+ All Categories
Home > Documents > 59270197 Module 3 Commissioning Instrument Transformers

59270197 Module 3 Commissioning Instrument Transformers

Date post: 14-Apr-2018
Category:
Upload: suresh-k-krishnasamy
View: 231 times
Download: 1 times
Share this document with a friend

of 80

Transcript
  • 7/27/2019 59270197 Module 3 Commissioning Instrument Transformers

    1/80

    10/5/2013 Module Three 1

    SUBSTATIONCOMMISSIONING COURSE

    MODULE THREE

    INSTRUMENT TRANSFORMER

    TESTING PROCEDURES

  • 7/27/2019 59270197 Module 3 Commissioning Instrument Transformers

    2/80

    10/5/2013 Module Three 2

    INTRODUCTION

    The electrical commissioning andacceptance testing of electric

    power systems is essential for theenergization of any electrical

    system for the first time.

  • 7/27/2019 59270197 Module 3 Commissioning Instrument Transformers

    3/80

    10/5/2013 Module Three 3

    INTRODUCTION

    Module Three

    Discuss theory and ratings

    Safety issues Test equipment operation &

    hands on testing

  • 7/27/2019 59270197 Module 3 Commissioning Instrument Transformers

    4/80

    10/5/2013 Module Three 4

    INTRODUCTION

    Skills learned in MODULE THREE:

    Acceptance testing for CTs and VTs

    Operate CT tester Apply safe work practices Analyze test values Complete test forms

  • 7/27/2019 59270197 Module 3 Commissioning Instrument Transformers

    5/80

    10/5/2013 Module Three 5

    INSTRUMENT TRANSFORMERS

    A general classification

    Current transformers (CT) Voltage transformers (VT)

    Isolate primary quantitiesand convert into useable

    secondary values via

    transformation

    Standard secondary rating:

    5A for CT 120V for VT < 24 kV 115V for VT > 24 kV

    Measurement values from

    CTs and VTs:

    Voltage, current,

    frequency, real / reactivepower, energy, power

    factor, impedance

  • 7/27/2019 59270197 Module 3 Commissioning Instrument Transformers

    6/80

    10/5/2013 Module Three 6

    INSTRUMENT TRANSFORMERS

    Polarity markings

    A designation of the relative instantaneous direction ofcurrents

    Current flowing into the polarity mark in the primary isrelatively in phase with current flowing out the polarity

    mark in the secondary

    As if the primary and secondary are connected straightthrough

  • 7/27/2019 59270197 Module 3 Commissioning Instrument Transformers

    7/80

    10/5/2013 Module Three 7

    INSTRUMENT TRANSFORMERS

  • 7/27/2019 59270197 Module 3 Commissioning Instrument Transformers

    8/80

    10/5/2013 Module Three 8

    INSTRUMENT TRANSFORMERS

    Manufacturers name ortrademark

    Manufacturers type Serial number Rated Voltage, maximum

    voltage or nominalsystem voltage

    Rated frequency

    Basic impulse insulationlevel (N/A for bushing

    CTs) Continuous rating factorfor CT (1.0 or more)

    Thermal burden rating forVT (VA)

    Accuracy rating

    Nameplate Data

  • 7/27/2019 59270197 Module 3 Commissioning Instrument Transformers

    9/80

    10/5/2013 Module Three 9

    INSTRUMENT TRANSFORMERS

    Ratio expression betweenwinding groups

    Example: VT with oneprimary and onesecondary winding

    14,400 : 120 VRatio 120 : 1

    Ratio between primary

    and secondary amperes

    Example: CT with one

    primary and one

    secondary winding

    100 : 5 A

    Ratio 20 : 1

    Nameplate Symbols (: colon)

  • 7/27/2019 59270197 Module 3 Commissioning Instrument Transformers

    10/80

    10/5/2013 Module Three 10

    INSTRUMENT TRANSFORMERS

    Voltage rating or ratios

    between winding groups

    Example: VT with two

    windings for series or

    parallel connection

    2,400 x 4800 V

    Ratio 20 x 40 : 1

    Current rating with two or

    more coils for series of

    parallel connection

    Example: CT with two

    primary windings for

    series or parallel conn.

    100 x 200 : 5 A

    Nameplate Symbols (x multiplication sign)

  • 7/27/2019 59270197 Module 3 Commissioning Instrument Transformers

    11/80

    10/5/2013 Module Three 11

    INSTRUMENT TRANSFORMERS

    (Not used for VT) Ampere rating ofseparate secondary

    winding with independentcore

    Example: CT with twosecondary windings and

    two cores.

    100 : 5// 5A

    Nameplate Symbols (// double slant lines)

  • 7/27/2019 59270197 Module 3 Commissioning Instrument Transformers

    12/80

    10/5/2013 Module Three 12

    INSTRUMENT TRANSFORMERS

    Voltage rating or ratios ofseparate winding on one

    core.

    Example: VT with oneprimary and twosecondary winding

    14,400 V: 120 & 72 V

    Ratio 120 & 200:1

    Ampere rating ofseparate primary winding

    on one core.

    Example 1: CT with twoprimary windingsdesigned to be used

    individually.

    100 & 600 : 5A

    Nameplate Symbols (& ampersand)

  • 7/27/2019 59270197 Module 3 Commissioning Instrument Transformers

    13/80

    10/5/2013 Module Three 13

    INSTRUMENT TRANSFORMERS

    Example 2: Totalizing CT

    with four primary

    windings designed to beused simultaneously.

    5 & 5 & 5 & 5 : 5A

    Nameplate Symbols (& ampersand)

  • 7/27/2019 59270197 Module 3 Commissioning Instrument Transformers

    14/80

    10/5/2013 Module Three 14

    INSTRUMENT TRANSFORMERS

    Example 3: CT for three-

    wire single phase.

    100 & 100 : 5A

    Nameplate Symbols (& ampersand)

  • 7/27/2019 59270197 Module 3 Commissioning Instrument Transformers

    15/80

    10/5/2013 Module Three 15

    INSTRUMENT TRANSFORMERS

    Two or more primary orsecondary ratingsobtained by taps in the

    secondary winding

    Example 1: VT withsecondary tap for moreprimary voltage rating

    12,000/14,400 :120 V

    Ratio 100/120 : 1

    Different primary currentratings obtained by tapsin the secondary winding

    Example: CT with taps inthe secondary foradditional ratios

    100 : 5// 5A

    Nameplate Symbols (/ single slant line)

  • 7/27/2019 59270197 Module 3 Commissioning Instrument Transformers

    16/80

    10/5/2013 Module Three 16

    INSTRUMENT TRANSFORMERS

    Example 2: VT with

    secondary tap for

    additional secondaryvoltage ratings

    14,400 : 120/72 V

    Ratio 120/200:1

    Nameplate Symbols (/ single slant line)

  • 7/27/2019 59270197 Module 3 Commissioning Instrument Transformers

    17/80

  • 7/27/2019 59270197 Module 3 Commissioning Instrument Transformers

    18/80

    10/5/2013 Module Three 18

    INSTRUMENT TRANSFORMERS

    CSA Standards CAN/CSA-C60044-1 to -8 (part 1 to part 8), 2007

    Part 1: Current Transformers Part 2: Inductive Voltage transformers

    Part 3: Combined Transformers Part 4: N/A Part 5: Capacitive Voltage transformers Part 6: Requirements for Protective Current

    Transformers for Transient Performance Part 7: Electronic Voltage Transformers Part 8: Electronic Current Transformers

  • 7/27/2019 59270197 Module 3 Commissioning Instrument Transformers

    19/80

    10/5/2013 Module Three 19

    INSTRUMENT TRANSFORMERS

    What is a CT ?

    A device that isolates and transforms the primary currentquantity into a proportional secondary current quantity

    The CT has: Primary winding or primary conductor Magnetic core

    Secondary winding

  • 7/27/2019 59270197 Module 3 Commissioning Instrument Transformers

    20/80

    10/5/2013 Module Three 20

    INSTRUMENT TRANSFORMERS

    Distributed uniformwinding with negligible

    Leakage Flux

    Non-uniform distributedwinding with some

    Leakage Flux

  • 7/27/2019 59270197 Module 3 Commissioning Instrument Transformers

    21/80

    10/5/2013 Module Three 21

    INSTRUMENT TRANSFORMERS

    How does a CT work ?

    Primary current flows generates magnetic field aroundthe conductor

    Magnetic field flows in the magnetic core Magnetic field induces a voltage in the secondary

    winding

    Burden connected to secondary winding completes the

    circuit and allows current to flow

  • 7/27/2019 59270197 Module 3 Commissioning Instrument Transformers

    22/80

    10/5/2013 Module Three 22

    INSTRUMENT TRANSFORMERS

    Ipri x Npri = Isec x Nsec

    Ipri = Current flowing in primary winding

    Isec = Current generated in secondary windingNpri = Number of turns in primary winding

    Nsec = Number of turns in secondary winding

  • 7/27/2019 59270197 Module 3 Commissioning Instrument Transformers

    23/80

    10/5/2013 Module Three 23

    INSTRUMENT TRANSFORMERS

    What is the secondary current ?

    CT ratio: 5000:5A; 1000:1

    Iprimary = 1000A

    Isec = 1000A / (ratio) = 1000A /1000

    = 1A

    In reality, there will slightly less than 1A flowing.

    The difference is the known as the Ratio Error in %

  • 7/27/2019 59270197 Module 3 Commissioning Instrument Transformers

    24/80

    10/5/2013 Module Three 24

    INSTRUMENT TRANSFORMERS

    Never open the secondary of a CT when

    pr imary cu rrent is f low ing because

    dangerous high voltages will appear.

    IEEE C57.13 allow open c ircu it crest

    vo l tages up to 3500 V peak w ithou t

    vo l tage lim it ing devices.

  • 7/27/2019 59270197 Module 3 Commissioning Instrument Transformers

    25/80

    10/5/2013 Module Three 25

    INSTRUMENT TRANSFORMERS

    CT Types

    Torroidal Wound Primary

    Bar Type Split Core

    Tororoidal

    Low flux leakage Typical of bushing and

    window CTs Primary conductor passthrough center

    600V insulation can beused in MV application

    with insulated primaryconductors

  • 7/27/2019 59270197 Module 3 Commissioning Instrument Transformers

    26/80

    10/5/2013 Module Three 26

    INSTRUMENT TRANSFORMERS

    CT Types

    Torroidal (donut) Wound Primary

    Bar Type Split Core

    Wound Primary

    Has an internal primarywinding

    Wound more than 1

    full turn on the core Core can be torroidal Must be inserted in series

    with the conductors

    Bar provides primaryconnection points, oftenmistaken for bar type

  • 7/27/2019 59270197 Module 3 Commissioning Instrument Transformers

    27/80

    10/5/2013 Module Three 27

    INSTRUMENT TRANSFORMERS

    CT Types

    Torroidal (donut) Wound Primary

    Bar Type Split Core

    Bar Type

    Has a continuous bar forthe primary winding

    Only 1 turn primary Core can be torroidal Must be inserted in series

    with the conductors

    Primary insulation part ofCT construction

  • 7/27/2019 59270197 Module 3 Commissioning Instrument Transformers

    28/80

    10/5/2013 Module Three 28

    INSTRUMENT TRANSFORMERS

    CT Types

    Torroidal (donut) Wound Primary

    Bar Type Split Core

    Split Core

    Core is separated intotwo parts

    For use where primaryconductor cannot be

    easily removed

  • 7/27/2019 59270197 Module 3 Commissioning Instrument Transformers

    29/80

    10/5/2013 Module Three 29

    INSTRUMENT TRANSFORMERS

  • 7/27/2019 59270197 Module 3 Commissioning Instrument Transformers

    30/80

    10/5/2013 Module Three 30

    INSTRUMENT TRANSFORMERS

    CT Ratio

    Ratio or primary current to secondarycurrent

    Expressed as current quantities 1000 : 5 A

    Expressed as ratio numbers 200 : 1

  • 7/27/2019 59270197 Module 3 Commissioning Instrument Transformers

    31/80

  • 7/27/2019 59270197 Module 3 Commissioning Instrument Transformers

    32/80

  • 7/27/2019 59270197 Module 3 Commissioning Instrument Transformers

    33/80

    10/5/2013 Module Three 33

    INSTRUMENT TRANSFORMERS

    CT Standard Burden @ 5A, @ 60 Hz

  • 7/27/2019 59270197 Module 3 Commissioning Instrument Transformers

    34/80

    10/5/2013 Module Three 34

    INSTRUMENT TRANSFORMERS

    Basis for Accuracy class for Metering

    CTs and VTs correction factor is within specified limitsfor specified load conditions

    .6 lagging to unity PF

    CT operating between 10% to 100% rated current

    VT operating between 90% to 100% rated voltage

  • 7/27/2019 59270197 Module 3 Commissioning Instrument Transformers

    35/80

    10/5/2013 Module Three 35

    INSTRUMENT TRANSFORMERS

    IT Standard Accuracy Class for Metering @ 60 Hz

  • 7/27/2019 59270197 Module 3 Commissioning Instrument Transformers

    36/80

    10/5/2013 Module Three 36

    INSTRUMENT TRANSFORMERS

    CT Accuracy Rating for Metering

    Accuracy for a specified burdenExample: 0.3 B 1.8

    .3% accuracy for all other burden up to 1.8

    Example: 0.3 B @ 0.2

    .3% accuracy for burden of .2 and 3

  • 7/27/2019 59270197 Module 3 Commissioning Instrument Transformers

    37/80

    10/5/2013 Module Three 37

    INSTRUMENT TRANSFORMERS

    CT Accuracy Rating for Relaying @ 60 Hz

    Accuracy classification apply to full

    winding unless specified

  • 7/27/2019 59270197 Module 3 Commissioning Instrument Transformers

    38/80

    10/5/2013 Module Three 38

    INSTRUMENT TRANSFORMERS

    Relaying CT Class

    C (Calculated) T

    X

    Class C

    Low leakage flux CTs Torroidal type

    3% error @ 5A 10% error @ 100A

  • 7/27/2019 59270197 Module 3 Commissioning Instrument Transformers

    39/80

    10/5/2013 Module Three 39

    INSTRUMENT TRANSFORMERS

    Relaying CT Class

    C T (Tested)

    X

    Class T

    High leakage flux CTs Primary Wound type

    % error obtained fromtesting

    Tested to 100A or > until10% error is establish at

    specified burdens Test curve plotted for IprVs Isec, the overcurrent

    curve

  • 7/27/2019 59270197 Module 3 Commissioning Instrument Transformers

    40/80

    10/5/2013 Module Three 40

    INSTRUMENT TRANSFORMERS

    Relaying CT Class

    C T

    X (Defined)

    Class X

    User defined along withexpected accuracy rating

    for protection application Minimum knee point

    voltage; Vk

    Maximum excitation

    current Ik at Vk Maximum secondarywinding resistance at

    75C, Rs

  • 7/27/2019 59270197 Module 3 Commissioning Instrument Transformers

    41/80

    10/5/2013 Module Three 41

    INSTRUMENT TRANSFORMERS

    Secondary Terminal Voltage

    Saturation voltage level at20X rated current

    100 A

    Vsat = 100 A x Burden

  • 7/27/2019 59270197 Module 3 Commissioning Instrument Transformers

    42/80

    10/5/2013 Module Three 42

    INSTRUMENT TRANSFORMERS

    Saturation Curve

    B-H CurveExcitation Current Vs

    Excitation voltage

    Knee Point voltage, Vk

    10% Ve 50% Ie

  • 7/27/2019 59270197 Module 3 Commissioning Instrument Transformers

    43/80

    10/5/2013 Module Three 43

    INSTRUMENT TRANSFORMERS

    Transformer Formula

    Erms = 2 f N a Bpeak / 2 4.44 f N a B

    Where:

    f = the supply frequency

    N = number of turns

    a = cross sectional area of the coreB = peak magnetic flux density

  • 7/27/2019 59270197 Module 3 Commissioning Instrument Transformers

    44/80

    10/5/2013 Module Three 44

    INSTRUMENT TRANSFORMERS

    Class C Saturation Curve

    Plotted on log-log scale Induced voltage Y-axis

    Excitation current X-axis Voltage begins at 1% Voltage ends at 5X Irated Vk identified where curve

    is at 45 tangent axis

  • 7/27/2019 59270197 Module 3 Commissioning Instrument Transformers

    45/80

    10/5/2013 Module Three 45

    INSTRUMENT TRANSFORMERS

  • 7/27/2019 59270197 Module 3 Commissioning Instrument Transformers

    46/80

    10/5/2013 Module Three 46

    INSTRUMENT TRANSFORMERS

    Class T O/C Ratio Curve

    Plotted of linear scale Secondary current Y-axis

    Primary current X-axis 1 to 22 x rated I-primary

    for all standard burdens

    Curve identifies the

    burden which causes50% ratio correction

  • 7/27/2019 59270197 Module 3 Commissioning Instrument Transformers

    47/80

  • 7/27/2019 59270197 Module 3 Commissioning Instrument Transformers

    48/80

    10/5/2013 Module Three 48

    INSTRUMENT TRANSFORMERS

    5 Groups of VT

    All capable of operating at 110% for emergencycondition

    Emergency for 1 minute Some have special emergency rating conditions All must operate within thermal limits and or specified

    temperature rise

  • 7/27/2019 59270197 Module 3 Commissioning Instrument Transformers

    49/80

  • 7/27/2019 59270197 Module 3 Commissioning Instrument Transformers

    50/80

  • 7/27/2019 59270197 Module 3 Commissioning Instrument Transformers

    51/80

    10/5/2013 Module Three 51

    INSTRUMENT TRANSFORMERS

    Thermal Burden Rating

    The maximum volt-ampere (VA) it can carry withintemperature design limits

    Each winding can have its own rating One specified rating is for combined distribution

    between the 2ndaries, including taps

    TESTING INSTRUMENT

  • 7/27/2019 59270197 Module 3 Commissioning Instrument Transformers

    52/80

    10/5/2013 Module Three 52

    TESTING INSTRUMENT

    TRANSFORMERS

    Safety Consideration

    Many testing involves using high voltages Should be done by trained qualified personnel

    Safe work practice and procedures required

    Review Module 2 IEEE Standard 510 1983,

    Recommended Practice for Safety in HighVoltage & High Power Testing

    TESTING INSTRUMENT

  • 7/27/2019 59270197 Module 3 Commissioning Instrument Transformers

    53/80

    10/5/2013 Module Three 53

    TESTING INSTRUMENT

    TRANSFORMERS

    CT Testing

    Primary InsulationResistance

    Dielectric Withstand Secondary Insulation

    Resistance

    Secondary Burden

    Saturation Ratio and Polarity

    TESTING INSTRUMENT

  • 7/27/2019 59270197 Module 3 Commissioning Instrument Transformers

    54/80

    10/5/2013 Module Three 54

    TESTING INSTRUMENT

    TRANSFORMERS

    CT Testing

    Primary InsulationResistance

    Dielectric Withstand Secondary Insulation

    Resistance

    Secondary Burden

    Saturation Ratio and Polarity

    Primary Ins. Resistance Test

    For Bar and Primary woundCTs

    DC voltage test at the ratedcrest voltage on the primary

    winding

    Secondary grounded

    1 minute test

    TESTING INSTRUMENT

  • 7/27/2019 59270197 Module 3 Commissioning Instrument Transformers

    55/80

    10/5/2013 Module Three 55

    TESTING INSTRUMENT

    TRANSFORMERSCT Insulation Resistance: Bar Type and Primary Wound

    DC Voltage test

    Isolate Primary

    Isolate & Gnd Secondary Connect HV lead to H1/H2 Connect LV to Gnd /

    2ndary

    Test for 1 minute Record test value

    TESTING INSTRUMENT

  • 7/27/2019 59270197 Module 3 Commissioning Instrument Transformers

    56/80

    10/5/2013 Module Three 56

    TESTING INSTRUMENT

    TRANSFORMERS

    CT Testing

    Primary InsulationResistance

    Dielectric Withstand Secondary Insulation

    Resistance

    Secondary Burden

    Saturation Ratio and Polarity

    Dielectric Withstand Test

    For Bar and Primary woundCTs

    AC voltage test at the 75%factory test voltage

    Secondary grounded 1 minute test

    TESTING INSTRUMENT

  • 7/27/2019 59270197 Module 3 Commissioning Instrument Transformers

    57/80

    10/5/2013 Module Three 57

    TESTING INSTRUMENT

    TRANSFORMERS

    CT Dielectric Withstand: Bar Type and Primary Wound

    AC Voltage test

    Isolate & Gnd Secondary

    Connect HV lead to H1/H2 Connect LV to Gnd /

    2ndary

    Test for 1 minute

    Record test value

  • 7/27/2019 59270197 Module 3 Commissioning Instrument Transformers

    58/80

    TESTING INSTRUMENT

  • 7/27/2019 59270197 Module 3 Commissioning Instrument Transformers

    59/80

    10/5/2013 Module Three 59

    TESTING INSTRUMENT

    TRANSFORMERS

    CT Secondary Circuit Insulation Test

    TESTING INSTRUMENT

  • 7/27/2019 59270197 Module 3 Commissioning Instrument Transformers

    60/80

    10/5/2013 Module Three 60

    TESTING INSTRUMENT

    TRANSFORMERS

    CT Testing

    Primary InsulationResistance

    Dielectric Withstand Secondary InsulationResistance

    Secondary Burden

    Saturation Ratio and Polarity

    2ndary Burden Test

    Conducted in 2 parts Part 1, 1A current injection

    Measure circuit burden Part 2, four-wire resistancemeasurement

    Measure secondary

    winding resistance Burden = part 1 + part 2

    TESTING INSTRUMENT

  • 7/27/2019 59270197 Module 3 Commissioning Instrument Transformers

    61/80

    10/5/2013 Module Three 61

    TESTING INSTRUMENT

    TRANSFORMERS

    Part 1: CT Secondary Circuit Burden Measurement

  • 7/27/2019 59270197 Module 3 Commissioning Instrument Transformers

    62/80

    TESTING INSTRUMENT

  • 7/27/2019 59270197 Module 3 Commissioning Instrument Transformers

    63/80

    10/5/2013 Module Three 63

    TESTING INSTRUMENT

    TRANSFORMERS

    Total burden calculation

    ZT = RCT + (RL + ZB)

    WhereZT = Total burden ()

    RCT = DC Winding resistance ()RL = Lead resistance ()ZB = Device impedance ()

    TESTING INSTRUMENT

  • 7/27/2019 59270197 Module 3 Commissioning Instrument Transformers

    64/80

    10/5/2013 Module Three 64

    TESTING INSTRUMENT

    TRANSFORMERS

    CT Testing

    Primary InsulationResistance

    Dielectric Withstand Secondary InsulationResistance

    Secondary Burden Saturation Ratio and Polarity

    Saturation Test

    Secondary winding excitationtest

    Primary open circuited Step voltage increase,current proportional

    Test for knee-point voltage Rapid rise is I-excitation 10% V = 50% I

    TESTING INSTRUMENT

  • 7/27/2019 59270197 Module 3 Commissioning Instrument Transformers

    65/80

    10/5/2013 Module Three 65

    TESTING INSTRUMENT

    TRANSFORMERS

    CT Saturation test

    TESTING INSTRUMENT

  • 7/27/2019 59270197 Module 3 Commissioning Instrument Transformers

    66/80

    10/5/2013 Module Three 66

    TESTING INSTRUMENT

    TRANSFORMERS

    CT Testing

    Primary InsulationResistance

    Dielectric Withstand Secondary InsulationResistance

    Secondary Burden Saturation Ratio and Polarity

    Ratio and Polarity test

    Secondary winding excited at1V per turn

    Primary open circuited H1-H2 compared to X1-X2 Phase measured, ratio

    calculated

    Phase difference 0 meanspolarity correct

    TESTING INSTRUMENT

  • 7/27/2019 59270197 Module 3 Commissioning Instrument Transformers

    67/80

    10/5/2013 Module Three 67

    TESTING INSTRUMENT

    TRANSFORMERS

    CT Ratio and Polarity Test

    TESTING INSTRUMENT

  • 7/27/2019 59270197 Module 3 Commissioning Instrument Transformers

    68/80

    10/5/2013 Module Three 68

    TESTING INSTRUMENT

    TRANSFORMERS

    CT Testing

    Primary InsulationResistance

    Dielectric Withstand Secondary InsulationResistance

    Secondary Burden Saturation Ratio and Polarity

    Ratio and Polarity test (ALT)

    Use individual meters, phaseangle and voltmeter

    Secondary winding excited at1V per turn

    Primary open circuited H1-H2 compared to X1-X2 Phase measured, ratio

    calculated

    Phase difference 0 meanspolarity correct

    TESTING INSTRUMENT

  • 7/27/2019 59270197 Module 3 Commissioning Instrument Transformers

    69/80

    10/5/2013 Module Three 69

    TESTING INSTRUMENT

    TRANSFORMERS

    CT Ratio and Polarity Test (alternate connections)

  • 7/27/2019 59270197 Module 3 Commissioning Instrument Transformers

    70/80

    TESTING INSTRUMENT

  • 7/27/2019 59270197 Module 3 Commissioning Instrument Transformers

    71/80

    10/5/2013 Module Three 71

    TESTING INSTRUMENT

    TRANSFORMERS

    VT Testing

    Insulation Resistance Dielectric Withstand

    Ratio and Polarity

    Insulation Resistance Test

    DC voltage test at the ratedcrest voltage

    3 tests HV to Gnd HV to LV LV to Gnd

  • 7/27/2019 59270197 Module 3 Commissioning Instrument Transformers

    72/80

    TESTING INSTRUMENT

  • 7/27/2019 59270197 Module 3 Commissioning Instrument Transformers

    73/80

    10/5/2013 Module Three 73

    TESTING INSTRUMENT

    TRANSFORMERS

    VT Testing

    Insulation Resistance Dielectric Withstand

    Ratio and Polarity

    Dielectric Withstand Test

    AC voltage test at the 75%factory test voltage

    Secondary grounded 1 minute test

    TESTING INSTRUMENT

  • 7/27/2019 59270197 Module 3 Commissioning Instrument Transformers

    74/80

    10/5/2013 Module Three 74

    TESTING INSTRUMENT

    TRANSFORMERS

    VT Dielectric Withstand Tests

    TESTING INSTRUMENT

  • 7/27/2019 59270197 Module 3 Commissioning Instrument Transformers

    75/80

    10/5/2013 Module Three 75

    TESTING INSTRUMENT

    TRANSFORMERS

    VT Testing

    Insulation Resistance Dielectric Withstand

    Ratio and Polarity

    Ratio and Polarity test

    Primary winding excited at1V per turns ratio

    Secondary open circuited X1-X2 compared to H1-H2 Phase measured, ratio

    calculated

    Phase difference 0 meanspolarity correct

    Compare ratio withnameplate

  • 7/27/2019 59270197 Module 3 Commissioning Instrument Transformers

    76/80

    10/5/2013 Module Three 76

    NETA STANDARD

    5. NETA Acceptance Testing Procedure

    5.1 Visual and Mechanical Inspection

    5.2 Electrical Test 5.2.1 Current Transformer

    5.2.2 Voltage Transformer

    5.3 Test Value Analysis

    5.3.1 Visual and Mechanical

    5.3.2 CT Electrical Test

    5.3.3 VT Electrical Test

  • 7/27/2019 59270197 Module 3 Commissioning Instrument Transformers

    77/80

    10/5/2013 Module Three 77

    TEST SET MANUAL

    Module 3: CT Tester

    Module 2:

    15 KV Insulation Resistance Test set AC High Potential Test set

    DC High Potential Test set

    Digital Low Resistance Test set

    S O S

  • 7/27/2019 59270197 Module 3 Commissioning Instrument Transformers

    78/80

    10/5/2013 Module Three 78

    TEST FORMS

    Current Transformer Test Form

    Voltage Transformer Test Form

  • 7/27/2019 59270197 Module 3 Commissioning Instrument Transformers

    79/80

    10/5/2013 Module Three 79

  • 7/27/2019 59270197 Module 3 Commissioning Instrument Transformers

    80/80


Recommended