+ All Categories
Home > Documents > Adams Solar PV Project

Adams Solar PV Project

Date post: 09-Sep-2015
Category:
Upload: pcelis
View: 53 times
Download: 3 times
Share this document with a friend
Description:
Solar PV
Popular Tags:
24
18/02/2014 NERSA – PUBLIC HEARINGS 18/02/2014 NERSA – PUBLIC HEARINGS Northern Cape PV Project – 82,5MW ADAMS SOLAR PV PROJECT PUBLIC HEARING KIMBERLEY 18 FEBRUARY 2014
Transcript
  • 18/02/2014 NERSA PUBLIC HEARINGS 18/02/2014 NERSA PUBLIC HEARINGS

    Northern Cape PV Project 82,5MW

    ADAMS SOLAR PV PROJECT PUBLIC HEARING KIMBERLEY 18 FEBRUARY 2014

  • 18/02/2014 NERSA PUBLIC HEARINGS 2

    PREFERRED BIDDER IPPID RE_PV_0006_004

    Adams Solar PV Project Two (Pty) Ltd 2012/114124/07 Preferred bidder in REIPPPP Round 3 Registered address: No. 3 Atherstone Bower, 77 King Edward Road, Lombardy East 2090 Johannesburg, South Africa PO Box 2005, Edenvale 1610

    Tel:

    Alternative:

    Email:

    071 299 1468

    072 261 6601

    [email protected]

    PROJECT COMPANY General information

    18/02/2014

  • 18/02/2014 NERSA PUBLIC HEARINGS

    COMPANY STRUCTURE: SPV, EPC and O&M Contractors

    18/02/2014 NERSA PUBLIC HEARINGS 3

  • 18/02/2014 NERSA PUBLIC HEARINGS

    THE SPONSOR COMPANY OVERVIEW Enel Green Power South Africa BV

    A subsidiary of Enel Green Power SpA, the Renewable company of Enel SpA the biggest Italian Electricity Group

    Established in 2013, specifically for participation in the Third Bid Submission Phase of the Department of Energys IPP-Renewable Procurement Programme

    Awarded in the Third Bid Submission Phase for 6 Renewable Projects (4 PV and 2 WIND) > 500 MW

    Participating in Upington PV Project (Northern Cape) awarded during the Second Submission Phase, currently under construction

    Focused on long term presence and complex business plan in South Africa

    18/02/2014 NERSA PUBLIC HEARINGS 4

  • 18/02/2014 NERSA PUBLIC HEARINGS 5

    Italy&Europe

    Capacity: 4,112 MW Production: 15.3

    TWh Technologies:

    North America

    Capacity: 1,679 MW Production: 4.9 TWh

    Technologies:

    Iberia & Latin America

    Capacity: 2,898 MW Production: 8.5 TWh

    Technologies:

    Capacity by technology

    Production by technology

    1. Reported capacity as of September 30, 2013. Reported production latest twelve months 2. Including co-generation

    Geo Hydro Wind Biomass Solar

    2

    Total = 8.7 GW

    30%

    9%

    57%

    3% 1%

    2 2

    Total = 28.7 TWh

    39%

    20%

    38%

    1% 2%

    2 2

    ENEL GREEN POWER GLOBAL PRESENCE September 2013

  • 18/02/2014 NERSA PUBLIC HEARINGS

    Presence in 40 countries Installed capacity 97,800 MW Annual production

    296 TWh EBITDA 16.7 Bln Customers

    61 million Employees

    73,700 Capex 2013-17 27 Bln

    ENEL TODAY An international energy operator

    Data as of 31.12.2012.

    Stock exchange Enel is listed on the Milan stock exchange (~1.33 mln shareholders). 14 companies of the Group are listed on Milan, Madrid, Mosca, New York stock exchanges and in other Latin American countries

    6

  • 18/02/2014 NERSA PUBLIC HEARINGS

    THE SPONSOR COMPANY OVERVIEW Enel Green Power South Africa BV

    The primary investment vehicle of the Royal Bafokeng Nation (RBN), a community of approximately 150 000 Tswana-speaking people in South Africas North West Province

    Established in 2006 as a community-based investment company

    Holding assets across the mining, financial services, infrastructure, oil and gas services and industrial sectors

    Looking for stable and long term growing investments

    18/02/2014 NERSA PUBLIC HEARINGS 7

  • 18/02/2014 NERSA PUBLIC HEARINGS 8

    LOCATION OF THE PV PLANT

    The Adams Solar PV project is situated in the Northern Cape Province, 21 kilometers south of Hotazel and 39 kilometers north of Kathu along the R380 tarred road joining these two towns, on the farm Adams 328. The site adjoins the tarred road to the east, while Mamatwan manganese mine (owned by the BHP Billiton mining group) occurs west of the tarred road and open pit excavations occur roughly 2 kilometers west of the site

    Latitude 27 22' 13.32" S` Longitude 23 05' 52.36" E

  • Use: Insert Classification

    18/02/2014 9 NERSA PUBLIC HEARINGS

    PV PLANT GENERAL TECHNICAL INFORMATION

    Address: Farm Adams, Number 328, Portion 0 Kuruman RD, Joe Morolang Municipality Total Area: 275 ha Generation type: Solar Photovoltaic Plant (PV) Expected Commissioning: August 2016 Planned Capacity: 82.5 MWp DC Estimated annual output: 167 GWh average over 20 years Specific Output: 2032 kWh/kWp/annum CO2 Saved: 150981 tons/year Coal Saved: 40000 tons/year

    PV Module Technology: Thin Film Mounting Structure: Fixed ground mounted 14 x 3

    portrait tilted at 20, oriented at 0N

  • Use: Insert Classification

    18/02/2014 10 NERSA PUBLIC HEARINGS

    PV PLANT SITE & GRID CONNECTION 1/2

    The proposed construction of a line from the Project site to the Dougnor substation was dependant on the construction of a second line between the Dougnor Substation and the nearby Ferrum-Umtu 132kV line. This second line has been delayed and therefore it will no longer be possible for Adams Solar PV 2 to supply into the Dougnor substation. As a direct consequence the solution as presented in the Cost Estimate Letter is no longer feasible. The new solution under consideration involves the construction of a Switching Station adjacent to the Ferrum Umtu line. A line of roughly 700m between the on-site transformer and this switching station will be built. Eskom proposes this as a Self-Build project.

  • Use: Insert Classification

    18/02/2014 11 NERSA PUBLIC HEARINGS

    Dougnor Station 132kV/32kV

    New Ferrum-Umtum OHL ADAMS PV PLANT

    Switching Station

    PV Plant Step Up

    700 m OHL between Step-Up

    and Switching Station

    PV PLANT SITE & GRID CONNECTION 2/2

  • 18/02/2014 NERSA PUBLIC HEARINGS 12

    LIST OF PERMITS

    Permit Status Comments EA Granted Date: 28/03/2013

    Civil Aviation Granted Date: 17/06/2013 Heritage Consent Granted Date: 20/04/2012 Consent for Subdivision of Agricultural Land

    Expected Mid March

    Currently drafting approval letter

    Consent for Site Access Granted Date: 12/07/2013

    SKA Approval Granted Date: 19/07/2013

    DMR Consent Granted Date: 28/11/2012

    LCC (Land Claim Consent) No Claims Date: 13/08/2012 Water General Authorization Submitted To be obtained prior to Financial Close Consent to Change Land Use - Rezoning

    Granted Approved by Municipality (22/01/2014)

    Building Plan Approval Pending To be obtained prior to Financial Close

  • 18/02/2014 NERSA PUBLIC HEARINGS

    FINANCIAL INFORMATION

    Construction Operations Start date 01-Jul-14 01-Aug-16 Duration 25 months 20 years End date 31-Jul-16 31-Jul-36

    TIMING

    Capital Costs % of Total Modules 37.2% BOP 58.1% Land Acquisition 0.2% Development Costs 2.5% Connection - Eskom 0.3% Connection - EPC 0.6% Scada (BOP - Movable) 0.1% Engineering costs 0.1% Safety costs 0.9%

    Socio Economic Development 0.1% TOTAL 100%

    CAPEX SUMMARY AND DRAWDOWN PROFILE

    0% 10% 20% 30% 40% 50% 60% 70% 80% 90%

    100%

    01-J

    ul-1

    4 01

    -Aug

    -14

    01-S

    ep-1

    4 01

    -Oct

    -14

    01-N

    ov-1

    4 01

    -Dec

    -14

    01-J

    an-1

    5 01

    -Feb

    -15

    01-M

    ar-1

    5 01

    -Apr

    -15

    01-M

    ay-1

    5 01

    -Jun

    -15

    01-J

    ul-1

    5 01

    -Aug

    -15

    01-S

    ep-1

    5 01

    -Oct

    -15

    01-N

    ov-1

    5 01

    -Dec

    -15

    01-J

    an-1

    6 01

    -Feb

    -16

    01-M

    ar-1

    6 01

    -Apr

    -16

    01-M

    ay-1

    6 01

    -Jun

    -16

    01-J

    ul-1

    6

    ZAR

    cos

    ts

    Cumulative Capex Spend

    13

  • 18/02/2014 NERSA PUBLIC HEARINGS

    KEY TENETS OF IMPACTFUL ED

    1. Learn from Historical Lessons

    Involve community from the beginning

    Plan for worker demobilisation

    2. Compliance Is Threshold, Development Is Target

    3. Give The Communities Voice

    4. Recognise Existing Assets: Leverage Resources

    5. Legacy achieved only through Sustainability

    14

  • 18/02/2014 NERSA PUBLIC HEARINGS

    JOB CREATION

    Sub-Elements Compliance Obligations

    Construction Jobs

    Operations Jobs

    Beyond Compliance

    South African Citizens 93.34% 4 973pm= 414 jobs

    17 320pm= 1443 jobs

    Youth and women ensuring representation via EPC contractors

    Black Citizens 78.06% 3 449pm= 287 jobs

    15 180pm= 1265 jobs

    On-site apprenticeship for unskilled labour

    Skilled Black Citizens

    56.24% 463pm = 39 jobs 3 500pm= 292 jobs

    Demobilisation strategy that will focus on post-construction education (bursary)

    Local Citizens 61.81% 2 472pm = 206 jobs

    12 280pm= 1023 jobs

    On-site training for O&M phase (diploma programmes)

    15

  • 18/02/2014 NERSA PUBLIC HEARINGS

    Sub-Elements Compliance Obligations Beyond Compliance

    Key Components 51,87% Early identification of key suppliers- WOV, QSEs, SMES, local suppliers

    Local supplier Chain Support- formalisation & record keeping

    Educate SMMEs & WOV about RE Opportunities

    Marketing: Cross-project linkages despite different EPC/O&M

    LOCAL CONTENT

    16

  • 18/02/2014 NERSA PUBLIC HEARINGS

    Sub-Elements Compliance Obligations Beyond Compliance

    BBBEE 77,04% Early identification of key suppliers- WOV, QSEs, SMES, local suppliers

    QSE 17,7% Local supplier Chain Support- formalisation & record keeping

    Women Owned Vendors 5,26% Educate SMMEs & WOV about RE Opportunities

    Marketing: Cross-project linkages despite different EPC/O&M

    PREFERENTIAL PROCUREMENT

    17

  • 18/02/2014 NERSA PUBLIC HEARINGS

    Sub-Elements Compliance Obligations Beyond Compliance

    Black People 100% 100% Black top management

    Women 50% Skills development in key areas to grow IPP specialisation

    Working with willing BEE partners to become true Energy Service Providers

    MANAGEMENT CONTROL

    18

  • 18/02/2014 NERSA PUBLIC HEARINGS

    Sub-Elements Compliance Obligations

    Beyond Compliance

    Enterprise Development Contributions

    0,6% Invest in ED during construction to leverage project opportunities

    Develop local industry to respond to the infrastructure needs of the sector & beyond

    Connect local enterprises to national & global value chains

    Create community-based development professionals

    Measure Impact, not just accounting for expenditure

    ENTERPRISE DEVELOPMENT

    19

  • 18/02/2014 NERSA PUBLIC HEARINGS

    Sub-Elements Compliance Obligations

    Beyond Compliance

    Socio-Economic Development Contributions

    1,5% First SED project to be implemented during construction phase to avoid delayed social benefit

    Link skills development to enterprise opportunities to ensure post-qualification demand

    Measure Impact, not just accounting for expenditure

    Build a local development institution with research, fund-raising and project management capabilities

    SOCIO-ECONOMIC DEVELOPMENT

    20

  • 18/02/2014 NERSA PUBLIC HEARINGS

    45 Participants in focus groups drawn randomly from various

    communities

    5 Semi-Structured Interviews with leaders ranging from Black

    Farmers Union to Govt. LED Officer

    Community Priorities: 1. Health Care 2. Education

    3. Jobs on existing infrastructure & mining projects

    IDP Priorities: 1. Water & Sanitation 2. Road Maintenance 3. LED- SMME Dev

    Results of Primary & Secondary Data

    Analysis

    SOCIO-ECONOMIC NEEDS ASSESSMENT

    21

  • 18/02/2014 NERSA PUBLIC HEARINGS

    Key Beneficiary Communities Tlapeng

    Tsineng

    Matoro

    Magobing

    Dinokaneng

    Magojaneng

    Tsineng-Kop

    Masankong

    Mokalanoga

    Kanana

    Gasese

    Gatshekedi

    Maipeng

    The PRA Tools also revealed the

    relative development status of each

    community

    DEFINING THE COMMUNITY

    22

  • 18/02/2014 NERSA PUBLIC HEARINGS

    Construction Phase Targeted Need

    Agricultural exchange programme Agricultural skills Transfer & Social Cohesion

    Enterprise Development Developing SMMEs to become procurement ready

    Operations Phase (first 5 years) Targeted Need

    Community-Owned Jobs Fund Job Creation & Bridging work experience gap

    ENELSI Training programme Developing construction workers skills

    Starting Chance: ECD Addressing education from developmental phase

    SMME Support Technical and financial support for new and existing entrepreneurs

    Community Healthcare Developing NGO capacity to deal with diagnostic health services & mental wellness

    PROGRAMMATIC RESPONSE

    23

  • 18/02/2014 NERSA PUBLIC HEARINGS

    A training programme to develop technical skills in solar photovoltaic, solar PV installation and general business management

    1. Basics and advanced elements of electricity & solar photovoltaic

    2. How to set up and manage an enterprise

    3. Business plan of a solar PV installation

    4. Client relationship management

    Key Outputs

    Trainees will be capable to deliver solar photovoltaic installations throughout South Africa.

    Graduates to set-up and manage small businesses individually or as small groups.

    Long-term Vision

    EGP franchising network for rooftop installations

    Preferential procurement for EGP Programme Graduates

    ENEL GREEN POWER Flagship training programme

    24

    ADAMS SOLAR PV PROJECTPUBLIC HEARINGKIMBERLEY18 FEBRUARY 2014Slide Number 2COMPANY STRUCTURE: SPV, EPC and O&M ContractorsTHE SPONSOR COMPANY OVERVIEWEnel Green Power South Africa BVENEL GREEN POWER GLOBAL PRESENCESeptember 2013ENEL TODAYAn international energy operator THE SPONSOR COMPANY OVERVIEWEnel Green Power South Africa BVSlide Number 8Slide Number 9Slide Number 10Slide Number 11Slide Number 12FINANCIAL INFORMATIONKEY TENETS OF IMPACTFUL EDJOB CREATIONSlide Number 16Slide Number 17Slide Number 18Slide Number 19Slide Number 20Slide Number 21Slide Number 22Slide Number 23Slide Number 24


Recommended