Date post: | 08-Jan-2016 |
Category: |
Documents |
Upload: | hani-a-menem-mahmoud |
View: | 21 times |
Download: | 0 times |
of 23
Planning Repetitive ActivitiesfLine of Balance
Sabah Alkass PhD PEng FASCEProfessor
Line of Balance Planning Techniques
PROCEDURE FOR LOB SCHEDULINGPROCEDURE FOR LOB SCHEDULINGWhen preparing a line of balance schedule the
following stages should be systematically undertaken:
1. Preparation of logic diagram2. Assessment of manhours per operation3. Selection of buffer times4 Assessment of the ate of const ction fo t o
Dr. S. Alkass 2
4. Assessment of the rate of construction for two related operations
5. Assessment of start and finish times for first and last unit
Line of Balance Planning Techniques
Dr. S. Alkass 3
Line of Balance Planning Techniques
1. Preparation of logic diagramThe logic diagram illustrates the sequence ofThe logic diagram illustrates the sequence of
undertaking the construction operations relative to the finish and start of related activities.
FABRICATE
C-COLUMN SEQUENCE
SITESTRIP FNDNS EXT. BWK
FDNDSSUPER
1ST FIX JOINER
A-FOUNDATION SEQUENCE
B-HOUSING SEQUENCE
FABRICATE
REINFTFIX
REINFT
FIX FWK
CONCRETE
COLUMNS
FABRICATE fwk
PILINGPILE CAPS
GROUND BEAMS
ERECT STEEL
EXTERNAL BRICKWORK
ROOF
Dr. S. Alkass 4
FDNDS STRUCTURE ROOF1ST PLUMBER
1ST FIX
ELECTRICIAN
PLASTERROOF CLADDING
D-STEEL FRAMED FACTORY BUILDING
Line of Balance Planning Techniques2. Assessment of manhours per operationThe manhour allocation is required To calculate the operational duration once the gang size
has been established. Assessment of the rate of construction based upon the
forecast completion or handover ratelExample: Operation foundations
Gang size - 2 labourersManhours allocated per unit 64 manhours
Duration for one unit based on an 8 hour working day
Dr. S. Alkass 5
Duration = manhours allocated
Gang size x 8 hours/day
= 64 hours / (2 x 8) = 4 gang days
Line of Balance Planning Techniques
3. Selection of buffer times Th b ff ti i th ti i d i d b t th The buffer time is the time period in days between the
finish of one operation and the commencement of the succeeding one in the construction sequence.
The buffer period allows flexibility to be built into the planning process and is intended to prevent operations p a g p ocess a d s te ded to p e e t ope at o soverlapping.
It enables one trade to be clear of the work area before the next trade commences.The buffer period may be directly affected by
Dr. S. Alkass 6
construction constraints such as allowances for curing times or drying out periods.
Line of Balance Planning Techniques
4. Assessment of the rate of construction for4. Assessment of the rate of construction for two related operations
Example: Foundations project shown in logic diagram ARate of construction 2 house units per week.Number of units to be constructed 10 NosSite Strip 32 hours / unit Operation 1Foundations 120 hours / unit Operation 2
Dr. S. Alkass 7
Ext Bwk - 160 hours / unit Operation 3
Line of Balance Planning Techniques
SITE STRIP OPERATION 1SITE STRIP OPERATION 1Manhours required for 2 units = 2 x 32 hours = 64 manhoursPlanned nos of men to achieve 2 units/week = 64 mh /(40 hours per week)
= 1.5 menOptimum number of men in gang = 2 menNumber of gangs to be used = 1 no.
Actual rate of construction =
Actual no. of men to be used on site strip1 gang consisting of 2 men = 2 menPlanned no. of men to achieve forecast rate of construction of 2 units/week = 1.5 men Actual construction rate = (2.0/1.5) x 2.0 = 2.66
Actual no. of men
Planned no. of menX reqd rate of construction
Dr. S. Alkass 8
Rate of construction required = 2.0 houses/weekUtilizing the labour resources as shown the rate of construction on site strip will be faster than the required rateThe duration of the site strip for each unit will be: (32 manhours / unit ) / (2 men x 8 hours)
= 32 / 16 = 2 days
Line of Balance Planning TechniquesFOUNDATIONS OPERATION 2Manhours required for 2 units = 2 x 120 hours = 240 manhoursPlanned nos of men to achieve 2 units/week = 240 mh /(40 hours per week)
= 6 0 men= 6.0 menOptimum number of men in gang = 3 menNumber of gangs to be used = 2 no.
Actual rate of construction =
Actual no. of men to be used on foundations = 2 gangs consisting of 3 men = 6 men
Actual no. of menPlanned no. of men
X reqd rate of construction
Planned no. of men to achieve forecast rate of construction of 2 units/week = 6 men Actual construction rate = (6.0/6.0) x 2.0 = 2.0Rate of construction required = 2.0 houses/weekUtilizing the labour resources as shown the rate of construction on foundations will be at the required rateThe duration of the foundations work for each unit will be: (120 manhours / unit ) / (3 men x 8 hours) =120 / 24 = 5 days
Dr. S. Alkass 9
hours) 120 / 24 5 days
The rate of construction for the site strip (2.66 units/week) is faster than the rate of construction for the foundations (2.0 units / week). The balance line for the site strip will therefore be at a greater slope than that of the foundations.
Line of Balance Planning Techniques5. Assessment of start and finish times for first and
last unitIn order to develop the balance lines for each operation the start and finish timeIn order to develop the balance lines for each operation, the start and finish time
of the first and last unit must be calculated. Assume that a minimum buffer time of 2 days is to be allowed between the site strip and foundation works.
SITE STRIP - OPERATION 1For the first house unit site strip operationsCommencement of first unit = Day 0Commencement of first unit = Day 0Completion of first unit = Day 0 + Duration = 0+ 2 Days = Day 2
Start of last unit =
Start of last unit = Day 18
(No. of unit 1) x durationNo. of gangs =
(10 1) x 21 =
18
1=18
Dr. S. Alkass 10
Finish of last unit = Day 18 + Duration = Day 18 + 2 = Day 20.Summary: Site stripHouse unit 1 Starts Day 0, Finishes Day 2House unit 10 Starts Day 18, Finishes Day 20.
Line of Balance Planning TechniquesFOUNDATIONS OPERATION 2Commencement of first unit = Unit 1C l i f i i U i 1 D 2 2 d b ffCompletion of site strip to Unit 1 = Day 2 + 2 day buffer =
Day 4 Completion of foundations to Unit 1 = Day 4 + 5 day duration = Day 9
Start of last unit = (No. of units 1) x durationStart of last unit = = Day 4 + (10 1)5 /2 = (9x5)/2= Day 4 + Day 22.5 = Day 26.5
Completion of last unit = Day 26.5 + 5 day duration = Day 31.5
Summary: Foundations
no of gangs
Dr. S. Alkass 11
yHouse unit 1 Starts Day 4, Finishes Day 9House unit 10 Starts Day 26.5, Finishes Day 31.5
Line of Balance Planning Techniques
EXTERNAL BRICKWORK OPERATION 3Manhours required for 2 units = 2 x 160 hours = 320Planned no. of men to achieve 2 units/week = (320 mh) / (40 hours/week) = 8.0Optimum gang size = 3.0 menNumber of gangs to be used = 3 nosActual rate of construction = (9.0 / 8.0) x 2 = 2.25 units/weekRate of construction required 2 00 units/weekRate of construction required = 2.00 units/weekUsing 3 gangs of 3 men the rate of construction will be faster than the required
rateDuration for 1 unit = 160 mhs / (3 men x 8 hours) = 160 / 24 mh = 6.7 days =
say 7 daysAs the rate of construction for the external brickwork is faster than the foundation
Dr. S. Alkass 12
operation, the balance line will be at a steeper gradient. The external brickwork balance line must
therefore relate to the completion of the last house unit on foundations in order to prevent operations overlapping.
Line of Balance Planning TechniquesCommencement of last house unit unit 10.Completion of foundations to Unit 10 = Day 31.5 + 2 day bufferCommencement of external brickwork for Unit 10 = Day 33.5Completion of external brickwork for Unit 10 = Day 33.5 + 7 day duration =
Day 40.5
Commencement of Unit 1 for ext. bwk
Commencement of ext. bwk to Unit 10 = (No. of units 1) x duration
No of gangs
= Day 33.5 -= Day 12.5
Commencement of external brickwork Unit 1- 12.5Completion of brickwork Unit 1= Day 12.5 + 7 days duration
= Day 19.5
No of gangs
(10-1) x 73
Dr. S. Alkass 13
ySummary: External brickworkHouse Unit 1 Starts Day 12.5, Finishes Day 19.5House Unit 10 Starts Day 33.5, Finishes Day 40.5
Line of Balance Planning Techniques
Dr. S. Alkass 14
Line of Balance Planning Techniques
Dr. S. Alkass 15
Techniques
Line of Balance Planning Techniques
TechniquesResource bar chart
Use of RatiosPlanned performancePlanned performancePlanned liability/planned earning
Actual performanceActual liability/actual earning
Effi i
Dr. S. Alkass 16
EfficiencyActual performance/planned performance
Planning repetitive work
Line of balanceBased on establishing a delivery or a
handover ratehandover rateThe basic construction logic of the
repetitive unit is expressed in a form of a network called a production diagramNormally a constant rate of delivery is
Dr. S. Alkass 17
Normally a constant rate of delivery is used which is expressed in (no.of units/unit time)
Determining the handover rateExample- Road project
6 3 5 7 4
Handover rate
Dr. S. Alkass 18Time (days)0 10 20 30 40 50 60
Determining the handover rate (cont.)Example Road project
Waitingtime
Handover rate
Dr. S. Alkass 19Time (days)0 10 20 30 40 50 60
G1G2
Preparing a L.O.B schedule
In order to avoid non-productive time(Waiting Time) in parallel scheduling, resources are taken into account as part of the scheduling procedure.
Dr. S. Alkass 20
Preparing scheduling information
1 2 3 4 5 6 7 8
M Q g
Example project ( in road project based on R=4)
1 2 3 4 5 6 7 8op. M G Q g U T Ssub str 120 12 3 12 4 5 36 25=37sub.str 120 12 3 12 4 5 36.25=37
sup. str 290 29 6 30 4.14 6.04 35.02=35int.part. 250 25 4 24 3.84 7.81 37.76=38plumb. 40 4 3 3 3 1.67 48.33=49
Dr. S. Alkass 22
pelectr. 30 3 2 2 2.67 1.87 54.31=55finish. 220 22 5 20 3.64 5.5 39.84=40
1 2 3 4 5 6 7 8op. M G Q g U T Ssub.str 120 12 3 12 4 5 36.25=37sup. str 290 29 6 30 4.14 6.04 35.02=35int.part. 250 25 4 24 3.84 7.81 37.76=38plumb. 40 4 3 3 3 1.67 48.33=49electr. 30 3 2 2 2.67 1.87 54.31=55finish. 220 22 5 20 3.64 5.5 39.84=40
Time (days)
0 10 20 30 40 50 60 70 80 90 100