+ All Categories
Home > Documents > Accidental beam losses and protection in the LHC

Accidental beam losses and protection in the LHC

Date post: 15-Jan-2016
Category:
Upload: ellery
View: 39 times
Download: 0 times
Share this document with a friend
Description:
Accidental beam losses and protection in the LHC. R.Schmidt and J.Wenninger f or the Working Group on Machine Protection HB 2004 Bensheim. LHC parameters and associated risks Overview accidental beam losses Aperture and accidental beam losses Protection and redundancy Conclusions. - PowerPoint PPT Presentation
Popular Tags:
49
HB 2004 1 Accidental beam losses and Accidental beam losses and protection in the LHC protection in the LHC R.Schmidt and J.Wenninger f or the Working Group or the Working Group on Machine Protection on Machine Protection HB 2004 Bensheim HB 2004 Bensheim LHC parameters and associated LHC parameters and associated risks risks Overview accidental beam losses Overview accidental beam losses Aperture and accidental beam Aperture and accidental beam losses losses Protection and redundancy Protection and redundancy Conclusions Conclusions
Transcript
Page 1: Accidental beam losses and protection in the LHC

HB 2004 1

Accidental beam losses and protection in Accidental beam losses and protection in the LHC the LHC

R.Schmidt and J.Wenninger

for the Working Group on or the Working Group on Machine ProtectionMachine Protection

HB 2004 BensheimHB 2004 Bensheim

LHC parameters and associated risksLHC parameters and associated risks

Overview accidental beam lossesOverview accidental beam losses

Aperture and accidental beam lossesAperture and accidental beam losses

Protection and redundancyProtection and redundancy

ConclusionsConclusions

Page 2: Accidental beam losses and protection in the LHC

HB 2004 2

LHC tunnel

Beam dump tunnel

Page 3: Accidental beam losses and protection in the LHC

HB 2004 3

Some numbers for 7 TeVSome numbers for 7 TeVMomentum at collision 7 TeV/cBeam intensity 2808 1.1 1011 protons per beamLuminosity 1034 cm-2s-1

Dipole field at 7 TeV 8.33 TeslaTypical beam size 200-300 µm

• Energy stored in the magnet system: 10 GJoule

• Energy stored in one (of 8) dipole circuit: 1.1 GJoule

• Energy stored in one beam: 350 MJoule

• Average beam power to compare with

high power accelerators, both beams: some 10 kWatt

• Instantaneous beam power for one beam: 3.9 TWatt….during 89 µs

….corresponds to the power of 1700 nuclear power plants

• Energy to heat and melt one kg of copper: 700 kJ

Page 4: Accidental beam losses and protection in the LHC

HB 2004 4

Bunch intensities, quench and damage levelBunch intensities, quench and damage level

• Intensity one “pilot” bunch 5109

• Nominal bunch intensity 1.11011

• Batch from SPS (216/288 bunches at 450 GeV) 31013

• Nominal beam intensity with 2808 bunches 31014

• Damage level for fast losses at 450 GeV 1-21012

• Damage level for fast losses at 7 TeV 1-21010

• Quench level for fast losses at 450 GeV 2-3109

• Quench level for fast losses at 7 TeV 1-2106

Damage and quench assessment approximative, supported by experience in SPS and calculations

Further calculations and material tests at SPS in two weeks planned

Page 5: Accidental beam losses and protection in the LHC

HB 2004 5

Livingston type plot: Livingston type plot: Energy stored in the beamEnergy stored in the beam

0.01

0.10

1.00

10.00

100.00

1000.00

1 10 100 1000 10000Momentum [GeV/c]

En

erg

y st

ore

d in

th

e b

eam

[M

J]

LHC topenergy

LHC injection(12 SPS batches)

ISR

SNSLEP2

SPS fixed target

HERA

TEVATRON

SPSppbar

SPS batch to LHC

Factor~200

RHIC proton

Page 6: Accidental beam losses and protection in the LHC

HB 2004 6

Failure scenarios and accidental beam losses Failure scenarios and accidental beam losses

A large number of different mechanisms can cause accidental particle losses: Classification of accidental beam losses according to time constant for the loss

• Ultra fast beam losses (single turn or less) • to be avoided, beam dump block is the only element that can safely

absorb the 7 TeV LHC beam

passive protection with collimators and beam absorber

• Very fast beam losses (some turns to some milliseconds)• Fast beam losses (5 ms – several seconds)• Slow beam losses (several seconds – 0.2 hours)

active protection, by detecting failure and extracting the beams into beam dump block

Page 7: Accidental beam losses and protection in the LHC

HB 2004 7

Single turn accidental beam lossesSingle turn accidental beam losses

Failure mechanisms

• Failure of beam dump kicker (prefiring, asynchronous beam dump)• Failure of kickers for tune measurements and aperture exploration• During transfer and injection

• failure of injection kicker • wrong trajectory or mismatch of beam energy• obstruction of beam passage

• Recent studies on protection during transfer and injection of the beams from SPS at 450 GeV to the LHC (see H.Burkhardt)

Strategy for protection

• Avoid such failures (systems with high reliability)• Block beam transfer from SPS to LHC if parameters are not correct (i.e. magnet

current)• Beam trajectory after such failure is reasonably well defined • Passive protection: rely on collimators and beam absorbers

Page 8: Accidental beam losses and protection in the LHC

HB 2004 8

Consequence of a failure scenario: Full 7 TeV LHC beam deflected into copper target

Target length [cm]

vaporisation

melting

Copper target

2 m

Energy density [GeV/cm3] on target axis

2808 bunches7 TeV 350 MJoule

collaboration with N.Tahir (GSI) et al.

Page 9: Accidental beam losses and protection in the LHC

HB 2004 9

Density change in target after impact of 100 bunches

• Energy deposition calculations using FLUKA• Numerical simulations of the hydrodynamic and thermodynamic response of the target with two-dimensional hydrodynamic computer codeFrom this calculations one can estimate the longitudinal range of full beam in copper

between 10m and 40m

Target radial coordinate [cm]

radial

copper solid state

collaboration with N.Tahir (GSI) et al.

100 bunches – target density reduced to 10%

Copper target

Page 10: Accidental beam losses and protection in the LHC

HB 2004 10

LHC Layout

eight arcs (sectors with a length of about 2300 m)

eight long straight sections (about 700 m long)

IR6: Beam dumping system

IR4: RF + Beam instrumentation

IR5:CMS

IR1: ATLAS

IR8: LHC-BIR2:ALICE

Injection

IR3: Momentum Cleaning (normal conducting magnets)

IR7: Betatron Cleaning (normal conducting magnets)

Transfer Line Transfer Line

Injection

Page 11: Accidental beam losses and protection in the LHC

HB 2004 11

IR6: Beam dumping system

IR5:CMS

IR1: ATLAS

IR8: LHC-BIR2:ALICE

IR3: Momentum Cleaning (normal conducting magnets)

IR7: Betatron Cleaning (normal conducting magnets)

Collimators for cleaning the beam halo • close to the beam between 5-10 • must be accurately adjusted (within a fraction of one )• position depends on optics and possibly on energy

IR4: RF + Beam instrumentation

Injection

Transfer Line Transfer Line

Injection

Page 12: Accidental beam losses and protection in the LHC

HB 2004 12

IR6: Beam dumping system

IR5:CMS

IR1: ATLAS

IR8: LHC-BIR2:ALICE

IR3: Momentum Cleaning (normal conducting magnets)

IR7: Betatron Cleaning (normal conducting magnets)

IR4: RF + Beam instrumentation

Collimators for protection of equipment against single turn beam losses• shadow equipment downstream • must be adjusted (better than one σ)• position depends on LHC operational mode (injection, energy ramp, …) and on optics

Injection

Transfer Line Transfer Line

Injection

Page 13: Accidental beam losses and protection in the LHC

HB 2004 13

IR6: Beam dumping system

IR5:CMS

IR1: ATLAS

IR8: LHC-BIR2:ALICE

IR3: Momentum Cleaning (normal conducting magnets)

IR7: Betatron Cleaning (normal conducting magnets)

IR4: RF + Beam instrumentation

For protection of equipment against multiturn beam losses• all collimators limiting the aperture contribute to this function

Injection

Transfer Line Transfer Line

Injection

Page 14: Accidental beam losses and protection in the LHC

HB 2004 14

IR6: Beam dumping system

IR5:CMS

IR1: ATLAS

IR8: LHC-BIR2:ALICE

IR3: Momentum Cleaning (normal conducting magnets)

IR7: Betatron Cleaning (normal conducting magnets)

IR4: RF + Beam instrumentation

Collimators for protection and cleaning of the low-beta insertions, mainly in IR1 and IR5 • close to the beam about 10 • must be accurately adjusted (within about one )• mainly required during squeeze and for squeezed beams

Injection

Transfer Line Transfer Line

Injection

Page 15: Accidental beam losses and protection in the LHC

HB 2004 15

Lifetime of the beam - for Lifetime of the beam - for nominal intensity at 7 TeVnominal intensity at 7 TeV

Beam lifetime

Beam power into equipment (1 beam)

Comments

100 h 1 kW Healthy operation, beam cleaning should capture > 99% of the protons

10 h 10 kW Operation acceptable, beam cleaning should capture 99.9% of the protons

(approximate beam losses = cryogenic cooling power at 1.9 K)

0.2 h 500 kW Operation only possibly for 10 s, beam cleaning must be VERY efficient

1 min 6 MW Equipment or operation failure - operation not possible - beam must be dumped

<< 1 min > 6 MW Beam must be dumped VERY FAST

Accidental beam lossesAccidental beam losses

Page 16: Accidental beam losses and protection in the LHC

HB 2004 16

Accidental multiturn beam losses Accidental multiturn beam losses

• Closed orbit grows around the ring

• Fast emittance growth: beam size explodes

• Both

Can happen very fast

Can be detected around the entire accelerator

• Local orbit bump • cannot happen very fast• might be detected only locally

Protection: Detect failure and dump beamDetection, transmission to beam dump, and beam dump – takes at least 3 turns ~ 270 s

Page 17: Accidental beam losses and protection in the LHC

HB 2004 17

Multiple turn failures: Magnet powering failuresMultiple turn failures: Magnet powering failures

• Quench of superconducting magnets• Discharge of superconducting magnets switching a

resistance into the circuit (after quench, or by accident) • Failure of magnet powering

For some magnets very fast beam loss (several turns): D1 normal conducting magnet

• Electric short in the coil of a normal conducting magnet

Page 18: Accidental beam losses and protection in the LHC

HB 2004 18

Multiple turn failures: Other failuresMultiple turn failures: Other failures

• Aperture limitation in beam pipe (circulating beam)• Vacuum valve moves into beam

• Collimator moves into beam

• Other element moves into beam

• Loss of beam vacuum

• Failure in the RF system• Debunching of beam and number of protons in the abort gap… could

lead to single turn failure when beam is dumped

• Operational failures

• Combined failures, for example after Mains Disturbances (thunderstorm, …)

Page 19: Accidental beam losses and protection in the LHC

HB 2004 19

Beam losses and apertureBeam losses and aperture

The aperture of the LHC at 450 GeV is limited (about 7.5σ, assuming

closed orbit excursions=4 mm, beta-beating, ….)

Critical operation at 7 TeV with squeezed optics: -function up to 4850 m in insertions IR1 and IR5 • very strong low- quadrupole magnets with orbit offset • normal conducting dipole magnets • superconducting dipole magnets

• In general, particle losses first at collimators

• Fast orbit changes are the most critical failures• collimators at about 6-9 from the beam• 1% of the beam would damage the collimators for fast beam loss

Page 20: Accidental beam losses and protection in the LHC

HB 2004 20

Critical apertures around the LHC (Critical apertures around the LHC ( illustration drawing)illustration drawing)

in units of beam size in units of beam size at 450 TeV at 450 TeV

IR1 IR2 IR3 IR4 IR5 IR6 IR7 IR8

collimators (betatroncleaning)

collimators(momentumcleaning)

aperture in cleaning insertions about 6-9

6-9

arc aperturedown to about 7.5

aperture in cleaning insertions about 6-9

Page 21: Accidental beam losses and protection in the LHC

HB 2004 21

Critical apertures around the LHC (Critical apertures around the LHC ( illustration drawing)illustration drawing)

in units of beam size in units of beam size 7 TeV and 7 TeV and * = 0.55 m in IR1 and IR5* = 0.55 m in IR1 and IR5

IR1 IR2 IR3 IR4 IR5 IR6 IR7 IR8

arc apertureabout 50

Triplet Triplet

TCDQat ~10

beam dumppartial kick

TCT TCT collimators (betatroncleaning)

collimators(momentumcleaning)

aperture in cleaning insertions about 6-9

6-9

triplet apertureabout 14

Page 22: Accidental beam losses and protection in the LHC

HB 2004 22

0 0.001 0.002 0.003 0.004 0.005 0.006 0.007 0.008 0.009 0.010

0.1

0.2

0.3

0.4

0.5

0.6

0.7

0.8

0.9

11.0

0

1000 x MQX tx( )

1000 x D1 tx( )

1000 x D2 tx( )

1000 x MB tx( )

0.010.00 tx

Most likely failures for fast losses: quenchesMost likely failures for fast losses: quenchesFailures leading to the fastest multiturn losses: D1 magnet Failures leading to the fastest multiturn losses: D1 magnet

Quench of:- MQX - D2- MB

Powering Failure of D1 normal conducting

D1 normalconducting

very fast loss

Squeezed optics with max beta of 4.8 km

All 4 quadrupole magnets (inner triplet MQX) quench , approximately Gaussian current decay with time constant 0.2 s

Powering failure for D1, exponential current decay, time constant 2.5 s

Quench of one MB, approximately Gaussian current decay with time constant 0.2 s

D2 quenchfast loss

time [seconds]

orbit [mm]

MB quench

fast loss

MQX: 2 quads quench

fast loss

V.Kain Diploma thesis 2001 / O.Brüning

Page 23: Accidental beam losses and protection in the LHC

HB 2004 23

Particles that touch collimator after failure of normal conducting D1 magnets

After about 13 turns 3·109 protons touch collimator, about 6 turns later 1011 protons touch collimator

V.Kain

“Dump beam” level

1011 protons at collimator

HERA experience confirmes worries: very fast beam losses

Page 24: Accidental beam losses and protection in the LHC

HB 2004 24

Protection and redundancy: what triggers a beam Protection and redundancy: what triggers a beam dump? dump?

1. Hardware diagnostics

2. Quench signal from Quench Protection System

3. Beam loss monitors at the collimators and other aperture limitations

4. Beam loss monitors in the arcs

5. Magnet current change monitors

6. Beam position change monitors

7. Fast beam current decay (“lifetime”) monitors

Page 25: Accidental beam losses and protection in the LHC

HB 2004 25

Hardware failure diagnostics Hardware failure diagnostics

• Vacuum valve leaving the “OUT” position (…away from end switch)

• Other movable devices leaving the “OUT” position

• Powering failures detected by the power converter, requesting a beam dump (typical times in the order of 10 ms)

• Failures of cooling for normal conducting magnets

• Failure in the RF system

• Anticipated failure in the beam dumping system (before it is too late), e.g. when 1 out of 15 kicker is lost

• Failure in critical beam absorbers and collimators

Page 26: Accidental beam losses and protection in the LHC

HB 2004 26

Hardware failure diagnostics Hardware failure diagnostics

PLUS• Does not require collimators to have correct settings• If early enough, can dump the beam before particle losses

MINUS• For many type of failures the beam dump comes too late • Complexity of hardware: not all failures are detected• Too many channels: too many “False Beam Dumps” • Risk of including failures that would not lead to particle losses

Page 27: Accidental beam losses and protection in the LHC

HB 2004 27

Quench detection Quench detection

1. Magnet starts to quench

2. Resistive Voltage across magnet > 0.1 V

+10 ms: quench detection

• fire quench heater

• requests energy extraction

• requests a beam dumpThe quench heaters become effective

Magnet current starts to debypass magnet by diode

+5 ms: current starts to decay exponentially

+300 s: the beam dump kicker extracts beam

+ 3 ms: the interlock system transmits the request to the beam dump

Page 28: Accidental beam losses and protection in the LHC

HB 2004 28

Quench detection Quench detection

PLUS• Does not require collimators to have correct settings• If early enough, beam gone before losses• Dumps beam for failures of the quench protection system• Does not reduce the availability of LHC: Quench protection is

always required. After a quench the beam must be dumped

MINUS• Only covers beam losses due to magnet quenches• Might be too late (…being further analysed, efficiency depends on

quench process, magnet field, beam loss pattern, etc…)• Large complexity (several 1000 channels) – good post mortem

analysis required

Page 29: Accidental beam losses and protection in the LHC

HB 2004 29

Beam loss monitoring at aperture limitations Beam loss monitoring at aperture limitations

In general, collimators are limiting the aperture• Always true for beam blow up• Mostly true for orbit changes

Beam loss monitors at aperture restrictions continuously measuring beam losses

• Losses are detected within less than a turn• After detection it takes 2-3 turns to extract all particles into beam

dump block

Page 30: Accidental beam losses and protection in the LHC

HB 2004 30

Beam loss monitoring at aperture limitations Beam loss monitoring at aperture limitations

PLUS• Should capture (nearly) all types of accidental beam losses• Dumps the beam if there are really particle losses• Very fast (< 100 s)• Limited complexity (some 100 channels)• Expected to be very reliable

MINUS• Does require collimators to have correct settings and defining the

aperture• Does not catch beam losses in the arcs (for example, closed orbit

bumps)• Random spikes might trigger beam dump• Setting of thresholds not obvious - if too low, False Beam Dumps –

if too high - risk of damage

Page 31: Accidental beam losses and protection in the LHC

HB 2004 31

Beam loss monitoring around the acceleratorBeam loss monitoring around the accelerator

Beam loss monitors continuously measuring beam losses• Together with the BLMs at aperture limitations, covers most

of the LHC (all arcs)• Losses can be detected within less than a turn• After detection it takes 2-3 turns to extract all particles into

beam dump block

Page 32: Accidental beam losses and protection in the LHC

HB 2004 32

Beam loss monitoring around the acceleratorBeam loss monitoring around the accelerator

PLUS• Dumps the beam if there are really particle losses• For failures leading to orbit changes and emittance growth• Detection can be made very fast (< 100 s)• Does not require collimators to have correct settings • Catches failures that appear only in the arcs (for example, closed

bump)

MINUS• Large complexity (some 1000 channels)• Could increase number of False Beam Dumps• Setting thresholds: delicate balance between avoiding magnet

quenches and avoiding False Beam Dumps

Page 33: Accidental beam losses and protection in the LHC

HB 2004 33

Magnet current decay monitoring for critical magnets Magnet current decay monitoring for critical magnets

Very fast detection of power converter / magnet failures • Monitors change of magnet current (Hall probes, voltage, …)• Prototype “quick and dirty” gave promising results (M.Zerlauth)• Similar technique recently successfully implemented at HERA

(M.Werner)• Should be possible to detect powering failures in less than one

millisecond

Interlock signal creation using Hall-Probe

-1

0

1

2

3

4

5

6

5 10 15 20 25

Time [ms]

Vo

ltag

e [

V]

Reference Ramp Converter Hall probe readout Interlock Signal

Page 34: Accidental beam losses and protection in the LHC

HB 2004 34

Magnet current decay monitoring for critical magnets Magnet current decay monitoring for critical magnets

PLUS• Independent method to monitor failures in the powering system:

power converter fault / thunderstorm / short circuit in magnet / other problems

• Does not require collimators to have correct settings • Can be made fast (< 1ms)• Mainly for normal conducting magnets

MINUS• Needs to be demonstrated if practical (EMC, …) – wait for HERA

experience• Setting of thresholds required – could be delicate• Should be limited to a few electrical circuits with normal conducting

magnets – otherwise too complex

Page 35: Accidental beam losses and protection in the LHC

HB 2004 35

Beam position change monitors Beam position change monitors

If the orbit start to moves very fast, dump the beam

• Fast orbit changes can be observed anywhere around the LHC

• Observation for each beam, each plane, two monitors with 90 degrees phase advance: in total 8 BPMs• …system with limited complexity

• BPMs at location of high beta function, using the same monitors that are already required for machine protection (to ensure x < 4 mm in the insertion IR6 for the beam dumping system)

Page 36: Accidental beam losses and protection in the LHC

HB 2004 36

Beam position change monitors: thresholdsBeam position change monitors: thresholds

450 GeV: fastest orbit movement during normal operation by an orbit corrector magnetSuperconducting orbit correctors : 2 mm/s … 15 mm/s

Normal conducting orbit correctors: 0.6 mm/s … 1.7 mm/s

450 GeV: if the change of the orbit exceeds, say, some 10 mm/s corresponding to 0.01 mm/msec, there is something wrongDetection of very fast orbit drifts:

(IF dx/dt > 0.1 mm/ms) OR

(IF dx/dt > 1 mm/100ms) THEN beam dump

7 TeV: if the change of the orbit exceeds, say, some 1 mm/s corresponding to 0.001 mm/msec, there is something wrong(IF dx/dt > 0.05 mm/ms) OR

(IF dx/dt > 0.3 mm/100ms) THEN beam dump

numbers prelim

inary

Page 37: Accidental beam losses and protection in the LHC

HB 2004 37

Beam position change monitors Beam position change monitors

PLUS• Independent method to measure fast orbit drifts due to failures• Does not require collimators to have correct settings • Can be made fast (< 1ms)• Beam dump before particles are lost• Limited complexity

MINUS• Is it practical ? False Beam Dumps ?• Setting of thresholds delicate• What to do during injection, during kicks for Q-measurements, …

to be studied• Only for beam orbit changes, not for emittance growth• Studies needed

Page 38: Accidental beam losses and protection in the LHC

HB 2004 38

Fast beam current decay monitoring Fast beam current decay monitoring

Very fast beam current monitor, could detect losses within short time

• Measuring proton losses with, say, N / t = 1010 protons • Interlock condition

• if (N / t > Nthreshold(E) · 1010) THEN BEAM DUMP

t could be as short as one turn

• Nthreshold decreases with energy to be always efficient

• For start of LHC operation, when intensity is limited, resolution should be no problem

• Challenge: must be fast and accurate• First discussions with experts - looks promising

Page 39: Accidental beam losses and protection in the LHC

HB 2004 39

Fast beam current decay monitoring Fast beam current decay monitoring

PLUS• Independent method to measure beam losses• Does not require collimators to have correct settings • Fast for reduced accuracy (< 1ms)• Slow for high accuracy (> 10ms)• Limited complexity – one instrument

MINUS• Needs to be demonstrated if practical • Setting of thresholds required• Not sufficient for all LHC operation modes and for shortest

accidental beam losses time constants • Could be ok for 450 GeV, not for 7 TeV • Studies needed

Page 40: Accidental beam losses and protection in the LHC

HB 2004 40

Protection and redundancy at 450 GeVProtection and redundancy at 450 GeV

System Needs collimators

In time? Complete protection

Add. develop.

effort

Complexity

Y=1, N=3 Y=3, N=1 Y=3, N=1 Y=1, N=3 Y=1, N=3

Hardware diagnostics

3 1 1 3 2

Quench signal 3 3 1 3 3

Beam loss monitors collimators and aperture limitations

1 2 2 3 2

Beam loss monitors in the arcs

3 2 2 3 1

Magnet current change monitors

3 2 1 2 2

Beam position change monitors

3 3 2 2 3

Fast beam current decay (“lifetime”) monitors

2 3 3 2 3

Page 41: Accidental beam losses and protection in the LHC

HB 2004 41

Protection and redundancy at 7 TeVProtection and redundancy at 7 TeV

System Needs collimators

In time? Complete protection

Add. develop.

effort

Complexity

Y=1, N=3 Y=3, N=1 Y=3, N=1 Y=1, N=3 Y=1, N=3

Hardware diagnostics

3 1 1 3 2

Quench signal 3 2 2 3 3

Beam loss monitors collimators and aperture limitations

1 3 3 3 2

Beam loss monitors in the arcs

3 2 1 3 1

Magnet current change monitors

3 2 1 2 2

Beam position change monitors

3 3 2 2 3

Fast beam current decay (“lifetime”) monitors

2 2 2 1 3

Page 42: Accidental beam losses and protection in the LHC

HB 2004 42

ConclusionsConclusions

• Protection for LHC starts before extraction from SPS• Protection is required during the entire cycle

Large redundancy in protection

Availability of the machine due to the complex protection is an important issue

• Large energy: stringent protection required - too few interlocks could lead to severe damage of the LHC

• Unprecedented complexity: too conservative interlocking of the machine protection systems could prevent efficient LHC exploitation

• Initial operation with part of the protection systems• Commissioning of other protection systems during initial operation

Page 43: Accidental beam losses and protection in the LHC

HB 2004 43

Some questions to the workshop……..Some questions to the workshop……..

Fast beam current decay monitoring

Fast beam position change monitoring

• What can be achieved?

• Who has experience?

• Where else might such systems be required?

Page 44: Accidental beam losses and protection in the LHC

HB 2004 44

AcknowledgementsAcknowledgements

The presentation is based on the work that was performed in many groups in several CERN Departments, as well as collaborators from other labs (Fermilab, GSI, Protvino, Triumf, ….)

Contributions of many colleagues are acknowledged, in particular for the discussions in the Machine Protection WG, Collimation WG and Injection WG

particular thanks for R.Assmann, H.Burkhardt, E.Carlier, B.Dehning, B.Goddard, E.B.Holzer, J.B.Jeanneret, V.Kain, B.Puccio, J.Uythoven. M.Zerlauth ……

Page 45: Accidental beam losses and protection in the LHC

HB 2004 45

Recent question in MPWG: Can we dump the beam in time after a quench of a dipole magnet?

Beam is to be dumped before the current in the dipoles starts to decay

The sequence of following actions has to be determined beam loss causes the magnet to quench the voltage builds up and exceeds the threshold of the quench detector the quench detector detects the voltage after some time the quench detector fires quench heaters or triggers the energy extraction at the same time, the PIC is informed

PIC sends a dump request to the BIC the heaters become efficient the BIC sends a dump request to the beam dumping system the voltage exceeds the diode voltage, and the current starts to bypass the magnet the switch opens, and the current in the string of magnets decays

The Powering Interlock Controller is the only system sending (direct) beam dump request after powering failures

‘Secondary’ protection with collimators, BLM (possibly BPM / beam lifetime)

Def

ined

seq

uen

ce

Wh

o’s

qu

ick

est?

Page 46: Accidental beam losses and protection in the LHC

HB 2004 46

Hardware configuration (main dipole circuit) and signal transmission

Quenching (dipole) magnet in the arc

Beam DumpRequest

Beam Dumping System

Beam Interlock Controller

Beam DumpRequest

‘Quench Loop’ stretching over the arcs

Page 47: Accidental beam losses and protection in the LHC

HB 2004 47

The PIC process times

For main circuitsHardware Matrix (CPLD)Process time < 0.2ms

PIC Controller (PLC)Process time < 5ms

Quench Protection

System

Power Converters

Quench Signals, Discharge Requests

Power Permit, Powering Failure,Discharge Requests

Beam Dump Requests

Interlock Controller is based on a PLC controlled process, monitoring and controlling up to 45 electrical circuits (>200 signals)

For time (beam) critical circuits -> configurable hardwired matrix in parallel

Page 48: Accidental beam losses and protection in the LHC

HB 2004 48

The Timescales

T0 Quench signal

T2 PIC reads signal

T1 Quench Loop Controller Receives signal

T3 PIC issues beam dumpT4

Beam dump is received by the BIC

T5 Completion of beam dump

0.2 … 5ms < 100μs < 270μs

< 15 μs < 100 μs 5..7 ms

T1 EE system readsQuench signalT2

Switch Opening

T3 Last branch open, arc is extinct –Current in dipole magnets decays

Current in dipole circuitDiode becomes conductive > 80ms

< 15 μs< 100 μs

Decay starts somewhat before the complete arc extinction due to resistive arc // resistor

Mechanic opening & arc extinction

PIC process

Page 49: Accidental beam losses and protection in the LHC

HB 2004 49

Conclusions

Due to the delay in the switch opening of the 13kA energy extraction system, the beam is dumped before the current in the magnet starts decaying also true in case of self triggering of EE

For all other sc magnets the time constraints are less critical

For time critical signals (mainly main dipole and quadrupole circuits due to large effects on the circulating beams), a hardwired matrix within the PIC can be configured in parallel to the PLC process

What to do for nc magnets?!


Recommended