Presented to: PASS
By: AJW-22
Date: 4 Oct 2012
Federal AviationAdministrationACEPS Type II Brief
Power Services Group, AJW-22
1
Federal AviationAdministration
ACEPS TYPE II4 October 2012
Planning Phases ACEPS II• Program Plan• Engineering Design• Engineering Services • Operational Support• Generic Schedule• Site-specific Schedule• Site Coordination• Implementation Plan• Training• National Integrated Logistical Support Plan• Program Close Out• Organizational Roles and Responsibilities• OT&E
2
Federal AviationAdministration
ACEPS TYPE II4 October 2012
Program Plan• Requirements
– ACEPS Obsolete Issues– National Design– Financial – Phase I
• Temp Power, Critical Power Center (CPC) Reduction, PCMS Modification, Installation (UPS’s and switch gear are replaced in this phase)
– Phase II• EG Replacement
– Sustainment• UPS System Life Extension Program(SLEP), E/G SLEP as needed
3
Federal AviationAdministration
ACEPS TYPE II4 October 2012
Engineering Design
• EYP– Completed National Design
– Completed Equipment Specifications
– Completed Design Data Handbook
– Completed Technical Instruction Books
4
Federal AviationAdministration
ACEPS TYPE II4 October 2012
Engineering Services
• Provide Professional Services
• Interface with site Air Traffic and Service Area
• Complete Site As-Built Drawings
• Provide RE and Engineering Support as Needed
5
Federal AviationAdministration
ACEPS TYPE II4 October 2012
PSG Operational Support
• Site Adapt Technical Instruction Books
• Develop Maintenance Handbook
• Develop Operational Testing and Evaluation Plan
• Conduct Operational Testing And Evaluation
• Provide Lifecycle Management
6
Federal AviationAdministration
ACEPS TYPE II4 October 2012
Site-Specific Schedule(as of Aug 2012)
Site Survey Phase I Start Phase I Completion
• ZAN Aug/2011 June/2012 Feb/2013
• ZMA Dec/2011 Jan/2013 Sep/2013
• ZTL Jul/2012 Mar/2013 Nov/2013
• ZLA Jan/2012 May/2013 Jan/2014
• ZJX* FY 13 FY14 FY 14
• ZLC* FY 13 FY 14 FY 15
• ZMP*FY 11 FY 15 FY 15
7
Federal AviationAdministration
ACEPS TYPE II4 October 2012
Generic Schedule– Installation of Temporary Power SystemConduct Training on
Temp Power System with Vendor Training on Eaton 825 kVA UPS and L3 STS-I
– CPC Reduction– Mobilization and Kick Off Meeting– Transition of Critical Power Centers (CPCs) to Temporary
Power System– Phase 1 Demolition– New Equipment Installation– PCMS Modification– Energize ACEPS II System– Test and Commission ACEPS II System– Cutover to ACEPS II System– Remove Temp Power System and Demobilize
8
Federal AviationAdministration
ACEPS TYPE II4 October 2012
Site Coordination
• Site Survey• Program Planning Phases (CPC, Temporary
Power, Install & Mechanical)• Integrated Risk Management Checklists• Reclaim equipment space if required• Property Disposal
9
Federal AviationAdministration
ACEPS TYPE II4 October 2012
Implementation Plan
• SRMD, NCP, GSIP Complete• Submittal Packages 50 and 90 %• 100% Design Package
10
Federal AviationAdministration
ACEPS TYPE II4 October 2012
Training• Vendor Training (L3 Static Switch, Square D Switchgear,
Eaton UPS)• System Level Training at Engineering Support Facility
(ESF) in Raleigh, NC• Temporary Power OJT and Certification• AMA Course Development and transition to MMAC
11
Federal AviationAdministration
ACEPS TYPE II4 October 2012
National Integrated Logistical Support
• ACEPS – Legacy • ACEPS – Type II
– ILSP– Site Sparing– Test Equipment
12
Federal AviationAdministration
ACEPS TYPE II4 October 2012
Maintenance Requirements
ACEPS Maint. Tasks
ACEPS Other
Total ACEPS
ACEPS II Maint. Tasks
ACEPS II Others
Total ACEPS II
8-hour 6 6 30 30
Daily 28 28 0
Weekly 2 9 11 9 9
Monthly 27 12 39 32 11 43
Quarterly 38 9 47 28 16 44
Annual 46 64 110 28 83 111
2 year 2 32 34 2 30 32
5 year 14 5 19 14 5 19
294 288
Federal AviationAdministration
ACEPS TYPE II4 October 2012
Project Closeout
• Inventory• Schedule Close for Deliverables• Property Disposition• CAI/JAI• Site De-Mobilization
14
Federal AviationAdministration
ACEPS TYPE II4 October 2012
Organizational Roles and Responsibilities
• Organizational Roles and Responsibilities Charts
• The Role of the Contracting Officer (CO) and Contracting Officer’s Technical Representative (COTR)
15
Federal AviationAdministration
ACEPS TYPE II4 October 2012
16
Federal AviationAdministration
ACEPS TYPE II4 October 2012
FAA Program Office Responsibilities
• Program Management, Integration• Furnishing all new ACEPS II equipment as well as the
temporary trailers and equipment as shown on the design plans
• Scheduling vendor startup and training activities• Pursuing equipment warranty issues• Furnishing all new equipment spare parts and documentation
17
Federal AviationAdministration
ACEPS TYPE II4 October 2012
Installation Contractor Responsibilities
• Furnishing all material, tools, and labor to effect the replacement of the ACEPS critical system and the modification of the PCMS as shown on the design plans, specifications, and schedule.
• Shipment of the temporary system at the beginning of the project
• Installation, startup, and cutover of the temporary equipment• Disconnection and preparation of the temporary equipment for
shipment to the next site• Crating (palletizing) and shipment of selected removed
equipment as shown on the design plans
18
Federal AviationAdministration
ACEPS TYPE II4 October 2012
FAA Resident Engineer Responsibilities• Coordinating activities and tasks of the Installation Contractor
with the Site Facility, Technical, and Air Traffic Personnel• Coordinating access, escorts, deliveries, parking, and lay-down
areas.• Reviewing and coordinating installation plans and specifications
with the Installation Contractor• Coordinating cutover activities• Coordinating vendor startup, testing, and on-site training
activities• Preparing equipment excess/disposal forms for handover to the
Installation Contractor• Witnessing and signing off installation-related procedures such
as cable meggar and torque checks. • Implementing the lockout/tagout procedure for personnel safety.
19
Federal AviationAdministration
ACEPS TYPE II4 October 2012
FAA Technical Site Personnel Responsibilities
• Operating the ACEPS, including powering busses on and off.• Rotating loads between busses.• Opening and racking out breakers, as required, to ensure safe
working conditions.• Implementing the lockout/tagout procedure for personnel safety.• Coordinating (in conjunction with RE) and performing the transfer of
CPC loads to their alternate source to allow each CPC to be de-energized for modifications and transfers.
• Attending local and off-site vendor and FAA component and system level training and OJT courses for the new ACEPS II equipment.
• Passing FAA Certification Exams for both the Temporary and permanent ACEPS II system.
• Witnessing startup-related test procedures and field familiarization during OT&E for the new ACEPS II equipment.
20
Federal AviationAdministration
ACEPS TYPE II4 October 2012
FAA Technical Site Management Responsibilities
• Attend local project coordination meetings• Ensure proper Peabody/SAL entries for FSEP • Ensure technician certification.• Ensure proper Certification for both the Temporary and
permanent ACEPS II systems prior to cutover.
21
Federal AviationAdministration
ACEPS TYPE II4 October 2012
Installation Contractor Site Superintendent Responsibilities
• Coordinating all Installation Contractor on-site activities with the FAA site personnel.
• Coordinating (with the FAA) site access for all Installation Contractor employees and subcontractors.
• Inventorying, controlling, and tracking all new hardware.• Directing and assisting in the installation, wiring, and
energizing of the new hardware.• Maintaining a daily log of Installation Contractor on-site
activities and site conditions.• Reporting equipment warranty issues.• Submitting weekly reports as well as incident reports.
22
Federal AviationAdministration
ACEPS TYPE II4 October 2012
Installation Contractor Craft Labor Responsibilities
• Working under lockout/tagout procedures to ensure personnel safety
• Removing the existing ACEPS components and installing new components as shown on the design plans and schedule.
• Remove/replace construction opening siding, if required• Constructing and installing temporary construction barriers,
as required• Keeping the work area clean and safe.
23
Federal AviationAdministration
ACEPS TYPE II4 October 2012
FAA Equipment Vendors (Square D, Eaton, and L3)
• Verifying equipment is installed and connected in accordance with FAA and manufacturer’s requirements
• Performing FAA-approved component and system level startup and test procedures.
• Correcting deficiencies as they are found.• Providing startup and training reports, as required by the FAA
specifications
24
Federal AviationAdministration
ACEPS TYPE II4 October 2012
PSG OPS Engineering Testing Responsibilities
• Performing all inspections and tests required by the FAA Testing Specification
• Preparing required test reports, including certifying compliance with test parameters
• OT&E Results to be provided as baseline data for FRDF.
25
Federal AviationAdministration
ACEPS TYPE II4 October 2012
Questions????
26
Federal AviationAdministration
ACEPS TYPE II4 October 2012
• Arc Flash (Redundant Equipment, Reduced Energy Levels)
• De-energizing Equipment for maintenance
• IR Scanning
• Remote Operations
Safety Improvements
Federal AviationAdministration
ACEPS TYPE II4 October 2012
Wet Cell Battery
• Longer life, increased reliability• Modifications to battery room will include
spill containment, positive ventilation, hydrogen detection
• Maintenance Requirements reduced due to integrated Battery Monitoring System. E.g. specific gravity checks
• Thermal Runaway significantly less of a concern than in VRLA batteries
Federal AviationAdministration
ACEPS TYPE II4 October 2012
ACEPS II Operational Test & Evaluation (OT&E)
ACTIVITIES OVERVIEW
•Electrical installation inspection.•Vendor equipment startups.•Subsystem performance testing (UPS, STS, Batteries, and etc.)•Documentation validation (Technical Instruction Book, Standard Operating Procedures, etc.).•Logistical support validation (on site sparing and depot support).•Overall System testing
– Degraded power mode testing.– Transfer testing.
29
Federal AviationAdministration
ACEPS TYPE II4 October 2012
ACEPS II Operational Test & Evaluation (OT&E)
DELIVERABLES
•Test Plan & Schedule. – Expanded explanation of OT&E activities and time allocated for each activity.
•Punch List.– List of discrepancies found during OT&E with suggested solutions.
•Waveform Data.– Dranetz Power Disturbance Analyzers will be used to capture waveform and harmonic data of test
events.
•Battery Baseline Data.– Battery voltage and resistance readings, as well as discharge data.
•Quick Look Test Report.– High level report typically available within two weeks of completion of OT&E.
•Final Test Report.– Detailed report containing expanded explanation of OT&E test and results, typically available within 4
weeks of completion of OT&E.
30