US-95 Granite North Safety Improvements 95 Project Update - January 2019 The Idaho Transportation Department (ITD) held a public meeting on July 31, 2018, to share plans to add frontage roads along US-95 from just south of Homestead Rd. to Trails End Rd. and to widen approximately 1.5 miles of the highway. We heard your concerns and the project team is working to address as many as possible. The project team is working to refine the design and is meeting individually with several property owners to discuss right of way (ROW) needs and impacts. As a result, the ROW acquisition process will occur in spring 2019 rather than this winter. Construction is still anticipated to start in spring/summer of 2020. ITD Project Websites - itdprojects.org 2018 2019 O N D J F M A M J J A S O N D Final Design Bidding & Advertisement ROW Plans Value Engineering Study we are here Conceptual & Final Roadway Design ROW Acquisition Process Meet with Property Owners Schedule
Transcript
Page 1: 95 US-95 Granite North Safety Improvements Project Update - … · 2019. 2. 6. · ITD Project Websites - itdprojects.org 2018 2019 O N D J F M A M J J A S O N D Final Design Bidding

US-95 Granite North Safety Improvements95Project Update - January 2019

The Idaho Transportation Department (ITD) held a public meeting on July 31, 2018, to share plans to add frontage roads along US-95 from just south of Homestead Rd. to Trails End Rd. and to widen approximately 1.5 miles of the highway. We heard your concerns and the project team is working to address as many as possible. The project team is working to refine the design and is meeting individually with several property owners to discuss right of way (ROW) needs and impacts. As a result, the ROW acquisition process will occur in spring 2019 rather than this winter. Construction is still anticipated to start in spring/summer of 2020.

ITD Project Websites - itdprojects.org

2018 2019O N D J F M A M J J A S O N D

Final Design Bidding & Advertisement

ROW Plans

ValueEngineering

Study

we are here

Conceptual & Final Roadway Design

ROW Acquisition Process

Meet with Property Owners

Schedule

Page 2: 95 US-95 Granite North Safety Improvements Project Update - … · 2019. 2. 6. · ITD Project Websites - itdprojects.org 2018 2019 O N D J F M A M J J A S O N D Final Design Bidding

US-95 Granite North Safety Improvements ProjectITD - District 1ATTN: Chance Cole600 W. Prairie AvenueCoeur d’Alene, ID 83814

Idaho Transportation DepartmentUS-95 Granite North Safety ImprovementsIf you have questions, please contact:Merrill SharpITD Project Manager208.334.4420ITD Projects Website - itdprojects.org

Granite Lake

Mara Meadows Road

Old House Road

Rock

Sprin

gs R

oad

Project AreaConceptual design shown as colored lines on map

Vintage 95 RoadSouthbound US-95Northbound US-95Mineral Ridge RoadCounty Road Connection

Legend

Granite Loop Road


Recommended