+ All Categories
Home > Documents > A. Siemko and N. Catalan Lasheras Insulation vacuum and beam vacuum overpressure release – V....

A. Siemko and N. Catalan Lasheras Insulation vacuum and beam vacuum overpressure release – V....

Date post: 03-Jan-2016
Category:
Upload: tracey-goodwin
View: 217 times
Download: 0 times
Share this document with a friend
Popular Tags:
26
SESSION 4 STRATEGY FOR CONSOLIDATION TO AVOID INCIDENT AND LIMIT COLLATERAL DAMAGE A. Siemko and N. Catalan Lasheras Insulation vacuum and beam vacuum overpressure release – V. Parma Bus bar joints stability and protection – A. Verweij Improved anchoring of SSS with vacuum barrier to avoid displacement – O. Capatina QPS Upgrade and Re-commissioning– R. Denz Risk Analysis for the Different Consolidation Proposals – J. Strait
Transcript
Page 1: A. Siemko and N. Catalan Lasheras Insulation vacuum and beam vacuum overpressure release – V. Parma Bus bar joints stability and protection – A. Verweij.

SESSION 4STRATEGY FOR CONSOLIDATION TO

AVOID INCIDENT AND LIMIT COLLATERAL DAMAGE

A. Siemko and N. Catalan Lasheras

Insulation vacuum and beam vacuum overpressure release – V. Parma

Bus bar joints stability and protection – A. Verweij

Improved anchoring of SSS with vacuum barrier to avoid displacement – O. Capatina

QPS Upgrade and Re-commissioning– R. Denz

Risk Analysis for the Different Consolidation Proposals – J. Strait

Page 2: A. Siemko and N. Catalan Lasheras Insulation vacuum and beam vacuum overpressure release – V. Parma Bus bar joints stability and protection – A. Verweij.

Insulation vacuum and beam vacuum overpressure releaseV. Parma

Page 3: A. Siemko and N. Catalan Lasheras Insulation vacuum and beam vacuum overpressure release – V. Parma Bus bar joints stability and protection – A. Verweij.

The problem Insufficient pressure relief devices

in the current cryostats Vacuum vessel and vacuum barrier

designed to keep internal pressure ≤ 1.5 bars, for a helium release with mass flow ≤ 2 kg/s

Pressure estimated to 7 bars on September 19th. Peak mass flow 20kg/s.

MCI could create a helium mass flow of 40kg/s

MCI ?

Page 4: A. Siemko and N. Catalan Lasheras Insulation vacuum and beam vacuum overpressure release – V. Parma Bus bar joints stability and protection – A. Verweij.

The solution (A)

Use all existing ports as pressure relief ports BPM, vacuum and cryo-instrumentation ports in the

SSS x10 cross section Maximum pressure reduced to about 3 bars Vacuum barrier and cold posts still designed

for 1.5 bars but may resist 3 bars Critical now the floor and jack fixations Pressure relief spring tested Can be implemented in cold sectors

Page 5: A. Siemko and N. Catalan Lasheras Insulation vacuum and beam vacuum overpressure release – V. Parma Bus bar joints stability and protection – A. Verweij.

The solution (B) Adding new DN200 relief devices in dipoles

x33 cross section Maximum pressure below 1.5 bars. All other systems

are now conform Special cases in the mid-arc and DS Studied and feasible Can only be implemented in warm sectors Implementation end of week 14 for four

warm sectors

Page 6: A. Siemko and N. Catalan Lasheras Insulation vacuum and beam vacuum overpressure release – V. Parma Bus bar joints stability and protection – A. Verweij.

Pending issues

Testing vacuum barriers and cold posts Stand-alone magnets and inner triplets Beam insulation vacuum

From the discussion DFBs Derogations from safety in case of partial

solution

Page 7: A. Siemko and N. Catalan Lasheras Insulation vacuum and beam vacuum overpressure release – V. Parma Bus bar joints stability and protection – A. Verweij.

Improved anchoring of SSS with vacuum barrier to avoid displacementO. Capatina

Page 8: A. Siemko and N. Catalan Lasheras Insulation vacuum and beam vacuum overpressure release – V. Parma Bus bar joints stability and protection – A. Verweij.

The problem

Failure of some supports of SSS in sector 3-4 due to longitudinal loads on September 19th.

If internal pressure above 1.5 bars, support system is insufficient. Nominal operation for supporting system 0.1MPa,

exceptionally 0.15MPa (80kN, exceptionally 120kN)

Failure limit 150kN Coherent system

vacuum barrier/cold post/jacks/floor New requirements 240kN

Page 9: A. Siemko and N. Catalan Lasheras Insulation vacuum and beam vacuum overpressure release – V. Parma Bus bar joints stability and protection – A. Verweij.

The solution Anchoring of the jacks Tested in the tunnel floor(SX4) up to 380kN Drilling authorised without liquid helium Installation ok with liquid helium 2 weeks per sector plus alignment. Total of 25

days. 867.000 CHF for all 8 sectors.

Page 10: A. Siemko and N. Catalan Lasheras Insulation vacuum and beam vacuum overpressure release – V. Parma Bus bar joints stability and protection – A. Verweij.

Pending issues

Basically the same as in previous presentation

DFB’s stand alones, inner triplet Testing of the vacuum barrier and cold

post

From the discussion Do we need this if DN200 is implemented

in all magnets? 1.5 bars could be marginal for the current solution

Page 11: A. Siemko and N. Catalan Lasheras Insulation vacuum and beam vacuum overpressure release – V. Parma Bus bar joints stability and protection – A. Verweij.

Bus bar joints stability and protectionA. Verweij

Page 12: A. Siemko and N. Catalan Lasheras Insulation vacuum and beam vacuum overpressure release – V. Parma Bus bar joints stability and protection – A. Verweij.

The problem An interconnection opened on September

19th. Probably a bad splice. Two potential

scenarios Bad electrical and thermal contact

Between joint, u-shape and wedge Between u-shape and wedge and bus-bar

(longitudinally) Resistive cable plus longitudinal discontinuity

Page 13: A. Siemko and N. Catalan Lasheras Insulation vacuum and beam vacuum overpressure release – V. Parma Bus bar joints stability and protection – A. Verweij.

The problem Fast localised thermal runaway

Stable resistive heating below 7.5kA. Slow voltage increase much below QPS threshold (mV)

Fast normal zone development Temperature increases rapidly above melting

point

0.01

0.1

1

10

100

1000

0 1000 2000 3000 4000 5000 6000 7000 8000 9000

Current [A]

Length normal zone [m]

Power [W]

T_max [K]

Voltage [mV]

Fast localised thermal runaway at T_max=30 K, P=70 W, V=10 mV, z_norm=0.3 m

V=0.3 mVStart normal zone

P=11 W@7 kA

Page 14: A. Siemko and N. Catalan Lasheras Insulation vacuum and beam vacuum overpressure release – V. Parma Bus bar joints stability and protection – A. Verweij.

The solution QPS threshold of 0.3 mV. Integration time 10s

Detects any resistance larger than 25 nOhms up to nominal current

Avoid bad splices Excessive longitudinal gap, Lack of solder Clamping

0

2000

4000

6000

8000

10000

12000

10 100 1000

R_joint [nOhm]

I_ru

n [

A]

RRR=240, weak thermal contact (Incident)

RRR=120, no thermal contact (worst case)

Worst case -500 A

50 Watt

10 Watt

0.3 mV

1 mV

0.5 mV

25 nOhm

Page 15: A. Siemko and N. Catalan Lasheras Insulation vacuum and beam vacuum overpressure release – V. Parma Bus bar joints stability and protection – A. Verweij.

Pending issues

QPS system cannot protect the circuit in case of a sudden mechanical opening of the joint

Other bus-bar types (6 kA, pigtails...)

From the discussion Operability Clamping

Page 16: A. Siemko and N. Catalan Lasheras Insulation vacuum and beam vacuum overpressure release – V. Parma Bus bar joints stability and protection – A. Verweij.

QPS Upgrade and Re-commissioningR. Denz

Page 17: A. Siemko and N. Catalan Lasheras Insulation vacuum and beam vacuum overpressure release – V. Parma Bus bar joints stability and protection – A. Verweij.

The problem

Symmetric quenches between apertures went unnoticed for more than half a second

Local bus-bar protection capable of detecting bad splices Threshold 0.3mV, integration time 10s

Page 18: A. Siemko and N. Catalan Lasheras Insulation vacuum and beam vacuum overpressure release – V. Parma Bus bar joints stability and protection – A. Verweij.

The solution

Detection of symmetric quenches: Compare consecutive magnets New card design Not in the baseline for 2009 before Chamonix

mtg. (E<5TeV) Splice detection

Uses existing voltage taps in the diode Uses protection cards for HTS leads Regular scans during operation

Both solutions require additional cabling (240Km)

Page 19: A. Siemko and N. Catalan Lasheras Insulation vacuum and beam vacuum overpressure release – V. Parma Bus bar joints stability and protection – A. Verweij.

Pending issues

Radiation hardness of the electronics Verifying the cabling Commissioning of the new system In the critical path

From the discussion Beam induced symmetric quenches Spurious triggers

Page 20: A. Siemko and N. Catalan Lasheras Insulation vacuum and beam vacuum overpressure release – V. Parma Bus bar joints stability and protection – A. Verweij.

Risk Analysis for the Different Consolidation ProposalsJ. Strait

Page 21: A. Siemko and N. Catalan Lasheras Insulation vacuum and beam vacuum overpressure release – V. Parma Bus bar joints stability and protection – A. Verweij.

Solutions planned

Improved QPS system for detection of bad splices in bus-bars

Added procedures Calorimetric measurements Snapshot on individual magnets Snapshot in bus-bars

Avoid collateral damage Additional DN200 ports in dipoles in half of the

machine Additional pressure relief ports in SSS in all LHC Improved anchoring for SSS with vacuum barrier

Page 22: A. Siemko and N. Catalan Lasheras Insulation vacuum and beam vacuum overpressure release – V. Parma Bus bar joints stability and protection – A. Verweij.

Solutions recommended

Pressure relief in vacuum system Improve pressure relief in DFBs, stand

alone magnets and inner triplet Anchoring of the DFBA supports Intelligent reaction to quenches in bus-

bars and other sensible equipment opening of the quench release valves at a

lower pressure Firing more quench heaters to speed up

current decay

Page 23: A. Siemko and N. Catalan Lasheras Insulation vacuum and beam vacuum overpressure release – V. Parma Bus bar joints stability and protection – A. Verweij.

Scenarios

Add DN200 ports in all dipoles in the machine (warm-up other 4 sectors) Not recommended if prevents running this

year Add burst disks in the vacuum system

Recommended at least for warm sectors Adding DN200 in DFB Recommended at least for warm sectors

Intelligent reaction to quenches Should be studied carefully not mandatory

Page 24: A. Siemko and N. Catalan Lasheras Insulation vacuum and beam vacuum overpressure release – V. Parma Bus bar joints stability and protection – A. Verweij.

Scenarios

What if additional bad splices in the magnets are found?

When machine is cold Other mitigation measures will minimize the

risk of an accident Limited damage to one or two dipoles Leave it and change it in the next shutdown

By analysis of the already taken data (snapshots and cold tests) Change the magnet as soon as possible

Page 25: A. Siemko and N. Catalan Lasheras Insulation vacuum and beam vacuum overpressure release – V. Parma Bus bar joints stability and protection – A. Verweij.

Scenarios

What if additional splices are found in the bus-bars?

It will be detected when cold Warm up and repair the splices

What energy should we run in 20095 +5 TeV is achievable, safe AND useful

Page 26: A. Siemko and N. Catalan Lasheras Insulation vacuum and beam vacuum overpressure release – V. Parma Bus bar joints stability and protection – A. Verweij.

Conclusions

The incident in sector 34 revealed needs of enhanced: Early spotting of possible origins of faults Enhanced prevention of initial faults Mitigation of consequences

Means were developed and implementation scenarios proposed to a happy landing wherever we're falling to with the electrical splices of magnet circuits

Thanks to all speakers


Recommended