The presentation is part of Ace the PMP Exam, available on the iBookstore. Go to http://Aceitguides.com for more information. The critical path is the longest path in a network diagram, and therefore determines the shortest time that it will take to complete a project. This presentation illustrates a simple method to determine the critical path. The following example demonstrates the concept and will enable you to quickly answer some of the simpler questions on the PMP® exam.
Popular Tags:
12
The Critical Path Method This presentation is part of Ace the PMP Exam
Transcript
Page 1: A simple method to determine the Critical Path

The Critical Path

Method

This presentation is part ofAce the PMP Exam

Page 2: A simple method to determine the Critical Path

A Simple Method to Determine the Critical Path

The critical path is the longest path in a network diagram, and therefore determines the shortest time that it will take to complete a project.

This presentation illustrates a simple method to determine the critical path.

Page 3: A simple method to determine the Critical Path

A Simple Method to Determine the Critical Path

To use the simple method you look at all the different paths in the schedule, add the durations, and determine which is the longest.

The following example demonstrates the concept and will enable you to quickly answer some of the simpler questions on the PMP® exam.

Page 4: A simple method to determine the Critical Path

A Simple Method to Determine the Critical Path

Touch the screen to continue

Page 5: A simple method to determine the Critical Path

A2A2

D3D3

F3F3

B8B8

C4C4

E2E2

StartStart EndEnd

There are four possible paths in this network diagram: A D F➞ ➞ , B F➞ , B E➞ , and C E➞ .We will follow each path to determine its length.

Touch the screen to continue

A Simple Method to Determine the Critical Path

Page 6: A simple method to determine the Critical Path

Path 1: A D F = 2 + 3 + 3 = 8➞ ➞

A2A2

D3D3

F3F3

B8B8

C4C4

E2E2

StartStart EndEnd

A2A2

D3D3

F3F3

Touch the screen to continue

There are four possible paths in this network diagram: A D F➞ ➞ , B F➞ , B E➞ , and C E➞ .We will follow each path to determine its length.

Page 7: A simple method to determine the Critical Path

Path 2: B F = 8 + 3 = 11➞Path 1: A D F = 2 + 3 + 3 = 8➞ ➞

A2A2

D3D3

F3F3

B8B8

C4C4

E2E2

StartStart EndEnd

F3F3

B8B8

Touch the screen to continue

Path 1: A D F = 2 + 3 + 3 = 8➞ ➞

A2A2

D3D3

F3F3

Page 8: A simple method to determine the Critical Path

Path 2: B F = 8 + 3 = 11➞Path 3: B E = 8 + 2 = 10➞

Path 1: A D F = 2 + 3 + 3 = 8➞ ➞

A2A2

D3D3

F3F3

B8B8

C4C4

E2E2

StartStart EndEnd

B8B8

E2E2

Touch the screen to continue

F3F3

B8B8

Path 2: B F = 8 + 3 = 11➞

Page 9: A simple method to determine the Critical Path

Path 1: A D F = 2 + 3 + 3 = 8➞ ➞Path 2: B F = 8 + 3 = 11➞Path 3: B E = 8 + 2 = 10➞Path 4: C E = 4 + 2 = 6➞

A2A2

D3D3

F3F3

B8B8

C4C4

E2E2

StartStart EndEnd

C4C4

E2E2

Touch the screen to continue

B8B8

E2E2

Path 3: B E = 8 + 2 = 10➞

Page 10: A simple method to determine the Critical Path

Path 2: B F = 8 + 3 = 11➞

A2A2

D3D3

F3F3

B8B8

C4C4

E2E2

StartStart EndEnd

Path 3: B E = 8 + 2 = 10➞Path 2: B F = 8 + 3 = 11 (the longest path)➞

Path 4: C E = 4 + 2 = 6➞

Path 1: A D F = 2 + 3 + 3 = 8➞ ➞

A2A2

D3D3

C4C4

E2E2

StartStart EndEnd

F3F3

B8B8

End

C4C4

E2E2

Path 4: C E = 4 + 2 = 6➞

Page 11: A simple method to determine the Critical Path

A Simple Method to Determine the Critical Path

That was a simple method of determining the critical path in a network diagram.

For a systematic way of determining the critical path, see the Forward and Backward Pass video in this series.

Page 12: A simple method to determine the Critical Path

The Critical Path

Method

This presentation is part ofAce the PMP Exam