ENVIRONMENTAL RESOURCES MANAGEMENT CASTLE PEAK POWER COMPANY LIMITED
0308057_S7_WATER_REV 3.DOCX APRIL 2016
7-1
7 WATER QUALITY
7.1 INTRODUCTION
This Section presents an evaluation of the potential water quality impacts
from the construction and operation of the proposed additional CCGT units at
the BPPS. Mathematical modelling has been used to predict potential
impacts to water quality, the results of which have then been assessed with
reference to the relevant environmental legislation, standards and tolerance
criteria.
7.2 RELEVANT LEGISLATION & GUIDELINES
The following legislation and relevant guidance or non-statutory guidelines
are applicable to the evaluation of water quality impacts associated with the
construction and operation of the Project:
Water Pollution Control Ordinance (WPCO);
Technical Memorandum for Effluents Discharged into Drainage and Sewerage
Systems, Inland and Coastal Waters (TM- ICW);
Environmental Impact Assessment Ordinance (EIAO) and the Technical
Memorandum on EIA Process (EIAO-TM), Annexes 6 and 14; and
Practice Note for Professional Persons, Construction Site Drainage (ProPECC
PN1/94).; and
Town Planning Board Guidelines for Application for Developments within Deep
Bay Area under Section 16 of the Town Planning Ordinance (TPB PG-No.
12C).
7.2.1 Water Pollution Control Ordinance (WPCO)
The Water Pollution Control Ordinance (WPCO) is the primary legislation for the
control of water pollution and water quality in Hong Kong. Under the
WPCO, Hong Kong waters are divided into 10 Water Control Zones (WCZs).
Each WCZ has a designated set of statutory Water Quality Objectives (WQO).
The proposed Project is located close to the boundary between the Deep Bay
WCZ and North Western WCZ. Location of the additional CCGT units is
shown in Figure 3.1. The applicable WQOs for these two WCZs are
presented below in Table 7.1.
ENVIRONMENTAL RESOURCES MANAGEMENT CASTLE PEAK POWER COMPANY LIMITED
0308057_S7_WATER_REV 3.DOCX APRIL 2016
7-2
Table 7.1 Water Quality Objectives Applicable to this Water Quality Impact Assessment
Water Quality Objective Deep Bay WCZ North Western WCZ
A. AESTHETIC APPEARANCE
a) Waste discharges shall cause no objectionable odours or discolouration of the water.
Whole zone
Whole zone (including North Western Supplementary Zone)
b) Tarry residues, floating wood, articles made of glass, plastic, rubber or of any
other substances should be absent.
Whole zone Whole zone (including North Western
Supplementary Zone)
c) Mineral oil should not be visible on the surface. Surfactants should not give
rise to a lasting foam.
Whole zone Whole zone (including North Western
Supplementary Zone)
d) There should be no recognisable sewage-derived debris. Whole zone Whole zone (including North Western Supplementary Zone)
e) Floating, submerged and semi-submerged objects of a size likely to interfere with the free movement of vessels, or cause damage to vessels, should be
absent.
Whole zone Whole zone
(including North Western Supplementary Zone)
f) Waste discharges shall not cause the water to contain substances which settle to form objectionable deposits.
Whole zone Whole zone
(including North Western Supplementary
Zone)
B. BACTERIA
a) The level of Escherichia coli should not exceed 610 per 100 mL, calculated as
the geometric mean of all samples collected in one calendar year.
Secondary Contact Recreation Subzone and
Mariculture Subzone
Secondary Contact Recreation Subzone and
North Western Supplementary Zone
b) The level of Escherichia coli should not exceed 180 per 100 mL, calculated as
the geometric mean of all samples collected from March to October inclusive in one calendar year. Samples should be taken at least 3 times in a calendar
month at intervals of between 3 and 14 days.
Yung Long Bathing Beach Subzone
Bathing Beach Subzone
D. DISSOLVED OXYGEN
a) Waste discharges shall not cause the level of dissolved oxygen to fall below 4
mg per litre for 90% of the sampling occasions during the year; values should be taken at 1 metre below surface.
Inner Marine Subzone excepting Mariculture
Subzone
-
b) Waste discharges shall not cause the level of dissolved oxygen to fall below 4 mg per litre for 90% of the sampling occasions during the year; values should be calculated as water column average. In addition, the concentration of
dissolved oxygen should not be less than 2 mg per litre within 2 metres of the seabed for 90% of the sampling occasions during the year.
Outer Marine Subzone excepting Mariculture Subzone (water column average specified as arithmetic mean of at least 2 measurements at
1 metre below surface and 1 metre above seabed)
Marine Waters (water column average specified as arithmetic mean of at least 3 measurements at 1 metre below surface, mid-
depth and 1 metre above seabed); and North Western Supplementary Zone
c) The dissolved oxygen level should not be less than 5 mg per litre for 90% of
the sampling occasions during the year; values should be taken at 1 metre below surface.
Mariculture Subzone
-
E. pH
ENVIRONMENTAL RESOURCES MANAGEMENT CASTLE PEAK POWER COMPANY LIMITED
0308057_S7_WATER_REV 3.DOCX APRIL 2016
7-3
Water Quality Objective Deep Bay WCZ North Western WCZ
a) The pH of the water should be within the range of 6.5 - 8.5 units. In addition, waste discharges shall not cause the natural pH range to be
extended by more than 0.2 units.
Marine waters excepting Yung Long Bathing Beach Subzone
Marine waters (including North Western Supplementary Zone)
excepting Bathing Beach Subzones
b) The pH of the water should be within the range of 6.0 - 9.0 units for 95% of samples. In addition, waste discharges shall not cause the natural pH range
to be extended by more than 0.5 units.
Yung Long Bathing Beach Subzone
Bathing Beach Subzones
F. TEMPERATURE
Waste discharges shall not cause the natural daily temperature range to change by more than 2.0 °C.
Whole zone Whole zone (including North Western Supplementary Zone)
G. SALINITY
Waste discharges shall not cause the natural ambient salinity level to change by
more than 10%.
Whole zone Whole zone (including North Western
Supplementary Zone)
H. SUSPENDED SOLIDS
a) Waste discharges shall neither cause the natural ambient level to be raised by
30% nor give rise to accumulation of suspended solids which may adversely affect aquatic communities.
Marine waters Marine waters (including North Western
Supplementary Zone)
I. AMMONIA
The un-ionized ammoniacal nitrogen level should not be more than 0.021 mg per litre, calculated as the annual average (arithmetic mean).
Whole zone Whole zone (including North Western Supplementary Zone)
J. NUTRIENTS
a) Nutrients shall not be present in quantities sufficient to cause excessive or nuisance growth of algae or other aquatic plants.
Inner and Outer marine Subzones
Marine waters (including North Western Supplementary Zone)
b) Without limiting the generality of objective (a) above, the level of inorganic nitrogen should not exceed 0.3 mg per litre, expressed as annual water
column average (arithmetic mean of at least 3 measurements at 1m below surface, mid-depth and 1m above seabed).
- Castle Peak Bay Subzone
c) Without limiting the generality of objective (a) above, the level of inorganic nitrogen should not exceed 0.7 mg per litre, expressed as annual mean.
Inner Marine Subzone
-
d) Without limiting the generality of objective (a) above, the level of inorganic nitrogen should not exceed 0.5 mg per litre, expressed as annual water
column average.
Outer Marine Subzone (water column average specified as arithmetic mean of at least 2
measurements at 1 metre below surface and 1 metre above seabed)
Marine waters (including North Western Supplementary Zone)
excepting Castle Peak Bay Subzone (water column average specified as arithmetic mean
of at least 3 measurements at 1m below surface, mid-depth and 1m above seabed)
K. 5-DAY BIOCHEMICAL OXYGEN DEMAND
ENVIRONMENTAL RESOURCES MANAGEMENT CASTLE PEAK POWER COMPANY LIMITED
0308057_S7_WATER_REV 3.DOCX APRIL 2016
7-4
Water Quality Objective Deep Bay WCZ North Western WCZ
a) Waste discharges shall not cause the 5-day biochemical oxygen demand to exceed 3 milligrams per litre.
Yuen Long & Kam Tin (Upper) Subzone, Beas Subzone, Indus Subzone, Ganges Subzone
and Water Gathering Ground Subzones
Tuen Mun (A), Tuen Mun (B) and Tuen Mun (C) Subzones and Water Gathering Ground
Subzones)
b) Waste discharges shall not cause the 5-day biochemical oxygen demand to
exceed 5 milligrams per litre.
Yuen Long & Kam Tin (Lower) Subzone and
other inland waters
Other Inland waters
L. CHEMICAL OXYGEN DEMAND
a) Waste discharges shall not cause the chemical oxygen demand to exceed 15
milligrams per litre.
Yuen Long & Kam Tin (Upper) Subzone, Beas
Subzone, Indus Subzone, Ganges Subzone and Water Gathering Ground Subzones
Tuen Mun (A), Tuen Mun (B) and Tuen Mun
(C) Subzones and Water Gathering Ground Subzones)
b) Waste discharges shall not cause the chemical oxygen demand to exceed 30 milligrams per litre.
Yuen Long & Kam Tin (Lower) Subzone and other inland waters
Other Inland waters
M. TOXINS
a) Waste discharges shall not cause the toxins in water to attain such levels as to produce significant toxic, carcinogenic, mutagenic or teratogenic effects in
humans, fish or any other aquatic organisms, with due regard to biologically cumulative effects in food chains and to interactions of toxic substances with each other.
Whole zone
Whole zone (including North Western Supplementary Zone)
b) Waste discharges shall not cause a risk to any beneficial uses of the aquatic environment.
Whole zone
Whole zone (including North Western Supplementary Zone)
N. PHENOLS
Phenols shall not be present in such quantities as to produce a specific odour, or
in concentration greater than 0.05 mg per litre as C6H5OH.
Yung Long Bathing Beach Subzone Bathing Beach Subzones
O. TURBIDITY
Waste discharges shall not reduce light transmission substantially from the
normal level.
Yung Long Bathing Beach Subzone Bathing Beach Subzones
ENVIRONMENTAL RESOURCES MANAGEMENT CASTLE PEAK POWER COMPANY LIMITED
0308057_S7_WATER_REV 3.DOCX APRIL 2016
7-5
7.2.2 Technical Memorandum for Effluents Discharged into Drainage and Sewerage
Systems, Inland and Coastal Waters (TM-ICW)
All discharges from the construction and operation phases of the proposed
Project are required to comply with the Technical Memorandum Standards for
Effluents Discharged into Drainage and Sewerage Systems, Inland and Coastal
Waters (TM-ICW) issued under Section 21 of the WPCO.
The TM-ICW defines acceptable discharge limits to different types of receiving
waters. Under the TM-ICW, effluents discharged into the drainage and
sewerage systems, inshore and coastal waters of the WCZs are subject to
pollutant concentration standards for specified discharge volumes. These are
defined by the Environmental Protection Department (EPD) and are specified
in licence conditions for any new discharge within a WCZ.
7.2.3 Technical Memorandum on Environmental Impact Assessment Process
(EIAO-TM)
Annexes 6 and 14 of the EIAO-TM provide general guidelines and criteria to be
used in assessing water quality impacts.
The EIAO-TM recognises that, in the application of the above water quality
criteria, it may not be possible to achieve the WQO at the point of discharge as
there are areas which are subject to greater impacts (which are termed by the
EPD as the mixing zones), where the initial dilution of the discharge takes
place. The definition of this area is determined on a case-by-case basis. In
general, the criteria for acceptance of the mixing zones are that it must not
impair the integrity of the water body as a whole and must not damage the
ecosystem.
7.2.4 Practice Note for Professional Persons, Construction Site Drainage
Apart from the above statutory requirements, the Practice Note for Professional
Persons, Construction Site Drainage (ProPECC PN 1/94), issued by EPD in 1994,
also provides useful guidelines on the prevention of water pollution
associated with construction activities.
7.2.5 Town Planning Board Guidelines for Application for Developments within
Deep Bay Area under Section 16 of the Town Planning Ordinance (TPB PG-
No. 12C)
Under TPB PG-No. 12C, any development within the Wetland Conservation
Area (WCA) or Wetland Buffer Area (WBA) stipulated under this guideline
“should not add to the pollution load of the Deep Bay Area”. It is known as
the “No Net Increase in Pollution Load in Deep Bay” policy and would be
observed for the operation phase of the development. The same requirement
is stipulated under Section 4(xi) of the EIA Study Brief for this Project. As
such, the requirement would be observed and the additional CCGT units
would be designed such that there would be no net increase in pollution load
to the Deep Bay waters during the operation phase.
ENVIRONMENTAL RESOURCES MANAGEMENT CASTLE PEAK POWER COMPANY LIMITED
0308057_S7_WATER_REV 3.DOCX APRIL 2016
7-6
7.3 BASELINE CONDITIONS
7.3.1 Assessment Area
In accordance with the EIA Study Brief, the Assessment Area for the water
quality assessment covers the Deep Bay WCZ and the North Western WCZ
and the water quality sensitive receivers (WSRs) in the vicinity of the Project.
WSRs within 9 km from the Project were identified and described in detail in
Section 7.3.4. Water quality modelling study was conducted under this Study
using Delft3D suite of model. Fine grid models, covering the whole Deep
Bay WCZ, North Western WCZ and waters west to the HK marine boundary,
are used to study the potential change in hydrodynamic and water quality.
Details about model coverage and settings are provided in Annex 7B.
7.3.2 Marine Water Quality
Baseline marine water quality in the vicinity of the Project has been
determined through a review of EPD routine water quality monitoring data
collected between 2005 and 2014. This dataset provides Hong Kong’s most
comprehensive long-term water quality monitoring data and allows an
indication of temporal and spatial change in marine water quality in Hong
Kong. Four EPD monitoring stations are identified in the vicinity of the
Project and the locations of these stations are presented in Figure 7.1.
According to EPD’s Marine Water Quality in Hong Kong in 2014, the WQO
compliance rate of the Deep Bay WCZ in 2014 was 40%, same as from 2008 to
2013 except in 2012 (53%). Similar to the previous years, the Deep Bay WCZ
had relatively high nutrient levels in 2014. The total inorganic nitrogen (TIN)
level in the Deep Bay outer subzone (0.9 – 1.2 mg L-1) was higher than the
respective TIN objective of 0.5 mg L-1.
The collaboration of EPD with its Shenzhen counterpart in reducing pollution
load, and the voluntary farm surrender schemes for poultry and pig farms
implemented in 2005-2008 result in water quality improvement since mid-
2000s. The declining water quality trend observed during the period 1986-
2007 was reversed after 2007. A comparison of the monitoring results
collected between 1997-2006 and 2007-2014 suggests that the water quality of
Deep Bay has improved in terms of reduction in organic loading (i.e., 5-day
biochemical oxygen demand, BOD5), nutrients (e.g., ammonia nitrogen, TIN
and orthophosphate) and bacterial levels.
In 2014, the North Western WCZ attained an overall WQO compliance rate of
61% because of lower compliance with the dissolved oxygen (DO) objective
(50%) due to the hot summer weather. Compliance with unionized ammonia
(UIA) and TIN objectives in this WCZ was 100% and 33% respectively. The
higher levels of TIN (annual mean 0.42 - 0.74 mg L-1) might be associated with
the higher background level of the discharges from the Pearl River, and some
local discharges and surface run-off from the Northwest New Territories as
well as north Lantau.
ENVIRONMENTAL RESOURCES MANAGEMENT CASTLE PEAK POWER COMPANY LIMITED
0308057_S7_WATER_REV 3.DOCX APRIL 2016
7-7
Table 7.2 Summary of EPD Routine Water Quality Monitoring Data from Selected
Stations of the Deep Bay and North Western Water Control Zones (2005 -
2014)
Parameter DM4 DM5 NM3 NM5
Temperature (C) 24.4 24.2 23.5 23.6
(15.4-31.0) (15.8-30.6) (15.2-29.6) (15.4-29.7)
Salinity (psu) 23.1 25.8 28.9 27.6
(4.3-31.6) (7.6-33.0) (18.2-33.2) (15.7-33.1)
Dissolved Oxygen (mg L-1) -
Depth Averaged
6.1 6.1 6.0 5.9
(3.3-11.2) (3.6-11.1) (3.2-9.6) (3.0-9.8)
Dissolved Oxygen (mg L-1) -
Bottom
6.0 5.9 5.7 5.6
(3.1-11.1) (3.2-10.5) (2.4-9.9) (2.1-9.5)
Suspended Solids (mg L-1) 12.9 8.4 7.8 11.1
(2.2-88.5) (1.8-36.4) (1.8-30.7) (2.0-53.8)
5-day Biochemical Oxygen
Demand (mg L-1)
0.9 0.8 0.7 0.8
(0.2-3.9) (0.2-6.4) (0.2-2.5) (0.2-2.7)
Unionised Ammonia (mg L-
1)
0.009 0.006 0.005 0.006
(0.002-0.068) (0.001-0.033) (0.001-0.013) (0.001-0.017)
Total Inorganic Nitrogen
(mg L-1)
1.19 0.87 0.53 0.67
(0.47-2.85) (0.24-2.16) (0.12-1.48) (0.13-1.94)
Orthophosphate
Phosphorus (mg L-1)
0.055 0.037 0.025 0.030
(0.006-0.135) (0.004-0.092) (0.006-0.053) (0.007-0.059)
Total Phosphorus (mg L-1) 0.08 0.06 0.05 0.05
(0.05-0.29) (0.03-0.22) (0.03-0.08) (0.03-0.11)
Chlorophyll-a (g L-1) 4.2 3.5 3.5 3.5
(0.3-43.0) (0.5-42.0) (0.5-22.0) (0.4-23.0)
Escherichia coli (cfu/100ml) 181 333 339 930
(2-5190) (40-2267) (10-9147) (11-11385)
Notes:
(a) Data presented are depth-averaged values calculated by taking the means of three depths, i.e. surface (S), mid-
depth (M) and bottom (B), except as specified.
(b) Data presented are annual arithmetic means except for E. coli, which are geometric means of depth-average values..
(c) Data in brackets indicate the ranges for the corresponding depths.
(d) Bold and underlined figures indicate non-compliance with the WQOs: DO = 4 mg L-1 for depth-averaged level, UIA
= 0.021 mg L-1, TIN = 0.5 mg L-1 for Deep Bay WCZ (Outer Subzone) and North Western WCZ.
7.3.3 Marine Sediment Quality
Baseline marine sediment quality in the vicinity of the Project has been
determined through a review of EPD routine monthly sediment quality
monitoring data collected in 2005 to 2014. Four EPD monitoring stations are
identified in the vicinity of the Project and the locations of these stations are
presented in Figure 7.1.
Sediment monitoring data from the EPD monitoring stations were compared
with the relevant sediment quality criteria specified in ADV-21 Management
Framework for Disposal of Dredged/Excavated Sediment. The EPD routine
monitoring data indicated a mild level of sediment contamination in the
vicinity of the Project. Exceedance of the Lower Chemical Exceedance Level
(LCEL) of arsenic is identified at all selected monitoring stations. Exceedance
of the Upper Chemical Exceedance Level (UCEL) for copper is identified at
monitoring station DS3 (Table 7.3).
ENVIRONMENTAL RESOURCES MANAGEMENT CASTLE PEAK POWER COMPANY LIMITED
0308057_S7_WATER_REV 3.DOCX APRIL 2016
7-8
Sediment sampling and testing was conducted under this EIA to identify the
level of sediment contamination within the marine construction works area.
Sediment sampling locations are shown in Figure 7.2. Sediment elutriate test
was conducted using sediment samples from these sampling stations to
identify the potential of release of sediment-bounded nutrients, heavy metals
and trace organic pollutants due to disturbance from marine works under this
Project. Sediment testing and the associated elutriate testing results from the
laboratory are enclosed in Annex 7A.
The sediment testing results are compared against the LCEL and UCEL, which
show minor exceedances in LCEL for arsenic in all sediment samples (Table
7.4). This is consistent with the results of the nearby EPD sediment quality
monitoring data (and the general pattern all over Hong Kong). The sediment
elutriate test results showed no significant release of heavy metals (including
arsenic), trace organics, tributyltin, nitrate, nitrite, and total phosphorus (Table
7.5).
ENVIRONMENTAL RESOURCES MANAGEMENT CASTLE PEAK POWER COMPANY LIMITED
0308057_S7_WATER_REV 3.DOCX APRIL 2016
7-9
Table 7.3 Summary of EPD Routine Marine Sediment Quality Monitoring Data from Selected Station of the Deep Bay and North Western
Water Control Zones (2005 - 2014)
Parameter ETWB TC(W) No. 34/2002 Guideline Deep Bay WCZ North Western WCZ
LCEL UCEL DS3 DS4 NS3 NS4
Arsenic (mg kg-1) 12 42 11.8 11.4 11.2 10.5
(5.5 - 15.0) (8.5 - 15.0) (8.3 - 14.0) (8.1 - 15.0)
Cadmium (mg kg-1) 1.5 4 0.2 0.1 0.1 0.1
(<0.1 - 0.3) (<0.1 - 0.2) (<0.1 - 0.1) (<0.1 - 0.1)
Chromium (mg kg-1) 80 160 39 33 33 30
(22 - 53) (16 - 49) (19 - 44) (22 - 47)
Copper (mg kg-1) 65 110 56 30 31 28
(12 - 230) (9 - 65) (13 - 48) (12 - 51)
Lead (mg kg-1) 75 110 45 39 39 36
(29 - 61) (24 - 58) (26 - 51) (29 - 53)
Mercury (mg kg-1) 0.5 1 0.11 0.10 0.11 0.09
(<0.05 - 0.16) (<0.05 - 0.14) (0.06 - 0.16) (<0.05 - 0.23)
Nickel (mg kg-1) 40 40 24 20 20 18
(12 - 35) (14 - 31) (11 - 26) (13 - 27)
Silver (mg kg-1) 1 2 0.3 0.1 0.1 <0.2
(<0.2 - 1.0) (<0.2 - 1.0) (<0.2 - 1.0) (<0.2 - <0.2)
Zinc (mg kg-1) 200 270 125 98 99 100
(65 - 200) (63 - 140) (62 - 130) (78 - 130)
Total Polychlorinated Biphenyls (PCBs)
(g kg-1)
23 180 18 18 18 18
(18 - 18) (18 - 18) (18 - 18) (18 - 18)
Low Molecular Weight Polycyclic Aromatic
Hydrocarbons (LMW PAHs) (μg kg-1)
550 3,160 95.7 57.5 116.5 107.1
(90.0 - 116.5) (45.0 - 169.5) (90.0 - 502.5) (90.0 - 243.5)
High Molecular Weight Polycyclic Aromatic
Hydrocarbons (HMW PAHs) (μg kg-1)
1,700 9,600 86.7 50.5 111.4 72.6
(28.5 - 276.5) (16.0 - 92.5) (24.0 - 694.0) (24.0 - 126.5)
Chemical Oxygen Demand (mg kg-1) -- -- 13155 13270 13755 13855
(9300 - 18000) (7400 - 18000) (9400 - 23000) (9100 - 19000)
Total Kjeldahl Nitrogen (mg kg-1) -- -- 351 305 366 336
(160 - 590) (100 - 560) (170 - 570) (110 - 600)
Ammonia Nitrogen (mg kg-1) -- -- 3.51 5.07 5.82 8.10
(<0.01 - 23.00) (<0.05 - 15.00) (<0.05 - 21.00) (0.11 - 28.00)
ENVIRONMENTAL RESOURCES MANAGEMENT CASTLE PEAK POWER COMPANY LIMITED
0308057_S7_WATER_REV 3.DOCX APRIL 2016
7-10
Parameter ETWB TC(W) No. 34/2002 Guideline Deep Bay WCZ North Western WCZ
LCEL UCEL DS3 DS4 NS3 NS4
Total Phosphorus (mg kg-1) -- -- 209 175 196 184
(100 - 310) (60 - 270) (130 - 250) (77 - 260)
Notes:
Bold figures indicate non-compliance with the LCEL.
Bold and underlined figures indicate non-compliance with the UCEL
LCEL: Lower Chemical Exceedance Level; UCEL: Upper Chemical Exceedance Level
Table 7.4 Summary of Marine Sediment Quality at Sampling Stations of this EIA
Parameter (Unit) LOR LCEL UCEL IT1 IT2 OF1 Reference Sample
Silver (mg kg-1) 0.1 1 2 0.5 0.4 0.4 <0.1
Arsenic (mg kg-1) 1 12 42 14 16 15 3
Cadmium (mg kg-1) 0.2 1.5 4 0.2 0.3 <0.2 0.6
Chromium (mg kg-1) 1 80 160 50 49 48 26
Copper (mg kg-1) 1 65 110 63 53 53 13
Nickel (mg kg-1) 1 40 40 35 32 34 19
Lead (mg kg-1) 1 75 110 53 51 52 29
Zinc (mg kg-1) 1 200 270 151 137 143 69
Mercury (mg kg-1) 0.05 0.5 1 0.13 0.1 0.11 <0.05
Total PCBs (µg kg-1) 18 23 180 <18 <18 <18 <18
LMW PAHs (µg kg-1) 550 550 3160 <550 <550 <550 <550
HMW PAHs (µg kg-1) 1700 1700 9600 <1700 <1700 <1700 <1700
TBT (µg kg-1) 0.015 0.15 0.15 <0.015 <0.015 <0.015 <0.015
Notes:
Bold figures indicate non-compliance with the LCEL.
Reference sample was taken from EPD marine sediment monitoring station PS6 (HK8 coordinate: E850234 N820057).
LOR: Limit of Reporting; LCEL: Lower Chemical Exceedance Level; UCEL: Upper Chemical Exceedance Level
ENVIRONMENTAL RESOURCES MANAGEMENT CASTLE PEAK POWER COMPANY LIMITED
0308057_S7_WATER_REV 3.DOCX APRIL 2016
7-11
Table 7.5 Summary of Sediment Elutriate Test Results at Sampling Stations of this EIA
Parameter (Unit) WQC LOR IT1 IT2 OF1
Elutriate
Blank
IT1
Elutriate
Blank
IT2
Elutriate
Blank
OF1
Mercury (µg L-1) 0.3 1 <0.05 <0.05 <0.05 <0.05 <0.05 <0.05
Arsenic (µg L-1) 25 10 <10 <10 <10 <10 <10 <10
Cadmium (µg L-1) 2.5 0.1 <0.1 <0.1 0.1 <0.1 <0.1 <0.1
Chromium (µg L-1) 15 1 <1 <1 <1 <1 <1 <1
Copper (µg L-1) 5 1 <1 <1 <1 4 2 5
Lead (µg L-1) 25 1 <1 <1 <1 <1 <1 <1
Nickel (µg L-1) 30 5 2 2 2 2 1 2
Silver (µg L-1) 1.9 1 <1 <1 <1 <1 <1 <1
Zinc (µg L-1) 40 10 <10 <10 <10 <10 <10 14
Total PAHs (µg L-1) 3 3 <3 <3 <3 <3 <3 <3
Total PCBs (µg L-1) 0.03 0.03 <0.03 <0.03 <0.03 <0.03 <0.03 <0.03
TBT (µg L-1) 0.1 0.015 <0.015 <0.015 <0.015 <0.015 <0.015 <0.015
Notes:
WQC: Water quality assessment criteria (stipulated under Table 7.10); LOR: Limit of Reporting
Elutriate blanks are conducted using only seawater taken from the sampling stations stipulated.
ENVIRONMENTAL RESOURCES MANAGEMENT CASTLE PEAK POWER COMPANY LIMITED
0308057_S7_WATER_REV 3.DOCX APRIL 2016
7-12
7.3.4 Water Quality Sensitive Receivers
The sensitive receivers that may be affected by changes in water quality
arising from the Project are identified in accordance with the EIAO-TM. For
each of the sensitive receivers, established threshold criteria or guidelines
have been utilised for establishing the significance of impacts to water quality.
The locations of the identified WSRs are provided in Figure 7.1. The
approximate shortest distances by sea from the Project are detailed in Table
7.6.
Table 7.6 Water Quality Sensitive Receivers in the Vicinity of the Project
Description Location Model
Output
Location
Approximate Shortest
Distance by Sea from
Project (km)
Fisheries Sensitive Receivers
Oyster Production Area Sheung Pak Nai SR14 3.5
Recognised Spawning/ Nursery
Grounds
Fisheries Spawning Ground in
North Lantau
SR15 4.1
Artificial Reef Deployment Area Sha Chau and Lung Kwu Chau SR12 7.9
Marine Ecological Sensitive Receivers
Mangroves Ngau Hom Shek SR1 6.5
Sheung Pak Nai SR2 4.9
Marine Park Designated Sha Chau and Lung
Kwu Chau
SR6 4.4
SR7 3.3
SR13 8.5
Intertidal Mudflats Ha Pak Nai SR3 3.5
Seagrass Beds Sheung Pak Nai SR2 4.9
Ha Pak Nai SR3 3.5
Horseshoe Crab Nursery Grounds Ha Pak Nai SR3 3.5
Ngau Hom Shek SR1 6.5
Lung Kwu Sheung Tan SR5 2.4
Coral Colonies Identified Along
Survey Transect under this Project
Transect D SR17 At the proximity of
the Project
Transect C SR18 At the proximity of
the Project
Water Quality Sensitive Receivers
Non-gazetted Beaches Lung Kwu Sheung Tan SR5 2.4
Lung Kwu Tan SR8 3.8
Secondary Recreation Subzone North Western Water Control Zone SR8 3.8
Seawater Intakes Black Point Power Station SR4 At the proximity of
the Project
Castle Peak Power Station SR9 4.8
Tuen Mun Area 38 SR11 6.5
Shiu Wing Steel Mill SR10 5.6
Sludge Treatment Facilities SR16 1.5
The WSRs of this Project cover marine waters of about 9 km from the Project
by sea. Other sensitive receivers within the Deep Bay and North Western
WCZs beyond this distance are considered too far away to be affected by the
ENVIRONMENTAL RESOURCES MANAGEMENT CASTLE PEAK POWER COMPANY LIMITED
0308057_S7_WATER_REV 3.DOCX APRIL 2016
7-13
construction and operation of the Project. They are therefore not considered
in this assessment.
It should be noted that coral identified at coral survey transect D (SR17) under
this EIA is located within the direct footprint of sediment dredging for
construction phase. The coral colony is hence expected to be removed during
project construction and therefore would not be considered in this water
quality assessment.
7.4 ASSESSMENT CRITERIA
7.4.1 Suspended Solids (SS)
Specific water quality criteria for SS level allowed at seawater intakes for the
BPPS and the Castle Peak Power Station (CPPS) are stipulated below. For all
other WSRs with no specific water quality criteria, elevation in SS
concentrations resulting from the Project’s construction and operational
activities were assessed against the WQO. The WQO for SS is defined as not
to raise the natural ambient level by 30%, nor cause the accumulation of SS
which may adversely affect aquatic communities. The assessment criterion is
hence defined as the WQO allowable increase in SS concentrations within the
corresponding WCZs.
SS data from EPD’s routine water quality monitoring programme in 2005-2014
have been analysed to determine the WQO allowable increase at the WSRs.
This is calculated as 30% of the ambient level (90th-percentile value (1)) from the
2005-2014 baseline marine water quality data. For each WSR, ambient level
was derived from the closest EPD water quality monitoring station. The
assessment criterion for SS at each WSR is summarised in Table 7.7.
Both power station intakes (SR4 and SR9) have specific requirements for
intake water quality. The applicable criteria for temperature and SS for the
BPPS and CPPS seawater intakes are below 30°C and 764 mg L-1, respectively.
In view of the relatively high level of ambient SS, the tolerance level of 700 mg
L-1 for maximum SS elevation at these two WSRs would be taken as
assessment criteria. There are no particular criteria specified for the seawater
intakes of Tuen Mun Area 38 (SR11), Shiu Wing Steel Mill (SR10) and Sludge
Treatment Facilities (SR16) and hence WQOs have been adopted (Table 7.7).
(1) The use of 90th-percentile value of baseline SS level from nearby EPD marine water quality monitoring stations are
common practices in past approved EIA, including the Black Point Gas Supply Project EIA (AEIAR-150/2010),
Development of the Integrated Waste Management Facilities Phase 1 EIA (AEIAR-163/2012) as well as the recently
approved Expansion of Hong Kong International Airport into a Three-Runway System EIA (AEIAR-185/2014).
ENVIRONMENTAL RESOURCES MANAGEMENT CASTLE PEAK POWER COMPANY LIMITED
0308057_S7_WATER_REV 3.DOCX APRIL 2016
7-14
Table 7.7 Water Quality Assessment Criteria for Suspended Solids (mg L-1) at WSRs
Sensitive Receivers Name Model
Output
Location
EPD
Station
Relevant Depth for
Assessment
Dry Season Wet Season
Ambient Level (a)
WQO
Allowable
Change
Ambient Level (a)
WQO
Allowable
Change
Fisheries Sensitive Receivers
Oyster Production
Area
Sheung Pak Nai SR14 DM4 Depth-averaged 26.05 7.82 20.60 6.18
Recognised
Spawning/ Nursery
Grounds
Fisheries Spawning
Ground in North
Lantau
SR15 NM5 Depth-averaged 20.70 6.21 20.21 6.06
Artificial Reef
Deployment Area
Sha Chau and Lung
Kwu Chau
SR12 NM5 Bottom 32.20 9.66 36.20 10.86
Ecological Sensitive Receivers
Mangroves Ngau Hom Shek SR1 DM4 Bottom 32.30 9.69 24.00 7.20
Sheung Pak Nai SR2 DM4 Bottom 32.30 9.69 24.00 7.20
Marine Park Designated Sha
Chau and Lung
Kwu Chau
SR6 NM5 Depth-averaged 20.70 6.21 20.21 6.06
SR7 NM5 Depth-averaged 20.70 6.21 20.21 6.06
SR13 NM5 Depth-averaged 20.70 6.21 20.21 6.06
Intertidal Mudflats Ha Pak Nai SR3 DM4 Bottom 32.30 9.69 24.00 7.20
Seagrass Beds Sheung Pak Nai SR2 DM4 Bottom 32.30 9.69 24.00 7.20
Ha Pak Nai SR3 DM4 Bottom 32.30 9.69 24.00 7.20
Horseshoe Crab
Nursery Grounds
Ha Pak Nai SR3 DM4 Bottom 32.30 9.69 24.00 7.20
Ngau Hom Shek SR1 DM4 Bottom 32.30 9.69 24.00 7.20
Lung Kwu Sheung
Tan
SR5 NM5 Bottom 32.20 9.66 36.20 10.86
Coral Colonies
Identified Along
Survey Transect
under this Project
Transect C SR18 DM5 Bottom 28.30 8.49 15.00 4.50
Water Quality Sensitive Receivers
ENVIRONMENTAL RESOURCES MANAGEMENT CASTLE PEAK POWER COMPANY LIMITED
0308057_S7_WATER_REV 3.DOCX APRIL 2016
7-15
Sensitive Receivers Name Model
Output
Location
EPD
Station
Relevant Depth for
Assessment
Dry Season Wet Season
Ambient Level (a)
WQO
Allowable
Change
Ambient Level (a)
WQO
Allowable
Change
Non-gazetted
Beaches
Lung Kwu Sheung
Tan
SR5 NM5 Depth-averaged 20.70 6.21 20.21 6.06
Lung Kwu Tan SR8 NM5 Depth-averaged 20.70 6.21 20.21 6.06
Secondary
Recreation Subzone
North Western
Water Control
Zone
SR8 NM5 Depth-averaged 20.70 6.21 20.21 6.06
Seawater Intakes Black Point Power
Station
SR4 DM5 Bottom 28.30 700.00 (c) 15.00 700.00 (c)
Castle Peak Power
Station
SR9 NM5 Bottom 32.20 700.00 (c) 36.20 700.00 (c)
Tuen Mun Area 38 SR11 NM3 Bottom 18.30 5.49 20.00 6.00
Shiu Wing Steel
Mill
SR10 NM3 Bottom 18.30 5.49 20.00 6.00
Sludge Treatment
Facilities
SR16 DM5 Bottom 28.30 8.49 15.00 4.50
Notes:
(a) Ambient level is calculated as 90th percentile of the EPD routine monitoring data of 2005-2014 at respective EPD station close to the WSRs.
(b) This table is applicable for those WSRs which were assessed against the WQO.
(c) Assessment of cooling water intakes of power stations (SR4 and SR9) should refer to the specific assessment criterion of SS for this type of WSR. The
applicable criterion for SS is below 764 mg L-1. The tolerance criterion of 700 mg L-1 was adopted.
ENVIRONMENTAL RESOURCES MANAGEMENT CASTLE PEAK POWER COMPANY LIMITED
0308057_S7_WATER_REV 3.DOCX APRIL 2016
7-16
7.4.2 Sediment Deposition
Impacts to artificial reefs (SR12) as well as coral colonies identified on
shoreline of BPPS in dive survey conducted under this Study (SR18) have been
assessed with regard to sediment deposition. The assessment criterion of 200
gram per square metre per day (200 g m-2 d-1), has been used in approved EIA
Reports (1) (2) (3) and has been adopted here.
7.4.3 Dissolved Oxygen
Oxygen depletion resulting from the Project’s construction activities will be
assessed against the WQO. The assessment criterion is defined as the WQO
allowable depletion in DO levels at the WSRs. The depletion of dissolved
oxygen in the water column is not expected to affect the operation of cooling
water intakes for BPPS and CPPS (SR4 and SR9). Therefore no assessment
criteria for these two WSRs are proposed.
DO data from EPD’s routine water quality monitoring programme from 2005-
2014 have been analysed to determine WQO allowable depletion at the WSRs.
Allowable DO depletion is calculated as the ambient DO level minus the
WQO, i.e. 4 mg L-1 for depth-averaged, surface and middle layers, and 2 mg L-
1 for bottom layer. Ambient level is calculated as the 10th-percentile value
from the 2005-2014 marine water quality data for assessment against the WQO
criterion for DO (Table 7.1 refers). For each WSR, ambient level was derived
from the closest EPD water quality monitoring station. The assessment
criteria for DO at each WSR are summarised in Table 7.8.
(1) ERM – Hong Kong, Ltd (2000) EIA for Construction of an International Theme Park in Penny's Bay of North
Lantau together with its Essential Associated Infrastructures - Environmental Impact Assessment. Final EIA
Report. For Civil Engineering Department, Hong Kong SAR Government.
(2) ERM - Hong Kong, Ltd (2006) Liquefied Natural Gas (LNG) Receiving Terminal and Associated Facilities. For
CAPCO. Final EIA Report. December 2006.
(3) ERM - Hong Kong, Ltd (2010) Black Point Gas Supply Project. For CAPCO. Final EIA Report. Febuary 2010.
ENVIRONMENTAL RESOURCES MANAGEMENT CASTLE PEAK POWER COMPANY LIMITED
0308057_S7_WATER_REV 3.DOCX APRIL 2016
7-17
Table 7.8 Water Quality Assessment Criteria for Dissolved Oxygen (mg L-1) at WSRs
Sensitive Receivers Name Model
Output
Location
EPD
Station
Relevant Depth
for Assessment
Annual Dry Season Wet Season
Ambient
Level (a)
WQO
Allowable
Change
Ambient
Level (a)
WQO
Allowable
Change
Ambient
Level (a)
WQO
Allowable
Change
Fisheries Sensitive Receivers
Oyster Production
Area
Sheung Pak Nai SR14 DM4 Depth-averaged 4.69 0.69 5.75 1.75 4.32 0.32
Recognised
Spawning/
Nursery Grounds
Fisheries
Spawning Ground
in North Lantau
SR15 NM5 Depth-averaged 4.19 0.19 5.98 1.98 3.90 - (c)
Artificial Reef
Deployment Area
Sha Chau and
Lung Kwu Chau
SR12 NM5 Bottom 3.09 1.09 5.98 3.98 2.89 0.89
Ecological Sensitive Receivers
Mangroves Ngau Hom Shek SR1 DM4 Bottom 4.40 2.40 5.69 3.69 4.08 2.08
Sheung Pak Nai SR2 DM4 Bottom 4.40 2.40 5.69 3.69 4.08 2.08
Marine Park Designated Sha
Chau and Lung
Kwu Chau
SR6 NM5 Depth-averaged 4.19 0.19 5.98 1.98 3.90 - (c)
SR7 NM5 Depth-averaged 4.19 0.19 5.98 1.98 3.90 - (c)
SR13 NM5 Depth-averaged 4.19 0.19 5.98 1.98 3.90 - (c)
Intertidal Mudflats Ha Pak Nai SR3 DM4 Bottom 4.40 2.40 5.69 3.69 4.08 2.08
Seagrass Beds Sheung Pak Nai SR2 DM4 Bottom 4.40 2.40 5.69 3.69 4.08 2.08
Ha Pak Nai SR3 DM4 Bottom 4.40 2.40 5.69 3.69 4.08 2.08
Horseshoe Crab
Nursery Grounds
Ha Pak Nai SR3 DM4 Bottom 4.40 2.40 5.69 3.69 4.08 2.08
Ngau Hom Shek SR1 DM4 Bottom 4.40 2.40 5.69 3.69 4.08 2.08
Lung Kwu Sheung
Tan
SR5 NM5 Bottom 3.09 1.09 5.98 3.98 2.89 0.89
Coral Colonies
Identified Along
Survey Transect
under this Project
Transect C SR18 DM5 Bottom 4.09 2.09 6.09 4.09 3.90 1.90
Water Quality Sensitive Receivers
ENVIRONMENTAL RESOURCES MANAGEMENT CASTLE PEAK POWER COMPANY LIMITED
0308057_S7_WATER_REV 3.DOCX APRIL 2016
7-18
Sensitive Receivers Name Model
Output
Location
EPD
Station
Relevant Depth
for Assessment
Annual Dry Season Wet Season
Ambient
Level (a)
WQO
Allowable
Change
Ambient
Level (a)
WQO
Allowable
Change
Ambient
Level (a)
WQO
Allowable
Change
Non-gazetted
Beaches
Lung Kwu Sheung
Tan
SR5 NM5 Depth-averaged 4.19 0.19 5.98 1.98 3.90 - (c)
Lung Kwu Tan SR8 NM5 Depth-averaged 4.19 0.19 5.98 1.98 3.90 - (c)
Secondary
Recreation Subzone
North Western
Water Control
Zone
SR8 NM5 Depth-averaged 4.19 0.19 5.98 1.98 3.90 - (c)
Seawater Intakes Black Point Power
Station
SR4 DM5 Bottom 4.09 N/A (b) 6.09 N/A (b) 3.90 N/A (b)
Castle Peak Power
Station
SR9 NM5 Bottom 3.09 N/A (b) 5.98 N/A (b) 2.89 N/A (b)
Tuen Mun Area 38 SR11 NM3 Bottom 3.40 1.40 5.90 3.90 3.10 1.10
Shiu Wing Steel
Mill
SR10 NM3 Bottom 3.40 1.40 5.90 3.90 3.10 1.10
Sludge Treatment
Facilities
SR16 DM5 Bottom 4.09 2.09 6.09 4.09 3.90 1.90
Notes:
(a) Ambient level is calculated as 10th percentile of the EPD routine monitoring data of 2005-2014 at respective EPD station close to WSRs.
(b) This table is applicable for those WSRs which were assessed against the WQO. WQO is not applicable for the assessment of cooling water intakes for
power stations (SR4 and SR9).
(c) As stated in item D(b) under Table 7.1, the DO criteria for WQO requires depth-averaged DO criteria for 90% of incident throughout the year.
Background ambient depth-averaged DO level is below 4 mg L-1 at NM5 in wet season. Assessing potential DO depletion based on background DO
levels of two seasons at WSRs near NM5 would be too conservative in view of the low DO level in wet season. For WSRs near NM5, the assessment for
DO depletion would be made with reference to the annual baseline data.
ENVIRONMENTAL RESOURCES MANAGEMENT CASTLE PEAK POWER COMPANY LIMITED
0308057_S7_WATER_REV 3.DOCX APRIL 2016
7-19
7.4.4 Nutrients
Elevation in the levels of nutrients as a result of the Project’s construction
activities, if any, will be compared against the respective WQO. It should be
highlighted that continual exceedance in TIN was observed in Deep Bay and
North Western WCZs from 2005 to 2014 (refer to Table 7.2). Assessing the
potential elevation in TIN against the WQO criterion with such high
background level (mean TIN level from 2005 to 2014 at the four nearby EPD
marine water quality monitoring stations all exceeded 0.5 mg L-1) would be
too conservative and an alternative assessment criterion was adopted for this
EIA. The proposed allowed TIN increase from marine construction would be
limited to 1% of the WQO TIN criterion for the corresponding WCZs, which is
0.005 mg L-1 for all WSRs (1) except SR4 and SR9 (seawater intake for BPPS and
CPPS) which are not considered sensitive to elevation in TIN. The proposed
TIN elevation criteria would also be below 1% of the mean ambient level,
which is expected to be well within seasonal variation (which is significantly
affected by the Pearl River Delta discharge as stated in EPD’s Marine Water
Quality in Hong Kong in 2014). Therefore, such a short term increase in TIN
level would be insignificant in term of water quality and would be considered
acceptable.
The increase in UIA from the proposed dredging works at seawater intake
and discharge outfall was assessed against the corresponding WQO criterion
for UIA. Again, this assessment criterion does not apply to SR4 and SR9.
The proposed assessment criteria for TIN and UIA are summarised below in
Table 7.9.
Table 7.9 Proposed Assessment Criteria for Nutrients from Marine Dredging
Assessment Criteria
Deep Bay WCZ (Outer Subzone) North Western WCZ
TIN (mg L-1) 0.005 (elevation) 0.005 (elevation)
UIA (mg L-1) 0.021 (total)
0.012 (allowed elevation near DM4)
0.015 (allowed elevation near DM5)
0.021 (total)
0.016 (allowed elevation near NM3)
0.015 (allowed elevation near NM5)
Note: While the Assessment Area also covers the Deep Bay WCZ (Inner Subzone), no WSR is
identified within the Inner Subzone. Therefore no assessment criterion is proposed.
7.4.5 Water Temperature
Cooling water discharge from the proposed additional CCGT units would
result in elevation of ambient seawater temperature. The predicted elevation
in ambient seawater temperature will be assessed against the WQO for all
WSRs except for those discussed below. The WQO allowable increase in
water temperature above ambient is 2°C at WSRs.
(1) The WQO TIN criteria is 0.7 mg L-1 for Deep Bay WCZ (Inner Subzone), yet there is no WSRs identified within the part
of the Assessment Area which is located within the Subzone.
ENVIRONMENTAL RESOURCES MANAGEMENT CASTLE PEAK POWER COMPANY LIMITED
0308057_S7_WATER_REV 3.DOCX APRIL 2016
7-20
As discussed in the previous section, the optimal operation temperature for
cooling water systems for BPPS and CPPS is below 30°C. This has been
adopted for assessment under this EIA.
Coral colonies identified along survey transect under this Project (SR18) are
located very close to existing cooling water discharge outfall of BPPS. These
coral colonies are considered adapted to thermal discharge with relatively
high ambient water temperature. The proposed assessment criterion is
considered only for reference at this WSR.
7.4.6 Criteria for Dissolved Metals and Organic Compounds
There are no existing regulatory standards or guidelines for dissolved metals
and organic contaminants in the marine waters of Hong Kong. It is thus
proposed to make reference to relevant international standards and this
approach has been adopted in previous approved EIAs, i.e., EIA for
Decommissioning of Cheoy Lee Shipyard at Penny’s Bay (1), EIA for Disposal
of Contaminated Mud in the East Sha Chau Marine Borrow Pit (2), EIA for
Wanchai Development Phase II (3), EIA for Liquefied Natural Gas (LNG)
Receiving Terminal and Associated Facilities (4), and EIA for Hong Kong
Offshore Wind Farm in Southeastern Waters ( 5 ). Table 7.10 shows the
assessment criteria for dissolved metals and organic compounds for this
Study.
Table 7.10 Summary of Assessment Criteria for Dissolved Metals and Organic
Compounds
Parameter Unit Assessment Criteria for this EIA
Metals
Cadmium (Cd) g L-1 2.5 (a) (b)
Chromium (Cr) g L-1 15 (a) (b)
Copper (Cu) g L-1 5 (a) (b)
Nickel (Ni) g L-1 30 (a) (b)
Lead (Pb) g L-1 25 (a) (b)
Zinc (Zn) g L-1 40 (a) (c)
Mercury (Hg) g L-1 0.3 (b)
Arsenic (As) g L-1 25 (a) (b)
Silver (Ag) g L-1 1.9 (d)
Total PAHs g L-1 3.0 (f)
Total PCBs g L-1 0.03 (d)
Tributyltin (TBT) g L-1 0.1 (e)
Notes:
(1) Maunsell (2002). EIA for Decommissioning of Cheoy Lee Shipyard at Penny's Bay. For Civil Engineering
Department, Hong Kong SAR Government.
(2) ERM – Hong Kong (1997). EIA for Disposal of Contaminated Mud in the East Sha Chau Marine Borrow Pit. For
Civil Engineering Department, Hong Kong SAR Government.
(3) Maunsell (2001). EIA for Wanchai Development Phase II - Comprehensive Feasibility Study. For Territory
Development Department, Hong Kong SAR Government.
(4) ERM - Hong Kong, Ltd (2006) EIA Study for Liquefied Natural Gas (LNG) Receiving Terminal and Associated Facilities.
For CAPCO. Register No.: AEIAR-106/2007.
(5) BMT Asia Pacific Ltd (2009). EIA for Hong Kong Offshore Wind Farm in Southeastern Waters. For HK Offshore
Wind Limited
ENVIRONMENTAL RESOURCES MANAGEMENT CASTLE PEAK POWER COMPANY LIMITED
0308057_S7_WATER_REV 3.DOCX APRIL 2016
7-21
(a) UK Environment Agency, Environmental Quality Standards (EQS) for List 1 & 2
dangerous substances, EC Dangerous Substances Directive (76/464/EEC)
(http://www.ukmarinesac.org.uk/activities/water-quality/wq4_1.htm).
(b) Annual average dissolved concentration (i.e. usually involving filtration a 0.45-um
membrane filter before analysis).
(c) Annual average total concentration (i.e. without filtration).
(d) U.S. Environmental Protection Agency, National Recommended Water Quality Criteria,
2009. (http://www.epa.gov/waterscience/criteria/wqctable). The Criteria Maximum
Concentration (CMC) is an estimate of the highest concentration of a material in surface
water (i.e. saltwater) to which an aquatic community can be exposed briefly without
resulting in an unacceptable effect. CMC is used as the criterion of the respective
compounds in this study.
(e) Salazar MH, Salazar SM (1996) Mussels as Bioindicators: Effects of TBT on Survival,
Bioaccumulation, and Growth under Natural Conditions. In Organotin, edited by M.A.
Champ and P.F. Seligman. Chapman & Hall, London.
(f) Australian and New Zealand Environment and Conservation Council (ANZECC),
Australian and New Zealand Guidelines for Fresh and Marine Water Quality (1992)
There are no existing regulatory standards or guidelines for total PCBs, total
PAHs and tributyltin (TBT) in water and hence reference has been made to the
United States Environmental Protection Agency (USEPA) water quality
criteria, Australian water quality guidelines, and international literature,
respectively. The assessment criteria for total PCBs, total PAHs and TBT are
0.03 μg L-1, 3.0 μg L-1 and 0.1 μg L-1 respectively.
7.4.7 Criteria for Total Residual Chlorine
As per the current practice at BPPS, electrochlorination of seawater would be
conducted to control biofouling of the cooling water system. The same
arrangement would be adopted in the proposed additional CCGT units. The
stream of cooling water discharge would carry low level of residual chlorine
of less than or equal to 0.5 mg L-1 (which is the same as the existing thermal
discharge at BPPS) and be discharged into marine waters. Previous studies (1) (2 ) indicated adverse impacts on marine organisms may arise for total
residual chlorine (TRC) at or above 0.02 mg L-1. This criterion was adopted
in approved EIAs of Kai Tak Development (AEIAR-130/2009) and Desalination
Plant in Tseung Kwan O (AEIAR-192/2015), and was adopted as assessment
criterion in this EIA.
Seawater intakes (SR4, SR9, SR10, SR11 and SR16), non-gazetted beaches (SR5
and SR8) and secondary recreation subzone (SR8) are not considered sensitive
to TRC. No assessment criterion is proposed for these WSRs.
Coral colonies identified along survey transect under this Project (SR18) are
located very close to existing cooling water discharge outfall. These coral
colonies are considered adapted to exposure to thermal discharge and
associated level of TRC. Similarly, the horseshoe crab nursery grounds at
Lung Kwu Sheung Tan (SR5) are influenced by the cooling water discharge
(1) Langford, T. E. (1983). Electricity Generation and the Ecology of Natural Waters.
(2) Tender Ref. WP 98-567 Provision of Service for Ecotoxicity Testing of Marine Antifoulant – Chlorine in Hong Kong
Final Report January 2000. Submitted to Environmental Protection Department by the Centre for Coastal Pollution
and Conservation, City University of Hong Kong.
ENVIRONMENTAL RESOURCES MANAGEMENT CASTLE PEAK POWER COMPANY LIMITED
0308057_S7_WATER_REV 3.DOCX APRIL 2016
7-22
from the nearby CPPS which contains TRC. These marine ecological
sensitive receivers are considered adapted to exposure to a background TRC
level and the proposed assessment criterion is considered only for reference at
these WSRs.
7.5 ASSESSMENT METHODOLOGY
7.5.1 General Methodology
The methodology employed to assess potential water quality impacts
associated with the construction and operation of the Project is presented in
the Water Quality Modelling Method Statement (Annex 7B) and has been
based on the information presented in the Project Description (Section 3).
Full details of the scenarios examined in the modelling works are provided in
Annex 7B. Results of model verification are provided in Annex 7C. The
WSRs assessed are presented in Figure 7.1.
7.5.2 Uncertainties in Assessment Methodology
Uncertainties in Sediment Transport Assessment
Uncertainties in the assessment of the impacts from sediment plumes have
been considered when drawing conclusions from the assessment. In carrying
out the assessment, the worst case assumptions have been made in order to
provide a conservative assessment of environmental impacts. These
assumptions are considered in detail in Annex 7B Water Quality Modelling
Method Statement and are not further discussed here.
Uncertainties arising from Operations
Uncertainties in operation phase thermal discharge modelling have been
identified in Annex 7B Water Quality Modelling Method Statement. To ensure
robustness of modelling assessment, conservative assumptions have been
made to address the uncertainties from future operation. These assumptions
include:
Temperature and level of TRC of effluent from the additional CCGT units
were assumed to be released at their maximum level (40°C and 0.5 mg L-1)
from the plant. This ensures any fluctuation in effluent quality of
effluent from the additional CCGT units within specified limit will not
result in water quality impact beyond the modelled worst case; and
Model spin up was conducted for multiple tidal spring-neap cycles to
ensure sufficient background build-up of heat and TRC, if any, could be
captured in the modelling.
ENVIRONMENTAL RESOURCES MANAGEMENT CASTLE PEAK POWER COMPANY LIMITED
0308057_S7_WATER_REV 3.DOCX APRIL 2016
7-23
7.6 POTENTIAL SOURCES OF IMPACT
Potential sources of impacts to water quality arising from the Project may
occur during both the construction and operation phases. Each is discussed
in turn below.
7.6.1 Construction Phase
As described in Section 3, the Project would be implemented in phases for the
two additional CCGT units. No marine works would be required for the
construction of CCGT Unit No.1. Land-based construction activities of
CCGT Unit No.1 have the potential to affect water quality through land-based
site runoff, sewage effluent from construction workforce, and chemical
cleaning during pre-commissioning activities.
Should the additional CCGT Unit No.2 be installed, marine-based and land-
based construction activities have the potential to affect water quality through:
Changes in water quality, including suspended sediment dispersion,
sediment deposition, DO depletion, and elevated concentrations of
nutrients, heavy metals and micro-organic pollutants, due to marine
dredging at proposed outfall and seawater intake. Other marine
construction detailed in Section 3 and Annex 7B would not involve
significant sediment disturbance;
Vessel discharges;
Land-based site runoff;
Sewage effluent from construction workforce; and
Chemical cleaning during pre-commissioning activities.
7.6.2 Operation Phase
The potential impacts to water quality arising from the operation of the Project
have been identified as follows:
Increase in the seawater temperature and TRC level due to the increase in
cooling water discharge from the additional CCGT units;
Potential risk of fuel spill due to the operation of the additional CCGT
units;
Potential increase in pollution loads from the increased effluent from
plant and oil interceptors;
Chemical cleaning during plant operation; and
ENVIRONMENTAL RESOURCES MANAGEMENT CASTLE PEAK POWER COMPANY LIMITED
0308057_S7_WATER_REV 3.DOCX APRIL 2016
7-24
Potential water quality impact from maintenance dredging at the
proposed seawater intake and discharge outfall for the additional CCGT
Unit No.2.
7.7 IMPACT ASSESSMENT – CONSTRUCTION PHASE
Additional cooling water intake and discharge outfall may be required for the
additional CCGT Unit No.2. Marine dredging would be required for the
construction of the cooling water intake and discharge outfall. The major
potential impacts to water quality arising from this Project during the
construction phase relate to disturbances to the seabed, re-suspension of
marine sediment, and potential physio-chemical changes in the water column
from such marine dredging. Other marine construction activities related to
the construction of intake and outfall structures for the additional CCGT Unit
No.2 include installation (and removal) of cofferdam, removal (and
reinstatement) of rock armours, filling activities etc. which may also result in
disturbance to seabed. The potential impacts on water quality are, however,
expected to be far less significant than those from the dredging operation.
Therefore the potential impact on marine water quality from dredging
operation at the proposed cooling water intake and discharge outfall would be
assessed by mathematical modelling as worst case scenario for construction
phase.
7.7.1 Suspended Solids Dispersion and Sedimentation
Marine dredging near the proposed intake and outfall will not be concurrent.
Simulation results of SS elevation arising from the marine dredging at the
proposed seawater intake in both the dry and wet seasons are presented in
Table 7.11. Results for SS elevation from the marine dredging at the proposed
discharge outfall are presented in Table 7.12. It should be highlighted that the
values presented in Table 7.11 and Table 7.12 are the maximum SS elevation
throughout the simulated tidal cycle at the specified water depth for
assessment at the WSRs. The predicted SS elevation is compared with the
proposed assessment criteria described in Section 7.4.1 and Table 7.7. Contour
plots of maximum depth-averaged and bottom SS elevation over the
simulation period for dredging at seawater intake and discharge outfall in
unmitigated scenario are also provided in Annex 7D for both seasons.
ENVIRONMENTAL RESOURCES MANAGEMENT CASTLE PEAK POWER COMPANY LIMITED
0308057_S7_WATER_REV 3.DOCX APRIL 2016
7-25
Table 7.11 Predicted Maximum Elevation in Suspended Solids and Sediment Deposition
at WSRs from Marine Dredging at Seawater Intake – Unmitigated Scenario
WSR (ID) SS Elevation (mg L-1)
Sediment Deposition
(g m-2 d-1)
Dry Season Wet Season Criteria
Dry
Season
Wet
Season
Criteria Max Criteria Max Max Max
Fisheries Sensitive Receivers
Oyster Production Area - Sheung Pak Nai (SR14) 7.82 2.1043 6.18 1.1264 - - -
Recognised Spawning/ Nursery Grounds - Fisheries
Spawning Ground in North Lantau (SR15)
6.21 0.4594 6.06 0.3992 - - -
Artificial Reef Deployment Area - Sha Chau and Lung
Kwu Chau (SR12)
9.66 0.0952 10.86 0.0691 200 2.8120 2.3965
Ecological Sensitive Receivers
Mangroves - Ngau Hom Shek (SR1) 9.69 0.5920 7.20 0.4838 - - -
Mangroves - Sheung Pak Nai (SR2) 9.69 3.7076 7.20 0.9238 - - -
Marine Park - Designated Sha Chau and Lung Kwu Chau
(SR6)
6.21 0.0896 6.06 0.0378 - - -
Marine Park - Designated Sha Chau and Lung Kwu Chau
(SR7)
6.21 0.2972 6.06 0.2453 - - -
Marine Park - Designated Sha Chau and Lung Kwu Chau
(SR13)
6.21 0.0976 6.06 0.0619 - - -
Intertidal Mudflats - Ha Pak Nai (SR3) 9.69 1.6588 7.20 1.9657 - - -
Seagrass Beds - Sheung Pak Nai (SR2) 9.69 3.7076 7.20 0.9238 - - -
Seagrass Beds - Ha Pak Nai (SR3) 9.69 1.6588 7.20 1.9657 - - -
Horseshoe Crab Nursery Grounds - Ha Pak Nai (SR3) 9.69 1.6588 7.20 1.9657 - - -
Horseshoe Crab Nursery Grounds - Ngau Hom Shek
(SR1)
9.69 0.5920 7.20 0.4838 - - -
Horseshoe Crab Nursery Grounds - Lung Kwu Sheung
Tan (SR5)
9.66 9.6917 10.86 6.7096 - - -
Coral Colonies Identified Along Survey Transect under
this Project - Transect C (SR18)
8.49 266.7900 4.50 241.8500 200 3604.8 3605.8
Water Quality Sensitive Receivers
Non-gazetted Beaches - Lung Kwu Sheung Tan (SR5) 6.21 4.9835 6.06 3.3953 - - -
Non-gazetted Beaches - Lung Kwu Tan (SR8) 6.21 6.3219 6.06 3.4352 - - -
Secondary Recreation Subzone - North Western Water
Control Zone (SR8)
6.21 6.3219 6.06 3.4352 - - -
Seawater Intakes - Black Point Power Station (SR4) 700.00 7.0058 700.00 29.0970 - - -
Seawater Intakes - Castle Peak Power Station (SR9) 700.00 2.1536 700.00 1.5957 - - -
Seawater Intakes - Tuen Mun Area 38 (SR11) 5.49 1.3638 6.00 0.8333 - - -
Seawater Intakes - Shiu Wing Steel Mill (SR10) 5.49 1.6632 6.00 0.9952 - - -
Seawater Intakes - Sludge Treatment Facilities (SR16) 8.49 8.5693 4.50 11.1400 - - -
Note:
Bold and underlined figures indicate exceedance of WQO.
ENVIRONMENTAL RESOURCES MANAGEMENT CASTLE PEAK POWER COMPANY LIMITED
0308057_S7_WATER_REV 3.DOCX APRIL 2016
7-26
Table 7.12 Predicted Maximum Elevation in Suspended Solids and Sediment Deposition
at WSRs from Marine Dredging at Discharge Outfall – Unmitigated Scenario
WSR (ID) SS Elevation (mg L-1)
Sediment Deposition
(g m-2 d-1)
Dry Season Wet Season Criteria
Dry
Season
Wet
Season
Criteria Max Criteria Max Max Max
Fisheries Sensitive Receivers
Oyster Production Area - Sheung Pak Nai (SR14) 7.82 3.5387 6.18 2.3172 - - -
Recognised Spawning/ Nursery Grounds - Fisheries
Spawning Ground in North Lantau (SR15)
6.21 0.3933 6.06 0.2979 - - -
Artificial Reef Deployment Area - Sha Chau and Lung
Kwu Chau (SR12)
9.66 0.0919 10.86 0.0625 200 2.6432 1.6105
Ecological Sensitive Receivers
Mangroves - Ngau Hom Shek (SR1) 9.69 1.4292 7.20 1.0506 - - -
Mangroves - Sheung Pak Nai (SR2) 9.69 5.8988 7.20 1.9499 - - -
Marine Park - Designated Sha Chau and Lung Kwu Chau
(SR6)
6.21 0.0829 6.06 0.0328 - - -
Marine Park - Designated Sha Chau and Lung Kwu Chau
(SR7)
6.21 0.2534 6.06 0.1743 - - -
Marine Park - Designated Sha Chau and Lung Kwu Chau
(SR13)
6.21 0.0941 6.06 0.0456 - - -
Intertidal Mudflats - Ha Pak Nai (SR3) 9.69 7.6504 7.20 4.1168 - - -
Seagrass Beds - Sheung Pak Nai (SR2) 9.69 5.8988 7.20 1.9499 - - -
Seagrass Beds - Ha Pak Nai (SR3) 9.69 7.6504 7.20 4.1168 - - -
Horseshoe Crab Nursery Grounds - Ha Pak Nai (SR3) 9.69 7.6504 7.20 4.1168 - - -
Horseshoe Crab Nursery Grounds - Ngau Hom Shek
(SR1)
9.69 1.4292 7.20 1.0506 - - -
Horseshoe Crab Nursery Grounds - Lung Kwu Sheung
Tan (SR5)
9.66 8.5051 10.86 5.3648 - - -
Coral Colonies Identified Along Survey Transect under
this Project - Transect C (SR18)
8.49 191.0800 4.50 72.4190 200 3,444.8 1,225.9
Water Quality Sensitive Receivers
Non-gazetted Beaches - Lung Kwu Sheung Tan (SR5) 6.21 3.4058 6.06 2.6735 - - -
Non-gazetted Beaches - Lung Kwu Tan (SR8) 6.21 3.5000 6.06 2.6116 - - -
Secondary Recreation Subzone - North Western Water
Control Zone (SR8)
6.21 3.5000 6.06 2.6116 - - -
Seawater Intakes - Black Point Power Station (SR4) 700.00 4.0603 700.00 22.6030 - - -
Seawater Intakes - Castle Peak Power Station (SR9) 700.00 1.6531 700.00 1.3559 - - -
Seawater Intakes - Tuen Mun Area 38 (SR11) 5.49 1.1559 6.00 0.7558 - - -
Seawater Intakes - Shiu Wing Steel Mill (SR10) 5.49 1.3290 6.00 0.8726 - - -
Seawater Intakes - Sludge Treatment Facilities (SR16) 8.49 28.2150 4.50 19.6770 - - -
Note:
Bold and underlined figures indicate exceedance of WQO.
Compliance with the corresponding assessment criteria for SS elevation and
sedimentation flux is predicted at a majority of the WSRs in both seasons. A
number of exceedances of the WQO SS elevation criterion are predicted for
dredging at the seawater intake and discharge outfall in both seasons. For
dredging at seawater intake in the dry season, the sediment plume mainly
affects WSRs along the shoreline of Deep Bay as well as the Lung Kwu Tan
embayment (Annex 7D). Elevation of SS is predicted to be above the
corresponding assessment criteria at coral colonies identified along survey
transect under this Project at Transect C (SR18), horseshoe crab nursery
ground at Lung Kwu Sheung Tan (SR5) and seawater intake for Sludge
ENVIRONMENTAL RESOURCES MANAGEMENT CASTLE PEAK POWER COMPANY LIMITED
0308057_S7_WATER_REV 3.DOCX APRIL 2016
7-27
Treatment Facilities (SR16) for dredging at seawater intake in the dry season.
For SR18, the predicted SS elevations are high because of the short distance
from the dredging area, and the corresponding maximum sedimentation flux
is predicted to exceed the assessment criterion for sedimentation. A similar
pattern of SS elevation and exceedance of the corresponding assessment
criteria is also predicted for dredging at seawater intake in the wet season.
For dredging at discharge outfall, the overall zone of influence of SS elevation
is predicted to shift to the northeast of the dredging area. The predicted SS
elevation at the Lung Kwu Tan embayment is significantly smaller due to the
longer distance from the dredging area. Also, as the dredging area for the
proposed new outfall is located northeast to the existing outfall, the discharge
from the existing outfall carries the sediment plume from the dredging area
away from the shore and dilute the sediment plume. As a result, the
predicted SS elevation is much lower for most of the WSRs. Elevation of SS
above the corresponding assessment criterion is predicted at SR16 and SR18 in
both seasons. SR18 remains the most impacted receivers in both seasons
because of the very short distance from the dredging area.
To mitigate potential impacts on SR 16 and SR18, mitigation measures in form
of silt curtain around grab dredger are proposed to be adopted for the
dredging at both the proposed seawater intake and discharge outfall. Silt
curtains are highly effective in areas where current speeds are low, but the
effectiveness of the silt curtains will be reduced in areas of high current
speeds. Hydrodynamic simulation by Delft3D indicated that tidal current
near the proposed outfall and seawater intake would be in general below 0.2
m/s, which is deemed appropriate for the use of silt curtain. According to
the Contaminated Spoil Management Study (1), the implementation of silt
curtain around the closed grab dredgers will reduce the dispersion of SS by a
factor of 4 (or about 75%). This SS reduction factors have been adopted in a
number of past studies involving release of marine sediment, including the
approved SCL Hung Hom to Admiralty Section, IWMF, WDII & CWB EIA,
CT Dredging EIA as well as the Western Coast Road EIA study.
Furthermore, the rate of dredging at the both the seawater intake and
discharge outfall is also proposed to be reduced from 4,000 m3 per day (in the
unmitigated scenario) to 740 m3 per day. Under the mitigated scenario of
this Project, the combined use of silt curtain and reduction of dredging rate
would significantly reduce the level of SS elevation at SR16 and SR18. To
provide further protection to coral colonies at SR18, an additional single layer
of floating type silt curtain is proposed to surround the coral colonies at SR18.
Similar arrangement was proposed in the approved EIA for Liquefied Natural
Gas (LNG) Receiving Terminal and Associated Facilities (2) for the protection
of nearby marine ecological and fisheries WSRs. A sediment reduction factor
of 2.5 (equivalent to 60% reduction) was assumed in the approved LNG EIA
and is also adopted in this assessment. The predicted SS elevations and
(1) Mott MacDonald (1991). Contaminated Spoil Management Study, Final Report, Volume 1, for EPD, October 1991.
(2) ERM - Hong Kong, Ltd (2006) EIA Study for Liquefied Natural Gas (LNG) Receiving Terminal and Associated Facilities.
For CAPCO. Register No.: AEIAR-106/2007.
ENVIRONMENTAL RESOURCES MANAGEMENT CASTLE PEAK POWER COMPANY LIMITED
0308057_S7_WATER_REV 3.DOCX APRIL 2016
7-28
sediment deposition with the implementation of silt curtains and reduced
dredging rate are presented in Table 7.13 and Table 7.14 for dredging at
seawater intake and discharge outfall respectively. Full compliance with the
corresponding assessment criteria for SS elevation and sedimentation flux is
predicted in both seasons. The corresponding instantaneous SS elevation at
depth-averaged and bottom layer of the water column on typical working day
for dredging at seawater intake and discharge outfall for mitigated scenario
are also provided in Annex 7D for both seasons.
Table 7.13 Predicted Maximum Elevation in Suspended Solids and Sediment Deposition
at WSRs from Marine Dredging at Seawater Intake – Mitigated Scenario
WSR (ID) SS Elevation (mg L-1)
Sediment Deposition
(g m-2 d-1)
Dry Season Wet Season Criteria
Dry
Season
Wet
Season
Criteria Max Criteria Max Max Max
Fisheries Sensitive Receivers
Oyster Production Area - Sheung Pak Nai (SR14) 7.82 0.0973 6.18 0.0521 - - -
Recognised Spawning/ Nursery Grounds - Fisheries
Spawning Ground in North Lantau (SR15)
6.21 0.0212 6.06 0.0185 - - -
Artificial Reef Deployment Area - Sha Chau and Lung Kwu
Chau (SR12)
9.66 0.0044 10.86 0.0032 200 0.1301 0.1108
Ecological Sensitive Receivers
Mangroves - Ngau Hom Shek (SR1) 9.69 0.0274 7.20 0.0224 - - -
Mangroves - Sheung Pak Nai (SR2) 9.69 0.1715 7.20 0.0427 - - -
Marine Park - Designated Sha Chau and Lung Kwu Chau
(SR6)
6.21 0.0041 6.06 0.0017 - - -
Marine Park - Designated Sha Chau and Lung Kwu Chau
(SR7)
6.21 0.0137 6.06 0.0113 - - -
Marine Park - Designated Sha Chau and Lung Kwu Chau
(SR13)
6.21 0.0045 6.06 0.0029 - - -
Intertidal Mudflats - Ha Pak Nai (SR3) 9.69 0.0767 7.20 0.0909 - - -
Seagrass Beds - Sheung Pak Nai (SR2) 9.69 0.1715 7.20 0.0427 - - -
Seagrass Beds - Ha Pak Nai (SR3) 9.69 0.0767 7.20 0.0909 - - -
Horseshoe Crab Nursery Grounds - Ha Pak Nai (SR3) 9.69 0.0767 7.20 0.0909 - - -
Horseshoe Crab Nursery Grounds - Ngau Hom Shek (SR1) 9.69 0.0274 7.20 0.0224 - - -
Horseshoe Crab Nursery Grounds - Lung Kwu Sheung Tan
(SR5)
9.66 0.4482 10.86 0.3103 - - -
Coral Colonies Identified Along Survey Transect under this
Project - Transect C (SR18)
8.49 4.9356 4.50 4.4742 200 66.6888 66.7073
Water Quality Sensitive Receivers
Non-gazetted Beaches - Lung Kwu Sheung Tan (SR5) 6.21 0.2305 6.06 0.1570 - - -
Non-gazetted Beaches - Lung Kwu Tan (SR8) 6.21 0.2924 6.06 0.1589 - - -
Secondary Recreation Subzone - North Western Water
Control Zone (SR8)
6.21 0.2924 6.06 0.1589 - - -
Seawater Intakes - Black Point Power Station (SR4) 700.00 0.3240 700.00 1.3457 - - -
Seawater Intakes - Castle Peak Power Station (SR9) 700.00 0.0996 700.00 0.0738 - - -
Seawater Intakes - Tuen Mun Area 38 (SR11) 5.49 0.0631 6.00 0.0385 - - -
Seawater Intakes - Shiu Wing Steel Mill (SR10) 5.49 0.0769 6.00 0.0460 - - -
Seawater Intakes - Sludge Treatment Facilities (SR16) 8.49 0.3963 4.50 0.5152 - - -
Note:
Bold and underlined figures indicate exceedance of WQO.
ENVIRONMENTAL RESOURCES MANAGEMENT CASTLE PEAK POWER COMPANY LIMITED
0308057_S7_WATER_REV 3.DOCX APRIL 2016
7-29
Table 7.14 Predicted Maximum Elevation in Suspended Solids and Sediment Deposition
at WSRs from Marine Dredging at Discharge Outfall – Mitigated Scenario
WSR (ID) SS Elevation (mg L-1)
Sediment Deposition
(g m-2 d-1)
Dry Season Wet Season Criteria
Dry
Season
Wet
Season
Criteria Max Criteria Max Max Max
Fisheries Sensitive Receivers
Oyster Production Area - Sheung Pak Nai (SR14) 7.82 0.1637 6.18 0.1072 - - -
Recognised Spawning/ Nursery Grounds - Fisheries
Spawning Ground in North Lantau (SR15)
6.21 0.0182 6.06 0.0138 - - -
Artificial Reef Deployment Area - Sha Chau and Lung Kwu
Chau (SR12)
9.66 0.0043 10.86 0.0029 200 0.1222 0.0745
Ecological Sensitive Receivers
Mangroves - Ngau Hom Shek (SR1) 9.69 0.0661 7.20 0.0486 - - -
Mangroves - Sheung Pak Nai (SR2) 9.69 0.2728 7.20 0.0902 - - -
Marine Park - Designated Sha Chau and Lung Kwu Chau
(SR6)
6.21 0.0038 6.06 0.0015 - - -
Marine Park - Designated Sha Chau and Lung Kwu Chau
(SR7)
6.21 0.0117 6.06 0.0081 - - -
Marine Park - Designated Sha Chau and Lung Kwu Chau
(SR13)
6.21 0.0044 6.06 0.0021 - - -
Intertidal Mudflats - Ha Pak Nai (SR3) 9.69 0.3538 7.20 0.1904 - - -
Seagrass Beds - Sheung Pak Nai (SR2) 9.69 0.2728 7.20 0.0902 - - -
Seagrass Beds - Ha Pak Nai (SR3) 9.69 0.3538 7.20 0.1904 - - -
Horseshoe Crab Nursery Grounds - Ha Pak Nai (SR3) 9.69 0.3538 7.20 0.1904 - - -
Horseshoe Crab Nursery Grounds - Ngau Hom Shek (SR1) 9.69 0.0661 7.20 0.0486 - - -
Horseshoe Crab Nursery Grounds - Lung Kwu Sheung Tan
(SR5)
9.66 0.3934 10.86 0.2481 - - -
Coral Colonies Identified Along Survey Transect under this
Project - Transect C (SR18)
8.49 3.5350 4.50 1.3398 200 63.7288 22.6792
Water Quality Sensitive Receivers
Non-gazetted Beaches - Lung Kwu Sheung Tan (SR5) 6.21 0.1575 6.06 0.1236 - - -
Non-gazetted Beaches - Lung Kwu Tan (SR8) 6.21 0.1619 6.06 0.1208 - - -
Secondary Recreation Subzone - North Western Water
Control Zone (SR8)
6.21 0.1619 6.06 0.1208 - - -
Seawater Intakes - Black Point Power Station (SR4) 700.00 0.1878 700.00 1.0454 - - -
Seawater Intakes - Castle Peak Power Station (SR9) 700.00 0.0765 700.00 0.0627 - - -
Seawater Intakes - Tuen Mun Area 38 (SR11) 5.49 0.0535 6.00 0.0350 - - -
Seawater Intakes - Shiu Wing Steel Mill (SR10) 5.49 0.0615 6.00 0.0404 - - -
Seawater Intakes - Sludge Treatment Facilities (SR16) 8.49 1.3049 4.50 0.9101 - - -
Note:
Bold and underlined figures indicate exceedance of WQO.
In conclusion, with the implementation of mitigation measures to control the
dispersion of SS, including (1) reduction from dredging rate from 4,000 m3 per
day to 740 m3 per day, (2) implementation of silt curtain at grab dredger
(which reduce sediment loss rate by 75% and (3) implementation of silt curtain
near coral colonies SR18 (which reduce sediment level at SR18 by 60%), no
unacceptable water quality impact on nearby WSRs would be expected.
ENVIRONMENTAL RESOURCES MANAGEMENT CASTLE PEAK POWER COMPANY LIMITED
0308057_S7_WATER_REV 3.DOCX APRIL 2016
7-30
7.7.2 Dissolved Oxygen Depletion
The degree of DO depletion exerted by a sediment plume is a function of the
sediment oxygen demand of the sediment, its concentration in the water
column and the rate of oxygen replenishment. The impact of the sediment
oxygen demand on DO concentrations has been calculated based on the
following equation (1):
DO (mg O2 L-1) = DO ( g O2/m3) = SS (g DW/m3) × fraction of organic matter
in sediment (g C/g DW) × 2.67 (g O2/gC)
The assumption behind this equation is that all the released organic matter is
eventually re-mineralized within the water column. This leads to an
estimated depletion with respect to the background DO concentrations. This
DO depletion depends on the quality of the released sediments, i.e. on the
percentage of organic matter in the sediment. The fraction of organic matter
in sediment (Chemical oxygen demand in Table 7.3) was taken as 18,000 mg
kg-1 based on maximum data from EPD sediment monitoring station DS4
located near the Project from 2005-2014. It should be noted that other EPD
sediment monitoring stations are much further away from the Project site (>3
km) and therefore the adoption of DS4 is deemed the most appropriate.
This is a conservative prediction of DO depletion since oxygen depletion is not
instantaneous and will depend on tidally averaged suspended sediment
concentrations. It is worth noting that the above equation does not account
for re-aeration which would tend to reduce impacts of the SS on DO
concentrations in the water column. The proposed analysis, which is on the
conservative side, will not, therefore, underestimate the DO depletion.
Further, it should be noted that, for sediment in suspension to exert any
oxygen demand in the water column it will take time and, at the same time,
the sediment will be transported and mixed or dispersed with oxygenated
water. As a result, the oxygen demand and the impact on DO concentrations
will diminish as the suspended sediment concentrations decrease.
The predicted maximum DO depletion at all WSRs are presented in Table 7.15
and Table 7.16 for dredging at seawater intake and discharge outfall
respectively. Overall, the predicted maximum DO depletion is quite low at
all WSRs, with maximum DO depletion predicted to be below 0.1 mg L-1.
Contour plots showing the predicted maximum DO depletion are also
provided in Annex 7D.
(1) ERM - HK Ltd (2010). Development of an Offshore Wind Farm in Hong Kong. Final Environmental Impact
Assessment. For the Hong Kong Electric Company
ENVIRONMENTAL RESOURCES MANAGEMENT CASTLE PEAK POWER COMPANY LIMITED
0308057_S7_WATER_REV 3.DOCX APRIL 2016
7-31
Table 7.15 Predicted Maximum Dissolved Oxygen Depletion from Marine Dredging at
Seawater Intake – Mitigated Scenario
WSR (ID) Unit for SS Elevation and DO Depletion: mg L-1
Annual Dry Season Wet Season
Max SS
Elevation(a)
Allowed
DO
Depletion
Max DO
Depletion
Max SS
Elevation
Allowed
DO
Depletion
Max DO
Depletion
Max SS
Elevation
Allowed
DO
Depletion
Max DO
Depletion
Fisheries Sensitive Receivers
Oyster Production Area -
Sheung Pak Nai (SR14)
0.0973 0.69 0.0018 0.0973 1.75 0.0018 0.0521 0.32 0.0009
Recognised Spawning/
Nursery Grounds -
Fisheries Spawning
Ground in North Lantau
(SR15)
0.0212 0.19 0.0004 0.0212 1.98 0.0004 0.0185 - (b) 0.0003
Artificial Reef
Deployment Area - Sha
Chau and Lung Kwu
Chau (SR12)
0.0044 1.09 0.0001 0.0044 3.98 0.0001 0.0032 0.89 0.0001
Ecological Sensitive Receivers
Mangroves - Ngau Hom
Shek (SR1) 0.0274 2.40 0.0005 0.0274 3.69 0.0005 0.0224 2.08 0.0004
Mangroves - Sheung Pak
Nai (SR2) 0.1715 2.40 0.0031 0.1715 3.69 0.0031 0.0427 2.08 0.0008
Marine Park - Designated
Sha Chau and Lung Kwu
Chau (SR6)
0.0041 0.19 0.0001 0.0041 1.98 0.0001 0.0017 - (b) 0.0000
Marine Park - Designated
Sha Chau and Lung Kwu
Chau (SR7)
0.0137 0.19 0.0002 0.0137 1.98 0.0002 0.0113 - (b) 0.0002
Marine Park - Designated
Sha Chau and Lung Kwu
Chau (SR13)
0.0045 0.19 0.0001 0.0045 1.98 0.0001 0.0029 - (b) 0.0001
Intertidal Mudflats - Ha
Pak Nai (SR3) 0.0909 2.40 0.0016 0.0767 3.69 0.0014 0.0909 2.08 0.0016
Seagrass Beds - Sheung
Pak Nai (SR2)
0.1715 2.40 0.0031 0.1715 3.69 0.0031 0.0427 2.08 0.0008
Seagrass Beds - Ha Pak
Nai (SR3)
0.0909 2.40 0.0016 0.0767 3.69 0.0014 0.0909 2.08 0.0016
Horseshoe Crab Nursery
Grounds - Ha Pak Nai
(SR3)
0.0909 2.40 0.0016 0.0767 3.69 0.0014 0.0909 2.08 0.0016
Horseshoe Crab Nursery
Grounds - Ngau Hom
Shek (SR1)
0.0274 2.40 0.0005 0.0274 3.69 0.0005 0.0224 2.08 0.0004
Horseshoe Crab Nursery
Grounds - Lung Kwu
Sheung Tan (SR5)
0.4482 1.09 0.0081 0.4482 3.98 0.0081 0.3103 0.89 0.0056
Coral Colonies Identified
Along Survey Transect
under this Project -
Transect C (SR18)
4.9356 2.09 0.0888 4.9356 4.09 0.0888 4.4742 1.90 0.0805
Water Quality Sensitive Receivers
Non-gazetted Beaches -
Lung Kwu Sheung Tan
(SR5)
0.2305 0.19 0.0041 0.2305 1.98 0.0041 0.157 - (b) 0.0028
Non-gazetted Beaches -
Lung Kwu Tan (SR8) 0.2924 0.19 0.0053 0.2924 1.98 0.0053 0.1589 - (b) 0.0029
Secondary Recreation
Subzone - North Western
Water Control Zone (SR8)
0.2924 0.19 0.0053 0.2924 1.98 0.0053 0.1589 - (b) 0.0029
Seawater Intakes - Black
Point Power Station (SR4)
1.3457 N/A (c) 0.0242 0.324 N/A (c) 0.0058 1.3457 N/A (c) 0.0242
ENVIRONMENTAL RESOURCES MANAGEMENT CASTLE PEAK POWER COMPANY LIMITED
0308057_S7_WATER_REV 3.DOCX APRIL 2016
7-32
WSR (ID) Unit for SS Elevation and DO Depletion: mg L-1
Annual Dry Season Wet Season
Max SS
Elevation(a)
Allowed
DO
Depletion
Max DO
Depletion
Max SS
Elevation
Allowed
DO
Depletion
Max DO
Depletion
Max SS
Elevation
Allowed
DO
Depletion
Max DO
Depletion
Seawater Intakes - Castle
Peak Power Station (SR9)
0.0996 N/A (c) 0.0018 0.0996 N/A (c) 0.0018 0.0738 N/A (c) 0.0013
Seawater Intakes - Tuen
Mun Area 38 (SR11)
0.0631 1.40 0.0011 0.0631 3.90 0.0011 0.0385 1.10 0.0007
Seawater Intakes - Shiu
Wing Steel Mill (SR10)
0.0769 1.40 0.0014 0.0769 3.90 0.0014 0.046 1.10 0.0008
Seawater Intakes - Sludge
Treatment Facilities
(SR16)
0.5152 2.09 0.0093 0.3963 4.09 0.0071 0.5152 1.90 0.0093
Note:
(a) Max SS elevation for “Annual” column is the higher prediction among two seasons.
(b) For WSRs where DO level is below the corresponding WQO criterion, the “Allowed DO Depletion” is shown as “ -“. Any
observable level of DO depletion (i.e. ≥0.0001) is considered exceedance and is shown in bold and underline under such circumstance.
(c) Cooling water intakes for power stations are not considered sensitive to DO depletion. Therefore no assessment criterion and
allowed DO depletion are provided. The predicted values for DO depletion are for reference only.
Table 7.16 Predicted Maximum Dissolved Oxygen Depletion from Marine Dredging at
Discharge Outfall – Mitigated Scenario
WSR (ID) Unit for SS Elevation and DO Depletion: mg L-1
Annual Dry Season Wet Season
Max SS
Elevation(a)
Allowed
DO
Depletion
Max DO
Depletion
Max SS
Elevation
Allowed
DO
Depletion
Max DO
Depletion
Max SS
Elevation
Allowed
DO
Depletion
Max DO
Depletion
Fisheries Sensitive Receivers
Oyster Production Area -
Sheung Pak Nai (SR14)
0.1637 0.69 0.0029 0.1637 1.75 0.0029 0.1072 0.32 0.0019
Recognised Spawning/
Nursery Grounds -
Fisheries Spawning
Ground in North Lantau
(SR15)
0.0182 0.19 0.0003 0.0182 1.98 0.0003 0.0138 - (b) 0.0002
Artificial Reef
Deployment Area - Sha
Chau and Lung Kwu
Chau (SR12)
0.0043 1.09 0.0001 0.0043 3.98 0.0001 0.0029 0.89 0.0001
Ecological Sensitive Receivers
Mangroves - Ngau Hom
Shek (SR1) 0.0661 2.40 0.0012 0.0661 3.69 0.0012 0.0486 2.08 0.0009
Mangroves - Sheung Pak
Nai (SR2) 0.2728 2.40 0.0049 0.2728 3.69 0.0049 0.0902 2.08 0.0016
Marine Park - Designated
Sha Chau and Lung Kwu
Chau (SR6)
0.0038 0.19 0.0001 0.0038 1.98 0.0001 0.0015 - (b) 0.0000
Marine Park - Designated
Sha Chau and Lung Kwu
Chau (SR7)
0.0117 0.19 0.0002 0.0117 1.98 0.0002 0.0081 - (b) 0.0001
Marine Park - Designated
Sha Chau and Lung Kwu
Chau (SR13)
0.0044 0.19 0.0001 0.0044 1.98 0.0001 0.0021 - (b) 0.0000
Intertidal Mudflats - Ha
Pak Nai (SR3)
0.3538 2.40 0.0064 0.3538 3.69 0.0064 0.1904 2.08 0.0034
Seagrass Beds - Sheung
Pak Nai (SR2)
0.2728 2.40 0.0049 0.2728 3.69 0.0049 0.0902 2.08 0.0016
ENVIRONMENTAL RESOURCES MANAGEMENT CASTLE PEAK POWER COMPANY LIMITED
0308057_S7_WATER_REV 3.DOCX APRIL 2016
7-33
WSR (ID) Unit for SS Elevation and DO Depletion: mg L-1
Annual Dry Season Wet Season
Max SS
Elevation(a)
Allowed
DO
Depletion
Max DO
Depletion
Max SS
Elevation
Allowed
DO
Depletion
Max DO
Depletion
Max SS
Elevation
Allowed
DO
Depletion
Max DO
Depletion
Seagrass Beds - Ha Pak
Nai (SR3)
0.3538 2.40 0.0064 0.3538 3.69 0.0064 0.1904 2.08 0.0034
Horseshoe Crab Nursery
Grounds - Ha Pak Nai
(SR3)
0.3538 2.40 0.0064 0.3538 3.69 0.0064 0.1904 2.08 0.0034
Horseshoe Crab Nursery
Grounds - Ngau Hom
Shek (SR1)
0.0661 2.40 0.0012 0.0661 3.69 0.0012 0.0486 2.08 0.0009
Horseshoe Crab Nursery
Grounds - Lung Kwu
Sheung Tan (SR5)
0.3934 1.09 0.0071 0.3934 3.98 0.0071 0.2481 0.89 0.0045
Coral Colonies Identified
Along Survey Transect
under this Project -
Transect C (SR18)
3.535 2.09 0.0636 3.535 4.09 0.0636 1.3398 1.90 0.0241
Water Quality Sensitive Receivers
Non-gazetted Beaches -
Lung Kwu Sheung Tan
(SR5)
0.1575 0.19 0.0028 0.1575 1.98 0.0028 0.1236 - (b) 0.0022
Non-gazetted Beaches -
Lung Kwu Tan (SR8) 0.1619 0.19 0.0029 0.1619 1.98 0.0029 0.1208 - (b) 0.0022
Secondary Recreation
Subzone - North Western
Water Control Zone (SR8)
0.1619 0.19 0.0029 0.1619 1.98 0.0029 0.1208 - (b) 0.0022
Seawater Intakes - Black
Point Power Station (SR4)
1.0454 N/A (c) 0.0188 0.1878 N/A (c) 0.0034 1.0454 N/A (c) 0.0188
Seawater Intakes - Castle
Peak Power Station (SR9)
0.0765 N/A (c) 0.0014 0.0765 N/A (c) 0.0014 0.0627 N/A (c) 0.0011
Seawater Intakes - Tuen
Mun Area 38 (SR11) 0.0535 1.40 0.0010 0.0535 3.90 0.0010 0.035 1.10 0.0006
Seawater Intakes - Shiu
Wing Steel Mill (SR10) 0.0615 1.40 0.0011 0.0615 3.90 0.0011 0.0404 1.10 0.0007
Seawater Intakes - Sludge
Treatment Facilities
(SR16)
1.3049 2.09 0.0235 1.3049 4.09 0.0235 0.9101 1.90 0.0164
Note:
(a) Max SS elevation for “Annual” column is the higher prediction among two seasons.
(b) For WSRs where DO level is below the corresponding WQO criterion, the “Allowed DO Depletion” is shown as “ -“. Any
observable level of DO depletion (i.e. ≥0.0001) is considered exceedance and is shown in bold and underline under such circumstance.
(c) Cooling water intakes for power stations are not considered sensitive to DO depletion. Therefore no assessment criterion and
allowed DO depletion are provided. The predicted values for DO depletion are for reference only.
While the highest maximum DO depletion is predicted at the coral colonies
(SR18) located next to the existing outfall which is the most impacted by SS in
both seasons, full compliance to the corresponding annual WQO assessment
criteria is predicted as well as in both seasons for this WSR. The predicted
maximum DO depletion is much lower for other WSRs. Except for those
WSRs located close to EPD monitoring station NM5, full compliance in annual
WQO DO criteria is predicted at all WSRs as well as in the dry season and wet
season separately, for both intake and outfall dredging works.
As shown in Table 7.8, the baseline 10%-percentile depth-averaged DO level is
already below the WQO criteria (4 mg L-1) at NM5 in the wet season. As
stated in item D(b) under Table 7.1, the DO criteria for WQO requires depth-
averaged DO criteria for 90% of incident throughout the year. It is
ENVIRONMENTAL RESOURCES MANAGEMENT CASTLE PEAK POWER COMPANY LIMITED
0308057_S7_WATER_REV 3.DOCX APRIL 2016
7-34
considered too conservative to assess the potential DO depletion with baseline
DO exceedance at NM5 in wet season. The annual baseline 10%-percentile
depth-averaged DO level, together with the worst case DO depletion
predicted, would be used for assessment for WSRs located near NM5 (SR6,
SR7, SR8, SR13 and SR15). For both the intake and outfall dredging works,
the predicted DO depletion at these WSRs is below 0.01 mg L-1 in both
seasons, which is considered minimal, and compliance to the annual WQO
DO criteria is also predicted at these WSRs. In view of the above, no
unacceptable DO depletion impact from both intake and outfall dredging
works is expected.
7.7.3 Nutrients
Other than readily-biodegradable organic compounds (which are assessed in
the previous section), sediment-bounded nitrogenous compounds could also
be released into the water column and result in an increase of TIN and UIA.
To quantify the elevation in TIN and UIA from the proposed dredging
operation, mathematical modelling has been conducted using an inert tracer.
Review of sediment quality data (Table 7.3) indicated that the level of TKN is
similar among the four EPD sediment monitoring stations near the Project site.
For assessing the potential release of nitrogenous species from sediment, the
maximum TKN level at DS4 (560 mg kg-1) was taken for calculation of
potential TIN and UIA elevation. While nitrate and nitrite may also be
constituent of TIN in marine water, they are generally in negligible
concentration because of low electrochemical potential of marine sediment.
Under low electrochemical potential (i.e. reducing environment), oxidized
forms of nitrogen (e.g. nitrate and nitrite) tend to be reduced to their reduced
form (e.g. ammonia), and thus is considered as part of TKN. Therefore the
contribution of TIN from nitrate and nitrite is negligible and was not
considered. Since TKN takes into account both organic nitrogen and
ammonia nitrogen, TKN level in sediment already represents the vast majority
of nitrogen content in sediment, and is thus considered sufficiently
conservative for the assessment.
EPD marine water quality monitoring data at DM5 from 2005 to 2014 also
indicated that on average 3.78% of ammonia nitrogen exists as UIA. This
ratio would be adopted to determine the elevation of UIA at WSRs from the
corresponding elevation of TIN (i.e. assuming 100% of TIN exists in form of
ammonia nitrogen).
The predicted maximum elevations of TIN and UIA at WSRs for dredging at
seawater intake and discharge outfall in the dry and wet season, taking into
account the mitigation measures recommended under Section 7.7.1, are
provided in Table 7.17. Contour plots for maximum TIN and UIA elevation
throughout the modelling period are provided in Annex 7E.
ENVIRONMENTAL RESOURCES MANAGEMENT CASTLE PEAK POWER COMPANY LIMITED
0308057_S7_WATER_REV 3.DOCX APRIL 2016
7-35
Table 7.17 Predicted Maximum TIN and UIA Elevation at WSRs for Dredging at
Seawater Intake and Discharge Outfall in Dry and Wet Season
WSR (ID) TIN (mg L-1) UIA (mg L-1)
Criteria Intake Outfall Criteria Intake Outfall
Dry Wet Dry Wet Dry Wet Dry Wet
Fisheries Sensitive Receivers
Oyster Production Area -
Sheung Pak Nai (SR14)
0.005 <0.001 <0.001 <0.001 <0.001 0.012 <0.0001 <0.0001 <0.0001 <0.0001
Recognised Spawning/
Nursery Grounds - Fisheries
Spawning Ground in North
Lantau (SR15)
0.005 <0.001 <0.001 <0.001 <0.001 0.015 <0.0001 <0.0001 <0.0001 <0.0001
Artificial Reef Deployment
Area - Sha Chau and Lung
Kwu Chau (SR12)
0.005 <0.001 <0.001 <0.001 <0.001 0.015 <0.0001 <0.0001 <0.0001 <0.0001
Ecological Sensitive Receivers
Mangroves - Ngau Hom Shek
(SR1)
0.005 <0.001 <0.001 <0.001 <0.001 0.012 <0.0001 <0.0001 <0.0001 <0.0001
Mangroves - Sheung Pak Nai
(SR2)
0.005 <0.001 <0.001 <0.001 <0.001 0.012 <0.0001 <0.0001 <0.0001 <0.0001
Marine Park - Designated Sha
Chau and Lung Kwu Chau
(SR6)
0.005 <0.001 <0.001 <0.001 <0.001 0.015 <0.0001 <0.0001 <0.0001 <0.0001
Marine Park - Designated Sha
Chau and Lung Kwu Chau
(SR7)
0.005 <0.001 <0.001 <0.001 <0.001 0.015 <0.0001 <0.0001 <0.0001 <0.0001
Marine Park - Designated Sha
Chau and Lung Kwu Chau
(SR13)
0.005 <0.001 <0.001 <0.001 <0.001 0.015 <0.0001 <0.0001 <0.0001 <0.0001
Intertidal Mudflats - Ha Pak
Nai (SR3) 0.005 <0.001 <0.001 <0.001 <0.001 0.012 <0.0001 <0.0001 <0.0001 <0.0001
Seagrass Beds - Sheung Pak
Nai (SR2) 0.005 <0.001 <0.001 <0.001 <0.001 0.012 <0.0001 <0.0001 <0.0001 <0.0001
Seagrass Beds - Ha Pak Nai
(SR3) 0.005 <0.001 <0.001 <0.001 <0.001 0.012 <0.0001 <0.0001 <0.0001 <0.0001
Horseshoe Crab Nursery
Grounds - Ha Pak Nai (SR3)
0.005 <0.001 <0.001 <0.001 <0.001 0.012 <0.0001 <0.0001 <0.0001 <0.0001
Horseshoe Crab Nursery
Grounds - Ngau Hom Shek
(SR1)
0.005 <0.001 <0.001 <0.001 <0.001 0.012 <0.0001 <0.0001 <0.0001 <0.0001
Horseshoe Crab Nursery
Grounds - Lung Kwu Sheung
Tan (SR5)
0.005 <0.001 <0.001 <0.001 <0.001 0.015 <0.0001 <0.0001 <0.0001 <0.0001
Coral Colonies Identified
Along Survey Transect under
this Project - Transect C
(SR18)
0.005 0.001 0.001 0.001 0.001 0.015 <0.0001 0.0001 <0.0001 <0.0001
Water Quality Sensitive Receivers
Non-gazetted Beaches - Lung
Kwu Sheung Tan (SR5)
0.005 <0.001 <0.001 <0.001 <0.001 0.015 <0.0001 <0.0001 <0.0001 <0.0001
Non-gazetted Beaches - Lung
Kwu Tan (SR8)
0.005 <0.001 <0.001 <0.001 <0.001 0.015 <0.0001 <0.0001 <0.0001 <0.0001
Secondary Recreation
Subzone - North Western
Water Control Zone (SR8)
0.005 <0.001 <0.001 <0.001 <0.001 0.015 <0.0001 <0.0001 <0.0001 <0.0001
Seawater Intakes - Black Point
Power Station (SR4)
N/A <0.001 0.001 <0.001 0.001 N/A <0.0001 <0.0001 <0.0001 <0.0001
Seawater Intakes - Castle Peak
Power Station (SR9)
N/A <0.001 <0.001 <0.001 <0.001 N/A <0.0001 <0.0001 <0.0001 <0.0001
Seawater Intakes - Tuen Mun
Area 38 (SR11)
0.005 <0.001 <0.001 <0.001 <0.001 0.016 <0.0001 <0.0001 <0.0001 <0.0001
ENVIRONMENTAL RESOURCES MANAGEMENT CASTLE PEAK POWER COMPANY LIMITED
0308057_S7_WATER_REV 3.DOCX APRIL 2016
7-36
WSR (ID) TIN (mg L-1) UIA (mg L-1)
Criteria Intake Outfall Criteria Intake Outfall
Dry Wet Dry Wet Dry Wet Dry Wet
Seawater Intakes - Shiu Wing
Steel Mill (SR10)
0.005 <0.001 <0.001 <0.001 <0.001 0.016 <0.0001 <0.0001 <0.0001 <0.0001
Seawater Intakes - Sludge
Treatment Facilities (SR16)
0.005 <0.001 <0.001 0.001 0.001 0.015 <0.0001 <0.0001 <0.0001 <0.0001
Note: Predicted level exceeding the proposed assessment criteria is bold and underlined.
Table 7.17 shows that the elevation in TIN level is very minimal in both
seasons at all WSRs and is far below the proposed assessment criteria of 0.005
mg L-1 elevation. No unacceptable TIN elevation from the proposed marine
dredging is expected.
Similar to the case of TIN, the predicted UIA elevation is very limited in both
seasons for dredging at the proposed seawater intake and discharge outfall,
and the predicted UIA elevations are below the corresponding WQO
assessment criteria at all WSRs. No unacceptable UIA elevation from the
proposed marine dredging is expected.
7.7.4 Heavy Metals and Micro-Organic Pollutants
The proposed dredging operation may disturb bottom sediment and result in
release of sediment-bounded pollutants, namely heavy metals, metalloid
(arsenic) and trace organic compounds (PAHs, PCBs and TBT). As shown in
Table 7.5, the sediment elutriate test results indicated that there is no
significant release of heavy metals, metalloid and trace organic compounds
from the sediment samples analysed under this EIA and the levels of these
contaminants are below the corresponding proposed assessment criteria.
Therefore the proposed marine dredging works would be unlikely to result in
a significant release of sediment-bounded pollutants into the water column.
No adverse water quality impact associated with the release of sediment-
bounded pollutants would be expected.
7.7.5 Other Marine Construction Activities
Marine construction works other than sediment dredging would be required
for the installation of intake and outfall structure. Potential disturbance to
marine sediment by these marine works are expected to be less significant
than that of sediment dredging. Therefore no adverse water quality impact
from the potential disturbance of bottom sediment is expected from these
marine construction activities.
Construction vessels have the potential for the following liquid discharges:
Uncontaminated deck drainage;
Potentially contaminated drainage from machinery spaces; and
Sewage/grey water.
ENVIRONMENTAL RESOURCES MANAGEMENT CASTLE PEAK POWER COMPANY LIMITED
0308057_S7_WATER_REV 3.DOCX APRIL 2016
7-37
Deck drainage is likely to be uncontaminated and is not likely to impact water
quality. Other sources of possible impacts to water quality may arise from
discharges of hydrocarbons (oil and grease) from machinery space drainage
and biochemical oxygen demand (BOD) and microbiological constituents
associated with sewage/grey water. These waste streams are all readily
amenable to control as part of appropriate practice on vessels. Possible
impacts associated with construction vessel discharges are therefore
considered to be negligible.
No solid wastes will be permitted to be disposed of overboard by vessels
during construction works, thus impacts from such sources will be eliminated.
7.7.6 Sewage Discharges
Sewage will arise from the construction workforce and site office’s sanitary
facilities. It is estimated that the average number of workers working onsite
is about 500. Based on the general effluent generation rate (150 L per worker
per day (1), approximately 75,000 L of effluent will be generated at the site
during the construction phase. The same per head sewage discharge rate
was adopted in the approved EIA of Black Point Gas Supply Project (AEIAR-
150/2010) and is considered appropriate. To accommodate the increase in
sewage effluent from construction workforce, chemical toilets would be
provided onsite. These chemical toilets would be regularly maintained and
cleaned by licensed contractor to avoid any environmental nuisance. As
sewage discharges into the sea are not expected to occur, no unacceptable
water quality impacts to sensitive receivers are anticipated.
7.7.7 Land Based Construction Activities
Discharges and runoff from the site during land-based construction and
installation activities may contain suspended solids which could be a source of
water pollution. However, it is anticipated that no adverse water quality
impacts would arise from the land-based works if proper mitigation
measures, described in Section 7.9.1, are in place.
7.7.8 Chemical Cleaning during Plant Pre-commissioning
Before the commissioning of the additional CCGT Unit No.1 and No.2,
passivation (i.e. make inert) of the inner surfaces of the heat recovery steam
generator of the additional CCGT units would be conducted by chemical
cleaning. Such cleaning operation is also currently undertaken for all
existing CCGT units in BPPS once every 10 to 20 years. Chemical cleaning
solution adopted in current operation consists of water, pH control (generally
hydrochloric acid, ammonia or lime), surfactant and corrosion inhibitor (i.e.
oxidizing agent(s) or other agent such as sulphuric acid, hydrogen peroxide,
etc. which form protective coating on metal surface). Chemical cleaning
solution of similar nature (with tailored formulation) would be adopted for
(1) Based on Table 2 of the Drainage Services Department's Sewerage Manual.
ENVIRONMENTAL RESOURCES MANAGEMENT CASTLE PEAK POWER COMPANY LIMITED
0308057_S7_WATER_REV 3.DOCX APRIL 2016
7-38
the additional CCGT Units No.1 and 2. These constituents are generally non-
toxic and some are commonly used in household products. Based on the
record of a recent similar cleaning event for an existing plant in the BPPS, the
volume of wastewater generated from a cleaning event of one of the
additional CCGT unit is conservatively estimated to be about 5,000 m3 per
event. Wastewater generated will be neutralised to a pH range of 6 to 10 and
discharged into the existing Effluent Treatment Facility onsite for treatment.
Since the constituent ions of the chemical cleaning solution are generally quite
abundant in marine water, no significant change in marine water quality
would be expected upon discharge after neutralization. Residual oxidizing
agent, such as hydrogen peroxide, is expected to decompose quickly into
harmless water and oxygen in the Effluent Treatment Facility. The
wastewater will be treated to appropriate discharge standards (as specified
under the existing / future WPCO discharge licence). With compliance of
the relevant discharge standards same as the existing practice, no
unacceptable water quality impact would be expected from the cleaning
events during the pre-commissioning of the additional CCGT Unit No.1 and
No.2.
7.8 IMPACT ASSESSMENT – OPERATION PHASE
The current BPPS with eight CCGT units has a maximum cooling water
discharge of 4,600,000 m3 per day with allowed maximum discharge
temperature of 40°C and maximum TRC level of 0.5 mg L-1. The proposed
two additional CCGT units would follow similar design specifications, with
cooling water discharge of 950,400 m3 per day for each of the additional CCGT
units with allowed maximum discharge temperature of 40°C and TRC level of
0.5 mg L-1. The potential change in water quality from the increase in
thermal discharge and TRC discharge were assessed separately below.
It is important to note that the two additional CCGT units are expected to be
commissioned in two phases. It is considered conservative to assess the
worst case scenario for the ultimate case of future operation with the existing
BPPS plus both of the additional CCGT units. Assessment for the
intermediate case with only the BPPS plus one CCGT unit is considered less
conservative and is not included.
7.8.1 Increase in Thermal Discharge
The potential change in water quality due to the increase in thermal discharge
was assessed by comparing the change in ambient water temperature under
two modelling scenarios, namely,
Baseline scenario: Existing BPPS discharge at 4,600,000 m3 per day at
40°C;
Future scenario (Additional CCGT Unit No.1 only): Future BPPS
discharge at 5,550,400 m3 per day (4,600,000 + 950,400) at 40°C.and
ENVIRONMENTAL RESOURCES MANAGEMENT CASTLE PEAK POWER COMPANY LIMITED
0308057_S7_WATER_REV 3.DOCX APRIL 2016
7-39
Future scenario (Additional CCGT Unit No.1 and No.2): Future BPPS
discharge at 6,500,800 m3 per day (4,600,000 + 2 × 950,400) at 40°C.
As discussed in Section 7.4.4, for WSRs except for the two cooling water
intakes for BPPS and CPPS, the maximum WQO allowable increase in water
temperature is 2°C.
The modelled mean and maximum water temperature at WSRs for the three
scenarios in both seasons are shown in Table 7.18. The change in mean and
maximum water temperature at WSRs are also provides in Table 7.18 for
comparison with the 2°C WQO criterion. Contour plots for envelope where
predicted water temperature elevation exceeded 2°C for selected tidal
conditions in dry and wet seasons are provided in Annex 7F. Predicted
average and maximum water temperature at WSRs for the two modelled
scenarios are also provided in Table 7.18 below.
The predicted elevation in mean and maximum water temperature is equal to
or below 0.6°C in both the dry and wet season of the future scenario with
additional CCGT Units No.1 & No.2 (Table 7.18), which is well within the 2°C
WQO assessment criterion. The future scenario with additional CCGT Unit
No.1 only shows lower predicted mean and maximum temperature elevation
at all WSRs. The most impacted WSRs in both seasons include SR16, which
represents seawater intake for the Sludge Treatment Facilities, SR3 (ecological
receivers along the coastline of Ha Pak Lai) and SR4 (BPPS) due to the short
distance from the outfall location. It is also observed that the WSRs in Deep
Bay are generally less affected by the thermal discharge in wet season. It is
because the difference between ambient temperature (lower in dry season and
higher in wet season) and modelled thermal discharge (constant at 40°C in
both seasons for worst case assessment) is smaller in wet season.
ENVIRONMENTAL RESOURCES MANAGEMENT CASTLE PEAK POWER COMPANY LIMITED
0308057_S7_WATER_REV 3.DOCX APRIL 2016
7-40
Table 7.18 Predicted Average and Maximum Water Temperature (°C) at WSRs under Baseline and Two Future Scenarios in Dry and Wet
Seasons
Sensitive
Receivers
Name Model Output
Location
Relevant Depth for
Assessment
Baseline
Scenario
Future Scenario Future Scenario
Additional CCGT
Unit No.1 only
Predicted
Change
Additional CCGT
Unit No.1 & No.2
Predicted
Change
Mean Max Mean Max Mean Max Mean Max Mean Max
Dry Season
Fisheries Sensitive Receivers
Oyster
Production Area
Sheung Pak Nai SR14 Depth-averaged 23.03 23.51 23.07 23.72 0.04 0.21 23.10 23.84 0.07 0.33
Recognised
Spawning/
Nursery Grounds
Fisheries Spawning
Ground in North
Lantau
SR15 Depth-averaged 21.79 22.49 21.82 22.55 0.03 0.06 21.84 22.64 0.05 0.15
Artificial Reef
Deployment Area
Sha Chau and Lung
Kwu Chau
SR12 Bottom 22.10 22.71 22.13 22.81 0.03 0.10 22.16 22.92 0.06 0.21
Ecological Sensitive Receivers
Mangroves Ngau Hom Shek SR1 Bottom 23.00 23.07 23.01 23.14 0.01 0.07 23.01 23.20 0.01 0.13
Sheung Pak Nai SR2 Bottom 23.02 23.23 23.04 23.36 0.02 0.13 23.06 23.46 0.04 0.23
Marine Park Designated Sha Chau
and Lung Kwu Chau
SR6 Depth-averaged 22.22 22.78 22.25 22.80 0.03 0.02 22.27 22.84 0.05 0.06
SR7 Depth-averaged 21.91 22.69 21.93 22.72 0.02 0.03 21.96 22.77 0.05 0.08
SR13 Depth-averaged 22.27 24.09 22.31 24.16 0.04 0.07 22.35 24.19 0.08 0.10
Intertidal
Mudflats
Ha Pak Nai SR3 Bottom 23.05 23.43 23.12 23.62 0.07 0.19 23.18 23.75 0.13 0.32
Seagrass Beds Sheung Pak Nai SR2 Bottom 23.02 23.23 23.04 23.36 0.02 0.13 23.06 23.46 0.04 0.23
Ha Pak Nai SR3 Bottom 23.05 23.43 23.12 23.62 0.07 0.19 23.18 23.75 0.13 0.32
Horseshoe Crab
Nursery Grounds
Ha Pak Nai SR3 Bottom 23.05 23.43 23.12 23.62 0.07 0.19 23.18 23.75 0.13 0.32
Ngau Hom Shek SR1 Bottom 23.00 23.07 23.01 23.14 0.01 0.07 23.01 23.20 0.01 0.13
Lung Kwu Sheung Tan SR5 Bottom 22.45 26.98 22.48 26.98 0.03 0.00 22.50 26.98 0.05 0.00
Coral Colonies Transect C SR18 Bottom 23.64 34.07 23.66 34.40 0.02 0.33 23.67 34.70 0.03 0.63
Water Quality Sensitive Receivers
Non-gazetted
Beaches
Lung Kwu Sheung Tan SR5 Depth-averaged 22.97 27.16 23.02 27.16 0.05 0.00 23.05 27.16 0.08 0.00
ENVIRONMENTAL RESOURCES MANAGEMENT CASTLE PEAK POWER COMPANY LIMITED
0308057_S7_WATER_REV 3.DOCX APRIL 2016
7-41
Sensitive
Receivers
Name Model Output
Location
Relevant Depth for
Assessment
Baseline
Scenario
Future Scenario Future Scenario
Additional CCGT
Unit No.1 only
Predicted
Change
Additional CCGT
Unit No.1 & No.2
Predicted
Change
Mean Max Mean Max Mean Max Mean Max Mean Max
Lung Kwu Tan SR8 Depth-averaged 24.38 32.90 24.42 32.93 0.04 0.03 24.44 32.96 0.06 0.06
Secondary
Recreation
Subzone
North Western Water
Control Zone
SR8 Depth-averaged 24.38 32.90 24.42 32.93 0.04 0.03 24.44 32.96 0.06 0.06
Seawater Intakes Black Point Power
Station
SR4 Bottom 22.47 24.29 22.50 24.29 0.03 0.00 22.53 24.30 0.06 0.01
Castle Peak Power
Station
SR9 Bottom 21.64 23.20 21.65 23.23 0.01 0.03 21.66 23.24 0.02 0.04
Tuen Mun Area 38 SR11 Bottom 21.43 22.95 21.45 22.95 0.02 0.00 21.45 22.96 0.02 0.01
Shiu Wing Steel Mill SR10 Bottom 21.50 23.35 21.51 23.35 0.01 0.00 21.52 23.39 0.02 0.04
Sludge Treatment
Facilities
SR16 Bottom 23.04 24.45 23.15 24.69 0.11 0.24 23.23 24.89 0.19 0.44
Wet Season
Fisheries Sensitive Receivers
Oyster
Production Area
Sheung Pak Nai SR14 Depth-averaged 28.33 29.14 28.37 29.18 0.04 0.04 28.40 29.20 0.07 0.06
Recognised
Spawning/
Nursery Grounds
Fisheries Spawning
Ground in North
Lantau
SR15 Depth-averaged 27.24 28.08 27.27 28.10 0.03 0.02 27.28 28.10 0.04 0.02
Artificial Reef
Deployment Area
Sha Chau and Lung
Kwu Chau
SR12 Bottom 27.51 28.32 27.53 28.47 0.02 0.15 27.53 28.47 0.02 0.15
Ecological Sensitive Receivers
Mangroves Ngau Hom Shek SR1 Bottom 28.19 29.10 28.21 29.10 0.02 0.00 28.21 29.10 0.02 0.00
Sheung Pak Nai SR2 Bottom 28.28 29.09 28.31 29.10 0.03 0.01 28.33 29.11 0.05 0.02
Marine Park Designated Sha Chau
and Lung Kwu Chau
SR6 Depth-averaged 27.91 28.68 27.94 28.70 0.03 0.02 27.94 28.70 0.03 0.02
SR7 Depth-averaged 27.37 28.29 27.41 28.31 0.04 0.02 27.41 28.31 0.04 0.02
SR13 Depth-averaged 27.84 28.71 27.88 28.74 0.04 0.03 27.88 28.74 0.04 0.03
Intertidal
Mudflats
Ha Pak Nai SR3 Bottom 28.41 29.09 28.46 29.13 0.05 0.04 28.50 29.13 0.09 0.04
Seagrass Beds Sheung Pak Nai SR2 Bottom 28.28 29.09 28.31 29.10 0.03 0.01 28.33 29.11 0.05 0.02
Ha Pak Nai SR3 Bottom 28.41 29.09 28.46 29.13 0.05 0.04 28.50 29.13 0.09 0.04
ENVIRONMENTAL RESOURCES MANAGEMENT CASTLE PEAK POWER COMPANY LIMITED
0308057_S7_WATER_REV 3.DOCX APRIL 2016
7-42
Sensitive
Receivers
Name Model Output
Location
Relevant Depth for
Assessment
Baseline
Scenario
Future Scenario Future Scenario
Additional CCGT
Unit No.1 only
Predicted
Change
Additional CCGT
Unit No.1 & No.2
Predicted
Change
Mean Max Mean Max Mean Max Mean Max Mean Max
Horseshoe Crab
Nursery Grounds
Ha Pak Nai SR3 Bottom 28.41 29.09 28.46 29.13 0.05 0.04 28.50 29.13 0.09 0.04
Ngau Hom Shek SR1 Bottom 28.19 29.10 28.21 29.10 0.02 0.00 28.21 29.10 0.02 0.00
Lung Kwu Sheung Tan SR5 Bottom 27.93 30.73 28.02 30.82 0.09 0.09 28.05 30.92 0.12 0.19
Coral Colonies Transect C SR18 Bottom 31.64 37.11 31.70 37.26 0.06 0.15 31.76 37.44 0.13 0.34
Water Quality Sensitive Receivers
Non-gazetted
Beaches
Lung Kwu Sheung Tan SR5 Depth-averaged 28.41 29.98 28.48 30.37 0.07 0.39 28.52 30.40 0.11 0.42
Lung Kwu Tan SR8 Depth-averaged 26.97 29.36 27.00 29.39 0.03 0.03 27.02 29.41 0.05 0.05
Secondary
Recreation
Subzone
North Western Water
Control Zone
SR8 Depth-averaged 26.97 29.36 27.00 29.39 0.03 0.03 27.02 29.41 0.05 0.05
Seawater Intakes Black Point Power
Station
SR4 Bottom 28.10 32.19 28.24 32.57 0.14 0.38 28.31 32.74 0.21 0.55
Castle Peak Power
Station
SR9 Bottom 26.97 29.36 27.01 29.39 0.04 0.03 27.02 29.41 0.05 0.05
Tuen Mun Area 38 SR11 Bottom 26.68 28.28 26.68 28.30 0.00 0.02 26.70 28.33 0.02 0.05
Shiu Wing Steel Mill SR10 Bottom 26.86 29.32 26.90 29.32 0.04 0.00 26.91 29.34 0.05 0.02
Sludge Treatment
Facilities
SR16 Bottom 28.60 30.46 28.79 30.75 0.19 0.29 28.95 31.00 0.35 0.54
Note: 1. All numbers are rounded to 1 decimal place. “0.00” indicates all values below 0.005.
2. SR5 and SR8, which are both located within the footprint of Reclamation at Lung Kwu Tan Project and would potentially be removed by that project. The
predicted values for SR5 and SR8 presented are derived assuming these WSRs would be relocated at the new coastline of the reclaimed Lung Kwu Tan.
Since there is no available information on whether these WSRs would indeed be relocated, the predictions at these WSRs are provided for reference only.
ENVIRONMENTAL RESOURCES MANAGEMENT CASTLE PEAK POWER COMPANY LIMITED
0308057_S7_WATER_REV 3.DOCX APRIL 2016
7-43
The size of the thermal plume is generally observed to be larger in dry season
than the wet season (Annex 7F). It is because the modelling exercise assumes
constant discharge at the maximum allowed temperature limit of 40°C thus
resulting in higher temperature difference between the ambient seawater and
the thermal discharge from BPPS. This is a conservative assumption because
while the maximum allowed discharge temperature from BPPS is 40°C, the
actual discharge temperature would generally be lower than the limit. In dry
season when the ambient water temperature is lower, the discharge
temperature would generally be lower as well. It should also be highlighted
that the discharge from the Pearl River plays an important role in shaping the
thermal plume in wet season. While the discharge of thermal plume occurs
close to the surface of the water column, the continuous high discharge from
the Pearl River forces the thermal plume from BPPS (existing and additional
CCGT units altogether) to stay closer to the coastline (when compared with
the same tidal condition in dry season) and moves lower in the water column.
As shown in Annex7F, the thermal plume occurs in the lower level of the
water column for some of the tidal conditions, even though the discharge
occurs on the surface layer. Such a phenomenon also affects the dispersion
of total residual chlorine in the thermal discharge, which is addressed
separately in Section 7.8.2 below.
As discussed in Section 7.4.4, the optimal operation temperature for the two
cooling water intakes for BPPS (SR4) and CPPS (SR9) is below 30°C. As
shown in Table 7.18, the predicted maximum water temperature at SR4 in the
wet season is 32.2°C in the baseline scenario and 32.7°C in the future scenario,
which both exceeded the optimal operation temperature of 30°C. Modelling
prediction indicates that for about 2.1% of time in the wet season the water
temperature at SR4 exceeds 30°C. With the thermal discharge from the
additional CCGT units, the percentage of time with water temperature at SR4
exceeding 30°C increases to 2.3%, which is considered minimal and within the
tolerance of the existing BPPS. As discussed in the previous section, both
modelled baseline and future scenarios assume continuous discharge of
cooling water of maximum allowed temperature (40°C) at the maximum
allowed rate. The assumed discharge temperature and discharge rate are
both conservative. In reality, the discharge temperature and discharge rate
may vary but staying below the allowed rate and temperature, and thus the
temperature elevation should be lower than the model prediction.
As shown in the modelling results, the predicted level of ambient water
temperature is well below the proposed assessment criteria based on WQO,
and is considered to be within or similar to the range of daily fluctuation.
The increase in thermal discharge would lead to small increase in duration
when water temperature at the BPPS seawater intake exceeds the optimal
30°C operation criterion under the conservative assumption. The increase in
water temperature as well as the duration for exceeding 30°C is deemed
minimal for the operation of the BPPS. No unacceptable water quality
impact from the increase in thermal discharge from the proposed CCGT units
is expected.
ENVIRONMENTAL RESOURCES MANAGEMENT CASTLE PEAK POWER COMPANY LIMITED
0308057_S7_WATER_REV 3.DOCX APRIL 2016
7-44
7.8.2 Increase in Total Residual Chlorine Discharge
Electrochlorination of seawater would be conducted to control biofouling of
the cooling water system. The same arrangement would be adopted for the
proposed additional CCGT units. The maximum level of TRC in the cooling
water discharge would be 0.5 mg L-1, which is the same as that of the cooling
water discharge of the existing eight CCGT units in the BPPS. The discharge
of TRC from the additional CCGT units, together with that of the existing
eight CCGT units, are simulated using mathematical model to determine the
level of TRC at nearby identified WSRs.
As discussed in Section 7.4.7, the proposed assessment criterion for TRC at the
applicable marine ecological and fisheries sensitive receivers is 0.02 mg L-1.
Since the maximum discharge concentration of TRC from the existing and
additional CCGT plants is 0.5 mg L-1, this means a 25-times reduction, either
by mixing with ambient seawater, by decay of TRC itself or a combination of
both, would result in compliance to the proposed criterion.
The predicted average and maximum TRC levels under baseline (existing
BPPS and CPPS) and Project (future BPPS with additional CCGT Units No.1,
No.2 and CPPS) at relevant WSRs in both seasons are provided in Table 7.19.
Contour plots for maximum and average TRC level throughout the simulated
period are provided in Annex 7G.
ENVIRONMENTAL RESOURCES MANAGEMENT CASTLE PEAK POWER COMPANY LIMITED
0308057_S7_WATER_REV 3.DOCX APRIL 2016
7-45
Table 7.19 Predicted Maximum and Mean Elevation in Total Residual Chlorine
WSR (ID)
Criteria
TRC - Baseline (mg L-1) Additional CCGT Unit No.1 only
(mg L-1)
Additional CCGT Unit No.1 & No.2
(mg L-1)
Dry Season Wet Season Dry Season Wet Season Dry Season Wet Season
Mean Max Mean Max Mean Max Mean Max Mean Max Mean Max
Fisheries Sensitive Receivers
Oyster Production Area - Sheung Pak Nai (SR14) 0.02 0.0000 0.0023 0.0000 0.0058 0.0000 0.0028 0.0000 0.0069 0.0000 0.0033 0.0000 0.0081
Recognised Spawning/ Nursery Grounds - Fisheries
Spawning Ground in North Lantau (SR15)
0.02 0.0001 0.0035 0.0000 0.0010 0.0001 0.0035 0.0000 0.0010 0.0001 0.0036 0.0000 0.0011
Artificial Reef Deployment Area - Sha Chau and Lung
Kwu Chau (SR12)
0.02 0.0000 0.0010 0.0000 0.0001 0.0000 0.0010 0.0000 0.0001 0.0000 0.0012 0.0000 0.0001
Ecological Sensitive Receivers
Mangroves - Ngau Hom Shek (SR1) 0.02 0.0000 0.0007 0.0000 0.0025 0.0000 0.0009 0.0000 0.0031 0.0000 0.0010 0.0000 0.0036
Mangroves - Sheung Pak Nai (SR2) 0.02 0.0000 0.0018 0.0000 0.0047 0.0000 0.0022 0.0000 0.0057 0.0000 0.0026 0.0000 0.0067
Marine Park - Designated Sha Chau and Lung Kwu
Chau (SR6)
0.02 0.0000 0.0008 0.0000 0.0001 0.0000 0.0009 0.0000 0.0001 0.0000 0.0009 0.0000 0.0001
Marine Park - Designated Sha Chau and Lung Kwu
Chau (SR7)
0.02 0.0000 0.0017 0.0000 0.0003 0.0000 0.0018 0.0000 0.0004 0.0000 0.0019 0.0000 0.0005
Marine Park - Designated Sha Chau and Lung Kwu
Chau (SR13)
0.02 0.0000 0.0019 0.0000 0.0004 0.0000 0.0020 0.0000 0.0004 0.0000 0.0020 0.0000 0.0004
Intertidal Mudflats - Ha Pak Nai (SR3) 0.02 0.0001 0.0050 0.0001 0.0084 0.0001 0.0062 0.0001 0.0101 0.0001 0.0073 0.0001 0.0118
Seagrass Beds - Sheung Pak Nai (SR2) 0.02 0.0000 0.0018 0.0000 0.0047 0.0000 0.0022 0.0000 0.0057 0.0000 0.0026 0.0000 0.0067
Seagrass Beds - Ha Pak Nai (SR3) 0.02 0.0001 0.0050 0.0001 0.0084 0.0001 0.0062 0.0001 0.0101 0.0001 0.0073 0.0001 0.0118
Horseshoe Crab Nursery Grounds - Ha Pak Nai (SR3) 0.02 0.0001 0.0050 0.0001 0.0084 0.0001 0.0062 0.0001 0.0101 0.0001 0.0073 0.0001 0.0118
Horseshoe Crab Nursery Grounds - Ngau Hom Shek
(SR1)
0.02 0.0000 0.0007 0.0000 0.0025 0.0000 0.0009 0.0000 0.0031 0.0000 0.0010 0.0000 0.0036
Horseshoe Crab Nursery Grounds - Lung Kwu Sheung
Tan (SR5)
0.02 0.0013 0.0203 0.0018 0.0243 0.0013 0.0203 0.0018 0.0243 0.0013 0.0203 0.0019 0.0243
Coral Colonies Identified Along Survey Transect under
this Project - Transect C (SR18)
0.02 0.0347 0.0834 0.2756 0.3472 0.0398 0.0862 0.2768 0.3639 0.0411 0.0889 0.2819 0.3823
Note:
1. All numbers are rounded to 4 decimal places. “0.0000” indicates all values below 0.00005.
2. SR5, which is both located within the footprint of Reclamation at Lung Kwu Tan Project and would potentially be removed by that project. The predicted values for SR5
presented are derived assuming this WSR would be relocated at the new coastline of the reclaimed Lung Kwu Tan. Since there is no available information on whether this
WSR would indeed be relocated, the predictions at these WSR are provided for reference only.
3. Exceedances in proposed assessment criteria are shown in bold.
ENVIRONMENTAL RESOURCES MANAGEMENT CASTLE PEAK POWER COMPANY LIMITED
0308057_S7_WATER_REV 3.DOCX APRIL 2016
7-46
As shown in Table 7.19, compliance with the proposed assessment criterion for
TRC is predicted at most marine ecological and fisheries WSRs except for SR5
and SR18. SR5 and SR18 are located in close proximity to the existing
discharge outfalls of the CPPS and BPPS respectively, and are predicted to
show non-compliance with the TRC assessment criterion without the Project,
thus no new exceedance of the proposed TRC criterion is expected with the
Project in place in both seasons. It is also important to note that the
magnitude of change in TRC level at these two WSRs with and without Project
is rather small and is deemed acceptable. Maximum TRC level is predicted
at coral colonies at SR18 in both seasons, regardless of baseline or project
scenarios. The predicted levels of TRC for other marine ecological and
fisheries WSRs are lower than that of SR5 and SR18, with mean TRC level two
orders of magnitude (i.e. one-hundredth) smaller than the proposed criteria of
0.02 mg L-1. Increase in TRC level due to the additional CCGT Units No.1
and No.2 is more observable in the Deep Bay WCZ; in the North Western
WCZ, the predicted elevation is very limited, as a result of fast current flow of
the Urmston Road and the existing discharge of the CPPS.
As shown in Annex 7G, the mixing zone of TRC (i.e. concentration above 0.02
mg L-1) discharged from the BPPS covers the shoreline along the BPPS and
part of the open waters off the shoreline. The dispersion of TRC is better in
dry season as shown by the lower build up level. On the other hand, the
dispersion of TRC is weaker and results in higher TRC buildup along the
BPPS shoreline (Annex 7G and Table 7.19). The mixing zone of TRC is also
predicted to be larger in the bottom than the rest of the water column, as a
result of higher Pearl River discharge pushing the plume close to the shoreline
and even drive the plume down the water column. These are consistent with
the observations in the operation phase thermal discharge modelling
discussed in the previous Section 7.8.1.
In short, results of modelling simulation indicate the discharge of TRC from
the existing and additional CCGT units would result in limited increase in
TRC level in ambient marine water. Compliance with the proposed
assessment criteria for TRC is predicted at all applicable WSRs. In view of
the above, no unacceptable water quality impact from the discharge of TRC
from the Project is expected.
7.8.3 Potential Risk of Fuel Spill
The primary fuel for the proposed additional CCGT Units No.1 and 2 is
natural gas and there is no risk of spillage of this fuel into marine waters, and
so no unacceptable water quality impact is anticipated and quantitative
assessment is not necessary.
The operation of the additional CCGT units will make use of fuel supply from
the three existing oil tanks at the BPPS as back up fuel, and no additional oil
tank would be built for the proposed Project. Since fuel oil would only be
utilised as back up fuel for the proposed additional CCGT units, the use of
ENVIRONMENTAL RESOURCES MANAGEMENT CASTLE PEAK POWER COMPANY LIMITED
0308057_S7_WATER_REV 3.DOCX APRIL 2016
7-47
fuel oil by the Project would be limited, and no additional associated
transhipment and transfer of fuel oil is anticipated. Therefore no significant
increase in potential risk of fuel spillage is expected. Operation staff of the
BPPS follows stringent established rules on control, operation, inspection and
maintenance of the BPPS facilities to minimise any risk of fuel and other
chemicals stored onsite. The three existing oil tanks are installed with leak
detection and other safety protections. Secondary containment is provided
for the three existing oil tanks and major oil spillage from the existing oil
tanks, if any, would be fully contained. Also, design features such as
shutdown valves and leak detectors have been included to avoid and
minimise potential fuel leak. Accidental release is unlikely as the pipes are
fully welded. Oil leakage, if any, would be promptly notified, rectified and
directed to oil contaminated drains for proper handling. Given the small
scale and prompt reaction to any leakage of fuel, major accidental release of
fuel oil from these pipelines (which are located beyond the secondary
containment) is not expected. The contingency plan for the existing
operation of the BPPS is considered sufficient for directing immediate
response to any accidental spillage event. Currently, CLP maintains an
appropriate level of spill response capability within the BPPS through onsite
staff. Sufficient spill response equipment is stored onsite to effectively
respond to the potential spill scenarios. No unacceptable water quality
impact is anticipated and quantitative assessment is not necessary.
7.8.4 Increase in Pollution Load from Other Operational Discharge
As discussed in Section 7.2.5, the operation of the future BPPS with the two
additional CCGT units would be designed such that there would be no net
increase in pollution load to the Deep Bay waters during the operation phase.
The following sections detail the loading discharge conditions for the existing
BPPS, proposed future loads from additional CCGT units and the proposed
measures to ensure no net increase in total load from future operation.
Based on the latest WPCO discharge licence granted to CAPCO for the
operation of BPPS under Section 23 of WPCO, there are a number of discharge
streams which are discharged into the marine waters of Deep Bay. These
discharge streams and the principal pollution loads of concerns are listed in
Table 7.20.
Table 7.20 Stream of Pollution Loads for Existing BPPS
Effluent Stream WPCO Discharge
Licence ID
Flow BOD TP TN
m3 per day mg L-1 mg L-1 mg L-1
Cooling Water Effluent (1) (2) 4,600,000 N.S. N.S. N.S.
Station Effluent Treatment Plant Effluent (3) 1,000 20 10 100
Station Effluent Treatment Plant Effluent (4) 1,000 20 10 100
Oil Separator No. 1 Effluent (5) 800 20 10 100
Oil Separator No. 2 Effluent (6) 800 20 10 100
Oil Separator No. 3 Effluent (7) 500 20 10 100
Oil Separator No. 4 Effluent (8) 50 20 10 100
Oil Separator No. 5 Effluent (9) 600 20 10 100
Oil Separator No. 9 Effluent (10) 150 20 10 100
ENVIRONMENTAL RESOURCES MANAGEMENT CASTLE PEAK POWER COMPANY LIMITED
0308057_S7_WATER_REV 3.DOCX APRIL 2016
7-48
Effluent Stream WPCO Discharge
Licence ID
Flow BOD TP TN
m3 per day mg L-1 mg L-1 mg L-1
Permanent Sewage Treatment Plant Effluent (11) 420 20 10 100
Effluent Treatment Facility Effluent (12) 1,000 20 10 100
Note: ID (1) and (2) represent cooling water effluent from the existing outfall. This effluent is expected to be
chemically similar to the ambient marine waters at the intake, with the exception of elevated TRC and defoaming
agent. Water quality parameters, including SS, BOD, chemical oxygen demand (COD), oil and grease (O&G),
total phosphorus (TP) and total nitrogen (TN), are not specified in the existing WPCO Discharge License for this
effluent. These parameters are marked as “N.S.” above.
Among the list of water quality parameters, BOD, TP and TN are of water
quality concern under TPB PG-No. 12C. They are considered as constituents
of pollution loads which should be controlled for compliance with the “no net
increase in pollution load” consideration. The maximum allowed loadings
for the existing operation of the BPPS are presented in Table 7.21.
Table 7.21 Maximum Allowed Loading for Existing BPPS
Effluent Stream WPCO
Discharge
Licence ID
Flow BOD TP TN
m3 per day kg per day kg per day kg per day
Station Effluent Treatment Plant Effluent (3) 1,000 20.0 10.0 100.0
Station Effluent Treatment Plant Effluent (4) 1,000 20.0 10.0 100.0
Oil Separator No. 1 Effluent (5) 800 16.0 8.0 80.0
Oil Separator No. 2 Effluent (6) 800 16.0 8.0 80.0
Oil Separator No. 3 Effluent (7) 500 10.0 5.0 50.0
Oil Separator No. 4 Effluent (8) 50 1.0 0.5 5.0
Oil Separator No. 5 Effluent (9) 600 12.0 6.0 60.0
Oil Separator No. 9 Effluent (10) 150 3.0 1.5 15.0
Permanent Sewage Treatment Plant Effluent (11) 420 8.4 4.2 42.0
Effluent Treatment Facility Effluent (12) 1,000 20.0 10.0 100.0
Total 6,320 126.4 63.2 632.0
Note: Cooling water effluent (ID (1) & (2)) is not included because there is no specification on pollution load
associated with those effluents.
Based on the latest design information, an increase in effluent from the
additional CCGT units would be expected during project operation. Flow of
additional effluent streams which are expected from the additional CCGT
units are provided in Table 7.22. Among these streams, (13) is the cooling
water effluent (assessed in Sections 7.8.1 and 7.8.2) which carries waste heat
and TRC but no additional pollution load. For effluent streams (14) to (17)
and (19) to (22), their properties and pollution load carried should resemble
their counterpart of the existing CCGT units in BPPS. The total flow of these
additional effluent streams is 1,950 and 3,900 m3 per day for one additional
CCGT unit and two additional CCGT units respectively.
Table 7.22 Stream of Pollution Loads for the Additional CCGT Units at BPPS
Effluent Stream ID Discharge Point denoted
under WPCO Discharge
Licence
Flow
m3 per day
Additional CCGT Unit No.1
Cooling Water Effluent (13) DP1 950,400
ENVIRONMENTAL RESOURCES MANAGEMENT CASTLE PEAK POWER COMPANY LIMITED
0308057_S7_WATER_REV 3.DOCX APRIL 2016
7-49
Effluent Stream ID Discharge Point denoted
under WPCO Discharge
Licence
Flow
m3 per day
Station Effluent Treatment Plant Effluent (14) New discharge point 500
Oil Interceptor A Effluent (15) New discharge point 800
Oil Interceptor B Effluent (16) New discharge point 500
Oil Interceptor C Effluent (17) New discharge point 150
Sum of (14) to (17) 1,950
Additional CCGT Unit No.2
Cooling Water Effluent (18) New discharge point 950,400
Station Effluent Treatment Plant Effluent (19) New discharge point 500
Oil Interceptor A Effluent (20) New discharge point 800
Oil Interceptor B Effluent (21) New discharge point 500
Oil Interceptor C Effluent (22) New discharge point 150
Sum of (19) to (22) 1,950
Note: Cooling water effluent ID (13) will be discharged via the existing BPPS cooling water
outfall together with the cooling water effluent stream ID (1) and (2) while cooling water
effluent ID (18) is anticipated to be discharged via the proposed new discharge outfall.
It should be noted that whilst there is an increase in total flow with the
implementation of this Project, the total pollution load will remain to be
capped at the same level as the existing allowable pollution load of the BPPS
to comply with the “no net increase in pollution load” requirement.
Currently, the following measures are being implemented to control the total
daily pollution load discharge into the Deep Bay waters:
The effluents from the station effluent treatment plant and oil separator
will be discharged batch wise, i.e. the effluents in the facilities are allowed
for settlement and removal of pollutants before discharge if necessary.
Samples will be taken from the effluents for laboratory measurements to
ensure compliance with the discharge limits before batch wise discharge.
Effluents from the station effluent treatment plant, oil separator and
sewage treatment facility would be collected by licenced collectors for
treatment and disposal if needed.
The maximum pollution load for water quality parameters listed in Table 7.21
would be considered as the “cap”. Upon the commissioning of the
additional CCGT Unit(s) No.1 and / or No.2, the retention time of effluents
from the station effluent treatment plant and oil separator may need to
increase to allow further settlement and removal of pollutants (so total
pollution load does not increase despite the increase in flow. Offsite
treatment and disposal by licensed collectors would also be adopted when
needed to ensure the “cap” of pollution load into the Deep Bay waters is
properly implemented. Operation staff of the BPPS reviewed the above
control measures and confirmed it is possible to control the total pollution
loads in the effluent streams of the existing and future BPPS to remain under
the maximum total daily discharge requirements specified in Table 7.21. Such
discharge requirement would be taken into account by the BPPS operator as
well as in the WPCO Discharge License of the BPPS upon the commissioning
ENVIRONMENTAL RESOURCES MANAGEMENT CASTLE PEAK POWER COMPANY LIMITED
0308057_S7_WATER_REV 3.DOCX APRIL 2016
7-50
of the proposed first additional CCGT unit. Operation phase effluent
monitoring would be conducted in the first year of operation of each of the
Additional CCGT Unit No.1 and No. 2 to ensure compliance to the proposed
discharge standard.
With the pollution reduction in existing waste stream and control of pollution
loading in the future waste stream, no net increase in pollution load in Deep
Bay would be expected from the expanded operation of the BPPS.
Compliance with the Town Planning Board Guidelines TPB PG-No. 12C
requirement is expected.
Under existing practice, the use of defoaming agent is required to avoid the
formation of foam due to the heating of organic-rich salt water in the cooling
water system. Defoamer PS, a defoaming agent, is used in current operation
and would also be used for the proposed Additional CCGT Unit No.1 and 2.
Defoamer PS contains about 1% of 2-[hydroxymethyl)amino]ethanol by
weight as its active ingredient while the remainder is water and additives (1).
Based on the 2013 to 2014 records of the BPPS, the average concentration of 2-
[hydroxymethyl)amino]ethanol in cooling discharge is about 0.211 µg L-1 (with
minimum of 0.067µg L-1 and maximum of 0.507µg L-1) to control the
formation of foam upon discharge and similar level of dosage is be expected
for the future operation of the proposed Additional CCGT Unit No.1 and No.
2. According to the USEPA (2 ), 2-[hydroxymethyl)amino]ethanol rapidly
degrades in the environment and therefore the exposure and risk to this
compound, while slightly toxic to aquatic organisms, is expected to be
minimal. Due to its rapid degradation, bioaccumulation is not known to be a
concern. Chemical toxicity studies on aquatic organism (3) (4) (5) indicates
LC/EC50 of fish and crustacean species are at least 19.6 mg L-1. For
conservative assessment and to take into account inter- and intra-species
variation, an assessment factor of 1,000 is considered to derive Predicted No-
Effect-Concentrations ( 6 ) for the compound, which is 19.6 µg L-1. The
Predicted No-Effect-Concentrations of the compound is over 90 times of the
existing and future discharge concentration of the compound. Hence, the use
of defoaming agent is not expected to result in adverse impact on nearby
marine ecology as well as other sensitive uses, while preventing the formation
of persistent foam which is prohibited under WQO as shown in Table 7.1. No
(1) Additives consist of fatty alcohol (long-chain alcohol, which is known to be non-toxic and biodegradable. Fatty
alcohol is also used commonly as non-ionic detergent, emulsifier and even dietary supplements for human.
(2) A USEPA R.E.D. Fact (EPA-738-F-93-024) available at
http://archive.epa.gov/pesticides/reregistration/web/pdf/3070fact.pdf. Last retrieved on 7 January 2016.
(3) PAN Pesticides database. Available at http://www.pesticideinfo.org/List_AquireAll.jsp?Rec_Id=PC33060.
Last retrieved on 7 January 2016.
(4) Material safety data sheet. Available at
http://www.kellysolutions.com/erenewals/documentsubmit/KellyData%5CND%5Cpesticide%5CMSDS%5C53
83%5C5383-11%5C5383-11_MERGAL_174_9_8_2004_4_40_21_PM.pdf. Last retrieved on 7 January 2016.
(5) Material safety data sheet. Available at http://www.walter-
tools.com/SiteCollectionDocuments/downloads/ca/valcool/en-us/msds-sheet-valcool-mergal-2010-us-en.pdf.
Last retrieved on 7 January 2016.
(6) Technical Guidance Document on Risk Assessment. European Chemical Bureau, Institute for Health and
Consumer Protection, European Commission. Available at
(https://echa.europa.eu/documents/10162/16960216/tgdpart2_2ed_en.pdf. Last retrieved on 7 January 2016.
ENVIRONMENTAL RESOURCES MANAGEMENT CASTLE PEAK POWER COMPANY LIMITED
0308057_S7_WATER_REV 3.DOCX APRIL 2016
7-51
unacceptable water quality impact associated with the use of defoaming agent
is expected.
Upon the operation of the additional CCGT units, an additional 20 operation
and maintenance staff would be required for each additional CCGT unit.
The associated increase in sewage generation (20 workers per unit × 150 L per
worker per day = 3,000 L per day per unit, i.e. 3,000 L per day for one
additional CCGT unit and 6,000 L per day for two additional CCGT units) is
considered minimal when compared with the average daily workforce size of
556 for the existing BPPS operation. There is sufficient capacity in the
existing permanent sewage treatment plant (item 11 in Table 7.20 to Table 7.21)
onsite to handle the additional sewage flow from the new staff. No direct
discharge of sewage would be expected and therefore no unacceptable water
quality impact is expected.
It should also be noted that there is an established drainage system within the
Project Site and the rest of the BPPS. Stormwater is collected onsite with
appropriate pollution control facilities. Similar drainage provisions would be
included at the Project Site upon the operation of the proposed additional
CCGT units. Therefore, no significant change in stormwater or other non-
point source pollution is expected during operation phase.
7.8.5 Chemical Cleaning during Plant Operation
As stated under Section 7.7.8 chemical cleaning would be required for CCGT
unit which has been in operation once every 10 to 20 years of operation for
maintenance. It is expected the same volume (about 5,000 m3 per event per
unit) and constituents (water, corrosion inhibitor, surfactant and pH control)
of wastewater would be generated from the event. Wastewater generated
will be neutralised to a pH range of 6 to 10 and discharged into the existing
Effluent Treatment Facility onsite for treatment. The wastewater will be
treated to appropriate discharge standards (as specified under the existing /
future WPCO discharge license). With compliance of the relevant discharge
standards same as the existing practice, no unacceptable water quality impact
would be expected from the cleaning events during the operation of the
additional CCGT Unit No.1 and No.2.
It should be highlighted that the need for chemical cleaning may vary among
CCGT units due to subtle differences on operation conditions and the cleaning
frequency is anticipated to be infrequent, i.e. once every 10 to 20 years of
operation. Chemical cleaning would be properly scheduled so the events are
spread out temporally to avoid concurrent washing as far as practicable. The
effluent from every cleaning event would be properly treated before
discharge. Also, as the wastewater from chemical cleaning would be
discharged into the existing Effluent Treatment Facility onsite, its contribution
to the total loading from the BPPS would also be controlled by the specified
measures stipulated under Section 7.8.4, therefore no net increase in pollution
load in Deep Bay would be expected from the expanded operation of the
BPPS.
ENVIRONMENTAL RESOURCES MANAGEMENT CASTLE PEAK POWER COMPANY LIMITED
0308057_S7_WATER_REV 3.DOCX APRIL 2016
7-52
7.8.6 Maintenance Dredging at Proposed Seawater Intake and Outfall for
Additional CCGT Unit No.2
Subject to the actual rate of sedimentation upon the operation of the additional
CCGT units, maintenance dredging at the proposed seawater intake and
discharge outfall may be required at regular intervals. The extent of
maintenance dredging would be the same as that of the proposed dredging
under construction phase, and the thickness and total volume of sediment to
be removed would be much smaller. The potential water quality impacts
from construction phase dredging operation is assessed under Section 7.7, and
the potential water quality impacts on nearby WSRs from operation phase
maintenance dredging at the same or lower rate with the same mitigation
measures is considered similar or less significant. Since no unacceptable
water quality impact is predicted at the WSRs for construction phase
dredging, the same would be expected for operation phase maintenance
dredging.
It should be highlighted that during the operation phase of the additional
CCGT units, the intake of the second additional CCGT unit would be itself a
WSR to SS elevation from the maintenance dredging. Since the intake itself
would be the most affected by the maintenance dredging near the intake,
additional modelling assessment has been conducted to determine the
potential maximum SS elevation from the maintenance dredging based on the
mitigated 740 m3 per day dredging rate with silt curtain around the grab
dredger. The predicted maximum SS elevations at the new seawater intake
for maintenance dredging near the seawater intake are presented in Table 7.23.
Table 7.23 Predicted Maximum Elevation in Suspended Solids at Seawater Intake of the
Second Additional CCGT Unit WSRs from Maintenance Dredging at
Seawater Intake
WSR (ID) SS Elevation (mg L-1)
Dry Season Wet Season
Criteria Max Criteria Max
Seawater Intake of the Second Additional CCGT Unit 700 23.66 700 14.13
The predicted SS elevations at new seawater intake are below the
corresponding assessment criteria in both seasons. In view of the far longer
separation from the new seawater intake to the dredging area at the discharge
outfall, the potential SS elevation at the new seawater intake would be much
lower for dredging at the discharge outfall and thus is not further discussed.
Other water quality parameters, such as DO depletion, nutrient, heavy metals
and tracer organic contaminants would also be affected by the maintenance
dredging. The potential water quality impacts on all WSRs identified are
expected to be the same or below that of the construction phase dredging
operation, which are all found to have no unacceptable impact. The new
seawater intake for the second additional CCGT unit is not considered to be
sensitive to these water quality parameters, and assessment for these water
quality parameters are considered not necessary. No unacceptable water
ENVIRONMENTAL RESOURCES MANAGEMENT CASTLE PEAK POWER COMPANY LIMITED
0308057_S7_WATER_REV 3.DOCX APRIL 2016
7-53
quality impact from the maintenance dredging at the proposed seawater
intake and discharge outfall is expected.
7.9 MITIGATION MEASURES
7.9.1 Construction Phase
Marine Construction
To minimise potential water quality impacts from elevated SS due to the
proposed dredging works for the additional CCGT Unit No.2 at the seawater
intake and discharge outfall, the following mitigation measures are
recommended:
Reduction of dredging rate from 4,000 m3 per day to 740 m3 per day for
dredging at the seawater intake and discharge outfall;
Floating type silt curtain around grab dredger; and
Another single layer of floating type silt curtain surrounding coral colonies
identify at dive survey Transect C (SR18).
Silt curtains shall be formed from tough, abrasion resistant, permeable
membranes, suitable for the purpose, supported on floating booms in such a
way as to ensure that the sediment plume shall be restricted to within the limit
of the works area. The silt curtain shall be formed and installed in such a
way that tidal rise and fall are accommodated, with the silt curtains always
extending from the surface to the bottom of the water column and held with
anchor blocks. The silt curtain surrounding SR18 should provide sufficient
clearance to the coral colonies such that no direct impact from the installation
and anchoring of silt curtain would be inflicted on the coral colonies. The
contractor shall regularly inspect the silt curtains and check that they are
moored and marked to avoid danger to marine traffic. Regular inspection on
the integrity of the silt curtain should be carried out by the contractor and any
damage to the silt curtain shall be repaired by the contractor promptly.
Relevant marine works shall only be undertake when the repair is fixed to the
satisfaction of the engineer.
Construction of intake and outfall structure shall be conducted behind
drained cofferdam as stated in Section 3. This minimises the potential
disturbance to the seabed and the associated impact on water quality.
Furthermore, a number of standard measures and good site practices are
recommended to be implemented to avoid/minimise the potential impacts
from marine construction. These measures include:
All vessels should be well maintained and inspected before use to limit
any potential discharges to the marine environment;
All vessels must have a clean ballast system;
ENVIRONMENTAL RESOURCES MANAGEMENT CASTLE PEAK POWER COMPANY LIMITED
0308057_S7_WATER_REV 3.DOCX APRIL 2016
7-54
No discharge of sewage/grey wastewater should be allowed.
Wastewater from potentially contaminated area on working vessels
should be minimized and collected. These kinds of wastewater should
be brought back to port and discharged at appropriate collection and
treatment system; and
No soil waste is allowed to be disposed overboard.
Land-based Construction
Standard site practices outlined in ProPECC PN 1/94 “Construction Site
Drainage” will be followed as far as practicable in order to reduce surface
runoff, minimise erosion, and also to retain and reduce any SS prior to
discharge. These practices include the following:
Silt removal facilities such as silt traps or sedimentation facilities will be
provided to remove silt particles from runoff to meet the requirements of
the TM standard under the WPCO. The design of silt removal facilities
will be based on the guidelines provided in ProPECC PN 1/94. All
drainage facilities and erosion and sediment control structures will be
inspected on a regular basis and maintained to confirm proper and
efficient operation at all times and particularly during rainstorms.
Deposited silt and grit will be removed regularly.
Earthworks to form the final surfaces will be followed up with surface
protection and drainage works to prevent erosion caused by rainstorms.
Appropriate surface drainage will be designed and provided where
necessary.
The precautions to be taken at any time of year when rainstorms are likely
together with the actions to be taken when a rainstorm is imminent or
forecasted and actions to be taken during or after rainstorms are
summarised in Appendix A2 of ProPECC PN 1/94.
Oil interceptors will be provided in the drainage system where necessary
and regularly emptied to prevent the release of oil and grease into the
storm water drainage system after accidental spillages.
Temporary and permanent drainage pipes and culverts provided to
facilitate runoff discharge, if any, will be adequately designed for the
controlled release of storm flows.
The temporary diverted drainage, if any, will be reinstated to the original
condition when the construction work has finished or when the
temporary diversion is no longer required.
As the Project site is next to the shoreline, infiltration of seawater during
excavation is anticipated. Appropriate infiltration control, such as cofferdam
wall, is recommended to be adopted to limit groundwater inflow to the
ENVIRONMENTAL RESOURCES MANAGEMENT CASTLE PEAK POWER COMPANY LIMITED
0308057_S7_WATER_REV 3.DOCX APRIL 2016
7-55
excavation works areas in the Project site. Groundwater pumped out from
excavation area should be discharged into the storm system via silt removal
facilities.
Appropriate numbers of chemical toilets shall be provided by a licensed
contractor to serve the construction workers over the construction site to
prevent direct disposal of sewage into the water environment.
7.9.2 Operation Phase
Modelling assessment for operation phase thermal and TRC discharge
indicated that no unacceptable water quality impact would be expected from
the discharge of additional CCGT units cooling water. To ensure compliance
with the effluent discharge standards stipulated in Sections 7.8.1 and 7.8.2,
monitoring of effluent temperature as well as TRC level is recommended for
the first year of operation of the first and second additional CCGT units.
Furthermore, water quality monitoring at nearby WSRs is recommended for
first year of operation of the first and second additional CCGT units. Details
are provided in the standalone EM&A Manual.
The additional risk associated with accidental fuel spill from the operation of
the additional CCGT units is expected to be minimal. Design features such
as shutdown valves and leak detectors are also included to avoid and
minimise potential fuel leak. The contingency plan for the existing operation
of the BPPS is considered sufficient for directing immediate response to any
accidental spillage event. No additional water quality mitigation measure is
required.
Control measures would be implemented to ensure total average daily
loading of batch wise discharge of effluents from the future operation of BPPS
remain below the maximum allowed level of the existing operation. These
measures include (1) batch wise discharge to allow settlement and removal of
part of the pollution load, (2) laboratory measurements to ensure compliance
with the discharge limits before batch wise discharge and (3) disposal of
effluent from the station effluent treatment plant, oil separator and sewage
treatment facility offsite by licensed collector for treatment if needed. This
makes the overall pollution load from the operation of the expanded BPPS (i.e.
two additional CCGT units included) remain the same at the level of the
existing operation.
There is existing drainage and sewerage infrastructure onsite which would
also cover the proposed Project upon its operation. Therefore no additional
mitigation measures would be required on these aspects.
With the implementation of the above measures, no unacceptable water
quality impact from the operation of the proposed additional CCGT units is
expected.
Mitigation measures required for maintenance dredging at seawater intake
and discharge outfall for additional CCGT Unit No.2 would be the same as
ENVIRONMENTAL RESOURCES MANAGEMENT CASTLE PEAK POWER COMPANY LIMITED
0308057_S7_WATER_REV 3.DOCX APRIL 2016
7-56
that recommended for construction phase dredging operation under Section
7.9.1. With the implementation of the proposed measures, no unacceptable
water quality impact from the operation phase maintenance dredging is
expected.
7.10 RESIDUAL IMPACT
7.10.1 Construction Phase
It is predicted that the maximum SS elevation at all WSRs would be in
compliance with the corresponding WQO SS criteria with the implementation
of proposed mitigation measures. No unacceptable residual water quality
impact from SS elevation due to marine dredging at seawater intake and
discharge outfall is expected.
No exceedance of the proposed sedimentation criterion is predicted at coral
colonies at SR18 and artificial reef at SR12 with the implementation of
proposed mitigation measures. No unacceptable sedimentation impact from
SS elevation due to marine dredging at seawater intake and discharge outfall
is expected.
With the implementation of proposed mitigation measures, no exceedance of
the WQO DO criteria is predicted at all WSRs in the mitigated scenario. No
unacceptable dissolved oxygen depletion due to marine dredging at seawater
intake and discharge outfall is expected.
With the implementation of proposed mitigation measures, no exceedance of
the proposed assessment criteria for TIN and UIA is predicted at all WSRs in
the mitigated scenario. Sediment elutriate test results indicated there is no
tendency of release of heavy metals, metalloid and trace organic contaminants
from the sediment to the water column. No unacceptable water quality
impact from release of nutrient and contaminants due to marine dredging at
seawater intake and discharge outfall is expected.
Potential water quality impacts from land-based construction activities are
expected to be controlled with the implementation of proposed mitigation
measures stipulated in Section 7.9.1. No unacceptable water quality impact
from land-based construction activities is expected.
7.10.2 Operation Phase
Modelling assessment for operation phase thermal and TRC discharge
indicated that no unacceptable water quality impact would be expected from
the discharge of additional CCGT units cooling water. Some level of increase
in duration when water temperature at seawater intake exceeds the optimum
30 °C may occur. Yet the increase is minimal for normal operation of the
existing BPPS.
The additional risk associated with accidental fuel spill from the operation of
the additional CCGT units is expected to be minimal. With the
ENVIRONMENTAL RESOURCES MANAGEMENT CASTLE PEAK POWER COMPANY LIMITED
0308057_S7_WATER_REV 3.DOCX APRIL 2016
7-57
implementation of leak control design features as well as the adoption of
contingency plan for the existing operation of the BPPS, no unacceptable
water quality impact would be expected.
With the implementation of the proposed measures in controlling overall
pollution load discharge from the BPPS into the Deep Bay WCZ, there would
be no net increase in pollution load into the Deep Bay WCZ from the BPPS
upon the future expanded operation. The discharge level of defoaming agent
would be much lower than that of the Predicted No-Effect-Concentrations for
the compound and no adverse impact to marine ecology as well as other
sensitive uses is expected. No unacceptable water quality impact from the
operation of the proposed additional CCGT units is expected.
With the implementation of the proposed measures in controlling SS
dispersion from maintenance dredging at seawater intake and discharge
outfall, no unacceptable water quality impact from the operation phase
maintenance dredging is expected.
7.11 CUMULATIVE IMPACT
According to publicly available sources, a list of identified projects in the
vicinity of BPPS is summarised in Table 5.1 of Annex 7B. Considerations with
regards to cumulative water quality impact assessment are further elaborated
below.
ENVIRONMENTAL RESOURCES MANAGEMENT CASTLE PEAK POWER COMPANY LIMITED
0308057_S7_WATER_REV 3.DOCX APRIL 2016
7-58
Table 7.24 Nearby Projects Identified and Consideration in Water Quality Assessment in this EIA
Project Duration Location Major Marine Activity Considerations in Water Quality Assessment
Engineering Feasibility Study
for Industrial Estate at Tuen
Mun Area 38 (EIA Study Brief
ESB-277/2014)
Construction: 2019
to 2023
Tuen Mun Area
38 (3 km away)
(1) Construction of
submarine outfall
(2) Treated sewage
effluent discharge from
new sewage treatment
works
(1) Letter was issued to the Hong Kong Science and Technology Parks
Corporation (the project proponent) to obtain the letter project update.
Hong Kong Science and Technology Parks Corporation replied there is
no further update in design and project programme available. Thus
assessment was done based solely on information provided by the
submitted project profile.
(2) Based on the project profile, project construction at Tuen Mun Area
38 would tentatively be commenced in 2019 and be completed by 2023.
It is not expected that the marine construction required for the second
additional CCGT unit under this Project would be conducted
concurrently with those of the Tuen Mun Area 38 project. No
cumulative construction phase impact is expected.
(3) There is no sewage discharge under this Project. No thermal
discharge from the Tuen Mun Area 38 project is expected as well.
Therefore no cumulative water quality impact would be expected from
the discharge of treated sewage effluent under the Tuen Mun Area 38
project.
West New Territories (WENT)
Landfill Extensions (Register
No.: AEIAR-147/2009)
Uncertain West New
Territories
(WENT) Landfill
(2 km away)
nil No marine construction as well as direct discharge of sewage or landfill
leachate would be expected from the expanded operation. Therefore no
cumulative water quality impact would be expected.
ENVIRONMENTAL RESOURCES MANAGEMENT CASTLE PEAK POWER COMPANY LIMITED
0308057_S7_WATER_REV 3.DOCX APRIL 2016
7-59
Project Duration Location Major Marine Activity Considerations in Water Quality Assessment
Expansion of Hong Kong
International Airport into a
Three-Runway System (Register
No.: AEIAR- 185/2014)
Construction: 2015
to 2023
HKIA and the
marine waters
north to the HKIA
(> 8 km away)
(1) Marine ground
treatment, seawall
construction,
reclamation for the
proposed third runway
(2) Dredging for
approach beacons and
submarine cable field
joint excavation
(3) Cooling water intake
and thermal discharge
(1) Based on the approved EIA, the marine construction works would be
conducted from late 2015 to 2021. Based on the information available at
the time of report, it is not expected that the marine construction for the
second additional CCGT unit under this Project would be conducted
concurrently with those under the 3RS-HKIA. Therefore no cumulative
construction phase assessment is required.
(2) The proposed reclamation of the three runway system is expected to
be completed before the commencement of the marine construction
under this Project. Therefore the presence of reclamation of the three
runway system has been included in the modelling assessment for
construction and operation phase under this EIA.
(3) Cooling water intakes and thermal discharge from the expanded
airport operation is considered minimal and is far away from the Project
(> 9km). Therefore they are not taken into account in the modelling
assessment.
Pyrolysis Plant at EcoPark (EIA
Study Brief ESB-259/2013)
Construction: 2015 EcoPark of Tuen
Mun (4.5 km
away)
nil (1) No marine works would be required for the pyrolysis plant
development. No cumulative construction phase assessment would be
required.
(2) Based on its EIA Project Profile, the cooling water for the pyrolysis
plant would be reused in closed circuit system. Therefore, no thermal
discharge and discharge of associated chlorine or biocides would be
expected.
ENVIRONMENTAL RESOURCES MANAGEMENT CASTLE PEAK POWER COMPANY LIMITED
0308057_S7_WATER_REV 3.DOCX APRIL 2016
7-60
Project Duration Location Major Marine Activity Considerations in Water Quality Assessment
Potential Reclamation Site at
Lung Kwu Tan
Uncertain Lung Kwu Tan
(1.5 km away)
Reclamation (1) Letter was issued to the Civil Engineering and Development
Department (CEDD, the project proponent) to obtain the letter project
update. CEDD replied the reclamation at Lung Kwu Chau would be
commenced in 2021 the earliest, and could be subjected to changes.
CEDD also advised the consultant to refer to Cumulative Environmental
Impact Assessment for the Three Potential Reclamation Sites in Western Waters (1) for information regarding other project information.
(2) The potential reclamation has been taken into account in the
operation phase water quality assessment to capture potential worst case
for operation. On the other hand, due to the lack of detailed
construction programme, phasing and construction method for the
reclamation at Lung Kwu Tan project, no cumulative construction phase
assessment can be conducted.
Enhanced Ash Utilisation and
Water Management Facilities at
Castle Peak Power Station
(CPPS) (EP-441/2012)
Construction: 2016
to 2019
Castle Peak
Power Station (3
km away)
nil No marine works and major discharge to marine water would be
required for this project. No cumulative water quality assessment
would be required.
Decommissioning of West
Portion of the Middle Ash
Lagoon at Tsang Tsui, Tuen
Mun (Register No.: AEIAR-
186/2015)
Decommission:
September 2015 to
March 2016
Tsang Tsui Ash
Lagoon (1 km
away)
nil No marine works would be required for this project. Since this is a
decommissioning project, there will not be an operation phase and no
discharge of cooling water or chlorine would be expected after the
completion of construction phase. No cumulative water quality
assessment would be required.
(1) Agreement No. CE 14/2013 (CE) Cumulative Environmental Impact Assessment Study for the Three Potential Nearshore Reclamation Sites in the Western Waters of Hong Kong - Investigation -
Executive Summary (Final) (2013). Retrieved October 6, 2015 from Civil Engineering and Development Department, Web site:
http://www.cedd.gov.hk/eng/landsupply/doc/Executive%20Summary%20on%20Final%20Report(S2)b.pdf
ENVIRONMENTAL RESOURCES MANAGEMENT CASTLE PEAK POWER COMPANY LIMITED
0308057_S7_WATER_REV 3.DOCX APRIL 2016
7-61
Project Duration Location Major Marine Activity Considerations in Water Quality Assessment
Sludge Treatment Facilities (STF)
(Register No. AEIAR-129/2009)
Existing operation Tsang Tsui (1.5
km away)
nil (1) The sewage effluent from the Sludge Treatment Facilities operation
would be treated and reused onsite. No sewage discharge would be
required.
(2) A small scale desalination plant is installed onsite with saline
discharge of about 1,000 m3 per day at about 1.7 times salinity of ambient
seawater salinity. The discharge rate is quite low (about 11.6 L/s) and
is considered negligible from 1.5 km away. The seawater intake for the
desalination plant has been taken into account in the modelling exercise
as a WSR (SR16).
Permanent Aviation Fuel
Facility (PAFF) for Hong Kong
International Airport (Register
No.: AEIAR-107/2007)
Existing operation Castle Peak, Tuen
Mun (4.5 km
away)
nil No marine works and major discharge to marine water would be
required for this project. No cumulative water quality assessment
would be required.
Black Point Power Station
(BPPS)
Existing operation At the immediate
vicinity
Cooling water discharge (1) The existing thermal discharge from the existing operation of the
BPPS has been taken into account in the construction and operation
phase modelling exercise. Also, the thermal and TRC discharge from
existing CCGT units at the BPPS have also been modelled in the baseline
and operation scenarios.
(2) The existing seawater intake of the BPPS has been taken into account
as a WSR (SR4) in the water quality modelling exercise.
Castle Peak Power Station
(CPPS)
Existing operation Castle Peak, Tuen
Mun (4 km away)
Cooling water discharge (1) The existing discharge from the CPPS has been taken into account in
both the construction and operation phase sediment plume modelling
and thermal discharge modelling. Also, the thermal and TRC discharge
from the existing CCGT units at the BPPS has also been modelled in the
baseline and operation scenarios.
(2) The existing seawater intake of the CPPS has been taken into account
as WSR (SR9) in the water quality modelling exercise.
Green Island Cement Plant
Existing operation Castle Peak, Tuen
Mun (4 km away)
nil There is no known discharge of cooling water or chlorine to marine
water from this current operation (1). No cumulative water quality
impact from the operation of the Green Island Cement Plant is expected.
(1) Green Island Cement (holding) Limited (2013). Cement Manufacturing Process. Retrieved October 2, 2015 from, Web site: http://www.gich.com.hk/Facilities/f_manflow.htm.
ENVIRONMENTAL RESOURCES MANAGEMENT CASTLE PEAK POWER COMPANY LIMITED
0308057_S7_WATER_REV 3.DOCX APRIL 2016
7-62
Project Duration Location Major Marine Activity Considerations in Water Quality Assessment
Shiu Wing Steel Mill Existing operation Castle Peak, Tuen
Mun (4 km away)
nil (1) There is no known discharge of cooling water or chlorine to marine
water from this current operation. No cumulative water quality impact
from the operation of the Green Island Cement Plant is expected.
(2) The seawater intake for Shiu Wing Steel Mill has been taken into
account as a WSR (SR10) in the water quality modelling exercise.
ENVIRONMENTAL RESOURCES MANAGEMENT CASTLE PEAK POWER COMPANY LIMITED
0308057_S7_WATER_REV 3.DOCX APRIL 2016
7-63
7.12 ENVIRONMENTAL MONITORING AND AUDIT
7.12.1 Construction Phase
Marine water quality monitoring at selected WSRs is recommended for
marine dredging at seawater intake and discharge outfall under this Project.
Site audit would also be conducted throughout the marine and land-based
construction under this Project. Details of the environmental monitoring
procedures and audit requirements are provided in the standalone EM&A
Manual.
7.12.2 Operation Phase
It is expected that regular monitoring of effluent quality during normal
operation is required under the WPCO Discharge Licence of the future
expanded BPPS. To ensure compliance with the effluent standard specified
in Sections 7.8.1 and 7.8.2 (or other standard stipulated in the WPCO Discharge
Permit), marine water monitoring at selected nearby WSRs during the first
year of project commission of the first and second additional CCGT units are
recommended to ensure compliance with WQO or other water quality criteria.
Details of the environmental monitoring procedures and audit requirements
are provided in the standalone EM&A Manual.
Marine water quality monitoring at selected nearby WSRs would also be
required for maintenance dredging at seawater intake and discharge outfall.
Details of the environmental monitoring procedures and audit requirements
are provided in the standalone EM&A Manual.
7.13 CONCLUSION
7.13.1 Construction Phase
Computational modelling has been conducted to predict various potential
water quality impacts from the proposed marine dredging operation under
this Project, including SS elevation, sedimentation, DO depletion, release of
nutrient, heavy metal and trace organic pollutants. Full compliance is
predicted at all identified WSRs for all parameters in both seasons with the
implementation of (1) reduction in dredging rate from 4,000 m3 per day to 740
m3 per day, (2) silt curtain around grab dredger and (3) another layer of silt
curtain surrounding coral colonies at SR18. To ensure environmental
compliance, marine water monitoring for the marine dredging works is
recommended.
Other potential water quality impacts from marine and land-based
construction were also addressed. Appropriate preventive and mitigation
measures are recommended to minimise the potential water quality impact
from these works. Environmental monitoring and audit is recommended to
ensure the proper implementation of these measures.
ENVIRONMENTAL RESOURCES MANAGEMENT CASTLE PEAK POWER COMPANY LIMITED
0308057_S7_WATER_REV 3.DOCX APRIL 2016
7-64
7.13.2 Operation Phase
The potential change in hydrodynamic and water quality from Project
operation was assessed in detail using Delft3D modelling tools. The changes
in water temperature as well as TRC at WSRs during normal operation were
assessed quantitatively. The increase in water temperature and TRC level is
predicted to be highly localised in both seasons. The elevation in
temperature and TRC are predicted to be diluted and dissipated soon after
leaving the discharge outfall. The predicted effluent plume would not
encroach to additional nearby marine ecology and fisheries resources. To
ensure environmental compliance, monitoring of discharge effluent quality
and marine water quality at nearby selected WSRs are recommended.
No significant increase in potential risk of fuel spillage is expected from the
operation of the additional CCGT units. Design features such as shutdown
valves and leak detectors have been included to avoid and minimise potential
fuel leak. Contingency plan for the existing operation of the BPPS would be
in place and would be sufficient for directing immediate response to any
accidental spillage event. Therefore no significant increase in potential risk
of fuel spillage is expected.
With the implementation of the proposed measures in controlling overall
pollution load discharge from the BPPS into the Deep Bay WCZ, there would
be no net increase in pollution load into the Deep Bay WCZ from the BPPS
upon the future expanded operation. No unacceptable water quality impact
from the operation of the proposed additional CCGT units is expected.
Maintenance dredging at seawater intake and discharge outfall is also
expected during operation phase of the additional CCGT Unit No.2. No
unacceptable water quality impact from the maintenance dredging is expected
to the nearby WSRs.