+ All Categories
Home > Documents > ad de Taludes by SteveYaeger

ad de Taludes by SteveYaeger

Date post: 08-Apr-2018
Category:
Upload: ctorres88
View: 220 times
Download: 0 times
Share this document with a friend

of 12

Transcript
  • 8/7/2019 ad de Taludes by SteveYaeger

    1/12

    Slope Stability and Methods of Increasing the Factor of Safety

    By Steve YaegerECI 281a

    University of California, Davis

    Department of Civil and Environmental Engineering

    Introduction

    Slope stability is one of the fundamental problems faced on a consistent basis by the

    majority of practicing Geotechnical Engineers. This is why slope stability analysis is

    emphasized both at the undergraduate and more so at the graduate level of Geotechnical

    studies. Currently one can find and use multiple computer programs to perform anything

    from integration and analysis of seepage through a section of an earth dam to an analysis

    of the stability of a slope. It is in some ways it could be considered engineering by

    Windows. Computers and computer programs are a very large part of current

    engineering practice. So much so that it is very easy to forget the engineering principles

    on which the programs are founded.

    This paper serves to review and summarize some of the simpler techniques for the

    analysis of slope stability as well as their applications and limitations.

    This paper will also review techniques for increasing the factor of safety of unstable

    slopes including the use of tiebacks, and the construction of stone columns. A case study

    of the Forks of Butte project that used tiebacks as a stabilization method will also be

    reviewed.

    Techniques of Slope Stability Analysis

    The following analysis techniques will be reviewed in this section:

    1) Ordinary Method of Slices.

    2) Simplified Janbu Method.

    3) Simplified Bishop Method.

  • 8/7/2019 ad de Taludes by SteveYaeger

    2/12

    All of the above methods of analysis divide a slide mass into a number of slices and

    analyze the individual slices as seen in Figure 1. Dividing up the soil mass into a number

    of slices allows one to accommodate differing slide mass geometries, stratified soils

    within the mass and external loads.

    Figure 1 Illustration of Division of Sliding Mass into Slices (Abramson et al., 1996).

    F = Factor of Safety ZL = left interslice forceSa = available strength ZR= right interslice force

    Sm = mobilized strength L = left interslice force angle

    U = pore water force R= right interslice force angle

    U = surface water force hL = height of force ZL

    W = weight of slice hR= height of for ZRN = effective normal force = inclination of slice base

    Q = external surcharge = inclination of slice topkv = vertical seismic coefficient h = average height of slice

    kh = horiz. seismic coefficient hc = height of centroid of slice

    Figure 2 Forces acting on a typical slice. (Abramson et al., 1996)

  • 8/7/2019 ad de Taludes by SteveYaeger

    3/12

    Ordinary Method of Slices

    This method assumes that the resultant of interslice forces is inclined such that it is

    parallel to the base of the slice. This assumption does not satisfy interslice force

    equilibrium. Please see the following equations derived from Figure 2 and the above

    assumption:

    )cos()cos(cos)1(sin' +++= QUkWWkUN vh

    The mobilized shear strength at the base of each slice is determined using the following

    equation:

    F

    NCSm

    tan'+=

    The moment equilibrium of the slices about a common center of the circular failure

    surface is

    =

    ++=n

    i

    vo RQUkWM1

    sin]coscos)1([

    =

    +n

    i

    hRQU1

    )cos](sinsin[

    = =

    =+n

    i

    n

    i

    chm hRWkRS1 1

    0)]cos([][

    If the factor of safety F is assumed to be the same for all of the slices then the following

    can be derived:

    =

    =

    +

    =

    =n

    i

    n

    i

    AAA

    NC

    F

    1

    321

    1

    )tan'(

    )(cos

    ))(cossinsin(

    sin)coscos)1((

    3

    2

    1

    R

    hWkA

    R

    hQUA

    QUkWA

    ch

    v

    =

    +=

    ++=

  • 8/7/2019 ad de Taludes by SteveYaeger

    4/12

    Simplified Janbu Method

    The simplified Janbu Method assumes zero interslice shear forces and does not satisfy

    moment equilibrium. However, the simplified Janbu method does satisfy vertical force

    equilibrium and overall horizontal force equilibrium.

    The normal effective stress at the base of each slice can be determined with the following

    equations:

    cos

    coscos)1(sincos'

    QUkWSUN

    vm +++=

    The overall horizontal force equilibrium for the slide mass is determined from the

    following:

    =

    = =

    =+

    +

    +++=

    n

    i

    n

    i

    n

    i

    hiH

    F

    NCQ

    UWkUNF

    1

    1 1

    0]costan'

    sin[

    ]sinsin)'[(][

    It then follows that the Factor of Safety F can be determined with the following equation:

    sinsinsin

    sin'

    cos]tan'[

    4

    1

    4

    1

    QUWkUA

    NA

    NC

    F

    h

    n

    i

    n

    i

    +++=

    +

    +

    =

    =

    =

    The Simplified Janbu Method does not satisfy moment equilibrium for the slide mass, as

    mentioned earlier. Therefore, Janbu performed more rigorous solutions and compared

    the result to those found using his simplified method. He then presented the following

    chart as seen in Figure 3 to correct for his over-determined solution.

  • 8/7/2019 ad de Taludes by SteveYaeger

    5/12

    Figure 3 Janbus Correction factor for his simplified method

    FJanbu=fo * Fcalcualted

    Simplified Bishop Method

    The Simplified Bishop assumes zero interslice shear forces, satisfies moment equilibrium

    around the center of a circular failure surface and satisfies vertical force equilibrium.

    The moment equilibrium of the sliding mass is given by the following:

    = =

    =

    =

    =+

    +

    ++=

    n

    i

    n

    i

    chm

    n

    i

    n

    i

    vo

    hRWkRS

    hRQU

    RQUkWM

    1 1

    1

    1

    0)]cos([][

    )cos](sinsin[

    sin]coscos)1([

    The factor of safety, F, can be determined from the following:

    =

    =

    +

    +

    =n

    i

    n

    i

    AAA

    NC

    F

    1

    765

    1

    tan'

    )(cos

    ))(cossinsin(

    sin)coscos)1((

    7

    6

    5

    R

    hWkA

    R

    hQUA

    QUkWA

    ch

    v

    =

    +=

    ++=

  • 8/7/2019 ad de Taludes by SteveYaeger

    6/12

    The vertical effective stress at the base of the slice can be determined by summing the

    vertical forces:

    ]tantan

    1[cos

    ]coscoscossin

    )1([1

    '

    Fm

    QUUF

    CkW

    mN v

    +=

    ++=

    Bishops Simplified Method does not satisfy horizontal force equilibrium for one of the

    slices and can only be applied to circular surfaces. As can be seen from the simplicity of

    the above equations the method is very easy and can provide results within five percent

    of those found with more rigorous methods.

    The methods described above are very simple, however with simplicity comes

    limitations. Failure is assumed to begin when the factor of safety on the failure surface is

    equal to one therefore the stress-strain relationship is neglected (i.e. the methods to not

    allow for strain hardening of the soil.) The methods mentioned above also assume a

    constant factor of safety along the failure surface. This error in this assumption is

    amplified when there are different soils along the failure plane.

    Methods of Increasing the Factor of Safety

    It is very well known fact that slopes fail. They fail for a variety of reasons. One may be

    excavation of the toe of an embankment removing the balancing moment of the slope and

    causing failure. Another could be an increase in pore pressure along the failure plane and

    a corresponding decrease in vertical effective stress and a loss of strength.

    There have been methods developed to help stabilize failing slopes and reinforce slopes

    that could fail. This section will discuss two techniques that are used to reinforce existing

    failures, installation of tiebacks and the installation of stone columns. It will be seen thatthese methods can be very effective, if utilized correctly, stabilizing existing failures and

    increasing the strength of slopes on the verge of failing.

  • 8/7/2019 ad de Taludes by SteveYaeger

    7/12

    Tiebacks

    The concept of tiebacks is basically that one carries the lateral earth pressure with a tie.

    The tie transfers the lateral load of the soil to a zone of soil or rock located beyond the

    failure plane as can be seen in Figure 4.

    Figure 4 Illustration of Tieback Mode of Stabilization

    The following design guideline should be used when working with tiebacks:

    1) Tiebacks are typically installed in cohesionless soils

    2) Typically have a design load of 50-130 tons (for ease of installation and size of

    equipment required.

    3) The length if the tieback should be selected such that the anchorage zone is

    beyond the original failure plane.

    4) Shallow failure surfaces typically only require one row of tiebacks.

    5) The inclination of the tiebacks should be between 10 and 30 degrees from the

    horizontal.

    6) There should be a minimum of 15 feet of overburden above the zone of

    embedment.

    7) All permanent tiebacks should be corrosion resistant.

  • 8/7/2019 ad de Taludes by SteveYaeger

    8/12

    Stone Columns

    Stone columns increase the factor of safety by two means:

    1) Increases the average shear resistance of a soil by displacing or replacing the soil

    with a series of gravel columns. (Reference Figure 5)2) Columns act as a drain to decrease the effective stress in the soil and thereby

    increase the strength along the failure surface.

    According to Abramson et al. (1996) stone columns should be used in soils with shear

    strengths in the range of 200-1000lb/ft2. Soils in the lower range of these limits may not

    provide enough lateral support and thus the soil will consume too much stone to make the

    method cost effective. Soils in the higher range may not benefit from the placement of

    stone columns.

    Figure 5 Use of Stone Columns to Stabilize Slopes

    The interested reader is encouraged to reference Abramson et al. (1996) for design

    techniques.

    Case Study

    This case history takes us to Northern California, approximately 30 miles east of Chico,

    California, to the Forks at Butte hydroelectric project. The project site was located on a

    large landslide deposit (a section through the deposit along with the construction

    alterations can be seen in Figure 6.)

  • 8/7/2019 ad de Taludes by SteveYaeger

    9/12

    Figure 5 Section of Existing Site Conditions Prior to Remediation

    As can be seen in Figure 5 the activities until failure included installation of a tensar wall

    and excavation of the area at the top of the wall along with the installation of tiebacks to

    support the new face of the slope. Slope movement was detected with the use of slope

    inclinometers. All construction activity halted when slope movement was detected.

    As can be seen in figure 5 the reason for movement was due to the excavation of the toe

    of the slope causing an unbalance in the moment of the slope. Tiebacks were install to

    maintain the face of the cut in slope however as seen in figure 5 they were useless in

    increasing the factor of safety of the slope due to the fact that they did not extend beyond

    the failure plain.

    After considerable analysis it was determined to increase the factor of safety with a

    combination of techniques. The first was using a buttress fill at the toe of the large slope

    as can be seen in Figure 6. This technique was not discussed in this paper however is

    pretty simple to see that by placing the buttress fill one is increasing the balancing

  • 8/7/2019 ad de Taludes by SteveYaeger

    10/12

    moment of the slope similar to replacing what was excavated in this application. The

    second was the installation of additional tiebacks.

    Figure 6 Section of Site after Remediation

    Five additional rows of tieback were installed above the cut slope that extended into the

    bedrock underlying the site. Five additional rows of tiebacks were also placed at the very

    bottom toe of the slope and were also embedded in the underlying bedrock.

    Figure 7 Slope Inclinometer Data

    As can be seen from the slope inclinometer data in Figure 7 the remediation activities

    were successful. Upon completion the movement ceased.

  • 8/7/2019 ad de Taludes by SteveYaeger

    11/12

    Conclusions

    This paper has discussed methods of analytical analysis of the factor of safety of slopes

    along with methods of increasing the factor of safety and finally a case study

    demonstrating the effectiveness of one of the remediation techniques.

    Currently there are several slope stability analysis computer programs on the market that

    can analyze much more complex slopes and conditions then any gifted engineer could all

    in a matter of seconds. It then becomes the engineers responsibility to examine the

    output and determine if the program was effective in its analysis. Most of the time the

    computer will be right if all of the parameters have been specified correctly. One still

    needs to check.

    The methods of analysis are useful for that purpose, to anticipate the solution prior to

    running the program. After all this author would content that if you cant estimate the

    solution prior to letting something else do it for you then you have no business trying to

    solve the problem.

    Methods of increasing the factor of safety were also discussed. There will always be

    circumstances as illustrated in the previous case study where construction activities begin

    and unbalance a slope or disturb and existing failure. Those mistakes can be costly and

    life threatening. It then becomes essential to be able to fix the problem. The methods

    discussed along with countless others can and should be utilized in practice to save not

    only ongoing construction sites but existing structures as well.

    References

    Powrie, William (1997), Soil Mechanics Concepts and Applications, E&FN Spon,

    London, England

    Abramson, Lee W., Lee, Thomas S., Sharma, Sunhill, Boyce, Glenn M. (1996), Slope

    Stability and Stabilization Methods, John Wiley & Sons, Inc., New York, New York.

  • 8/7/2019 ad de Taludes by SteveYaeger

    12/12

    Klein, S.J., Hughes, D.K. (1992) Slope Stabilization at the Forks of Butte Project,

    Stability and Performance of Slopes and Embankments II, Geotechnical Special

    Publication No. 31, Session 7


Recommended