of 24
7/30/2019 53-FA02111C-C-001 English
1/24
Drawing No.53-FA02111C -C-001
RIAU COAL FIRED STEAM POWER PLANT PROJECT
2X110MW
Preliminary Design Stage
Volume 6 Ash Handling Part
Preliminary Design Description
State class A Certificate No.: A153001315
J uly 2011 K unming
7/30/2019 53-FA02111C-C-001 English
2/24
RIAU COAL FIRED STEAM POWER PLANT PROJ ECT 2X110MW
PRELIMINARY DESIGN
1
APPROVED BY
REVIEWED BY
CHECKED BY
PREPARED BY
7/30/2019 53-FA02111C-C-001 English
3/24
RIAU COAL FIRED STEAM POWER PLANT PROJ ECT 2X110MW
PRELIMINARY DESIGN
2
Table of Content
Chapter 1 General Description.........................................................................................1
1.1 Project Summary ..................................................................................................1
1.2 Design Basis .........................................................................................................1
1.3 Major Design Principle.........................................................................................2
1.4 Original Design Data ............................................................................................2
1.5 Design Contents and Scopes ................................................................................5
1.6 Boiler Ash and Slag Quantity and Limestone Powder Consumption Quantity....5
Chapter 2 Bottom ash handling system...........................................................................7
2.1 The principle for Determination of the System....................................................7
2.2 Technical Process of Bottom Ash Handling System ............................................7
2.3 System Output and Equipment Configuration .....................................................8
Chapter 3 Limestone Powder Handling System...........................................................10
3.1 Principle of the System Determination...............................................................10
3.2 Technical Process of Limestone Powder Conveying System.............................10
Chapter 4 Ash Handling System ....................................................................................13
4.1 Principle of the System Determination...............................................................13
4.2 Technical Process of Ash Handling System .......................................................13
4.3 System Output and Equipment Arrangement.....................................................14
4.4 Selection and Arrangement of Pneumatic Ash Handling Auxiliary System ......15
Chapter 5 Water Supply System Of Ash Handling......................................................18
Chapter 6 Ash Conveyance System Of Off-site............................................................19
Chapter 7 Labor Safty And Profession Health .............................................................20
7.1 Labor Safety .......................................................................................................20
7.2 Dust Prevention ..................................................................................................20
7.3 Noise Prevention ................................................................................................20
7/30/2019 53-FA02111C-C-001 English
4/24
RIAU COAL FIRED STEAM POWER PLANT PROJ ECT 2X110MW
PRELIMINARY DESIGN
1
Chapter 1 General Description
1.1 Project Summary
The project site is located at southeast of Tenayan industry park of
Pekanbaru district of Riau Province on Sumatral island. The power plant is at
northeast side with a distance of 10 kilometers to Pekanbaru (capital city of
Riau Province), and the power plant faces coastline of Siak in north side and
adjoins with Gajah Mada Street in west side. It is located at southeast side in
Tenayan industry park.
This projects construction scale is 2430t/h high-temperature and
high-pressure parameters circulating fluidized bed boiler and 2110MW
high-temperature and high-pressure parameters condensing turbo-generating
unit. Planning capacity is 2110MW. Due to space constraints, expansion will
not be considered.
1.2 Design Basis
1The EPC contract of PLTU RIAU 2110 MW project was signed by PT
PLN(PERSERO) and Consortium PT Rekayasa IndustriHubei Hongyuan
Power Eng.Co, Ltd
2The tender documentthe addendum and the clarification document of
PLTU RIAU 2110 MW project was issued by PT PLN (PERSERO)
3The design contract of PLTU RIAU 2110 MW project was signed by
Hubei Hongyuan Power Eng.Co., Ltd and Yunnan Electric Power Design
Institute
4Technical code for designing fossil fuel power plants DL 5000-2000
5Regulation for content and depth of primary design document of fossil
fuel power plants DL/T 5427-2009
6
Technical code for designing ash handling of power plants DL/T
7/30/2019 53-FA02111C-C-001 English
5/24
RIAU COAL FIRED STEAM POWER PLANT PROJ ECT 2X110MW
PRELIMINARY DESIGN
2
5142-2002
7Boiler, steam turbine and generator, three main equipments contract for
goods and technical agreements
8The relevant Chinese laws, regulations, policies and procedures related
to the design, specifications, etc
9Indonesia's local laws, regulations, policies and relevant provisions, etc.
1.3 Major Design Principle
1.3.1 Separated fly ash and bottom ash handling system and dry ash in dry
drainage system shall be adopted for ash and bottom ash handling system. The
bottom ash handling system shall be determined in accordance with machinery
conveying schedule; fly ash handlingsystem shall be determined in accordance
with pneumatic conveying method of positive pressure and dense phase, and fly
ash and bottom ash outside shall be determined inaccordance with motor
transportation schedule.
1.3.2 Limestone powder conveying system shall be determined in accordance
with the schedule of level-one positive pressure convey to bolier.
1.3.3 Centralized compressed air station shall be set up for compressed air
system of the whole plant.
1.3.4 Sufficient margin for fly ash and bottom ash handling system shall be
remained in order to adjust to the coal quality of the Project.
1.3.5 Based on the principle of equal importance to save and development and
reasonable utilization of resources, closed cooling water shall be adopted for the
whole equipment and reused water for dry ash mixing.
1.4 Original Design Data
1.4.1 Analysis of the coal data and ash components of the Project are as shown
in following Table 1-1 and Table 1-2:
7/30/2019 53-FA02111C-C-001 English
6/24
RIAU COAL FIRED STEAM POWER PLANT PROJ ECT 2X110MW
PRELIMINARY DESIGN
3
Table 1-1 Coal analysis tables
RangeParameter
Minimum MaximumTypical
Proximated Analysis% as received
Total Moisture 25 40 35
Inherent Moisture 13.8 25 18
Ash 3.3 6 5
Volatile 27.9 40 35
Fixed Carbon 23 41 25
Specific Energy (as received)
High Heating Value (kcal/kg)3700 4700 4000
Ultimate Analysis (% dry ash free
Carbon 65 80 68.2
Hydrogen 3 5.9 5.7
Nitrogen 0.54 1.2 1.13
Oxygen 12 30 23.17
Sulfur 0.13 2.2 1.8
Table 1-2 Ash analysis tables
RangeParameter
Minimum MaximumTypical
SiO2 2 60 34
Al2O3 3 52 6
Fe2O3 4.7 52.5 39TiO3 0.02 4.1 0.48
Mn3O4 0.2 8.8 2
CaO 0.8 27.7 10
MgO 0.02 32.6 5
Na2O 0.05 4.12 0.17
K2O 0.1 2.4 1.3
P2O5 0.03 0.8 0.51
7/30/2019 53-FA02111C-C-001 English
7/24
RIAU COAL FIRED STEAM POWER PLANT PROJ ECT 2X110MW
PRELIMINARY DESIGN
4
RangeParameter
Minimum MaximumTypical
SO3 0.2 24.6 1
Ash Fusion Temperature Reducing Reducing Reducing
I.D.Tdefromation 1050
S.T.(softening) 1100
H.T.(hemispherical) 1150
F.T.(fluid) 1200
Ash Fusion Temperature Oxidizing Oxidizing Oxidizing
Slagging and Fouling Index Medium
Hardgrove Grindability Index (HGI) 40 65 50
1.4.2 Utilization hours of the machine unit
The annual utilization hours of the boiler of the Project is calculated as
7008 hours, and daily utilization hours as 20 hours.
1.4.3 Distribution ratio of bottom ash and fly ash
The distribution ratio of bottom ash and fly ash is 20:80 according to the
data provided by boiler factory.
1.4.4 Slagging methods of the boiler
Roller-type bottom ash cooler and continuous slagging method is adopted
for boiler bottom ash cooling equipment.
1.4.5 Precipitator type and efficiency
Electrical precipitator is adopted for the Project with an efficiency of
99.7%.
1.4.6 Ash Yard
The ash storage yard is located at south side of the plant. Dry ash removal
process is adopted for the operation of the ash storage yard and ash and slag will
be transported to ash storage yard for storage by trucks.
The ash storage yard is on the right bank of Siak River with a flat and open
area, and low mountains and hills are separately distributed at west side with a
7/30/2019 53-FA02111C-C-001 English
8/24
RIAU COAL FIRED STEAM POWER PLANT PROJ ECT 2X110MW
PRELIMINARY DESIGN
5
distance of 1km to the west side of the yard. The geomorphic unit type is flood
plain and swamp which is formed by fluvial outwash and the elevation is
normally between 2.5m~3.0m according to the local elevation system of
Indonesia. The land is covered by dense vegetation and the ash storage yard is
now mainly covered by weeds and pteridophyte plants after the original palm
land has been cut down without preservation. Affected by Siak River, a few
surface water systems which exist in a form of small stream or brook with small
water volume develop in and around the yard. There are no buildings or
structures in the yard.
1.5 Design Contents and Scopes
The design contents of the Project are bottom ash handling system, fly ash
handling system, limestone powder conveying system and auxiliary system; and
the design scopes are as follows: all the equipment, pipelines, pipe fittings and
valves of the fly ash handling system from the outlet of precipitator ash hopper
to the outlet of ash discharge equipment in fly ash bin; all the equipment,
pipelines, pipe fittings and valves of the bottom ash handling system from the
outlet of boiler slag cooler to the outlet of unloading equipment of bottom ash
bin; and all the equipment, pipelines, pipe fittings and valves of the limestone
powder conveying system from the loading of limestone powder in bags to
limestone silo then to boiler furnace.
1.6 Boiler Ash and Slag Quantity and Limestone Powder Consumption
Quantity
The boiler ash quantity and limestone powder consumption quantity are
shown in the following Table 1-3 and Table 1-4:
7/30/2019 53-FA02111C-C-001 English
9/24
RIAU COAL FIRED STEAM POWER PLANT PROJ ECT 2X110MW
PRELIMINARY DESIGN
6
Table 1-3 Ash quantity
Hourly ash quantityt/h Daily ash quantityt/d Yearly ash quantityt/aITEM
Fly ash Bottom ash Total Fly ash Bottom ash Total Fly ash Bottom ash Total
1
430 t/hboiler 7.327 1.832 9.159 146.54 36.64 183.18 51348 12839 64186
2430t/h
boiler 14.654 3.664 18.318 293.08 73.28 366.36 102695 25677 128372
Table1-4 Limestone powder quantity
ITEM Hourly quantityt/h Daily quantityt/d Yearly quantityt/a
1430 t/h
boiler5.744 114.88 40254
2430 t/h
boiler 11.488 229.76 80508
7/30/2019 53-FA02111C-C-001 English
10/24
RIAU COAL FIRED STEAM POWER PLANT PROJ ECT 2X110MW
PRELIMINARY DESIGN
7
Chapter 2 Bottom ash handling system
2.1 The principle for Determination of the System
Because the CaO and CaSO4 content of the bottom ash discharged by CFB
is very high, so the waterpower handling methods shall not be adopted.
Therefore, mechanical handling methods is adopted for the bottom ash handling
system of the Project.
2.2 Technical Process of Bottom Ash Handling System
Because the CFB contains limestone for burning, so the CaO content in
bottom ash is high and the bottom ash owns the characteristics of radiation,
expansion, hardening and alkalinity when meets water, so waterpower handling
methods shall not be adopted. And mechanical handling method is more
adjustable to the change of the slag quantity with higher technology and lower
energy consumption, so mechanical conveying system is preliminarily adopted
for the bottom ash handling system of the Project.
Mechanical bottom ash handling system diagram refer to 53-FA02111C
-C-002.
Process flow diagram shown below:
Bottom ash cooler
En-masse scra er conve er
Bottom ash bin
Pu mill
Ash ard
Bucket elevator
7/30/2019 53-FA02111C-C-001 English
11/24
RIAU COAL FIRED STEAM POWER PLANT PROJ ECT 2X110MW
PRELIMINARY DESIGN
8
Two bottom ash coolers shall be set up for each boiler and their slagging outlets
are parallel on the same line. One en-masse scraper conveyer is set up below the
cooler to convey the discharged slag into bucket elevator after the bottom ash is
collected, and the bucket elevator then conveys them into bottom ash bin. One
discharge openings shall be set up below the bottom ash bin, and one double
paddle blender shall be set up at the same time. Bottom ash shall be humidified
by the double paddle blender and then conveyed to ash yard .
One bottom ash bin of steel structure with a diameter of 5m with an
available volume of 25m3
shall be set up for each boiler and close to the boiler,
and it can store a quantity of bottom ash for 15 hours under the design working
conditions of the boiler. In order to make bottom ash discharge convenient and
smooth, one bucket wall vibrator shall be set up.
2.3 System Output and Equipment Configuration
One unit of bottom ash handling system shall be set up for each boiler, and
one en-masse scraper conveyer and one bucket elevator shall be set up for eachunit of bottom ash handling system. The system output is 200% of boiler bottom
ash volume under design working conditions, that is 4t/h, to meet the
requirements of operation and accidental overhaul. The main equipment
configuration of bottom ash handling system is shown as following in Table
2-1:
Table 2-1 The main equipment configuration of bottom ash handling system
NO. NAME MODEL AND SPECIFICATION UNIT QTY. REMARKS
1 Steel bottom ash bin 5 m Available volume:25m3
Set 2
2 En-masse scraper conveyer Q4t/h L25m N=4.5KW Set 2
3 Bucket elevator Q4t/h L18m N=5.5KW Set 2
4 Arrester S25m2
Set 2
7/30/2019 53-FA02111C-C-001 English
12/24
RIAU COAL FIRED STEAM POWER PLANT PROJ ECT 2X110MW
PRELIMINARY DESIGN
9
5Vacuum and pressure relief
valve508 Set 2
6 Vibrator 0.75KW Set 12
7 Double paddle blender Q=100t/h N=11+2.2KW Set 2
8 Vertical sewage pumpQ=26.6m
3/h P=0.24MPa
N=5.5 KWSet 2
Bottom ash conveying equipment layout of boiler refer to 53-FA02111C
-C-006.
7/30/2019 53-FA02111C-C-001 English
13/24
RIAU COAL FIRED STEAM POWER PLANT PROJ ECT 2X110MW
PRELIMINARY DESIGN
10
Chapter 3 Limestone Powder Handling System
3.1 Principle of the System Determination
First level pneumatic conveying method is adopted for limestone powder
handling system of the Project.
3.2Technical Process of Limestone Powder Conveying System
Limestone powder of the Project comes from two ways: one is purchased
finished powder in bags (grain size distribution meets the requirements of the
boiler factory),the finished powder will be sent into bag breaking machine by
fork-lift truck and then into limestone powder silo by bucket elevator; the other
one is purchased bulk limestone powder (grain size distribution meets the
requirements of the boiler factory), and after it is sent to limestone powder
underground hopper by the tipper, it will be sent into bucket elevator by screw
conveyer and then into limestone powder silo through bucket elevator.
First level pneumatic conveying method shall be adopted for conveying of
the limestone powder from limestone powder silo to boiler. This method isrelatively simple, and with fewer intermediate links and a high reliability of
system operation.
Limestone powder handling system diagram refer to 53-FA02111C -C-004.
Process flow diagram shown below:
7/30/2019 53-FA02111C-C-001 English
14/24
RIAU COAL FIRED STEAM POWER PLANT PROJ ECT 2X110MW
PRELIMINARY DESIGN
11
One limestone powder silo in steel structurer shall be set up for each boiler
and located close to the boiler. Each steel structurer silo with a diameter of 5m
with an available volume of 65m3 and a capacity for 12-hour consumption of
the limestone powder necessary for the each boiler under design working
conditions. One limestone powder conveyor shall be set up below each silo to
convey limestone powder to boiler. The output of limestone powder handling
system shall be continuous and adjustable, and the maximum output of the
limestone powder handling system shall not be lower than 150% of the design
limestone powder consumption of a single boiler, i.e. the system output shall be
9t/h .
Vacuum and pressure relief valve and arrester shall be set up at the top of
limestone powder silo and aeration device at the bottom of it in order to make
limestone powder discharge more convenient. One discharge opening shall be
set up below each limestone powder silo and one unit limestone powder
conveyor shall be set up below each discharge opening. Compressed air for
Limestone powder
in bag
Fork-lift
truck Bag-breaking machine
Bulk limestone
powder Underground hopper Screw conveyer
Bucket
elevator
Limestone powder silo Pressure vessel conveyer Screw feeder
Boiler
7/30/2019 53-FA02111C-C-001 English
15/24
RIAU COAL FIRED STEAM POWER PLANT PROJ ECT 2X110MW
PRELIMINARY DESIGN
12
limestone powder conveying and aeration air all comes from compressed air
system of the whole plant and air tank shall be set up beside the limestone
powder silo.
The main equipment configuration of limestone handling system is shown
as following Table 3-1:
Table 3-1 The main equipment configuration of limestone handling system
NO. NAME MODEL AND SPECIFICATION UNIT QTY. REMARKS
1 Steel limestone silo 5 m Available volume:65m3
set 2
2 Steel underground hopper Available volume:20m3
set 2
3 Bag-breaking Machine Q15t/h N=5.5KW set 2
4 Bucket elevator Q15t/h L22m N=7.5KW set 2
5 Pressure vessel conveyer V=1.2m3
set 2
6 Screw conveyer Q=0~15t/h N=4.5kW set 4Frequency
control
7 Arrester S40m2
set 2
8Vacuum and pressure relief
valve
SSF508 set 2
9 Round aeration stone 120 set 12
10 Electric air heater N=30KW set 2
11 Fork-lift truck G1t set 3
Layout for equipment of limestone conveying refer to 53-FA02111C
-C-008.
7/30/2019 53-FA02111C-C-001 English
16/24
RIAU COAL FIRED STEAM POWER PLANT PROJ ECT 2X110MW
PRELIMINARY DESIGN
13
Chapter 4 Ash Handling System
4.1 Principle of the System Determination
The pneumatic conveying mode of positive pressure and dense phase is
adopted for fly ash handling system of the Project.
4.2 Technical Process of Ash Handling System
The pneumatic conveying mode of positive pressure and dense phase is
with advanced technology, low conveying speed, and small air consumption as
well as high ratio of ash and air conveyed, low energy consumption, low
attrition and simple and reliable system, and it also has excellent operation
performance and obvious advantages in environmental cleaning, appearance
and arrangement, and operation maintenance. Therefore, pneumatic conveying
mode of positive pressure and dense phase shall be preliminarily adopted for fly
ash handling system of the Project.
Dry ash collected by ash bucket of precipitator and ash bucket below air
preheater shall be conveyed to fly ash bin by the compressed air. And dry ash infly ash bin shall be sent to ash yard after stirring by the wet-type blender.
Pneumatic ash handling system diagram refer to 53-FA02111C -C-003.
Process flow diagram shown below:
Eight ash hoppers shall be set up for each boiler precipitator and every two
Precipitator ash hopper Compressed air
Pressure vessel conveyer
Fly ash bin
Pu mill
Ash stora e
Air preheater hopper
7/30/2019 53-FA02111C-C-001 English
17/24
RIAU COAL FIRED STEAM POWER PLANT PROJ ECT 2X110MW
PRELIMINARY DESIGN
14
ash hoppers are in a row and in total 4 rows. One ash conveyor shall be set up
for each ash hopper. Two ash pipelines shall be set up for fly ash handling
system, and one ash pipeline shall be set up for the first electric field of the
precipitator and the second, third and fourth electric fields jointly use one ash
pipeline. Two ash hoppers shall be set up for each boiler air preheater and the
ash of air preheater hoppers shall be conveyed to the second electric field
pipeline through one ash pipeline, and the ash shall be conveyed into coarse ash
bin or fine ash bin by the compressed air.
Two fly ash bins of steel structure shall be set up for the two boilers. Fly
ash bins shall be arranged close to chimney and maximum conveying distance is
about 200m.
The diameter of each fly ash bin shall be 6m and available volume shall be
120m3, and the total capacity of two fly ash bins shall store 12-hour boiler
discharged ash volume provided that the two boilers use the design coal. One
discharge openings shall be set up below each fly ash bin, and one double
paddle blender with an output of 100t/h shall be set up. Fly ash shall behumidified by the double paddle blender and then conveyed to ash yard .
4.3 System Output and Equipment Arrangement
One unit of pneumatic ash handling system shall be set up for each boiler.
The design system output shall be 150% of the ash volume discharged by a
single boiler under its maximum evaporation capacity and burned with design
coal, that is, the system output shall be 11t/h in a continuous operation mode.
The main equipment configuration of fly ash handling system is shown in the
following Table 4-1:
7/30/2019 53-FA02111C-C-001 English
18/24
RIAU COAL FIRED STEAM POWER PLANT PROJ ECT 2X110MW
PRELIMINARY DESIGN
15
Table 4-1 The main equipment configuration of ash handling system
NO. NAME MODEL AND SPECIFICATION UNIT QTY. REMARKS
1 Steel fly ash silo 6 m Available volume:120m3 set 2
2 Pressure vessel conveyer V=0.7m3
set 4
3 Pressure vessel conveyer V=0.3m3
set 12
4 Pressure vessel conveyer V=0.1m3
set 4
5 Arrester S=60m2
set 2
6Vacuum and pressure
relief valveSSF508 set 2
7 Double paddle blender Q=100t/h N=11+2.2KW set 2
8 Electric hoist G=1t H20m N=1.5+0.4KW set 1
9 Round aeration stone 120 set 12
Layout for piping and equipment of fly ash silo refer to 53-FA02111C
-C-009.
4.4 Selection and Arrangement of Pneumatic Ash Handling Auxiliary
System
4.4.1 Aeration air system
In order to prevent moisture condensation, increase the flowability of dry
ash in ash hopper of precipitator, and make discharge process smooth, two
aeration blowers shall be set at the 0m floor below precipitator to supply
aeration air to ash hopper of precipitator and fly ash bin for gasification. Besides,
one electric heater shall be set up to heat the aeration air into 150. The
electric heater for precipitator shall be set up at 0m floor and that for fly ash bin
shall be at fly ash bin operation floor in order to save land occupation.
4.4.2 Compressed air system of the whole plant
Unified air compressor station shall be set up for the whole plant in order
to supply air for boiler, ash handling, control and chemical, and it makes various
7/30/2019 53-FA02111C-C-001 English
19/24
RIAU COAL FIRED STEAM POWER PLANT PROJ ECT 2X110MW
PRELIMINARY DESIGN
16
specialized air supply systems into an unified one and changes the defects that
there are too many spare sets of equipment, too much of equipment and various
specifications as well as the situation of separated arrangement and difficult
maintenance management.
The technically matured oil-free screw type air compressor is adopted for
the air supply equipment and corresponding treatment equipment post air
processing is also adopted in order to prevent the blocking of the ash conveying
pipeline caused by compressed air with water or oil. Three oil-free screw type
air compressors are set up in air compressor station with two in operation and
another one for standby; meanwhile three combination compressed air dryers
and four air tanks of 10m3
are also equipped in order to make sure that the air
quality is good and the air supply is stable.
4.4.3 Cleaning system
Hydraulic cleaning system as well as sewage tank shall be adopted in fly
ash bin and bottom ash bin area. The waste water shall be conveyed into
coal-containing sewage tank through sewage pump and reused after treatment inorder to save water and enhance the clean and harmonious production level. The
main equipment configuration of ash handling auxiliary system is shown in the
following Table 4-2:
Table 4-2 The main equipment configuration of ash handling auxiliary system
NO. NAME MODEL AND SPECIFICATION UNIT QTY. REMARKS
1 Screw type air compressorQ=27m
3
/min P=0.8Mpa
N=160kWset 3
Shared device
of whole plant
2Combination compressed
air dryersQ=30m
3/min P=0.8Mpa N=6kW set 3
3 Air Tank V10m3
P=1.0MPa set 4
4 Roots blower Q=10m3/min P=78kPa N=30kW set 2
5 Electric air heater N30Kw set 4
7/30/2019 53-FA02111C-C-001 English
20/24
RIAU COAL FIRED STEAM POWER PLANT PROJ ECT 2X110MW
PRELIMINARY DESIGN
17
6motor single-track
bridge crane
G5t L=10.5m H6m
N7.5+0.8+0.4KWset 1
7 Vertical sewage pumpQ=26.6m
3/h P=0.24MPa
N=5.5 KWset 2
7/30/2019 53-FA02111C-C-001 English
21/24
RIAU COAL FIRED STEAM POWER PLANT PROJ ECT 2X110MW
PRELIMINARY DESIGN
18
Chapter 5 Water Supply System Of Ash Handling
Water for ash handling system shall be provided by thermomechanic and
discharge major. Cooling water for equipment shall be provided by
thermomechanic major and mixing water shall be reused water provided by
discharge major. The water consumption equipment is shown in the following
Table 5-1:
Table5-1 List of water consumption equipment of ash handling system
NO. NAMECONSUMP
TIONm3/hWATER QUALITY
PRESSURE
MPaWATER WAY
1Screw type
air compressor24
closed cycle cooling
water0.3~0.5
continuous
2Combination
compressed air dryers12
closed cycle cooling
water0.3~0.5
continuous
3 Double paddle mixer 40 re-use of water 0.2~0.3interrupt
7/30/2019 53-FA02111C-C-001 English
22/24
RIAU COAL FIRED STEAM POWER PLANT PROJ ECT 2X110MW
PRELIMINARY DESIGN
19
Chapter 6 Ash Conveyance System Of Off-site
The ash shall be conveyed by tip truck to ash yard for storage . Relevant
description of ash yard is in introduction related to hydro-structure major.
7/30/2019 53-FA02111C-C-001 English
23/24
RIAU COAL FIRED STEAM POWER PLANT PROJ ECT 2X110MW
PRELIMINARY DESIGN
20
Chapter 7 Labor Safty And Profession Health
7.1 Labor Safety
Protective cover shall be installed for all the operating machines in ash
handling system as well as outside the couplers of all the operating machines in
order to prevent potential machinery injury. Safety rails shall be installed in ash
bin, at the top of bottom ash bin and on operation platform in accordance with
specifications; rails and cover plates shall be set up at dangerous sites where are
of a potential of falling down, such as platform, walking board (footpath),
hatchway, hoisting hole, gate well and pool sides. Emergency stopping switch
shall be set up for ash handling control system to prevent accidents due to
mistaken operation of turning on or off the equipment.
Heat insulation shall be conducted for electric air heater and aeration
pipelines succeeding it in order to prevent scalding.
7.2 Dust Prevention
Arresters are set up for fly ash bin and at the top of bottom ash bin in orderto make sure the dust content of the discharged air outside the ash bin can meet
the environmental protection requirements and the discharged exhaust gas meet
relevant standards of national environmental protection department and to
reduce environmental pollution; reused water shall be used to wash fly ash bin
and bottom ash bin area in ground cleaning work and the water after being used
shall be collected and conveyed to coal-containing waste water pool for
treatment in order to enhance the clean and harmonious production level of
bottom ash bin and fly ash bin.
7.3 Noise Prevention
During the selection of the equipment for ash handling system, it is
required that the noise level shall not be greater than 85 dB at the point one
meter away from the equipment (A). Sound insulation and absorbing measures
7/30/2019 53-FA02111C-C-001 English
24/24
RIAU COAL FIRED STEAM POWER PLANT PROJ ECT 2X110MW
PRELIMINARY DESIGN
21
in architectural design for each control room shall be considered, i.e. installation
of sound isolation room, sound absorbing wall and celling,etc. Main working
and living areas shall be far away from high noise source in order toreduce the
harm. Sound isolating measures as well as cold-proof and cooling protection
measures such as the installation of air conditioners shall be adopted outside the
fly ash bin and bottom ash bin operation room.