MULTI-GENERATION SYSTEM FOR BUILDING APPLICATION 1
A Carbon Neutral SOFC (Solid Oxide Fuel Cell)-Based
Multi-generation System for Building Application
A Briefing Summary
The Hong Kong Polytechnic University
Submitted by:
HONG Jingke Chris
CHEN Mengpei Julia
CHEN Tingting Cindy
LEE Pan
JIANG Chen David
MULTI-GENERATION SYSTEM FOR BUILDING APPLICATION 2
Abstract
Global energy crisis urges the development of alternative energy and enhancement of energy
utilization efficiency. This study proposes a Carbon Neutral SOFC Multi-generation System to utilize
the wastes for the provision of electricity, cooling and hot water. This system consists of four major
components: 1) biogas digestion plant where the organic waste (e.g. food waste and sewage) is
utilized; 2) SOFC energy server for uninterrupted electricity generation; 3) absorption cooling system
recovering the exhaust heat from high temperature SOFC; 4) hot water production from the residual
thermal energy by a bottoming cycle. A real case simulation of Hong Kong International Airport is
used to demonstrate the applicability of this proposed system. This system will be analysed through
three different perspectives, namely economic, environmental and social aspects. Firstly, cost and
saving analysis was conducted to investigate the financial feasibility of the proposed system.
Sensitivity analysis was then carried out to identify the significant factors affecting the payback period
of the system. Secondly, life cycle energy performance assessment and greenhouse gas emission
assessment were also performed to compare the environmental performance between the multi-
generation system and the traditional power plant in terms of energy consumption, CO2, CH4 and N2O
emission. Thirdly, social factors were considered to solicit the views from difference stakeholders on
the use of the proposed system. Finally, the recommendations in policy-making level were made to
enhance the further use of this Carbon Neutral SOFC Multi-generation System.
Keywords: Multi-generation system, SOFC, Absorption Chiller, Biogas, Sustainable
MULTI-GENERATION SYSTEM FOR BUILDING APPLICATION 3
1. INTRODUCTION
Energy crisis has become an undeniable global issue. Not only developing countries as far apart as
South Africa are plagued by electricity disruptions, developed countries are also facing periodic
blackouts and concerning security of energy supply (ElBaradei, 2010). In China, the Electricity
Council expected a power deficit of 40 million kilowatts in 2012 (Caixin Online, 2012), and the coal
shortage has become the most significant factor restricting the power supply (International Society of
Automation, 2008). Besides, the large consumption of fossil fuels causes serious pollution and climate
changes around the world (Jiang et al, 2011).
To address the energy crisis, there are two options: 1) searching for alternative energy sources, 2)
increasing system efficiency during energy generation thus reducing the energy loss. Biogas
production from municipal sewage sludge and food waste is considered as a means to supplement the
supply of energy and reduce the demand of waste treatment in many developed countries (Curry and
Pillay, 2012). Furthermore, developing technologies that increase energy efficiency and recovery of
waste heat have been gaining attention. Multi-generation, most commonly in form of cogeneration to
provide power and heating at the same time, is one of such technologies. This system can raise the
system efficiency to over 80% while the conventional electricity generation systems have the average
efficiency of 30-35%. Apart from the fossil-fuel combustion generation, there have been promising
conversion technologies replacing the direct chemical reactions to reduce energy loss, such as fuel
cells, which produce electricity with high efficiency through electrochemical reactions. Another way
to increases system efficiency is by heat-recovery such as absorption cooling, which is commonly
adopted to recover high quality exhaust heat for space cooling.
Up to present, there is no previous study on the SOFC-based multi-generation for condition in
Mainland China or Hong Kong, let alone a carbon-neutral SOFC multi-generation system using biogas
as fuel. Therefore, an investigation for large-scale application of such system is worth conducting.
2. SELECTION OF PREMISES - HONG KONG INTERNATIONAL AIRPORT
In order to investigate the suitability of the Carbon Neutral Multi-generation System, a set of criteria
is established, with considerations on the daily and monthly energy demand patterns, reusable waste
generation, composition of energy resources as well as the space available for the installation. These
criteria are detailed as follows:
MULTI-GENERATION SYSTEM FOR BUILDING APPLICATION 4
Electricity demand should be relatively consistent in daily basis, as the SOFC energy server
will be operating uninterruptedly.
Preferably there should be consistent demand in space cooling and hot water around the clock,
as the power generation and the provision of cooling and hot water are simultaneously.
For the biogas digestion, large amount of organic wastes from mainly three sources (i.e. used
cooking oil, food waste and sewage) are required to provide sufficient amount of gas fuel for
the energy server.
As the installation of the system will take up considerable space within the buildings/
development, especially for the digestion plant, it is suggested that non-commercial buildings
with lower building density are of higher applicability.
Taking the above four aspects into consideration, transport buildings with comprehensive customer
services operating around the clock will be of highest applicability for the proposed multi-generation
system. In this study, Hong Kong International Airport (HKIA) is chosen with its waste profile targeted
for design of the carbon-neutral multi-generation system and the following feasibility study.
The target wastes to be utilized for the multi-generation system are used cooling oil, food waste
and the sewage from the toilet facilities. The estimation of target wastes is listed in Table 1.
To sum up, the organic waste from used cooking oil, food waste and the sewage amounts to
34,667kg/day from HKIA.
3. SYSTEM CONFIGURATION - CARBON NEUTRAL MULTI-GENERATION SYSTEM
The Carbon Neutral Multi-Generation System consists of four major components, namely Biogas
Production Plant, SOFC Power Generator, Absorption Chiller and Hot Water System.
3.1 Biogas Production Plant
The methane-rich biogas is produced from the biomass resources through the process of anaerobic
digestion. Anaerobic digestion is a process in which micro-organism breaks down biodegradable
material in the absence of oxygen (Curry and Pillay, 2011). Through this complicated biochemical
Table 1: The estimation of target wastes
Target wastes Original volume Density Quantity Data source
Cooling oil 120 liter 0.92 kg/liter 110.4 kg/day Airport Authority
Food waste 200 kg/day ———— 200 kg/day Airport Authority
Sewage 156164 passengers/day *1.1 kg /per
persom=171781 kg/day
0.2 (utilization rate) 34,356kg/day Xiao & Huang, 2010
Airport Authority
MULTI-GENERATION SYSTEM FOR BUILDING APPLICATION 5
process, different strains of bacteria digest complex chains of carbohydrates, fats and proteins into
roughly 60% of methane (CH4) and 40% of carbon dioxide (CO2). Theoretically, the estimated
amount of biogas can be calculated using Buswell’s Equation (George et al, 1993):
a 2 4 2 3
4 2 3 4 2 3 4 2 3
4 8 8b c d
a b c d a b c d a b c dC H O N H O CH CO dNH
However, the above calculation is assumed that 100% of the food waste is utilized. In practice,
when no additional heat input to the system, around only 40-65% of the food waste is broken down
and converted to the biogas.
As discussed in the previous section, around 34,667 kg/day of the usable organic waste,
including sewage, cooking oil and food waste, is collected per day in HKIA. Based on the value of
biogas yield for mesophilic digestion (367 m3/tonne), the daily biogas produced from the organic
waste is 12,723 m3, with regards to the incomplete breakdown of organic waste.
3.2 SOFC Power Generation
A SOFC consists of two porous electrodes, namely the anode and the cathode, which are separated by
electrolyte to conduct oxide-ion (Singhal, 2008). During the operation, oxygen is supplied at the
cathode to react with electrons from circuit. The resulting oxide ions will pass through the electrolyte
to the anode. At the anode side, gas fuels such as hydrogen, natural gas and biogas are supplied and
internally reformed under the high operating temperature.
Bloom Energy’s ES-5700 Energy Server will be adopted for this study as it is the largest SOFC
energy server commercially available at present. Given the technical specification of ES-5700,
1.32MMBtu/h (equals to 1393.7484MJ/h) fuel input generates a base output of 200kWh; on average
an efficiency of 51.66% can be expected. According to the organic waste collection data in HKIA, the
biogas digestion plant should be able to produce 12,722.63m3 biogas on daily basis, which is capable
of providing power at 1,597kW given the electrical efficiency of ES-5700. To cope with potential
fluctuation in gas supply, the multi-generation is designed with 7 units of ES-5700 server, providing
electricity at 1,400kW uninterruptedly.
3.3 Configuration of Absorption Cooling System
The multi-generation system in this study adopts a double-effect absorption chiller to recovery the
high quality exhaust heat from the SOFC power generator.
MULTI-GENERATION SYSTEM FOR BUILDING APPLICATION 6
As mentioned, seven ES-5700 energy servers will be employed in the multi-generation system.
Considering each of the servers has the fuel requirement of 1.32MMBtu/hour and a base load output
of 200kW, and it is assumed that the energy server box is thermally enclosed, the residual energy will
be exhausted in form of steam and carbon dioxide mixture. The high temperature exhaust steam will
then be directed to a flow controller to achieve a desired temperature of 500°C. The efficiency of the
flow controller is taken as 100%. The exhaust gas at 500°C serves as the energy input for the
absorption chiller. By the calculation (the details, please refer to the full report), the hourly exhaust
flow rate = 4,716,238.8 kJ/hour ÷ [1.70kJ/(kg∙K) * (500-20)K] = 5,780 kg/hour, and the Broad X
Non-electric Packaged Hot W/Exhaust Chiller BE Mode 75 is used for the cogeneration system,
providing cooling at 872kW .
3.4 Hot Water System
One characteristic of SOFC is the high operating temperature. Although the temperature of the
exhaust gas passing through the absorption chiller is reduced for space cooling, it is still high enough
to provide hot water for water heating system in HKIA. This process can be simply realized by a heat
exchanger in which the heat from the exhaust gas is transferred to the water for hot water provision.
4. RESULTS AND DISCUSSIONS
4.1 Economic Analysis
4.1.1 Cost and Savings Analysis
Cost and savings analysis was conducted to calculate the total costs and savings of the system (See
Table 2). The results show that it is possible for the system to offset the initial investment through
energy saving in around 3 years if the government subsidy is provided at 50% of system cost.
4.1.2 Sensitivity Analysis
A set of cost and savings are summarized above as the baseline profile for the sensitivity analysis. In
regard to the uncertainties behind the assumptions made in compiling this profile, 10% variance on
the cost of the biogas production plant, SOFC energy server, absorption chiller, auxiliary components,
the level of government subsidy, unit price of fuel and electricity as well as the maintenance cost will
be considered for the sensitivity study. The results are presented in the Table 3 and Figure 1 (For
details, please refer to the full report, Appendix 3).
MULTI-GENERATION SYSTEM FOR BUILDING APPLICATION 7
Table 2 Summary of costs and savings for multi-generation system
System Costs Data Sources for Cost and Saving Calculations
Amount (HK$)
Biogas Production Plant 4,923,000 The unit cost of unheated biogas plant ranged from 50 to 70 US dollar per m3 capacity
(Advisory Service on Appropriate Technology)
SOFC Energy Server 54,180,000 Apple’s 4.8 megawatts fuel cell farm in North Carolina (24 ES-5700 units) was set at
the cost of US$ 6.7 million (Ginter, 2012)
The small units (1kW) for residential use is expected at the cost less than US$ 3,000
(Dr. K. R. Sridhar, the CEO of Bloom Energy)
Absorption Chiller 1,940,000 The chosen Two-stage Non-Electric Chiller costs 1.42 million RMB in 2011 price
(Broad Air Conditioning, 2011)
5% inflation rate and currency exchange rate of 1.24 are considered in the cost
calculation
Hot Water Production System 610,434 1% of the cost of the biogas production plant, SOFC energy server and the chiller
Auxiliary Components 6,104,341 10% of the cost of the biogas production plant, SOFC energy server and the chiller
Total Initial Cost 62,224,341
Initial Cost at Government Subsidy of 50% 31,112,170 The purchase cost of the system and the related project can be reduced by 80% through
government (Seattle City Light, 2010)
Operational Costs
Amount (HK$/month)
Biogas Production Plant 3,154 0.2-0.3 RMB/m3 (Biomass Utilization Project)
Electrical Cost for Absorption Chiller 3,766 The tariff rates offered by the China Light and Power Company
Maintenance Cost 311,122 An annual maintenance cost at 6% of the total system cost is set (0.5%/month)
Total Operational Cost 318,042
Operational Savings
Amount (HK$/month)
Electricity Savings by SOFC Power Generation 831,563 Based on the selected model ES-5700, the whole SOFC system generates
1,008,000kWh per month, and the bulk tariff is on the basis that the On-Peak period is
312 hours per month whilst the Off-Peak Period is 408 hours (For details, please refer
to the full report, Table 6.1)
Electricity Savings on Cooling by Absorption Cooling 111,025 Electricity savings are calculated if the water-cooled chillers with the COP of 4.6 is
replaced by the absorption chillers under the same amount of cooling load (For details,
please refer to the full report, Table 6.2)
Fuel Savings by Hot Water Production 173,708 Fuel savings are calculated if the Commercial Heater (Blue Flame NJW321FEL)
manufactured by Towngas is replaced by hot water system under the same amount of
hot water being produced per day. (For details, please to refer the full report, Table 6.3)
Total Operational Savings 1,116,296
Payback Period in Months 39.358
Payback Period in Years 3.28
MULTI-GENERATION SYSTEM FOR BUILDING APPLICATION 8
Table 3 Summary of single factor sensitivity analyses for cogeneration system
+10% Factor Change -10% Factor Change
Payback Period (years) Changes Payback Period (years) Changes
Level of Government Subsidy 2.83 -20.00% 4.24 20.00%
Rate of Electricity 3.16 -10.52% 4.01 13.33%
Cost of Auxiliary Components 3.89 9.91% 3.36 -4.95%
Cost of SOFC Energy Server 3.85 8.88% 3.22 -8.88%
Cost of Maintenance 3.68 4.06% 3.40 -3.75%
Cost of fuel 3.46 -2.13% 3.62 2.23%
Cost of Biogas Production Plant 3.57 0.81% 3.51 -0.81%
Cost of Absorption Chiller 3.55 0.32% 3.53 -0.32%
Operational Cost for Biogas Plant 3.54 0.04% 3.54 -0.04%
-20.00%
-15.00%
-10.00%
-5.00%
0.00%
5.00%
10.00%
15.00%
20.00%
Level of
Government
Subsidy
Rate of
Electricity
Cost of
Auxiliary
Components
Cost of SOFC
Energy Server
Cost of
Maintenance
Cost of fuel Cost of Biogas
Production Plant
Cost of
Absorption
Chiller
Operational
Cost for Biogas
Plant
+10% Factor Change -10% Factor Change
Figure 1 Results of sensitivity analysis
The combined effects of these factors are remarkable. While single factor can extend or shorten the
payback period by 20% at most, the time required for the operational savings to compensate the initial
cost can be more than doubled if adverse changes occur altogether, prolonging the payback period to
over 5 years. Similarly, in a most favourable circumstance, it is possible for the payback period to be
almost halved, leaving less than 3 years for the initial investment to be financially justified.
4.2 Environmental Analysis
The environmental analysis focuses on the comparison of energy performance and greenhouse gas
emissions between the multi-generation system and the traditional power plant, aiming to evaluate the
energy consumption and air emissions during the whole life cycle. Life-cycle assessment (LCA) is a
method for evaluating the environmental load and energy consumption of processes or products, goods,
and services during their life cycle from cradle to grave (ISO 2006). This study adopts hybrid LCA
analysis method to evaluate the life cycle energy and air emission performance of two alternatives
namely multi-generation system and tradition power plant.
4.2.1 Embodied Energy Analysis
In general, embodied phase of a certain product includes the extraction of raw materials,
transportation, manufacturing process of component, and production. All the infinite interrelationships
MULTI-GENERATION SYSTEM FOR BUILDING APPLICATION 9
evolved in this process have been reflected in Input-Output Table. By using the cost of each
component of the system (See Table 2) and energy intensity of the industry to which the
corresponding component of multi-generation system belongs, the embodied energy of multi-
generation energy supply system is 7,332.5 tce (tonnes coal equivalent). Figure 2 shows that SOFC
system accounts for around 80% of all energy use, and followed by transformer, flower controller and
biogas digester with the proportion of 9.16% and 5.52% respectively. The embodied energy of the
equivalent cost of the construction of electric power plant by generating 122.64 million kWh is 191.69
tce, which is only 2.6% of embodied energy consumption of the multi-generation system (Figure 3).
4.2.2 Operational Energy Analysis
During the operation, the energy supply system generates electricity by using biogas from biogas
digester. Biogas digestion recovers the energy from the used cooking oil, food waste and sewage
sludge; no additional energy source is required to fuel the SOFC energy server. Therefore, the
operational energy consumption of multi-generation system is -5515.38 tce, which is equal to the sum
of the energy savings from air-conditioning and hot water heating. For the conventional power plant,
according to the energy intensity of traditional electricity generation, the energy required for
generating 122.64 million kWh electricity is 4,586.74 tce.
4.2.3 Life Cycle Energy Performance of Two Alternatives
When considering the whole life cycle, the energy performances of the proposed system and the
conventional system are summarized in Table 4. One unit of kilowatt-hour electricity generated by the
multi-generation system consumes 0.151 kgce while the traditional power plant consumes 0.398 kgce.
The halved energy requirement indicates that this innovative energy supply system is much more
energy-efficient and sustainable in long term use.
SOFC
81.40%
Transformer+Flo
w controller
9.16%
Absorption Chiller
2.98%
Heating exchanger
0.94%
Biogas digester
5.52%
0.00%
1.00%
2.00%
3.00%
4.00%
5.00%
6.00%
Figure 2 Embodied energy contributions from 7 components Figure3 Ratio of embodied energy between traditional
power plant and multi-generation system
MULTI-GENERATION SYSTEM FOR BUILDING APPLICATION 10
4.2.4 Greenhouse Effect Analysis
In this study, three types of gas emissions (CO2, CH4, N2O), which are the primary causes of the
greenhouse effect are studied. According to the conversion coefficients from the Intergovernmental
Panel on Climate Change (IPCC) report, the volume of life cycle the emissions is listed in Table 5.
From the perspective of the whole life cycle, traditional electricity generation method will
produce more CO2 and N2O. In contract, multi-generation system emits more CH4 due to the large
volume in the embodied phase. However, it should be noticed that as the SOFC technology is new to
the market, the unit price of the energy server may not realistically reflect the embodied energy.
4.3 Social Factors Analysis
In order to establish the comprehensiveness of this study, other influential factors for the prospect of
this Carbon Neutral Multi-Generation System are investigated through extensive literature reviews
concerning the technology of biogas digestion, SOFC and absorption chiller to solicit the views from
different stakeholders towards the proposed system. Economic, environmental, technological and
social aspects are considered for circumstances in China. Meanwhile, interviews (For details, please
refer to the full report Appendix 3) with the government official, scholars in relevant fields,
engineering consultant and the end-user were conducted to discuss the feasibility, benefits, and
attitudes towards the prospect of carbon neutral multi-generation system in China, energy
management performance as well as distributed power generation in a broader sense. Key points
raised during the discussion are summarised in the Table 6.
For the prospect of the carbon neutral multi-generation system, the environmental and public
safety impacts are at the heart of the Government’s concern. From the users’ perspective, noticeable
financial benefit is always the primary concern in large-scale commercialization. The amount of initial
Table 4 Life cycle energy performance of two electricity supply system
Embodied phase
(tce)
Operational phase
(tce)
Whole life cycle
(tce)
Quo-generation system 7332.5 -5515.38 1817.12
Power plant 191.69 4586.74 4778.43
Table 5 Life cycle greenhouse gas emissions
Embodied phase Operation phase Life cycle Intensity (g/KWh)
CO2 CH4 N2O CO2 CH4 N2O CO2 CH4 N2O CO2 CH4 N2O
Multi-generation system 28309.8 410.0 393.3 -16546.1 -165.5 -248.2 11763.7 244.5 145.1 98.0 2.0 1.2
Power Plant 665.1 10.0 9.1 13760.2 137.6 206.4 14425.3 147.6 215.5 120.2 1.2 1.8
MULTI-GENERATION SYSTEM FOR BUILDING APPLICATION 11
Table 6 Summary of indicators of utilization of carbon neutral multi-generation system from different stakeholders
Economic Environmental Social Technology
Government Energy loans
Cost
competitiveness
in the market
Project cost
Stimulus of the
renewable
industry
Environmental impact
assessment
The environmental
protection facilities
Pollution Prevention
The reduction of
greenhouse gas emissions
and global warming
Energy supply
Energy demand
The reduction of waste
Energy security
The emerging social
expectation towards
green technology
Public interest
The awareness of
environmental
protection
Education
The increase of the
renewable energy
generation
The reduction of
carbon emission
The use of biogas
technology
End-users
(Clients) Government
support
(subsidies)
Operating and
maintenance
costs
The economic
costs and
benefits
Energy consumption
Compliance of local
regulations
Enhancement of
corporation image
Corporate reputation
Social responsibility
Enterprise culture
Engineering
equipment and
material
Constant power
production
Choice of fuel
Technological
breakthrough
System reliability
Citizen The
justifications
of public
expenditures
for
government
subsidies
The reduction
of electricity
costs
The reduction of
greenhouse gas
emissions and global
warming
The reduction of carbon
emissions
The alleviation of
landfill burden
Improvement of air and
water quality
Enhancement of living
standard and public
health
Levels of trust in
public and private
sector organizations,
The support for future
local energy
development
Social consequences
of renewable energy
The impact of modern
and clean city image
Long-term
performance
capital investment and the length of payback period may carry different weight for users from various
backgrounds. On the other hand, the ordinary citizens are more likely to consider the impacts of the
system on the enhancement of the living standard and the public health and safety.
5. Conclusion
Global energy crisis urges the development of alternative energy and enhancement of energy
utilization efficiency. In this study, an uninterrupted SOFC based multi-generation system, integrated
with biogas digestion, is proposed for building application. Apart from cleaner power generation and
minimal wastage, the system is able to achieve carbon-neutral as fuelled by biogas, and serves as an
alternative for urban waste treatment.
MULTI-GENERATION SYSTEM FOR BUILDING APPLICATION 12
Economic analysis based on a case study of Hong Kong International Airport shows that the
system is of noticeable financial feasibility; it is possible for the system to offset the initial investment
through energy savings in around 3 years. Sensitivity analyses incorporating 9 influential factors
indicate that a payback period of around 2 years in the most optimistic cases and 5 years in the
pessimistic scenario.
From the environmental perspective, the multi-generation system has demonstrated advantages
in life cycle energy performance and greenhouse gas emissions. For per unit of kilowatt-hour power,
the energy use in generating the equivalent electricity by proposed system are less than half of the
energy use in conventional power generation.
According to the interviews conducted with different stakeholders towards the proposed system,
popularity of this multi-generation system to a large extent relies on the government support at starting
stage. In the long-term, the payback period is still vital for the prospect system application. Citizens put
more emphasis on the health and safety issues, as well as the enhancement of the living standard brought
by the system. To sum up, the proposed system brings the advantages ofis promising for the reduction of
greenhouse gas emission; it eases the energy crisis by renewable energy application and a efficient
energy utilization; it is also a possible solution for urban waste treatment.
References
Airport Authority Hong Kong. (2013). HKIA Master
Plan 2030 Technical Report. HKSAR.
Broad Air Conditioning. (2011, 3). Model Selection &
Design Manual. Changsha, China.
Caixin Online. (2012). Power Shortage to Continue in
2012. Beijing, China.
Curry, N., & Pillay, P. (2011). Biogas prediction and design
of a food waste to energy system for the urban
environment. Renewable Energy , 41, pp. 200-209.
ElBaradei, M. (2010). Tackling the Global Energy Crisis.
International Atomic Energy Agency Bulletin, 50 (1).
Ginter, S. (2012, 4 24). Apple Joins Clean Energy
Production Movement. Retrieved 2 22, 2013, from
Energy & Capital:
International Organization for Standardization (ISO).
(2006). Environmental management –life cycle
assessment-principles and framework (ISO14040:
2006), Geneve. International Society of Automation. (2008). Coal
shortage has China living on the edge. Retrieved
November 4, 2012, from ISA:
http://www.isa.org/InTechTemplate.cfm?Section=In
Tech&template=/ContentMa
nagement/ContentDisplay.cfm&ContentID=68134
Seattle City Light. (2010). Integrated Resources Plan.
USA.
Xiao, D., & Huang, D. (2010). Strategy for Water
Resrouces Demand and Supply Management in
Taiwan. Taiwan.