+ All Categories
Home > Documents > Aace-estimating Panel Feb 2 2015

Aace-estimating Panel Feb 2 2015

Date post: 25-Feb-2018
Category:
Upload: gilberto-yoshida
View: 216 times
Download: 0 times
Share this document with a friend

of 44

Transcript
  • 7/25/2019 Aace-estimating Panel Feb 2 2015

    1/44

    Montreal Section of AACE InternationalPresents.

    Its Only an Estimate!

    A Panel Discussion: Roundtable

  • 7/25/2019 Aace-estimating Panel Feb 2 2015

    2/44

    Agenda

    Its Only an Estimate!

    Safety Topic

    Panel Introduction

    Overview on Capital Cost Estimating Panel Questions & Discussion

    Question period

  • 7/25/2019 Aace-estimating Panel Feb 2 2015

    3/44

    Safety Topic

    Walking on Montreal Streets in Winter..

  • 7/25/2019 Aace-estimating Panel Feb 2 2015

    4/44

    The PANEL Introduction

    The Owner: Guillaume Lafortune Hydro

    Quebec

    The Consultant: John Alarcon Hatch

    The Contractor: Patrick Habib LCO

  • 7/25/2019 Aace-estimating Panel Feb 2 2015

    5/44

    Its Only an Estimate!

    The conceptOf Course,

    Thats Only an

    ESTIMATE..The ACTUAL cost

    will be muchmore!

  • 7/25/2019 Aace-estimating Panel Feb 2 2015

    6/44

    Art Imitates Life..

    Why estimators are cautious

  • 7/25/2019 Aace-estimating Panel Feb 2 2015

    7/44

    Industry Results

    J. Hollmann Presentation 2011

  • 7/25/2019 Aace-estimating Panel Feb 2 2015

    8/44

    COST ESTIMATINGA predictive process used to quantify, cost, & price

    resources required by scope of an asset

    investment option, activity, or project.

    As a predictive process, estimating must address

    risks & uncertainties.

    Outputs of estimating are used primarily as inputsfor budgeting, cost or value analysis, decision

    making in business, asset & project planning, or

    for project cost & schedule control processes.

    Its Only an Estimate!

    Definitions

  • 7/25/2019 Aace-estimating Panel Feb 2 2015

    9/44

    Estimate Defined

    Estimate (aace): A compilation of all the costs of the

    elements of a project or effort included within an

    agreed upon scope.

    PMBoK: A quantitative assessment of the likelyamount or outcome. Usually applied to project costs,

    resources, effort and durations and is usually preceded

    by a modifier (i.e. preliminary, conceptual, feasibility,

    OoM, definitive). It should also include some indicationof accuracy e.g. +/-percent).

  • 7/25/2019 Aace-estimating Panel Feb 2 2015

    10/44

    Basic Estimating Process

    Planning Preparation Development Summation Document Review

    Final

    Estimate

    MandateOwner reqts

    Estimate Level

    WBS

    Est. Resources

    Est. Methods

    Schedule

    Scope of Work

    Site Survey

    Labour rates

    Productivity

    Prev. Est.

    Equip. Lists & Eng. DocsMTOs

    Quotes/$ Databases

    Direct Labour

    Schedule Data

    Indirect Costs/Owner

    Risk Review

    Methodology

    Data Sources

    Inclusions

    Exclusions

    Quantities

    Cost summaries

    Historical data

    Benchmark data

    Risk Evaluation

    Variance Analysis

    Owner

    Requirements

    WBS

    Commodity

    Coding

    Estimate

    Plan

    Quantified & priced

    Line items

    Direct & Indirect

    Allowances

    Contingency & Esc.

    Summary by WBS

    Discipline

    Quantities , hours

    & cost

    Variance report

    Basis of

    Estimate

    Supporting

    worksheets

    Labour rates &

    Crews

    productivity

    Activities typically shown for Class 3 estimate

  • 7/25/2019 Aace-estimating Panel Feb 2 2015

    11/44

  • 7/25/2019 Aace-estimating Panel Feb 2 2015

    12/44

  • 7/25/2019 Aace-estimating Panel Feb 2 2015

    13/44

  • 7/25/2019 Aace-estimating Panel Feb 2 2015

    14/44

    Reference: AACE International Recommended Practice No. 18R-97 COST ESTIMATE CLASSIFICATION SYSTEM

    Its Only an Estimate!

    Estimate Classes

  • 7/25/2019 Aace-estimating Panel Feb 2 2015

    15/44

    Capacity factors (6/10 rule), analogous,expert judgment, cost indices (top down)

    Factors applied to plant (Hand

    factor) or equipment (Lang factor)Parametric estimating (related to aphysical attr ibute/s)

    Model based with CAE 5D (BIM)

    Detail l ine items with MTOs and

    pricing from estimating databases& market pricing (bottom-upestimating)

    School of Project Controls

    Estimating Methods

    Reference: Estimating in 3D: the Next Dimension, Barmania & McMullan, AACE International Annual Meeting, 2004

  • 7/25/2019 Aace-estimating Panel Feb 2 2015

    16/44

    Estimate Elements

    Direct Contractor View

    COST

    ESTIMATE

    Direct

    Costs

    Indirect

    Costs

    Labor Material Equipment Subcontract

    TaxesGeneral

    ConditionsRisk / Reward Overhead

    Profit Contingency

  • 7/25/2019 Aace-estimating Panel Feb 2 2015

    17/44

    Its Only an Estimate!

    Estimate Summary

  • 7/25/2019 Aace-estimating Panel Feb 2 2015

    18/44

    Class & Stage-Gate

    Doing the Right Project

    Doing the Project Right

    Project Shaping

    18

    Class 5 Class 4 Class 3Class

    4,5

    Sanction

    Appropriat ion

    4 Definit ive

    5 Tender

    Check

  • 7/25/2019 Aace-estimating Panel Feb 2 2015

    19/44

    Estimate types and Stage-Gate

    At what stage are you most involved?

    Is the stage-gate process

    effective?

    Where are there areas for

    improvement? (e.g. communications,

    interfaces)

    Its Only an Estimate!

    Panel Discussion

  • 7/25/2019 Aace-estimating Panel Feb 2 2015

    20/44

    Flaws

    Each of the stages do not meet requireddeliverables, leading to recycling: FEL G1 = Robust business case

    FEL G2 = Scope complete (base case selected)

    FEL G3 = Project ready to execute

    Stage-gate approval conditional

    FEL drives cost and schedule predictability*

    FEL & Context: 3 key areas of context* Challenges of physical location

    Availability & quality of construction labour

    Permitting

    * industrial megaprojects by E.W. Merrow, chapter 10

  • 7/25/2019 Aace-estimating Panel Feb 2 2015

    21/44

    From Social Media

    Reference: When Good Projects Go Bad SOR - April 2011

  • 7/25/2019 Aace-estimating Panel Feb 2 2015

    22/44

    One of the reasons given for project

    overrun is poor estimating.

    How do you respond?

    What is the most variable part of the

    estimate and has greatest impact?

    What can the industry do to improve?

    Its Only an Estimate!

    Panel Discussion

  • 7/25/2019 Aace-estimating Panel Feb 2 2015

    23/44

    Flyvbjergs Top Reasons for

    Mega project Overrun

  • 7/25/2019 Aace-estimating Panel Feb 2 2015

    24/44

    Most variable costs

    Typical areas of highest growth:

    Bulk Quantities

    Construction Labour hoursIndirect related labour costs

    Construction indirect costs

    Field Overheads

    Consultant services

    Owner costs

    EQUIP

    23%

    BULKS

    24%

    DIR.

    LAB.21%

    HO

    13%

    INDIR.19%

    RATIOS

  • 7/25/2019 Aace-estimating Panel Feb 2 2015

    25/44

    Contingency& Escalation

    How do you define each?

    How do you assess conty?

    Deterministic, probabilistic orparametric?

    Who owns the project contingency?

    Its Only an Estimate!

    Panel Discussion

  • 7/25/2019 Aace-estimating Panel Feb 2 2015

    26/44

    Project Contingency

    ContingencyAn amount added to an estimate to allow for

    items, conditions, or events for which the state,

    occurrence, and/or effect is uncertain and that

    experience shows will likely result, in aggregate, in

    additional costs.

    Typically estimated using statistical analysis or

    judgment based on past asset or project

    experience.

  • 7/25/2019 Aace-estimating Panel Feb 2 2015

    27/44

    Risk Methods

  • 7/25/2019 Aace-estimating Panel Feb 2 2015

    28/44

    Risk Methods

  • 7/25/2019 Aace-estimating Panel Feb 2 2015

    29/44

    Escalation

  • 7/25/2019 Aace-estimating Panel Feb 2 2015

    30/44

    Estimating Accuracy:

    What does it mean?

    How do you establish and

    validate it?

    How do we improve it?

    Its Only an Estimate!

    Panel Discussion

  • 7/25/2019 Aace-estimating Panel Feb 2 2015

    31/44

  • 7/25/2019 Aace-estimating Panel Feb 2 2015

    32/44

    Estimate accuracy

  • 7/25/2019 Aace-estimating Panel Feb 2 2015

    33/44

    International Projects:

    How is labour productivity

    evaluated in the estimate?

    What are the things to watchfor remote locations?

    Its Only an Estimate!

    Panel Discussion

  • 7/25/2019 Aace-estimating Panel Feb 2 2015

    34/44

    Sample Labour Productivity

    evaluation sheet

  • 7/25/2019 Aace-estimating Panel Feb 2 2015

    35/44

    Selling the estimate: why so

    important?

    What is your estimate review

    process/processes?

    How do you convince mgmt, client

    and stakeholders?

    School of Project Controls

    Panel Discussion

  • 7/25/2019 Aace-estimating Panel Feb 2 2015

    36/44

    Typical Reviews

    Progressive internalreviews

    Estimating/Controlsteam review

    Project ReviewConsult. Mgmt

    ReviewOwner Review

  • 7/25/2019 Aace-estimating Panel Feb 2 2015

    37/44

    Collecting Benchmarking &

    Historical Data:Is it really worthwhile?

    What is your approach?

    Its Only an Estimate!

    Panel Discussion

  • 7/25/2019 Aace-estimating Panel Feb 2 2015

    38/44

    Budget and Cost Control Workflow

    Capital EstimateScope of

    WorkBudget

    Trending &

    Forecasting

    CommitmentsChange Orders

    Progress

    Databases

    Design Data/

    Quantities

    Project

    Statistics

    and Metrics

    Final Cost

    Market

    Data

  • 7/25/2019 Aace-estimating Panel Feb 2 2015

    39/44

    Estimating & Project Controls:

    Should front end estimating be

    part of project controls?

    How has technology affected the

    estimating process? ( Systems/Methods)

    What is role of estimating during

    execution?

    Its Only an Estimate!

    Panel Discussion

  • 7/25/2019 Aace-estimating Panel Feb 2 2015

    40/44

    Lessons learned and

    estimating:

    In summary, is there a

    lesson learned that means

    the most to you that youwould like to share?

    Its Only an Estimate!

    Panel Discussion

  • 7/25/2019 Aace-estimating Panel Feb 2 2015

    41/44

    Question Period

  • 7/25/2019 Aace-estimating Panel Feb 2 2015

    42/44

  • 7/25/2019 Aace-estimating Panel Feb 2 2015

    43/44

  • 7/25/2019 Aace-estimating Panel Feb 2 2015

    44/44


Recommended