
21/28
MRP 21
Lot sizing implications in MRP
The load profiles at work centers in the system depend on the lotsizing rules used
Load profiles determine:undertime / overtimeleadtimes
Example:Lot size Lot size
Pd. Demand Rule 1 Rule 21 5 5 20
2 15 15 03 15 15 204 5 5 0
(Assume 1 unit requires 1 machine hour.)
8/10/2019 5 MRP.ppt
22/28
MRP 22
Lot sizing implications in MRP (cont.)
20 20
15 15
10 10
5 5
0 0
Load profile Load profile Rule 1 Rule 2
M a c h
i n e h r s .
1 2 3 4 1 2 3 4
8/10/2019 5 MRP.ppt
23/28
MRP 23
Lot sizing techniques used in MRPsystems
Lot-for-lot (L4L) most used
Economic order quantity (EOQ)
Period order quantity (POQ)
8/10/2019 5 MRP.ppt
24/28
MRP 24
Lot-for-lot (L4L) example
(Assume LT)
The L4L technique:
Minimizes carrying costs
Is certainly the best method for- highly discontinuous demand- expensive purchased items
Period 1 2 3 4 5 6 7 8 9 Total
Net rqmts. 35 10 40 20 5 10 30 150
Planned order 35 10 40 20 5 10 30 150
MRP1.xls
8/10/2019 5 MRP.ppt
25/28
MRP 25
EOQ example
Setup cost, S = $100Unit price, C = $50Holding costs, H R = .24 per annum
HP = .02 per period
Annual demand, D = 200 Q = (2DS / CH R )1/2 = 58
Period 1 2 3 4 5 6 7 8 9 10
Net rqmts. 35 10 40 20 5 10 30
Planned orders 58 58 58
Remnants 23 13 13 31 31 11 6 54 24 24
8/10/2019 5 MRP.ppt
26/28
MRP 26
Period order quantity exampleTechnique:1. Compute EOQ to determine number of orders per year
2. Divide number of periods in one year by number of orders to getordering interval
EOQ = 58Number of periods in one year = 12D = 200200 / 58 = 3.4 (orders per year)12 / 3.4 = 3.5 (ordering interval)
Period 1 2 3 4 5 6 7 8 9 Total
Net rqmts. 35 10 40 20 5 10 30 150
Planned orders 85 35 30
8/10/2019 5 MRP.ppt
27/28
MRP 27
Safety stocks in MRP systems
Need for safety stocks: Variations in demand due to end-item forecast errors and
inventory errors Variations in supply both lead-times and quantities
Since demand is not random, traditional statisticaltechniques do not apply.
Options to provide safety factors: Fixed quantity buffer stocks Safety lead-time Increase gross requirements
8/10/2019 5 MRP.ppt
28/28
MRP 28
Safety stocks in MRP systems (cont.) Fixed quantity buffer stocks
Good rule of thumb: Set buffer = max. demand likely in a singleperiod
Never generate order solely to replenish buffer stocks
Safety time method
Simply order early Distorts LTs and priorities Better than buffer stocks for items with infrequent demand Also better for purchases outside company
Increase in gross requirements Should be done at end item level only so that
Components available in matched sets Safety stocks are not duplicated at different levels