Access Yard Assembly Marco Oriunno (SLAC), November 13, 2013 LCWS13, TOKYO.

Date post: 08-Jan-2018
Category:
Upload: reginald-barton
View: 215 times
Download: 1 times
Share this document with a friend
Description:
3 Kitakami site - Detector Access Yard Several location options for of the Access Yard, how to select them : 1.Ideally a Short tunnel length and a low slope, but most likely a compromise of the two features. 2.How much does the Detector Access Yard share with the installation and maintenance of the CFS around the IP ? A seprate Access Yard for the machine ? 3.Proximity to Freeways and Rail rated for heavy loads transport 4.Assuming that the same developed area for all the options is available 5.Costs.
22
Access Yard Assembly Marco Oriunno (SLAC), November 13, 2013 LCWS13, TOKYO
Transcript
Page 1: Access Yard Assembly Marco Oriunno (SLAC), November 13, 2013 LCWS13, TOKYO.

Access Yard AssemblyMarco Oriunno (SLAC), November 13, 2013LCWS13, TOKYO

Page 2: Access Yard Assembly Marco Oriunno (SLAC), November 13, 2013 LCWS13, TOKYO.

2

Japanese ILC Site – Horizontal Tunnel Access

Page 3: Access Yard Assembly Marco Oriunno (SLAC), November 13, 2013 LCWS13, TOKYO.

3

Kitakami site - Detector Access Yard

Several location options for of the Access Yard, how to select them :

1. Ideally a Short tunnel length and a low slope, but most likely a compromise of the two features.

2. How much does the Detector Access Yard share with the installation and maintenance of the CFS around the IP ? A seprate Access Yard for the machine ?

3. Proximity to Freeways and Rail rated for heavy loads transport

4. Assuming that the same developed area for all the options is available

5. Costs.

Page 4: Access Yard Assembly Marco Oriunno (SLAC), November 13, 2013 LCWS13, TOKYO.

4

ILC needs to have “Lean” Detectors

Toyota Factories pioneered Lean Assembly :

“preserving value with less work”

Fight The Seven Muda (futilities)

Transportation, Inventory, Motion, Waiting, Over-processing, Over-production, Defects.

Big Detectors for Big Science must be Lean :Time vs labor (Costs)Time vs Technology drive (Increasing Performances)Low Maintenance (Costs)High Upgradability (Costs and Scientific reach)Shorter commissioning to get nominal performancesInternational Competition

Page 5: Access Yard Assembly Marco Oriunno (SLAC), November 13, 2013 LCWS13, TOKYO.

5

Lean assembly – Some Examples

CMS Detector Shipbuilding

Airbus

Page 6: Access Yard Assembly Marco Oriunno (SLAC), November 13, 2013 LCWS13, TOKYO.

6

Detector Hall Requirements – The War of Resources

Two detectors in one experimental hall must share a lot of infrastructures even more than beam time.

1. Single Horizontal tunnel : Minimize by design the risk of logjam

2. Single 200t+ bridge crane : strict planning of the heavy lifts

3. Unfriendly environment

4. Safety of the personnel

…Planning tasks on surface As Many As Reasonable Achievable : A.M.A.R.A.

…Decoupling detector assembly from Experimental Hall construction

Page 7: Access Yard Assembly Marco Oriunno (SLAC), November 13, 2013 LCWS13, TOKYO.

7

Assembly Yard - CMS

140 m

223 m

150 m

34,000 m2

25 m

Con

trol R

oom

Offi

ces

Gas 1

Gas 2

He

Page 8: Access Yard Assembly Marco Oriunno (SLAC), November 13, 2013 LCWS13, TOKYO.

8

Assembly Yard - CMS

Page 9: Access Yard Assembly Marco Oriunno (SLAC), November 13, 2013 LCWS13, TOKYO.

9

SPS beam extraction - North area (CERN)

46 m

230 m

Page 10: Access Yard Assembly Marco Oriunno (SLAC), November 13, 2013 LCWS13, TOKYO.

10

SPS beam extraction - North area (CERN)

Page 11: Access Yard Assembly Marco Oriunno (SLAC), November 13, 2013 LCWS13, TOKYO.

11

Detector Assembly Hall

Iron Barrel Doors

Solenoid

One bridge crane ~ 30t

Ground motion with pushback trucks

Detector units loaded with sensors, tested and pre-commissioned

Loading Area

Page 12: Access Yard Assembly Marco Oriunno (SLAC), November 13, 2013 LCWS13, TOKYO.

12

Kitakami Access Yard

60,000 m2

Tunnel

Page 13: Access Yard Assembly Marco Oriunno (SLAC), November 13, 2013 LCWS13, TOKYO.

13

Access Yard Buildings

Assembly Hall #2

Assembly Hall #1

OfficesAccess Tunnel

Site Entrance

400t Loading Station

Page 14: Access Yard Assembly Marco Oriunno (SLAC), November 13, 2013 LCWS13, TOKYO.

14

Kitakami Access Yard

5% 190 m

320 m

Undergound Detector Hall

Page 15: Access Yard Assembly Marco Oriunno (SLAC), November 13, 2013 LCWS13, TOKYO.

Solenoid Assembly and Commissioning

Page 16: Access Yard Assembly Marco Oriunno (SLAC), November 13, 2013 LCWS13, TOKYO.

16

Detector Units on cart + Pushback track

Page 17: Access Yard Assembly Marco Oriunno (SLAC), November 13, 2013 LCWS13, TOKYO.

17

DCL-TLG100 Moving Crane – 400 T

Page 18: Access Yard Assembly Marco Oriunno (SLAC), November 13, 2013 LCWS13, TOKYO.

18

Transferring parts underground

Page 19: Access Yard Assembly Marco Oriunno (SLAC), November 13, 2013 LCWS13, TOKYO.

19

Loading station 400 tons

Page 20: Access Yard Assembly Marco Oriunno (SLAC), November 13, 2013 LCWS13, TOKYO.

20

Loading station 400 tons

Page 21: Access Yard Assembly Marco Oriunno (SLAC), November 13, 2013 LCWS13, TOKYO.

21

Detector Hall

Page 22: Access Yard Assembly Marco Oriunno (SLAC), November 13, 2013 LCWS13, TOKYO.

Magnet Installation – Japanese Site

215 tons Crane