+ All Categories
Home > Documents > 5 MRP.ppt

5 MRP.ppt

Date post: 02-Jun-2018
Category:
Upload: rkraghuram007
View: 213 times
Download: 0 times
Share this document with a friend

of 28

Transcript
  • 8/10/2019 5 MRP.ppt

    1/28

  • 8/10/2019 5 MRP.ppt

    2/28

    MRP 2

    E n

    d i t e m

    C o m p o n e n

    t

    R a w

    m a

    t e r i a

    l

    RTime

    LTLT

    RTime

    LT

    R

    TimeLT

    Order point system with dependent demand

  • 8/10/2019 5 MRP.ppt

    3/28

    MRP 3

    E n

    d i t e m

    C o m p o n e n

    t

    R a w m a

    t e r i a

    l

    R

    Time

    Time

    Time

    The MRP approach

  • 8/10/2019 5 MRP.ppt

    4/28

    MRP 4

    The simultaneous probabilityproblem

    When components are ordered independently with an order pointsystem, the probability that all will be in stock at the same time ismuch lower than the probabilities for individual components

    Computation:Let P n = Prob. that n components arein stock simultaneously

    Si = Prob. of stockout on oneorder cycle for component i

    ThenPn = S 1 x S 2 x S 3 Sn

  • 8/10/2019 5 MRP.ppt

    5/28

    MRP 5

    The simultaneous probabilityproblem (cont.)

    Example:

    End Item

    S1 = .9 S 2 = .9 S 3 = .9

    P3 = .9 x .9 x .9 =

    = Prob. that all 3 components will be available at any given time tobuild the end item

    1 2 3

    .729

  • 8/10/2019 5 MRP.ppt

    6/28

    MRP 6

    Probabilities of simultaneousavailability of components

    Number of Service levelcomponent items 90% 95%

    1 .900 .9502 .810 .9023 .729 .857

    4 .656 .8145 .590 .7746 .531 .7357 .478 .6988 .430 .6639 .387 .63010 .348 .59915 .206 .46320 .121 .35825 .071 .277

  • 8/10/2019 5 MRP.ppt

    7/28

    MRP 7

    Mfg. orders

    Demandforecasts and

    customer orders

    Aggregateplanning/

    masterscheduling

    Productdesign

    changesInventory

    transactions

    Bill

    ofmaterials

    MRPsystem

    Inventoryrecords

    Purchaseorders

    Capacity report

    Performance/exceptions

    Detailedscheduling

    system

    Purchasingdept.

    MRP inputs and outputs

  • 8/10/2019 5 MRP.ppt

    8/28

    MRP 8

    Product tree vs. indented parts list

    Product tree

    A Level 0

    B(2) C(4) Level 1

    D(1) E(3) D(2) F(1) G(3) Level 2

  • 8/10/2019 5 MRP.ppt

    9/28

    MRP 9

    Product tree vs. indented parts list(cont.)

    Indented parts list

    A B(2)

    D(1) E(3)

    C(4) D(2) F(1)

    G(3)

  • 8/10/2019 5 MRP.ppt

    10/28

    MRP 10

    WeekLead

    1 2 3 4 5 6 7 8 9 time

    Quiz: MRP plan to produce 10 unitsof A due in week 9

    Gross Rqmts.

    Planned order rls.1

    Gross Rqmts.Planned order rls. 2

    Gross Rqmts.Planned order rls.

    3

    Gross Rqmts.Planned order rls. 3

    Gross Rqmts.Planned order rls. 2

    Gross Rqmts.Planned order rls. 3

    Gross Rqmts.Planned order rls.

    4

    A

    B

    C

    G

    F

    E

    D

  • 8/10/2019 5 MRP.ppt

    11/28

    MRP 11

    Problems in requirementscomputations

    Product structure

    Recurring requirements within the planninghorizon

    Multilevel items

    Rescheduling open orders

  • 8/10/2019 5 MRP.ppt

    12/28

    MRP 12

    Product structure

    Bills of material are hierarchical with distinct levels

    To compute requirements, always proceed down bill ofmaterials, processing all requirements at one level beforestarting another

  • 8/10/2019 5 MRP.ppt

    13/28

    MRP 13

    Product structure (cont.)

    Example:Level Inventory O.H.

    Truck 0 0

    A. Transmission (1) 1 2

    B. Gearbox (1) 2 15

    C. Gear (1) 3 7

    D. Forging Blank (1) 4 46

    Suppose we are to produce 100 trucks. What are the netrequirements for each component?

  • 8/10/2019 5 MRP.ppt

    14/28

    MRP 14

    Recurrence of requirements withinthe planning horizon The same item may be required for several different lots within

    the planning horizon always process one lot entirely, level bylevel, before starting the next.

    Example: One lot of 12 trucks, followed by 2nd lot of 100Lot 1 Lot 2

    Level 1: Gross requirements 12 100

  • 8/10/2019 5 MRP.ppt

    15/28

    MRP 15

    Multilevel itemsThe same item may appear at different levels on one or more BOMs result is multiple retrievals of same record to update system.

    Examples:

    1

    2

    3

    4

    X

    A

    Y

    A

    Z

    A

    A

  • 8/10/2019 5 MRP.ppt

    16/28

    MRP 16

    Multilevel items (cont.)

    Solution: Low-level coding. Lowest level an item appears is codedon inv. record. Processing delayed until that level reached .

    1

    2

    3

    4

    X

    A

    Y

    A

    Z

    A A

  • 8/10/2019 5 MRP.ppt

    17/28

  • 8/10/2019 5 MRP.ppt

    18/28

    MRP 18

    Rescheduling open orders (cont.)

    Example:Week

    1 2 3 4 5 6

    Most MRP systems make such schedule changes automatically.

    Gross requirements 30 5 10 10 10

    Scheduled receipts 20 20

    On hand 27 -3 12 12 22 12 2

  • 8/10/2019 5 MRP.ppt

    19/28

    MRP 19

    Tactical questions in MRP

    Regeneration vs. net change

    Lot sizing

    Safety stocks

  • 8/10/2019 5 MRP.ppt

    20/28

    MRP 20

    Regeneration vs. net change

    Regeneration Complete replanning of requirements and update of inventory

    status for all items

    High data processing efficiency

    Usually initiated by weekly update of master schedule

    Net change Daily update based on inventory transactions

    More responsive to changing conditions

    Requires more discipline in file maintenance

  • 8/10/2019 5 MRP.ppt

    21/28

    MRP 21

    Lot sizing implications in MRP

    The load profiles at work centers in the system depend on the lotsizing rules used

    Load profiles determine:undertime / overtimeleadtimes

    Example:Lot size Lot size

    Pd. Demand Rule 1 Rule 21 5 5 20

    2 15 15 03 15 15 204 5 5 0

    (Assume 1 unit requires 1 machine hour.)

  • 8/10/2019 5 MRP.ppt

    22/28

    MRP 22

    Lot sizing implications in MRP (cont.)

    20 20

    15 15

    10 10

    5 5

    0 0

    Load profile Load profile Rule 1 Rule 2

    M a c h

    i n e h r s .

    1 2 3 4 1 2 3 4

  • 8/10/2019 5 MRP.ppt

    23/28

    MRP 23

    Lot sizing techniques used in MRPsystems

    Lot-for-lot (L4L) most used

    Economic order quantity (EOQ)

    Period order quantity (POQ)

  • 8/10/2019 5 MRP.ppt

    24/28

    MRP 24

    Lot-for-lot (L4L) example

    (Assume LT)

    The L4L technique:

    Minimizes carrying costs

    Is certainly the best method for- highly discontinuous demand- expensive purchased items

    Period 1 2 3 4 5 6 7 8 9 Total

    Net rqmts. 35 10 40 20 5 10 30 150

    Planned order 35 10 40 20 5 10 30 150

    MRP1.xls

  • 8/10/2019 5 MRP.ppt

    25/28

    MRP 25

    EOQ example

    Setup cost, S = $100Unit price, C = $50Holding costs, H R = .24 per annum

    HP = .02 per period

    Annual demand, D = 200 Q = (2DS / CH R )1/2 = 58

    Period 1 2 3 4 5 6 7 8 9 10

    Net rqmts. 35 10 40 20 5 10 30

    Planned orders 58 58 58

    Remnants 23 13 13 31 31 11 6 54 24 24

  • 8/10/2019 5 MRP.ppt

    26/28

    MRP 26

    Period order quantity exampleTechnique:1. Compute EOQ to determine number of orders per year

    2. Divide number of periods in one year by number of orders to getordering interval

    EOQ = 58Number of periods in one year = 12D = 200200 / 58 = 3.4 (orders per year)12 / 3.4 = 3.5 (ordering interval)

    Period 1 2 3 4 5 6 7 8 9 Total

    Net rqmts. 35 10 40 20 5 10 30 150

    Planned orders 85 35 30

  • 8/10/2019 5 MRP.ppt

    27/28

    MRP 27

    Safety stocks in MRP systems

    Need for safety stocks: Variations in demand due to end-item forecast errors and

    inventory errors Variations in supply both lead-times and quantities

    Since demand is not random, traditional statisticaltechniques do not apply.

    Options to provide safety factors: Fixed quantity buffer stocks Safety lead-time Increase gross requirements

  • 8/10/2019 5 MRP.ppt

    28/28

    MRP 28

    Safety stocks in MRP systems (cont.) Fixed quantity buffer stocks

    Good rule of thumb: Set buffer = max. demand likely in a singleperiod

    Never generate order solely to replenish buffer stocks

    Safety time method

    Simply order early Distorts LTs and priorities Better than buffer stocks for items with infrequent demand Also better for purchases outside company

    Increase in gross requirements Should be done at end item level only so that

    Components available in matched sets Safety stocks are not duplicated at different levels


Recommended