Date post: | 01-Feb-2016 |
Category: |
Documents |
Upload: | gaurav-pundir |
View: | 11 times |
Download: | 0 times |
04/22/2023 1
Outline• Introduction• Current workflow• Project goal & methodology• Analytical study• Simulation study• Recommendation• Lessons learned• Acknowledgements• Q&A
1 2 3 4 5
Introduction
• University of Wisconsin Medical Foundation is the clinical practice organization for the faculty physicians of the UW School of Medicine and Public Health
• Provides medical and surgical services– Cancer, Neurology, Radiology, Transplant Services,
Trauma Surgery and many others
04/22/2023 2
1 2 3 4 5
Background
• CT Scanning (X-ray computed tomography)– A three-dimensional image of the inside of an
object is generated from a large series of two-dimensional X-ray images
– 19 different visit types, some requiring up to 4 studies
04/22/2023 3
1 2 3 4 5
Current state
• Two CT scanners available– New scanner with short scanning time– Old scanner for special studies, long scanning time
• Four technicians (14019) available– 1 tech (Tech A) operates the scanner– 2 techs (Tech B) escort and assist patients– 1 tech (Tech C) focus on scheduling, operates
the old scanner when necessary
04/22/2023 4
1 2 3 4 5
CT workflow
04/22/2023 5
IV
Reformatting
Image Review
Scanning
Preparation
1 2 3 4 5
Project goal and performance measures
• Goal– Recommend cost-saving changes for the CT
scanning process through improving the staffing model to accommodate existing and future CT workflow
• Performance Measures– Study Length of Stay (LOS)
• LOS1 for new scanner• LOS2 for old scanner
– Technician utilization
04/22/2023 6
04/22/2023 7
• PDCA (Plan, Do, Act, Check)• PSE (Parallel serial line with Exponential machines
with resources)
Process modeling Data collection Modeling and
analysis
ValidationWhat-If and sensitivity analysis
Recommendations
3 4 5
Methodology
1 2
04/22/2023 8
1 2 3 4 5
Analytical model
• Assisting patient changing and delivering paperwork not considered
04/22/2023 9
1 2 3 4 5
Simulation model
New scanner
Old scanner
Techs
04/22/2023 10
1 2 3 4 5
Input/Output
Arrival Wait IV Wait Preparation Scanning Image
ReviewImage
Reformat
Length of Stay (LOS)
Data point identification:
Cycle time for tech
04/22/2023 11
1 2 3 4 5
Data collection
• Method– Time study for 1 week– Average service times obtained from time study– Demand information obtained from patient visit
record of February and March
Time Point Optinal Staff Time Note1 Tech gets the patient from the front D 11:40:002 Tech takes patient to changing room v D 11:40:203 Tech picks up the patient from changing room v D 11:45:004 Tech starts IV test and screen v D 11:465 Tech completes IV test and screen v D 11:566 Tech and Patient arrive CT room D 11:56:307 Tech starts IV test and screen -8 Tech completes IV test and screen -9 Tech leaves the CT room and starts scanning K 12:03:00
10 Tech finishes the scanning and waits for image processing K 12:04:0011 Tech reformats the image for the previous patient -12 Tech completes reformatting for the previous patient -13 Reformatted image sent to the computer -14 Tech prints out the paper work to the radiologist -15 Image loading complete K 12:07:0016 Tech takes the patient out from CT room D 12:08:0017 Tech reformats the image for the current patient v K 12:07:3018 Tech completes reformatting for the current patient v K 17:08:4019 Reformatted image sent v K 12:11:0020 Tech prints out the paperwork to the radiologist -21 Tech sets up the CT machine for the next patient D 12:08-12:09
04/22/2023 12
1 2 3 4 5
Data analysis
• 44 patients observed• 75% of patients required IV• 36% of studies required manual image reformat• Inter-arrival time
– New scanner:20 min
• Avg. service time‐ IV time: 4 min‐ Preparation time: 1.6 min‐ Scanning time: 2.6 min‐ Image review time:3.6 min‐ Image reformat time: 3.2 min
• LOS1: 10.84 min
04/22/2023 13
• Errors are below 10%. Both models are validated.
1 2 3 4 5
Model validation & analytical results
Performance
measure
Analytical
Simulation
Collected data
Error (Analytica
l)
Error (Simulatio
n)
LOS1 (min) 11.64 11.33 10.84 7.38% 4.52%
Resource utilization Analytical Simulation
LOS1(min) 11.64 11.33
LOS2(min) 23.29 22.94
Utilization A (%)
40.0940.07
Utilization B (%)
19.1419.05
Utilization C(%)
4.714.48
Observation:Low utilization of
Tech B & C
4 5
Simulation model
• Purpose– Perform what-if analysis to evaluate the impact of
• Different staffing settings• Increasing demand
– Conduct sensitivity analysis to identify bottleneck operation
04/22/2023 14
1 2 3
4 5
What-If analysis
04/22/2023 15
• Staffing– Scenario 1: 1 A, 1 B, 1 C– Scenario 2: 1 A, 1 B
• Demand– Scenario 3: Increase demand by 10%– Scenario 4: Increase demand by 20%
• Combination– Scenario 5: combination of Scenario 1 and 4– Scenario 6: combination of Scenario 2 and 4
1 2 3
4 5
What-If (Staffing, Scenario 1)
04/22/2023 16
• 1 A, 1 B, 1 C: reduce the number of Tech B from 2 to 1 From To Impact
LOS1 (min) 11.33 11.56 1.98%
LOS2 (min) 22.94 23.13 0.85%
Utilization A (%) 40.07 40.07 0
Utilization B (%) 19.05 38.10 19.05
Utilization C (%) 4.48 4.48 0
• Impact on LOS is minimal• Utilization of Tech B doubles• Loss of flexibility, two scanners cannot be used at
the same time
1 2 3
4 5
What-If (Staffing, Scenario 2)
04/22/2023 17
• 1 A,1 B: Reduce the number of Tech B from 2 to 1; replace Tech C with a lower level scheduling assistant From To Impact
LOS1 (min) 11.33 12.08 6.57%
LOS2 (min) 22.94 23.63 3.05%
Utilization A (%) 40.07 44.55 4.48
Utilization B (%) 19.05 38.10 19.05
Utilization C (%) 4.48 0 -4.48
• LOS1 increases by less than 7%• Staff utilization increases
1 2 3
4 5
What-If (Demand, Scenario 3, 4)
04/22/2023 18
• Original demand• Increased demand: 10% (Scenario 3), 20% (Scenario
4)Original demand Scenario 3 Scenario 4
LOS1 (min) 11.33 11.64 12.28
LOS2 (min) 22.94 23.55 23.55
Utilization A (%) 40.07 44.37 49.83
Utilization B (%) 19.05 21.06 23.64
Utilization C (%) 4.48 4.89 5.57
• LOS increases by less than 9%• Staff utilization remains below 50%• System is capable of handling higher demand in the
future
1 2 3
4 5
What-If (Combination, Scenario 5)
04/22/2023 19
• Scenario 5: Reduce the number of Tech B from 2 to 1; increase demand by 20%
From To Impact
LOS1 (min) 11.33 13.31 17.45%
LOS2 (min) 22.94 24.50 6.79%
Utilization A (%) 40.07 49.83 9.76
Utilization B (%) 19.05 47.28 28.23
Utilization C (%) 4.48 5.57 1.09
• LOS1 increases more than 15%• Utilization of Tech A and B close to 50%
1 2 3
4 5
What-If (Combination, Scenario 6)
04/22/2023 20
• Scenario 6: Reduce the number of Tech B from 2 to 1; replace Tech C with a lower level scheduling assistant; increase demand by 20%
From To Impact
LOS1 (min) 11.33 14.65 19.27%
LOS2 (min) 22.94 26.24 11.44%
Utilization A (%) 40.07 55.40 15.33
Utilization B (%) 19.05 47.28 28.23
Utilization C (%) 4.48 0.00 -4.48
• LOS1 increases more than 19%• Utilization of Tech A over 50%
1 2 3
4 5
Sensitivity analysis – Bottleneck identification
04/22/2023 21
• Reduce service times by 10%– Scenario 1: IV time– Scenario 2: Preparation time– Scenario 3: Scanning time– Scenario 4: Image review time– Scenario 5: Image reformat time
Measure\Scenario 1 2 3 4 5
LOS1 (min) 10.97 11.16 11.03 10.89 11.31
LOS2 (min) 22.82 22.92 22.32 22.06 23.10
Utilization A (%) 39.63 39.99 38.70 38.20 39.43
Utilization B (%) 18.35 18.71 18.40 19.12 19.12
Utilization C (%) 4.47 4.48 4.36 4.31 4.45
Bottleneck operation
1 2 3
4 5
Final scenario
04/22/2023 22
• Reduce image review time by 50% by upgrading computer motherboard
• Combined with What-If Scenario 6 – 1 A, 1 B; increase demand by 20%
What-If Scenario 6 To Impact
LOS1 (min) 14.65 10.65 -27.30%
LOS2 (min) 26.24 19.32 -26.37%
Utilization A (%) 55.40 42.85 -12.55
Utilization B (%) 47.28 47.44 0.16
Utilization C (%) 0.00 0.00 0.00
• LOS can be reduced significantly
1 2 3
5
Cost savings
04/22/2023 23
Current Scenario
Improved Scenario
# $/year # $/year
Tech 14019 4 220,000 1 55,000
Tech 14010 - - 1 45,000
Scheduling Assistant - - 1 35,000
Total 4 220,000 3 135,000
Salary savings = 85,000 $/year
Total saving (including overhead, benefit) = 161,500 $/year
Note: Salary information obtained from www.salary.com
1 2 3 4
1 2 5
Conclusions
• Low staff utilization in current system
04/22/2023 24
3 4
Reduce the number of Tech B to 1, and replace Tech C with a lower level scheduling assistant
Slight impact on LOS, staff utilization increases
But if demand increases 20%LOS increases significantly
Reduce image review time by half LOS decreases from 14.6 to 10.65 (min)
Potential total cost savings of $161,500/year can be achieved
1 2 3
Lessons Learned
• Top management support is important• Need of understanding the system:
continuous learning • Difficulties to obtain data: unavailable,
hard to collect
04/22/2023 25
4 5
Questions?
04/22/2023 26