+ All Categories
Home > Documents > 615 Presentation CT Staffing Analysis

615 Presentation CT Staffing Analysis

Date post: 01-Feb-2016
Category:
Upload: gaurav-pundir
View: 11 times
Download: 0 times
Share this document with a friend
Description:
Production system engineering.
Popular Tags:
26
Outline Introduction Current workflow Project goal & methodology Analytical study Simulation study Recommendation Lessons learned Acknowledgements Q&A 06/16/2022 1
Transcript
Page 1: 615 Presentation CT Staffing Analysis

04/22/2023 1

Outline• Introduction• Current workflow• Project goal & methodology• Analytical study• Simulation study• Recommendation• Lessons learned• Acknowledgements• Q&A

Page 2: 615 Presentation CT Staffing Analysis

1 2 3 4 5

Introduction

• University of Wisconsin Medical Foundation is the clinical practice organization for the faculty physicians of the UW School of Medicine and Public Health

• Provides medical and surgical services– Cancer, Neurology, Radiology, Transplant Services,

Trauma Surgery and many others

04/22/2023 2

Page 3: 615 Presentation CT Staffing Analysis

1 2 3 4 5

Background

• CT Scanning (X-ray computed tomography)– A three-dimensional image of the inside of an

object is generated from a large series of two-dimensional X-ray images

– 19 different visit types, some requiring up to 4 studies

04/22/2023 3

Page 4: 615 Presentation CT Staffing Analysis

1 2 3 4 5

Current state

• Two CT scanners available– New scanner with short scanning time– Old scanner for special studies, long scanning time

• Four technicians (14019) available– 1 tech (Tech A) operates the scanner– 2 techs (Tech B) escort and assist patients– 1 tech (Tech C) focus on scheduling, operates

the old scanner when necessary

04/22/2023 4

Page 5: 615 Presentation CT Staffing Analysis

1 2 3 4 5

CT workflow

04/22/2023 5

IV

Reformatting

Image Review

Scanning

Preparation

Page 6: 615 Presentation CT Staffing Analysis

1 2 3 4 5

Project goal and performance measures

• Goal– Recommend cost-saving changes for the CT

scanning process through improving the staffing model to accommodate existing and future CT workflow

• Performance Measures– Study Length of Stay (LOS)

• LOS1 for new scanner• LOS2 for old scanner

– Technician utilization

04/22/2023 6

Page 7: 615 Presentation CT Staffing Analysis

04/22/2023 7

• PDCA (Plan, Do, Act, Check)• PSE (Parallel serial line with Exponential machines

with resources)

Process modeling Data collection Modeling and

analysis

ValidationWhat-If and sensitivity analysis

Recommendations

3 4 5

Methodology

1 2

Page 8: 615 Presentation CT Staffing Analysis

04/22/2023 8

1 2 3 4 5

Analytical model

• Assisting patient changing and delivering paperwork not considered

Page 9: 615 Presentation CT Staffing Analysis

04/22/2023 9

1 2 3 4 5

Simulation model

New scanner

Old scanner

Techs

Page 10: 615 Presentation CT Staffing Analysis

04/22/2023 10

1 2 3 4 5

Input/Output

Arrival Wait IV Wait Preparation Scanning Image

ReviewImage

Reformat

Length of Stay (LOS)

Data point identification:

Cycle time for tech

Page 11: 615 Presentation CT Staffing Analysis

04/22/2023 11

1 2 3 4 5

Data collection

• Method– Time study for 1 week– Average service times obtained from time study– Demand information obtained from patient visit

record of February and March

Time Point Optinal Staff Time Note1 Tech gets the patient from the front D 11:40:002 Tech takes patient to changing room v D 11:40:203 Tech picks up the patient from changing room v D 11:45:004 Tech starts IV test and screen v D 11:465 Tech completes IV test and screen v D 11:566 Tech and Patient arrive CT room D 11:56:307 Tech starts IV test and screen -8 Tech completes IV test and screen -9 Tech leaves the CT room and starts scanning K 12:03:00

10 Tech finishes the scanning and waits for image processing K 12:04:0011 Tech reformats the image for the previous patient -12 Tech completes reformatting for the previous patient -13 Reformatted image sent to the computer -14 Tech prints out the paper work to the radiologist -15 Image loading complete K 12:07:0016 Tech takes the patient out from CT room D 12:08:0017 Tech reformats the image for the current patient v K 12:07:3018 Tech completes reformatting for the current patient v K 17:08:4019 Reformatted image sent v K 12:11:0020 Tech prints out the paperwork to the radiologist -21 Tech sets up the CT machine for the next patient D 12:08-12:09

Page 12: 615 Presentation CT Staffing Analysis

04/22/2023 12

1 2 3 4 5

Data analysis

• 44 patients observed• 75% of patients required IV• 36% of studies required manual image reformat• Inter-arrival time

– New scanner:20 min

• Avg. service time‐ IV time: 4 min‐ Preparation time: 1.6 min‐ Scanning time: 2.6 min‐ Image review time:3.6 min‐ Image reformat time: 3.2 min

• LOS1: 10.84 min

Page 13: 615 Presentation CT Staffing Analysis

04/22/2023 13

• Errors are below 10%. Both models are validated.

1 2 3 4 5

Model validation & analytical results

Performance

measure

Analytical

Simulation

Collected data

Error (Analytica

l)

Error (Simulatio

n)

LOS1 (min) 11.64 11.33 10.84 7.38% 4.52%

Resource utilization Analytical Simulation

LOS1(min) 11.64 11.33

LOS2(min) 23.29 22.94

Utilization A (%)

40.0940.07

Utilization B (%)

19.1419.05

Utilization C(%)

4.714.48

Observation:Low utilization of

Tech B & C

Page 14: 615 Presentation CT Staffing Analysis

4 5

Simulation model

• Purpose– Perform what-if analysis to evaluate the impact of

• Different staffing settings• Increasing demand

– Conduct sensitivity analysis to identify bottleneck operation

04/22/2023 14

1 2 3

Page 15: 615 Presentation CT Staffing Analysis

4 5

What-If analysis

04/22/2023 15

• Staffing– Scenario 1: 1 A, 1 B, 1 C– Scenario 2: 1 A, 1 B

• Demand– Scenario 3: Increase demand by 10%– Scenario 4: Increase demand by 20%

• Combination– Scenario 5: combination of Scenario 1 and 4– Scenario 6: combination of Scenario 2 and 4

1 2 3

Page 16: 615 Presentation CT Staffing Analysis

4 5

What-If (Staffing, Scenario 1)

04/22/2023 16

• 1 A, 1 B, 1 C: reduce the number of Tech B from 2 to 1 From To Impact

LOS1 (min) 11.33 11.56 1.98%

LOS2 (min) 22.94 23.13 0.85%

Utilization A (%) 40.07 40.07 0

Utilization B (%) 19.05 38.10 19.05

Utilization C (%) 4.48 4.48 0

• Impact on LOS is minimal• Utilization of Tech B doubles• Loss of flexibility, two scanners cannot be used at

the same time

1 2 3

Page 17: 615 Presentation CT Staffing Analysis

4 5

What-If (Staffing, Scenario 2)

04/22/2023 17

• 1 A,1 B: Reduce the number of Tech B from 2 to 1; replace Tech C with a lower level scheduling assistant From To Impact

LOS1 (min) 11.33 12.08 6.57%

LOS2 (min) 22.94 23.63 3.05%

Utilization A (%) 40.07 44.55 4.48

Utilization B (%) 19.05 38.10 19.05

Utilization C (%) 4.48 0 -4.48

• LOS1 increases by less than 7%• Staff utilization increases

1 2 3

Page 18: 615 Presentation CT Staffing Analysis

4 5

What-If (Demand, Scenario 3, 4)

04/22/2023 18

• Original demand• Increased demand: 10% (Scenario 3), 20% (Scenario

4)Original demand Scenario 3 Scenario 4

LOS1 (min) 11.33 11.64 12.28

LOS2 (min) 22.94 23.55 23.55

Utilization A (%) 40.07 44.37 49.83

Utilization B (%) 19.05 21.06 23.64

Utilization C (%) 4.48 4.89 5.57

• LOS increases by less than 9%• Staff utilization remains below 50%• System is capable of handling higher demand in the

future

1 2 3

Page 19: 615 Presentation CT Staffing Analysis

4 5

What-If (Combination, Scenario 5)

04/22/2023 19

• Scenario 5: Reduce the number of Tech B from 2 to 1; increase demand by 20%

From To Impact

LOS1 (min) 11.33 13.31 17.45%

LOS2 (min) 22.94 24.50 6.79%

Utilization A (%) 40.07 49.83 9.76

Utilization B (%) 19.05 47.28 28.23

Utilization C (%) 4.48 5.57 1.09

• LOS1 increases more than 15%• Utilization of Tech A and B close to 50%

1 2 3

Page 20: 615 Presentation CT Staffing Analysis

4 5

What-If (Combination, Scenario 6)

04/22/2023 20

• Scenario 6: Reduce the number of Tech B from 2 to 1; replace Tech C with a lower level scheduling assistant; increase demand by 20%

From To Impact

LOS1 (min) 11.33 14.65 19.27%

LOS2 (min) 22.94 26.24 11.44%

Utilization A (%) 40.07 55.40 15.33

Utilization B (%) 19.05 47.28 28.23

Utilization C (%) 4.48 0.00 -4.48

• LOS1 increases more than 19%• Utilization of Tech A over 50%

1 2 3

Page 21: 615 Presentation CT Staffing Analysis

4 5

Sensitivity analysis – Bottleneck identification

04/22/2023 21

• Reduce service times by 10%– Scenario 1: IV time– Scenario 2: Preparation time– Scenario 3: Scanning time– Scenario 4: Image review time– Scenario 5: Image reformat time

Measure\Scenario 1 2 3 4 5

LOS1 (min) 10.97 11.16 11.03 10.89 11.31

LOS2 (min) 22.82 22.92 22.32 22.06 23.10

Utilization A (%) 39.63 39.99 38.70 38.20 39.43

Utilization B (%) 18.35 18.71 18.40 19.12 19.12

Utilization C (%) 4.47 4.48 4.36 4.31 4.45

Bottleneck operation

1 2 3

Page 22: 615 Presentation CT Staffing Analysis

4 5

Final scenario

04/22/2023 22

• Reduce image review time by 50% by upgrading computer motherboard

• Combined with What-If Scenario 6 – 1 A, 1 B; increase demand by 20%

What-If Scenario 6 To Impact

LOS1 (min) 14.65 10.65 -27.30%

LOS2 (min) 26.24 19.32 -26.37%

Utilization A (%) 55.40 42.85 -12.55

Utilization B (%) 47.28 47.44 0.16

Utilization C (%) 0.00 0.00 0.00

• LOS can be reduced significantly

1 2 3

Page 23: 615 Presentation CT Staffing Analysis

5

Cost savings

04/22/2023 23

Current Scenario

Improved Scenario

# $/year # $/year

Tech 14019 4 220,000 1 55,000

Tech 14010 - - 1 45,000

Scheduling Assistant - - 1 35,000

Total 4 220,000 3 135,000

Salary savings = 85,000 $/year

Total saving (including overhead, benefit) = 161,500 $/year

Note: Salary information obtained from www.salary.com

1 2 3 4

Page 24: 615 Presentation CT Staffing Analysis

1 2 5

Conclusions

• Low staff utilization in current system

04/22/2023 24

3 4

Reduce the number of Tech B to 1, and replace Tech C with a lower level scheduling assistant

Slight impact on LOS, staff utilization increases

But if demand increases 20%LOS increases significantly

Reduce image review time by half LOS decreases from 14.6 to 10.65 (min)

Potential total cost savings of $161,500/year can be achieved

Page 25: 615 Presentation CT Staffing Analysis

1 2 3

Lessons Learned

• Top management support is important• Need of understanding the system:

continuous learning • Difficulties to obtain data: unavailable,

hard to collect

04/22/2023 25

4 5

Page 26: 615 Presentation CT Staffing Analysis

Questions?

04/22/2023 26


Recommended