Adani
Appendix E9 – Traffic Engineering Report
Abbot Point Coal Terminal 0 EIS • Adani
Terminal 0 Environmental Impact Statement
TTM Consulting Pty Ltd
41 105 037 045 Brisbane | Gold Coast | Sunshine Coast Melbourne | Sydney | Singapore
PO Box 949
Maroochydore, QLD 4558
t (07) 5479 2455 f (07) 5479 3651
www.ttmgroup.com.au
EIS Traffic and Transport Assessment
Adani T0 Project
Abbot Point, Qld
Prepared for:
Adani
May 2013
Reference: 12SCT0042/Rep03
Traffic Engineering Report
© 2013 - TTM Consulting Pty Ltd Reference: 12SCT0042/03
i T:\Projects\12SCT\12SCT0042 Abbot Point EIS\Reports\RFI Update May 2013\EIS Traffic and Transport Assessment 20 May 2013.docx
EIS Traffic and Transport Assessment Adani T0 Project: Abbot Point, QLD
© 2013 - TTM Consulting Pty Ltd
ABN 41 105 037 045
Level 1/8 First Avenue, Maroochydore
PO Box 949 Maroochydore QLD 4558
T: (07) 5479 2455 F: (07) 5479 3651 E: [email protected]
Document Status
Rev No.
Author Reviewed / Approved
Description Date Name Signature
01 G Harris P Penman
Draft 19.09.2012
02 G Harris P Penman
Final 23.10.2012
03 G Harris P Penman
Update 20.05.2013
© 2013 - TTM Consulting Pty Ltd Reference: 12SCT0042/03
ii T:\Projects\12SCT\12SCT0042 Abbot Point EIS\Reports\RFI Update May 2013\EIS Traffic and Transport Assessment 20 May 2013.docx
EIS Traffic and Transport Assessment Adani T0 Project: Abbot Point, QLD
Table of Contents
Executive Summary v
1 Introduction 1
1.1 Project Overview 1
1.2 Investigation Process 1
1.3 References 1
1.4 Scope 1
1.5 Consultation 2
2 Project Profile 3
2.1 Project Description 3
2.2 Project Timeframes 3
2.3 Staffing Operation 5
2.3.1 T1 – Existing Staffing Model 5
2.3.2 T0 – Staffing Model 6
2.3.3 Construction Workforce 7
2.4 Heavy Vehicle Movements 7
2.5 Description of Proposed Vehicles 8
2.6 Site Access 8
2.7 Other Relevant Projects 8
3 Regional Context 9
3.1 Project Location 9
3.2 Existing and Proposed Port Infrastructure 9
3.3 Existing Road Network 9
3.3.1 Bruce Highway 9
3.3.2 Abbot Point Road 10
3.4 Major Structures 11
3.5 Public Transport and School Bus Routes 11
3.6 Future Road Improvement Projects 11
3.7 Rail Access 11
4 Development Traffic Generation and Distribution 12
4.1 Basis for Traffic Impact Analysis 12
4.2 Existing Operations: Traffic Demands 12
4.3 Construction Stage: Traffic Demands 14
© 2013 - TTM Consulting Pty Ltd Reference: 12SCT0042/03
iii T:\Projects\12SCT\12SCT0042 Abbot Point EIS\Reports\RFI Update May 2013\EIS Traffic and Transport Assessment 20 May 2013.docx
EIS Traffic and Transport Assessment Adani T0 Project: Abbot Point, QLD
4.3.1 Construction Stage: Heavy Vehicle Traffic Generation 14
4.3.2 Construction Stage: Workforce Traffic Generation 19
4.3.3 Construction Stage: Traffic Distribution 20
4.4 Completed Works/Operational Stage: Traffic Generation 21
4.4.1 Operational Traffic 21
4.4.2 Completed Works/Operational Stage: Traffic Distribution 22
4.5 Impacts of Decommissioning 22
5 Traffic Operation Assessment 23
5.1 Introduction 23
5.2 Average Annual Daily Traffic (AADT) 23
5.3 Road Corridor Capacity Criteria 24
5.4 Bruce Highway Operational Performance 25
5.5 Construction Stage 26
5.6 Operational Stage 26
5.7 Proposed Haulage Route 27
6 Site Access Review 28
6.1 Introduction 28
6.2 Existing Intersection Layout 28
6.3 Accident Review 28
6.4 Sight Distance Review 28
6.5 Intersection Turn Warrant Requirement Review 28
6.6 Right and Left Turn Requirements 30
6.7 Intersection Capacity Review 30
6.8 Uninterrupted Flow Conditions 30
6.9 Adjacent Bruce Highway Intersections 31
6.10 Updated Traffic Capacity Assessment 31
7 Road Pavement Impact Assessment 32
7.1 Existing ESA Pavement Loadings 32
7.2 Development Heavy Vehicle Generation & Impacts 32
7.3 Mitigation Review 33
8 Draft Road-use Management Plan (RMP) 34
8.1 Introduction 34
8.2 Draft RMP Policy Statement 34
8.3 Draft RMP Objectives 34
8.4 Draft RMP Implementation Strategy 34
© 2013 - TTM Consulting Pty Ltd Reference: 12SCT0042/03
iv T:\Projects\12SCT\12SCT0042 Abbot Point EIS\Reports\RFI Update May 2013\EIS Traffic and Transport Assessment 20 May 2013.docx
EIS Traffic and Transport Assessment Adani T0 Project: Abbot Point, QLD
8.5 Draft Implementation Strategy 35
8.5.1 Driver Fatigue Policies 35
8.5.2 Driver Behaviour Policies 35
8.5.3 Work Related Travel and Transport Policies 35
8.5.4 Over-dimension Vehicle Management 35
8.5.5 Road Safety Audit Review, Capacity & ALCAM Assessment 36
8.5.6 Road Noise Management 36
8.5.7 Dust Control Management 36
8.5.8 On-site Parking Management 36
8.5.9 Dangerous Goods Management 37
9 Conclusions and Recommendations 38
Table Index Table 2.1: Existing and Proposed Projects Abbot Point 8
Table 3.1: Local Road Hierarchy 9
Table 4.1: Existing Operational Traffic 13
Table 4.2: Construction Vehicle Requirements (External to Site) 17
Table 4.3: Full Operational Site Traffic Generation 21
Table 5.1: Existing AADT Volumes on State-Controlled Roads 23
Table 5.2: Two Lane Rural Road Capacity – Rolling Terrain Two-Way Flow 24
Table 5.3: Maximum AADT’s for Various LOS on Two-Lane Two-Way Rural Roads 24
Table 5.4: Level of Service: Bruce Highway 25
Table 5.5: Impact on Road Network: Construction Stage 26
Table 5.6: Impact on Road Network: Operational Stage 27
Table 7.1: Construction Stage: Daily ESA Generation 32
Table 7.2: Operational Stage: Daily ESA Generation 32
Table 7.3: Bruce Highway Impact on Road Network: Construction Stage 33
Table 7.4: Bruce Highway Impact on Road Network: Construction Stage 33
Figure Index Figure 2.1: Project Site Location and Regional Transport Network 4
Figure 3.1: Existing Road Network & Site Access 10
Figure 6.1: Bruce Highway / Abbot Point Road Intersection Count Data 29
Figure 6.2: Existing Layout Review: Operational Phase 2026 30
Figure 6.3: RPDM Chapter 13: Table 13.4 31
© 2013 - TTM Consulting Pty Ltd Reference: 12SCT0042/03
v
www.ttmgroup.com.au T: (07) 5479 2455 F: (07) 5479 3651 E: [email protected]
EIS Traffic and Transport Assessment Adani T0 Project: Abbot Point, QLD
Executive Summary
The Project is located at the Port of Abbot Point in Central Queensland (Figure 2.1). The Port of
Abbot Point currently supports existing coal export infrastructure (the T1 Terminal) which is
owned (under a 99 year lease term) by Adani Abbot Point Terminal (AAPT). The arrangements
provide a provision for expansion of the facility in the future and as capacity requirements require
additional works. The T1 infrastructure will continue to operate once the T0 Project is operational.
The Project is proposed to receive coal (initially 35 Mtpa and up to 70 Mtpa) by rail from the
Adani Carmichael Mine and Rail project located in the Galilee Basin and other sources of export
coal from the Bowen and Galilee basins. The Project is situated on Strategic Port Land (SPL) at the
Port of Abbot Point and is adjacent to the Abbot Point State Development Area (APSDA).
This report investigates the road transport aspects associated with the proposed Project. The
report evaluates the developments traffic and transport impacts on the existing road network and
recommends appropriate measures to mitigate any significant traffic impacts from either the
construction or operational development stages.
The investigation has identified that the development traffic generated during the construction
stage will generally be low due to the shipping of major construction materials and the use of
buses to transport workers from their accommodation locations.
The investigation has further indentified that the traffic generated during the operational stage is
likely to have a minor traffic impact due to the highly automated nature of the port facilities.
It is intended for a Road-user Management Plan (RMP) to be prepared at least 6 months prior to
the commencement of construction activities. This RMP will review and identify any road
capacity, safety and operational issues, which can be corrected through the implementation of
strategies or corrective actions. This RMP will ensure that no undesirable operational or safety
impact will impact occur on both the road and rail networks, with the RMP updated through
monitoring, auditing and reporting.
© 2013 - TTM Consulting Pty Ltd Reference: 12SCT0042/03
1
EIS Traffic and Transport Assessment Adani T0 Project: Abbot Point, QLD
1 Introduction
1.1 Project Overview The Port of Abbot Point (project site) is located approximately 25 km north/west of Bowen and is
Australia’s most northerly coal port. The Port of Abbot Point is of particular significance to both the
Commonwealth and the State as there are few locations along Queensland’s eastern seaboard with
in-shore proximity to deep water.
The Port of Abbot Point supports an existing coal export terminal (T1) with capacity to export 50
Mtpa of product coal. Capacity at the port and rail which feeds the port was expanded to 50 Mtpa in
recent years. The Project will be developed for operation over two phases - Phase 1 and Phase 2.
Development of the port is proposed to occur over a 5-6 year period and will be timed to correspond
with production outputs at the Adani Carmichael Coal Mine being developed by Adani Mining Pty
Ltd. The Project will allow for an initial throughput of 35 Mtpa and an eventual maximum
throughput of 70 Mtpa. This allows for potential increases in mine output efficiency and any other
sources of coal to be incorporated into the port’s capacity. Assessment of traffic impacts was divided
into two primary stages for the Project; construction stage and operational stage. The traffic assessment
has been based on a continuous construction schedule, over a 3 year period, to address any potential
changes in the phasing. Adani are submitting the Project Environmental Impact Statement (EIS)
under the Environment Protection and Biodiversity Conservation Act 1999 (EPBC Act), which is
administered by the Commonwealth Department of Sustainability, Environment, Water, Populations
and Communities (SEWPaC). Adani lodged their referral for the Project in 2011 (Referral No.
2011/6194) and have received guidelines for which the EIS needs to be prepared in accordance with.
This report addresses road and traffic impacts for the Project in accordance with the EIS Guidelines.
1.2 Investigation Process In addition to information provided by Adani, TTM undertook their own investigations to gather
relevant traffic data and have contacted the Department of Transport and Main Roads (DTMR) to
collate existing traffic and transport data for the surrounding road network.
1.3 References In preparing this report, the following guidelines and planning documents were referenced:
Department of Transport and Main Road’s Road Planning and Design Manual, (May 2010);
and
Department of Transport and Main Road’s Guidelines for Assessment of Road Impacts of
Development, (April 2006).
1.4 Scope This report forms part of the overall EIS technical documentation and investigates the traffic
demands anticipated to generated by the Project including a review of potential development traffic
impacts.
The scope of the transport aspects which have been investigated are as follows:
© 2013 - TTM Consulting Pty Ltd Reference: 12SCT0042/03
2
EIS Traffic and Transport Assessment Adani T0 Project: Abbot Point, QLD
Review of the existing road network in the vicinity of the Project;
Review of the existing traffic volumes provided by DTMR for the road segments identified as
part of the potential haulage and transport routes for the Project;
Review crash statistics provided by DTMR for all road segments relevant to the Project;
Estimation of developmental traffic demand;
Estimation of future traffic demand for scenarios with and without the influence of the
Project;
Identification of likely impacts to the community resulting from the additional traffic. This
includes:
o locations where traffic and pavement impacts are likely to be significant;
o impacts on vehicle safety; and
o impacts on sensitive receivers within the community.
Identification of possible mitigation measures required to address impacts on the road
network and pavement due to the increased traffic demand of the Project where necessary.
1.5 Consultation TTM has undertaken consultation with the Whitsunday Regional Council (WRC) and DTMR to
acquire information about school bus routes, accident data and traffic volume and
intersection data. TTM also note that this report has been updated and reviews the traffic,
safety and rail issues raised by DTMR in their Information Request, dated 3 April 2013.
© 2013 - TTM Consulting Pty Ltd Reference: 12SCT0042/03
3
EIS Traffic and Transport Assessment Adani T0 Project: Abbot Point, QLD
2 Project Profile
2.1 Project Description Due to capacity constraints at the current coal terminals in Queensland, the Abbot Point Port
Authority – North Queensland Bulk Ports Corporation (NQBP), has been undertaking studies and
proceeding with development to expand export capacity. Currently, the Port of Abbot Point is
planning to expand its capacity with port users requiring additional infrastructure due to increases in
the number of proposed coal mines within the Bowen and Galilee Basins.
It is intended that the Project will consist of the following elements:
Two rail receiving bottom dump stations located in a single common concrete vault situated
on the proposed rail loop corridor;
Two narrow gauge rail loops within the rail corridor;
Two streams of inloading conveyors feeding coal to the stockyard;
Stockyard consisting of six stockpile rows, arranged either side of three machine bunds with
two rows per bund;
Six stacker/reclaimers with each of the three bunds supporting two stackers/reclaimers;
Two outloading conveyor streams in parallel and each stream consisting of one conveyor
system, surge bin, sample plant and travelling ship loader;
Onshore infrastructure including stockyard drains, sediment ponds, roads, stormwater
retention dams, administrative building, workshop, sewerage treatment plant, car park and
amenities bloc;
An expansion of the existing Material Offloading Facility (MOF) so it can receive Roll-on Roll-
off (RORO) vessels (e.g. barges) and vehicles;
Construction of a new reservoir north of the stockpile area at Bald Hill and within the Project
boundary to provide additional water storage for operational use as part of Phase 2
construction works;
Piled wharf approach jetty structure extending approx. 2.75 km north north-east from the
shore line adjacent to the existing T1 port facility carrying the out loading stream of
conveyors and access road; and
Piled wharf structure at the end of the jetty which consists of two berths, each with one
shiploader.
2.2 Project Timeframes The construction and operation of the Project is planned to occur in two phases over a 5-6 year period
Assessment of traffic impacts was divided into two primary stages for the Project; construction stage and
operational stage. The traffic assessment has been based on a continuous construction schedule, over a 3
year period, to address any potential changes in the phasing. Therefore, modelling for the Project is
based on construction commencing in 2013, with first production planned for 2017.
It is expected that the project will have an expected life greater than 50 years.
© 2013 - TTM Consulting Pty Ltd Reference: 12SCT0042/03
4
EIS Traffic and Transport Assessment Adani T0 Project: Abbot Point, QLD
Figure 2.1: Project Site Location and Regional Transport Network
© 2013 - TTM Consulting Pty Ltd Reference: 12SCT0042/03
5
EIS Traffic and Transport Assessment Adani T0 Project: Abbot Point, QLD
2.3 Staffing Operation
2.3.1 T1 – Existing Staffing Model
In 2012 the staffing of T1 (50 Mtpa capacity), at a planned operation throughput of 20 Mtpa,
currently consists of:
EMPLOYMENT
Staff 50
Production 9
Maintenance 15
Strategic Development 6
Administration 4
Commercial 7
Logistics 9
Wages 82
Production (incl. casuals) 45
Maintenance - Mechanical 21
Maintenance - Electrical 16
Apprentices 17
Total Employees 149
Contractors 35
Total Manning 184
The maintenance crew is currently structured to operate during day time hours only. Maintenance
employees form 2 teams, with each team working a 12 hour shift each day (6am-6pm), with a 7 days
on / 7 days off rotating roster.
The operating team is required to keep the terminal operating on a continuous 24 hour production
mode, to receive trains and load vessels. The operating crew includes both production and a
skeleton maintenance crew, primarily to manage system failures between 6pm to 6am (when the
main maintenance crew is off shift). The crew is broken up into 4 teams with each team working a
12 hour shift, on a 7 days on / 7 days off rotating roster.
Leave and other absences are covered by: providing over time to off shift employees, moving
employees between work crews, employing contractors for specified period of time or by sourcing
casuals from the local townships.
© 2013 - TTM Consulting Pty Ltd Reference: 12SCT0042/03
6
EIS Traffic and Transport Assessment Adani T0 Project: Abbot Point, QLD
2.3.2 T0 – Staffing Model
At full operating capacity (70 Mtpa), the following staff levels are anticipated:
EMPLOYMENT
Staff 73
Production 15
Maintenance 25
Strategic Development 7
Administration 4
Commercial 10
Logistics 11
Wages 107
Production (incl casuals) 58
Maintenance - Mechanical 30
Maintenance - Electrical 19
Apprentices 26
Total Employees 207
Contractors 29
Total Manning 236
The main consideration to determining the structural change between the Project and the current
T1 staffing structure is that the Project will be highly automated, both operationally and logistically.
As a result, less staff will be required at full operation.
A total of 236 employees are planned to operate the terminal at a peak output of 70 Mtpa. At this
modelled manning level, the Project will be one of the most highly productive coal terminal
operations in the world, with productivity at 297,000 tonnes per employee per year. This high
productivity figure is based on achieving a high degree of automation throughout the operating site,
in addition to transparent communication and planning systems with the miners, rail providers and
vessel owners.
At full capacity, maintenance and operational crewing is planned to be structured for a continuous
24 hour operation to receive trains, load vessels, and execute continuous minor and major
maintenance tasks (both planned and unplanned), to keep the terminal operating at full capacity.
As a consequence, both operating and maintenance site teams will be broken up in to 4 equally sized
teams. Each team will work a 12 hour shift, on a 7 days on / 7 days off continuous rotating roster. In
addition to the above crews, there will also be a weekday permanent maintenance crew that will be
tasked to perform project work or support the day time shifts. This team will be drawn on to cover
manning gaps in the roster for holiday leave, sick leave and other absences.
© 2013 - TTM Consulting Pty Ltd Reference: 12SCT0042/03
7
EIS Traffic and Transport Assessment Adani T0 Project: Abbot Point, QLD
2.3.3 Construction Workforce
The works on site for both the construction and typical port operations will be based around a 24
hours a day, seven days a week operation. From a review of existing site operations it is considered
that the main workforce will be split into two main 12 hour shifts. The ‘day’ shift is likely to utilise
approximately 70% of staff, with the ‘night’ shift consisting of the remaining 30% of staff.
The accommodation for workers during the construction stage is likely to be located in the vicinity of
the Bowen Township. Temporary accommodation may also be required for personnel who perform
site set-up works prior to construction, which could be located near Bowen or further afield in the
Townsville or Proserpine township areas.
It is estimated the Project would require approximately 500 workers during the construction stage.
The construction workforce will typically consist of permanent fly in / fly out (FIFO) staff who are
likely to reside near regional centres. This FIFO rotation is typical when working a seven days on/
seven days off roster. However, this can vary based on individual worker requirements at the
construction site.
It is expected that transport between the worker accommodation village and the site will
predominantly be via buses, with limited private transport. The transfer of shift staff by buses is a
general requirement of Occupational Health and Safety standards due to the length of shifts.
The remaining construction work force will comprise from the local population and subcontractors.
The sub-contractors may participate in drive in / drive out from accommodation centres likely to be
located near Bowen or potentially utilise other accommodation facilities that could be located in the
surrounding townships. Local residents, including local subcontractors, would be expected to drive
their private vehicles to the site.
As noted, on completion of the construction works it is anticipated that there will be a total of 236
workers employed to manage typical port operations. It is anticipated that the majority of workers
will stay in nearby residential township areas, such as Bowen, Proserpine, Ayr, etc.
2.4 Heavy Vehicle Movements All construction materials transported by the road network will access the site via the Bruce
Highway. The Bruce Highway will continue to provide heavy vehicle access to supply the site with
equipment, services and resources in undertaking port operations. The proposed access and haulage
routes will be discussed in further detail in Chapter 3.
© 2013 - TTM Consulting Pty Ltd Reference: 12SCT0042/03
8
EIS Traffic and Transport Assessment Adani T0 Project: Abbot Point, QLD
2.5 Description of Proposed Vehicles The site will be accessed by the full scope of vehicles, from private cars to B-doubles for construction
materials and over dimensional OD vehicles for construction plant and large construction material
requirements. This will include buses which transport workers between the site and their
accommodation. The designation type of OD vehicles are those which exceed the following
dimensions when loaded:
Width of 2.5m;
Height of 4.6m; and
Length of: 12.5m for a rigid truck, 19m for an articulated vehicle and 25m for a B-Double.
2.6 Site Access The Port of Abbot Point site is currently accessed via the port access road (Abbot Point Road) which
has direct access to the Bruce Highway. It is proposed that the Abbot Point Road will be used as the
main staff, contractor, and heavy vehicle access for travel from the Bruce Highway. As the
construction activity is contained within the Port of Abbot Point site, it is anticipated that no roads
or accesses will have to be closed for any traffic management requirements. The site access (Bruce
Highway / Abbot Point Road intersection) is a typical priority intersection with three approaches
with left and right turn lane treatments.
2.7 Other Relevant Projects Given the high demand on Port services to satisfy the current and proposed coal mines, there are
other port construction and expansion activities occurring at Abbot Point. These other proponents
and their Projects are outlined in Table 2.1. To provide the necessary environmental information on
the potential cumulative impacts of these three proposals, the current proponents are undertaking a
voluntary cumulative environmental impact assessment for the Port of Abbot Point, in conjunction
with NQBP. This project is referred to as the Abbot Point Cumulative Impact Assessment (CIA) and is
intended to enable a comprehensive assessment of the three projects under the EPBC Act, the Great
Barrier Reef Marine Park Act 1975 (GBRMP Act) and relevant State planning laws.
Table 2.1: Existing and Proposed Projects Abbot Point
Project Name Proponent Description Approval Status
The Project (T0) and associated rail
Adani Adani T0 development, approximately 35 Mtpa in two phases (total 70 Mtpa)
EPBC Referred for rail and port separately
T1 (existing operation)
Adani Adani existing 50 Mtpa coal export terminal and associated rail
Operational
T2 and associated rail
BHP Billiton 60 Mtpa expansion EPBC referred for rail and port separately
T3 and associated rail
Hancock Coal 60 Mtpa expansion EPBC referred for rail and port separately
T0 / T2 / T3 Dredging
NQBP Combined dredging proposals EPBC Referred
© 2013 - TTM Consulting Pty Ltd Reference: 12SCT0042/03
9
EIS Traffic and Transport Assessment Adani T0 Project: Abbot Point, QLD
3 Regional Context
3.1 Project Location The Project is located at the Port of Abbot Point in Central Queensland.
3.2 Existing and Proposed Port Infrastructure The Project relates to the development of new port facilities, with all construction works intended to
be undertaken within the site boundary.
3.3 Existing Road Network The external local roads in the vicinity of the site are administered by the WRC, with the DTMR
Controlled Bruce Highway providing the main route and connection into the site. Abbot Point Road
is maintained by the Port Authority (NQBP). The hierarchy and description of surrounding access and
external roads is provided in Table 3.1.
Table 3.1: Local Road Hierarchy
Road Authority Classification Carriageway
width
Description
Abbot Point
Road
NQBP Access Road 7.0 m Fully sealed carriageway, two lanes.
Bruce Highway DTMR National
Strategic
9.0 m Fully sealed carriageway, two lanes
plus shoulders.
3.3.1 Bruce Highway
The Bruce Highway forms part of the Australian National Highway Network (AUSLINK) and is a major
north-south route along the Brisbane-Cairns corridor. To the north of Brisbane, the Bruce Highway is
a divided multi-lane road for most of its distance to Cairns. However, further north the Bruce
Highway is essentially a two lane rural highway with sections of four lanes near regional centres. The
Bruce Highway links the regional centres of Rockhampton, Mackay and Townsville via Proserpine
and Bowen.
This report will focus on the Bruce Highway corridor between Townsville, Bowen and Proserpine. It
is anticipated that the majority of traffic generated by the development will access these key areas.
This segment of highway has one lane in each direction with sealed shoulders on both sides. The
highway has a posted speed limit of 100 kph. There are limited public transport, walking and cycling
facilities along this segment of Bruce Highway, with no educational or child facilities having direct
access to the Highway. The Bruce Highway between Proserpine and Cairns is a two lane rural
highway carrying between 2,500 and 8,000 vehicles per day.
© 2013 - TTM Consulting Pty Ltd Reference: 12SCT0042/03
10
EIS Traffic and Transport Assessment Adani T0 Project: Abbot Point, QLD
3.3.2 Abbot Point Road
The Abbot Point Road will provide the main access route into the site and runs in a north south
direction connecting the main port facilities with the Bruce Highway to the south. The road has one
lane in each direction with sealed shoulders on both sides.
Figure 3.1: Existing Road Network & Site Access
Bruce
Highway
Abbot Point
Road
Abbot Point
Terminal
© 2013 - TTM Consulting Pty Ltd Reference: 12SCT0042/03
11
EIS Traffic and Transport Assessment Adani T0 Project: Abbot Point, QLD
3.4 Major Structures There is separated road and rail bridge along the access route that crosses Saltwater Creek along
Abbot Point Road, which has been designed to cater for general port traffic demands. There are also
various bridge and culvert structures along the Bruce Highway corridor between Townsville, Bowen
and Proserpine. As noted, the Bruce Highway is a strategic highway and it is anticipated that the
associated structures will be able to cater for the anticipated development traffic demands.
3.5 Public Transport and School Bus Routes There are no school bus stops along the internal site access route or in the vicinity of the site.
However, there are existing school bus services that utilise sections of the Bruce Highway, which
provides access to key townships along the corridor, with the school buses generally operating
between 7:30 am and 8:30 pm; and 2:30 pm and 3:30pm.
3.6 Future Road Improvement Projects The DTMR ‘Road Implementation Program (RIP) 2011-2012 to 2013-2014’ document for the
Mackay/Whitsunday Region outlines proposed road improvement projects within the vicinity of the
site. This document has been studied to identify any improvement projects scheduled for roads
relevant to the Project.
It is noted that roads in the inland areas of the Mackay/Whitsunday Region were particularly
impacted by flooding which impacted large tracts of Queensland in early 2011. As such, a significant
proportion of the budget is allocated to road maintenance requirements, with $40.4 million planned
works along 72km of the Bruce Highway through Isaac, Mackay and the Whitsundays.
TTM understand that there are plans to upgrade the Bruce Highway into Townsville from the south;
however, no scheme funding has been identified at this stage.
3.7 Rail Access The Queensland North Coast rail line provides connectivity between the major urban centres along
the coast, with stops at Mackay, Proserpine, Bowen, Home Hill, Ayr, Giru and Townsville. The
nearest train station to the site is located in Bowen, However, due to the limited rail services; it is
unlikely that any staff or contractors will travel by train.
The Port of Abbot Point is currently served by heavy rail with connections to various inland coal
mines to the south of the site. There are future plans for upgrading the heavy rail access which is
intended to enhance the existing rail port capacity. As part of the port expansion works, it is
intended that a new internal rail loop will be constructed including coal and ancillary facilities.
© 2013 - TTM Consulting Pty Ltd Reference: 12SCT0042/03
12
EIS Traffic and Transport Assessment Adani T0 Project: Abbot Point, QLD
4 Development Traffic Generation and Distribution
4.1 Basis for Traffic Impact Analysis In establishing the overall traffic demands, it is necessary to review the traffic associated with the
existing Port of Abbot Point facilities and the likely level of construction traffic activity. A final review
will be undertaken to determine the traffic associated with the port operation once the construction
works have been completed.
The assessment of traffic generation during the proposed development construction stage is split
into two vehicular categories. The staff categorisation is calculated based on the movement of
workers to and from the site and the number of associated trips generated. The second category
includes construction traffic predominantly consisting of heavy goods and oversized vehicles.
Construction of the Project will occur over a 5-6 year period, however traffic generation has been
based on a 3 year construction period to address any potential changes to the phasing. The primary
tasks involved will be the construction of the additional port facilities and infrastructure. The
following provides a review of the proposed traffic generation for existing operations, construction
stage and completed works/operational stage.
4.2 Existing Operations: Traffic Demands As noted, there are 184 existing staff working at the Port of Abbot Point, with 4 teams working a 12
hour shift, on a 7 days on / 7 days off rotating roster.
On this basis it is anticipated that 46 staff work each shift and arrive and depart during the shift
changes, i.e. between 5:30am to 6:30am and 5:30pm to 6:30pm. It is therefore estimated that there
are approximately 30 vehicles entering and exiting the site during the shift changes, based on vehicle
occupancy of 1.5 workers.
The existing port operation requires constant servicing and is supplied daily with materials,
including: food supplies and maintenance equipment etc, with a typical demand of 70 service
vehicles per day. The service vehicles range in size, with the smaller and medium type service
vehicles (Van, SRV, MRV to HRV) providing the majority of daily service requirements. However,
there may be operational requirements for larger loads by Articulated Vehicles (AV) to access the
site, with one delivery anticipated per working day. In general, most deliveries will be undertaken
during the working day with limited activity during the shift change periods.
In terms of vehicle distributions, the level of typical traffic accessing the site from the Bruce Highway
is similar in both the north/west and south/east directions with the following breakdown in existing
site traffic:
AM Peak Period (5:30am to 6:30am): 30 private and 3 service vehicles from north/west; 30
private and 3 service vehicles from south/east;
Off Peak Period (7am to 5pm): typically 6 service vehicles per hour (In/Out); and
PM Peak Period (5:30pm to 6:30pm): 30 private and 3 service vehicles from north/west; 30
private and 3 service vehicles from south/east.
© 2013 - TTM Consulting Pty Ltd Reference: 12SCT0042/03
13
EIS Traffic and Transport Assessment Adani T0 Project: Abbot Point, QLD
Table 4.1 provides a breakdown on worker movements covering a typical daily operation.
Table 4.1: Existing Operational Traffic
Shift Day Night
Total Workforce 184
Total Rostered Staff 92
Shift Staff 46 46
Staff Access:
Bus
Private
-
30
-
30
Total Staff Movements 60 vehicles per hour (vph)
Total peak hour traffic generation, service vehicles
6
Total peak hour traffic generation, including heavy vehicles
65vph (In/Out)
Daily service vehicle movements 70vpd
Total traffic generation – vehicles per day (vpd) 260vpd (In/Out)
© 2013 - TTM Consulting Pty Ltd Reference: 12SCT0042/03
14
EIS Traffic and Transport Assessment Adani T0 Project: Abbot Point, QLD
4.3 Construction Stage: Traffic Demands The following provides a breakdown of the likely traffic generated at the construction phase.
4.3.1 Construction Stage: Heavy Vehicle Traffic Generation
This inventory is based on an understanding of general construction requirements, which are based
on the individual material transportation requirements. Site construction materials will be sourced
from various locations, with the following providing a summary of likely sourced materials locations:
Local – within 100km of the site, includes: Ayr, Bowen, Collinsville and Proserpine;
Regional – generally within 400km, such as Charters Towers, Mackay and Townsville;
State – All areas of Qld;
National – provided from within Australia, but outside Qld; and
International – provided from outside Australia, with delivery most likely via the existing
port.
This demand assessment has made several assumptions in respect to the overall scope of works, as
follows:
Supply of all construction materials for the Project, including:
A rail connection from the existing track and/or a new rail connection from the
South west;
Rail loops and train unloading facilities;
Coal stockpile bunds and associated infrastructure;
Conveyors from the coal terminal tranches to port facilities;
Berthing and ship loading facilities;
Land for lay down areas and support industries; and
Site and common user infrastructure including but not limited to roads, phone,
electricity, water supply and storage and sewage treatment.
Transportation of workers via bus between township camps and site during construction;
Supply of all materials and replacement equipment to operate the site; and
Local accommodation camp likely to be located near Bowen.
It is intended that sea transport will be used for most of the overseas manufactured items and
materials with road transport being used for most of the locally sourced materials and items. These
large components and modules are expected to use the existing MOF facility which was established
in 1982 for the original port development works, by upgrading through maintenance and
refurbishment.
At this stage of the development/design process there is limited information in relation to the
percentage break-down between sea and road transport. This percentage break-down depends on
what this comparison is to be based upon, i.e., mass/size of materials/items or time/number of trips
to transportation the required items/materials. In a review of the mass/size of construction
materials it is considered that larger materials/operating equipment will be transported by sea, with
smaller typical construction materials/plant arriving by road. It is anticipated that this mass/size
break-up would probably be approximately 75% by sea and 25% by road.
© 2013 - TTM Consulting Pty Ltd Reference: 12SCT0042/03
15
EIS Traffic and Transport Assessment Adani T0 Project: Abbot Point, QLD
A major part of the construction activity will be raising the ground level of the site, with infill
material likely to be sourced from the existing Abbot Point Quarries 1 and 2 along the Abbot Point
access road. It is anticipated that approximately 400,000m3 of infill material is required for the Phase
1 construction works of the Project, with this material trucked from the existing quarries. A further
900,000m3 will be required for the Phase 2 construction works. The timing of phase 2 is expected to
follow on straight after the completion of the Phase 1 works.
TTM understand that the existing quarry operator will use a B-double set-up to transport the fill
material from the quarry to the site. This truck and trailer set-up will allow cartage of 35 tonnes of
material per trip. For the transport of 400,000m3 of fill it is calculated that there will be a
requirement for 17,400 internal truck trips/movements. Fill will predominately be gravel and less
permeable material, and a bulking factor of between 1.2 and 1.3 has been used to determine the
necessary truck trips.
In assuming a construction time of six months to complete the earthworks for the Phase 1 works
only, the frequency of trucks taking fill material to the Project site from the quarry would be
approximately 13 trucks per hour. This equates to one truck travelling along Abbot Point Road
approximately every 5 minutes to and from the quarry. This calculation is based on 9 hours of actual
travelling time for a 12 hour working day and a six day working week.
For Phase 2 construction works, the frequency of trucks travelling along the Abbot Point road is not
expected to increase from the calculated rates above. The duration of the trucks’ hauling period will
increase proportionally for the additional quantity of material which will be required for the Phase 2
works based on an approximate duration of 14 months.
There will be a requirement for further materials, plant and equipment to be transported via the
external road network for the Project works. At the commencement of the on-site construction
activities, all contractor’s plant, equipment, temporary offices and amenities will be transported to
site via the road network. All locally sourced building materials such as ready mixed concrete,
precast concrete products (e.g. reinforced concrete stormwater pipes, manholes, reinforced
concrete box culverts, etc), steel reinforcement, etc will be transported by road.
Locally sourced hire equipment and plant such as cranes, concrete pumping trucks, earthmoving
plant and equipment, etc will either be transported or self-driven via the existing road network.
There will be several new buildings required for the Project and all materials to be incorporated in
these new building will be sourced locally and will be transported via the existing road network.
It is understood that the transport of many goods which cannot be further divided into smaller
components will require transport on over dimensional (OD) type vehicles, with pilot vehicles and
police escorts where required.
The largest vehicles accessible to the site will be a type 2 road train. However, the access for these
types of vehicles is generally limited due to the limited accessibility, with B-double trucks expected
to be the largest, standard access vehicles accessing the site during the works phase.
© 2013 - TTM Consulting Pty Ltd Reference: 12SCT0042/03
16
EIS Traffic and Transport Assessment Adani T0 Project: Abbot Point, QLD
Table 4.2 provides a summary of the likely construction vehicle requirements external to the site,
with approximately 2,235 trucks movements covering the three year construction of the site.
It is estimated that on average there will be 6 truck deliveries, or 12 total truck movements, per day,
based on 6 loaded and 6 unloaded trip movements, covering typical construction operations. This
level of activity may increase during specific construction operations which may peak at 12 truck
deliveries, or 24 total truck movements, per day based on 12 loaded and 12 unloaded trip
movements.
It is assumed that all construction equipment/plant delivered to the site will be dedicated to
construction activities and will be located on-site for the duration of construction activities and not
transported to and from as required.
© 2013 - TTM Consulting Pty Ltd Reference: 12SCT0042/03
17
EIS Traffic and Transport Assessment Adani T0 Project: Abbot Point, QLD
Table 4.2: Construction Vehicle Requirements (External to Site)
Plant/Materials Quantity Transport
Arrangements
Delivery Vehicles Origin
General Construction Equipment Requirements
Mobile Cranes 2 2 (AV) Regional
Fork lifts 4 1 (AV) Local
Grader 3 3 (AV) Regional
Dozer 10
Stored on-site for
construction
activities
10 (AV)
Regional
Excavators 10
Stored on-site for
construction
activities
10 (AV)
Regional
Dump trucks 10
Standard size
articulated tippers,
self drive to site
Stored on-site for
construction
activities
10 (AV)
Regional
Buildings/Storage Tanks Requirements
Workshops Constructed from
base materials
(steel/concrete)
2 (AV) Regional
Stores 4 (AV) Regional
Workforce admin/muster
Demountable offices
(25m2)
Footings
20 (AV)
5 (AV)
State
Wash Facilities 3 (AV) Regional
Fuel/oil 2 tanks 2 (AV) Regional
Waste station 2 tanks 2 (AV) Regional
Hazardous materials 2 tanks 2 (AV) Local
Water tanks / treatment 3 tanks 3 (AV) Local
New Rail Loop Requirements
Rails Delivered by road 150 (AV) State
Sleepers Delivered by road 50 (AV) State
© 2013 - TTM Consulting Pty Ltd Reference: 12SCT0042/03
18
EIS Traffic and Transport Assessment Adani T0 Project: Abbot Point, QLD
Plant/Materials Quantity Transport
Arrangements
Delivery Vehicles Origin
Base material 35 tonnes per truck
and trailer 50 (AV) Local
Construction Materials Requirements
Internal access roads material, Rock
armour, quarry materials
33 tonnes per truck
and trailer 500 (B-double) Local
Concrete For footings,
retaining walls
standard concrete
truck 100(AV) Local
Road Pavement/Rock armour
Coal Handling Machinery Requirements
Buildings/structures
50 (AV) Regional
Coal handling facility structure Delivered by sea - Internation
al
Regular Service Vehicles Requirements
Potable water 2 per week (312 LRV) Local
Fuel 1 per week (156 LRV) Regional
General supplies (office, catering and
miscellaneous equipment) 3 per week (468 SRV) Regional
Waste collection 2 per week (312 MRV) Local
Internal Infrastructure
Sewerage pipes 2 (AV) Regional
Electricity wire/poles 2 (AV) Regional
Telecom line 2 (AV) Regional
Water pipes 2 (AV) Regional
Total 2,235
© 2013 - TTM Consulting Pty Ltd Reference: 12SCT0042/03
19
EIS Traffic and Transport Assessment Adani T0 Project: Abbot Point, QLD
4.3.2 Construction Stage: Workforce Traffic Generation
The main factor influencing workforce traffic generation will be the general self-contained nature of
the site. The provision of internal equipment and facilities will allow the majority of employees to
stay within the vicinity of the site at most times during their shifts.
Considering the spatial nature of the development it is considered that employees will be sourced
primarily from southeast Queensland and secondly from the vicinity of Townsville, Bowen, Ayr and
Proserpine local township areas. It is therefore considered that the majority of traffic generated by
the development will generally travel to and from these areas.
At this initial development stage, the specific location of the accommodation village is yet to be
determined, however, it is likely to be located in the vicinity of the Bowen township to the
south/east of the site.
It is considered that the majority of worker movements from the accommodation village will be via
bus (40 person capacity) movements to the site, with further buses collecting workers at various
nearby airports. However, not all workers will travel by bus, with approximately 20% likely to reside
in nearby townships and use their private vehicles to access the site. There will also be a
requirement for sub-contractor workers and they are likely to use a private vehicle or hire car as
their primary method of transportation.
The traffic generation also takes into account the expected roster and shift systems which would
result in:
500 workers estimated to be required during the construction stage;
70% of workers rostered on two shifts of 12 hours each, with 70% of the rostered staff on
day shift and 30% on night shift;
80% of workers to utilise group transport between worker accommodation and the site,
averaging 40 persons per bus;
20% of workers (including subcontractors) to access the site utilising private vehicles, with
an average car occupancy for passenger vehicles being 1.5 persons; and
Peak hour movements account for approximately 20% of daily traffic.
As such, the maximum number of workers accessing the site (worst case scenario) for the day shift
will be 350 and the evening shift will be 150. This will generate the following vehicle trips:
Morning Shift Change: (5:30am to 6:30am): In: 196 workers utilising 5 buses, with 33 private
vehicles (1.5 worker occupancy) and Out: 84 workers, 3 buses, with 14 private vehicles; and
Evening Shift Change: (5:30pm to 6:30pm): In: 84 workers utilising 3 buses, with 14 private
vehicles (1.5 worker occupancy) and Out: 196 workers, 5 buses, with 33 private vehicles.
This is considered a worst case scenario as it assumes that shift workers, administrative staff and
sub-contractors all arrive and depart the site during the same peak hour, which is unlikely to occur.
© 2013 - TTM Consulting Pty Ltd Reference: 12SCT0042/03
20
EIS Traffic and Transport Assessment Adani T0 Project: Abbot Point, QLD
4.3.3 Construction Stage: Traffic Distribution
The total daily traffic volume generated by the construction activity is expected to equate to 122
vehicle movements per day based on average construction operations. The following provides a
breakdown of likely worker and vehicle distributions during the construction period.
It is anticipated that the construction workers will have the following distributions:
10% to and from Ayr, Townsville and other townships along the Bruce Highway;
10% to and from Bowen, Proserpine and other southbound townships; and
80% to and from the worker accommodation camp.
Further indirect traffic will be generated by FIFO activities. Once shifts are complete, the workers will
fly back to regional centres for leave periods. Staff and contractors based in southeast Queensland
and other states are expected to fly to and from Townsville, Proserpine and Mackay airports. TTM
note that the construction and operation of an accommodation camp will be dealt separately from
this traffic assessment.
It is anticipated that the construction and service vehicles will have the following distributions:
50% to and from Townsville along the Bruce Highway; and
50% to and from Bowen, Proserpine and further southbound along the Bruce Highway.
Of the site generated traffic, 20% are expected to continue through Proserpine and travel further
south towards Brisbane. These movements are primarily expected to consist of long distance heavy
vehicle movements, servicing the site from major regional centres along the coast.
Approximately 80% of these trips will be from the local area. These will consist of material deliveries
from local quarries and suppliers for materials in addition to infrastructure components and
equipment likely to be sourced from the Townsville area. The remainder will be sourced from the
wider region, including inter-state.
Based on the above assessment of construction (non site staff) vehicle trips it is estimated that there
will be an average of 5 Heavy Goods Vehicles (HGV) trips per day to and from the site during the
construction stage. It is therefore estimated that there will be approximately 122 total trips daily
vehicle trips generated during the construction stage, with the majority of site workers using bus
transport.
© 2013 - TTM Consulting Pty Ltd Reference: 12SCT0042/03
21
EIS Traffic and Transport Assessment Adani T0 Project: Abbot Point, QLD
4.4 Completed Works/Operational Stage: Traffic Generation The Project will be operational for greater than 50 years. The primary tasks involved will be
stockpiling coal from rail deliveries and processing coal for shipping export. The primary
requirements for service vehicles will be the supply of operating goods and maintenance of the rail
and port equipment plant.
4.4.1 Operational Traffic
For the duration of the operational life span of the port facility it is anticipated that the majority of
staff will stay in nearby residential areas, such as, Bowen, Proserpine, etc townships. All staff and
service vehicle movements will access the site via the Bruce Highway.
As noted, a total of 236 employees are planned to operate the terminal at 70 Mtpa output. It is
intended that the port facility will be highly automated, both operationally and logistically, with less
staff required during operations.
The staff will continue to work on a 4 team basis over a 12 hour shift, on a 7 days on / 7 days off
rotating roster. On this basis it is anticipated that 59 staff cover each shift and arrive and depart
during the shift changes being 5:30am to 6:30am in the morning and 5:30pm to 6:30pm in the
evening.
It is therefore estimated that there are approximately 40 vehicles entering and exiting the site during
the shift changes, which is based on vehicle occupancy of 1.5 workers.
The port operation will continue to require constant servicing and will be supplied with daily
materials including: food and replacement and maintenance equipment etc, with a typical demand
being 100 service vehicles per day. The service vehicles will range in size, with the smaller type
service vehicles providing the majority of daily service requirements.
Table 4.3 identifies all the likely traffic generation and heavy vehicle requirements during the full
operational stage (70 Mtpa).
Table 4.3: Full Operational Site Traffic Generation
Shift Day Night
Total Workforce 236
Total Rostered Staff 118
Shift Staff 59 59
Staff Access:
Bus
Private
-
40
-
40
Total Staff Movements 80 vehicles per hour (vph)
Total peak hour traffic generation, service vehicles
6
Total peak hour traffic generation, including heavy vehicles
86vph (In/Out)
Daily service vehicle movements 100vpd
Total traffic generation – vehicles per day (vpd) 360vpd (In/Out) Additional 100vpd (In/Out)
© 2013 - TTM Consulting Pty Ltd Reference: 12SCT0042/03
22
EIS Traffic and Transport Assessment Adani T0 Project: Abbot Point, QLD
4.4.2 Completed Works/Operational Stage: Traffic Distribution
As shown in Table 4.3, the daily traffic volume generated by the site is expected to equate to a total
of 360 daily vehicle movements or an additional 100 daily vehicle movements based on existing site
operations.
These traffic volumes are expected to be distributed as follows:
30% to the east/south along the Bruce Highway; and
70% to the north/west along the Bruce Highway.
Of the port generated heavy vehicle traffic, 70% is anticipated to be generated from the Townsville
area, with the remaining 30% from the south and further southern Queensland destinations, with
the following breakdown of full future year operational site traffic:
AM Peak Period (5:30am to 6:30am): 56 private, 4 service vehicles from and to north/west,
24 private, 2 service vehicles from and to south/east;
Off Peak Period (7am to 5pm): Typically 8 service vehicles per hour (In/Out); and
PM Peak Period (5:30pm to 6:30pm): 56 private, 4 service vehicles from and to north/west,
24 private, 2 service vehicles from and to south/east.
4.5 Impacts of Decommissioning It is assumed that the site will have an operational life span over 50 years, with no plans for any
decommissioning process.
However, if decommissioned, the Port will require several operations which will have an impact on
the local and state controlled network. This will include
Removal of hazardous material;
Decommissioning of buildings and structures;
Removal of waste material;
Environmental actions; and
Removal of plant and machinery from site.
© 2013 - TTM Consulting Pty Ltd Reference: 12SCT0042/03
23
EIS Traffic and Transport Assessment Adani T0 Project: Abbot Point, QLD
5 Traffic Operation Assessment
5.1 Introduction This chapter reviews the traffic operation and capacity performance of the Bruce Highway corridor
adjacent to the site including the Bruce Highway/ Abbot Point Road intersection.
5.2 Average Annual Daily Traffic (AADT) Table 5.1 identifies the typical (2011) traffic volumes, sourced from DTMR, for the Bruce Highway
between Bowen and Ayr, with the volumes used in the traffic assessment.
It is anticipated that the traffic growth on the Bruce Highway will continue to remain at 3% based on
historical traffic growth that over a ten year period.
Table 5.1: Existing AADT Volumes on State-Controlled Roads
Traffic Analysis and Reporting System: Road Section 10J – Bruce Highway (Proserpine – Bowen):
Traffic Analysis and Reporting System: Road Section 10K – Bruce Highway (Bowen - Ayr):
Traffic Analysis and Reporting System: Road Section 10L – Bruce Highway (Ayr - Townsville):
© 2013 - TTM Consulting Pty Ltd Reference: 12SCT0042/03
24
EIS Traffic and Transport Assessment Adani T0 Project: Abbot Point, QLD
5.3 Road Corridor Capacity Criteria The AUSTROADS Guide to Traffic Engineering Practice - Part 2: Roadway Capacity indicates that two-
lane rural highways have a capacity of 2,800 passenger cars per hour total for both directions of
flow, under ideal conditions where there are no restrictive roadway, terrain or traffic conditions.
However, considering the prevailing roadway and traffic conditions along Bruce Highway, it is
estimated that the highest total service flow rate (AM Peak) is approximately 900 vehicles per hour
total for both directions of flow based on 2011 traffic levels.
AUSTROADS defines level of service as a qualitative measure describing operational conditions
within a traffic stream. The term Level of Service (LOS) and its characteristics for rural roads is
defined in Table 5.2.
Table 5.2: Two Lane Rural Road Capacity – Rolling Terrain Two-Way Flow
LOS Description Rating
A Free, unrestrictive flow Very Good
B Mostly free flow, few disruptions Very Good
C Stable flow Good
D Mostly stable flow, some delays Acceptable
E Congested flow, delays common Bad
F Forced flow Bad Source: Austroads Guide to Traffic Engineering Practice, Part 2
The volume and composition of traffic on a given road determines the level of interaction between
vehicles and is measured as its LOS. LOS decreases with increasing traffic volumes. LOS ‘A’, LOS B’,
LOS ‘C’ in a rural context are satisfactory, with a LOS ‘D’ satisfactory in some circumstances.
In cases where traffic, terrain or geometric data may not be precisely known, the AUSTROADS Guide
provides planning guidance on maximum AADT values that two-lane, two-way rural roads can
accommodate under various terrain conditions. Table 5.3 shows the values for various Levels of
Service for a rural road in rolling terrain with varying ratios of design hour volume to AADT.
Table 5.3: Maximum AADT’s for Various LOS on Two-Lane Two-Way Rural Roads
Level of Service
Design Hour Volume to AADT
Ratio
A B C D E
0.10 1,100 2,800 5,200 8,000 14,800
0.11 1,000 2,500 4,700 7,200 13,500
0.12 900 2,300 4,400 6,600 12,300
0.13 900 2,100 4,000 6,100 11,400
0.14 800 1,480 3,700 5,700 10,600
0.15 700 1,800 3,500 5,300 9,900
© 2013 - TTM Consulting Pty Ltd Reference: 12SCT0042/03
25
EIS Traffic and Transport Assessment Adani T0 Project: Abbot Point, QLD
(Source: AUSTROADS Guide to Traffic Engineering Practice, Part 2: Roadway Capacity, Table 3.9)
5.4 Bruce Highway Operational Performance For a LOS ‘C’, the maximum AADT values range from 3,500 to 8,000 depending on the design hour
volume to AADT ratio. The peak hour volumes along the Bruce Highway corridor were observed to
be approximately 10% (or 0.10) of the average daily traffic based on the traffic peak periods.
From Table 5.3 above, a maximum AADT of 5,200 to 8,000 is assumed for a LOS ‘C’. Comparing these
values with the average AADT levels along the Bruce Highway indicates that the existing road
corridor generally operates at LOS ‘C’, as shown in Table 5.4. As noted, the future year corridor
operation is based on a 3% background traffic growth and from the criteria noted in Table 5.4 will
generally operate at a LOS ‘D’ in 2026 (10 year post construction completion).
Table 5.4: Level of Service: Bruce Highway
Bruce Highway
Route/Counter Site
2013 AADT
2016 AADT
2026 AADT
LOS
2013 2016 2026
10J/82847 11172 12208 16407 D D E
10J/82817 3839 4195 5638 B B C
10J/82717 2660 2906 3906 B B B
10J/90003 3758 4106 5518 B B C
10J/90050 6174 6747 9067 B B C
10K/90051 8114 8866 11915 D D D
10K/92198 3803 4156 5585 B B C
10K/90042 3014 3293 4426 B B C
10K/91439 7612 8318 11178 C D D
10K/90004 9362 10231 13749 D D D
10K/91396 10964 11981 16102 D D D
10J/91398 6081 6645 8930 C C D
10J/91399 7669 8380 11262 C D D
10J/91699 5438 5942 7986 C C C
10J/90028 8425 9206 12372 D D D
© 2013 - TTM Consulting Pty Ltd Reference: 12SCT0042/03
26
EIS Traffic and Transport Assessment Adani T0 Project: Abbot Point, QLD
5.5 Construction Stage The traffic assessment has been based on a continuous construction schedule, over a 3 year period, to
address any potential changes in the phasing. Construction will not occur for any less than a three year
period, and therefore this assessment has modelled the Project based on the most intensive possible
schedule. Construction will involve the employment of up to 500 staff and will be accommodated
near Bowen. Due to the self contained nature of the pre-construction site set-up it is anticipated
that traffic impacts during this period will be lower than either the full construction or operational
stages and as such have not been assessed.
5.6 Operational Stage The operational stage of the port will last longer than 50 years from the anticipated construction
completion of Phase 1 in 2016.
Table 5.5 shows the predicted construction stage vehicle activity, with Table 5.6 showing the
operational stage traffic activity, with the traffic impacts below the 5% impact threshold which is
therefore considered to have a negligible impact on overall highway performance.
Table 5.5: Impact on Road Network: Construction Stage
Road Route/ Counter Site
2013 AADT Construction Site Generated Traffic
Vehicles per day % Increase
Bruce Highway 10J/82847 11172 130 <5%
10J/82817 3839 130 <5%
10J/82717 2660 130 <5%
10J/90003 3758 130 <5%
10J/90050 6174 130 <5%
10K/90051 8114 130 <5%
10K/92198 3803 130 <5%
10K/90042 3014 130 <5%
10K/91439 7612 47 <5%
10K/90004 9362 47 <5%
10K/91396 10964 47 <5%
10J/91398 6081 47 <5%
10J/91399 7669 47 <5%
10J/91699 5438 47 <5%
10J/90028 8425 47 <5%
© 2013 - TTM Consulting Pty Ltd Reference: 12SCT0042/03
27
EIS Traffic and Transport Assessment Adani T0 Project: Abbot Point, QLD
Table 5.6: Impact on Road Network: Operational Stage
Road Route/ Counter Site
2016 AADT Site Generated Traffic
Vehicles per day % Increase
Bruce Highway 10J/82847 12208 30 <5%
10J/82817 4195 30 <5%
10J/82717 2906 30 <5%
10J/90003 4106 30 <5%
10J/90050 6747 30 <5%
10K/90051 8866 30 <5%
10K/92198 4156 30 <5%
10K/90042 3293 30 <5%
10K/91439 8318 70 <5%
10K/90004 10231 70 <5%
10K/91396 11981 70 <5%
10J/91398 6645 70 <5%
10J/91399 8380 70 <5%
10J/91699 5942 70 <5%
10J/90028 9206 70 <5%
5.7 Proposed Haulage Route The Bruce Highway is intended to be the main haulage route to the site and is considered to carry
the majority of the construction vehicles. The Bowen Developmental Road to the south of Bowen
may carry construction vehicle traffic, however, the level of potential generated traffic is considered
negligible, with the majority of traffic using the Bruce Highway from both the north and southern
directions.
© 2013 - TTM Consulting Pty Ltd Reference: 12SCT0042/03
28
EIS Traffic and Transport Assessment Adani T0 Project: Abbot Point, QLD
6 Site Access Review
6.1 Introduction This chapter reviews the adequacy of the Bruce Highway / Abbot Point Road intersection to
adequately cater for the predicted development traffic demands.
6.2 Existing Intersection Layout The intersection layout is a typical priority 3-arm intersection with left and right turn treatments.
The intersection has good inter-visibility in all directions, with the following key traffic and geometric
attributes:
A posted speed limit of 100km/hr;
A 9 metre wide carriageway;
An approximate 30 metre entry width for AV turning vehicles; and
Left turn lane provision being approximately 130m Length, with a right turn lane provision
being approximately 130m in length treatments and shoulder provisions.
6.3 Accident Review TTM are unaware of any prior accident history or safety concerns at this intersection location.
6.4 Sight Distance Review TTM have reviewed the intersection sight distance requirements with reference made to the
Department of Main Roads: Road Planning and Design Manual Chapter 13: Intersections at Grade
requirements, with the intersection’s sight distance adequate in all directions.
6.5 Intersection Turn Warrant Requirement Review
TTM has reviewed the turn warrant requirements as part of the overall intersection review with
reference made to the RPDM Chapter 13: Intersections at Grade: Warrants for Turn Treatments on
Roads with a Design Speed >100km/h Figure 13.22, as shown in Figure 6.1. This assessment review
relates to a worst case assessment, which is based on Completed Works/Operational Phase in 2026.
The traffic volumes are based on the likely peak periods for the site traffic:
AM Peak Period (5:30am to 6:30am): 56 private, 4 service vehicles from and to north/west,
24 private, 2 service vehicles from and to south/east;
Off Peak Period (7am to 5pm): Typically 8 service vehicles per hour (In/Out); and
PM Peak Period (5:30pm to 6:30pm).
TTM have undertaken a 14-hour traffic count at the Bruce Highway / Abbot Point Road intersection
to establish existing peak hour traffic volumes. The traffic survey has indentified that the Bruce
Highway carries relatively low traffic volumes in the AM peak 110 vehicles each direction and 100
vehicles each direction in the PM peak, Figure 6.1 showing a total volume count summary.
Figure 6.2 shows the growth factored peak hour base traffic against the highest existing peak hour
(AM peak) and the predicted development traffic volumes. This RPDM Figure indicates that the
existing intersection treatments are adequate based on existing highway traffic volumes and the
predicted level of traffic generated from the existing Port of Abbot Point site.
© 2013 - TTM Consulting Pty Ltd Reference: 12SCT0042/03
29
EIS Traffic and Transport Assessment Adani T0 Project: Abbot Point, QLD
Figure 6.1: Bruce Highway / Abbot Point Road Intersection Count Data
TTM Reference:
Location:
Suburb:
Date:
Survey Period:
Weather:
www.ttmgroup.com.au
00% indicates the heavy vehicle percentage
208 173 0 173
707 676 6 682
915 0 849 6 855
20% 0%
0 159 150 9
0
0
0% 6 6 0
0 6% 147 138 9
23% 6% 153 144 9
Total Light Heavy
1062 909 153 0 996
845 701 144 814
217 208 9 182
© TTM Consulting Pty Ltd
12SCT0107
Bruce Hwy / Abbot Point Rd Intersection
Bowen
Tuesday 05/03/2013
Fine
0500-1900
Light
Heavy
Bruce Hwy
Total
Abbot Point Rd
Bruce Hwy
Heavy
Light
Total
© 2013 - TTM Consulting Pty Ltd Reference: 12SCT0042/03
30
EIS Traffic and Transport Assessment Adani T0 Project: Abbot Point, QLD
Figure 6.2: Existing Layout Review: Operational Phase 2026
6.6 Right and Left Turn Requirements In reviewing the RPDM right turn warrant requirements as noted, the existing intersection lane
provisions can adequately cater for both the construction and operational traffic demands.
6.7 Intersection Capacity Review In a review of the GARID Guidelines Criteria 3: Traffic Operation Assessment, traffic operation
impacts need to be considered for any section of a State Controlled Road (SCR) where the
construction or operational traffic generated by the development equals or exceeds 5% of the
existing AADT on the road section, intersection movements or turning movements.
6.8 Uninterrupted Flow Conditions TTM note that reference has been made to Road Planning and Design Manual (RPDM), Table 13.4
Intersection Capacity - Uninterrupted Flow Conditions as shown in Figure 6.3. The table provides
criteria details on the level of traffic for uninterrupted flow conditions which assumes intersections
will operate with nominal delays and queuing if traffic volumes are less than the volumes stated.
The level of peak hour traffic anticipated (with development traffic) is predicted to have two-way
peak hour volumes less than 300vph. This level of traffic in accordance with the RPDM is therefore
unlikely to impact significantly on the intersection performance, with the intersections operating
under uninterrupted flow conditions with nominal delays and queuing.
TTM note that the majority of site worker activity will occur prior to the highway morning peak
period (before 8:00am) and after the highway evening peak period (after 5:00pm), with any
construction vehicle activity operating throughout the working day.
Left Turn
Right Turn
© 2013 - TTM Consulting Pty Ltd Reference: 12SCT0042/03
31
EIS Traffic and Transport Assessment Adani T0 Project: Abbot Point, QLD
Figure 6.3: RPDM Chapter 13: Table 13.4
6.9 Adjacent Bruce Highway Intersections As noted, it is anticipated that the construction and operational traffic volumes will have a negligible
traffic impact along the Bruce Highway corridor, due to the level of traffic on the Bruce Highway
during the development peak traffic periods. TTM do not envisage any further traffic impacts at any
further intersections along the Bruce Highway corridor.
6.10 Updated Traffic Capacity Assessment TTM note that an updated traffic capacity assessment will be undertaken as part of the RMP, which
will review in detail the traffic generated by the construction activities.
© 2013 - TTM Consulting Pty Ltd Reference: 12SCT0042/03
32
EIS Traffic and Transport Assessment Adani T0 Project: Abbot Point, QLD
7 Road Pavement Impact Assessment This chapter will review the road pavement traffic impacts associated with the construction and
operational activities, with the Bruce Highway subject to additional heavy vehicle traffic due to site
operations.
7.1 Existing ESA Pavement Loadings It is assumed that the average ESA on the Bruce Highway equates to 2.8 for heavy vehicle
classification. Traffic data gained from DTMR has established that the average percentage of heavy
vehicles on the Bruce Highway between Bowen and Townsville is between 5% to 22%, with the
percentage level of trucks on the Bruce Highway adjacent to the Port Access Road being 21%.
7.2 Development Heavy Vehicle Generation & Impacts The total heavy vehicle traffic from the site has been estimated in Chapter 4 of this report. This
identified that the site will generate 12 (24 total) larger type service vehicle and 7 (14 total) bus trips
per day during the construction stage. This will change to 30 (60 total) smaller type service vehicles
during the operational stage.
The vehicles that terminate in the vicinity of Townsville are expected to be local service vehicles
(generally smaller trucks). The vehicles which continue beyond Townsville and to the south are
expected to be larger configuration (B-double and road train if based on abnormal loads).
Heavy vehicle distribution by classification is expected to be geared towards the higher loads and
larger vehicles during the construction activity, with an average ESA of 3.0 per heavy vehicle. The
type of load and truck is anticipated to be smaller during the operational stage, with typical bus,
servicing and maintenance deliveries to the site having an average ESA of 2.2 per heavy vehicle.
Table 7.1 and Table 7.2 show the level of predicted generated heavy vehicle volumes and their
resultant ESA’s, with Table 7.3 and Table 7.4 showing the respective impacts.
Table 7.1: Construction Stage: Daily ESA Generation
Road Trucks ESA
Truck
Truck
ESAs
Buses Average
ESA bus
Bus ESAs Daily
ESAs
Bruce Highway 24 3.0 72 14 2.2 31 103
Table 7.2: Operational Stage: Daily ESA Generation
Road Trucks ESA
Truck
Truck
ESAs
Buses Average
ESA bus
Bus ESAs Daily
ESAs
Bruce Highway 60 2.2 132 - - - 132
© 2013 - TTM Consulting Pty Ltd Reference: 12SCT0042/03
33
EIS Traffic and Transport Assessment Adani T0 Project: Abbot Point, QLD
Table 7.3: Bruce Highway Impact on Road Network: Construction Stage
Route/ Counter Site
2013 AADT Existing Truck ESA Development Truck ESA
% CV ESA ESA Impact
10K/92198 3803 21% 2,236 82 (South) 3.7%
10K/92198 3803 21% 2,236 21 (North) 0.9%
Table 7.4: Bruce Highway Impact on Road Network: Construction Stage
Route/ Counter Site
201 AADT Existing Truck ESA Development Truck ESA
% CV ESA ESA Impact
10K/92198 4156 21% 2,444 40 (South) 1.6%
10K/92198 4156 21% 2,444 92 (North) 3.8%
7.3 Mitigation Review By definition, the construction and operational traffic impacts due to the project are deemed to be
insignificant as the additional levels will be less than 5% of existing daily traffic levels on the majority
of the SCR network.
As shown in Table 7.3 and Table 7.4 the level of construction and full operational activity is
considered to have an insignificant traffic and pavement impact on the Bruce Highway adjacent to
the site.
TTM note that an updated pavement impact assessment will be undertaken as part of the RMP,
which will review in detail the traffic generated by the construction activities.
© 2013 - TTM Consulting Pty Ltd Reference: 12SCT0042/03
34
EIS Traffic and Transport Assessment Adani T0 Project: Abbot Point, QLD
8 Draft Road-use Management Plan (RMP)
8.1 Introduction It is intended that a RMP will be prepared at least 6 months prior to the commencement of
construction activities. The RMP will be a transforming document which evolves over time based on
project requirements and the road environment.
The purpose of a RMP is to identify appropriate protection objectives and associated
implementation strategies together with monitoring, auditing, reporting and corrective actions to be
adopted if an undesirable impact or unforeseen level of impact occurs.
It is noted that the RMP will be reviewed and periodically updated, if necessary, to reflect knowledge
gained during the detailed design process, construction and the course of operations. The following
provides an outline RMP, highlighting potential key policies and objectives:
8.2 Draft RMP Policy Statement It is intended that the key RMP policy will be based on ‘minimising any impacts on the State
Controlled Road (SCR) and associated traffic generated by the Project, including the transportation
and handling of materials’.
8.3 Draft RMP Objectives The following provides a summary on the key RMP objectives:
To minimise the impact on the efficiency of the State Controlled Road Network;
To ensure for safe operation of vehicles on and off the site; and
To minimise any potential traffic-related complaints and incidents.
In order to meet these objectives the RMP will include the following:
A summary of updated project traffic information and impact assessments;
Review of mitigation strategies including time frames for approvals, permits and
implementation;
Identification of roles and responsibilities of the working group, and the monitoring process
involved; and
Development, Consultation and Implementation of Strategies and Policies.
8.4 Draft RMP Implementation Strategy It is anticipated that a working party will be established to review and sign off on the RMP which will
enable the proponent and its contractors to formally adopt and implement the RMP in relation to
any site vehicular transport requirements. The working party would likely consist of members from
DTMR Fitzroy Region, Council, local emergency services (Police, Fire and Ambulance authorities),
HVROPO including a representative from the local school bus committee. The RMP will be made
available to the public with key contact details provided. It is envisaged that this RMP will be
updated annually included a review by all members of the working party.
© 2013 - TTM Consulting Pty Ltd Reference: 12SCT0042/03
35
EIS Traffic and Transport Assessment Adani T0 Project: Abbot Point, QLD
The RMP will include an updated traffic and pavement impact assessment based on the latest
information available. It is anticipated that these assessments will form the basis of financial
agreements between the proponent, DTMR regarding road upgrade, maintenance and rehabilitation
contributions.
8.5 Draft Implementation Strategy The RMP Strategies/Policies will be developed and implemented in consultation with key
stakeholders as to mitigate any road safety risks associated with the development traffic generation.
This will be for safer road conditions and driver behaviour on all roads accessing the Project. The
RMP once complete will provide more detailed information on each strategy/policy and may
incorporate additional strategies, however the following provides an outline of several key strategies
to be implemented and developed further:
8.5.1 Driver Fatigue Policies
The proposed development will result in an additional DIDO trips on the road network, where
fatigue is a significant factor. As such, it is recommended that the local Road Accident Action Group
(RAAG) is consulted with respect to local policy on fatigue. The construction industry as a whole
should participate in this forum to address the issue of fatigue and determine strategies for dealing
with fatigue for DIDO trips.
Typical Strategies to minimise the impacts of driver fatigue include the following:
Allowing DIDO staff to work shorter shifts at the start and end of their working period;
Providing DIDO staff with an additional day or night of accommodation prior to commencing
work or driving home; and
Sponsorship of rest zones and driver reviver stations.
8.5.2 Driver Behaviour Policies
This policy relates to DIDO workers, staff who drive private vehicles to site and contractors. This
policy will include requirements for these employees and contractors to drive in a safe manner when
in charge of a vehicle, with additional attention to any instance of public transport use (school bus
times), OD, heavy vehicle use and pedestrian and cyclist activity. This policy will also inform workers
of other strategies including their implementation, monitoring and reporting as to discourage use of
local roads that do not form part of the access route to the construction site.
8.5.3 Work Related Travel and Transport Policies
This policy relates to the use of communal transport, work access, and alternative travel modes
related to construction and operation of the project. This policy will include use targets and
strategies to increase communal transport use by staff and contractors, reduce the impact on the
local community and to deal with the movement of goods to and from site in a safe and responsible
manner.
8.5.4 Over-dimension Vehicle Management
As part of the construction and operation phases of the development it is necessary that some
indivisible components will be delivered by over-dimensional (OD) vehicles. Where OD access is
required it is necessary to provide pilot vehicles and police escorts, dependant on the size of the
vehicle.
© 2013 - TTM Consulting Pty Ltd Reference: 12SCT0042/03
36
EIS Traffic and Transport Assessment Adani T0 Project: Abbot Point, QLD
The proponent will liaise with the Heavy Vehicle Road Operations Program Office (HVROPO) in
Rockhampton regarding OD use as early as possible. It is noted that a 6 month lead time to organise
permits and personnel is required by this office. The community will also be advised of any OD
vehicle activity related to the construction and operation of the Project. These strategies may
include radio announcements and information via the internet, however the RMP will identify all OD
and heavy vehicle movements as early as possible.
8.5.5 Road Safety Audit Review, Capacity & ALCAM Assessment
An independent Road Safety Audit (RSA) will be undertaken by an accredited auditor in relation to
the operation of the Abbot Point intersection. This audit will be undertaken prior to any construction
activity and will establish the existing road safety conditions and potential impacts associated with
the construction traffic.
The RSA will also review any school bus activity, however, due to the relatively secluded location of
the development and limited bus activity along the Bruce Highway, the level of development traffic
is considered to have a minor impact on any school or public transport operations along this
highway.
A further intersection analysis will be undertaken once the site construction vehicle activity and
programme has been updated/refined to determine the level of any development traffic impacts.
An ALCAM assessment will be undertaken once the site construction vehicle activity and programme
has been updated/refined. This ALCAM assessment will identify any potential mitigation measures
associated with the level crossing, which will be further discussed with both Aurizon, DTMR officials
including key stakeholders (Port Authority).
8.5.6 Road Noise Management
There are residential and sensitive noise receiving developments located immediately adjacent to
the Bruce Highway at the Ayr, Bowen and Proserpine townships. Typically, these residents are set-
back suitably to allow for rural highway traffic volumes and are set back from the highway.
Operationally, it will be communicated to truck drivers that they are expected to conduct
themselves with appropriate care towards local residents. This will include limiting the use of air
brakes in townships and near residences, restricting the movements of heavy vehicles to within
standard business hours when possible, and driving in a safe and responsible manner.
8.5.7 Dust Control Management
Internally, it is expected that all heavy vehicles leaving the site will be subject to a wash-down of
tyres to limit loose material being transported onto SCR network.
8.5.8 On-site Parking Management
It is recommended that parking on site be provided as follows:
1 space for every employee during peak accumulation;
On-site bus set-down facilities; and
On-site standing and parking for service vehicles separate from private vehicle areas.
© 2013 - TTM Consulting Pty Ltd Reference: 12SCT0042/03
37
EIS Traffic and Transport Assessment Adani T0 Project: Abbot Point, QLD
8.5.9 Dangerous Goods Management
All transportation of dangerous goods by road will be carried out in accordance with the licensing
and vehicles requirements set out by DTMR. This includes operational policies for the port
operators, its suppliers and sub-contractors that all drivers transporting dangerous goods are
adequately trained, hold valid licenses and that all vehicles are adequate for transportation of these
materials.
Typical dangerous goods expected to be transported to / from the site include:
Fuel and oil;
Flammable gas;
Corrosive materials including solvents; and
Chemical waste (including sewerage).
© 2013 - TTM Consulting Pty Ltd Reference: 12SCT0042/03
38
EIS Traffic and Transport Assessment Adani T0 Project: Abbot Point, QLD
9 Conclusions and Recommendations From a traffic engineering perspective, the peak traffic impacts associated with the Project are
expected to be between 2013 and 2014 during the main on-site construction activity. On
completion, it is anticipated that the port will employ approximately a total of 250 workers to serve
typical port operations.
This traffic impact assessment has considered both the construction and operational stages of the
Project.
The level of likely worker activity has been assessed which has established that their traffic impacts
will be negligible due to the roster and shift patterns, with construction workers being generally
transported by bus.
A likely inventory of the heavy vehicles required during construction has been developed as
provided which is expected to generate approximately 24 total loaded and unloaded heavy vehicle
trips per day. During the peak operational stage the site is expected to generate a further 60 total
loaded and unloaded heavy vehicle trips per day per day.
The level of traffic generated by both the construction and full operational stage (70 Mtpa
throughput) is therefore not expected to have a significant traffic impact on the local or wider
strategic road network.
However, it is intended for a RMP to be prepared as to identify any appropriate protection
objectives and associated implementation strategies, together with any monitoring, auditing,
reporting and corrective actions to be adopted. This RMP will ensure that any undesirable impact or
unforeseen level of impact is assessed/addressed on both the road and rail networks