FEDERAL MINISTRY OF POWER
MID-TERM ACHIEVEMENTS OF PRESIDENT GOODLUCK JONATHAN, GCFR, IN THE POWER SECTOR
PRESENTED AT THE 2013 MINISTERIAL PLATFORM
FOR THE PERIOD OF MAY, 2011 – MAY 2013
ON TUESDAY, JULY 23rd, 2013
BY
PROF. CHINEDU NEBO, OON, NPOM HONOURABLE MINISTER OF POWER
& HAJIYA ZAINAB IBRAHIM KUCHI, FICMC HONOURABLE MINISTER OF STATE FOR POWER
FEDERAL MINISTRY OF POWER
1
FEDERAL MINISTRY OF POWER 2 FEDERAL MINISTRY OF POWER
FEDERAL MINISTRY OF POWER 3 FEDERAL MINISTRY OF POWER
FEDERAL MINISTRY OF POWER 4 FEDERAL MINISTRY OF POWER
FEDERAL MINISTRY OF POWER 5 FEDERAL MINISTRY OF POWER
FEDERAL MINISTRY OF POWER 6
AMBASSADOR (DR) GODKNOWS IGALI OON, FNAH Permanent Secretary, Federal Ministry of Power
FEDERAL MINISTRY OF POWER
FEDERAL MINISTRY OF POWER
Let me start by acknowledging the high-level political will of His Excellency, President Dr. Goodluck Ebele Jonathan, GCFR and His Excellency, Vice-President, Arc. Mohammed Namadi Sambo, GCON, to have launched the process fundamental to the transformation witnessed in the power sector in recent years. Without this level of commitment, the achievements recorded from 2011 to date would not have been realised. More importantly, the launching of the Power Sector Roadmap by Mr. President in August, 2010 has accelerated the pace of the reform and the significant achievements recorded so far in the power sector.
Introduction
7 FEDERAL MINISTRY OF POWER
FEDERAL MINISTRY OF POWER
• PTFP • GenCos
• TCN • DisCos
• NDPHC • NBET
• NELMCO • EMS
• NAPTIN • REA
• HYPERDEC
• Residential
• Commercial
• Industrial
• NERC • FMoP
Policy Regulation
Operations Customers
Introduction…Cont’d. Power Sector Structure
8 FEDERAL MINISTRY OF POWER
FEDERAL MINISTRY OF POWER
Introduction…Cont’d.
Focus on Activities of the Power Sector
Power stability, reliability & sustainability
Diversification of energy mix (large hydros, renewables & coal)
Electricity market stabilization Improving rural access to electricity
Human capacity development
Improving policy and regulatory environment for rapid growth through private investment
Reducing production cost and making manufacturing sector
more competitive
Empowering SMEs with more power supply and creating
employment
9 FEDERAL MINISTRY OF POWER
FEDERAL MINISTRY OF POWER FEDERAL MINISTRY OF POWER
Omotosho 304MW
Ibom 190MW
Afam VI 650MW
Shiroro 600MW
Jebba 540MW
Kainji 760MW
Egbin 1,320MW
Delta 900MW
Afam I-V 726MW
Okpai 450MW
Sapele 720MW
Omoku 120MW
N I G E R I A
Power Generation.
Existing Power Stations Connected to Grid
Design Installed
Capacity (MW)
Kainji 760
Jebba 540
Shiroro 600
Olorunsogo 304
Egbin 1320
Sapele - FGN 720
Delta 900
Afam I-V 726
Afam VI (Shell) 650
Okpai Omoku Omotosho 304
Geregu 414
AES 294
Ibom Power 190 Olorunsogo 304MW
AES 294MW
Geregu 414MW
450
120
10
FEDERAL MINISTRY OF POWER
Power Generation. Cont’d
Rehabilitation Works
11
• Shiroro: Repair works on Unit 2 which led to recovery of 150MW in 2012
Hydropower Plant.
• Jebba: Hydro Power Station preventive maintenance of 2G2 in 2012 to
ensure availability and sustainability of 96.4MW.
• Egbin: In 2012, several worn parts of the plant were replaced with new
ones. This has improved plant reliability from 60% to more than
70%.
• Kainji: Rehabilitation works on 1G5 & 1G12 Units to recover 220MW
capacity by Dec 2014.
FEDERAL MINISTRY OF POWER
FEDERAL MINISTRY OF POWER
Power Generation. Cont’d
Rehabilitation Works – Kainji Hydro Power Station
Rehabilitation works on 1G5 & 1G12 Units to recover 220MW capacity by Dec 2014
12 FEDERAL MINISTRY OF POWER
FEDERAL MINISTRY OF POWER FEDERAL MINISTRY OF POWER 13
Mambilla 3050MW
Calabar 563MW
Geregu-2 434MW
Olorusogo-2 675MW
Omotosho-2 451MW
Alaoji 960MW
Egbema 338MW
Omoku 225MW
Ihovbor 450MW
Sapele 450MW
Gbarain 225MW
Kaduna 215MW
Katsina wind 10MW
Zungeru 700MW
Kashimbila 40MW
Gurara 30MW
Installed Capacity (MW)
Katsina 10
Kaduna 215
Zungeru 700
Gurara I 30
Mambilla 3,050
Olorunsogo -2 675
Omotosho - 2 451
Geregu - 2 434
Kashimbilla 40
Ihovbor 450
Sapele 450
Gbarin 225
Omoku 225
Alaoji 960
Egbema 338
Calabar 563
13
Power Generation. Cont’d
Newly Completed/On-going Power Plants for Increased Generation
FEDERAL MINISTRY OF POWER
Power Generation. Cont’d
Completed Generation Projects in the period under review
14
S/No Power Station Date MW Cumulative MW
1 Olorunsogo Jan-11 112.5 112.5
2 Olorunsogo Feb-11 112.5 225.0
3 Olorunsogo May-11 112.5 337.5
4 Sapele Aug-11 112.5 450.0
5 Olorunsogo Nov-11 112.5 562.5
6 Sapele Feb-12 112.5 675.0
7 Alaoji Apr-12 112.5 787.5
8 Omotosho Apr-12 112.5 900.0
9 Olorunsogo Jul-12 112.5 1,012.5
10 Sapele Aug-12 112.5 1,125.0
11 Omotosho Aug-12 112.5 1,237.5
12 Alaoji Sep-12 112.5 1,350.0
13 Omotosho Oct-12 112.5 1,462.5
14 Sapele Oct-12 112.5 1,575.0
15 Omotosho Dec-12 112.5 1,687.5
FEDERAL MINISTRY OF POWER
FEDERAL MINISTRY OF POWER
Energy Mix
In order to enhance the security of power supply, government is assiduously working towards the diversification of the fuel mix. In this regard, the nation’s vast resources of coal, wind, solar, biomass and hydropower potentials are being fully exploited. • Feasibility Studies on the development of coal to power are on-
going in five(5) coal blocks in Enugu axis and three (3) coal blocks in Benue, Kogi and Gombe axis. Progress of work on the studies is at 25% and is expected to focus on clean coal technology.
• Feasibility Studies on ten (10) dams with small hydropower potentials which commenced in Y2011 have been completed and ready for concession.
15 FEDERAL MINISTRY OF POWER
FEDERAL MINISTRY OF POWER
Hydro Power Development in Nigeria
16
• Zungeru project in Niger State…………………….700MW
• Mambilla project – Taraba State…………………..3,050MW
• Gurara II project – Niger State……………………...360MW
• Gurara I Project Niger State…………………………..30MW
• Itisi project – Kaduna State……………………………40MW
• Kashimbilla project – Taraba State…………………40MW
• Other Small/medium hydropower projects – Nationwide
FEDERAL MINISTRY OF POWER
FEDERAL MINISTRY OF POWER
Hydro Power Development in Nigeria Small/Medium Hydropower studies completed by FMP from 2011 to date
S/N DAM STATE CAPACITY (MW)
1 Oyan Ogun 10
2 Ikere Gorge Oyo 6
3 Bakolori Zamfara 3
4 Challawa Kano 7.5
5 Tiga Kano 10
6 Kampe Kogi 3
7 Owena Ondo 0.45
8 Doma Nasarawa 1
9 Zobe Katsina 0.30
10 Jibia Katsina 4
17 FEDERAL MINISTRY OF POWER
FEDERAL MINISTRY OF POWER
Hydro Power Development in Nigeria
360MW GURARA II Multi-purpose Project
C.A. 2,510
km2
C.A. 2,840
km2 Gurara II
Located 140km downstream of Gurara I and 40km from Abuja Design basis: 360MW and 1,130GWhr of energy per annum IRR = 8.9% at MYTO tariff Estimated cost: US$800m Irrigation potential: 8,000Ha
18 FEDERAL MINISTRY OF POWER
FEDERAL MINISTRY OF POWER
Hydropower Development in Nigeria (Zungeru)
19
The construction of the 700MW Zungeru hydropower project was approved by FEC in
2012 in favour of a consortium of Messrs. Sinohydro/CNEEC in the contract sum of
US$ 1.237 billion and a completion period of 48 months.
FEDERAL MINISTRY OF POWER
FEDERAL MINISTRY OF POWER
Hydropower Project in Nigeria Zungeru
20
•Ground breaking ceremony for the project was performed by His Excellency President Goodluck Jonathan, GCFR on 28th May, 2013
FEDERAL MINISTRY OF POWER
FEDERAL MINISTRY OF POWER
River Basins with Large and Small Scale Hydropower Potential
Focus on Renewable Energy Resources Development
Solar Map Hydro Potentials
21 FEDERAL MINISTRY OF POWER
River Basins with Large and Small Scale Hydropower Potential
FEDERAL MINISTRY OF POWER
Focus on Renewable Energy Resources Development
contd.
Wind Map
22 FEDERAL MINISTRY OF POWER
FEDERAL MINISTRY OF POWER
The 10 MW Katsina Windfarm Power Project is at 98% completion and will soon be commissioned
Focus on Renewable Energy Resources Development contd.
23 FEDERAL MINISTRY OF POWER
FEDERAL MINISTRY OF POWER
Nigeria’s Transmission Grid
24
• Transmission development activities are mainly carried out by Transmission
Company of Nigerian (TCN) and Niger/Delta Power Holding Company
(NDPHCN) under the National Independent Power Project (NIPP).
• TCN Projects are funded through the statutory budgets from the FGN.
• NIPP projects are funded by the 3-tiers of the government from the excess crude
account.
• For the period under review several transmission projects have been completed
which lead to modest increase in the nation’s transmission capacity as listed in
the following slides.
FEDERAL MINISTRY OF POWER
FEDERAL MINISTRY OF POWER
330kV System
Capacity (blue line)
6870 MW 5650 KM
Nigeria 330kV Network
25
Nigeria’s Transmission Grid
FEDERAL MINISTRY OF POWER
FEDERAL MINISTRY OF POWER
Nigeria’s Transmission Grid Completed Transmission Projects (Substations) - NIPP
26
PROJECT DESCRIPTION MVA
LOT 9-A 330/132/33KV Ganmo SS (New) 300
LOT 9-B 132/33KV Ayede SS (Ext.) 150
LOT 10-A 132/33KV Central Area SS (Ext.) 60
LOT 10-B 330/132KV Katampe SS (Ext.) 150
LOT 10-C 132/33KV Kumbotso SS (Ext.) 60
LOT 10-D 330/132/33KV Mando SS (Ext.) 150
LOT 11-A 132/33KV Agbara SS (Ext.) 60
LOT 11-B 132/33KV Ikeja West SS (Ext.) 150
LOT 11-C 132/33KV Ojo SS (Ext.) 120
LOT 11-D 132/33KV Oworonsoki SS (Ext.) 120
LOT 13-A 330/132KV Aja G.I.S. SS (Ext.) 150
LOT 13-B 132KV Aja G.I.S. SS (Ext.)
LOT 24-1 330/132KV Papalanto SS (New) 450
LOT 26-1 330/132KV Omotosho SS (New) 450
LOT 27A 330KV Sapele SS (Rehab. & Ext.)
LOT 27B 330KV Benin SS (Rehab.)
TOTAL 2,370
FEDERAL MINISTRY OF POWER
FEDERAL MINISTRY OF POWER
Nigeria’s Transmission Grid Completed Transmission Projects (Lines) - NIPP
27
PROJECT
DESCRIPTION
LENGTH (KM)
LOT 9-C 330KV DC Ganmo-(Jebba/Osogbo SC - Turn in/Turn out) 12
LOT 9-D 132KV DC Ganmo-(Ilorin/Oshogbo SC Turn in/Turn out) 2
LOT 19-3A 330KV DC Ihovbor-(Benin Main-Oshogbo) (Line A) 17
LOT22-2 330KV DC Ajaokuta-Lokoja-Gwagwalada 222
LOT 24-2 330KV DC Papalanto-(Ikeja West/Ayede) 16
LOT 26-2 330KV DC Omotosho - Ikeja West 5
TOTAL 274
FEDERAL MINISTRY OF POWER
FEDERAL MINISTRY OF POWER 28
Nigeria’s Transmission Grid Completed Transmission Projects - TCN
Completed Projects from 2011 to Date
S/N Title of Project Project
Location Deliverables
1 Construction of 150MVA 330/132/33kV T/F and 330kV bays at Onitsha and Benin.
Edo & Anambra 150MVA increase in transformer capacity at 330kV Voltage level at Onitsha
2 Calabar 2x150MVA, 330/132/33kV Substation and line bay at Alaoji Substation.
Cross River & Abia
300MVA Transformer capacity at 330kV level in Calabar, Cross River State
3 Construction of Alaoji-Umuahia 132kV DC line Abia 50km of 132kV Transmission line. Increase wheeling capacity to Umuahia, Abia State
4 Umuahia 2x30/40MVA, 132/33kV Substation Abia 80MVA Transformer capacity at 132kV level in Umuahia, Abia State
5 Gombe-Damaturu-Maiduguri 330kV line. Gombe, Yobe & Borno
376km of 330kV Transmission line. Increase wheeling capacity to Yobe and Borno States
6 Jos - Kafanchan 132KV D/C Line . Plateau & Kaduna
80km of 132kV Transmission line. Increase wheeling capacity to Kafachan & Environs, Kaduna State
7 2 x 30MVA 132/33KV S/S at Pankshin and Makeri Plateau 60MVA Transformer capacity at 132kV level in Makeri & Pankshin towns in Plateau State
FEDERAL MINISTRY OF POWER
FEDERAL MINISTRY OF POWER 29
Nigeria’s Transmission Grid
Completed Transmission Projects - TCN
Completed Projects from 2011 to Date
S/N Title of Project Project Location Deliverables
8 3rd Benin - Onitsha 330KV DC Line Edo, Delta & Anambra 131km of 330kV Transmission line. Increase wheeling capacity to Onitsha & Environs, Anambra States
9 Rehabilitation of Sokoto – Talata Mafara 132KV DC line Sokoto & Zamfara Recovery of 125km of 132kV Transmission line
10 Transmission & Supply of Substation at Tamburawa Water Facility
Kano 80MVA Transformer capacity at 132kV level in Tamburawa
11 1X30 MVA 132/33 KV SS at Kwanar Dangora Kano 30MVA Transformer capacity at 132kV level in Kwanar Dangora
12 Reinforcement of Birnin Kebbi and Kumbotso Substations with 1x150MVA, 330/132kV transformer each.
Kebbi and Kano States 150MVA transformer capacity increase at 330kV level in both Birnin Kebbi and Kano
1 Kainji-New Bussa 330kV single-circuit transmission line Kainji to New Bussa in Niger State
8.6km of 330kV transmission line to link Kainji and New Bussa
FEDERAL MINISTRY OF POWER
FEDERAL MINISTRY OF POWER 30
Nigeria’s Transmission Grid.
On-Going TCN Projects at advanced stages of Implementation
S/N
Project Description Name of Contractor Project
Location Project Total Cost
(Naira) Project Deliverables
Status of Implementation (%)
Impact of Project
1 Arochukwu 2x30/40MVA, 132/33kV substation
Omen International Ltd. Abia State 937,496,022.58 80MVA Transformer capacity at 132kV level in Arochukwu, Abia State
86% Improvement of Power supply to Arochukwu and environs and enhancement of socio-economic life of the people.
2 Mbalano-Okigwe 132kv SC line
Atlantic Engineering & Construction
Mbalano (Abia) to Okigwe (Imo)
329,754,483.86 20km of 132kV Transmission line.
100% Improvement of Power supply to Okigwe and environs and enhancement of socio-economic life of the people.
3 Okigwe 2x30/40MVA 132/33kV Substation
Union Allied Engineering Ltd.
Imo State 1,839,789,715.03 80MVA Transformer capacity at 132kV level in Okigwe, Imo State
60% Improvement of Power supply to Okigwe and environs and enhancement of socio-economic life of the people.
4 Umuahia-Ohafia 132kv SC line
Harlesden Engineering Ltd
Umuahia to Ohafia in Abia State
1,257,267,830.78 49.5km of 132kV Transmission line.
60% Improvement of Power supply to Ohafia and environs and enhancement of socio-economic life of the people.
5 Ohafia 2x30/40MVA 132/33kV substation.
Union Allied Engineering Ltd.
Abia State 1,972,613,202.90 80MVA Transformer capacity at 132kV level in Ohafia, Abia State
60% Improvement of Power supply to Ohafia and environs and enhancement of socio-economic life of the people.
6 Mbalano 2x30/40MVA 132/33kV substation.
Union Allied Engineering Ltd.
Abia State 1,409,011,316.42 80MVA Transformer capacity at 132kV level in Mbalano, Abia State
60% Improvement of Power supply to Mbalano and environs and enhancement of socio-economic life of the people.
FEDERAL MINISTRY OF POWER 31
Nigeria’s Transmission Grid.
On-Going TCN Projects at advanced stages of Implementation
S/N Project Description Name of Contractor Project
Location Project Total Cost
(Naira) Project Deliverables
Status of Implementation
(%) Impact of Project
7 1x150MVA,330/132KV Transformer at Birnin Kebbi and Reinforcement at 330/132KV substation at Kumbotso
MBH Power Kebbi and Kano States
3,559,832,144.00 150MVA Transformer capacity at 330KV level in Birnin Kebbi
98% Improvement of Power supply to Birnin Kebbi, Kumbotso and envirohancemens and enhance ment of socio-economic activities in the areas.
8 Kainji - New Bussa 132KV DC Transmission line & 330KV SC River crossing
Dextron Engineering Ltd Kainji to New Bussa, Niger State
308,108,608.00 132kV and 330KV transmission lines to wheel more power to Nerw Bussa.
98% Improvement of Power supply to New Bussa and environs and enhancement of socio-economic life of the people.
9 Katampe-National Stadium 132kv DC line
ABB Powerlines; Energo Nigeria Ltd
FCT 2,656,115,130.98 8.4km of 132kV double-circuit underground cable and 4km of 132kV DC overhead transmission line.
55% Improvement of Power supply to the FCT.
10 Kainji 1x150MVA, 330/132KV & 2x30/40MVA substation at New Bussa
MBH Power Niger State 4,599,287,900.00 150MVA Transformer capacity in kainji, Niger State.
89% Improvement of Power supply to New Bussa and environs and enhancement of socio-economic life of the people.
11 2x60MVA, 132/33KV Substation at Odogunyan and Ayobo with 132KV DC line Ikeja west - Ayobo.
LAGA CePower Lagos State 3,657,155,630.00 120MVA Transformer capcity at 132kV level at Odogunyan and Ayobo.
89% Improvement of Power supply to Odogunyan, Ayobo and environs and improvement of socio-economic activities in the areas.
12 Ikorodu - Odogunyan - Shagamu 132KV DC Transmission line
PPCL/ Westcom JV Ikorodu to Odogunyan, Lagos State
3,192,097,186.00 132kV DC transmission line from Ikorodu to Odogunyan
52% Improvement of Power supply to Odogunyan, Shagamu and environs and improvement of socio-economic activities in the areas.
13 Damaturu 330/132kV Substation
Parsian High VoltageDiv./ Cartlark Int'l Ltd
Yobe State 2,502,960,280.52 150MVA Transformer capacity at 330kV level in Damaturu, Yobe State
80% Improvement of Power supply to Damaturu and environs and improvement of socio-economic activities in the areas.
FEDERAL MINISTRY OF POWER 32
Nigeria’s Transmission Grid.
On-Going TCN Projects at advanced stages of Implementation
S/N Project Description Name of
Contractor Project
Location Project Total Cost
(Naira) Project Deliverables
Status of Implementati
on (%) Impact of Project
14 Nnewi 2x60 MVA 132kV substation
Valenz Holdings (Nig) Ltd.
Anambra State 735,801,070.00 120MVA Transformer capacity at 330kV level in Nnewi
65% Improvement of Power supply to Nnewi and environs and improvement of socio-economic activities in the areas.
15 Kafanchan 132kv 2 x 60mva Substation
Valenz Holding Ltd Kaduna State 1,407,774,049.57 120MVA Transformer capacity at 132kV level in Kafanchan
80% Improvement of Power supply to Kafanchan and environs and improvement of socio-economic activities in the areas.
16 Makeri - Pankshin 132KV DC Line
Mogabs Nig. Ltd Makeri to Pankshin, Plateau State
1,295,611,365.16 Rehabilitation of 122km of 132kV Transmission line.
75% Improvement of Power supply to Pankshin and environs and improvement of socio-economic activities in the areas.
17 2 x 30MVA 132/33KV S/S at Pankshin and Makeri
North China/EESE Plateau State 1,783,781,485.32 60MVA Transformer capacity at 132kV level in Makeri & Pankshin towns in Plateau State
100% Improvement of Power supply to Makeri, Pankshin and environs and improvement of socio-economic activities in the areas.
18 Kano- Walalanbe 132KV Line (Turn in and out of Dan agundi-Dakata 132KV single Cct Line) and 2 x 30/40MVA S/S at Walalambe
GIT Kano Sate 1,783,781,485.32 132kV DC Transmission line & 80MVA Transformer capacity at 132kV level in Walalambe
55% Improvement of Power supply to Kano and environs and improvement of socio-economic activities in the areas.
19 Yelwa - Yauri 2 x 30/40MVA S/S and 100KM of 33KV Line
Valenz/ Electromontaz
Kebbi State 1,242,074,910.89 100km of 33kV line & 80MVA Transformer capacity at 132kV level in Yelwa, Kebbi State
60% Improvement of Power supply to Yelwa, Yauri and environs and improvement of socio-economic activities in the areas.
20 Umuahia - Mbalano 132KV Line
Santon Energy L:td Abia State 991,759,726.68 30km of 132kV DC Transmission line.
67% Improvement of Power supply to Mbalano and environs and improvement of socio-economic activities in the areas.
21 Ohafia - Arochukwu 132KV Line
Mogabs Nig. Ltd Abia State 856,128,363.00 40km of 132kV DC Transmission line.
45% Improvement of Power supply to Arochukwu and environs and improvement of socio-economic activities in the areas.
FEDERAL MINISTRY OF POWER 33
Nigeria’s Transmission Grid.
On-Going TCN Projects at advanced stages of Implementation
S/N Project Description Name of
Contractor Project
Location Project Total Cost
(Naira) Project Deliverables
Status of Implementati
on (%) Impact of Project
22 Kukwaba 2x60MVA, 132/33kV substation
North China Power Egnineering
FCT 2,568,846,118.51 120MVA Transformer capacity at 132kV level in Kukwaba, FCT
40% Improvement of Power supply to the FCT.
23 2x60MVA, 132KV/33 at Aboh -Mbaise S/S
Ashtavinayaka/Bran Engineering
Imo State 1,480,777,014.45 120MVA Transformer capacity at 132kV level in Aboh Mbaise in Imo State
65% Improvement of Power supply to Aboh Mbaise and environs and improvement of socio-economic activities in the areas.
24 2x60 MVA, 132/33 kV substation at Ideato and 2 x132KV Line Bays at Okigwe
Ashtavinayaka/Bran Engineering
Imo State 1,739,004,381.00 120MVA Transformer capacity at 132kV level in Ideato in Imo State
60% Improvement of Power supply toIdeato and environs and improvement of socio-economic activities in the areas.
25 2x60 MVA, 132/33 kV substation at Oba and 2 x132KV Line Bays at Nnewi
Xian/GIT Engineering Anambra State 1,863,432,339.00 120MVA Transformer capacity at 132kV level in Oba.
45% Improvement of Power supply to Oba and environs and improvement of socio-economic activities in the areas.
26 Oshogbo- Ede 132KV DC Line
Aster Infrast/Aster Teleservices
Osun State 1,490,085,721.56 15km of 132kV DC transmission line
53% Improvement of Power supply to Ede and environs and improvement of socio-economic activities in the areas.
27 DC 132kV line from Alscon to Ibom Power and Switching Station to link the GIS at Alscon with associated bay extensions at Ibom Power - Akwa Ibom State
KEC International Limited
Akwa Ibom State
747,246,322.01 2.5km of 132kV DC Transmission line and 150km of 132kV DC underground Cable
45% Improvement of Power supply to Akwa Ibom State and improvement of socio-economiclife of the people.
28 Reconductoring of Afam-Port Harcourt 132kV line
Electrical Solutions Ltd Ricers State 290,000,000.00 Rehabilitation of 37.8km of 132kV Transmission line with increased wheeling capacity
100% Improvement of Power supply to Port Harcourt and environs and improvement of socio-economic activities in the areas.
FEDERAL MINISTRY OF POWER
FEDERAL MINISTRY OF POWER
Nigeria’s Transmission Grid NIPP Completed Transmission Projects
LOT 10-B (Charnel/AkAy 150MVA 330/132kV Katampe SS (Extension) in full service
LOT 11-B (Charnel/AkAy 150MVA 330/132kV Ikeja West SS (Extension) in full service
34 FEDERAL MINISTRY OF POWER
FEDERAL MINISTRY OF POWER
Distribution Activities
35
To ensure availability of un-interrupted power supply to
the consumers, this administration executed various
distribution projects (maintenance/expansion) across the
country through the eleven (11) Electricity Distribution
Companies (DisCos)
FEDERAL MINISTRY OF POWER
FEDERAL MINISTRY OF POWER
NIPP Completed Distribution Projects
36
• Abuja Zone –
- ABUJA - AIRPORT 33KV DC LINE
- APO 1 X 15MVA INJECTION S/S TRANSFORMER
• Benin Zone –
- IHOVBOR 2 X 2.5MVA INJECTION S/S TRANSFORMER
- AKURE Main 1x15mva INJECTION TRANSFORMER
• Eko –
- NEW IDUMAGBO 1 X 15MVA INJECTION S/S TRANSFORMER
- Beckely 1 X 15mva Injection S/S Transformer
- Alagbon 1 X 15mva Injection S/S Transformer
- Fowler 1 X 15mva Injection S/S Transformer
- Apapa Road 1 X 15mva Injection S/S Transformer
- Nitel 1 X 15mva Injection S/S Transformer
- Tincan 1 X 15mva Injection S/S Transformer
- Agbara 1 X 15mva Injection S/S Transformer
- Ajangbadi 1 X 15mva Injection S/S Transformer
• Ibadan Zone
- Akobo 1 X 15mva Injection S/S Transformer
- Awe - Oyo 1 X 7.5mva Injection S/S Transformer
- Samanda 1 X 15mva Injection S/S Transformer
- Apata 1 X 15mva Injection S/S Transformer
- Ikiru Road 1 X 15mva Injection S/S Transformer
-Tinumola 1 X 7.5mva Injection S/S Transformer
FEDERAL MINISTRY OF POWER
FEDERAL MINISTRY OF POWER
NIPP Completed Distribution Projects contd.
37
• Ikeja - IPAKODO 1 X 15MVA INJECTION S/S TRANSFORMER - IJEDE 1 X 15MVA INJECTION S/S TRANSFORMER - AGBOWA 1 X 15MVA INJECTION S/S TRANSFORMER - OWUTU 1 X 15MVA INJECTION S/S TRANSFORMER - IMOTA 1 X 15MVA INJECTION S/S TRANSFORMER - MAGODO 1 X 15MVA INJECTION S/S TRANSFORMER • Kaduna - ZAMBIAN CRESCENT 1 X 2.5MVA INJECTION S/S TRANSFORMER - KAGORO 1 X 7.5MVA INJECTION S/S TRANSFORMER - NARAYI 2 X 2.5MVA INJECTION S/S TRANSFORMER • Jos - PANKSHIN 1 X 7.5MVA INJECTION S/S TRANSFORMER - SHENDAM 1 X 7.5MVA INJECTION S/S TRANSFORMER - COMPLETED INJECTION S/S = 31 - CAPACITY = 492.5 MVA - COMPLETED CSP TRANSFORMERS = 2514 - COMPLETED 11KV LINES = 1221KM, 33KV = 230KM
FEDERAL MINISTRY OF POWER
FEDERAL MINISTRY OF POWER 38
DisCos Completed Distribution Projects
ENUGU ELECTRICITY DISTRIBUTION COMPANY
PROJECTS COMPLETED FROM 2011 TO DATE
DisCos Installed Transformer Capacity from 2011 to date
S/N Description Year
2011 2012 2013 (as at 31st May)
1 33/11KV Injection Substation (MVA) 959.75 974.75 1,083.50
2 33/0.415KV Distribution Substation (MVA)
972.67 1,028.62 1,047.32
3 11/0.415KV Distribution Substation (MVA)
1,600.99 1,657.84 1,680.74
ENUGU ELECTRICITY DISTRIBUTION COMPANY
PROJECTS COMPLETED FROM 2011 TO DATE
DisCos Installed 33KV and 11KV Overhead Lines from 2011 to date
S/N Description
Year
2011 2012 2013 (as at 31st
May)
1 33KV Overhead lines (Km) 6,596.50 6,651.95 6,924.80
2 11KV Overhead lines (Km) 3,464.80 3,504.00 3,522.90
FEDERAL MINISTRY OF POWER
FEDERAL MINISTRY OF POWER
SOME COMPLETED INJECTION SUBSTATION & SWITCH YARD in 2012
39
DisCos Completed Distribution Projects contd. Ikeja DisCo
FEDERAL MINISTRY OF POWER
FEDERAL MINISTRY OF POWER 40
REA was reactivated in June, 2012, to improve rural access to electricity.
The Ministry has developed a draft REA Strategy and Implementation Plan
and it is being finalized.
REA will focus on increased exploitation of renewables and the facilitation
of rural electrification projects.
The Agency carried out Survey, Design, Procurement and Award of
several rural electrification projects under 2012 capital appropriation.
Rural Electrification Agency (REA)
FEDERAL MINISTRY OF POWER
FEDERAL MINISTRY OF POWER
The Reform Process : Progress So Far
The Electric Power Sector Reform (EPSR) Act of 2005 provided the platform for the reform of deregulating the Nigerian Electricity Supply Industry (NESI) from the control, ownership and regulation of the sector by the Federal government to a private sector-driven industry. The launching of the Roadmap by Mr. President in August 2010 has led to significant progress in the implementation of the structural reforms outlined in the Act. The major achievements to date are as follows: i. Bidding and selection of preferred bidders for the 10 Distribution Companies
and the 5 Generation Companies was concluded in November 2012, contracts have been signed and bidders have already made initial payments of 25% of the bid price.
ii. Presidential Power Reform Transaction signing and presentation of certificates for payments of initial deposits to successful bidders of the DisCos and GenCos by Mr. President was performed on 22nd April, 2013.
iii. Handing over of TCN to Manitoba Hydro International for management contract concluded. Schedule of Delegated Authority (SODA) give to Manitoba
41 FEDERAL MINISTRY OF POWER
FEDERAL MINISTRY OF POWER
The Reform Process : Progress So Far contd.
iv. The Nigerian Electricity Regulatory Commission (NERC) has been reconstituted, strengthened and now is fully operational.
v. NERC launched MYTO 2 cost-reflective tariff in June, 2012, which is now operational.
vi. Nigeria Bulk Electricity Trading (NBET) PLC was incorporated in July, 2010 and is now in operation as a credit-worthy off - taker.
vii. The Nigeria Electricity Liability Management Company (NELMCO) was established in 2010 to assume and manage the assets, liabilities and other obligations that could not be earlier transferred from PHCN to any successor company
viii. Resolution of Labour issues is almost completed and payment of severance package to commence this week.
ix. Investor confidence evidenced by increased investment and signing of MoUs. Most recent being the MoU signed with Power China Corporation to develop 20,000 MW of Thermal Power Plants with associated substations and transmission lines up to 10,000 km
x. Sale of Ten (10) power plants built by the Niger Delta Power Holding Company Ltd commenced with road-shows in Lagos, London, Hong Kong and New York.
42 FEDERAL MINISTRY OF POWER
FEDERAL MINISTRY OF POWER
The Reform Process : Progress So Far contd.
43 FEDERAL MINISTRY OF POWER
FEDERAL MINISTRY OF POWER
The Reform Process : Progress So Far
iv. T
44
His Excellency, the Vice President , Arc. Namadi Sambo presenting certificates to one of the Core investors in the on-going privatisation of the Power Sector.
FEDERAL MINISTRY OF POWER
FEDERAL MINISTRY OF POWER
Reform Process:
Resolution of all labour issues
Seated from the left: The Honourable Minister of State for Finance, Yerima Ngama; Honourable Minister of State for Power, Hajiya Zainab Ibrahim Kuchi; Honourable Minister of Labour and Productivity, Emeka Wogu together with Labour Union in the sector.
45 FEDERAL MINISTRY OF POWER
FEDERAL MINISTRY OF POWER 46
A robust Nigeria Electricity Supply Industry requires a well-trained work force. Hence, strategies have been put in place to improve the competences of the existing work force through skill enhancement and professional development programmes. Part of these strategies include the establishment of the National Power Training Institute of Nigeria (NAPTIN) to ensure that the human capital needs of the sector are met. Key achievements include:
1. Rehabilitated six(6) existing Regional Training Centres (RTC) inherited from PHCN and building of 2 new ultra-modern training centres in Jos and Kano
2. Commenced intensive training of 1,000 graduate engineers (Graduate Skill Development Program)
3. Trained 70 engineers across the power sector on renewable energy options (solar, wind + hybrid)
4. Commissioned Power System Training Simulator at Ijora RTC in October, 2012
Capacity Building
National Power Training Institute (NAPTIN)
FEDERAL MINISTRY OF POWER
FEDERAL MINISTRY OF POWER 47
5. Laid foundation for the development of NAPTIN’s permanent site at Idu Industrial Layout, Abuja in October 2012
6. Completed rehabilitation of mechanical workshop at Ijora Regional Training Center (RTC), Lagos.
7. Installed / commissioned NAPTIN’s e-Learning platform in December, 2012
8. Installed / commissioned renewable hybrid solar PV + wind demonstration plants at Kainji RTC in November 2012
9. Completed Faculty profiling and curriculum development in December, 2012
10.Signed MoU with PNN Nigeria Limited (an indigenous renewable energy company) on the Training of 1,500 youths on installation and maintenance of solar PVs
11.Developed and commissioned 60 and 36-room executive hostel / guest house for trainees at Kainji and Akangba RTCs respectively.
12.Trained about 5,340 professionals to date since inception
Capacity Building National Power Training Institute (NAPTIN)
FEDERAL MINISTRY OF POWER
FEDERAL MINISTRY OF POWER
Capacity Building
National Power Training Institute (NAPTIN)
Various Projects Completed and Commissioned by NAPTIN in 2012
ENGINEERING LABORATORY ,
KAINJI
Electric Power System Simulator, Ijora
MECHANICAL WORKSHOP,
NAPTIN RTC IJORA
EXECUTIVE HOSTEL AT
AKANGBA RTC
Electric Power System Simulator, Ijora
EXECUTIVE HOSTEL AT
AKANGBA RTC
48 FEDERAL MINISTRY OF POWER
FEDERAL MINISTRY OF POWER
Capacity Building
National Power Training Institute (NAPTIN)
49
Various Training Courses Organized In 2012 Covering Technical And Administrative Skills
Scheduled Training Undertaken
FEDERAL MINISTRY OF POWER
FEDERAL MINISTRY OF POWER 50
Stakeholder Engagements
• Nigeria/Niger Joint Commission Meetings in Abuja & Niamey. • West African Power Pool Meetings. • ECREEE meeting at Cape Verde. • Engagements with Investors from international countries • Meetings with Development Partners. • Meetings with Manitoba Hydro International of Canada. • Meeting with AfDB, World Bank, JICA, EU, GIZ, USAID, USTDA, DFID, UNIDO, NAIF
etc. • Meeting with BOI on MoU for financial services for Public Private Partnership. • Bilateral Meetings with Reps of various countries on power sector development
(Sweden, Germany, Italy etc.) • Engagements with private investors (including FDI’s) in power sector • MYTO II tariff consultation with stakeholders • As part of advocacy, the Ministry had working visits and consultations with
traditional rulers.
FEDERAL MINISTRY OF POWER
FEDERAL MINISTRY OF POWER
Stakeholders Engagements
As part of advocacy visits, HMP on working visit to the HRH. Emir of Zazzau, Alh. Shehu Idiris.
Tariff consultation with Oba of Lagos in May 2012
FEDERAL MINISTRY OF POWER 51
FEDERAL MINISTRY OF POWER
52
Stakeholders Engagements
From left: Vice Chairman Senate Committee on Power, Sen. Chris Ngige; Chairman, Sen. Philip Aduda; HMP, Prof. Chinedu Nebo; HMSP, Hajiya Zainab Ibrahim Kuchi; Permanent Secretary Ministry of Power, Amb. Godknows Igali, during Senate committee on Power’s visit to the Ministry.
FEDERAL MINISTRY OF POWER
FEDERAL MINISTRY OF POWER
Summary of Key Output/Achievements
53 FEDERAL MINISTRY OF POWER
FEDERAL MINISTRY OF POWER
Record Peak Generation of 4,517.6MW . Record Average Energy Sent Out of 4,028.85MWh/h
Key Output/Achievements.
Generation
54 FEDERAL MINISTRY OF POWER
FEDERAL MINISTRY OF POWER 55
8,4979,9209,097
2012-2013 2011 2010
Installed Generation Capacity MW
5,5636,522
3,700
2010 2011 2012-2013
Available Generation Capacity MW
FEDERAL MINISTRY OF POWER 56
Key Output/Achievements.
Transmission
TCN Installed Transformer Capacity (MVA) at 330 and 132kV Transmission Voltage Levels
0
2000
4000
6000
8000
10000
12000
2007 2008 2009 2010 2011 2012
MVA @330/132kV
MVA @132/33kV
Volt Level 2007 2008 2009 2010 2011 2012 2013
MVA @330/132kV
6,098 6,398 6848 7,688 8,138 8,686 Being Up-
Dated MVA @132/33kV
8,244 8,350 8,590 9,130 9,800 10,792
FEDERAL MINISTRY OF POWER
FEDERAL MINISTRY OF POWER
3,640
4,527
2,800
2010 2011 2012
Transmission Wheeling Capacity (MW)
Transmission Wheeling Capacity (MW)
FEDERAL MINISTRY OF POWER
NIPP TCN TOTAL
58
Summary of deliverables of completed
Transmission line Projects from 2011 to date
FEDERAL MINISTRY OF POWER
Substation
capacity (MVA)
Transmission
line coverage
(Km.)
850 3,220 MVA
780.6 1,045.6 Km
2,370
274
FEDERAL MINISTRY OF POWER
Power Distribution Capacity at
33/11kV (MVA)
Abuja: 568 633 Benin: 529 625 Eko: 844 1019 Enugu: 668 757 Ibadan: 960 1057 Ikeja: 935 1058 Jos: 397 448 Kaduna: 368 390 Kano: 397 483 P/H: 550 681 Yola: 144 174
Disco YR 2011
Total 6,360 7,325
YR 2012
MVA MVA
59
Key Output/Achievements.
Distribution
FEDERAL MINISTRY OF POWER
FEDERAL MINISTRY OF POWER 60
8
16
12
Average no of hours of power availability per day
2012 2011 2010
Average No of Hours of Power availability per day
FEDERAL MINISTRY OF POWER
Transmission
Distribution
▪ 5515MW
▪ 12%
▪ 6360 MW
▪ N151 Billion
▪ 6870MW
▪ 12%
▪ 7325 MW
▪ N189 Billion
Generation ▪ 9,097MW ▪ 5,563MW ▪ 4,089 MW ▪ 27,692MWH
▪ 9,920MW ▪ 6,522MW ▪ 4,517 MW ▪ 29,196MWH
▪ Installed Capacity ▪ Available Capacity ▪ Record Peak Generation ▪ Average Energy Delivered
▪ Transmission capacity (nominal)
▪ Technical losses
▪ Distribution capacity (nominal)
▪ Total Revenue Collection from the Market
Sector
Reforms
• All power reform institutions are established and in operation
• FGN/Labour signed agreement and its implementation is at advanced stage
• Privatization of 10 DisCos and 5 GenCos at advanced stage
• TCN management has been handed over to Management Contractors
(Manitoba of Canada) and TCN Board Inaugurated.
Target Metric 2011 May, 2013
61
Key Output/Achievements
FEDERAL MINISTRY OF POWER
FEDERAL MINISTRY OF POWER
Projection for 2013 and beyond
62 FEDERAL MINISTRY OF POWER
FEDERAL MINISTRY OF POWER
Going forward, the Ministry will pursue vigorously the following:
• Restructuring of Ministry of Power and its Agencies to cope with the evolving role in a privatised environment.
• Private Investment - including Foreign Direct Investments (FDI) in
the Power sector (IPPs, distribution, renewable energy & capacity building)
• Transmission Grid Expansion (Super Grid)
• Develop framework for alternative funding of transmission projects that will allow recovery of investments.
• Renewable Energy Resource Development .
• Electricity Market Development.
• Effective Monitoring & Evaluation.
Focus in 2013 and beyond
FEDERAL MINISTRY OF POWER
FEDERAL MINISTRY OF POWER
• Conclusion of labour-related issues. • Develop Local Content framework in the power sector.
• Promoting Energy Efficiency and Conservation.
• Collaborate with other agencies to check vandalisation of
power infrastructure.
• Improving rural access to electricity.
• Divestment of NIPP sales now at bidding stage (EoI bid submission closed July 19, 2013).
• Conclude privatisation process by the end of 2013.
Focus in 2013 and beyond contd.
FEDERAL MINISTRY OF POWER
FEDERAL MINISTRY OF POWER
Focus in 2013 and beyond contd.
• Development of the major coal fields as this will contribute between 3000 - 4000 MW power to the National grid towards improving energy mix and security of supply when implemented.
• Establishment of National Council on Power to harmonize the activities of different
players: Federal Government, State Governments, Local Governments etc. for effective coordination of efforts in the Power Sector.
• The Ministry will leverage on the abundant Renewable Energy sources in the country which are environmentally friendly to increase power generation and guarantee security of supply.
• Graduate Trainee programme aimed at producing personnel equipped with the basic skills required in the Power Sector.
• The Ministry will consolidate the gains in the previous years performance and improve availability of power supply between 16 – 24 hours per day for Nigerians.
FEDERAL MINISTRY OF POWER
FEDERAL MINISTRY OF POWER
Future Plan for Transmission Expansion
(330kV and Super Grid Networks)
ONITSHA
KAINJI
JEBBA/GS
JEBBA/TS
SHIRORO
AJAOKUTA
Abeokuta
Ikeja
Akure
Benin
Asaba
Port Harcourt
Owerri
Uyo
ALAGBADO
Birnin Kebbi
Minna
Kaduna
Abuja
Jos
Bauchi
Gombe
Damaturu
Maiduguri Kano
IIorin
Ado Ekiti
Lokoja
Lafia
Makurdi
MAKURDI
Enugu Akwa
Umuahia
Ibadan
Sokoto
Gusau
Katsina
Hadejia
Jalingo
Yola
Abakaliki
Calabar
JIGAWA
KANO
KATSINA
SOKOTO
ZAMFARA
KEBBI
KWARA
KADUNA
ABUJA
NIGER
NASSARAWA
TARABA
YOBE
PLATEAU
BENUE
EBONYI
CROSS RIVER
AN AMBRA
OSUN
BAYELSA
KOGI
EDO
ABIA
RIVERS DELTA
ONDO
OYO
ENUGU
IMO
ADAMAWA
BORNO
GOMBE
BAUCHI
EKITI
LAGOS
AKWA IBOM
ATLANTIC OCEAN
NIGER
REPUBLIC
OF BENIN
REPUBLIC
OF CAMEROON
REPUBLIC
OF
CHAD
TRANSMISSION LINE LEGEND
BULK SUPPLY POINT
HYDROELECTRIC POWER STATION
THERMAL POWER STATIONS
330 kV
H
SAPELE P/ST.
DELTA POWER ST.
OGUN
Osogbo
EGBIN P/ST.
NIGERIA
Potiskum
Niamey
132 kV
2
3
2
3
4
2
2
Aliade
Mambila
Bali
2
AFAM POWER ST.
2
2
330kV LINES – MULTIPLE CIRCUITS
330kV LINES - EXISTING
2
2
2005 : new
2
2015 : new
2015 : new
2015 : new
2015 :
3rd Circuit
2010 : new
2015 : new
2010: new
2
2
4 2015 : new
SAPELE
P/ST.
Okitipupa
Geregu
2015 : 2nd Circuit
Agip
Zaria
2015 : new
2015 : new
2015 : new
2015 : new
700kV LINES – SUPER GRID
700 / 330kV SUBSTATION
Mambila Hydro
66 FEDERAL MINISTRY OF POWER
FEDERAL MINISTRY OF POWER
•General Electric
•Siemens AG
•Daewoo E&C
•Electrobras
•EDF/ETDE
•Power China Corp.
Investors from all over the world have shown commitment and keen interest in Nigeria’s Power sector owing to the clearly defined programme set out by its government
-Asia (China, India, South Korea) -Europe (Germany, Nordic Countries, UK) -North America (United States, Canada) -Africa (South Africa) -South America (Brazil)
These companies have all signed Memorandum of
Understanding with the Nigerian Government to support
Power Projects with a new approach of providing equity in
the investment
Focus on Partnerships & Investment
Activities in 2013
67 FEDERAL MINISTRY OF POWER
FEDERAL MINISTRY OF POWER 68
Conclusion
The Power Sector has recorded appreciable improvement in power delivery in the period under review despite daunting challenges. The Ministry will intensify effort in the implementation of the Roadmap and will ensure completion of key projects/programmes with renewed vigour in 2013 and beyond. Consequently, we seek continuous support and understanding from our numerous stakeholders. The Ministry is committed to ensuring that improved service delivery level is maintained during and after the transition to private ownership of the GenCos and DisCos. The Ministry wishes to express its profound gratitude to the Hon. Minister of Petroleum Resources for working assiduously to provide the thermal plants with adequate gas We also thank the Hon. Minister of Information for providing the platform to present our sectoral achievements over the past two years. The Power Sector revolution will unleash Nigeria into her new season of peace, progress, prosperity and development.
FEDERAL MINISTRY OF POWER
FEDERAL MINISTRY OF POWER
Lighting up
Nigeria 24/7
Thank You
69 FEDERAL MINISTRY OF POWER