7 - Manufacturing Resource Planning Dr. Ron Tibben-Lembke pp. 222-234, 236-7, 240
Transcript
Page 1: 7 - Manufacturing Resource Planning Dr. Ron Tibben-Lembke pp. 222-234, 236-7, 240.

7 - Manufacturing Resource Planning

Dr. Ron Tibben-Lembke

pp. 222-234, 236-7, 240

Page 2: 7 - Manufacturing Resource Planning Dr. Ron Tibben-Lembke pp. 222-234, 236-7, 240.

How do we

System for organizing WIP releases Consider LT for each item Look at BOM to see what parts needed Release so they will arrive just as needed

Example Figure 7.2 Order quantity is 50 units LT is one week I’ve added “Net requirements” and “scheduled

releases” rows to Figure for clarity

Page 3: 7 - Manufacturing Resource Planning Dr. Ron Tibben-Lembke pp. 222-234, 236-7, 240.

Fig 7.2

1 2 3 4 5

Gross Requirements 10 40 10

Scheduled receipts (begin) 50

Projected Available Balance (ending) 4

54

44

44

4

Net Requirements 6

Planned Order Receipts

Planned Order Releases

6 units short

Page 4: 7 - Manufacturing Resource Planning Dr. Ron Tibben-Lembke pp. 222-234, 236-7, 240.

Fig 7.2

1 2 3 4 5

Gross Requirements 10 40 10

Scheduled receipts (begin) 50

Projected Available Balance (ending) 4

54

44

44

4

Net Requirements 6

Planned Order Receipts 50

Planned Order Releases 50

Order 50 units week earlier

Page 5: 7 - Manufacturing Resource Planning Dr. Ron Tibben-Lembke pp. 222-234, 236-7, 240.

Fig 7.2

1 2 3 4 5

Gross Requirements 10 40 10

Scheduled receipts (begin) 50

Projected Available Balance (ending) 4

54

44

44

4

44

Net Requirements 6

Planned Order Receipts 50

Planned Order Releases 50

Ending inventory

Page 6: 7 - Manufacturing Resource Planning Dr. Ron Tibben-Lembke pp. 222-234, 236-7, 240.

Terminology

Projected Available balance Not on-hand (that may be greater) Tells how many will be available (in ATP sense)

Planned order releases ≠ scheduled receipts Only when material has been committed to their

production Move to scheduled receipts as late as possible Preserves flexibility

Page 7: 7 - Manufacturing Resource Planning Dr. Ron Tibben-Lembke pp. 222-234, 236-7, 240.

Figure 7.3 1605 Snow Shovel

1605 Snow Shovel

048Scoop-shaftconnector

13122 Top Handle Assy314 scoop assembly

118 Shaft (wood)

062 Nail (4)

14127 Rivet (4)

Page 8: 7 - Manufacturing Resource Planning Dr. Ron Tibben-Lembke pp. 222-234, 236-7, 240.

314 scoop assembly

314 scoop assembly

14127 Rivet (6)019 Blade (steel)

2142 Scoop (aluminum)

Page 9: 7 - Manufacturing Resource Planning Dr. Ron Tibben-Lembke pp. 222-234, 236-7, 240.

13122 Top Handle Assembly

1118Top handle

Coupling (steel)

11495 WeldedTop handle bracket

Assembly

13122 Top Handle Assembly

457 Top handle(wood)

129 Top HandleBracket (steel)

082 Nail (2)

Page 10: 7 - Manufacturing Resource Planning Dr. Ron Tibben-Lembke pp. 222-234, 236-7, 240.

BOM Explosion

Process of translating net requirements into components part requirementsTake into account existing inventoriesConsider also scheduled receipts

Page 11: 7 - Manufacturing Resource Planning Dr. Ron Tibben-Lembke pp. 222-234, 236-7, 240.

BOM Explosion Example

Need to make 100 shovelsWe are responsible for handle

assemblies.

Page 12: 7 - Manufacturing Resource Planning Dr. Ron Tibben-Lembke pp. 222-234, 236-7, 240.

13122 Top Handle Assembly

1118Top handle

Coupling (steel)

11495 WeldedTop handle bracket

Assembly

13122 Top Handle Assembly

457 Top handle(wood)

129 Top HandleBracket (steel)

082 Nail (2)

Page 13: 7 - Manufacturing Resource Planning Dr. Ron Tibben-Lembke pp. 222-234, 236-7, 240.

Net Requirements

Sch Gross NetPart Description Inv Rec Req ReqTop handle assy 25 -- 100 75

Top handle 22 25Nail (2 required) 4 50Bracket Assy 27 --

Top bracket 15 --Top coupling 39 15

Page 14: 7 - Manufacturing Resource Planning Dr. Ron Tibben-Lembke pp. 222-234, 236-7, 240.

Figure 7.5

Sch Gross NetPart Description Inv Rec Req ReqTop handle assy 25 -- 100 75

Top handle 22 25 75 28Nail (2 required) 4 50 150 96Bracket Assy 27 -- 75 48

Top bracket 15 --Top coupling 39 15

Page 15: 7 - Manufacturing Resource Planning Dr. Ron Tibben-Lembke pp. 222-234, 236-7, 240.

13122 Top Handle Assembly

1118Top handle

Coupling (steel)

11495 WeldedTop handle bracket

Assembly

13122 Top Handle Assembly

457 Top handle(wood)

129 Top HandleBracket (steel)

082 Nail (2)

Page 16: 7 - Manufacturing Resource Planning Dr. Ron Tibben-Lembke pp. 222-234, 236-7, 240.

Figure 7.5

Sch Gross NetPart Description Inv Rec Req ReqTop handle assy 25 -- 100 75

Top handle 22 25 75 28Nail (2 required) 4 50 150 96Bracket Assy 27 -- 75 48

Top bracket 15 -- 48 33Top coupling 39 15 48 --

Page 17: 7 - Manufacturing Resource Planning Dr. Ron Tibben-Lembke pp. 222-234, 236-7, 240.

Timing of Production

This tells us how many of each we needDoesn’t tell when to startStart as soon as possible?Dependent events (oh no, not that!)Front schedule Cutting approach (Fig. 7.6)Back schedule Fig. 7.7

Page 18: 7 - Manufacturing Resource Planning Dr. Ron Tibben-Lembke pp. 222-234, 236-7, 240.

Fig 7.8 – 13122 Top Handle Assy

13122 Top handle LT = 2

1

2

3

4

5

6

7

8

9

10

Gross Req 20 10 20 5 35 10

Sch receipts

Proj. Avail Bal (ending)

25

25

5

5

Net Req 5

Pl Order Rec 5

Pl Order Rel 5

p. 233

Page 19: 7 - Manufacturing Resource Planning Dr. Ron Tibben-Lembke pp. 222-234, 236-7, 240.

Fig 7.8 – 13122 Top Handle Assy-2

13122 Top handle LT = 2

1

2

3

4

5

6

7

8

9

10

Gross Req 20 10 20 5 35 10

Sch receipts

Proj. Avail Bal (ending)

25

25

5

5

0

0

0

0

0

0

0

Net Req 5 20 35 10

Pl Order Rec 5 20 35 10

Pl Order Rel 5 20 35 10

Page 20: 7 - Manufacturing Resource Planning Dr. Ron Tibben-Lembke pp. 222-234, 236-7, 240.

Fig 7.8 – 13122 Top Handle Assy -3

13122 Top handle LT = 2

1

2

3

4

5

6

7

8

9

10

Gross Req 20 10 20 5 35 10

Sch receipts

Proj. Avail Bal (ending)

25

25

5

5

0

0

0

0

0

0

0

Net Req 5 20 5 35 10

Pl Order Rec 5 20 5 35 10

Pl Order Rel 5 20 5 35 10

Page 21: 7 - Manufacturing Resource Planning Dr. Ron Tibben-Lembke pp. 222-234, 236-7, 240.

457 Top Handle

13122 Top handle LT = 2

1

2

3

4

5

6

7

8

9

10

Gross Req 20 10 20 5 35 10

Sch receipts

Proj. Avail Bal (ending)

25

25

5

5

0

0

0

0

0

0

0

Net Req 5 20 5 35 10

Pl Order Rec 5 20 5 35 10

Pl Order Rel 5 20 5 35 10

LT = 2

1

2

3

4

5

6

7

8

9

10

Gross Req 5 20 5 35 10

Sch receipts 25

Proj. Avail Bal (ending)

22

22

Net Req

Pl Order Rec

Pl Order Rel

One handle forEach assembly

Page 22: 7 - Manufacturing Resource Planning Dr. Ron Tibben-Lembke pp. 222-234, 236-7, 240.

457 Top Handle

LT = 2

1

2

3

4

5

6

7

8

9

10

Gross Req 5 20 5 35 10

Sch receipts 25

Proj. Avail Bal (ending)

22

22

17

Net Req

Pl Order Rec

Pl Order Rel

Page 23: 7 - Manufacturing Resource Planning Dr. Ron Tibben-Lembke pp. 222-234, 236-7, 240.

457 Top Handle

LT = 2

1

2

3

4

5

6

7

8

9

10

Gross Req 5 20 5 35 10

Sch receipts 25

Proj. Avail Bal (ending)

22

22

17

42

22

17

17

Net Req 18 10

Pl Order Rec 18 10

Pl Order Rel 18 10

Page 24: 7 - Manufacturing Resource Planning Dr. Ron Tibben-Lembke pp. 222-234, 236-7, 240.

082 Nail (2 required)

LT = 1 Lot Size = 50

1

2

3

4

5

6

7

8

9

10

Gross Req 10 40 10 70 20

Sch receipts 50

Proj. Avail Bal (ending)

4

54

Net Req

Pl Order Rec

Pl Order Rel

13122 Top handle LT = 2

1

2

3

4

5

6

7

8

9

10

Gross Req 20 10 20 5 35 10

Sch receipts

Proj. Avail Bal (ending)

25

25

5

5

0

0

0

0

0

0

0

Net Req 5 20 5 35 10

Pl Order Rec 5 20 5 35 10

Pl Order Rel 5 20 5 35 10

Two nails forEach assembly

Page 25: 7 - Manufacturing Resource Planning Dr. Ron Tibben-Lembke pp. 222-234, 236-7, 240.

082 Nail (2 required)

LT = 1 Lot Size = 50

1

2

3

4

5

6

7

8

9

10

Gross Req 10 40 10 70 20

Sch receipts 50

Proj. Avail Bal (ending)

4

54

44

44

4

Net Req 6

Pl Order Rec 50

Pl Order Rel 50

Page 26: 7 - Manufacturing Resource Planning Dr. Ron Tibben-Lembke pp. 222-234, 236-7, 240.

082 Nail (2 required)

LT = 1 Lot Size = 50

1

2

3

4

5

6

7

8

9

10

Gross Req 10 40 10 70 20

Sch receipts 50

Proj. Avail Bal (ending)

4

54

44

44

4

44

Net Req 6 26 20

Pl Order Rec 50

Pl Order Rel 50

Page 27: 7 - Manufacturing Resource Planning Dr. Ron Tibben-Lembke pp. 222-234, 236-7, 240.

082 Nail (2 required)

LT = 1 Lot Size = 50

1

2

3

4

5

6

7

8

9

10

Gross Req 10 40 10 70 20

Sch receipts 50

Proj. Avail Bal (ending)

4

54

44

44

4

44

44

24

4

4

4

Net Req 6 26

Pl Order Rec 50 50

Pl Order Rel 50

Page 28: 7 - Manufacturing Resource Planning Dr. Ron Tibben-Lembke pp. 222-234, 236-7, 240.

11495 Bracket Assembly

13122 Top handle LT = 2

1

2

3

4

5

6

7

8

9

10

Gross Req 20 10 20 5 35 10

Sch receipts

Proj. Avail Bal (ending)

25

25

5

5

0

0

0

0

0

0

0

Net Req 5 20 5 35 10

Pl Order Rec 5 20 5 35 10

Pl Order Rel 5 20 5 35 10

LT = 2

1

2

3

4

5

6

7

8

9

10

Gross Req

Sch receipts

Proj. Avail Bal (ending)

27

Net Req

Pl Order Rec

Pl Order Rel

One bracket forEach assembly

Page 29: 7 - Manufacturing Resource Planning Dr. Ron Tibben-Lembke pp. 222-234, 236-7, 240.

11495 Bracket Assembly

13122 Top handle LT = 2

1

2

3

4

5

6

7

8

9

10

Gross Req 20 10 20 5 35 10

Sch receipts

Proj. Avail Bal (ending)

25

25

5

5

0

0

0

0

0

0

0

Net Req 5 20 5 35 10

Pl Order Rec 5 20 5 35 10

Pl Order Rel 5 20 5 35 10

LT = 2

1

2

3

4

5

6

7

8

9

10

Gross Req 5

Sch receipts

Proj. Avail Bal (ending)

27

Net Req

Pl Order Rec

Pl Order Rel

One bracket forEach assembly

Page 30: 7 - Manufacturing Resource Planning Dr. Ron Tibben-Lembke pp. 222-234, 236-7, 240.

11495 Bracket Assembly

13122 Top handle LT = 2

1

2

3

4

5

6

7

8

9

10

Gross Req 20 10 20 5 35 10

Sch receipts

Proj. Avail Bal (ending)

25

25

5

5

0

0

0

0

0

0

0

Net Req 5 20 5 35 10

Pl Order Rec 5 20 5 35 10

Pl Order Rel 5 20 5 35 10

LT = 2

1

2

3

4

5

6

7

8

9

10

Gross Req 5 20 5 35 10

Sch receipts

Proj. Avail Bal (ending)

27

Net Req

Pl Order Rec

Pl Order Rel

One bracket forEach assembly

Page 31: 7 - Manufacturing Resource Planning Dr. Ron Tibben-Lembke pp. 222-234, 236-7, 240.

11495 Bracket Assembly

LT = 2

1

2

3

4

5

6

7

8

9

10

Gross Req 5 20 5 35 10

Sch receipts

Proj. Avail Bal (ending)

27

22

22

2

Net Req 3 35 10

Pl Order Rec 3 35 10

Pl Order Rel 3 35 10

Page 32: 7 - Manufacturing Resource Planning Dr. Ron Tibben-Lembke pp. 222-234, 236-7, 240.

129 Top Bracket

LT = 1

1

2

3

4

5

6

7

8

9

10

Gross Req 3 35 10

Sch receipts

Proj. Avail Bal (ending)

15

Net Req

Pl Order Rec

Pl Order Rel

LT = 2

1

2

3

4

5

6

7

8

9

10

Gross Req 5 20 5 35 10

Sch receipts

Proj. Avail Bal (ending)

27

22

22

2

Net Req 3 35 10

Pl Order Rec 3 35 10

Pl Order Rel 3 35 10

Page 33: 7 - Manufacturing Resource Planning Dr. Ron Tibben-Lembke pp. 222-234, 236-7, 240.

129 Top handle bracket

LT = 1

1

2

3

4

5

6

7

8

9

10

Gross Req 3 35 10

Sch receipts

Proj. Avail Bal (ending)

15

15

15

12

12

Net Req 23 10

Pl Order Rec 23 10

Pl Order Rel 23 10

Page 34: 7 - Manufacturing Resource Planning Dr. Ron Tibben-Lembke pp. 222-234, 236-7, 240.

1118 Top handle coupling

LT = 3 Safety Stock = 20

1

2

3

4

5

6

7

8

9

10

Gross Req 3 35 10

Sch receipts

Proj. Avail Bal (ending)

39

Net Req

Pl Order Rec

Pl Order Rel

LT = 2

1

2

3

4

5

6

7

8

9

10

Gross Req 5 20 5 35 10

Sch receipts

Proj. Avail Bal (ending)

27

22

22

2

Net Req 3 35 10

Pl Order Rec 3 35 10

Pl Order Rel 3 35 10

Page 35: 7 - Manufacturing Resource Planning Dr. Ron Tibben-Lembke pp. 222-234, 236-7, 240.

1118 Top handle coupling

LT = 3 Safety Stock = 20

1

2

3

4

5

6

7

8

9

10

Gross Req 3 35 10

Sch receipts 15

Proj. Avail Bal (ending)

39

39

54

51

51

16

Net Req 4

Pl Order Rec 4

Pl Order Rel 4

Page 36: 7 - Manufacturing Resource Planning Dr. Ron Tibben-Lembke pp. 222-234, 236-7, 240.

1118 Top handle coupling

LT = 3 Safety Stock = 20

1

2

3

4

5

6

7

8

9

10

Gross Req 3 35 10

Sch receipts 15

Proj. Avail Bal (ending)

39

39

54

51

51

20

20

20

20

20

20

Net Req 4 10

Pl Order Rec 4 10

Pl Order Rel 4 10

Page 37: 7 - Manufacturing Resource Planning Dr. Ron Tibben-Lembke pp. 222-234, 236-7, 240.

Other considerations

Safety stock if uncertainty in demand or supply quantity Don’t let available go down to 0

Safety LT if uncertainty in arrival time of supplyPlace order earlier than necessary

Order quantitiesEOQ, Lot-For-Lot, Periodic Order quantity,

more to come in ch. 14

Page 38: 7 - Manufacturing Resource Planning Dr. Ron Tibben-Lembke pp. 222-234, 236-7, 240.

Homework

DQ: 3, 7Problems: 3,5,6,7


Recommended