+ All Categories
Home > Documents > 59268158 Underground Mining

59268158 Underground Mining

Date post: 05-Apr-2018
Category:
Upload: rockymin
View: 228 times
Download: 0 times
Share this document with a friend

of 191

Transcript
  • 7/31/2019 59268158 Underground Mining

    1/191

    MECHANISATION

    OFUNDERGROUND COAL MINING

    METHOD

  • 7/31/2019 59268158 Underground Mining

    2/191

    NCL CIL

    EMS in Rs 1450.00 1400.00

    OMS 12.53 4.15

    Wage Cost in Rs/T 115.72 337.35

    Cost of Production Rs/T 585.82 681.34

    Sale Value. Rs/T 1020.25 923.21

    Wage Cost / Cost of Production % 19.75 49.51

    Wage Cost / Sale of Coal % 11.345 36.54

    WAGE COMPONENT IN TOTAL COST

  • 7/31/2019 59268158 Underground Mining

    3/191

    WHY MECHANISATION NEEDED FORUNDERGROUND MINES

    (i) WAGE COST PER TONNE OF COAL IS AS HIGHAS 50% APPROX. OF SALE VALUE OF COAL.

    (ii) GLOBALISATION & LIBERALISATION OF

    ECONOMY HAS RESULTED IN TO COMMERCIALCOMPETITION FROM IMPORTED COAL

    (iii) IMPORTED COAL AT COASTAL AREA IS

    CHEAPER THAN DOMESTIC POWER GRADE

    COAL WHEN COMPARED TO PER MILLION

    K.CAL. COAL.

    (iv) LANDED COST WILL BE AFFECTED BADLY IN FUTURE

    IF THE RAILWAY FREIGHT OR GOVT. LEVIES ARE

    INCREASED.

  • 7/31/2019 59268158 Underground Mining

    4/191

    (v) MOST OF THE SUPERIOR GRADE OF COAL IS BLOCKED

    AT GREATER DEPTH BEYOND THE ECONOMIC REACH OFOPENCAST MINE

    (vi) OUT OF APPROX. 256 BILLION TONES OF COAL,

    APPROX. 80 BILLION TONES IS AMENABLE FOR OPENCAST

    MINE . BEFORE THE O/C RESERVES ARE EXHAUSTED ,

    THERE IS IMMEDIATE NEED TO ESTABLISH APPROPRIATE

    MASS PRODUCTION TECHNOOGY

  • 7/31/2019 59268158 Underground Mining

    5/191

    1974 - 751

    1

    98

    MECHANISEDMINING

    PICK MINING

    MANUAL MINING

  • 7/31/2019 59268158 Underground Mining

    6/191

    2002 - 03

    64

    0

    46 MECHANISED MINING

    PICK MINING

    MANUAL MINING

  • 7/31/2019 59268158 Underground Mining

    7/191

    2011 - 2012

    99

    0

    1

    MECHANISED MINING

    PICK MINING

    MANUAL MINING

  • 7/31/2019 59268158 Underground Mining

    8/191

    PRESENT TECHNOLOGYAVAILABLE

    BORD & PILLAR METHOD WITH

    MANUAL LOADING

    BORD & PILLAR METHOD WITH SDL

    LOADING

    MASS PRODUCTION TECHNOLOGY

  • 7/31/2019 59268158 Underground Mining

    9/191

    0

    0.1

    0.2

    0.3

    0.4

    0.5

    0.6

    0.7

    0.8

    0.9

    0 1 2 3 4

    MINEOMS

    LOADER OMS Vs MINEOMS

    (LOADER : U/GMANPOWER) Vs MINEOMS

    (SURFACE MAN : U/GMAN) Vs OMS

    UNDERGROUND PRODUCTIVITY

  • 7/31/2019 59268158 Underground Mining

    10/191

  • 7/31/2019 59268158 Underground Mining

    11/191

  • 7/31/2019 59268158 Underground Mining

    12/191

  • 7/31/2019 59268158 Underground Mining

    13/191

    WHERE DO WE NEED TO MECHANISE

    1. COAL WINNING OPERATION

    i) GETTING OF COAL FROM FACE

    ii) TRANSPORTATION OF COAL ALONG GATE

    SYSTEM

    iii)TRANSPORTATION OF COAL THROUGH

    TRUNK SYSTEM

    iv) HANDLING OF COAL AT SURFACE

    2. COAL FACE MECHANISATION

    i) GETTING OF COAL

    ii) SUPPORT OF THE EXPOSED ROOF

    iii) LOADING OF COAL

  • 7/31/2019 59268158 Underground Mining

    14/191

    iv) TRANSPORTATION OF COAL FROM FACE

    TO GATE ROADS

  • 7/31/2019 59268158 Underground Mining

    15/191

    CONSTRAINTS OF BORD &

    PILLAR METHOD 1. IT IS CYCLIC

    2. LIMITATIONS OF COAL PREPARATION

    3.LABOUR INTENSIVE

    4.LOW PRODUCTION CAPACITY

    5.LOW DISTRICT PRODUCTIVITY

    6.VERY SENSITIVE WITH INCREASE OF WAGECOST

    7.EXPOSURE OF MORE WORKMEN TO

    HAZARDOUS AREA

    8.INHERENT HIGH ACCIDENT POTENTIAL

  • 7/31/2019 59268158 Underground Mining

    16/191

    CRITERIA FOR MASS PRODUCTION

    TECHNOLOGY FOR U/G

    1.Continuous in operation.

    2. High production capacity

    3. Higher man productivity

    4. Increased safety

    5. Higher recovery of coal

    6. Adoptability of technology

    7. Return on investment

    8. High reliability of production

    9. Efficient starta control

    10.Better protection to environment

  • 7/31/2019 59268158 Underground Mining

    17/191

    AVAILABLE MASS

    PRODUCTION TECHNOLOGY

    1. Continuous Miner

    2. Highwall Mining

    3. Powered Support Longwall system.

  • 7/31/2019 59268158 Underground Mining

    18/191

    STRENGTH OF CONTINUOUS MINER

    TECHNOLOGY

    BORD & PILLAR MINING CONTINUES TO BE THE

    BACK STAY OF U/G MINING

    OUR WORKMEN - SUPERVISORS ARE

    CONVERSANT WITH BORD & PILLAR MINING

    REQUIRES LESSER GEO-TECHNICALINVESTIGATION THAN PSLW

    COST OF EQUIPMENT IS LESSER THAN PSLW

    NOS.OF EQUIPMENT IS LESSER & EASY TO

    MAINTAIN

  • 7/31/2019 59268158 Underground Mining

    19/191

    DOES NOT REQUIRE MUCH TIME FOR

    INSTALLATION & FACE TRANSFER

    FACE IS EQUALLY PRODUCTIVE LIKEPSLW

    TECHNOLOGY IS FLEXIBLE

    IT IS CONTINUOUS IN OPERATION

  • 7/31/2019 59268158 Underground Mining

    20/191

    CONFIGURATION OF EQUIPMENT

    1. CONTINUOUS MINER

    2. SHUTTLE CARS

    3. MOBILE ROOF BOLTER

    4. SCOOP/LHD

    5. LUMP BREAKER

    6. BELT CONVEYORS

    7. ELECTRICALS

  • 7/31/2019 59268158 Underground Mining

    21/191

  • 7/31/2019 59268158 Underground Mining

    22/191

    Joy12CM15 Continuous Miner

    2 x 170kW Cutter Power

    530 kW Installed Power

    1.8 to 4.6m Cutting Range

  • 7/31/2019 59268158 Underground Mining

    23/191

  • 7/31/2019 59268158 Underground Mining

    24/191

    Roadway Section

  • 7/31/2019 59268158 Underground Mining

    25/191

  • 7/31/2019 59268158 Underground Mining

    26/191

    Shuttle Car 10SC32B(13.7 Tonne Capacity)

    4 Wheel Drive

    4 Wheel Steering

    Hydraulic Cable

    Reel Take-up

  • 7/31/2019 59268158 Underground Mining

    27/191

    Model: BF-14B-3-7C

    Throughput: 250-500 tph

    Coal size in: 700x500x400mm

    Coal size out: -200mm

    Breaker motor: 112kW

    Width: 1270mm

    Stamler Feeder Breaker

  • 7/31/2019 59268158 Underground Mining

    28/191

  • 7/31/2019 59268158 Underground Mining

    29/191

  • 7/31/2019 59268158 Underground Mining

    30/191

    UK Coal Mine

    Joy 12CM15

  • 7/31/2019 59268158 Underground Mining

    31/191

    Twin Entry Development Layout

    30 m

    30 - 70 m

    Feeder-BreakerBelt Shuttle CarContinuous

    Miner

  • 7/31/2019 59268158 Underground Mining

    32/191

    Twin Entry Longwall Layout

    200m

    2000m

    30m

    Typical Multi Pass Continuous Miner

  • 7/31/2019 59268158 Underground Mining

    33/191

    Typical Multi-Pass Continuous Miner

    Operation

  • 7/31/2019 59268158 Underground Mining

    34/191

  • 7/31/2019 59268158 Underground Mining

    35/191

    Shuttle

    Car

    Routes

    in

    5

    Entry

  • 7/31/2019 59268158 Underground Mining

    36/191

  • 7/31/2019 59268158 Underground Mining

    37/191

  • 7/31/2019 59268158 Underground Mining

    38/191

  • 7/31/2019 59268158 Underground Mining

    39/191

  • 7/31/2019 59268158 Underground Mining

    40/191

  • 7/31/2019 59268158 Underground Mining

    41/191

  • 7/31/2019 59268158 Underground Mining

    42/191

    Highwall Mining in India:

    Challenging Opportunities!

  • 7/31/2019 59268158 Underground Mining

    43/191

    What is Highwall Mining?

    Equipment

    Mining Methods

    How to Start in India?

  • 7/31/2019 59268158 Underground Mining

    44/191

    What is Highwall Mining?

  • 7/31/2019 59268158 Underground Mining

    45/191

    Highwall Mining: Mining a visible coal seam by making

    rectangular, mainly parallel, unsupported drives,using an unmanned cutter head and coaltransport system, controlled from a mining unitpositioned outside the drive, in front of the seam

  • 7/31/2019 59268158 Underground Mining

    46/191

    Equipment

  • 7/31/2019 59268158 Underground Mining

    47/191

  • 7/31/2019 59268158 Underground Mining

    48/191

    Base Unit

    Length base approx. 20.1 meters

    Width base approx. 9.2 meters

    Weight base approx. 160 tonnes

    Length of pushbeams 6.27meters 6 tonnes each

    50 pushbeams per miner

    Max. force in: approx. 170 tonnes,

    out: approx. 350 tonnes

  • 7/31/2019 59268158 Underground Mining

    49/191

    Tracks

    Four hydraulically powered tracksarticulate over 90 degrees for

    straight and cross travel

    Circle mode for accurate heading

    Each track 1 meter verticalmovement for adjusting seam dip

    and floor contour

    Turning of each track is achievedautomatically

  • 7/31/2019 59268158 Underground Mining

    50/191

    Reel and Chain

    Power chain for

    Electrical cables for cutter

    Hydraulic lines

    Closed circuit cooling water lines forcutter motors

    Methane sensor cable

    Control cableHoses protected by steel plates and links

    Hose chain approximately 330 meters

    Automatically unwinds/winds into/from

    channel on pushbeam

  • 7/31/2019 59268158 Underground Mining

    51/191

    Pushbeams

    Pushing Cutterhead straight in

    Transporting coal

    Pulling Cutterhead back

    Enclosed

    Stackable

  • 7/31/2019 59268158 Underground Mining

    52/191

    Pushbeams

    Striker Plates

  • 7/31/2019 59268158 Underground Mining

    53/191

    Cutter Heads

    Interchangeable, for

    seams 0.8 to approx. 5meters

    Width 2.9 to 3.5 metres

    Automatically following

    seam contour

  • 7/31/2019 59268158 Underground Mining

    54/191

    Anchoring

  • 7/31/2019 59268158 Underground Mining

    55/191

    Generator

    Motor Generator Set

    Capacity 1550KW & 2000 KW

  • 7/31/2019 59268158 Underground Mining

    56/191

    Controls

    Touch screen technology

    Automatic shearing, various options

    Automatic sumping, various options

    Straight holes due to rigid string inhorizontal direction

    Follows layers due to flexibility in

    vertical direction

    Accurate heading is important toensure parallel cuts

  • 7/31/2019 59268158 Underground Mining

    57/191

    Mobility

    Public road transport:Operational within three daysexcluding travelling time.

    Optional:Machine movers for longer hauls,fully assembled

    Example:

    During 9 months SHM-20 was movedto 7 different mining pits - somemoves over 6 kilometers in distance

  • 7/31/2019 59268158 Underground Mining

    58/191

    Production

    Penetration 300 meters

    Dip of up to 12 degrees

    Monthly production typicallyaround 100,000 tonnes

    Operates with a 3 / 4 man crew

    Up to 70% recovery, subject to

    - Coal compressionresistance

    - Overburden load

    - Seam height / Pillar

    stability

  • 7/31/2019 59268158 Underground Mining

    59/191

    Typical Highwall Mining

    Entries

  • 7/31/2019 59268158 Underground Mining

    60/191

    Video

    Strength of Technology

  • 7/31/2019 59268158 Underground Mining

    61/191

    Strength of Technology

    1. Recovers coal otherwise lost

    2. Safe: No man underground3. Economical: Cheaper than U/G mining4. Proven: 45 Machines working now5. Enclosed Pushbeams: No ash dilution

    6. Screw Conveyors: Simple, can handle wetcoal7. Compact: Narrow bench or trench8. Tracks: Easy travelling and positioning9. Modular: Easy to relocate mine to mine

  • 7/31/2019 59268158 Underground Mining

    62/191

    Mining Methods

  • 7/31/2019 59268158 Underground Mining

    63/191

    Mining Methods

    Contour Mining

    Trench Mining

    Bench mining

    Highwall Mining

  • 7/31/2019 59268158 Underground Mining

    64/191

    Contour MiningOutcrop of Seams

    Trench Mining

  • 7/31/2019 59268158 Underground Mining

    65/191

    Trench MiningFlat Seams

  • 7/31/2019 59268158 Underground Mining

    66/191

  • 7/31/2019 59268158 Underground Mining

    67/191

    Bench Mining Top Down

  • 7/31/2019 59268158 Underground Mining

    68/191

    Bench Mining

  • 7/31/2019 59268158 Underground Mining

    69/191

    Blast Bench

  • 7/31/2019 59268158 Underground Mining

    70/191

    Mine Floor Coal

  • 7/31/2019 59268158 Underground Mining

    71/191

    Highwall Mine Seam

  • 7/31/2019 59268158 Underground Mining

    72/191

    Highwall Mine Seam

  • 7/31/2019 59268158 Underground Mining

    73/191

    Blast 2nd Bench

  • 7/31/2019 59268158 Underground Mining

    74/191

    Blast 2nd Bench

  • 7/31/2019 59268158 Underground Mining

    75/191

    Mine Floor Coal Bench 2

  • 7/31/2019 59268158 Underground Mining

    76/191

    Highwall Mine Seam 2

  • 7/31/2019 59268158 Underground Mining

    77/191

    Highwall Mine Seam 2

  • 7/31/2019 59268158 Underground Mining

    78/191

    Strip Seam 3

  • 7/31/2019 59268158 Underground Mining

    79/191

    Strip Seam 3

  • 7/31/2019 59268158 Underground Mining

    80/191

    Strip Seam 3

  • 7/31/2019 59268158 Underground Mining

    81/191

    Highwall Mine Seam 3

  • 7/31/2019 59268158 Underground Mining

    82/191

    Highwall Mine Seam 3

  • 7/31/2019 59268158 Underground Mining

    83/191

    Ready!

    Highwall Mining

  • 7/31/2019 59268158 Underground Mining

    84/191

    O/C Pit Limit

    Wh b A li d

  • 7/31/2019 59268158 Underground Mining

    85/191

    Where to be Applied:

    1.Thin Seams

    2.Beyond Strip Limit

    3.Coal Blocked in Boundaries

    5.Spoils, Roads, Power Lines

    6.Villages

    B fit

  • 7/31/2019 59268158 Underground Mining

    86/191

    Benefits

    Coal otherwise lost can be recovered

    Low cost per ton compared to underground

    Up to 100.000 ton per month per machine

  • 7/31/2019 59268158 Underground Mining

    87/191

    STENGTH OF MECHANISED LONGWALL

    ALL OPERATIONS ARE MECHANISED

    IT IS CONTINUOUS NOT CYCLIC

    VERY HIGH PRODUCTIVE

    VERY SAFE VERY HIGH PRODUCTIVITY

    HIGH CONSERVATION OF COAL

    EFFICIENT STRATA CONTROL

    NO BLASTING - NO POLLUION OF ENVIRONMENT

  • 7/31/2019 59268158 Underground Mining

    88/191

  • 7/31/2019 59268158 Underground Mining

    89/191

  • 7/31/2019 59268158 Underground Mining

    90/191

  • 7/31/2019 59268158 Underground Mining

    91/191

  • 7/31/2019 59268158 Underground Mining

    92/191

  • 7/31/2019 59268158 Underground Mining

    93/191

  • 7/31/2019 59268158 Underground Mining

    94/191

  • 7/31/2019 59268158 Underground Mining

    95/191

  • 7/31/2019 59268158 Underground Mining

    96/191

  • 7/31/2019 59268158 Underground Mining

    97/191

  • 7/31/2019 59268158 Underground Mining

    98/191

  • 7/31/2019 59268158 Underground Mining

    99/191

    ARMOURED FLEXIBLE CONVEYORS

    FUNCTION OF AFC

    1/ To receive coal from shearer and carry it along the coal

    face.

    2/ To provide base for the Shearer and anchorage for

    Shearer chain 3/ To provide anchorage to powered support or advance

    4/ To enable a system of continuous mines because the

    conveyor being flexible

    MAIN COMPNENTS OF AFC

    1/ Drive Unit

    2/ Return Unit

  • 7/31/2019 59268158 Underground Mining

    100/191

  • 7/31/2019 59268158 Underground Mining

    101/191

    ANCIALLARY EQUIPMENT

    SPILL PLATE

    TO PREVENT SPILLAGE OF COAL

    TO ANCHOR POWERED SUPPORT

    TO GUIDE POWER LOADER

    TO PROTECT CABLE & HSES

    RAM PATE

    TO SCRAP & LOAD FLOOR COAL

    TO PROVIDE PATH FOR SHEARER

  • 7/31/2019 59268158 Underground Mining

    102/191

  • 7/31/2019 59268158 Underground Mining

    103/191

  • 7/31/2019 59268158 Underground Mining

    104/191

  • 7/31/2019 59268158 Underground Mining

    105/191

    Lesson learnt from past

    Inadequate Geotechnical investigation & assessment.

    Lack of matching infrastructure.

    Delay in gate road drivages.

    Non-availability of required spares. Non-existence of R&D study during operation.

    Low Accident potential.

    Higher recovery of coal.

    Wide gap between max. production achieved & average

    production.

    Least Impact of wage cost due to rise in EMS.

    Production to the tune of 1Million tonne per year is achievable.

    Strength of Powered Support

  • 7/31/2019 59268158 Underground Mining

    106/191

    Strength of Powered Support

    Longwall Technology

    Higher Production.

    Higher Productivity.

    Most safe mining method.

    Highest recovery.

  • 7/31/2019 59268158 Underground Mining

    107/191

    0

    50

    100

    150

    200

    250

    300

    1990 1991 1992 1993 1994 1995 2004

    Production year wise

    Productioninmillionshorttonne

    Continious Miner

    LongwallConventional

    Others

  • 7/31/2019 59268158 Underground Mining

    108/191

    0

    20

    40

    60

    80

    100

    120

    1976 1983 1993 1996 2004

    Years

    %P

    roductionbyLongwall/Underg

    round,NumberofLongwall

    0

    0.5

    1

    1.5

    2

    2.5

    3

    3.5

    4

    4.5

    AnnualProductionperLongwallinmilliontonne

    Number of longwall%Longwall/Underground production

    Annual Production in million tonne

    Milestone of Longwall production 2003

  • 7/31/2019 59268158 Underground Mining

    109/191

    Milestone of Longwall production 2003-

    2004

    USA produces 189 MT from 46 longwall.

    2 longwall produces >10 MT/year of cleaned coal .

    8 longwall produces >8 MT/year of cleaned coal.

    Australia produces 65 MT from 26 longwall.

    Shanhua group produces 73.84 MT from 5 longwall mines.

    Yujialing produced 11.64 MT.

    Diliuta produced 10.94 MT.

  • 7/31/2019 59268158 Underground Mining

    110/191

    Productivity

    USA -14 tonne per hour

    -14800 tonne per man year

    Criteria for Planning of Longwall

  • 7/31/2019 59268158 Underground Mining

    111/191

    Criteria for Planning of Longwall

    Project

    Geology.

    Cavablity & support design.

    Selection of equipment.

    Coal clearance.

    Spares management.

    Gate road drivages.

    Major parameters for evaluation

  • 7/31/2019 59268158 Underground Mining

    112/191

    Major parameters for evaluation

    of Support

    Support efficiency.

    Roof to floor convergence.

    Active horizontal force. Roof cavity.

    Canopy contact condition.

    Uniformity of Support load.

    Leg resistance.

  • 7/31/2019 59268158 Underground Mining

    113/191

    Gate road drivages

    Single entry.

    Double entry.

    Three entry. Four entry.

  • 7/31/2019 59268158 Underground Mining

    114/191

    Number of entries for longwall gate road drivages

    0

    10

    20

    30

    40

    50

    60

    70

    80

    1979 1985 1990 1995 1996 2004

    Years

    %d

    rivage

    system

    2 entry

    3 entry4 entry

    others

  • 7/31/2019 59268158 Underground Mining

    115/191

    Higher up time

    Higher capacity-Reliable equipment.

    5000 7

  • 7/31/2019 59268158 Underground Mining

    116/191

    0

    500

    1000

    1500

    2000

    2500

    3000

    3500

    4000

    4500

    1980 1990 2000

    TPH,LongwallProductivityIndex

    0

    1

    2

    3

    4

    5

    6

    Milliontonneperyear

    TPH

    Longwall Productivity Index

    Million ton per year

    How Delay Matters

  • 7/31/2019 59268158 Underground Mining

    117/191

    0

    5

    10

    15

    20

    25

    30

    0 2 4 6 8 10 12

    SHEARER SPEED IN M/MIN

    NUMBEROFSHEARSPERDAY

    D = 0

    D = 30

    D = 60

    D = 120

  • 7/31/2019 59268158 Underground Mining

    118/191

    0

    10

    20

    30

    40

    50

    60

    70

    80

    90

    1979 1982 1985 1988 1990 1992 1994 1996

    Years

    %o

    ftotalLongwallface

    100-150

    151-200

    201-250

    251-300

    301-350

    Panel Length

  • 7/31/2019 59268158 Underground Mining

    119/191

    0

    10

    20

    30

    40

    50

    60

    70

    80

    1979 1985 1990 1995 1996

    Years

    Numberof

    Panels

  • 7/31/2019 59268158 Underground Mining

    120/191

    Optimization of Shearer cutting

    sequence

    Uni-directional.

    Bi-directional.

    Half web. Partial opening.

  • 7/31/2019 59268158 Underground Mining

    121/191

    Comparison of the Production vs Seam height for different mining sequence

    0

    1000

    2000

    3000

    4000

    5000

    6000

    Seam Height Uni directional Bi directional Half Opening Half Web

    Cutting sequence

    ProductioninTPH

    Series1

    Series2

    Series3

  • 7/31/2019 59268158 Underground Mining

    122/191

    ECONOMICS

    Sl.No. Description Rajendra Colliery(Longwal started from Dec'981997-98 1998-99 Upto July'99 Upto July'98

  • 7/31/2019 59268158 Underground Mining

    123/191

    Rs./T % of total Rs./T % of total Rs./T % of total Rs./T % of total

    cost cost cost cost

    1 O.M.S 0.76 -- 1.92 -- 2.94 -- 0.71 --

    2 E.M.S. 391.95 -- 448.31 -- 434.57 -- 366.05 --

    3 Wage Cost 524.81 46.5 235.11 33.57 148.64 30.68 518.07 53.99

    4 O/H Cost 45.91 4.07 43.88 6.27 40.9 8.44 39.23 4.095 Store Cost 158.18 14.02 43.55 6.22 34.66 7.15 80.3 8.37

    6 Power Cost 168.68 14.95 77.84 11.11 69.57 14.36 188.19 19.61

    7 Coal Tran.cost 30.81 2.73 33.79 4.82 41.8 8.62 31.24 3.26

    8 Interest 113.99 10.1 206.65 29.5 50.47 10.42 26.1 2.72

    9 Description 58.04 5.15 54.56 7.79 77.19 15.93 45.26 4.7210 Misc. cost 28.1 2.49 5.07 0.01 21.23 4.38 31.13 3.24

    11 Prod. cost 1128.52 -- 700.45 -- 484.46 -- 959.52 --

    12 Sale value 890.85 -- 930 -- 874.63 -- 977

    13 Profit (-) 237.67 -- 229.55 -- 390.17 -- 17.28 --

    Sl.No. Description Balrampur Colliery (Longwal started from May'98)1997-98 1998-99 Upto July 99 Upto July'98

  • 7/31/2019 59268158 Underground Mining

    124/191

    Rs./T % of total Rs./T % of total Rs,/T % of total Rs./T % of tota

    cost cost cost cost

    1 O.M.S. 1.04 -- 1.39 -- 3.86 -- 1.67 --2 E.M.S. 319.27 -- 361.34 -- 375.9 -- 321.85 --

    3 Wage cost 310.62 37.32 362.55 31.69 97.84 22.47 193.82 34.54

    4 O/H Cost 49.88 5.99 56.04 6.76 43.43 9.97 71.06 12.66

    5 Store cost 129.97 15.62 117.73 14.21 72.91 16.74 109.31 19.48

    6 Power cost 171.19 20.57 120.75 14.57 70.93 16.29 95.18 16.96

    7 Coal Trans.cost 26.78 3.21 19.32 2.33 21.36 4.91 17.98 3.2

    8 Interest 56.62 5.12 134.19 16.2 38.19 8.77 17.69 3.2

    9 Depreciation 42.51 5.11 81.74 9.87 61.44 14.11 32.06 5.11

    10 Misc. cost 44.72 5.37 36.24 4.37 29.36 6.74 23.99 4.2811 Prod. cost 832.29 -- 828.56 -- 435.46 -- 561.09 --

    12 Sale value 852.02 -- 888.17 -- 837.37 -- 919.89 --

    13 Profit 19.73 -- 59.61 -- 401.91 -- 358.8 --

    TECHNOLOGYTECHNOLOGY WISE COST PERFORMANCEWISE COST PERFORMANCE

  • 7/31/2019 59268158 Underground Mining

    125/191

    250.55-199.60-58.64-576.44Profit/Loss (Rs / Te)13

    818.95740.59861.28797.27Sale Price (Rs/Te)12

    568.40940.19919.921373.71Total Cost (Rs/te)11

    82.5497.8561.7949.71Depreciation

    (Rs/Te)

    10

    59.1953.9842.9442.01Interest (Rs/Te)9

    94.35108.10103.1499.12Store Cost (Rs/Te)8

    86.47136.9683.18217.22Power Cost (Rs/Te)7

    133.61433.83469.49871.02Wages Cost (Rs./Te)6

    23.51%46.14%51.04%63.41%Wages cost as % of

    Total

    5

    375.58386.76403.22428.19EMS (Rs.)4

    2.820.900.880.51OMS (Te)3

    CDCCGrade2

    6.791.991.550.87Rev.Production (LT)1

    BALRAMPUR

    LONGWALL

    BANGWAR

    SDL

    PIPARIA

    MANUAL +

    SDL

    CHACHAI

    UG

    MANUAL

    DESCRIPTIONSl.No

    Australian longwall production for 2003-2004

  • 7/31/2019 59268158 Underground Mining

    126/191

  • 7/31/2019 59268158 Underground Mining

    127/191

    US Longwall production 2004

  • 7/31/2019 59268158 Underground Mining

    128/191

  • 7/31/2019 59268158 Underground Mining

    129/191

    TEN FACTS ABOUT LONGWALL

  • 7/31/2019 59268158 Underground Mining

    130/191

    TEN FACTS ABOUT LONGWALL

    Geology is not the cause of roof fall

    100% of roof falls are caused by people

    95% of roof falls are avoidable Poor roof conditions are frequently caused

    by faulty roof supports

    Roof falls statistically occur after ashutdown

    TEN FACTS ABOUT LONGWALL

  • 7/31/2019 59268158 Underground Mining

    131/191

    TEN FACTS ABOUT LONGWALL

    A 950 TON ROOF SUPPORT WILL HOLD THE

    WEIGHT OF TWO FULLY LOADED BOEING

    747 WITH 400 PASSENGERS

    SET LOAD IS MORE IMPORTANT THAN

    YIELD LOAD

    LONGWALL ROOF FALLS COST INDUSTRY

    MILLONS OF DOLLAR EVERY YEAR

    TEN FACTS ABOUT LONGWALL

  • 7/31/2019 59268158 Underground Mining

    132/191

    TEN FACTS ABOUT LONGWALL

    The powered roof support system on a

    modern longwall is the most physically

    abused, grossly neglected and totallymisunderstood integration of leading edge

    technology that exists today

    YOU can make a defference.

  • 7/31/2019 59268158 Underground Mining

    133/191

    THANK YOU

  • 7/31/2019 59268158 Underground Mining

    134/191

    What is Support Capacity

  • 7/31/2019 59268158 Underground Mining

    135/191

    What is Rated Load Density or Load Density at yield

    Capacity of Support

    RLD =

    Maximum Span X Spacing

    Overall Rated Load density = X .RLD

  • 7/31/2019 59268158 Underground Mining

    136/191

    y

    X Depends on

    1) System Hydraulic Leakage

    2) Deviation of span

    3) Deviation of setting load & yield load

    What is Load on the support

    What is the caving height

    Height of extraction

    Caving height = H = ------------------------------

    Bulk factor - 1

  • 7/31/2019 59268158 Underground Mining

    137/191

    EXPERIENCE AT JHANJRA

  • 7/31/2019 59268158 Underground Mining

    138/191

    EXPERIENCE AT JHANJRA

    i) Support density of 55 T/Sq.m.(KM 130) was less.ii) Where H/t ratio more than 10 - no significant strata

    problem.

    iii) Panel experienced strata problem where H/t 8 or less.

    iv) Support density of 88T/Sq.m. proved better for strata

    control point of view.

    v) MLD/RLD was 0.8 with 55 T/sq.m.

    vi) MLD/RLD was 0.6 with 88 T/sq.m.

    vii) Subsidence 57% to 58% of Height of Extraction

    viii)Convergence 7%- 8% of Height of Extraction

    Borehole details of Panel 1 of Rajendra U/G Mine

  • 7/31/2019 59268158 Underground Mining

    139/191

    Borehole Number Position of centre

    from start of face

    BH 1 30m

    BH 2 150m

    BH 5 300m

    BH 6 600m

    BH 7 1050m

    PhysicoMechanical Properties of overlying Strata

    SL. DETAILS B.H.NO B.H.NO B.H.NO B.H.NO B.H.NO

  • 7/31/2019 59268158 Underground Mining

    140/191

    NO 1 2 5 6 7

    1. Position from startof panel

    30m 150m 300m 600m 1050m

    2. Depth of highest

    R.Q.D. strata

    24m 41m 39m 51m 36m

    3. R.Q.D value 73% 84% 58% 57% 66%

    4. Depth of CoalSeam

    62.50m 63.0m 63.25m 57.00m 56.00m

    5. Total Hard Cover 38.50m 39.00m 39.25m 42.00m 38.00m

    6. Seam Thickness 2.75m 3.3m 2.75m 2.15m 2.10m

    7. Average WorkingHeight

    2.40m 2.73m 2.73m 2.7 m 2.7 m

    R Q D of the beds Comp. Strength in MPa Tensile Strength in MPa

    PHYSICO-MECHANICAL PROPERTIES OF STRATA INDIFDIFFFERENT PANELS AT BALRAMPUR MINE :

  • 7/31/2019 59268158 Underground Mining

    141/191

    Depth (m)P-1 P-2 Panel P-1 Panel P-2 Panel P-1 Panel P-2

    00.00 - 12.00 00 00 00 00 00 00

    12.00 - 14.00 42 19 00 2.18 00 0.20

    14.00 - 17.00 92 25 8.04 2.18 0.83 0.20

    17.00 - 20.00 76 18 12.75 9.38 1.00 1.18-2.65

    20.00 - 23.00 82 50 9.35 16.8 1.19 1-1.16

    23.00 - 26.00 56 50 8.90 16.59 1.02 -

    26.00 - 29.00 16 50 8.90 13.1 1.02 1.58-2.91

    29.00 - 32.00 21 27 13.32 16.24 1.57 1.34-3.54

    32.00 - 35.00 30 57 9.27 12.22 0.59 0.98-2.11

    35.00 - 38.00 65 24 10.22 - 0.65 0.57-1.79

    38.00 - 41.00 96 64 9.69 43.66 0.66 1.03-1.81

    41.00 - 44.00 96 71 6.82 22.27 0.92 0.44-2.89

    44.00 - 48.00 34-60 71 13.96 - 2.14 1.34-1.59

    48.00 - 51.00 Coal 40 18.72 14.93 5.11 0.90-1.43

    51.00 - 54.00 51 12-85 18.96 - 1.94 0.74

    54.00 - 57.00 87 Coal 5.5 40.36 - -

    DEPTH

    Borehole cross section of BH-2 & BH-6

  • 7/31/2019 59268158 Underground Mining

    142/191

    ROOF STRATA DETAILSBALRAMPUR INCLINES

  • 7/31/2019 59268158 Underground Mining

    143/191

    Panel P-1 Panel P-2

    Soil/ weathered

    sand stone in M

    21.2 22.8 13.6 14.0

    Depth of cover in

    meter

    47.5 49.3 53.6 54.0

    Medium to coarse

    gr. Sst (hard

    cover) h

    (in meter)

    26.3 26.5 40.05 40.05

    Seam thick in m

    (extractedthickness in m(h))

    2.4

    (2..25)

    2.4

    (2.25)

    2.25

    (2.25)

    2.25

    (2.25)

    h/t - Hard cover/

    seam thickness

    ratio

    10.9 11.0 17.8 17.8

    BALRAMPUR

  • 7/31/2019 59268158 Underground Mining

    144/191

    BALRAMPUR

    i) Higher average RQD - 81-90

    ii) Higher H/t. ratio 10.9 - 17.8

    RAJENDRA

  • 7/31/2019 59268158 Underground Mining

    145/191

    RAJENDRA

    i) RQD average 70. Lesser than Balrampur &

    same in the range of Jhanjra. However, the high

    RQD(84) was above the coal seam 3 - 5 mtrs.

    ii) Moderately cavable (CI - 3513) against Jhanjra

    (2426 - 3076 ).

    iii) Higher H/t ratio 13.2 - 14.2

    EXPERIENCE AT BALRAMPUR 1ST PANEL UPTO

  • 7/31/2019 59268158 Underground Mining

    146/191

    FACE ADVANCEMENT OF 160 MTRS.

    i) Panel started 11.5.98

    ii) Periodic fall varies 20 -25 mtrs. interval

    iii) First main fall at 80 mtrs.- extracted area 12000 sq.m.

    16 supports in the mid zone collared.

    iv) 2nd main all at 160 mtrs. when exposed area 24000 sq.m.

    -- Convergence max. 630 mm

    -- Peak leg pressure - 400 kg./sq.cm.

    -- 13 supports got collared.v) Face was re-started after taking the following actions:

    -- To increase yield fro 35 MPa to 40 MPa

    -- To provide max. hydraulic travel in leg

  • 7/31/2019 59268158 Underground Mining

    147/191

    - To install positive set valve

    -- To induce caving by deep hole blasting from surface.

    -- To restrict the overhang to max. 36 mtrs. & Blasting to

    at an interval of 15 m from face.

    vi) First blasting was done at 178 m from strart of face when

    face was at 191 mtrs.

    vii) During blasting PPV at 15 m face on surface -67 mm/sec.

    PPV at centre of face at U/G -149 mm/sec.

    PPV at main gate at U/G - 51 mm/sec. PPV at tail gate at U/G - 31 mm/sec.

    viii) Radial distance from the edge of chock to blast hole - 22m

    Sl. No. Description Specification

    Details of the explosives charge column are given as under :

  • 7/31/2019 59268158 Underground Mining

    148/191

    1 Type of explosive Acquadyne

    2 Cartridge dia 83 mm

    3 Cartridge weight 2.78 Kg.

    4 Blast hole diameter 100 mm

    5 Loading density 9 Kg/m

    6 Detonation velocity 3400 - 4300 m/sec

    7 Density 1.12 to 1.2 mgs/cc

    BOTTOM DECK

    1 Length of the charge column 3 m

    2 Nos. of cartridge 10

    3 Total weight of explosives 27.8 Kg.

    TOP DECK

    1 Length of column 2.5 m

    2 Nos. of cartridges 8

    3 Total weight of explosives 22.2 Kg.

    4 Total no. of hole per blasting 9 to 13 nos.

    5 Total explosives charge per hole 50 Kg. (Approx.)

    6 Length of span of blasting 60 to 70 m

    SURFACE GROUND MOVEMENT STUDY

    S b id G id

  • 7/31/2019 59268158 Underground Mining

    149/191

    Subsidence Grid

    At start of panel at 6m interval along centre of panel from(-) 30m to 56m

    From 56m onwards at 15m interval

    Details of induced blasting

  • 7/31/2019 59268158 Underground Mining

    150/191

  • 7/31/2019 59268158 Underground Mining

    151/191

    The trend of loading on supports before blasting and after blasting.

  • 7/31/2019 59268158 Underground Mining

    152/191

    Load inT/m2

    45-65 65-70 70-75 75- YL Total

    Overall Frequency 98 13 8 5 124

    Percentage 80 10 6 4 100

    Before Frequency 29 2 - - 31

    Blasting Percentage 94 6 - - 100

    After Frequency 69 13 6 5 93

    Blasting Percentage 74 14 7 5 100

    INTERVAL BETWEEN THE PERIODIC WEIGHTINGS AT BALARAMPUR

  • 7/31/2019 59268158 Underground Mining

    153/191

    (5-10)m (10-20)m (20-30)m > 30 m Total

    Before Frequenc

    y

    2 3 3 1 9

    Blasting Percentag

    e

    23 33 33 11 100

    After Frequenc

    y

    2 15 9 1 27

    Blasting Percentag

    e

    7 56 33 4 100

    Complet

    e

    Frequenc

    y

    4 18 12 2 36

    Panel Percentag

    e

    11 50 33 6 100

    Frequency of periodic weighting at Rajendra

  • 7/31/2019 59268158 Underground Mining

    154/191

    Range (5-10)m (10-20)m (20-30)m

    Before blasting 5 % 67 % 28 %

    After blasting 14 % 81 % 5 %

    Complete panel 11 % 76 % 13 %

    Subsidence Percentage before and after blasting

  • 7/31/2019 59268158 Underground Mining

    155/191

    Days from the

    undisturbed day

    3rd day 9th day 14th day

    Before blasting 3.7 to 13.5 83 to 96 98 to 100

    After blasting 50 to 70 84 to 99 95 to 100

    Subsidence Profile before & after weighting on 10.02.2000

  • 7/31/2019 59268158 Underground Mining

    156/191

    MLD i 65 65 70 70 75 75 t YL T t l R k

    Loading frequency and MLD during periodic weightings :

  • 7/31/2019 59268158 Underground Mining

    157/191

    MLD in

    T/m2

  • 7/31/2019 59268158 Underground Mining

    158/191

    Cumulative Convergence experienced

  • 7/31/2019 59268158 Underground Mining

    159/191

    Cumulative Convergence experienced

  • 7/31/2019 59268158 Underground Mining

    160/191

  • 7/31/2019 59268158 Underground Mining

    161/191

    Cumulative Convergence in mm/hr

  • 7/31/2019 59268158 Underground Mining

    162/191

    Cumulative Convergence in mm/hr.

    Convergence mm/hr < 40 40-60 60-80 > 80 Total

    Before Frequency 1 1 1 2 5

    Blasting Percentage 20 20 20 40 100

    After Frequency 16 3 1 1 21

    Blasting Percentage 76 14 5 5 100

    Observation

  • 7/31/2019 59268158 Underground Mining

    163/191

    -- Magnitude of weighting on support reduce.-- Smoothening of subsidence profile.

    -- Support performance improved

    -- Maximum subsidence 118 cm i.e. 52.4% of seamextracted when face advanced 3.4 D and length of face

    2.9 D

    -- In low RQD regime, subsidence used to reach closer to

    the Longwall face and crack on surface had appeared

  • 7/31/2019 59268158 Underground Mining

    164/191

    the Longwall face and crack on surface had appeared

    within 4 mtrs. of face.-- Frequency of periodic weighting increased.

    -- Pressure Profile of leg circuit did not change.

    -- Convergence in leg redued.

    -- % subsidence reduced from over 50% to 42.3% after

    blasting due to increase of bulking factor.

    -- At 15 mtrs. interval blasting

    12% of max. on 3rd day ater blasting.

    60% of max. on 7th day after blasting

    - At 20 mtrs interal blasting:

  • 7/31/2019 59268158 Underground Mining

    165/191

    -- At 20 mtrs. interal blasting:

    17% of max. on 3rd day63% of max. on 7th day

    -- At 30 mtrs. interval

    11% of max. on 3rd day

    33% of max. on 7th day

    -- At 60 mtrs. interval

    3% of max. on 3rd day

    7% of max. on 7th day

    CONCLUSION

  • 7/31/2019 59268158 Underground Mining

    166/191

    -- p1 - initial support resistance after cut was 69 T/sq.m. &increased to 79 T/sq.m.-- p2- started with 79T/sq.m.

    -- P16- started with 79 T/sq.m.

    -- Before blasting, high convergence 126 mm/min. was

    observed.

    -- Due to presence of stony bed with 9/10 times the

    thickness of extraction, the caving was incomplete.

    -- H/t ratio was 11, 18 & 14 in different panels.

    -- Induced caving by blasting, reduced the intensity of

    convergence but loading on support was higher.

  • 7/31/2019 59268158 Underground Mining

    167/191

    -- Rate of face advance proved to have direct influence

    on convergence i.e. higher rate over 9/10 m/day

    contributed to roof control problem.

    -- Average rate of advance of 6/7 mtrs./day had better

    strata control.

    -- Ratio of MLD/RLD was high in the mid zone ie.

    35 to 80 nos. supports. It is almost equal during

    major weighting.

    -- Induced caving had

  • 7/31/2019 59268158 Underground Mining

    168/191

    Induced caving had

    i) Increased loading on supportsii) Reduced convergence

    iii) Increased periodicity of weighting between 10 - 20 m

    iv) Reduced periodicity beyond 30 m.

    v) Increased initial subsidencevi) Blasting increased better bulk factor

    vii) Blasting interval 20 m is established to be optimum.

    viii) Support resistance should be around 105-110T/sq.m.

  • 7/31/2019 59268158 Underground Mining

    169/191

    -- H/t ratio should be more than 15 if support resistance isless than 90 T/sq.m.

    -- Higher support resistance may reduce the H/t ratio.

  • 7/31/2019 59268158 Underground Mining

    170/191

  • 7/31/2019 59268158 Underground Mining

    171/191

    HOW TO MAKE MECHANISATION A

    SUCCESS

  • 7/31/2019 59268158 Underground Mining

    172/191

    EFFECT OF DELAYS IN LOGWALL

    PERFORMANCE

    FACTORS WHICH GUIDE PRODUCTION

    DELAY ANALYSIS

    COST OF LOST TIME

    HOW DELAY MATTERS

  • 7/31/2019 59268158 Underground Mining

    173/191

    0

    5

    10

    15

    20

    25

    30

    0 2 4 6 8 10 12

    SHEARER SPEED IN M/Sec

    NUMBER

    OFS

    HEARSPER

    DA

    Y

    D = 0

    D = 30

    D = 60D = 120

    Machine Time18 hours

    Face Length150 meter

    Cutting SequenceHalf

    face

    Fleeting Speed6 m / min

    DOWNTIME ANALYSIS OF MECHANISED LONGWALL FACES

    OPERATING WITHIN CIL - OTHER THN MOONIDIH

  • 7/31/2019 59268158 Underground Mining

    174/191

    Name of Mine Panel No. MRT in MAT lost de to breakdown in % age MAT lost due to d in%age

    %ge of Shearer AFC/STL Gate P.pack/ Elect. Total in Shift Bad geo- Power Face pre- Out bye TotalMAT belt chock %age of change mining failure paration clear- in %ge

    MAT time condit- and ance of MAT

    ion others

    DHEMO W-8 30.5 10.07 15.53 5.03 1.13 3.91 35.67 4.93 4.89 5.98 6.19 11.9 33.98

    MAIN W-9 38.46 1.63 12.6 7.8 2.92 -- 24.95 -- -- 1.75 11.48 23.34 36.59

    SETALPUR PH-2 37.81 6.44 10.95 6.16 5.84 4.25 33.64 10.98 -- 5.04 5.96 6.57 28.55

    PH-3 20.26 6.86 11.22 10.4 24.9 4.89 58.27 3.86 -- 5.13 7.82 4.66 21.47

    PATHA-

    KHERA Panel 35 11.8 9.26 1.13 2.4 8.9 33.49 -- -- -- 29.56 1.95 31.51

    Panel 30.13 17.22 7.15 0.86 7.33 7.47 40.03 -- -- 0.23 24.02 5.59 29.84

    Panel B 46.21 12.9 12.95 1.25 1.82 15.31 44.29 -- -- -- 4.9 4.61 9.5Panel 4 42.65 13.5 7.19 0.7 3.6 7.5 32.49 -- 1.7 1.4 17.52 4.24 24.86

    Panel-5 22.88 34 8.88 0.6 1.17 7.67 52.32 -- 0.33 0.3 16.3 1.87 24.8

  • 7/31/2019 59268158 Underground Mining

    175/191

    DOWN TIME ANALYSIS OF MECHNISED LONGWALL FACES

    Panel No. MAT lost due to breakdown in percentage MAT l lost due to delay

    MRT in % Shearer AFC/STL Gate/belt P.Pack/ Elect. Total in Shift Bade Geo- Out bye

  • 7/31/2019 59268158 Underground Mining

    176/191

    of MAT Chock % of MAT Change mining delay

    condition includingPower failure

    Balrampur 54.49 11.53 1.88 0.07 0 0.78 14.26 0 21.02 10.23

    P-2

    DOWN TIME ANALYSIS OF MECHNISED LONGWALL FACES

    MAT lost due to breakdown in percentage MAT l lost due to delay

    Panel No. MRT in % Shearer AFC/STL Gate/belt P.Pack/ Elect. Total in Shift Bade Geo-Out bye

    of MAT Chock % of MAT Change mining delay

    condition including

    Power failure

    RajendraP-16

    panel 51.98 14.63 4.04 0.68 0.18 1.86 21.39 0 16.69 9.94

    DELAY ANALYSIS

    BALRAMPUR P-1 PANEL

  • 7/31/2019 59268158 Underground Mining

    177/191

    54%

    18%

    28%

    MRT

    B/DOWN

    IDLE HRS

    DOWNTIME ANALYSIS

    BALRAMPUR P-2 PANEL

    12%

  • 7/31/2019 59268158 Underground Mining

    178/191

    63%

    19%

    4%

    2%

    SHEARER

    AFC/STL

    GATE BELT

    POWER PACK

    ELECTRICAL

    MONTHWISE PRODUCTION

  • 7/31/2019 59268158 Underground Mining

    179/191

    MONTHWISE PRODUCTION

    RAJENDRA P-16 PANEL

    0

    20000

    40000

    60000

    80000

    100000

    120000

    140000

    DEC'98 JAN'99 FEB'99 MARCH'99 APRIL'99 MAY'99 JUNE'99 JULY'99

    MONTH

    PRODN

    IN

    TE

    MONTHWISE PRODUCTIVITY

  • 7/31/2019 59268158 Underground Mining

    180/191

    MONTHWISE PRODUCTIVITY

    RAJENDRA P-16 PANEL

    0

    500

    1000

    1500

    20002500

    3000

    3500

    4000

    4500

    5000

    DEC'98 JAN'99 FEB'99 MARCH'99 APRIL'99 MAY'99 JUNE'99 JULY'99MONTH

    AV.PRODNP

    ER

    DAY

    INT

    MONTHWISE FACE OMS

    RAJENDRA P-16 PANEL

  • 7/31/2019 59268158 Underground Mining

    181/191

    0

    10

    20

    30

    40

    50

    60

    DEC'98

    JAN'99

    FEB'99

    MARC

    H'99

    APRIL'9

    9

    MAY'99

    JUNE'9

    9

    JULY'9

    9

    MONTH

    FACE

    OM

    S

    IN

    TE.

  • 7/31/2019 59268158 Underground Mining

    182/191

    MONTHWISE PROFITRAJENDRA P-16 PANEL

    0

    100

    200

    300

    400500

    600

    700

    800

    DEC'98 JAN'99 FEB'99 MARCH'99 APRIL'99 MAY'99 JUNE'99

    MONTH

    PROFIT/TE

    INR

    HOW TO REDUCE MACHINE DOWNTIME

  • 7/31/2019 59268158 Underground Mining

    183/191

    -- ANALYSIS OF BREAKDOWN

    -- PREVENTION

    -- APPRAISAL

    -- FAILURE RECTIFICATION

    /--------------------\

    : Prevention : : 3% :

    : -------------------:- /----------------------\

    : Appraisal : : Prevention :

    : 7-10% : : 6-8% :

    : ------------------- : : ----------------------- :

    : Failure : : Appraisal 1-2% :

    : 15-22% : : Failure 2-5% :

    : -- ----------------------------------------------------- :

    MAINTENANCE PROCESS

  • 7/31/2019 59268158 Underground Mining

    184/191

    0

    10

    20

    30

    4050

    60

    70

    80

    90

    100

    Break Down Preventing Predictive

    AVAILA

    BILITY

    Series1

    OBJECTIVE OF MAINTENANCE ENGINEER

  • 7/31/2019 59268158 Underground Mining

    185/191

    1. IDENTIFICATION AND DETECTION OF TROUBLE AS

    QUICKLY AS POSSIBLE.

    2. GETTING THE EQUIPMENT RIGHT AT FIRST AND

    WITH MINIMUM POSSIBLE TIME 3. PREVENTION AGAINST OCCURRENCE OF

    EQUIPMENT FAILURE

    4. CONTINUOUS IMPROVEMENT ON QUALITY

    DEFICIENCY IN P.P.M.

  • 7/31/2019 59268158 Underground Mining

    186/191

    (i) It is basically time-based maintenance (ii) It is regardless of its operating condition and

    based on past performance.

    (iii)It relies on judgment and skill of the

    maintenance crew (iv) It stands on the theory of probability and

    definite prediction is not possible.

    (v) Internal inspection is time consuming.

    (vi) Over and under maintenance are quite common

    (vii)Inspection is carried out when machine is idle

    and not in running condition.

    RELIABLITY

    LONGWALL EQUIPMENT WORKS IN A CHAIN.

  • 7/31/2019 59268158 Underground Mining

    187/191

    Q

    ROLL OF MANAGEMENT 1. PROPER INFRASTRUCTURAL FACILITY

    2. TRAINED AND SKILLED WORK FORCE

    3. PROPER LIAISON AND INTERACTION WITH

    EQUIPMENT MANUFACTURERS

    4. INTRODUCTIN OF MANAGEMENT INFORMATION

    SYSTEM TO GENERATE AND MONITOR

    OPERATION DATA

    5. GENERATION OF AN EFFECTIVE MAINTENANCE

    MANAGEMENT CULTURE

    -- TOTAL QUALITY MANAGEMENT CONCEPT

    CUSTOMER SATISFACTION

    DATA GENERATIONS

  • 7/31/2019 59268158 Underground Mining

    188/191

    FREQUENCY OF INSPECTION

    INSPECTION REPORTS

    FAILURE REPORTS

    SPARES CONSUMED

    TIME TO RECTIFY EFFICIENT PROGRAMME FOR REFURBISHMENT

    REDUCE TURN AROUND TIME.

    JUST IN TIME CONCEPT OF SPARE

    TESTING BY STIMULATION

    INDIGENOUS DEVELOPMENT OF SPARES

    REGULAR EVALUATION

  • 7/31/2019 59268158 Underground Mining

    189/191

    USE OF COMPUTER -- DELAY ANALYSIS (EASY)

    -- OWNERSHIP COST. REPCOST.

    -- PRODUCTION PERFORMANCE TREND

    -- MACHINE PERFORMANCE -- RCM

    -- SPARE MANAGEMENT.

    TRAINING

  • 7/31/2019 59268158 Underground Mining

    190/191

    BASIC TRAINING SCHEME 1. CLASS ROOM THEORETICAL TRAINING

    FOLLOWED BY

    2. CLOSE SUPERVISION ON JOB TRAINING.

    3. ADVANCED THEORETICAL CLASS ROOM

    TRAINING

    4. DEPLOYMENT ON ACTUAL JOB.

    5. REFRESHERS TRAINING.

    FURTHER TRAINING ON

  • 7/31/2019 59268158 Underground Mining

    191/191

    -- SELF MOTIVATION.

    -- LEADERSHIP.

    -- TEAM BUILDING -- PROBLEM ANALYSIS

    -- COMMUNICATION SKILL

    -- LISTENING SKILL

    -- WORK STANDARD

    -- SAFETY AWARENESS


Recommended