Date post: | 30-Dec-2015 |
Category: |
Documents |
Upload: | amberlynn-townsend |
View: | 213 times |
Download: | 0 times |
Project Risk
• Consequences of Risk:– Failure to obtain all, or any, of the anticipated
benefits because of implementation difficulties.
– Higher than expected implementation costs.– Longer than expected implementation time.– Resulting systems whose technical
performance is significantly below estimate.– System incompatibility with selected hardware
and software.
Project Dimensions Influencing Inherent Implementation Risk
Three important project dimensions influence inherent implementation risk:
• Project size
• Experience with the Technology
• Project structure
Project Categories and Degree of Risk
Low risk (very susceptible to mismanagement)
Low risk
Very low risk (very susceptible to mismanagement)
Very low risk
Very high risk Medium risk
High risk Medium-low risk
Low Structure High Structure
LargeProject
SmallProject
LargeProject
SmallProject
Low company-relative technology
High company-relative technology
Project Examples by Implementation Risk Categories
Spread support for budgeting
Manufacturing inventory control
On-line graphic support for advertising copy
Expert system bond trading
Low Structure High Structure
Low company-relative technology
High company-relative technology
Assessing Risk of Individual Projects
• Managers should ask themselves:– Are the benefits enough to offset the risk?– Can the affected parts of the organization
survive if the project fails?– Have the planners considered appropriate
alternatives?
Assessing Risk of Individual ProjectsSize Risk Assessment
Risk Factor Weight
1. Total development work-hours for system100 to 3,000
3,000 to 15,000
15,000 to 30,000
More than 30,000
2. Estimated project implementation time12 months or less
13 months to 24 months
More than 24 months
3. Number of departments involved with system
One
Two
Three or more
Low
Medium
Medium
High
Low
Medium
High
Low
Medium
High
1
2
3
4
1
2
3
1
2
3
5
4
4
Structure Risk Assessment Risk Factor Weight
1. If replacement system is proposed, what % of existing functions are replaced on a one-to-one basis?
0% to 25%
25% to 50%
50% to 100%
2. What is the severity of user-department procedural changes caused by the proposed system?
Low
Medium
High
3. What is the degree of needed user-organization structural change to meet requirements of the new system?
None
Minimal
Somewhat
Major
High
Medium
Low
Low
Medium
High
3
2
1
1
2
3
0
1
2
3
5
5
5
Structure Risk Assessment - Contd.Risk Factor Weight
4. What is the general attitude of the user?
Poor; against IT solution
Fair; sometimes reluctant
Good; understands value of IT solution
5. How committed is upper-level user management to the system?
Somewhat reluctant, or unknown
Adequate
Extremely enthusiastic
6. Has a joint IT-user team been established?
No
Part-time user representative appointed
Full-time user representative appointed
High
Medium
High
Medium
Low
High
Low
3
2
0
3
2
1
3
1
0
5
5
5
Technology Risk Assessment Risk Factor Weight
1. Which of the hardware is new to the company?
None
CPU
Peripheral and / or additional storage
Terminals
Mini or Macro
2. Is the system software (non operating system) new to IT project team?
No
Programming language
Database
Data communications
Other (please specify)
3. How knowledgeable is user in are of IT?
First exposure
Previous exposure but limited knowledge
High degree of capability
High
High
High
High
High
High
High
High
High
Medium
Low
0
3
3
3
3
0
3
3
3
3
3
2
1
5
5
5
Technology Risk Assessment - Contd.
Risk Factor Weight
4. How knowledgeable is user representative in proposed application area?
Limited
Understands concept but has no experience
Has been involved in prior implementation efforts
5. How knowledgeable is IT team in proposed application area?
Limited
Understands concept but has no experience
Has been involved in prior implementation efforts
High
Medium
Low
High
Medium
Low
3
2
1
3
2
1
5
5
Portfolio RiskPortfolio Risk Focus
Factor Low HighStability of IT development group. High Low
Perceived quality of IT development group by insiders. High Low
IT critical to delivery of current corporate services. No Yes
IT important decision support aid. No Yes
Experienced IT systems development group. Yes No
Major IT fiascoes in last two years. No Yes
New IT management team. No Yes
IT perceived critical to delivery of future corporate services.
No Yes
IT perceived critical to future decision support aids.
Company perceived as backward in use of IT. No Yes
Project Management: A Contingency Approach
• Management Tools:– External integration tools– Internal integration tools– Formal planning tools– Formal results-control
• Results controls have particularly effective in the following settings.
– Clear knowledge in advance of the desired results– The desired results can be controlled– Results can be measured effectively.
Tools of Project ManagementIntegration Tools, External Integration Tools, Internal
Selection of user as project manager.
User steering committee (which meets frequently).
User-managed change control process.
Distribution of project team information to key users.
Selection of users as team members.
User approval process for system specifications.
Prototyping with users.
Progress reports.
User involvement / responsibility in other key decisions and actions.
Selection of experienced IT professional to lead team.
Team meetings.
Distribution within team of information on key design decisions.
Technical status reviews / inspections.
Human resources techniques to maintain low turnover of team members.
Selection of high percentage of team members with significant previous work relationships.
Participation of team members in goal setting and deadline establishment.
Obtaining outside technical assistance.
Tools of Project Management – contd.
Formal Planning Tools Formal Control ToolsProject management software
PERT, CPM
Milestone selection.
Systems specification.
Project approval processes.
Post project audit procedures.
Status – versus – plan reports.
Change control disciplines and systems.
Milestone review meetings.
Analysis of deviations from plan.
Influences on Tool Selection
• High – Structure – Low – Technology projects.
• High – Structure – High – Technology projects.
• Low – Structure – Low – Technology projects.
• Low – Structure – High – Technology projects.
Relative Contribution of Tools to Ensuring Project Success by Project
TypeProject Type
Project Description
External Integration
Internal Integration
Formal Planning
Formal Results Control
I High structure – Low technology, large
Low Medium High High
II High structure – Low technology, small
Low Low Medium High
III High structure – Low technology, large
Low High Medium Medium
IV High structure – Low technology, small
Low High Low Low
Relative Contribution of Tools to Ensuring Project Success by Project
Type – Contd.Project Type
Project Description
External Integration
Internal Integration
Formal Planning
Formal Results Control
V Low Structure – Low technology, large
High Medium High High
VI Low Structure – Low technology, small
High Low Medium High
VII Low structure – High technology, large
High High Low+ Low+
VIII Low structure – High technology, small
High High Low Low
Emergence of Adaptive Project Management Methods
• Phases in Software Development Life Cycles– Analysis and Design– Construction– Implementation– Operation and Maintenance
Adaptive Methodology
• Basic Characteristics:– Iterative– Rely on fast cycles and require frequent delivery
(incremental)– Customer feedback– Skilled project staff capable of learning and making
midcourse adjustments in the middle of deployment.– Emphasize on “buying information” about outcomes
as a legitimate expenditure rather than as an investment with predictable outcomes.