+ All Categories
Home > Documents > A Case Study - Refining Community...Case Study Background Background / Customer PROBLEMS 2- drum,...

A Case Study - Refining Community...Case Study Background Background / Customer PROBLEMS 2- drum,...

Date post: 03-Jul-2020
Category:
Upload: others
View: 2 times
Download: 0 times
Share this document with a friend
42
Floating Slide Plates for Coke Chutes A Case Study
Transcript
Page 1: A Case Study - Refining Community...Case Study Background Background / Customer PROBLEMS 2- drum, delayed coking unit constructed in 1990. Evident concrete deterioration throughout

Floating Slide Plates for Coke ChutesA Case Study

Page 2: A Case Study - Refining Community...Case Study Background Background / Customer PROBLEMS 2- drum, delayed coking unit constructed in 1990. Evident concrete deterioration throughout

▪ Who is Structural Group?

▪ Case Study: 2017 Slide Plate Install

▪ Scope Development

▪ Engineered Solution

▪ Preplanning

▪ Implementation

▪ Closing remarks

▪ Open floor discussion/ Q&A period

Page 3: A Case Study - Refining Community...Case Study Background Background / Customer PROBLEMS 2- drum, delayed coking unit constructed in 1990. Evident concrete deterioration throughout

Materials & Engineering Support Services Specialty Contracting Services

WHO IS STRUCTURAL GROUP?

Page 4: A Case Study - Refining Community...Case Study Background Background / Customer PROBLEMS 2- drum, delayed coking unit constructed in 1990. Evident concrete deterioration throughout

▪ International Offices (3):

Abu Dhabi

Dubai

Qatar

▪ Corporate HQ:

Columbia, MD

▪ North America Offices (20):

Baltimore

Baton Rouge

Chicago

Dallas

Denver

Detroit

Ft. Lauderdale/Miami

Hartford

Houston

Kansas City

Lake Charles

Long Island

Los Angeles

New York

Philadelphia

Pittsburgh

San Francisco

Sarasota/West Florida

Springfield

Offices

Page 5: A Case Study - Refining Community...Case Study Background Background / Customer PROBLEMS 2- drum, delayed coking unit constructed in 1990. Evident concrete deterioration throughout

Case Study Background

▪ Background / Customer PROBLEMS

▪ 2- drum, delayed coking unit constructed in

1990.

▪ Evident concrete deterioration throughout

support structure and coke pit.

▪ Coke chutes lined with steel wear plates that

were a maintenance burden and required

replacement.

▪ Replacement planned for 2012 Turnaround

deferred due to cost and interference with

coke drum replacement.

▪ Engineered Solution OBJECTIVES

▪ Undertake structural concrete repairs.

▪ Remove and replace the steel wear plates.

ImplementationScope Development Engineered Solution Preplanning

Page 6: A Case Study - Refining Community...Case Study Background Background / Customer PROBLEMS 2- drum, delayed coking unit constructed in 1990. Evident concrete deterioration throughout

Condition Survey (2016)

▪ Primary Objectives:

▪ Identify, Quantify and Prioritize

Repairs.

▪ Using NDT, and Visual

Observation.

▪ Assessment Area Included:

▪ Coke Chutes (Hot Face)

▪ Coke Chutes (Underside)

▪ Coke Pit Walls

▪ Fines Settling Basin

ImplementationScope Development Engineered Solution Preplanning

Page 7: A Case Study - Refining Community...Case Study Background Background / Customer PROBLEMS 2- drum, delayed coking unit constructed in 1990. Evident concrete deterioration throughout

Condition Assessment: Deterioration Mapping

ImplementationScope Development Engineered Solution Preplanning

Page 8: A Case Study - Refining Community...Case Study Background Background / Customer PROBLEMS 2- drum, delayed coking unit constructed in 1990. Evident concrete deterioration throughout

Condition Assessment: Core Samples

▪ Four 3” diameter cores were

collected.

▪ Cores were extracted from the

South and East Pit Walls.

▪ Depths ranged from 2.5” to 8”

ImplementationScope Development Engineered Solution Preplanning

Page 9: A Case Study - Refining Community...Case Study Background Background / Customer PROBLEMS 2- drum, delayed coking unit constructed in 1990. Evident concrete deterioration throughout

Condition Assessment: Field Photographs

ImplementationScope Development Engineered Solution Preplanning

Page 10: A Case Study - Refining Community...Case Study Background Background / Customer PROBLEMS 2- drum, delayed coking unit constructed in 1990. Evident concrete deterioration throughout

▪ Floor Repair

▪ Top of Wall Repair

▪ Expansion Joints

▪ Weir Wall Modifications

▪ Coke Pit Wall Extension

▪ Outside Corner Repair

▪ Remove and Replace Slide Plates

ImplementationScope Development Engineered Solution Preplanning

Condition Assessment: Conclusions

Page 11: A Case Study - Refining Community...Case Study Background Background / Customer PROBLEMS 2- drum, delayed coking unit constructed in 1990. Evident concrete deterioration throughout

What is a Wear Plate?

ImplementationEngineered Solution PreplanningScope Development

Page 12: A Case Study - Refining Community...Case Study Background Background / Customer PROBLEMS 2- drum, delayed coking unit constructed in 1990. Evident concrete deterioration throughout

Typical Wear Plate Construction

Carbon Steel

Plate Welded to

Embedments

Mechanical

Anchorage

to Substrate

ImplementationEngineered Solution PreplanningScope Development

Page 13: A Case Study - Refining Community...Case Study Background Background / Customer PROBLEMS 2- drum, delayed coking unit constructed in 1990. Evident concrete deterioration throughout

Issues with Conventional Wear Plates

▪ Sections of wear-plate being

dislodged over time.

▪ On-going quarterly inspections

and emergency repairs.

▪ Operational downtime and on-

going maintenance costs.

▪ Inability to inspect concrete

structure below.

▪ Multi-million dollar, intrusive

replacement program.

▪ Cracked welds due to impact

from falling material and

thermal cycles.

Chute

Column

ImplementationEngineered Solution PreplanningScope Development

Page 14: A Case Study - Refining Community...Case Study Background Background / Customer PROBLEMS 2- drum, delayed coking unit constructed in 1990. Evident concrete deterioration throughout

INNOVATION: New “Floating” Slide Plate

Sacrificial

Stainless Steel

Floating Plate

ImplementationEngineered Solution PreplanningScope Development

Page 15: A Case Study - Refining Community...Case Study Background Background / Customer PROBLEMS 2- drum, delayed coking unit constructed in 1990. Evident concrete deterioration throughout

DESIGN HIGHLIGHT: Plate Mounting Bracket

▪ All components were fabricated from 304L Stainless Steel.

▪ Specialty components required 2+ month lead-time.

ImplementationEngineered Solution PreplanningScope Development

Page 16: A Case Study - Refining Community...Case Study Background Background / Customer PROBLEMS 2- drum, delayed coking unit constructed in 1990. Evident concrete deterioration throughout

DESIGN HIGHLIGHT: Front Nosing Plate

▪ Nosing plates were 304L SS and ½ thickness of the new wear plates.

▪ Plates were delivered to site in sections with the studs pre-welded.

ImplementationEngineered Solution PreplanningScope Development

Page 17: A Case Study - Refining Community...Case Study Background Background / Customer PROBLEMS 2- drum, delayed coking unit constructed in 1990. Evident concrete deterioration throughout

DESIGN HIGHLIGHT: New Slide Plate

▪ Slide plates (20’ x 40’) were made from 304L SS.

▪ Each plate was 4 separate sections welded on-site.

ImplementationEngineered Solution PreplanningScope Development

Page 18: A Case Study - Refining Community...Case Study Background Background / Customer PROBLEMS 2- drum, delayed coking unit constructed in 1990. Evident concrete deterioration throughout

DESIGN HIGHLIGHT: Material Selection

▪ Continuous issues with CS wear plate corrosion/erosion on slide

plates and in coke handling system

ImplementationEngineered Solution PreplanningScope Development

Page 19: A Case Study - Refining Community...Case Study Background Background / Customer PROBLEMS 2- drum, delayed coking unit constructed in 1990. Evident concrete deterioration throughout

DESIGN HIGHLIGHT: Material Selection

▪ The plant installed a “test plate” in 2011

▪ ¼” 304 SS plate welded on top of CS in slide zone

ImplementationEngineered Solution PreplanningScope Development

Page 20: A Case Study - Refining Community...Case Study Background Background / Customer PROBLEMS 2- drum, delayed coking unit constructed in 1990. Evident concrete deterioration throughout

DESIGN HIGHLIGHT: Material Selection

▪ 2013: Installed CS plate with 0.109” thick 317L SS cladding after

major plate failure.

▪ Final Decision: Solid 304 SS material chosen for long term benefits.

ImplementationEngineered Solution PreplanningScope Development

Page 21: A Case Study - Refining Community...Case Study Background Background / Customer PROBLEMS 2- drum, delayed coking unit constructed in 1990. Evident concrete deterioration throughout

Slide Plate Construction: Off-Site Welding

10’ x 20’ 10’ x 20’

ImplementationPreplanningScope Development Engineered Solution

Page 22: A Case Study - Refining Community...Case Study Background Background / Customer PROBLEMS 2- drum, delayed coking unit constructed in 1990. Evident concrete deterioration throughout

Slide Plate Construction: Off-Site Welding

ImplementationPreplanningScope Development Engineered Solution

Page 23: A Case Study - Refining Community...Case Study Background Background / Customer PROBLEMS 2- drum, delayed coking unit constructed in 1990. Evident concrete deterioration throughout

Slide Plate Construction: Off-Site Welding

ImplementationPreplanningScope Development Engineered Solution

Page 24: A Case Study - Refining Community...Case Study Background Background / Customer PROBLEMS 2- drum, delayed coking unit constructed in 1990. Evident concrete deterioration throughout

Slide Plate Construction: Shipping Plates To Site

ImplementationPreplanningScope Development Engineered Solution

Page 25: A Case Study - Refining Community...Case Study Background Background / Customer PROBLEMS 2- drum, delayed coking unit constructed in 1990. Evident concrete deterioration throughout

Slide Plate Construction: On-Site Welding

Preplanning ImplementationScope Development Engineered Solution

Page 26: A Case Study - Refining Community...Case Study Background Background / Customer PROBLEMS 2- drum, delayed coking unit constructed in 1990. Evident concrete deterioration throughout

Slide Plate Construction: On-Site Welding

Preplanning ImplementationScope Development Engineered Solution

Page 27: A Case Study - Refining Community...Case Study Background Background / Customer PROBLEMS 2- drum, delayed coking unit constructed in 1990. Evident concrete deterioration throughout

Slide Plate Construction: On-Site Welding

Preplanning ImplementationScope Development Engineered Solution

10’ x 40’

10’ x 40’

Page 28: A Case Study - Refining Community...Case Study Background Background / Customer PROBLEMS 2- drum, delayed coking unit constructed in 1990. Evident concrete deterioration throughout

▪ We developed a comprehensive Weld Distortion Control Guide to

compliment the WPS to control warping, twisting, and or curling.

Slide Plate Construction: Distortion Control

Preplanning ImplementationScope Development Engineered Solution

Page 29: A Case Study - Refining Community...Case Study Background Background / Customer PROBLEMS 2- drum, delayed coking unit constructed in 1990. Evident concrete deterioration throughout

Step #1: Layout Slide Plate Mounting Brackets

Preplanning ImplementationScope Development Engineered Solution

Page 30: A Case Study - Refining Community...Case Study Background Background / Customer PROBLEMS 2- drum, delayed coking unit constructed in 1990. Evident concrete deterioration throughout

Drill Bracket Holes On-Site to AVOID Rebar

Preplanning ImplementationScope Development Engineered Solution

Page 31: A Case Study - Refining Community...Case Study Background Background / Customer PROBLEMS 2- drum, delayed coking unit constructed in 1990. Evident concrete deterioration throughout

Step #2: Existing Slide Plate Demolition

Preplanning ImplementationScope Development Engineered Solution

Page 32: A Case Study - Refining Community...Case Study Background Background / Customer PROBLEMS 2- drum, delayed coking unit constructed in 1990. Evident concrete deterioration throughout

Oxygen (Oxy) Lance Cutting

Preplanning ImplementationScope Development Engineered Solution

Page 33: A Case Study - Refining Community...Case Study Background Background / Customer PROBLEMS 2- drum, delayed coking unit constructed in 1990. Evident concrete deterioration throughout

Oxy Lance Cutting Continued…

Preplanning ImplementationScope Development Engineered Solution

Page 34: A Case Study - Refining Community...Case Study Background Background / Customer PROBLEMS 2- drum, delayed coking unit constructed in 1990. Evident concrete deterioration throughout

Step #3: Install Stainless Steel Brackets

Preplanning ImplementationScope Development Engineered Solution

Page 35: A Case Study - Refining Community...Case Study Background Background / Customer PROBLEMS 2- drum, delayed coking unit constructed in 1990. Evident concrete deterioration throughout

Drill, Epoxy, and Set Brackets

Preplanning ImplementationScope Development Engineered Solution

Page 36: A Case Study - Refining Community...Case Study Background Background / Customer PROBLEMS 2- drum, delayed coking unit constructed in 1990. Evident concrete deterioration throughout

Step #4: Install Chute Nosing Plates

Preplanning ImplementationScope Development Engineered Solution

Page 37: A Case Study - Refining Community...Case Study Background Background / Customer PROBLEMS 2- drum, delayed coking unit constructed in 1990. Evident concrete deterioration throughout

Nose Plate Installation- Concrete Removal

Preplanning ImplementationScope Development Engineered Solution

Page 38: A Case Study - Refining Community...Case Study Background Background / Customer PROBLEMS 2- drum, delayed coking unit constructed in 1990. Evident concrete deterioration throughout

Nose Plate Installation- Concrete Placement

Preplanning ImplementationScope Development Engineered Solution

Page 39: A Case Study - Refining Community...Case Study Background Background / Customer PROBLEMS 2- drum, delayed coking unit constructed in 1990. Evident concrete deterioration throughout

Step #5: Installation of New Slide Plates

PLATE

FAB

AREA

LIFT

LOCATION

Preplanning ImplementationScope Development Engineered Solution

Page 40: A Case Study - Refining Community...Case Study Background Background / Customer PROBLEMS 2- drum, delayed coking unit constructed in 1990. Evident concrete deterioration throughout

Actual Plate Installation (May 2017)

Preplanning ImplementationScope Development Engineered Solution

Page 41: A Case Study - Refining Community...Case Study Background Background / Customer PROBLEMS 2- drum, delayed coking unit constructed in 1990. Evident concrete deterioration throughout

▪ Structural was able to value engineer

a solution from the original design that

saved Phillips 66 millions.

▪ Total on-site duration (28 days).

▪ Project completed on-time and on-

budget.

▪ ZERO safety incidents or first-aids.

▪ NDT inspection in Q4 2017 (6 months

after install) revealed NO issues with

system performance.

Page 42: A Case Study - Refining Community...Case Study Background Background / Customer PROBLEMS 2- drum, delayed coking unit constructed in 1990. Evident concrete deterioration throughout

Questions?

Thank You!

Matthew Hickey, P.Eng., PMP

Project Manager

[email protected]

Stephanie Keeth

Area Mechanical Engineer

[email protected]

COME VISIT US AT BOOTH No.72 FOR MORE INFORMATION!


Recommended