    OBJECTIVE THE OBJECTIVE OF THIS PROCEDURE IS TO CLEAN THE

    INTERNAL SURFACE OF STEAM GENERATINGPORTION AND HEATING SURFACE(ECONOMISER)

    USING SPECIFIED CHEMICALS.BY CARRYING OUT AN

    EFFECTIVE ALKALI BOIL-0UT GREASE AND ANY

    OTHER PROTECTIVE COATING APPPLIED ON THEINNER SURFACES OF PRESSURE PARTS ARE

    REMOVED.THEN IT IS SUBJECTED TO ACID CLEANING

    FOR THE REMOVAL PATCHY MILL SCALE AND

    RUST.FINALLY THE ACID PICKLED SURFACE IS

    PASSIVATED FOR THE FORMATION OF UNIFORM AND

    COHERENT MAGNETITE LAYER

  • 7/31/2019 Acid Cleaning Ppt

    2/21

    STATE OF PLANT THE FLAP OF NRV PROVIDED IN

    ECONOMIZER FILLING LINE IS REMOVED TOFACILITAE FAST FILING AND DRANING.

    ALL THE AUXILLARIES ARE MADE READYAND AVAILABLE FOR BOILER LIGHT UP.THIS

    INCLUDES AUXILLARY STEAM,CHEMICALDOZING PUMPS,TANKS CC PUMPS,FANS OILPUMP ETC.

    NITROGEN CAPING SYSTEM AT SUITABLELOCATION FOR EASE OF PPERATION.

    PROPER NEUTRALIZATIN ARRANGEMENT TONEUTRALIZE EFFLUENT BEFORE DISPOSAL

  • 7/31/2019 Acid Cleaning Ppt

    3/21

    FOR ABO ONLY PRIMARY SEPARATOR ARE ERECTEDIN UPPER DRUM AND BAFFLE PLATE IN LOWERDRUM.SECONDARY SEPARATORS AND DRYER NOT

    ERECTED IN THE UPPER DRUM AND ORIFICE NOTERECTED IN LOWER DRUM.FOR ACID CLEANINGPRIMARY SEPARATOR IS ALSO REMOVED.

    BOILER TUBE COUPONS ARE TO BE PLACED AT TWOENDS INSIDE BOILER UPPER AND LOWER DRUMS TOEFFECTIVENESS OF CLEANING.

  • 7/31/2019 Acid Cleaning Ppt

    4/21

    MINIMUM REQUIREMENT

    ONE SET ID,FD FAN,ONE SAPH ALONG WITH OIL

    CARRY OVER PROBE,SOOT BLOWING SYSTEM,FIRE

    DETECTION SYSTEM,ROTOR STOPPAGE ALARMAND

    AIR MOTOR,LDO,SCANNER FAN,HP DOSING AND LP

    DOSING SYSTEM,ALL BCW PUMP,BAH,COMPLETION

    OF ATT FOR URNACE.

    PROVISION FOR FREE EXPANSION OF BOILER AND

    EXPANSION MARKER.BLOW DOWN SYSTEM.

    PERSONAL SAFETY EQUIPMENTS.

    PURGE WATER FOR CC PUMP.

    READINESS OF TWO ESP PASS IN ALL RESPECT.

    EYE WASH BOTTLE AND EYE SHOWER.

  • 7/31/2019 Acid Cleaning Ppt

    5/21

    CHEMICAL USEDSL NO ACID

    Blr water

    Concentr

    ation in

    %Quantity

    required Used forProcess SL NO ACIDBlr water

    Concentr

    ation in

    %

    Hydrochl

    oric acid

    (HCL) 5 % + 1 % 70 tons Acidpickling

    & soaking

    Hydrochl

    oric acid

    (HCL) 5 % + 1 %Rodine 0.20 % 800 lts Rodine 0.20 %Ammoniu

    m

    Bifloride 0.25 % 1000 kgAmmoniu

    m

    Bifloride 0.25 %

    Ammonia

    ted Citric

    Acid0.2 % 800 kg Ammoniated citric

    acid rinseAmmonia

    ted Citric

    Acid0.2 %

    Di/Trisod

    ium

    phosphat

    e

    0.1 % &

    0.2 % in

    the boiler800 &

    1500 kgs

    Neutraliz

    ation

    processDi/Trisod

    ium

    phosphat

    e

    0.1 % &

    0.2 % in

    the boiler

  • 7/31/2019 Acid Cleaning Ppt

    6/21

    STEPS FOR ABO

    Prepare chemical water in chemical

    preparation tank of 60 m3 DM water

    through boiler fill pump ,add TSP 60 kg ,add

    DSP 30 kg ,start heating through steam from

    aux PRDS and run chemical pumps onrecirculation till a temp of 50 deg is

    achieved.

    Check the chemical solution concentrationof 500 ppm of DSP and 1000 ppm of TSP is

    achieved.

  • 7/31/2019 Acid Cleaning Ppt

    7/21

    Fill the boiler through bottom ring header drain, eco linedrain ,eco inlet header drain, BCW suction lines ,( BCWdischarge valve closed ) by chemical dosing pump till

    the minimum level of tank as marked at view glass oftank .

    Raise the drum pressure up to 40 ksc in steps of 10kscand take expansion readings,maintain it at 40 ksc , takeboiler expansion reading, hold 40 ksc for 4 hrs.Collectwater samples from CBD sample point for analysis ofalkalinity ,phosphate content ,dissolved silica and oil

    content

  • 7/31/2019 Acid Cleaning Ppt

    8/21

    Kill the fire in the boiler ,give blow down of 1 minutethrough bottom ring header drain to

    IBD(front).Ensure drum level does not go out ofvision in gauge glass.(DWLG at drum)

    Raise the drum level through MDBFP, Repeat the

    operation of raising the drum pressure to 40 ksc,then hold it for 2 hrs.give blow down through bottomring header drain to water wall drain header, for 1minute after killing fire

    Repeat the same procedure and give blow downthrough ECO line drains & ECO inlet header drain

  • 7/31/2019 Acid Cleaning Ppt

    9/21

    During this process if phosphateconcentration drops to half of the initial value,

    dose additional chemicals through phosphatedosing system to achieve originalconcentration.The boil out is declared complete when the oil

    contained in analyzed sample is less than 5PPM or minimum eight blow downs (in samesequence) are completed whichever is latter.

    Box up the boiler keeping BCW pumps inservice. Allow the boiler to go under naturalcooling ( ID suction & FD discharge open.).

  • 7/31/2019 Acid Cleaning Ppt

    10/21

    Fill the boiler with hot 80 deg DM water throughchemical feeding pump upto lowest port of drum.

    Back flush the S/H with DM water containing200ppm hydrazine and PH raised to 10 withammonia till it overflows into drum. Collect thesample from the sampling points of S/H Headerand low point drains for testing.

    Drain the boiler through IBD.

    Continue the filling & draining for rinsing till thephosphate contain in sample is less than 2 ppm.

  • 7/31/2019 Acid Cleaning Ppt

    11/21

    Steps for acid cleaning

    MOCK TRIAL:

    Mock trial is to be conducted one day in

    advance so as to check the healthiness of

    various pumps, valves and other connected

    system. Boiler filling in 1 hr (approx) and

    draining in 1 hr(approx) are to be achieved.

    Boiler filling with DM water & lighting up the

    boiler to raise the temp. to 80 0c before going

    for acid injection.

  • 7/31/2019 Acid Cleaning Ppt

    12/21

    Filling of Boiler along with Acid injection(Picking/Soaking)Fill the boiler with 60-70 0C water from the 250

    mm temporary header through water walls lowpoint drain hdr. / Eco filling line/ BCW pumpsunction manifold)Once the boiler drum level is at the bottom port

    stop filling through BCW suction manifoldContinue filling through other sources.

    Fill the boiler up to the drum level is 100 mm

    above center line.

    Start Boiler Water Circulating (BCW) pumpB

    ,center pump.

  • 7/31/2019 Acid Cleaning Ppt

    13/21

    Take sample at every 10 min interval.Continue this process till the iron content is inequilibrium for 3 consecutive sample .Start draining the boiler under N2 capping to theneutralization PitDM water rinse, after Acid pickling/Soaking is

    completed: Refill the boiler with DM water at 60-70 0C.Fill up to 50 % of the gauge glass .Then startback flushing of the SH through the LTSH drain

    till the water level is raised in the drum up to 8-9ports. Continue this operation till the sampleresult pH is upto 4.0

  • 7/31/2019 Acid Cleaning Ppt

    14/21

    Ammoniated Citric Acid rinse after DM waterrinse: Start injection of citric acid solutionprepared at temporary DM filling pump discharge

    through the acid injection pump & regulation valveat the acid pump dischargeAdjust the pH at thefilling point around 3.5-4.0. Collect sample from BCW pump discharge

    header after stopping the pump & analyze foracid strength & iron concentration .Continue this operation till 3 consecutivesamples read the acid % & iron content are

    steady .This operation shall be minimum 4 hrs &maximum 5 hrs duration .

  • 7/31/2019 Acid Cleaning Ppt

    15/21

    Demineralised water rinse: Continue the boilerfilling & draining operation till the sample at pointB is having IRON < 25 ppm

    Neutralisation of the boiler system:To removeacid pockets and neutralized acid.

    Fill the boiler with TSP AND DSP Solun. Light upthe boiler & raise the pressure to 10 ksc .Hold the pressure for about 6 hrs. After 6 hrs killthe fire .

    Allow the boiler to cool naturally .Drain the boiler after metal temperature of < 90 0Cis achievedBoiler is drained with drum vents open to

    atmosphere & no N2 capping is used .

  • 7/31/2019 Acid Cleaning Ppt

    16/21

    Passivation of Boiler :TO MAKE A LAYER OFMAGNETITE COATING ON PICKLED SURFACEFill the boiler with DM water & inject the preparedblended solution so that the final water having 200ppm of N2H4 & pH of 10 is feed to the boiler .Lightup the boiler at slow rate .

    Raise the drum pressure to 40 ksc & hold it for 24hrsAfter 24 hrs shut down the boiler & allow it to cooldown slowly .

    Neutralisation of boiler effluentsAs soon as the acid is drained to the neutralizing pitcaustic soda is added to neutralize .As soon as the citric acid is drained to the

    neutralizing pit caustic soda is added to neutralize .

  • 7/31/2019 Acid Cleaning Ppt

    17/21

  • 7/31/2019 Acid Cleaning Ppt

    18/21

  • 7/31/2019 Acid Cleaning Ppt

    19/21

  • 7/31/2019 Acid Cleaning Ppt

    20/21

  • 7/31/2019 Acid Cleaning Ppt

    21/21