A System Dynamic Simulation Model in the System Support Organization of a Speedy
Printing Company
(CND/ABC/Powersim Project)
Wei-Chen Chung
Abstract
The Capstone Project is based on a group model building project. Group members came from aprinting/coping company (ABC), the college of Notre Dame, and Powersim, Incorporated. Thegroup analyzed a speedy printing company (ABC Printing Company) using system dynamicmodeling. In this report, I will discuss the methods and solutions that were developed by theABC/CND/Powersim project team.
This project focused on sales and production problems of the ABC printing company. The projectteam under the guidance of the Powersim representative used the concept of system thinking andthe skill of systems dynamic modeling to produce a computer simulation. The simulation softwarecan be used to show forecasting curves of the companys profits and sales peoples revenue overthe next five years.
A high-level user interface was designed by this author to create a "user friendly" environment forworking with the simulation. CND students and the ABC printing company owner can now use thesoftware to successfully explore the outcomes of different business scenarios. The simulation anduser interface were evaluated by MSSM students and the owner of the ABC Printing Company.
Introduction
In the real world, structures of an organization have become complex. Therefore, we need tounderstand whole systems of the organization that can help us to make decisions for theorganization. In this project, I will discuss an optimized way to understand an organization. When Itook the Master of Science in Systems Management program, I tried to explore methodologies thatcould help me to understand systems management. When I took my second course, I made aproject about air traffic controlling using the concept of system dynamics which was a very usefulorganization learning concept for me. I was an air traffic controller during my military service inTaiwan. I saw many air near-collision events that were caused by poor management. If the concept
of system dynamics can be applied in air traffic management, many high-risk events would beavoided. Of course, system dynamics can support different business decisions.
I began participation in the "ABC/CND/Powersim" group project with Dr. Sylvia Shafto beginningin the spring, 1998. The project needed to use the concept of system dynamics to analyze thebusiness decisions of ABC Printing Company. In this group project, I understood more ideas aboutsystem dynamics and learned the skill of using the system simulation software.
7/31/2019 A System Dynamic Simulation Model
3/62
The purpose of the ABC/CND/Powersim project is to develop solutions that support ABC PrintingCompany using system dynamics model building. I will use the following steps to provide mycapstone project:
I. Project group background, meetings, and workshops
II. Project problemsIII. Project model-building process
I. Project group background, meetings, and workshops
The ABC/CND/Powersim project team includes three groups: the College of Notre Dame (CND),ABC printing company, and Powersim, Incorporated. The College of Notre Dame was partneringwith ABC printing company and Powersim Corporation to develop a computer modelingsimulation based on system dynamics to be used by CND's MBA and MSSM graduate programs.
The development of this real-world tool allows CND students to simulate outcomes of businessscenarios. By moving to implement such a technology with the graduate program, CND can furthersupport high technology-based educational tools in its program. ABC/CND/Powersim project teamused two meetings to get the project development started. I also attended a two-day workshop tounderstand Powersim simulation software.
The first meeting (August 13th, 1998)
In the first meeting of ABC/CND/Powersim, we developed our project criteria:
1. Model is to be used in educating students in CND's MBA and MSSM courses
2. Model is to be used in limited capacity by ABC Printing company3. Model must be dynamic, including circumstances played out over time
According to the project criteria, we decided on the project concepts and problem areas to focus onfor the ABC/CND/Powersim project:
1. Staffing -- support the company through its workforce/staffing decisions. This mayinclude analysis regarding sales per employee, retention, motivation and turnover.We may also develop the idea of sales force vs. production along with cross-functional work teams.
2. Outsourcing -- enable the company to maximize its potential through outsourcing.
The second meeting (August 28th, 1998)
In the second meeting of ABC/CND/Powersim, we studied the framing question: What are the keyissues facing ABC Printing company in managing sales and production staff over the next 5 years?The owner of the ABC Printing Company supplied the group with an excellent set of past five-yearbusiness data for the company. This provided the real-word basis for the model and simulation.
7/31/2019 A System Dynamic Simulation Model
4/62
We figured out the significant issues (Appendix A). According to the issues for ABC Company,we have developed the model for the company. In this paper, I will describe the details of themodel structure.
Powersim Workshop (September 14 & 15th at Crown Plaza, S.F.)
ABC/CND/Powersim project uses Powersim to develop the system dynamic simulation model. Forthis reason, I attended Powersim "Introduction to Business Modeling and Simulation withPowersim Constructor" workshop on September 14 and 15th at Crown Plaza, San Francisco. Thefollowing are the features of the workshop.
1. Focus on business problems quickly using simulation tools2. Analyze and communicate solutions and strategies more effectively using models3. Analyze possible solutions by constructing a model and experimenting with some
components: inventory control, product life cycle planning, capacity planning, humanresource and finance.
In the workshop, I learned the fundamentals of building problem-solving models and simulations.With the help of presentations, hands-on workshops, a case study and a step-by-step developmentprocess, I developed business models and simulations that could solve real problems. After theworkshop, I understood Powersim. Powersim is a simulation software, and it is similar to iThinkand Versim. Powersim is a Windows based software package for creating system dynamics modelsand custom-designed business simulators. Powersim can be used as the basis for creatingmanagement flight simulators which permit interactive experimentation with such issues ascorporate strategy, operations, marketing, competitive analysis, and decision-making.
Powersim can be used to create simulations across a wide spectrum of industries and business
areas, such as:
1. Strategic planning2. Resource management3. Crisis planning and management, and process reengineering.
II. Project problems
The ABC/CND/Powersim project needs to solve sales and production problems. There are threemain problems: "Strengths", "Weaknesses", and "Issues facing companys business future". In"Strengths", the project needs to identify the companys acquisitions and growth. The results will
give the decision-maker information to make decisions and take actions easily. In "Weaknesses",the project needs to recognize the companys problems. The "weaknesses" questions include "highlabor cost" and "problems with staff balance department by department". In "Issues facingcompanys business future", there are three challenges that need to be faced.
1. What will be the companys profit during the next five years?2. Will products of the company become profitable during the next five years?3. How much sales revenue will be received during next five years?
7/31/2019 A System Dynamic Simulation Model
5/62
The final solutions would focus on "Sales revenue", "Profit", and "Profitability" for ABC PrintingCompany. In the next part of this paper, I will analyze the processes that were used to develop theproject by the ABC/CND/Powersim project group.
III. Project model-building process
"Group model-building is an approach which involves the client consensus and createscommitment with the outcomes" (Vennix, 1996. p.110). I will use the following stages to providethe model-building process of ABC/CND/Poersim project:
1. Problem identification and model purpose2. System thinking and System dynamics3. Model formulation and analysis4. Simulation Application Software for ABC/CND/Powersim5. Evaluation and Feedback
1. Problem identification and model purpose
I think that a group model-builder feels sufficiently confident to start with problem identification.ABC/CND/Powersim developed the problem identification and model purpose in our first meetingon August 13th, 1998. I have described the problem identification and model purpose in the part of"Project group background, sessions, and workshops".
After defining the problem identification during the second meeting, the participants ofABC/CND/Powersim were invited to write down variables in silence. Each variable was written onmagnetic hexagon (Figure 1) and put on a metal board.
7/31/2019 A System Dynamic Simulation Model
6/62
Figure 1. Use of Hexagons in ABC/CND/Powersim to Group Model-building.
There are nine key areas that are included the
ABC/CND/Powersim model.
Management:
7/31/2019 A System Dynamic Simulation Model
7/62
Production:
Industry Changes:
7/31/2019 A System Dynamic Simulation Model
8/62
Production Cycle Time:
Equipment Costs & Purchase Decisions:
7/31/2019 A System Dynamic Simulation Model
9/62
Physical plant & facilities:
Production Staff:
7/31/2019 A System Dynamic Simulation Model
10/62
Sales Force:
7/31/2019 A System Dynamic Simulation Model
11/62
Customers Relations:
2. System thinking and System dynamics
The issue maps (Hexagons) tend to point to the interconnectedness of events. The issue maps aretranslated into a causal loop diagram (Figure 2). This implies the causal relations among elements.The interconnectedness events of ABC printing company are a complex system (Figure 1).
7/31/2019 A System Dynamic Simulation Model
12/62
System dynamics has its fundamentals in the field of systems thinking, and it was founded in 1956by MIT professor Jay Forrester (Appendix C). I learned the concept of systems thinking in theorganizational Theory with Mr. Moran. When I read the book "The Fifth Discipline" (Senge, 1994)that was written by Peter Senge, I had gotten the clear concept about systems thinking. "Systemsthinking is a discipline for seeing the 'structures' that underlie complex situations, and fordiscerning high from low leverage change" (Senge, 1994 p.69). Systems thinking is powerfulbecause it can help people to see their own mental models and how those models color theirperception of the real world.
The situations of the whole system in ABC Company are changing over time, and the system has a
dynamic behavior that is a consequence of its structure. We have talked of the system elements andtheir interconnections.
Senge, talks about two types of complexity. They are detail complexity and dynamic complexity.Detail complexity is associated with systems that have many component parts. Dynamiccomplexity is associated with systems that have cause and effect separated by time and space.Dynamic complexity determines system's behavior over time.
7/31/2019 A System Dynamic Simulation Model
13/62
I learned the concept of systems dynamics in my second course of MSSM, Deterministic Modelsin Decision Making with Dr. Sylvia Shafto. I am very interested in system dynamics. I think themain concept of systems dynamics is to model system structure and behavior using the principlesof feedback, dynamics and simulation. The following characteristics describe uses of systemdynamics modeling:
1. Search for useful solutions for real world problems.
2. Use computer simulation models to improve and understand such systems.
3. Base the simulation models on mental models,
qualitative knowledge and numerical information.
1. Seek improved methods to translate simulation
results into actual implementation.
According to Forrester, system dynamics is a theory of the behavior and structure of complexsystems. The structure of system dynamics has four hierarchical levels:
1. the closed boundary2. the feedback loop as the basic system component3. levels and rates4. goals, observed conditions, discrepancy between goals and observed conditions,
and desired action.
3. Model formulation and analysis
The basic ABC Printing Company model was developed in a group modeling session. ThePowersim representative led the group through the process of specifying the elements of the modeland the algebraic relations. The structure of ABC/CND/Powersim model is a very complexorganization. I use a mathematical method to evaluate the system dynamics of this model. I includethe whole ABC/CND/Powersim model that is a mathematical equation (Appendix E). It is acombination of many differential equations. The structure of the model includes three mainsections, and they are "Production", "Sales", and "Equipment". Powersim's system dynamicsimulation software shows the solutions of the structure.
I compare the equations, flow-stock diagram (Appendix D) and causal loop (Appendix C) diagramin the following.
"Production" section
Flow-stock diagram:
7/31/2019 A System Dynamic Simulation Model
14/62
Figure 3. flow-stock diagram of "PoductionStaff".
Equation:
ProductionStaff = -(ProductionStaffAttrition)dt
+(ProductionStaffHires)dt
ProductionStaffAttrition = ProductionStaff *ProductionStaffAttritionRate
ProductionStaffHires = MAX(0,(DesiredWorkforce-ProductionStaff+(ProductionStaffAttrition*TimeToHireProductionStaff))/(TimeToHireProductionStaff+TimeToMakeStaffingDecisions))
Causal loop diagram:
Figure 4. causal loop diagram of "PoductionStaff".
The structure is a "Shifting the Burden" archetype (Senge, 1994). A Shifting the Burden structureis composed of two balancing loops and a reinforcing loop. Both structures end up moving thesystem in a direction other than the one desired. The graph shows the effect on Production Staff ofthis structure in the model is:
7/31/2019 A System Dynamic Simulation Model
15/62
Figure 5. Curves of "PoductionStaff".
This structure also affects two results "TotalProductionStaff" and "ProductionStaffCosta". Theflow-stock diagram and equation of "TotalProductionStaff" is:
Figure 6. Flow-stock diagram of "TotalProductionStaff".
Equation:
TotalProductionStaff = ARRSUM(ProductionStaff)
The ARRSUM function computes the sum of the value of the elements in an array("ProductionStaff").
The result of the curve for "TotalProductionStaff" is (Figure 7):
7/31/2019 A System Dynamic Simulation Model
16/62
Figure 7. The curve of "TotalProductionStaff"
The flow-stock diagram (Figure 8)and equation of "ProductionStaffCosta" is:
Figure 8. The flow-stock of " ProductionStaffCosta"
ProductionStaffCosts = ProductionStaff(a)*(AvgProductionSalary(a)+ProductionTrainingCosts)
where a=ProductionGroups
The result of the curve for " ProductionStaffCosts " (Figure 9) is:
7/31/2019 A System Dynamic Simulation Model
17/62
Figure 9. Curve for "ProductionStaffCosts"
"Sales" section:
Flow-stock diagram (Figure 10):
Figure 10.
The flow-stock diagram of "Sales" section
The structure is also a "Shifting the Burden" archetype.
7/31/2019 A System Dynamic Simulation Model
18/62
Equation:
NumberOfSalesPeople = -dt*SalesPeopleAttrition
+dt*SalesHires
SalesPeopleAttrition = NumberOfSalesPeople*SalesforceAttritionRate
SalesHires = (DesiredSalesForce-NumberOfSalesPeople +SalesPeopleAttrition*TimeToHireSalesPeople))/TimeToHireSalesPeople
Causal loop diagram (Figure 11):
Figure 11. The causal loop diagram of "Sales"
The result of the curve for " NumberOfSalePeople "
(Figure12) is:
Figure 12. The curve of "NumberOfSalePeople
The output of this structure affects two results "SalesForceCosts" and "TotalSalesForceInvoices",and those equations reference Appendix E. Their curves are figure 13:
7/31/2019 A System Dynamic Simulation Model
19/62
Figure 13. The curves of "SalesForceCosts" and "TotalSalesForceInvoices"
"Equipment" section:
Flow-Stock Diagram:
Figure 14. The flow-stock diagram of "Equipment" section
There are two important equations in "Equipment" section, and they are "FacilitiesSize" and"EquipmentCapacity". "FacilitiesSize" is a "Reinforcing" structure, and "EquipmentCapacity" is a"Shifting the Burden" archetype.
Equation:
7/31/2019 A System Dynamic Simulation Model
20/62
(1) FacilitiesSize = +dt*ChangeInFacilitiesSize
FacilitiesSize = Facilities size initial is 2500
square feet.
(2) EquipmentCapacity = NeededCapacity*2
EquipmentCapacity = -dt*CapacityDepreciation +dt*NewCapacity
EquipmentCapacity = 128,000 copies per eight hour
day for four machines operating 50 weeks per day
time five days per week.
Causal Loop Diagram:
Figure 15. The causal loop diagram of "Equipment" section
The curve of "FacilitiesSize" is:
7/31/2019 A System Dynamic Simulation Model
21/62
Figure 16. The curve of " FacilitiesSize"
The value of "FacilitiesSize" is keeping 2,500 square feet.
The curve of "EquipmentCapacity" is:
Figure 17. The curve of "EquipmentCapacity"
Equipment costs "EquipmentCosts" is an output value that affects the profits and profitability inwhole model.
The equation of "EquipmentCosts" is:
EquipmentCosts = InitialEquipmentCosts/
INIT(EquipmentCapacity)*
EquipmentCapacity
The curve of "EquipmentCosts" is:
7/31/2019 A System Dynamic Simulation Model
22/62
Figure 18. The curve of "EquipmentCosts"
These three sections ("Production", "Sales" and "Equipment") are major key elements of themodel. Sales revenue, profitability, and profits and solutions that ABC/CND/Powersim project
group wants to get. I will describe the flow-stock diagrams, the equations, the causal loopdiagrams, and the curves of their solution in the following.
Flow-stock diagrams:
Figure 19. The flow-stock diagram of "SalesRevenue", "Profits", and "Profitability"
The equations:
SalesRevenue = AvgInvoice * TotalInvoices
Profits = SalesRevenue - TotalCosts
Profitability = Profits / SalesRevenue
7/31/2019 A System Dynamic Simulation Model
23/62
The causal loop diagram:
Figure 20. The causal loop diagram of "SalesRevenue", "Profits", and "Profitability"
The curves of "SalesRevenue", "Profits", and "Profitability":
Figure 21. The curves of "SalesRevenue", "Profits", and "Profitability"
If the growth rate of "SalesRevenue" is greater than the growth rate of "Profits", "Profitability"should decline. The curves of these components are the solutions that we want to get.
4. Simulation Application Software for ABC/CND/Powersim
The Powersim simulation application software allows the developer to design a "friendly"graphical user interface (GUI). This is a program interface that can be easily handled by users. I
will use the concepts of the two MSSM courses Decision Support System, and Person MachineFactors to provide the application software.
Decision Support System
The Powersim application software supports decision-makers of ABC printing company to maketheir decisions, and the application software is a very successful tool for developing a decisionsupport system.
7/31/2019 A System Dynamic Simulation Model
24/62
According to the generic framework of decision support system, a decision support system (DSS)can be defined in terms of four basic aspects:
1. A language system (LS)2. A presentation system (PS)
3. A knowledge system (KS)4. A problem-processing system (PPS) (p. 172 Holsapple, 1996)
ABC/CND/Powersim simulation application software is a simulation tool for ABC printingcompany that can forecast the company sales revenue, profits, and commercial profitability for thenext five years. The structure of the simulation application software is shown in the following:
Figure 22. The structure of ABC/CNS/Powersim DSS
ABC/CND/Powersim is a Rule-Oriented DSS.
1. LS: data input2. PS: Advice solution
(forecasting curves, time table)
3. KS: Flow-stock diagram (system dynamics language)4. PPS: System dynamics model
Structuredness: This application software is for multiple use.
Input: User can define data entry.
7/31/2019 A System Dynamic Simulation Model
25/62
Output: Curves, time table for analysis.
Feedback on output: Help user situation analysis
User Interface Design using Person Machine Factors:
I developed the high-level user interface for the ABC Printing Company simulation. Students andbusiness decision makers cannot interact easily with the modeling version of the simulation. So thePowersim software allows the developer to create a simpler, more easily used interface. ThePowersim simulation application software addresses the concerns of person machine factors fordesigning high-level user interface. It allows the developer to create Windows GUI, and eachfunction is based on object-oriented interface. The menu of the application software interface usesbuttons, and the buttons are three-dimensional. Users can easily select any window they want.Each button is contains text that easily identifies an action. The control is activated when "pressed"
by users.
The ACB/CND/Powersim simulation was constructed using combinations of colors in the softwareinterface that allows users to easily identify highlighted buttons in a window interface. We used theharmonious color combinations in the software interface.
The colors combination:
WindowsBackground colorsForeground colors
Menu White Gray
Help Teal White
Simulation White Non White
Input/Table White Black, Teal, Blue, Magenta
Other colors combinations reference Appendix F.
In the input window of the software, I used slider/bar to control each of the input variables. Userscan benefit from viewing the current value relative to range of all possible values. The output
results are used dynamic curves to display on the simulation window. Decision-makers (users) canquickly get the forecasting information for the next five years. The interfaces of theABC/CND/Powersim simulation are shown the following:
"Menu" and "Help" Windows
7/31/2019 A System Dynamic Simulation Model
26/62
Figure 23. "Menu" and "Help" Windows of ABC/CNS/Powersim software.
"Data Input" Window
Figure 24. "Data Input" Window of ABC/CNS/Powersim software.
7/31/2019 A System Dynamic Simulation Model
27/62
"Simulation" Window
Figure 25. "Simulation" Window of ABC/CNS/Powersim software.
"Table" Window
7/31/2019 A System Dynamic Simulation Model
28/62
Figure 26. "Table" Window of ABC/CNS/Powersim software.
"Causal Loop" Window
Figure 27. "Causal Loop" Window of ABC/CNS/Powersim software.
7/31/2019 A System Dynamic Simulation Model
29/62
"Model" Window
Figure 28. "Model" Window of ABC/CNS/Powersim software.
The simulation not only combines the concepts of
Decision Support Systems and Person Machine Factors, but uses the skill of software engineering.It is not only a case study, but is also a CASE (computer-aided software engineering) tool. Thisproject supports reengineering and enterprise level analysis techniques. Organizationalreengineering is the evaluation and redesign of ABC printing company's business processes, data,and technology. "The goals of reengineering are to achieve dramatic improvements in quality,service, speed, use of capital, and reduced costs" (Conger, 1994, p. 113). The following diagram isthe reengineering target for ABC/CND/Powersim project:
7/31/2019 A System Dynamic Simulation Model
30/62
The main sources of organization are people and information of ABC/CND/Powersim projectgroup. Data from ABC Printing Company is represented in the variables in the model. Technologyis the system dynamics concept and skill.
ABC printing company is a speedy growth organization, and CND uses system managementknowledge to develop a group model with Powersim business simulation software. The product ofABC/CND/Powersim group project is the user-friendly simulation application software.
5. Evaluation and Feedback
When ACB/CND/Powertsim simulation application software was almost done, I demonstrated theapplication software twice in the courses SY269 (Decision Support and Expert Systems) andSY221 (Deterministic Models in Decision-Maker) on February 27th and March 1st, 1999. I got verygood feedback from both two evaluations (ABC/CND/Powersim Evaluation form referenceAppendix G).
The summary of the first evaluation:
1. The software needs more factors/input.2. The model needs to be more realistic. Needs to have more functions (only five
functions) which the user can vary.3. Easy to understand the result.4. The workforce size can not be changed and should be adjustable.
7/31/2019 A System Dynamic Simulation Model
31/62
I got 80% negative feedback asking for improvements. I have updated some problems, and Dr.Sylvia Shafto gave me other opportunity to demonstrate the software. The following showsexample responses on the evaluation of the second model:
1. Software works well.
2. The model is excellent.3. Too complex.4. Good.5. The user interface is easier to use than Vensim.
Conclusion
ABC/CND/Powersim modeling project has applied the concept of system thinking and the skill ofsystem dynamics modeling to develop a group model. The whole project involved group modelbuilding. ABC/CND/Powersim project group identified the problems and model purpose, analyzedthe model formulation, developed simulation application software, and tested the software.
The user interface was improved based on the feedback from demonstrations. Base on thefeedback, the simulation application software has been updated.
System dynamics simulation model is a very useful and interesting concept for organizationlearning, and it combines system thinking and system dynamics. This idea not only supportsbusiness decisions, but also can be used in different areas. I believe system dynamics simulationwill be generally applied in the next century. For this reason, I have chosen the concept for mycapstone project.
Reference
Bailey, Robert W. (1996). Human Performance Engineering: Designing High Quality Professionalfor Computer Products, Application and System. Upper Saddle River, NJ: Prentice-Hall, Inc.
Byrkness, Arne-Helge (1996). Powersim Tutorial 1. Herndon, VA: Powersim Co.
Byrkness, Arne-Helge & Myrtveit,Magne (1996). Learning Dynamic Modeling. Herndon, VA:
Powersim Co.
Conger, Sue (1994). The New Software Engineering. Belmont, CA: International ThomsonPublishing.
Cover. Jennifer M. (1996). Introduction to System Dynamics. Herndon, VA: Powersim Co.
7/31/2019 A System Dynamic Simulation Model
32/62
Galitz, Wilbert O. (1997) Essential Guide to User Interface Design. New York: John Wiley &Sons, Inc.
Hannon, Bruce, & Ruth, Matthias. (1994). Dynamic Modeling. Urbana, IL: Springer-Verlag NewYork, Inc.
Holsapple, C., & Whinston, A. (1996). Decision support systems: A knowledge-based approach.San Francisco, CA: West Publishing Company.
McCleod, Raymond (1998). Management Information Systems. Seventh Edition. New York:Prentice Hall, Inc.
Senge, Peter (1994). The Fifth Discipline: The Art and Practice of the Learning Organization. NewYork: Doubleday.
Vennix, Jac A. M. (1996). Group Building: Facilitating Team Learning Using System Dynamics.
West Sussex, England: John Wiley & Sons Ltd.
7/31/2019 A System Dynamic Simulation Model
33/62
Appendix A
ABC/CND/Powersim
8/28/98 Meeting
The following were the significant issues identified by the group using the hexagons.
Management Number of decision makers
Internal communication efficiency
What is a good profit margin
Speed of decisions
Locus of decision making
Net profit (profitability)
Number of management layers
Production Number of jobs per day
Productivity and capacity utilization
Industry changes Jobs lost to competitors
Competition from large printing companies
Digital technology direction
Production Cycle Time Client response time
Bottleneck is in the prepress
Speed of decision making
7/31/2019 A System Dynamic Simulation Model
34/62
Equipment costs & purchase decisions Equipment cost
General and administrative costs
Fixed costs
Cost of buy versus lease
Sales Force Staff morale
Sales attrition
Costs of outside sales force
Sales goal per employee
Employee incentives
Company sales goal
Number of sales people to be trained
Employee rewards
Physical plant & facilities Location
Sales/square foot
Consolidation of locations
facilities
Rental vs. business
Outsourcing facilities (sales/sq. foot) $200-$300/sq. foot
Acquisition of independent printer company
Customer attractiveness
Growth leads to inefficiencies
Production Staff Quality of new hires
Quality of existing staff
7/31/2019 A System Dynamic Simulation Model
35/62
Number of temporary workers
Employee training/year
Attrition of production employees
Employee incentives
Staff morale
Cost of prepress staff
Payroll cost goal
Cost of outsourcing vs. in-house
Customer relations Specificity of services offered
Breadth of services offered
Pick up and delivery service
Customer satisfaction
Quality of product
Loss of sales
Customer retention/repeat sales
Customer loyalty
7/31/2019 A System Dynamic Simulation Model
36/62
7/31/2019 A System Dynamic Simulation Model
37/62
Appendix B
Causal loop diagram
7/31/2019 A System Dynamic Simulation Model
38/62
"Production" section:
"Equipment" section:
7/31/2019 A System Dynamic Simulation Model
39/62
"Sales" section:
7/31/2019 A System Dynamic Simulation Model
40/62
Relation among "Profits", "Profitability" and "SalesRevenue":
7/31/2019 A System Dynamic Simulation Model
41/62
7/31/2019 A System Dynamic Simulation Model
42/62
Appendix C
7/31/2019 A System Dynamic Simulation Model
43/62
Germeshausen Professor Emeritus of ManagementSenior Lecturer
University of Nebraska, BS '39, Electrical EngineeringMIT, SM '45, Electrical Engineering
Forrester, who invented random-access magnetic-core memory during the first wave of moderndigital computers, also pioneered the field of system dynamics -- analysis of the behavior ofsystems. He pursues three main interests based on system dynamics: the System DynamicsNational Model, which generates the major observed modes of economic behavior; a newmanagement education based on the inherent, dynamic complexity of all the related parts of acorporation and brings them into a unified system; and system dynamics as a methodology forgiving cohesion, meaning, and motivation to pre-college education.
Jay W. Forrester is Germeshausen Professor Emeritus and Senior Lecturer at the Sloan School ofManagement, Massachusetts Institute of Technology. He began his career as an electrical engineerworking on servomechanisms and large-scale digital computers. While Director of the MIT DigitalComputer Laboratory from 1946 to 1951, he was responsible for the design and construction ofWhirlwind I, one of the first high-speed digital computers.
In 1956, Professor Forrester started the
System Dynamics Groupat the Sloan School and with it, the field of system dynamics. The fivebooks he has written on system dynamics are available through Pegasus Communications inWaltham, Massachusetts.
Along with many writing and speaking commitments, Professor Forrester is currently working onthe National Model Project, a large computer model of the U.S. economy. He is also the director ofthe
System Dynamics in Education Project (SDEP), which is developing ways to use system dynamicsand computer modeling as a foundation for a new kind of kindergarten through 12th gradeeducation. The SDEP project at MIT is writingRoad Maps which is a guide to learning systemdynamics.
http://web.mit.edu/afs/athena.mit.edu/org/s/sysdyn/sd-group/home.htmlhttp://web.mit.edu/afs/athena.mit.edu/org/s/sysdyn/sd-group/home.htmlhttp://www.pegasuscom.com/http://web.mit.edu/afs/athena.mit.edu/org/s/sysdyn/http://www.rondo.com/capstone/Paper/road-maps/home.htmlhttp://www.rondo.com/capstone/Paper/road-maps/home.htmlhttp://www.pegasuscom.com/http://web.mit.edu/afs/athena.mit.edu/org/s/sysdyn/http://www.rondo.com/capstone/Paper/road-maps/home.htmlhttp://web.mit.edu/afs/athena.mit.edu/org/s/sysdyn/sd-group/home.html7/31/2019 A System Dynamic Simulation Model
44/62
Appendix D
7/31/2019 A System Dynamic Simulation Model
45/62
7/31/2019 A System Dynamic Simulation Model
46/62
7/31/2019 A System Dynamic Simulation Model
47/62
7/31/2019 A System Dynamic Simulation Model
48/62
Appendix E
EquipmentCapacity
init EquipmentCapacity = NeededCapacity*2
flow EquipmentCapacity = -dt*CapacityDepreciation
+dt*NewCapacity
doc EquipmentCapacity = 128,000 copies per eight hour day for four machines
operating 50 weeks per day time five days per week.
FacilitiesSize
init FacilitiesSize = 2500
flow FacilitiesSize = +dt*ChangeInFacilitiesSize
doc FacilitiesSize = Facilities size initial is 2500 square feet.
NumberOfSalesPeople
init NumberOfSalesPeople = 1
flow NumberOfSalesPeople = -dt*SalesPeopleAttrition
7/31/2019 A System Dynamic Simulation Model
49/62
+dt*SalesHires
dim ProductionStaff = (ProductionGroups)
ProductionStaff
init ProductionStaff = InitProductionStaff
flow ProductionStaff = -dt*ProductionStaffAttrition
+dt*ProductionStaffHires
CapacityDepreciation
aux CapacityDepreciation = EquipmentCapacity/CapacityLife
CapacityDepreciation
aux ChangeInFacilitiesSize = (DesiredFacilitiesSize-FacilitiesSize)/TimeToMove
NewCapacity
aux NewCapacity = MAX(0,(DesiredCapacity-EquipmentCapacity +
(CapacityDepreciation*TimeToAddNewCapacity))/TimeToAddNewCapacity)
dim ProductionStaffAttrition = (ProductionGroups)
ProductionStaffAttrition
aux ProductionStaffAttrition = ProductionStaff*ProductionStaffAttritionRate
dim ProductionStaffHires = (ProductionGroups)
ProductionStaffHires
aux ProductionStaffHires = MAX(0,(DesiredWorkforce-ProductionStaff +
(ProductionStaffAttrition*TimeToHireProductionStaff)) /
(TimeToHireProductionStaff+TimeToMakeStaffingDecisions))
SalesHires
7/31/2019 A System Dynamic Simulation Model
50/62
aux SalesHires = (DesiredSalesForce-NumberOfSalesPeople +
(SalesPeopleAttrition*TimeToHireSalesPeople)) / TimeToHireSalesPeople
SalesPeopleAttrition
aux SalesPeopleAttrition = NumberOfSalesPeople*SalesforceAttritionRate
AverageRevenuePerSalesPerson
aux AverageRevenuePerSalesPerson = SalesForceInvoices*AvgInvoice
AvgInvoice
aux AvgInvoice = IF(TIME>1995,120,120)
doc AvgInvoice = Estimate
CapacityUtilization
aux CapacityUtilization = NeededCapacity/EquipmentCapacity
CostOfGoodsSold
aux CostOfGoodsSold = TotalInvoices*VariableCostsPerInvoice
DesiredCapacity
aux DesiredCapacity = NeededCapacity/(1-DowntimeFraction)
DesiredFacilitiesSize
aux DesiredFacilitiesSize = INT(EquipmentCapacity /
INIT(EquipmentCapacity)+0.5)*INIT(FacilitiesSize)
DesiredSalesForce
aux DesiredSalesForce = IncrementalRevenue/INIT(AverageRevenuePerSalesPerson)
dim DesiredWorkforce = (ProductionGroups)
DesiredWorkforce
aux DesiredWorkforce = TotalInvoices/ProductionStaffProductivity
7/31/2019 A System Dynamic Simulation Model
51/62
EffectOfCommisions
aux EffectOfCommisions = GRAPH(AverageRevenuePerSalesPerson
/INIT(AverageRevenuePerSalesPerson) ,0,0.2,
[2,1.94,1.84,1.67,1.41,1,0.74,0.6,0.53,0.5,0.5"Min:0;Max:2;Zoom"])
EffectOfCommisions
aux EffectOfCustomerSatisfactionOnInvoices = EffectOfPriceOnCS *
EffectOfQualityOnCS*EffectOfServiceOnCS
EffectOfMoraleOnQuality
aux EffectOfMoraleOnQuality = DELAYINF(Morale, TIMESTEP, 1,1)
EffectOfPriceOnCS
aux EffectOfPriceOnCS = GRAPH(AvgInvoice/INIT(AvgInvoice),0,0.2,
[4,3.89,3.46,2.35,1.47,1,0.48,0.23,0.14,0.05,0.05"Min:0;Max:4;Zoom"])
EffectOfQualityOnCS
aux EffectOfQualityOnCS = GRAPH(EquipmentQuality*
NormalizedProductionTraining*EffectOfMoraleOnQuality,0,0.2,
[0,0.07,0.24,0.65,0.89,1,1.04,1.07,1.09,1.1,1.1"Min:0;Max:2;Zoom"])
EffectOfServiceOnCS
aux EffectOfServiceOnCS = GRAPH(PerceivedCycleTime/
INIT(PerceivedCycleTime),0,0.2,[4,3.84,3.32,2.25,1.51,1,0.67,0.47,0.36,0.29,
0.21,0.19,0.14,0.14,0.12,0.12,0.12,0.11,0.11,0.07,0.05"Min:0;Max:4;Zoom"])
EffectOfWorkloadOnMorale
aux EffectOfWorkloadOnMorale = GRAPH(ProductionWorkload,0,0.2,
7/31/2019 A System Dynamic Simulation Model
52/62
[0.61,0.61,0.61,0.64,0.75,1,1.11,1.11,0.77,0.65,0.64"Min:0;Max:2;Zoom"])
EquipmentCosts
aux EquipmentCosts = InitialEquipmentCosts/INIT(EquipmentCapacity)*
EquipmentCapacity
doc EquipmentCosts = About $2700 for copiers and $2700 for press per month.
FixedCosts
aux FixedCosts = OtherFixedCosts+EquipmentCosts
doc FixedCosts = This came from P&L Statement from 1995, Colorado.
IncrementalRevenue
aux IncrementalRevenue = RevenueGoal-(NonSalesForceRelatedInvoices*
AvgInvoice)
InitialEquipmentCosts
aux InitialEquipmentCosts = InitialEquipmentUnitCost*Year
doc InitialEquipmentCosts = About $2700 for copiers and $2700 for press per month.
LaborCosts
aux LaborCosts = ARRSUM(ProductionStaffCosts)+SalesForceCosts
doc LaborCosts = This came from P&L Statement from 1995, Colorado.
Morale
aux Morale = EffectOfWorkloadOnMorale
NeededCapacity
aux NeededCapacity = TotalInvoices*CopiesPerInvoice
NonSalesForceRelatedInvoices
aux NonSalesForceRelatedInvoices = 700000/INIT(AvgInvoice)*
7/31/2019 A System Dynamic Simulation Model
53/62
EffectOfCustomerSatisfactionOnInvoices
doc NonSalesForceRelatedInvoices = In 1994, $700,000 in sales occurred without the
help of the sales force.
NormalizedProductionTraining
aux NormalizedProductionTraining = ProductionTrainingCosts/
INIT(ProductionTrainingCosts)
NormalTimeToHireSalesPeople
aux NormalTimeToHireSalesPeople = HireRateForSalesPeople/Year
OtherFixedCosts
aux OtherFixedCosts = 800000*27%-INIT(EquipmentCosts)+
(FacilitiesSize*AnnualCostPerSquareFoot)
PerceivedCycleTime
aux PerceivedCycleTime = DELAYINF(ProductionCycleTime, 1/4,1,NormalCycleTime)
ProductionCycleTime
aux ProductionCycleTime = ((TotalInvoices/TotalProductionStaff)/
(INIT(TotalInvoices)/INIT(TotalProductionStaff)))*NormalCycleTime*Morale
ProductionStaffCosts
dim ProductionStaffCosts = (a=ProductionGroups)
aux ProductionStaffCosts = ProductionStaff(a)*(AvgProductionSalary(a)+ProductionTrainingCosts)
ProductionStaffProductivity
dim ProductionStaffProductivity = (ProductionGroups)
aux ProductionStaffProductivity = INIT(TotalInvoices)/InitProductionStaff*Morale
ProductionWorkload
7/31/2019 A System Dynamic Simulation Model
54/62
aux ProductionWorkload = ((TotalInvoices/TotalProductionStaff)/
(INIT(TotalInvoices)/INIT(TotalProductionStaff)))
doc ProductionWorkload = 1= Normal Work Load
Profitability
aux Profitability = Profits/SalesRevenue
Profits
aux Profits = (SalesRevenue-TotalCosts)
RevenueGoal
aux RevenueGoal = GRAPH(TIME,1994,1,[800000,950000,1000000,1070000,
1140000,1210000,1290000,1340000,1390000,1430000,1450000"
Min:0;Max:1500000;Zoom"])
SalesforceAttritionRate
aux SalesforceAttritionRate = 1*EffectOfCommisions
SalesForceCosts
aux SalesForceCosts = NumberOfSalesPeople*(AverageSalaryOfSalesPerson+
(SalesForceInvoices*AvgInvoice*SalesForceIncentives)+TrainingCosts)
SalesForceInvoices
aux SalesForceInvoices = NormSalesforceInvoices*
EffectOfCustomerSatisfactionOnInvoices
SalesRevenue
aux SalesRevenue = AvgInvoice*TotalInvoices
TimeToHireSalesPeople
7/31/2019 A System Dynamic Simulation Model
55/62
aux TimeToHireSalesPeople = EffectOfCommisions*NormalTimeToHireSalesPeople
TotalCosts
aux TotalCosts = CostOfGoodsSold+FixedCosts+LaborCosts
TotalInvoices
aux TotalInvoices = NonSalesForceRelatedInvoices+TotalSalesForceInvoices
TotalProductionStaff
aux TotalProductionStaff = ARRSUM(ProductionStaff)
TotalSalesForceInvoices
aux TotalSalesForceInvoices = SalesForceInvoices*NumberOfSalesPeople
TotalWorkforce
aux TotalWorkforce = NumberOfSalesPeople+ARRSUM(ProductionStaff)
AnnualCostPerSquareFoot
const AnnualCostPerSquareFoot = 12
AverageSalaryOfSalesPerson
const AverageSalaryOfSalesPerson = 1200*12
doc AverageSalaryOfSalesPerson = Average salary of sales force in 1994.
AvgProductionSalary
dim AvgProductionSalary = (ProductionGroups)
const AvgProductionSalary = [30000,15600,30000]
doc AvgProductionSalary = Full Time Equivalents. Press people and pre-press people
and managers make on average $12 per hour. Bindery and copier operators and
drivers make $7.50 per hour. Roughly 2/3 of the people are $12 and 1/3 are 7.50 =
about 10.50 per hour.
7/31/2019 A System Dynamic Simulation Model
56/62
CapacityLife
const CapacityLife = 7
doc CapacityLife = This is a mix of 3 - 4 years for a copier and longer for the press.
CopiesPerInvoice
const CopiesPerInvoice = INIT(AvgInvoice)/.05
DowntimeFraction
const DowntimeFraction = 10%
EquipmentQuality
const EquipmentQuality = 1
HireRateForSalesPeople
const HireRateForSalesPeople = 1
InitialEquipmentUnitCost
const InitialEquipmentUnitCost = 11000
InitProductionStaff
dim InitProductionStaff = (ProductionGroups)
const InitProductionStaff = [2,4,2]
NormalCycleTime
const NormalCycleTime = 4.5
doc NormalCycleTime = Days for printing
NormSalesforceInvoices
const NormSalesforceInvoices = 800000/120/8
doc NormSalesforceInvoices = The sales person did 12.5% of total sales in 1994.
ProductionStaffAttritionRat
7/31/2019 A System Dynamic Simulation Model
57/62
dim ProductionStaffAttritionRate = (ProductionGroups)
const ProductionStaffAttritionRate = [.67,.5,1]
ProductionTrainingCosts
const ProductionTrainingCosts = 500
doc ProductionTrainingCosts = 2 days of training per person per year, $150 per
person, =300, $200 for their time = $500 per person per year.
SalesForceIncentives
const SalesForceIncentives = 10%
doc SalesForceIncentives = Sales force incentives per person
TimeToAddNewCapacity
const TimeToAddNewCapacity = 1/12
TimeToHireProductionStaff
dim TimeToHireProductionStaff = (ProductionGroups)
const TimeToHireProductionStaff = [0.083,0.04,0.083]
TimeToMakeStaffingDecisions
dim TimeToMakeStaffingDecisions = (ProductionGroups)
const TimeToMakeStaffingDecisions = [0.167,0.167,0.167]*0
TimeToMove
const TimeToMove = TIMESTEP
TrainingCosts
const TrainingCosts = 840
doc TrainingCosts = 4 days of training per year, $150 per day of training. $1200 a
7/31/2019 A System Dynamic Simulation Model
58/62
month salary, 20 working days in a month, 1/5 x 1200 = 240 240 + 600= 840
VariableCostsPerInvoice
const VariableCostsPerInvoice = (27%*800000/INIT(TotalInvoices))
doc VariableCostsPerInvoice = This came from P&L Statement from 1995, Colorado.
Year
const Year = 12
7/31/2019 A System Dynamic Simulation Model
59/62
7/31/2019 A System Dynamic Simulation Model
60/62
Appendix F
7/31/2019 A System Dynamic Simulation Model
61/62
Appendix G
ABC/CND/Powersim Evaluation Form
Do you like the software? Why?Is it realistic model?What do you think about results from the
project?What do you think about the design of the project?
Text/Content
Organization
Performance
Graphics
Additional comments or recommendations: