+ All Categories
Home > Documents > A Tale of Two Sisters: Bangladesh and Philippine PPP Programs Sisters PPP Programme... · A Tale of...

A Tale of Two Sisters: Bangladesh and Philippine PPP Programs Sisters PPP Programme... · A Tale of...

Date post: 14-Feb-2018
Category:
Upload: buiquynh
View: 217 times
Download: 0 times
Share this document with a friend
17
A Tale of Two Sisters: Bangladesh and Philippine PPP Programs 26 November 2014 Presented at the UNESCAP PPP Workshop on Public-Private Partnerships for Infrastructure Development in Myanmar
Transcript
Page 1: A Tale of Two Sisters: Bangladesh and Philippine PPP Programs Sisters PPP Programme... · A Tale of Two Sisters: Bangladesh and Philippine PPP ... Public-Private Partnerships for

A Tale of Two Sisters:

Bangladesh and Philippine PPP Programs

26 November 2014

Presented at the UNESCAP PPP Workshop on

Public-Private Partnerships for Infrastructure Development in Myanmar

Page 2: A Tale of Two Sisters: Bangladesh and Philippine PPP Programs Sisters PPP Programme... · A Tale of Two Sisters: Bangladesh and Philippine PPP ... Public-Private Partnerships for

Background

• In early 2010, the governments of Bangladesh and Philippines

both recognized a need to completely overhaul their approach to

private participation in public infrastructure

• ADB, responding to this need, embarked on two Technical

Assistance programs for national PPP framework development:

– Bangladesh – December 2010

– Philippines – February 2011

• ADB staff worked jointly to design the programs, drawing on

– Outline national policies generated by each government

– Each country’s prior experience with PPPs – both successes and failures

• Both countries had initially successful attempts at PPP in the late 1990s

• Neither repeated these successes for about 10 years at the time of the TA

– Drew on ADB’s state-of-the-art knowledge of what elements were

required for a workable, robust PPP program

Page 3: A Tale of Two Sisters: Bangladesh and Philippine PPP Programs Sisters PPP Programme... · A Tale of Two Sisters: Bangladesh and Philippine PPP ... Public-Private Partnerships for

Common principles, common design

• The following slides present the common elements of the

Bangladesh and Philippine PPP programs

• The elements of these programs are now the standard by which

successful national PPP programs are measured

– The World Economic Forum and the G-20 have both recognized the

Philippine PPP program and its structures as the recommended

approach for countries pursuing PPP

G-20 Development Working Group

“Assessment of the Effectiveness of Project Preparation Facilities in Asia and Africa”

September 2014

https://www.g20.org/sites/default/files/g20_resources/library/

World Economic Forum

“Accelerating Infrastructure Delivery: new evidence from international financial institutions”

September 2014

http://www.weforum.org/reports/

– Why aren’t we hearing the same things about the Bangladesh program?

Page 4: A Tale of Two Sisters: Bangladesh and Philippine PPP Programs Sisters PPP Programme... · A Tale of Two Sisters: Bangladesh and Philippine PPP ... Public-Private Partnerships for

Common elements of the PPP programs

• Central PPP Office

– A professionalized team led by a CEO with private sector experience

– Office sits above sector line ministries, serving all

– Empowered by the President/Prime Minister under both political and

bureaucratic mandate to take control of the national development of PPP

• Enhanced Project Identification

– Objectively screen proposed projects from sector ministries/depts

– Use common criteria

– Assure they are viable as PPP

• Enhanced Project Preparation

– Use professional external advisors/consultants to prepare projects

– Preparation criteria in line with international project finance standards

– Development of robust project-level contracts that protect the interests of

government, assure reasonable risk allocation, and are bankable

– Assure all preparatory work is done before letting out for tender

Page 5: A Tale of Two Sisters: Bangladesh and Philippine PPP Programs Sisters PPP Programme... · A Tale of Two Sisters: Bangladesh and Philippine PPP ... Public-Private Partnerships for

Common elements of the PPP programs

• Dedicated Project Development Funding

– Establish a fund that is used solely for PPP project preparation

– Allows coverage of the higher costs of professional advisors outside

ordinary government operating budgets

– Fixed, objective criteria for consultant procurement and access to funds

• Transparent Tendering Process

– Standardized tendering process, outside ordinary govt procurement law

– Focused on achieving high quality output performance from projects (versus specifying inputs and quantities, like ordinary public sector procurement)

– Standardized prequalification documents – to assure bidders have

proper experience with building, financing and operating PPP projects

– Standardized request for proposal documents – to assure bidders have

all the information they need to lodge a firm proposal on an equal basis

Page 6: A Tale of Two Sisters: Bangladesh and Philippine PPP Programs Sisters PPP Programme... · A Tale of Two Sisters: Bangladesh and Philippine PPP ... Public-Private Partnerships for

Common elements of the PPP programs

• Consideration of PPP Project financial viability

– Seek to limit subsidies and rely on user fees wherever possible

– Seek to limit financial risk exposure of the government to PPP contracts,

subject to the principle of fair risk allocation (party gets a risk who is

best able to manage the risk)

– Subject to strict criteria, where a project is economically beneficial but

commercially challenged, provide subsidies or ‘viability gap financing’

from government, but limited to a maximum amount

• Public Financial Management

– Seek to quantify budget impacts and long-term liabilities that arise from

PPP contracts

– Report on these metrics to Finance Ministry/Dept

– Track cumulative impacts of PPP program

– Monitor and manage exposures, currency

– Use as lever for driving future reforms at sector level

Page 7: A Tale of Two Sisters: Bangladesh and Philippine PPP Programs Sisters PPP Programme... · A Tale of Two Sisters: Bangladesh and Philippine PPP ... Public-Private Partnerships for

Bangladesh PPP structure

Ministry of Finance

PPPO

7

PPP

Project

Line

Ministry

PPP

Office

Dept of Environment

Law Ministry

Cabinet Committee

on Economic Affairs

MOF

PPP Unit

Skills: Advisor Pool

Devel Money: PPP TA Fund

VGF

Budgeted Subsidies

Guarantees

Compliance with

environmental

laws, approvals

Contract vetting

+

PPPU reviews project proposals

prepared by PPPO for financial

vetting, quantifies and applies for

financial supports

PPPO determines which projects

can access /need skills and

financial support for project

development

CCEA provides:

• In-Principle Approval to

proceed with project

development

• Approves final project

Line Ministry:

• Originates projects

• Prelim studies

• Technical resources

• Ultimate project

ownership,

regulatory oversight

Sanctions funding

and supports

Reviews

and

Approvals

Project

proposal

Development

coordination

led by PPPO

Planning Commission

Sanctions Line Ministry

development program

= PPP-specific functions

= Other Govt functions

Page 8: A Tale of Two Sisters: Bangladesh and Philippine PPP Programs Sisters PPP Programme... · A Tale of Two Sisters: Bangladesh and Philippine PPP ... Public-Private Partnerships for

Philippine PPP Office Structure

Policy Formulation

& Evaluation

Service

Capacity Building &

Knowledge Mgt

Service

Administrative

Service

Policy Formulation

Division Project Development

Division

Mgt Information Svcs

Division Finance Division

Policy Evaluation &

Monitoring Division Project Management

Division

Knowledge Mgt

Division

Human Resources

Division

Capacity Building

Division

General Services

Division

Project

Development and

Monitoring Facility

Independent Fund

Manager NEDA

Hires and manages

external advisors

Bulk of staff and

services from this unit

Office of the Exec Director

Project

Development

Service

Legal Service PDMF Mgt Service

Page 9: A Tale of Two Sisters: Bangladesh and Philippine PPP Programs Sisters PPP Programme... · A Tale of Two Sisters: Bangladesh and Philippine PPP ... Public-Private Partnerships for

Actions taken

Bangladesh • Location

– Moved PPP functions from Board

of Investment to under the Prime

Minister’s Office

• Staffing

– Established office with 6 govt

administrative staff – govt office

– Hired professionally experienced

“CEO”

– Hired 6 staff professionally-

oriented staff from govt cadre

• Fiscal oversight by MOF PPP unit

– Administers subsidies and

support funds, against criteria

• Support funding from government

– PDF: $12m

– VGF: $325m

– Infra Fund: $200m

Philippines • Location

– Moved PPP Center from Dept of

Trade & Industry to National

Economic Development Authority

• Staffing

– Hired professionally experienced

“CEO”

– Hired 20 professional staff initially

– Quickly began adding staff with

growth in work load

• Fiscal oversight responsibility of

PPP Center, initially

• Support funding from government

– Established PDMF:

• Initially, $13m

• Increased in increments to $90m

– Contingent Liabilities Fund:

$200m

Page 10: A Tale of Two Sisters: Bangladesh and Philippine PPP Programs Sisters PPP Programme... · A Tale of Two Sisters: Bangladesh and Philippine PPP ... Public-Private Partnerships for

Outcomes to date (2011-2014)

* Project awarded before PPP framework and

procedures completed; project currently stalled due to

deficiencies in project preparation and contracts.

Metric Bangladesh Philippines

Office staffing:

Initially (2Q2011)

Now (4Q2014)

(Professional/Total)

1/6

7/19

(Professional/Total)

16/20

75/100

Sectors being covered 7 8

Projects screened > 200 > 200

Projects identified 42 51

Projects at concept stage 9 11

Projects procuring advisors 11 9

Projects under preparation 8 11

Projects tendered 4 15

Projects awarded 1* 8

Page 11: A Tale of Two Sisters: Bangladesh and Philippine PPP Programs Sisters PPP Programme... · A Tale of Two Sisters: Bangladesh and Philippine PPP ... Public-Private Partnerships for

Challenges encountered – both countries

• Project identification: First round is a ‘battle’ with sector line

ministries/departments

– Typically initially throw weak, non-viable or ‘leftover’ projects at PPP unit

– Not used to having someone else vet their projects – and have the full

authority to do so

– Haven’t had to think about performance outcomes previously, mostly

focus on inputs and quantities

– Lack of understanding of ‘commerciality’, ‘bankability’, risk allocation

• Consultants/Advisors

– Procurement of transaction advisors requires material amounts of PPP

staff time and effort and must be factored into development timeline

– Traditional national procurement standards may not be appropriate for

advisors; focus is on quality and experience, less on cost

– Consultants/advisors need oversight, require PPP units to obtain key

decisions from government ministries, both in sector and with ‘umbrella’

level rules/policies

Page 12: A Tale of Two Sisters: Bangladesh and Philippine PPP Programs Sisters PPP Programme... · A Tale of Two Sisters: Bangladesh and Philippine PPP ... Public-Private Partnerships for

Challenges encountered – both countries

• Project management in development

– PPP unit staff must have hands-on management of all aspects of the

PPP project development process

– There must be sufficient staff of appropriate quality to manage projects

– Need to liaison with govt ministries on sector-based inputs, integration

with other existing programs/infrastructure

– Need to support garnering of approvals, permissions from other govt

bodies for the projects

• Tendering

– PPP units face tremendous pressure from government to ‘get projects

out the door’, often before they are fully ready

– Evaluation of projects based on technical competency on a pass/fail

basis worries technocrats

– Government ministries try to avoid key sector issues that impact project

economics or ability to implement; this leads to challenges in developing

fully-formed project contracts

• Staffing

– Never enough! Need procurement, legal, financial, and tech staff

Page 13: A Tale of Two Sisters: Bangladesh and Philippine PPP Programs Sisters PPP Programme... · A Tale of Two Sisters: Bangladesh and Philippine PPP ... Public-Private Partnerships for

Next steps in evolution

Bangladesh

• Petitioning govt for more staff,

outside of govt pay scale

– Greatly needed to accelerate

consultant procurement,

administer to projects under

development/bidding, consult

with govt ministries

• Exhausting PPPTAF monies;

petitioning for top-up

• Nearing first success in 1Q15

– Govt in need of proof of

concept ahead of additional

funding; will that be too late?

Philippines

• Moved fiscal oversight unit out

of PPP Center to Dept of

Finance, creating ‘adversarial’

review process

– Will manage quantify, track,

and manage contingent

liabilities arising from PPPs

• Near term prospects to get

‘recycling’ of PDMF funds from

awarded projects

– Govt is not topping up the

PDMF as a result (not

necessarily negative!)

Page 14: A Tale of Two Sisters: Bangladesh and Philippine PPP Programs Sisters PPP Programme... · A Tale of Two Sisters: Bangladesh and Philippine PPP ... Public-Private Partnerships for

Lessons learned

• Political will and leadership is of paramount importance

• Empowerment and independence of PPP unit is essential

• PPP unit leadership must be of highest professional quality

• Staffing quantity and quality of high importance; has material

impact on speed, efficiency and quality of outcomes

• Clear, consistent, reliable rules, processes and institutional

application is key to attracting investors and lenders

• Sustained commitment of government funds and resources

required

• Adequate TA funding required upfront with external support

from development partners ($1.725m in BAN vs $7.20m in PHI)

• Projects take longer to prepare and tender than initially

anticipated: PDF monies need to be sized to account for this

• Once initial projects are through the process, it gets easier

• Outcomes from transparent competitive tendering have yielded

– High quality participants

– Value for money proposals

Page 15: A Tale of Two Sisters: Bangladesh and Philippine PPP Programs Sisters PPP Programme... · A Tale of Two Sisters: Bangladesh and Philippine PPP ... Public-Private Partnerships for

PPP, done correctly, can deliver too for Myanmar

• Public-Private Partnerships can be a key component of national development – Creates additional sources of investment

– Can deliver higher efficiency and performance

– Complements public sector/sovereign investments

– Better manages national finances, and contingent liability exposures

• But getting it right is important

– There is a proven formula for success in PPP

• Grounded in the principles of international project finance

– Evidence shows that varying from this formula usually results in sub-optimal outcomes

• Structuring and tendering PPPs correctly requires

– Skills – technical, legal, financial/commercial

– Project development capital – to hire skills, conduct studies

– Informed management – to drive outcomes, manage results

– National oversight of financial impacts – for sustainability

PPP holds potential for Government to achieve significant development investments at lowest cost and highest quality

Page 16: A Tale of Two Sisters: Bangladesh and Philippine PPP Programs Sisters PPP Programme... · A Tale of Two Sisters: Bangladesh and Philippine PPP ... Public-Private Partnerships for

ADB Contacts

J. Grant Hauber PPP TA Project Manager and

Principal Public-Private Partnership Specialist

Public Management, Financial Sector and

Trade Division

Southeast Asia Department

[email protected]

T: +632 683 1707

M: +63 917 888 0702

M: +95 9 259 627 681

Thatha Hla Financial Sector Economist

Public Management, Financial Sector

and Trade Division

Myanmar Resident Mission, Naypyitaw

[email protected]

T: +95 67 810 6066

M: +95 9 450 005 639

16

Page 17: A Tale of Two Sisters: Bangladesh and Philippine PPP Programs Sisters PPP Programme... · A Tale of Two Sisters: Bangladesh and Philippine PPP ... Public-Private Partnerships for

Bangladesh PPP structure

PPP

Office (PMO)

Prime

Minister

Line

Ministries Line

Ministries Line

Ministries Line

Ministries

PPP Advisory

Committee

Cabinet Committee

on Economic Affairs

PPP

Unit (MOF)

Finance

Division (MOF)

In-Principle and Final

Project Approvals

Policy

Consultation

Planning

Commission

Sanctions and Administers

Budgets for:

• Annual Development Plan

(capital expenditure

budget)

• Non-plan Budget

(annual operating

budgets)

• Special allocations for

funds, such as PPPTAF,

VGF, BIFF

• Assesses fiscal viability

and risk of PPP Projects

• Sanctions VGF, Subsidies

• Monitors Contingent

Liabilities

Creates and

sanctions Annual

Development Plan

(ADP), which

includes

identification of

specific

development

projects and

associated capital

budget allocation.

Responsible for

development of

Five-year Plans

Proposed

development

program

Budget

Allocation

Fund

Allocations

Fiscal

Sanctioning

of

Individual

PPP

Projects

Central point of PPP coordination for internal

government, external investor, lender and civil society

stakeholders.

Screens, supports development of PPP projects,

administers tendering, negotiates, and supports

financing process on behalf of Government, specifically

sector line ministries

Sanctioned Projects and Expenditures in ADP

PPP

Project

Proposals Core of PPP Program

CEO


Recommended