4/6/2010 1  Able Street and Terrace Road  Able Street and Terrace Road Improvements Project Improvements Project Neighborhood Pre Neighborhood Pre- -Construction Meeting Construction Meeting Tuesday, April 6, 2010 Tuesday, April 6, 2010 7:00 p.m. 7:00 p.m. Spring Lake Park City Hall Spring Lake Park City Hall Purpose of Tonight’s Meeting Purpose of Tonight’s Meeting Project Communication Project Communication Project Areas/Schedule Project Areas/Schedule Project Description Project Description Review Common Questions Review Common Questions   Brief overview o f the construction p rocess Brief overview of the construction process Project Cost Information Project Cost Information  Answer Project Questions  Answer Project Questions Project Communication Project Communication Communication during the Project is Communication during the Project is important to the City and the important to the City and the Residents Residents Multiple ways City and Residents can Multiple ways City and Residents can communicate during the Project communicate during the Project
Transcript
Page 1: Able-Terrace Presentation HANDOUT 4-6-10

8/7/2019 Able-Terrace Presentation HANDOUT 4-6-10

http://slidepdf.com/reader/full/able-terrace-presentation-handout-4-6-10 1/16

4/6/20

 Able Street and Terrace Road Able Street and Terrace RoadImprovements ProjectImprovements Project

Neighborhood PreNeighborhood Pre--Construction MeetingConstruction MeetingTuesday, April 6, 2010Tuesday, April 6, 20107:00 p.m.7:00 p.m.Spring Lake Park City HallSpring Lake Park City Hall

Purpose of Tonight’s MeetingPurpose of Tonight’s Meeting

Project CommunicationProject Communication

Project Areas/ScheduleProject Areas/Schedule

Project DescriptionProject Description

Review Common QuestionsReview Common Questions

 – – Brief overview of the construction processBrief overview of the construction process

Project Cost InformationProject Cost Information

 Answer Project Questions Answer Project Questions

Project CommunicationProject Communication

Communication during the Project isCommunication during the Project isimportant to the City and theimportant to the City and the

ResidentsResidents

Multiple ways City and Residents canMultiple ways City and Residents cancommunicate during the Projectcommunicate during the Project

Page 2: Able-Terrace Presentation HANDOUT 4-6-10

8/7/2019 Able-Terrace Presentation HANDOUT 4-6-10

http://slidepdf.com/reader/full/able-terrace-presentation-handout-4-6-10 2/16

4/6/20

Project CommunicationProject Communication

Dedicated Project Voice Mail NumberDedicated Project Voice Mail Number – – Project Voice Mail Number will beProject Voice Mail Number will be

(763) 792(763) 792--72167216

 – – Receive quick project updateReceive quick project update

 – – Leave questions, register concerns,Leave questions, register concerns,set up appointmentsset up appointments

 – – Monitored dailyMonitored daily

 – – For immediate concerns, contact City Hall atFor immediate concerns, contact City Hall at(763) 784(763) 784--64916491 (business hours 8:00 to 4:30)(business hours 8:00 to 4:30)and they will contact the inspectorand they will contact the inspector

Project CommunicationProject Communication

City Website: www.ci.springCity Website: www.ci.spring--lakelake--park.mn.uspark.mn.us

Project CommunicationProject Communication

Notifications forNotifications formajor constructionmajor construction

eventsevents

Page 3: Able-Terrace Presentation HANDOUT 4-6-10

8/7/2019 Able-Terrace Presentation HANDOUT 4-6-10

http://slidepdf.com/reader/full/able-terrace-presentation-handout-4-6-10 3/16

4/6/20

Project AreasProject Areas

 Able Street – OsborneRoad to CSAH 10

Terrace Road –Osborne Road toSanburnol Drive

SANBURNOL DRIVE

81ST AVENUE

OSBORNE ROAD

Project ScheduleProject Schedule

 Approximate start date: April 26, 2010 Approximate start date: April 26, 2010

Likely 1 crewLikely 1 crew

General order:General order:

 – – Terrace Road will be done first:Terrace Road will be done first:

Start on south half: Osborne Rd. to 81Start on south half: Osborne Rd. to 81stst Ave. Ave.

Then portion North of 81Then portion North of 81

stst

 Avenue Avenue

Project ScheduleProject Schedule

 – – Able Street will be done second: Able Street will be done second:

Don’t know specific order yetDon’t know specific order yet

Special schedule requirements by High SchoolSpecial schedule requirements by High School

Completion date (both streets):Completion date (both streets):

September 3September 3rdrd (substantial)(substantial)

October 8October 8thth (final)(final)

Page 4: Able-Terrace Presentation HANDOUT 4-6-10

8/7/2019 Able-Terrace Presentation HANDOUT 4-6-10

http://slidepdf.com/reader/full/able-terrace-presentation-handout-4-6-10 4/16

4/6/20

Project ScheduleProject Schedule

Schedule is subject to changeSchedule is subject to change

Notices will be delivered when there isNotices will be delivered when there iswork affecting your areawork affecting your area

Project DescriptionProject Description

Existing concrete curb and gutterExisting concrete curb and gutter

 – – WillWill be left in placebe left in place

 – – OnlyOnly spot replacements where neededspot replacements where needed

 – – Adjacent Adjacent pedestrian curb ramps andpedestrian curb ramps andisolated sidewalk isolated sidewalk repairsrepairs

Project DescriptionProject Description

Example of curb replacementExample of curb replacement

Page 5: Able-Terrace Presentation HANDOUT 4-6-10

8/7/2019 Able-Terrace Presentation HANDOUT 4-6-10

http://slidepdf.com/reader/full/able-terrace-presentation-handout-4-6-10 5/16

4/6/20

Project DescriptionProject Description

RebuildingRebuilding street section betweenstreet section between curbscurbs – – About 11”  About 11” deep (5” pavement, 6” gravel)deep (5” pavement, 6” gravel)

Project DescriptionProject Description

PrivatePrivate utilities:utilities: – – Small amount of work anticipatedSmall amount of work anticipated

City utilities:City utilities: – – Minor water main work (isolated spots)Minor water main work (isolated spots)

 – – Storm sewer repairsStorm sewer repairs

Driveways:Driveways: – – Concrete apronsConcrete aprons

 – – Further details later in presentationFurther details later in presentation

Project DescriptionProject Description

 Able Street Able Street

Existing street condition Existing storm sewer 

Page 6: Able-Terrace Presentation HANDOUT 4-6-10

8/7/2019 Able-Terrace Presentation HANDOUT 4-6-10

http://slidepdf.com/reader/full/able-terrace-presentation-handout-4-6-10 6/16

4/6/20

Project DescriptionProject Description

Terrace RoadTerrace RoadExisting street condition Existing storm sewer 

Common QuestionsCommon Questions

Qwest Communications will be doing work onQwest Communications will be doing work ontheir cables and structures in the project areatheir cables and structures in the project area

Some power pole relocationsSome power pole relocations

CenterPointCenterPoint Energy may have short sectionsEnergy may have short sectionsof gas main relocationof gas main relocation

Isolated areas of relocation and adjustmentsIsolated areas of relocation and adjustmentswill have little or no impact to residentswill have little or no impact to residents

 – – Some of the work will occur before City projectSome of the work will occur before City project

What are the private utilities doing?What are the private utilities doing?

Common QuestionsCommon Questions What are the private utilities doing?What are the private utilities doing?

Page 7: Able-Terrace Presentation HANDOUT 4-6-10

8/7/2019 Able-Terrace Presentation HANDOUT 4-6-10

http://slidepdf.com/reader/full/able-terrace-presentation-handout-4-6-10 7/16

4/6/20

Common QuestionsCommon Questions How do I get my mail?How do I get my mail?

Existing MailboxesExisting Mailboxes – – Most existing mailboxes will remain inMost existing mailboxes will remain in

place throughout constructionplace throughout construction

Will be baggedWill be bagged – – no deliveryno delivery

 – – Mailboxes conflicting with constructionMailboxes conflicting with constructionwill be salvaged by City and left withwill be salvaged by City and left withthe property owner for safe keepingthe property owner for safe keeping

Common QuestionsCommon Questions How do I get my mail?How do I get my mail?

During ConstructionDuring Construction

 – – All mail will be delivered to temporary All mail will be delivered to temporarylocations that are easily accessiblelocations that are easily accessiblethroughout constructionthroughout construction

 – – Temporary mailbox bank locations willTemporary mailbox bank locations willbe determined by the Post Masterbe determined by the Post Master

Common QuestionsCommon Questions How do I get my mail?How do I get my mail?

If prefer, can makeIf prefer, can make

private arrangementprivate arrangementwith Post Officewith Post Office

7440 University Ave7440 University AveFridley, MN 55432Fridley, MN 55432(763) 571(763) 571--20162016

Page 8: Able-Terrace Presentation HANDOUT 4-6-10

8/7/2019 Able-Terrace Presentation HANDOUT 4-6-10

http://slidepdf.com/reader/full/able-terrace-presentation-handout-4-6-10 8/16

4/6/20

Common QuestionsCommon Questions What will happen to my landscaping andWhat will happen to my landscaping and

sprinklers within the Right of Way?sprinklers within the Right of Way?

 – – Property owner may salvage ahead of timeProperty owner may salvage ahead of time – – Contractor remove during constructionContractor remove during construction

 – – No trees anticipated to be removedNo trees anticipated to be removed

Common QuestionsCommon Questions What are the stakes in my yard?What are the stakes in my yard?

 – – Survey stakes for utility constructionSurvey stakes for utility construction

 – – Staking done by City’s engineering firmStaking done by City’s engineering firm

Common QuestionsCommon Questions What are they doing to the street?What are they doing to the street?

Page 9: Able-Terrace Presentation HANDOUT 4-6-10

8/7/2019 Able-Terrace Presentation HANDOUT 4-6-10

http://slidepdf.com/reader/full/able-terrace-presentation-handout-4-6-10 9/16

4/6/20

Common QuestionsCommon Questions Will I be able to drive to my house?Will I be able to drive to my house?

Common QuestionsCommon Questions Will I be able to drive to my house?Will I be able to drive to my house?

Daily access on streetDaily access on street – – 7:00 p.m. to 7:00 a.m. minimum7:00 p.m. to 7:00 a.m. minimum

Some isolated shortSome isolated short--term interruptionsterm interruptions – – For items such as utility installationsFor items such as utility installations

 – – Mostly during the dayMostly during the day – – avoiding rush hoursavoiding rush hours

Common QuestionsCommon Questions Will I be able to drive to my house?Will I be able to drive to my house?

Some temporary street closuresSome temporary street closures

 – – Only portions of streetsOnly portions of streets

 – – Example: during work at intersectionsExample: during work at intersections

 – – Most for less than one full dayMost for less than one full day

 – – Signs will be put up in advanceSigns will be put up in advance

Concrete slabs at south endsConcrete slabs at south ends

 – – Will require 1 week closureWill require 1 week closure

Page 10: Able-Terrace Presentation HANDOUT 4-6-10

8/7/2019 Able-Terrace Presentation HANDOUT 4-6-10

http://slidepdf.com/reader/full/able-terrace-presentation-handout-4-6-10 10/16

4/6/20

Common QuestionsCommon Questions Will I always have access to my driveway?Will I always have access to my driveway?

Common QuestionsCommon Questions Will my Garbage Service be Interrupted?Will my Garbage Service be Interrupted?

No impact to residents anticipatedNo impact to residents anticipated

Common QuestionsCommon Questions Is the City replacing any utilities?Is the City replacing any utilities?

Water MainWater Main

Isolated service interruptionsIsolated service interruptions

Temporary durationTemporary duration

(less than 1 day)(less than 1 day)

Will avoid peak use timesWill avoid peak use times

Written notices will beWritten notices will bedelivered in advancedelivered in advance

Page 11: Able-Terrace Presentation HANDOUT 4-6-10

8/7/2019 Able-Terrace Presentation HANDOUT 4-6-10

http://slidepdf.com/reader/full/able-terrace-presentation-handout-4-6-10 11/16

4/6/20

Common QuestionsCommon Questions Is the City replacing any utilities?Is the City replacing any utilities?

Storm SewerStorm Sewer

Common QuestionsCommon Questions What kind of curb are we getting?What kind of curb are we getting?

Concrete, 6” highConcrete, 6” high

Matches existing typeMatches existing type

Depressed back atDepressed back atdriveways and rampsdriveways and ramps

Common QuestionsCommon Questions How will my driveway be restored?How will my driveway be restored?

 – – Curb cut (drop the back of the curb)Curb cut (drop the back of the curb)

 – – Concrete apronConcrete apron

 – – Patch to transition to existing drivewayPatch to transition to existing driveway

Same material as existing drivewaySame material as existing driveway

 – – Not all driveways will be disturbedNot all driveways will be disturbed

Page 12: Able-Terrace Presentation HANDOUT 4-6-10

8/7/2019 Able-Terrace Presentation HANDOUT 4-6-10

http://slidepdf.com/reader/full/able-terrace-presentation-handout-4-6-10 12/16

4/6/20

Common QuestionsCommon Questions How will my driveway be restored?How will my driveway be restored?

 – – In general, will match your existing driveway widthIn general, will match your existing driveway width

(within City Code requirements) unless you request(within City Code requirements) unless you requestotherwiseotherwise

Common QuestionsCommon Questions

Can I change the width of my driveway?Can I change the width of my driveway?

 –– Yes, the City has a process for this Yes, the City has a process for this

 – – Property owner must make written request,Property owner must make written request,and sign agreement with Cityand sign agreement with City

Forms available at City HallForms available at City Hall

 – – If widening, property owner is responsible forIf widening, property owner is responsible forpart of the cost beyond the existing widthpart of the cost beyond the existing width

Project installs only the apronProject installs only the apron

Property owner is required to finish the extraProperty owner is required to finish the extradriveway area within 1 yeardriveway area within 1 year

Common QuestionsCommon Questions Will I be able to have my entireWill I be able to have my entire

driveway redriveway re--done?done?

 – – City has discussed with theCity has discussed with the contractorcontractor

 – – ContractorContractor is willing to constructis willing to construct

 – – Concrete or Bituminous drivewaysConcrete or Bituminous driveways

Private contract between resident and Private contract between resident and contractor contractor – – not part of City project not part of City project 

Page 13: Able-Terrace Presentation HANDOUT 4-6-10

8/7/2019 Able-Terrace Presentation HANDOUT 4-6-10

http://slidepdf.com/reader/full/able-terrace-presentation-handout-4-6-10 13/16

4/6/20

Common QuestionsCommon Questions If you want to look into having yourIf you want to look into having your

driveway redriveway re--done:done:

CallCall Brent @ Valley Paving (952) 445Brent @ Valley Paving (952) 445--86158615

CallsCalls preferred before April 26preferred before April 26thth

Private contract between resident and Private contract between resident and contractor contractor – – not part of City project not part of City project 

Common QuestionsCommon Questions How long until I can use my new driveway?How long until I can use my new driveway?

•1 week curing period

Common QuestionsCommon Questions Where’s the pavement?Where’s the pavement?

Base CourseBase Course

Binder Course & Binder Course & 

Wear CourseWear Course

 – – Placed in three layers:Placed in three layers:

Page 14: Able-Terrace Presentation HANDOUT 4-6-10

8/7/2019 Able-Terrace Presentation HANDOUT 4-6-10

http://slidepdf.com/reader/full/able-terrace-presentation-handout-4-6-10 14/16

4/6/20

Common QuestionsCommon Questions How will my lawn be restored?How will my lawn be restored?

 – – Sod with topsoilSod with topsoil

City maintains for 60City maintains for 60--daysdays

Property owner is responsible for maintenanceProperty owner is responsible for maintenanceafter thatafter that

NonNon--Conforming DrivewaysConforming Driveways

MoreMore than one drivewaythan one driveway

Width greater than City CodeWidth greater than City Codemaximum (24 feet)maximum (24 feet)

Within City Code minimum setback Within City Code minimum setback 

 – – These These require approval from the City require approval from the City 

Project FundingProject Funding

Sources of fundingSources of funding

 – – Federal Funds (ARRA Program)Federal Funds (ARRA Program)

 – – Municipal State Aid Funds (MSA)Municipal State Aid Funds (MSA)

 – – City FundsCity Funds

 – – Assessments Assessments

Page 15: Able-Terrace Presentation HANDOUT 4-6-10

8/7/2019 Able-Terrace Presentation HANDOUT 4-6-10

http://slidepdf.com/reader/full/able-terrace-presentation-handout-4-6-10 15/16

4/6/20

Project Cost InformationProject Cost Information

 Assessments Assessments – – Determined per Pavement ManagementDetermined per Pavement Management

Policy (Resolution 98Policy (Resolution 98--48)48)

 – – Estimated assessment rates:Estimated assessment rates:

Single family home $3,106.83Single family home $3,106.83

NonNon--residential propertiesresidential properties $67.92/foot$67.92/foot

 – – Same values shown in June 2009Same values shown in June 2009

Project Cost InformationProject Cost Information

 Assessments (continued) Assessments (continued)

 – – Final assessments determined: Fall 2010Final assessments determined: Fall 2010

 – – Public Hearing held for assessmentsPublic Hearing held for assessments

 All property owners notified by US Mail All property owners notified by US Mail

 – – Final rates will be determined based onFinal rates will be determined based onactual project costsactual project costs

Could go up or down from estimateCould go up or down from estimate

Thank you for your Thank you for your 

attention! attention! 

We We ’    ’    re looking forward to re looking forward to 

a successful project! a successful project! 

Page 16: Able-Terrace Presentation HANDOUT 4-6-10

8/7/2019 Able-Terrace Presentation HANDOUT 4-6-10

http://slidepdf.com/reader/full/able-terrace-presentation-handout-4-6-10 16/16

4/6/20

Questions?Questions?