The “Greening of Aiken” project is a model, “deep energy retrofit” on the University of Vermont campus. It demonstrates that renovation can out-perform new construction, while meeting a tight budget. This project sets an example for low energy-consuming design and construction, responsible use of natural resources, and healthy learning and work environments.
Popular Tags:
62
Transcript
Page 1: A Net-Zero World and The Greening of Aiken
Page 2: A Net-Zero World and The Greening of Aiken

Beauty in Living

Photo by John Fowler / CC-BY-2.0

Photo modified by Disenyo from photo by Paul Kempeneers / CC-BY-SA-2.5

Photo by Martin St-Amant / CC-BY-SA-3.0

Photo modified by Edfu6 from photo by Rémih / CC-BY-SA-3.0

Photo by Bill Maclay

Photo  by  Pascal  Reusch  /  CC-­‐BY-­‐SA-­‐3.0    

Photo  derived  from  photo  by  Hans  Ollermann  /  CC-­‐BY-­‐2.0    

Photo  by  Timothy  A.  Price  and  Nichole  I.  /  CC-­‐BY-­‐SA-­‐3.0    

Public  Domain  

Page 3: A Net-Zero World and The Greening of Aiken

Evolution of Energy and Settlement

Renewable / Farms and Villages Coal / Urbanization Oil / Suburbanization Farming/Renewable Coal Oil

Painting by Thomas James Judkin / Public Domain

Photograph by Michigan Department of Transportation / Public Domain

painting by Jan Brueghel the Elder / Public Domain-US

painting by Jean-François Millet / Public Domain-US

Photo by austrini / CC BY 2.0

Photo by Rand, McNally & Co / Public Domain-US

photo by Seattle Eng Co / Public Domain-US

Photo by Minesweeper / CC-BY-SA-3.0

Photo by David Shankbone / CC-BY-SA-3.0

Derivative by Maclay Architects from Otto Krebs 1874 / Public Domain-US

Page 4: A Net-Zero World and The Greening of Aiken

economy, energy, environment, equity & population

Global Challenges & Our Buildings & Community’s Impacts

photo  by  Olsen  Dave,  U.S.  Fish  and  Wildlife  Service  /  Public  Domain  

Photo by Ahron de Leeuw / CC-BY-2.0

Public Domain

Photo by Perpetual Tourist / CC-BY-2.0

Photo by John Hill / CC-BY-SA-3.0

Page 5: A Net-Zero World and The Greening of Aiken
Page 6: A Net-Zero World and The Greening of Aiken

Historical World Oil Price

Page 7: A Net-Zero World and The Greening of Aiken

Projected Oil Price Based on Historical Growth

Page 8: A Net-Zero World and The Greening of Aiken

Campus Site Plan / Analysis of Building

Page 9: A Net-Zero World and The Greening of Aiken

Design Competition Submission

Page 10: A Net-Zero World and The Greening of Aiken

Living Building

Reprinted from David Lloyd Jones, Architecture and the Environment (Woodstock, NY: The Overlook Press, 1998). 34

Page 11: A Net-Zero World and The Greening of Aiken
Page 12: A Net-Zero World and The Greening of Aiken
Page 13: A Net-Zero World and The Greening of Aiken
Page 14: A Net-Zero World and The Greening of Aiken

Integrated Design

Page 15: A Net-Zero World and The Greening of Aiken

Living Systems Building

Page 16: A Net-Zero World and The Greening of Aiken
Page 17: A Net-Zero World and The Greening of Aiken

Collaborative Design

Page 18: A Net-Zero World and The Greening of Aiken

Pre-Renovation External Conditions

Dangerous North Entrance

Thermal Breaks Brick Spalling

Uninviting South Façade & Entrance

Page 19: A Net-Zero World and The Greening of Aiken

Classrooms: • Low ceilings • Poor lighting and air quality • Inefficient cooling and heating

Hallways: •  Dark, uninviting, cramped, not allowing community interactions

Atrium: •  Cramped with angled glazing limiting view and connection to campus

Pre-Renovation Internal Conditions

Page 20: A Net-Zero World and The Greening of Aiken

Air Intake at Ground Level Creates Indoor Air Quality Problems

Biological Materials Inside of Fresh Air Intake

Mechanical Room Duct Insulation Deteriorated

Pre- Renovation Mechanical Conditions

Page 21: A Net-Zero World and The Greening of Aiken

Pre-Renovation Wall Conditions

Page 22: A Net-Zero World and The Greening of Aiken

The George D. Aiken Center - Detail at Floor Slab

WALL SECTION AT FLOOR SLAB - RENOVATED

WALL SECTION AT FLOOR SLAB - EXISTING

Page 23: A Net-Zero World and The Greening of Aiken

The George D. Aiken Center – Therm Diagrams

Existing Building Envelope New Building Envelope

Page 24: A Net-Zero World and The Greening of Aiken

Daylighting Strategy

Page 25: A Net-Zero World and The Greening of Aiken
Page 26: A Net-Zero World and The Greening of Aiken
Page 27: A Net-Zero World and The Greening of Aiken
Page 28: A Net-Zero World and The Greening of Aiken
Page 29: A Net-Zero World and The Greening of Aiken

Base of Wall

Page 30: A Net-Zero World and The Greening of Aiken

Solarium Planter

Page 31: A Net-Zero World and The Greening of Aiken

Eco Machine

Detail

Page 32: A Net-Zero World and The Greening of Aiken

Parapet

Page 33: A Net-Zero World and The Greening of Aiken

Window Head

Page 34: A Net-Zero World and The Greening of Aiken

Window Installation Drawings

Page 35: A Net-Zero World and The Greening of Aiken

EIA Benchmark from – Commercial Building energy Use Survey 2003

Page 36: A Net-Zero World and The Greening of Aiken

Wrap jamb with self-adhering air and moisture barrier sheet membrane, lapped over sill membrane.

Page 37: A Net-Zero World and The Greening of Aiken

Install backer rod and sealant from the interior side of window, to seal window frame to air barrier. Install spray urethane foam (low-expanding type) between window frame and vinyl angle from the outside (not shown.)

Page 38: A Net-Zero World and The Greening of Aiken

APPLY SPRAY AIR & MOISTURE BARRIER MEMBRANE Apply spray air and moisture barrier (Tremco Exo-Air 120) over sheet AMB around window perimeter, over base of masonry wall anchors and metal panel wall anchors.

Page 39: A Net-Zero World and The Greening of Aiken

APPLY RIGID FOAM (XPS) INSULATION Install rigid foam tight to face of AMB, cut out around wall anchors, in two layers (3” and 2”) with joints staggered. Sealant daubs hold insulation boards temporarily, masonry wall anchors retain the insulation permanently.

Page 40: A Net-Zero World and The Greening of Aiken

Seal around openings (window openings, wall anchor penetrations) and gaps with spray foam or sealant. Gaps ¼” or greater in rigid foam are sealed with spray urethane foam, less than ¼” sealed with flexible sealant.

Page 41: A Net-Zero World and The Greening of Aiken

Existing walls adjacent to Solarium receive same treatment, with less insulation.

Page 42: A Net-Zero World and The Greening of Aiken

INSTALL REMAINDER OF MASONRY (BRICK) AND METAL PANELS Install brick first, then metal panels between.

Page 43: A Net-Zero World and The Greening of Aiken

Seal joints between brick and windows, brick and metal panels, metal panels below windows (window head not sealed to allow drainage.)

Page 44: A Net-Zero World and The Greening of Aiken

THERMAL ISOLATION Dense polyurethane blocks provide thermal isolation of exterior structural elements.

Page 45: A Net-Zero World and The Greening of Aiken

The Construction Process

•  Mock-up includes as many actual building elements as possible •  Shortened construction schedule by team working through details and

installation sequences

Page 46: A Net-Zero World and The Greening of Aiken

The Construction Process

•  Treat the mock-up as the building •  All elements of the mock-up reviewed •  Aiken included smoke testing the mock-up

Page 47: A Net-Zero World and The Greening of Aiken

The Construction Process

Inspection, Inspection, Inspection •  Every aspect of the membrane: mock-up to caulking

inspected •  Apparent flaws identified by colored dots and initialed by

contractor when complete for re-inspection •  All inspections of each stage needed to pass prior to next

step starting

Page 48: A Net-Zero World and The Greening of Aiken

•  Window air and water leakage testing •  Compliance Testing

Enclosure Testing During Construction

Page 49: A Net-Zero World and The Greening of Aiken

Enclosure Testing During Construction

Window water leakage testing

Page 50: A Net-Zero World and The Greening of Aiken

Enclosure Testing Result 0.11 cfm50/sq.ft. excluding slab – 3,900 cfm50

0.079 cfm50/sq.ft. including slab

Page 51: A Net-Zero World and The Greening of Aiken

George D. Aiken Center: The Results

South Entry Renovated North Entry and Stair

Page 52: A Net-Zero World and The Greening of Aiken
Page 53: A Net-Zero World and The Greening of Aiken
Page 54: A Net-Zero World and The Greening of Aiken

EcoMachine

Page 55: A Net-Zero World and The Greening of Aiken
Page 56: A Net-Zero World and The Greening of Aiken
Page 57: A Net-Zero World and The Greening of Aiken

The updated central stair with locally sourced boulders

Page 58: A Net-Zero World and The Greening of Aiken
Page 59: A Net-Zero World and The Greening of Aiken
Page 60: A Net-Zero World and The Greening of Aiken

Green Conference Room

Page 61: A Net-Zero World and The Greening of Aiken

Open Offices

Page 62: A Net-Zero World and The Greening of Aiken

TEAM MEMBERS   OWNER TEAM University of Vermont Robert Vaughn, Director, Capital Planning and Management Paula Carlaccini, Director, Facilities Design and Construction Ken Bean, University Architect Todd Merchant, Senior Construction Administrator Mike Stevens, Construction Project Coordinator “Greening of Aiken Committee” Gary Hawley, Research Associate Carl Waite, Senior Research Analyst Alan McIntosh, Professor Deane Want, Associate Professor Don DeHayes, Professor & Former Dean Mary Watzin, Dean Eco-Machine Matthew Beam, Graduate Student John Todd, Professor Commissioning Consultant Allan Bullis , Efficiency Innovations, LLC, Envelope Inspection and Testing Building Durability Consultant Gale Associates Construction Cost Consultant Vermeulens Cost Consultants DEW Construction, Inc. Owner LEED Consultant Linda Samter

CONSTRUCTION TEAM PC Construction, General Contractor Laura Clements, Project Manager Jordan Hershman, Project Engineer John Lavoie, Site Superintendent Amie Hammer & Kaitlyn Evarts, Project Assistants St. Albans Glass, Window and Metal Panel Subcontractor Greg Swan North Stars Masonry, Inc., Masonry Subcontractor Larry Shelton Dayco, Inc., Membrane Roofing Subcontractor Dana Geno Nicom Coatings, Corp., Wall Coatings and Membranes Subcontractor John Larosa DESIGN TEAM Maclay Architects Bill Maclay, Principal Brian Leet & Tom Bodell, Project Managers Lisa Sawin, Job Captain Chris Cook, Project Assistant Energy Consultant Andy Shapiro, Energy Balance Cost Consultant DEW Construction, Inc. Kohler Lewis, Mechanical and Plumbing Engineers Joe Kohler Adam Kohler Dan Lewis Roy Swain Pearson and Associates, Electrical Engineer Alan Gould Engineering Ventures, Civil Consulting Engineer Sarah Thyng Engineering Ventures, Structural Engineer Greg Sellers Chase Engineering, Fire Protection Engineer Matt Chase