New Reactor Construction Inspection
New Reactor Construction Inspection
Hal Thornberry
Vice President, Nuclear Construction
NRC Regulatory Information Conference
March 11, 2009
3
V.C. Summer, Vogtle Levy County ProjectsV.C. Summer, Vogtle Levy County Projects
• Shaw responsibilities:– Engineering– Procurement– Turbine island/balance of plant– Site-specific systems– Yard work – Construction
• Engineering, procurement, limited site development underway
• Permanent plant construction cannot beginuntil NRC approval of COLA in 2011-12,unless granted Limited Work Authorization
• First new unit at each site scheduled to begin commercial operation in 2016
4
Sanmen and Haiyang ProjectsSanmen and Haiyang Projects
• Twin AP1000™ units at each site
• Excavation started ahead of schedule– Sanmen: February 2008
– Haiyang: July 2008
• Start of commercial operation: – Sanmen: 2013
– Haiyang: 2014
5
85M
1020
06D
Sanmen Module Assembly Area Sanmen Module Assembly Area
6
85M
1020
06D
Inspection Preparation for ModulesInspection Preparation for Modules
• In-house fabrication and module expertise leveragedin creation of Global Modular Solutions– Shaw Fabrication & Manufacturing maintained ASME certification
for all activities related to construction of nuclear components – Assembly of modules in manufacturing setting will provide
consistent quality, reduce construction site activity– Fabrication of assemblies at one location will simplify
some NRC inspection activity
7
85M
1020
06D
Preparation for Construction InspectionPreparation for Construction Inspection
• Applying lessons learned from current Shaw nuclear projects– MOX (design, construction management)– LES (design)– China AP1000s (construction management)
• Evaluating lessons learned from first generationof nuclear construction, recent industry activity
• Flow mapping of construction installation activities, turnover and documentation processes
• Aligning construction procedures with NRC programs (including ITAAC), focus on ease of implementation
8
8
85M
1020
06D
Preparation for Construction Inspection (cont.)Preparation for Construction Inspection (cont.)
• Nuclear culture– Build on first NRC-approved Nuclear Quality Assurance Program
– Continued development of Safety-Conscious Work Environment
• Construction readiness reviews– Develop key project milestones
– Ensure reviews are timely and focused
– Establish a level of confidence
– Identify areas for improvement
– Identify programmatic issues
9
85M
1020
06D
Preparation for Construction Inspection (cont.)Preparation for Construction Inspection (cont.)
• Training and qualification – Construction training
– Craft skills training
– Process certification
• New plant construction – Training on Part 52 and ITAAC
– ITAAC planning and scheduling
– ITAAC maintenance
10
85M
1020
06D
Preparation for Construction Inspection (cont.)Preparation for Construction Inspection (cont.)
• Teamwork and interface with AP1000™ partners– U.S. AP1000™ project staff taking active role in construction
management and other key activities on China projects
– Development of QA/QC programs and policies
• Need for strong interaction with on-site NRC inspector