Date post: | 25-Feb-2018 |
Category: |
Documents |
Upload: | gilberto-yoshida |
View: | 216 times |
Download: | 0 times |
of 44
7/25/2019 Aace-estimating Panel Feb 2 2015
1/44
Montreal Section of AACE InternationalPresents.
Its Only an Estimate!
A Panel Discussion: Roundtable
7/25/2019 Aace-estimating Panel Feb 2 2015
2/44
Agenda
Its Only an Estimate!
Safety Topic
Panel Introduction
Overview on Capital Cost Estimating Panel Questions & Discussion
Question period
7/25/2019 Aace-estimating Panel Feb 2 2015
3/44
Safety Topic
Walking on Montreal Streets in Winter..
7/25/2019 Aace-estimating Panel Feb 2 2015
4/44
The PANEL Introduction
The Owner: Guillaume Lafortune Hydro
Quebec
The Consultant: John Alarcon Hatch
The Contractor: Patrick Habib LCO
7/25/2019 Aace-estimating Panel Feb 2 2015
5/44
Its Only an Estimate!
The conceptOf Course,
Thats Only an
ESTIMATE..The ACTUAL cost
will be muchmore!
7/25/2019 Aace-estimating Panel Feb 2 2015
6/44
Art Imitates Life..
Why estimators are cautious
7/25/2019 Aace-estimating Panel Feb 2 2015
7/44
Industry Results
J. Hollmann Presentation 2011
7/25/2019 Aace-estimating Panel Feb 2 2015
8/44
COST ESTIMATINGA predictive process used to quantify, cost, & price
resources required by scope of an asset
investment option, activity, or project.
As a predictive process, estimating must address
risks & uncertainties.
Outputs of estimating are used primarily as inputsfor budgeting, cost or value analysis, decision
making in business, asset & project planning, or
for project cost & schedule control processes.
Its Only an Estimate!
Definitions
7/25/2019 Aace-estimating Panel Feb 2 2015
9/44
Estimate Defined
Estimate (aace): A compilation of all the costs of the
elements of a project or effort included within an
agreed upon scope.
PMBoK: A quantitative assessment of the likelyamount or outcome. Usually applied to project costs,
resources, effort and durations and is usually preceded
by a modifier (i.e. preliminary, conceptual, feasibility,
OoM, definitive). It should also include some indicationof accuracy e.g. +/-percent).
7/25/2019 Aace-estimating Panel Feb 2 2015
10/44
Basic Estimating Process
Planning Preparation Development Summation Document Review
Final
Estimate
MandateOwner reqts
Estimate Level
WBS
Est. Resources
Est. Methods
Schedule
Scope of Work
Site Survey
Labour rates
Productivity
Prev. Est.
Equip. Lists & Eng. DocsMTOs
Quotes/$ Databases
Direct Labour
Schedule Data
Indirect Costs/Owner
Risk Review
Methodology
Data Sources
Inclusions
Exclusions
Quantities
Cost summaries
Historical data
Benchmark data
Risk Evaluation
Variance Analysis
Owner
Requirements
WBS
Commodity
Coding
Estimate
Plan
Quantified & priced
Line items
Direct & Indirect
Allowances
Contingency & Esc.
Summary by WBS
Discipline
Quantities , hours
& cost
Variance report
Basis of
Estimate
Supporting
worksheets
Labour rates &
Crews
productivity
Activities typically shown for Class 3 estimate
7/25/2019 Aace-estimating Panel Feb 2 2015
11/44
7/25/2019 Aace-estimating Panel Feb 2 2015
12/44
7/25/2019 Aace-estimating Panel Feb 2 2015
13/44
7/25/2019 Aace-estimating Panel Feb 2 2015
14/44
Reference: AACE International Recommended Practice No. 18R-97 COST ESTIMATE CLASSIFICATION SYSTEM
Its Only an Estimate!
Estimate Classes
7/25/2019 Aace-estimating Panel Feb 2 2015
15/44
Capacity factors (6/10 rule), analogous,expert judgment, cost indices (top down)
Factors applied to plant (Hand
factor) or equipment (Lang factor)Parametric estimating (related to aphysical attr ibute/s)
Model based with CAE 5D (BIM)
Detail l ine items with MTOs and
pricing from estimating databases& market pricing (bottom-upestimating)
School of Project Controls
Estimating Methods
Reference: Estimating in 3D: the Next Dimension, Barmania & McMullan, AACE International Annual Meeting, 2004
7/25/2019 Aace-estimating Panel Feb 2 2015
16/44
Estimate Elements
Direct Contractor View
COST
ESTIMATE
Direct
Costs
Indirect
Costs
Labor Material Equipment Subcontract
TaxesGeneral
ConditionsRisk / Reward Overhead
Profit Contingency
7/25/2019 Aace-estimating Panel Feb 2 2015
17/44
Its Only an Estimate!
Estimate Summary
7/25/2019 Aace-estimating Panel Feb 2 2015
18/44
Class & Stage-Gate
Doing the Right Project
Doing the Project Right
Project Shaping
18
Class 5 Class 4 Class 3Class
4,5
Sanction
Appropriat ion
4 Definit ive
5 Tender
Check
7/25/2019 Aace-estimating Panel Feb 2 2015
19/44
Estimate types and Stage-Gate
At what stage are you most involved?
Is the stage-gate process
effective?
Where are there areas for
improvement? (e.g. communications,
interfaces)
Its Only an Estimate!
Panel Discussion
7/25/2019 Aace-estimating Panel Feb 2 2015
20/44
Flaws
Each of the stages do not meet requireddeliverables, leading to recycling: FEL G1 = Robust business case
FEL G2 = Scope complete (base case selected)
FEL G3 = Project ready to execute
Stage-gate approval conditional
FEL drives cost and schedule predictability*
FEL & Context: 3 key areas of context* Challenges of physical location
Availability & quality of construction labour
Permitting
* industrial megaprojects by E.W. Merrow, chapter 10
7/25/2019 Aace-estimating Panel Feb 2 2015
21/44
From Social Media
Reference: When Good Projects Go Bad SOR - April 2011
7/25/2019 Aace-estimating Panel Feb 2 2015
22/44
One of the reasons given for project
overrun is poor estimating.
How do you respond?
What is the most variable part of the
estimate and has greatest impact?
What can the industry do to improve?
Its Only an Estimate!
Panel Discussion
7/25/2019 Aace-estimating Panel Feb 2 2015
23/44
Flyvbjergs Top Reasons for
Mega project Overrun
7/25/2019 Aace-estimating Panel Feb 2 2015
24/44
Most variable costs
Typical areas of highest growth:
Bulk Quantities
Construction Labour hoursIndirect related labour costs
Construction indirect costs
Field Overheads
Consultant services
Owner costs
EQUIP
23%
BULKS
24%
DIR.
LAB.21%
HO
13%
INDIR.19%
RATIOS
7/25/2019 Aace-estimating Panel Feb 2 2015
25/44
Contingency& Escalation
How do you define each?
How do you assess conty?
Deterministic, probabilistic orparametric?
Who owns the project contingency?
Its Only an Estimate!
Panel Discussion
7/25/2019 Aace-estimating Panel Feb 2 2015
26/44
Project Contingency
ContingencyAn amount added to an estimate to allow for
items, conditions, or events for which the state,
occurrence, and/or effect is uncertain and that
experience shows will likely result, in aggregate, in
additional costs.
Typically estimated using statistical analysis or
judgment based on past asset or project
experience.
7/25/2019 Aace-estimating Panel Feb 2 2015
27/44
Risk Methods
7/25/2019 Aace-estimating Panel Feb 2 2015
28/44
Risk Methods
7/25/2019 Aace-estimating Panel Feb 2 2015
29/44
Escalation
7/25/2019 Aace-estimating Panel Feb 2 2015
30/44
Estimating Accuracy:
What does it mean?
How do you establish and
validate it?
How do we improve it?
Its Only an Estimate!
Panel Discussion
7/25/2019 Aace-estimating Panel Feb 2 2015
31/44
7/25/2019 Aace-estimating Panel Feb 2 2015
32/44
Estimate accuracy
7/25/2019 Aace-estimating Panel Feb 2 2015
33/44
International Projects:
How is labour productivity
evaluated in the estimate?
What are the things to watchfor remote locations?
Its Only an Estimate!
Panel Discussion
7/25/2019 Aace-estimating Panel Feb 2 2015
34/44
Sample Labour Productivity
evaluation sheet
7/25/2019 Aace-estimating Panel Feb 2 2015
35/44
Selling the estimate: why so
important?
What is your estimate review
process/processes?
How do you convince mgmt, client
and stakeholders?
School of Project Controls
Panel Discussion
7/25/2019 Aace-estimating Panel Feb 2 2015
36/44
Typical Reviews
Progressive internalreviews
Estimating/Controlsteam review
Project ReviewConsult. Mgmt
ReviewOwner Review
7/25/2019 Aace-estimating Panel Feb 2 2015
37/44
Collecting Benchmarking &
Historical Data:Is it really worthwhile?
What is your approach?
Its Only an Estimate!
Panel Discussion
7/25/2019 Aace-estimating Panel Feb 2 2015
38/44
Budget and Cost Control Workflow
Capital EstimateScope of
WorkBudget
Trending &
Forecasting
CommitmentsChange Orders
Progress
Databases
Design Data/
Quantities
Project
Statistics
and Metrics
Final Cost
Market
Data
7/25/2019 Aace-estimating Panel Feb 2 2015
39/44
Estimating & Project Controls:
Should front end estimating be
part of project controls?
How has technology affected the
estimating process? ( Systems/Methods)
What is role of estimating during
execution?
Its Only an Estimate!
Panel Discussion
7/25/2019 Aace-estimating Panel Feb 2 2015
40/44
Lessons learned and
estimating:
In summary, is there a
lesson learned that means
the most to you that youwould like to share?
Its Only an Estimate!
Panel Discussion
7/25/2019 Aace-estimating Panel Feb 2 2015
41/44
Question Period
7/25/2019 Aace-estimating Panel Feb 2 2015
42/44
7/25/2019 Aace-estimating Panel Feb 2 2015
43/44
7/25/2019 Aace-estimating Panel Feb 2 2015
44/44