+ All Categories
Home > Documents > 9. Checkpoints of the process - student.apamaravathi.in · Iterative Process Planning: Work...

9. Checkpoints of the process - student.apamaravathi.in · Iterative Process Planning: Work...

Date post: 15-May-2020
Category:
Upload: others
View: 5 times
Download: 0 times
Share this document with a friend
17
UNIT - V Checkpoints of the process: Major mile stones, Minor Milestones, Periodic status assessments. Iterative Process Planning: Work breakdown structures, planning guidelines, cost and schedule estimating, Iteration planning process, Pragmatic planning. 9. Checkpoints of the process Three types of joint management reviews are conducted throughout the process: 1. Major milestones. These system wide events are held at the end of each development phase. They provide visibility to system wide issues, synchronize the management and engineering perspectives, and verify that the aims of the phase have been achieved. 2. Minor milestones. These iteration-focused events are conducted to review the content of an iteration in detail and to authorize continued work. 3. Status assessments. These periodic events provide management with frequent and regular insight into the progress being made. Each of the four phases-inception, elaboration, construction, and transition consists of one or more iterations and concludes with a major milestone when a planned technical capability is produced in demonstrable form. An iteration represents a cycle of activities for which there is a well-defined intermediate result-a minor milestone-captured with two artifacts: a release specification (the evaluation criteria and plan) and a release description (the results). Major milestones at the end of each phase use formal, stakeholder-approved evaluation criteria and release descriptions; minor milestones use informal, development-team-controlled versions of these artifacts. Figure 9-1 illustrates a typical sequence of project checkpoints for a relatively large project. MVR CSE
Transcript
Page 1: 9. Checkpoints of the process - student.apamaravathi.in · Iterative Process Planning: Work breakdown structures, planning guidelines, cost and schedule estimating, Iteration planning

UNIT - V Checkpoints of the process: Major mile stones, Minor Milestones, Periodic status

assessments.

Iterative Process Planning: Work breakdown structures, planning guidelines, cost and

schedule estimating, Iteration planning process, Pragmatic planning.

9. Checkpoints of the process Three types of joint management reviews are conducted throughout the process:

1. Major milestones. These system wide events are held at the end of each development phase. They provide visibility to system wide issues, synchronize the management and engineering perspectives, and verify that the aims of the phase have been achieved.

2. Minor milestones. These iteration-focused events are conducted to review the content of an iteration in detail and to authorize continued work.

3. Status assessments. These periodic events provide management with frequent and regular insight into the progress being made.

Each of the four phases-inception, elaboration, construction, and transition consists of one or more iterations and concludes with a major milestone when a planned technical capability is produced in demonstrable form. An iteration represents a cycle of activities for which there is a well-defined intermediate result-a minor milestone-captured with two artifacts: a release specification (the evaluation criteria and plan) and a release description (the results). Major milestones at the end of each phase use formal, stakeholder-approved evaluation criteria and release descriptions; minor milestones use informal, development-team-controlled versions of these artifacts. Figure 9-1 illustrates a typical sequence of project checkpoints for a relatively large project.

MVR CSE

Page 2: 9. Checkpoints of the process - student.apamaravathi.in · Iterative Process Planning: Work breakdown structures, planning guidelines, cost and schedule estimating, Iteration planning

9.1 MAJOR MILESTONES

The four major milestones occur at the transition points between life-cycle phases. They can be used in many different process models, including the conventional waterfall model. In an iterative model, the major milestones are used to achieve concurrence among all stakeholders on the current state of the project. Different stakeholders have very different concerns:

Customers: schedule and budget estimates, feasibility, risk assessment, requirements understanding, progress, product line compatibility

Users: consistency with requirements and usage scenarios, potential for accommodating growth, quality attributes

Architects and systems engineers: product line compatibility, requirements changes, trade-off analyses, completeness and consistency, balance among risk, quality, and usability

Developers: sufficiency of requirements detail and usage scenario descriptions, . frameworks for component selection or development, resolution of development risk, product line compatibility, sufficiency of the development environment

Maintainers: sufficiency of product and documentation artifacts, understandability, interoperability with existing systems, sufficiency of maintenance environment

Others: possibly many other perspectives by stakeholders such as regulatory agencies, independent verification and validation contractors, venture capital investors, subcontractors, associate contractors, and sales and marketing teams

Table 9-1 summarizes the balance of information across the major milestones.

MVR CSE

Page 3: 9. Checkpoints of the process - student.apamaravathi.in · Iterative Process Planning: Work breakdown structures, planning guidelines, cost and schedule estimating, Iteration planning

Life-Cycle Objectives Milestone The life-cycle objectives milestone occurs at the end of the inception phase. The goal is to present to all stakeholders a recommendation on how to proceed with development, including a plan, estimated cost and schedule, and expected benefits and cost savings. A successfully completed life-cycle objectives milestone will result in authorization from all stakeholders to proceed with the elaboration phase. Life-Cycle Architecture Milestone The life-cycle architecture milestone occurs at the end of the elaboration phase. The primary goal is to demonstrate an executable architecture to all stakeholders. The baseline architecture consists of both a human-readable representation (the architecture document) and a configuration-controlled set of software components captured in the engineering artifacts. A successfully completed life-cycle architecture milestone will result in authorization from the stakeholders to proceed with the construction phase.

MVR CSE

Page 4: 9. Checkpoints of the process - student.apamaravathi.in · Iterative Process Planning: Work breakdown structures, planning guidelines, cost and schedule estimating, Iteration planning

The technical data listed in Figure 9-2 should have been reviewed by the time of the lifecycle architecture milestone. Figure 9-3 provides default agendas for this milestone.

MVR CSE

Page 5: 9. Checkpoints of the process - student.apamaravathi.in · Iterative Process Planning: Work breakdown structures, planning guidelines, cost and schedule estimating, Iteration planning

Initial Operational Capability Milestone The initial operational capability milestone occurs late in the construction phase. The goals

are to assess the readiness of the software to begin the transition into customer/user sites and

to authorize the start of acceptance testing. Acceptance testing can be done incrementally

across multiple iterations or can be completed entirely during the transition phase is not

necessarily the completion of the construction phase. Product Release Milestone

The product release milestone occurs at the end of the transition phase. The goal is to assess the completion of the software and its transition to the support organization, if any. The results of acceptance testing are reviewed, and all open issues are addressed. Software quality metrics are reviewed to determine whether quality is sufficient for transition to the support organization.

MVR CSE

Page 6: 9. Checkpoints of the process - student.apamaravathi.in · Iterative Process Planning: Work breakdown structures, planning guidelines, cost and schedule estimating, Iteration planning

9.2 MINOR MILESTONES

For most iterations, which have a one-month to six-month duration, only two minor milestones are needed: the iteration readiness review and the iteration assessment review.

Iteration Readiness Review. This informal milestone is conducted at the start of each iteration to review the detailed iteration plan and the evaluation criteria that have been allocated to this iteration .

Iteration Assessment Review. This informal milestone is conducted at the end of each iteration to assess the degree to which the iteration achieved its objectives and satisfied its evaluation criteria, to review iteration results, to review qualification test results (if part of the iteration), to determine the amount of rework to be done, and to review the impact of the iteration results on the plan for subsequent iterations.

The format and content of these minor milestones tend to be highly dependent on the project and the organizational culture. Figure 9-4 identifies the various minor milestones to be considered when a project is being planned.

9.3 PERIODIC STATUS ASSESSMENTS Periodic status assessments are management reviews conducted at regular intervals (monthly, quarterly) to address progress and quality indicators, ensure continuous attention to project dynamics, and maintain open communications among all stakeholders. Periodic status assessments serve as project snapshots. While the period may vary, the recurring event forces the project history to be captured and documented. Status assessments provide the following: A mechanism for openly addressing, communicating, and resolving management

issues, technical issues, and project risks

Objective data derived directly from on-going activities and evolving product configurations

A mechanism for disseminating process, progress, quality trends, practices, and experience information to and from all stakeholders in an open forum Periodic status assessments are crucial for focusing continuous attention on the evolving

health of the project and its dynamic priorities. They force the software project manager to collect and review the data periodically, force outside peer review, and encourage

MVR CSE

Page 7: 9. Checkpoints of the process - student.apamaravathi.in · Iterative Process Planning: Work breakdown structures, planning guidelines, cost and schedule estimating, Iteration planning

dissemination of best practices to and from other stakeholders.

The default content of periodic status assessments should include the topics identified in

Table 9-2.

10. Iterative process planning

A good work breakdown structure and its synchronization with the process framework are critical factors in software project success. Development of a work breakdown structure dependent on the project management style, organizational culture, customer preference, financial constraints, and several other hard-to-define, project-specific parameters. A WBS is simply a hierarchy of elements that decomposes the project plan into the discrete work tasks. A WBS provides the following information structure: A delineation of all significant work

A clear task decomposition for assignment of responsibilities

A framework for scheduling, budgeting, and expenditure tracking

Many parameters can drive the decomposition of work into discrete tasks: product

subsystems, components, functions, organizational units, life-cycle phases, even geographies.

Most systems have a first-level decomposition by subsystem. Subsystems are then

decomposed into their components, one of which is typically the software.

10.1.1 CONVENTIONAL WBS ISSUES

MVR CSE

Page 8: 9. Checkpoints of the process - student.apamaravathi.in · Iterative Process Planning: Work breakdown structures, planning guidelines, cost and schedule estimating, Iteration planning

Conventional work breakdown structures frequently suffer from three fundamental flaws.

1. They are prematurely structured around the product design.

2. They are prematurely decomposed, planned, and budgeted in either too much or too little detail.

3. They are project-specific, and cross-project comparisons are usually difficult or impossible.

Conventional work breakdown structures are prematurely structured around the product design. Figure 10-1 shows a typical conventional WBS that has been structured primarily around the subsystems of its product architecture, then further decomposed into the components of each subsystem. A WBS is the architecture for the financial plan.

Conventional work breakdown structures are prematurely decomposed, planned, and budgeted in either too little or too much detail. Large software projects tend to be over planned and small projects tend to be under planned. The basic problem with planning too much detail at the outset is that the detail does not evolve with the level of fidelity in the plan.

Conventional work breakdown structures are project-specific, and cross-project comparisons are usually difficult or impossible. With no standard WBS structure, it is extremely difficult to compare plans, financial data, schedule data, organizational efficiencies, cost trends, productivity trends, or quality trends across multiple projects.

MVR CSE

Page 9: 9. Checkpoints of the process - student.apamaravathi.in · Iterative Process Planning: Work breakdown structures, planning guidelines, cost and schedule estimating, Iteration planning

Figure 10-1 Conventional work breakdown structure, following the product

hierarchy

Management

System requirement and design

Subsystem 1

Component 11

Requirements

Design

Code

Test

Documentation

…(similar structures for other components) Component 1N

Requirements

Design

Code

Test

Documentation

…(similar structures for other subsystems) Subsystem M

Component M1

Requirements

Design

Code

Test

Documentation

…(similar structures for other components)

Component MN

Requirements

Design

Code

Test

Documentation

Integration and test

Test planning

Test procedure preparation

Testing

Test reports

Other support areas

Configuration control

Quality assurance

System administration

MVR CSE

Page 10: 9. Checkpoints of the process - student.apamaravathi.in · Iterative Process Planning: Work breakdown structures, planning guidelines, cost and schedule estimating, Iteration planning

10.1.2 EVOLUTIONARY WORK BREAKDOWN STRUCTURES An evolutionary WBS should organize the planning elements around the process framework rather than the product framework. The basic recommendation for the WBS is to organize the hierarchy as follows:

First-level WBS elements are the workflows (management, environment, requirements, design, implementation, assessment, and deployment).

Second-level elements are defined for each phase of the life cycle (inception, elaboration, construction, and transition).

Third-level elements are defined for the focus of activities that produce the artifacts of each phase.

A default WBS consistent with the process framework (phases, workflows, and artifacts) is shown in Figure 10-2. This recommended structure provides one example of how the elements of the process framework can be integrated into a plan. It provides a framework for estimating the costs and schedules of each element, allocating them across a project organization, and tracking expenditures.

The structure shown is intended to be merely a starting point. It needs to be tailored to the specifics of a project in many ways.

Scale. Larger projects will have more levels and substructures.

Organizational structure. Projects that include subcontractors or span multiple organizational entities may introduce constraints that necessitate different WBS allocations.

Degree of custom development. Depending on the character of the project, there can be very different emphases in the requirements, design, and implementation workflows.

Business context. Projects developing commercial products for delivery to a broad customer base may require much more elaborate substructures for the deployment element.

Precedent experience. Very few projects start with a clean slate. Most of them are developed as new generations of a legacy system (with a mature WBS) or in the context of existing organizational standards (with preordained WBS expectations).

The WBS decomposes the character of the project and maps it to the life cycle, the budget, and the personnel. Reviewing a WBS provides insight into the important attributes, priorities, and structure of the project plan. Another important attribute of a good WBS is that the planning fidelity inherent in each element is commensurate with the current life-cycle phase and project state. Figure 10-3 illustrates this idea. One of the primary reasons for organizing the default WBS the way I have is to allow for planning elements that range from planning packages (rough budgets that are maintained as an estimate for future elaboration rather than being decomposed into detail) through fully planned activity networks (with a well-defined budget and continuous assessment of actual versus planned expenditures).

MVR CSE

Page 11: 9. Checkpoints of the process - student.apamaravathi.in · Iterative Process Planning: Work breakdown structures, planning guidelines, cost and schedule estimating, Iteration planning

Figure 10-2 Default work breakdown structure

A Management

AA Inception phase management

AAA Business case development

AAB Elaboration phase release specifications

AAC Elaboration phase WBS specifications

AAD Software development plan

AAE Inception phase project control and status assessments

AB Elaboration phase management

ABA Construction phase release specifications

ABB Construction phase WBS baselining

ABC Elaboration phase project control and status assessments

AC Construction phase management

ACA Deployment phase planning

ACB Deployment phase WBS baselining

ACC Construction phase project control and status assessments

AD Transition phase management

ADA Next generation planning

ADB Transition phase project control and status assessments

B Environment

BA Inception phase environment specification

BB Elaboration phase environment baselining

BBA Development environment installation and administration

BBB Development environment integration and custom toolsmithing

BBC SCO database formulation

BC Construction phase environment maintenance

BCA Development environment installation and administration

BCB SCO database maintenance

BD Transition phase environment maintenance

BDA Development environment maintenance and administration

BDB SCO database maintenance

BDC Maintenance environment packaging and transition

C Requirements

CA Inception phase requirements development

CCA Vision specification

CAB Use case modeling

CB Elaboration phase requirements baselining

CBA Vision baselining

CBB Use case model baselining

MVR CSE

Page 12: 9. Checkpoints of the process - student.apamaravathi.in · Iterative Process Planning: Work breakdown structures, planning guidelines, cost and schedule estimating, Iteration planning

CC Construction phase requirements maintenance

CD Transition phase requirements maintenance

D Design

DA Inception phase architecture prototyping

DB Elaboration phase architecture baselining

DBA Architecture design modeling

DBB Design demonstration planning and conduct

DBC Software architecture description

DC Construction phase design modeling

DCA Architecture design model maintenance

DCB Component design modeling

DD Transition phase design maintenance

E Implementation

EA Inception phase component prototyping

EB Elaboration phase component implementation

EBA Critical component coding demonstration integration

EC Construction phase component implementation

ECA Initial release(s) component coding and stand-alone testing

ECB Alpha release component coding and stand-alone testing

ECC Beta release component coding and stand-alone testing

ECD Component maintenance

F Assessment

FA Inception phase assessment

FB Elaboration phase assessment

FBA Test modeling

FBB Architecture test scenario implementation

FBC Demonstration assessment and release descriptions

FC Construction phase assessment

FCA Initial release assessment and release description

FCB Alpha release assessment and release description

FCC Beta release assessment and release description

FD Transition phase assessment

FDA Product release assessment and release description

G Deployment

GA Inception phase deployment planning

GB Elaboration phase deployment planning

GC Construction phase deployment

GCA User manual baselining

GD Transition phase deployment

GDA Product transition to user

MVR CSE

Page 13: 9. Checkpoints of the process - student.apamaravathi.in · Iterative Process Planning: Work breakdown structures, planning guidelines, cost and schedule estimating, Iteration planning

Figure 10-3 Evolution of planning fidelity in the WBS over the life cycle

Inception Elaboration

WBS Element Fidelity WBS Element Fidelity

Management High Management High

Environment Moderate Environment High

Requirement High Requirement High

Design Moderate Design High

Implementation Low Implementation Moderate

Assessment Low Assessment Moderate

Deployment Low Deployment Low

WBS Element Fidelity WBS Element Fidelity

Management High Management High

Environment High Environment High

Requirements Low Requirements Low

Design Low Design Moderate

Implementation Moderate Implementation High

Assessment High Assessment High Deployment High Deployment Moderate

Transition Construction

10.2 PLANNING GUIDELINES Software projects span a broad range of application domains. It is valuable but risky to make

specific planning recommendations independent of project context. Project-independent

planning advice is also risky. There is the risk that the guidelines may pe adopted blindly

without being adapted to specific project circumstances. Two simple planning guidelines

should be considered when a project plan is being initiated or assessed. The first guideline,

detailed in Table 10-1, prescribes a default allocation of costs among the first-level WBS

elements. The second guideline, detailed in Table 10-2, prescribes the allocation of effort and

schedule across the lifecycle phases.

MVR CSE

Page 14: 9. Checkpoints of the process - student.apamaravathi.in · Iterative Process Planning: Work breakdown structures, planning guidelines, cost and schedule estimating, Iteration planning

10-1 Web budgeting defaults

First Level WBS Element Default Budget

Management 10%

Environment 10%

Requirement 10%

Design 15%

Implementation 25%

Assessment 25%

Deployment 5%

Total 100%

Table 10-2 Default distributions of effort and schedule by phase

Domain Inception Elaboration Construction Transition

Effort 5% 20% 65% 10%

Schedule 10% 30% 50% 10%

10.3 THE COST AND SCHEDULE ESTIMATING PROCESS

Project plans need to be derived from two perspectives. The first is a forward-looking, top-down approach. It starts with an understanding of the general requirements and constraints, derives a macro-level budget and schedule, then decomposes these elements into lower level budgets and intermediate milestones. From this perspective, the following planning sequence would occur:

1. The software project manager (and others) develops a characterization of the overall size, process, environment, people, and quality required for the project.

2. A macro-level estimate of the total effort and schedule is developed using a software cost estimation model.

3. The software project manager partitions the estimate for the effort into a top-level WBS using guidelines such as those in Table 10-1.

4. At this point, subproject managers are given the responsibility for decomposing each of the WBS elements into lower levels using their top-level allocation, staffing profile, and major milestone dates as constraints.

The second perspective is a backward-looking, bottom-up approach. We start with the end in mind, analyze the micro-level budgets and schedules, then sum all these elements into the higher level budgets and intermediate milestones. This approach tends to define and populate the WBS from the lowest levels upward. From this perspective, the following planning sequence would occur:

1. The lowest level WBS elements are elaborated into detailed tasks

2. Estimates are combined and integrated into higher level budgets and milestones.

3. Comparisons are made with the top-down budgets and schedule milestones.

Milestone scheduling or budget allocation through top-down estimating tends to exaggerate the project management biases and usually results in an overly optimistic plan. Bottom-up

MVR CSE

Page 15: 9. Checkpoints of the process - student.apamaravathi.in · Iterative Process Planning: Work breakdown structures, planning guidelines, cost and schedule estimating, Iteration planning

estimates usually exaggerate the performer biases and result in an overly pessimistic plan. These two planning approaches should be used together, in balance, throughout the life

cycle of the project. During the engineering stage, the top-down perspective will dominate because there is usually not enough depth of understanding nor stability in the detailed task sequences to perform credible bottom-up planning. During the production stage, there should be enough precedent experience and planning fidelity that the bottom-up planning perspective will dominate. Top-down approach should be well tuned to the project-specific parameters, so it should be used more as a global assessment technique. Figure 10-4 illustrates this life-cycle planning balance.

Figure 10-4 Planning balance throughout the life cycle

Bottom up task level planning based on

metrics from previous iterations

Top down project level planning based on

microanalysis from previous projects

Engineering Stage Production Stage

Inception Elaboration Construction Transition Feasibility iteration Architecture iteration Usable iteration Product

Releases

Engineering stage planning

emphasis

Production stage planning

emphasis

Macro level task estimation for

production stage artifacts

Micro level task estimation for

production stage artifacts

Micro level task estimation for

engineering artifacts

Macro level task estimation for

maintenance of engineering artifacts

Stakeholder concurrence Stakeholder concurrence

Coarse grained variance analysis of

actual vs planned expenditures

Fine grained variance analysis of actual

vs planned expenditures

Tuning the top down project

independent planning guidelines into

project specific planning guidelines

WBS definition and elaboration

10.4 THE ITERATION PLANNING PROCESS Planning is concerned with defining the actual sequence of intermediate results. An evolutionary build plan is important because there are always adjustments in build content and schedule as early conjecture evolves into well-understood project circumstances. Iteration is used to mean a complete synchronization across the project, with a well-

MVR CSE

Page 16: 9. Checkpoints of the process - student.apamaravathi.in · Iterative Process Planning: Work breakdown structures, planning guidelines, cost and schedule estimating, Iteration planning

orchestrated global assessment of the entire project baseline. Inception iterations. The early prototyping activities integrate the foundation

components of a candidate architecture and provide an executable framework for elaborating the critical use cases of the system. This framework includes existing components, commercial components, and custom prototypes sufficient to demonstrate a candidate architecture and sufficient requirements understanding to establish a credible business case, vision, and software development plan.

Elaboration iterations. These iterations result in architecture, including a complete framework and infrastructure for execution. Upon completion of the architecture iteration, a few critical use cases should be demonstrable: (1) initializing the architecture, (2) injecting a scenario to drive the worst-case data processing flow through the system (for example, the peak transaction throughput or peak load scenario), and (3) injecting a scenario to drive the worst-case control flow through the system (for example, orchestrating the fault-tolerance use cases).

Construction iterations. Most projects require at least two major construction iterations: an alpha release and a beta release.

Transition iterations. Most projects use a single iteration to transition a beta release into the final product.

The general guideline is that most projects will use between four and nine iterations. The typical project would have the following six-iteration profile:

One iteration in inception: an architecture prototype

Two iterations in elaboration: architecture prototype and architecture baseline

Two iterations in construction: alpha and beta releases

One iteration in transition: product release

A very large or unprecedented project with many stakeholders may require additional

inception iteration and two additional iterations in construction, for a total of nine iterations.

10.5 PRAGMATIC PLANNING Even though good planning is more dynamic in an iterative process, doing it accurately is far

easier. While executing iteration N of any phase, the software project manager must be

monitoring and controlling against a plan that was initiated in iteration N - 1 and must be

planning iteration N + 1. The art of good project· management is to make trade-offs in the

current iteration plan and the next iteration plan based on objective results in the current

iteration and previous iterations. Aside from bad architectures and misunderstood

requirements, inadequate planning (and subsequent bad management) is one of the most

common reasons for project failures. Conversely, the success of every successful project can

be attributed in part to good planning. A project's plan is a definition of how the project requirements will be transformed into' a product within the business constraints. It must be realistic, it must be current, it must be a team product, it must be understood by the stakeholders, and it must be used. Plans are not just for managers. The more open and visible the planning process and results, the more ownership there is among the team members who need to execute it. Bad, closely held plans cause attrition. Good, open plans can shape cultures and encourage teamwork.

Unit – Important Questions

1. Define Model-Based software architecture?

2. Explain various process workflows?

3. Define typical sequence of life cycle checkpoints?

MVR CSE

Page 17: 9. Checkpoints of the process - student.apamaravathi.in · Iterative Process Planning: Work breakdown structures, planning guidelines, cost and schedule estimating, Iteration planning

4. Explain general status of plans, requirements and product across the major milestones.

5. Explain conventional and Evolutionary work break down structures?

6. Explain briefly planning balance throughout the life cycle?

MVR CSE


Recommended