+ All Categories
Home > Documents > ADDENDUM #3 TO CONTRACT DOCUMENTS FOR:...

ADDENDUM #3 TO CONTRACT DOCUMENTS FOR:...

Date post: 09-Aug-2020
Category:
Upload: others
View: 0 times
Download: 0 times
Share this document with a friend
34
Page 1 of 4 August 02, 2018 ADDENDUM #3 TO CONTRACT DOCUMENTS FOR: Project #CP181001 – Critical Care Addition - Roof Replacement ADVERTISEMENT DATE: July 9, 2018 PREPARED FOR: The Curators of the University of Missouri CONSULTANT: Planning, Design & Construction University of Missouri 130 General Services Building (573) 882-6800 The contract documents for the above noted project and the work covered thereby and herein modified. PROJECT MANUAL: 1) Table of Contents: ADD Alternates section “ALT/1”. REVISE number of pages in 07550 Specification to 18 2) Specification Section 1.A., Bid for Lump Sum Contract: A REVISED “Bid for Lump Sum Contract” is attached. Revisions have been made to paragraphs 3b Additive Alternate Bids. BIDS MUST SUBMITTED ON THE ATTACHED REVISED FORM. 3) Specification Section 1.H, Alternates: ADD this section in entirety. 1. Additive Alternate No. 1: Remove and replace building expansion joint system per the plans and specifications. 2. Additive Alternate No. 2: Provide a 40 year warranty in lieu of the specified 30 year warranty as specified within the base bid. 4) Specification Section 07550, Modified Bituminous Membrane Roofing, Paragraph 1.9. Warranty,: ADD the following paragraphs: 1. Warranty Period: 1. 30 years from the date of acceptance 2. Alternate 2: 40 years from the date of acceptance a. The 40 year warranty must be a standard warranty issued by the manufacturer and include any provisions required by the Manufacturer to meet the 40 year warranty term such as materials, inspections and installation requirements.
Transcript
Page 1: ADDENDUM #3 TO CONTRACT DOCUMENTS FOR: …operations-webapps.missouri.edu/pdc/adsite/projects/cp181001/add… · Page 1 of 4 August 02, 2018 ADDENDUM #3 TO CONTRACT DOCUMENTS FOR:

Page 1 of 4

August 02, 2018 ADDENDUM #3 TO CONTRACT DOCUMENTS FOR: Project #CP181001 – Critical Care Addition - Roof

Replacement ADVERTISEMENT DATE: July 9, 2018 PREPARED FOR: The Curators of the University of Missouri CONSULTANT: Planning, Design & Construction University of Missouri 130 General Services Building (573) 882-6800 The contract documents for the above noted project and the work covered thereby and herein modified. PROJECT MANUAL: 1) Table of Contents: ADD Alternates section “ALT/1”. REVISE number of pages in 07550

Specification to 18 2) Specification Section 1.A., Bid for Lump Sum Contract: A REVISED “Bid for Lump

Sum Contract” is attached. Revisions have been made to paragraphs 3b Additive Alternate Bids. BIDS MUST SUBMITTED ON THE ATTACHED REVISED FORM.

3) Specification Section 1.H, Alternates: ADD this section in entirety.

1. Additive Alternate No. 1: Remove and replace building expansion joint system per the plans and specifications.

2. Additive Alternate No. 2: Provide a 40 year warranty in lieu of the specified 30

year warranty as specified within the base bid. 4) Specification Section 07550, Modified Bituminous Membrane Roofing, Paragraph 1.9.

Warranty,: ADD the following paragraphs: 1. Warranty Period:

1. 30 years from the date of acceptance 2. Alternate 2: 40 years from the date of acceptance

a. The 40 year warranty must be a standard warranty issued by the manufacturer and include any provisions required by the Manufacturer to meet the 40 year warranty term such as materials, inspections and installation requirements.

Page 2: ADDENDUM #3 TO CONTRACT DOCUMENTS FOR: …operations-webapps.missouri.edu/pdc/adsite/projects/cp181001/add… · Page 1 of 4 August 02, 2018 ADDENDUM #3 TO CONTRACT DOCUMENTS FOR:

Page 2 of 4

 

5) Specification Section 07550, Modified Bituminous Membrane Roofing, Paragraph 2.1.B., Approved Equals (Subject to the Provisions of the Specifications): ADD the following paragraphs: 3.           Tremco Roofing & Building Maintenance:                a.            3735 Green Road, Beachwood, Ohio 44122.  Toll Free: 800‐562‐2728.  Web  

      Site:  www.tremcoroofing.com.                b.           Products to be included:                                 (1)      Base Sheet and Flashing Base:    POWERply Heavy Duty Base Sheet                                 (2)      Cap Sheet and Flashing Cap:       POWERply Premium FR Cap Sheet                                             (3)      Membrane Adhesive:                   POWERply Endure BIO Adhesive                                 (4)       Insulation Adhesive:                     POWERply Endure BIO Adhesive                                 (5)     Tapered Insulation:                       Trisotech Insulation                                 (6)      Coverboard:                                    Tremco GP Gypsum Dens‐Deck                                 (7)      Aluminum Coating:                        Alumanation 301  

6) Specification Section 07550, Modified Bituminous Membrane Roofing, Paragraph 2.1.C.1., Project Management: DELETE paragraph and REPLACE with the following paragraph: 1. Project Management: All on-site project management duties by the roof system

manufacturer must be completed by an actual employee of the manufacturer and may not be subcontracted to an outside source. For example: Consultants, product representatives, dealers, etc. are not acceptable. The Manufacturer’s Project Manager must complete the following duties: 1. Conduct and additional preconstruction meeting with the owner, architect,

roofing contractor, sheet metal contractor in order to layout all expectations and requirements of the project. This shall be completed by the roofing manufacturer at least two weeks prior to start of the project. Provide 3 onsite inspections per week during construction to ensure proper application of the roof system by the roofing contractor. Utilize the inspection form located at the end of this section of the specification which is to be filled out and emailed to the management and architects after each inspection.

7) Specification Section 07550, Cold Applied 2-ply Solvent Free Asphalt Roofing,

Paragraph 2.2.B.1, Modified Cap (Ply) Sheet: DELETE paragraph and REPLACE with the following paragraph: 1. 155 mil SBS (Styrene-Butadiene-Styrene) mineral surfaced, rubber modified

roofing membrane reinforced with a fiberglass and polyester composite scrim. ASTM D 6162, Type III Grade G 1) Tensile Strength, ASTM D 5147

a) 2 in/min. @ 73.4 +/- 3.6 deg. F MD 300 lbf/in XD 310 lbf/in b) 50 mm/min. @ 23 +/- 2 deg. C MD 54.25 kN/m XD 54.25 kN/m

2) Tear Strength, ASTM D 5147 a) 2 in/min. @ 73.4 +/- 3.6 deg. F MD 350 lbf XD 500 lbf b) 50 mm/min. @ 23 +/- 2 deg. C MD 2224 N XD 2224 N

Page 3: ADDENDUM #3 TO CONTRACT DOCUMENTS FOR: …operations-webapps.missouri.edu/pdc/adsite/projects/cp181001/add… · Page 1 of 4 August 02, 2018 ADDENDUM #3 TO CONTRACT DOCUMENTS FOR:

Page 3 of 4

8) Specification Section 07550, Cold Applied 2-ply Solvent Free Asphalt Roofing, Paragraph 2.2.C.1, Interply Adhesive: DELETE paragraph and REPLACE with the following paragraph: 1. Cold applied solvent free membrane adhesive: Low V.O.C. compliant performance

requirements (up to 5g/l VOC): 1. Non-Volatile Content ASTM D 4586

9) Specification Section 07550, Cold Applied 2-ply Solvent Free Asphalt Roofing,

Paragraph 2.2.E.1, Flashing Ply Adhesive: DELETE paragraph and REPLACE with the following paragraph: 1. Flashing Adhesive: Cold applied solvent free flashing adhesive: Low V.O.C.

compliant performance requirements (up to 5g/l VOC): 1. Non-Volatile Content ASTM D 4586 10) Specification Section 07550, Cold Applied 2-ply Solvent Free Asphalt Roofing,

Paragraph 2.2.E.2, Flashing (Cap) Ply Sheet: DELETE paragraph and REPLACE with the following paragraph: 2. Flashing Cap (Ply) Sheet:

1. 155 mil SBS and SIS (Styrene-Butadiene-Styrene and Styrene-Isoprene- Styrene) rubber modified membrane incorporating post-consumer recycled rubber and reinforced with a fiberglass and polyester composite scrim. Surfaced with the highly reflective Sunburst white mineral. ASTM D 6162, Type III Grade G. 1) Tensile Strength, ASTM D 5147 a) 2 in/min. @ 73.4 +/- 3.6 deg. F MD 300 lbf/in XD 310 lbf/in

b) 50 mm/min. @ 23 +/- 2 deg. C MD 175 kN/m XD 192.5 kN/m 2) Tear Strength,, ASTM D 5147 a) 2 in/min. @ 73.4 +/- 3.6 deg. F MD 350 lbf XD 500 lbf b) 50 mm/min. @ 23 +/- 2 deg. C MD 6,672.3 N XD 7,561.6 N

11) Specification Section 07550, Cold Applied 2-ply Solvent Free Asphalt Roofing,

Paragraph 2.3.N. Wall Expansion Joints: ADD paragraph N. Wall Expansion Joints:

1. All joints shall be designed to meet the specified performance criteria of the SEISMIC COLORSEAL product as manufactured by: (USA & International) EMSEAL JOINT SYSTEMS, LTD 25 Bridle Lane, Westborough, MA 01581-2603, Toll Free: 800-526- 8365. (Canada) EMSEAL, LLC 120 Carrier Drive, Toronto, Ontario, Canada M9W 5R1 Toll Free: 800-526-8365. www.emseal.com 2. Substitutions from alternate manufacturers must meet the following requirements:

1) All products must be certified by independent laboratory test report to exceed the requirements of curtain wall performance tests ASTM E330, E283-04, and E331. Product must meet or exceed hurricane-force wind loading with no deflection at both positive and negative pressures up to 4954 Pascals—equal to 200 mph winds (ASTM E330-02-procedure A). 2) All products must be certified by independent laboratory test report to ASTM E90-09 and to meet or exceed an STC 52 in STC 56 wall and OITC 38 rating in an OITC 38 wall.

Page 4: ADDENDUM #3 TO CONTRACT DOCUMENTS FOR: …operations-webapps.missouri.edu/pdc/adsite/projects/cp181001/add… · Page 1 of 4 August 02, 2018 ADDENDUM #3 TO CONTRACT DOCUMENTS FOR:

Page 4 of 4

3) All products must be certified by independent laboratory test report to be free in composition of any waxes or wax compounds using FTIR and DSC testing. 4) All products shall be certified in writing to be: a) capable of withstanding 150°F (65°C) for 3 hours while compressed down to the minimum of movement capability dimension of the basis of design product (-50% of nominal material size) without evidence of any bleeding of impregnation medium from the material; and b) that the same material after the heat stability test and after first being cooled to room temperature will subsequently self-expand to the maximum of movement capability dimension of the basis-of-design product (+50% of nominal material size) within 24 hours at room temperature 68°F (20°C). 5) Quality and Environmental control: Manufacturer shall be certified to both ISO-9001:2015 (quality management) and ISO-14001:2015 (environmental management), and shall provide written confirmation that formal Quality and Environmental management systems and processes have been adopted.

3. Provide watertight, energy-efficient exterior joints in vertical-plane walls (abovegrade). 4. Material shall be capable of movements of +50%, -50% (100% total) of nominal material size. 5. Color to be standard “Light Gray”. Confirm color with owner prior to installation. 6. Install and seal per manufacturer installation instructions.

PROJECT DRAWINGS: 1) ADD Drawing Detail 12/ A-2.1 and Drawing Detail 13/ A-2.1 related to the

expansion joint detail for Alternate 1.

END OF ADDENDUM #3

Page 5: ADDENDUM #3 TO CONTRACT DOCUMENTS FOR: …operations-webapps.missouri.edu/pdc/adsite/projects/cp181001/add… · Page 1 of 4 August 02, 2018 ADDENDUM #3 TO CONTRACT DOCUMENTS FOR:

PROJECT MANUAL FOR: CRITICAL CARE ADDITION – ROOF REPLACEMENT PROJECT NUMBER: CP181001

TABLE OF CONTENTS TITLE PAGE DIVISION 1 GENERAL REQUIREMENTS Advertisement for Bids 1.A Bid for Lump Sum Contract 1.A/1-5 1.B Bidder's Statement of Qualifications BSQ/1-2 1.B.2 Supplier Diversity Compliance Evaluation SD/1-2 1.B.3 Application for Waiver SD/3-4 1.B.4 Affidavit SD/5 1.B.5 Affidavit for Affirmative Action SD/6 1.B.6 Certifying Supplier Diversity Agencies SD/7 1.B.7 Newspapers for Outreach to Diverse Suppliers SD/8 1.B.8 Affidavit of Supplier Diversity Participation SD/9 1.C Information for Bidders IFB/1-5 1.D General Conditions GC/1-46 1.E Special Conditions SC/1-12 1.E.1 Scheduling Specification SS/1-5 1.E.2 Roofing System Manufacturer’s Certification RSMC/1

1.E.3 Contractor’s Roofing/Flashing/Sheet Metal Guarantee CRFSMG/1-2

1.E.4 Shop Drawing and Submittal Log SDSL/1-2 1.E.5 Operating Instructions and Service Manual Log OMML/1 1.E.6 Closeout Log CLOSL/1

Page 6: ADDENDUM #3 TO CONTRACT DOCUMENTS FOR: …operations-webapps.missouri.edu/pdc/adsite/projects/cp181001/add… · Page 1 of 4 August 02, 2018 ADDENDUM #3 TO CONTRACT DOCUMENTS FOR:

1.F Index of Drawings INDEX/1 1.G Prevailing Wage Rates PW/1-15 1.H Alternates ALT/1 DIVISION 2 EXISTING CONDITIONS (NOT USED) DIVISION 3 CONCRETE (NOT USED) DIVISION 4 MASONRY (NOT USED) DIVISION 5 METALS (NOT USED) DIVISION 6 WOOD AND PLASTICS, AND COMPOSITES (NOT USED) DIVISION 7 THERMAL AND MOISTURE PROTECTION 07550 Modified Bituminous Membrane Roofing 07550/1-18 DIVISION 8 OPENINGS (NOT USED) DIVISION 9 FINISHES (NOT USED) DIVISION 10 SPECIALTIES (NOT USED) DIVISION 11 EQUIPMENT (NOT USED) DIVISION 12 FURNISHINGS (NOT USED) DIVISION 13 SPECIAL CONSTRUCTION (NOT USED) DIVISION 14 CONVEYING SYSTEMS (NOT USED) DIVISION 21 FIRE SUPPRESSION (NOT USED) DIVISION 22 PLUMBING (NOT USED) DIVISION 23 MECHANICAL (NOT USED) DIVISION 25 INTEGRATED AUTOMATION (NOT USED) DIVISION 26 ELECTRICAL (NOT USED) DIVISION 27 COMMUNICATIONS (NOT USED) DIVISION 28 ELECTRONIC SAFETY AND SECURITY (NOT USED)

Page 7: ADDENDUM #3 TO CONTRACT DOCUMENTS FOR: …operations-webapps.missouri.edu/pdc/adsite/projects/cp181001/add… · Page 1 of 4 August 02, 2018 ADDENDUM #3 TO CONTRACT DOCUMENTS FOR:

DIVISION 31 EARTHWORK (NOT USED) DIVISION 32 EXTERIOR IMPROVEMENTS (NOT USED) DIVISION 33 UTILITIES (NOT USED) DIVISION 34 TRANSPORTATION (NOT USED)

END OF SECTION

Page 8: ADDENDUM #3 TO CONTRACT DOCUMENTS FOR: …operations-webapps.missouri.edu/pdc/adsite/projects/cp181001/add… · Page 1 of 4 August 02, 2018 ADDENDUM #3 TO CONTRACT DOCUMENTS FOR:

MU Project #CP181001 1.A - 1 Addendum 3

SECTION 1.A

BID FOR LUMP SUM CONTRACT

Date:____________________________ BID OF (hereinafter called "Bidder") a corporation* organized and existing under laws of the State of , a partnership* consisting of , an individual* trading as , a joint venture* consisting of . *Insert Corporation(s), partnership or individual, as applicable. TO: Curators of the University of Missouri

c/o Associate Vice Chancellor – Facilities Room L100, General Services Building University of Missouri Columbia, Missouri 65211

1. Bidder, in compliance with invitation for bids for construction work in accordance

with Drawings and Specifications prepared by Planning, Design, and Construction, entitled "Critical Care Addition – Roof Replacement", project number CP181001, dated June 28, 2018 having examined Contract Documents and site of proposed work, and being familiar with all conditions pertaining to construction of proposed project, including availability of materials and labor, hereby proposes to furnish all labor, materials and supplies to construct project in accordance with Contract Documents, within time set forth herein at prices stated below. Prices shall cover all expenses, including taxes not covered by the University of Missouri’s tax exemption status, incurred in performing work required under Contract documents, of which this Bid is a part.

Bidder acknowledges receipt of following addenda:

Addendum No. Dated Addendum No. Dated Addendum No. Dated Addendum No. Dated

2. In following Bid(s), amount(s) shall be written in both words and figures. In case of discrepancy between words and figures, words shall govern.

Page 9: ADDENDUM #3 TO CONTRACT DOCUMENTS FOR: …operations-webapps.missouri.edu/pdc/adsite/projects/cp181001/add… · Page 1 of 4 August 02, 2018 ADDENDUM #3 TO CONTRACT DOCUMENTS FOR:

MU Project #CP181001 1.A - 2 Addendum 3

3. BID PRICING a. Base Bid:

The Bidder agrees to furnish all labor, materials, tools, and equipment required to remove existing modified bitumen roofing and install new roofing; all as indicated on the Drawings and described in these Specifications for sum of: DOLLARS ($ ).

b. Additive Alternate Bids:

Above Base Bid may be changed in accordance with following Alternate Bids

as Owner may elect. Alternates are as described in Section 1.H of Project Manual. Alternates are written in a priority order, but Owner is not required to accept or reject in order listed. This is a one (1) contract project, therefore, Alternates shall be studied by each Bidder to determine effect on Bids of Contractor and each Subcontractor and/or Material supplier.

(1) Additive Alternate No. 1:

Remove and replace building expansion joint system per the plans and specifications. All for sum of:

DOLLARS ($ ).

(2) Additive Alternate No. 2:

Provide a 40 year warranty in lieu of the specified 30 year warranty as specified within the base bid. All for sum of:

DOLLARS ($ ).

4. PROJECT COMPLETION

a. Contract Period - Contract period begins on the day the Contractor receives unsigned Contract, Performance Bond, Payment Bond, and "Instructions for Execution of Contract, Bonds, and Insurance Certificates." Bidder agrees to complete project within One Hundred Twenty (120) calendar days from receipt of aforementioned documents. Fifteen (15) calendar days have been allocated in construction schedule for receiving aforementioned documents from Bidder.

b. Commencement - Contractor agrees to commence work on this project after

the "Notice to Proceed" is issued by the Owner. "Notice to Proceed" will be issued within seven (7) calendar days after Owner receives properly prepared and executed Contract documents listed in paragraph 4.a. above.

Page 10: ADDENDUM #3 TO CONTRACT DOCUMENTS FOR: …operations-webapps.missouri.edu/pdc/adsite/projects/cp181001/add… · Page 1 of 4 August 02, 2018 ADDENDUM #3 TO CONTRACT DOCUMENTS FOR:

MU Project #CP181001 1.A - 3 Addendum 3

c. Special scheduling requirements - Work shall be performed between 6:00 am

and 8:00 pm, Monday through Friday.

d. All noisy and vibration causing work shall only occur after being coordinated and approved at least 48 hours in advance with Owner's Representative.

e. Access to site will be limited the week of August 13th along the northern

access road abutting the residential life building; coordinate with owner’s representative for access plan a minimum of one week prior.

5. SUPPLIER DIVERSITY PARTICIPATION GOALS a. The Contractor shall have as a goal, subcontracting with Minority Business

Enterprise (MBE) of ten percent (10%), with Service Disabled Veteran Owned Business (SDVE) of three percent (3%); and with Women Business Enterprise (WBE), Disadvantage Business Enterprise (DBE), and/or Veteran Owned Business of ten percent (10%) of awarded contract price for work to be performed.

b. Requests for waiver of this goal shall be submitted on the attached

Application For Waiver form. A determination by the Director of Facilities Planning & Development, UM, that a good faith effort has not been made by Contractor to achieve above stated goal may result in rejection of bid.

c. The Undersigned proposes to perform work with following Supplier Diversity

participation level: MBE PERCENTAGE PARTICIPATION: percent ( %) SDVE PERCENTAGE PARTICIPATION: percent ( %) WBE, DBE, and/or VETERAN PERCENTAGE PARTICIPATION percent ( %)

d. A Supplier Diversity Compliance Evaluation form shall be submitted with this

bid for each diverse subcontractor to be used on this project. 6. BIDDER'S ACKNOWLEDGMENTS a. Bidder declares that he has had an opportunity to examine the site of the

work and he has examined Contract Documents therefore; that he has carefully prepared his bid upon the basis thereof; that he has carefully examined and checked bid, materials, equipment and labor required

Page 11: ADDENDUM #3 TO CONTRACT DOCUMENTS FOR: …operations-webapps.missouri.edu/pdc/adsite/projects/cp181001/add… · Page 1 of 4 August 02, 2018 ADDENDUM #3 TO CONTRACT DOCUMENTS FOR:

MU Project #CP181001 1.A - 4 Addendum 3

thereunder, cost thereof, and his figures therefore. Bidder hereby states that amount, or amounts, set forth in bid is, or are, correct and that no mistake or error has occurred in bid or in Bidder's computations upon which this bid is based. Bidder agrees that he will make no claim for reformation, modifica-tions, revisions or correction of bid after scheduled closing time for receipt of bids.

b. Bidder agrees that bid shall not be withdrawn for a period of sixty (60) days

after scheduled closing time for receipt of bids. c. Bidder understands that Owner reserves right to reject any or all bids and to

waive any informalities in bidding. d. Accompanying the bid is a bid bond, or a certified check, or an irrevocable

letter of credit, or a cashier's check payable without condition to "The Curators of the University of Missouri" which is an amount at least equal to five percent (5%) of amount of largest possible total bid herein submitted, including consideration of Alternates.

e. Accompanying the bid is a Bidder's Statement of Qualifications. Failure of

Bidder to submit the Bidder's Statement of Qualifications with the bid may cause the bid to be rejected. Owner does not maintain Bidder's Statements of Qualifications on file.

f. It is understood and agreed that bid security of two (2) lowest and responsive

Bidders will be retained until Contract has been executed and an acceptable Performance Bond and Payment Bond has been furnished. It is understood and agreed that if the bid is accepted and the undersigned fails to execute the Contract and furnish acceptable Performance/Payment Bond as required Contract Documents, accompanying bid security will be realized upon or retained by Owner. Otherwise, the bid security will be returned to the undersigned.

7. BIDDER'S CERTIFICATE

Bidder hereby certifies: a. His bid is genuine and is not made in interest of or on behalf of any

undisclosed person, firm or corporation, and is not submitted in conformity with any agreement or rules of any group, association or corporation.

b. He has not directly or indirectly induced or solicited any other bidder to put in

a false or sham bid. c. He has not solicited or induced any person, firm or corporation to refrain from

bidding.

Page 12: ADDENDUM #3 TO CONTRACT DOCUMENTS FOR: …operations-webapps.missouri.edu/pdc/adsite/projects/cp181001/add… · Page 1 of 4 August 02, 2018 ADDENDUM #3 TO CONTRACT DOCUMENTS FOR:

MU Project #CP181001 1.A - 5 Addendum 3

d. He has not sought by collusion or otherwise to obtain for himself any

advantage over any other Bidder or over Owner. e. He will not discriminate against any employee or applicant for employment

because of race, color, religion, sex or national origin in connection with performance of work.

f. By virtue of policy of the Board of Curators, and by virtue of statutory authority,

a preference will be given to materials, products, supplies, provisions and all other articles produced, manufactured, mined or grown within the State of Missouri. By virtue of policy of the Board of Curators, preference will also be given to all Missouri firms, corporations, or individuals, all as more fully set forth in "Information For Bidders."

END OF BIDDER’S CERTIFICATE

Page 13: ADDENDUM #3 TO CONTRACT DOCUMENTS FOR: …operations-webapps.missouri.edu/pdc/adsite/projects/cp181001/add… · Page 1 of 4 August 02, 2018 ADDENDUM #3 TO CONTRACT DOCUMENTS FOR:

MU Project #CP181001 1.A - 6 Addendum 3

9. BIDDER'S SIGNATURE

Note: All signatures shall be original; not copies, photocopies, stamped, etc.

Authorized Signature

Date

Printed Name

Title

Company Name Mailing Address City, State, Zip Phone No. Federal Employer ID No.

Fax No.

E-Mail Address

Circle one: Individual Partnership Corporation Joint Venture If a corporation, incorporated under the laws of the State of__________ Licensed to do business in the State of Missouri? ____yes _____no

(Each Bidder shall complete bid form by manually signing on the proper signature line above and supplying required information called for in connection with the signature. Information is necessary for proper preparation of the Contract, Performance Bond and Payment Bond. Each Bidder shall supply information called for in accompanying "Bidder's Statement of Qualifications.")

END OF SECTION

Page 14: ADDENDUM #3 TO CONTRACT DOCUMENTS FOR: …operations-webapps.missouri.edu/pdc/adsite/projects/cp181001/add… · Page 1 of 4 August 02, 2018 ADDENDUM #3 TO CONTRACT DOCUMENTS FOR:

MU Project #CP181001 PW - 2

SECTION 1.H

ALTERNATES Base Bid may be increased in accordance with following Additive Alternate proposal(s) as Owner may elect:

1. Additive Alternate No. 1: Remove and replace building expansion joint system per the plans and specifications.

2. Additive Alternate No. 2: Provide a 40 year warranty in lieu of the specified 30 year warranty as specified within the base bid.

END OF SECTION

Page 15: ADDENDUM #3 TO CONTRACT DOCUMENTS FOR: …operations-webapps.missouri.edu/pdc/adsite/projects/cp181001/add… · Page 1 of 4 August 02, 2018 ADDENDUM #3 TO CONTRACT DOCUMENTS FOR:

07550-1

SECTION 07550

MODIFIED BITUMINOUS MEMBRANE ROOFING

University of Missouri Health System CCA Roof Specification

Copyright 2018 ARCAT, Inc. - All rights reserved

PART 1 GENERAL

1.1 SECTION INCLUDES

A. Cold Applied 2-Ply Solvent Free Asphalt Roofing

B. Accessories, including roof insulation, cover board, walkway pads, sheet metal and manufactured roof specialties.

C. Edge Treatment and Roof Penetration Flashings.

1.2 REFERENCES

A. ASTM D 41 - Standard Specification for Asphalt Primer Used in Roofing, Dampproofing, and Waterproofing.

B. ASTM D 312 - Standard Specification for Asphalt used in Roofing.

C. ASTM D 451 - Standard Test Method for Sieve Analysis of Granular Mineral Surfacing for Asphalt Roofing Products.

D. ASTM D 1079 Standard Terminology Relating to Roofing, Waterproofing and Bituminous Materials.

E. ASTM D 1863 Standard Specification for Mineral Aggregate Used as a Protective Coating for Roofing.

F. ASTM D 2824 Standard Specification for Aluminum-Pigmented Asphalt Roof Coating.

G. ASTM D 4586 Standard Specification for Asphalt Roof Cement, Asbestos-Free.

H. ASTM D 4601 Standard Specification for Asphalt Coated Glass Fiber Base Sheet Used in Roofing.

I. ASTM D 5147 Standard Test Method for Sampling and Testing Modified Bituminous Sheet Materials.

J. ASTM D 6162 Standard Specification for Styrene Butadiene Styrene (SBS) Modified Bituminous Sheet Materials Using a Combination of Polyester and Glass Fiber Reinforcements.

K. ASTM D 6163 Standard Specification for Styrene Butadiene Styrene (SBS) Modified Bituminous Sheet Materials Using Glass Fiber Reinforcements.

L. ASTM D 6164 - Standard Specification for Styrene Butadiene Styrene (SBS) Modified Bituminous Sheet Materials Using Polyester Reinforcements.

M. ASTM E 108 - Standard Test Methods for Fire Test of Roof Coverings

Page 16: ADDENDUM #3 TO CONTRACT DOCUMENTS FOR: …operations-webapps.missouri.edu/pdc/adsite/projects/cp181001/add… · Page 1 of 4 August 02, 2018 ADDENDUM #3 TO CONTRACT DOCUMENTS FOR:

07550-2

N. Factory Mutual Research (FM): Roof Assembly Classifications.

O. National Roofing Contractors Association (NRCA): Roofing and Waterproofing Manual.

P. Sheet Metal and Air Conditioning Contractors National Association, Inc. (SMACNA) - Architectural Sheet Metal Manual.

Q. Underwriters Laboratories, Inc. (UL): Fire Hazard Classifications.

R. Warnock Hersey (WH): Fire Hazard Classifications.

S. ANSI-SPRI ES-1 Wind Design Standard for Edge Systems used with Low Slope Roofing Systems.

T. ASCE 7, Minimum Design Loads for Buildings and Other Structures

U. UL - Fire Resistance Directory.

V. FM Approvals - Roof Coverings and/or RoofNav assembly database.

1.3 SUBMITTALS

A. Submit under provisions of Section 1.E- Special Conditions.

B. Product Data: Manufacturer's data sheets on each product to be used, including: 1. Preparation instructions and recommendations. 2. Storage and handling requirements and recommendations. 3. Installation instructions.

C. Shop Drawings: Submit shop drawings including installation details of roofing, flashing, fastening, insulation and vapor barrier, including notation of roof slopes and fastening patterns of insulation and base modified bitumen membrane, prior to job start.

D. Design Pressure Calculations: Submit design pressure calculations for the roof area in accordance with ASCE 7 and local Building Code requirements. Include a roof system attachment analysis report, certifying the system's compliance with applicable wind load requirements before Work begins. Report shall be signed and sealed by a Professional Engineer registered in the State of the Project who has provided roof system attachment analysis for not less than 5 consecutive years.

E. Recycled or Bio-Based Materials: Provide third party certification through UL Environment of roof System membranes containing recycled or bio based materials.

F. Verification Samples: For each modified bituminous membrane ply product specified, two samples, minimum size 6 inches (150 mm) square, representing actual product, color, and patterns.

G. Manufacturer's Certificates: Provide to certify products meet or exceed specified requirements.

H. Test Reports: Submit test reports, prepared by an independent testing agency, for all modified bituminous sheet roofing, indicating compliance with ASTM D5147.

I. Manufacturer's Fire Compliance Certificate: Certify that the roof system furnished is approved by Factory Mutual (FM), Underwritters Laboratories (UL), Warnock Hersey (WH) or approved third party testing facility in accordance with ASTM E108, Class A for external fire and meets local or nationally recognized building codes.

Page 17: ADDENDUM #3 TO CONTRACT DOCUMENTS FOR: …operations-webapps.missouri.edu/pdc/adsite/projects/cp181001/add… · Page 1 of 4 August 02, 2018 ADDENDUM #3 TO CONTRACT DOCUMENTS FOR:

07550-3

J. Closeout Submittals: Provide manufacturer's maintenance instructions that include recommendations for periodic inspection and maintenance of all completed roofing work. Provide product warranty executed by the manufacturer. Assist Owner in preparation and submittal of roof installation acceptance certification as may be necessary in connection with fire and extended coverage insurance on roofing and associated work.

1.4 QUALITY ASSURANCE

A. Perform Work in accordance with NRCA Roofing and Waterproofing Manual.

B. Manufacturer Qualifications: Company specializing in manufacturing products specified with documented ISO 9001 certification and minimum of twelve years of documented experience and must not have been in Chapter 11 bankruptcy during the last five years.

C. Installer Qualifications: Company specializing in performing Work of this section with minimum five years documented experience and a certified Pre-Approved Garland Contractor.

D. Installer's Field Supervision: Maintain a full-time Supervisor/Foreman on job site during all phases of roofing work while roofing work is in progress.

E. Product Certification: Provide manufacturer's certification that materials are manufactured in the United States and conform to requirements specified herein, are chemically and physically compatible with each other, and are suitable for inclusion within the total roof system specified herein.

F. Source Limitations: Obtain all components of roof system from a single manufacturer. Secondary products that are required shall be recommended and approved in writing by the roofing system Manufacturer. Upon request of the Architect or Owner, submit Manufacturer's written approval of secondary components in list form, signed by an authorized agent of the Manufacturer.

1.5 PRE-INSTALLATION MEETINGS

A. Convene minimum two weeks prior to commencing Work of this section.

B. Review installation procedures and coordination required with related Work.

C. Inspect and make notes of job conditions prior to installation: 1. Record minutes of the conference and provide copies to all parties present. 2. Identify all outstanding issues in writing designating the responsible party for follow-up

action and the timetable for completion. 3. Installation of roofing system shall not begin until all outstanding issues are resolved

to the satisfaction of the Architect.

1.6 DELIVERY, STORAGE, AND HANDLING

A. Deliver and store products in manufacturer's unopened packaging with labels intact until ready for installation.

B. Store all roofing materials in a dry place, on pallets or raised platforms, out of direct exposure to the elements until time of application. Store materials at least 4 inches above ground level and covered with "breathable" tarpaulins.

C. Stored in accordance with the instructions of the manufacturer prior to their application or installation. Store roll goods on end on a clean flat surface except store KEE-Stone FB 60 rolls flat on a clean flat surface. No wet or damaged materials will be used in the application.

Page 18: ADDENDUM #3 TO CONTRACT DOCUMENTS FOR: …operations-webapps.missouri.edu/pdc/adsite/projects/cp181001/add… · Page 1 of 4 August 02, 2018 ADDENDUM #3 TO CONTRACT DOCUMENTS FOR:

07550-4

D. Store at room temperature wherever possible, until immediately prior to installing the roll. During winter, store materials in a heated location with a 50 degree F (10 degree C) minimum temperature, removed only as needed for immediate use. Keep materials away from open flame or welding sparks.

E. Avoid stockpiling of materials on roofs without first obtaining acceptance from the Architect/Engineer.

F. Adhesive storage shall be between the range of above 50 degree F (10 degree C) and below 80 degree F (27 degree C). Area of storage shall be constructed for flammable storage.

1.7 COORDINATION

A. Coordinate Work with installing associated metal flashings as work of this section proceeds.

1.8 PROJECT CONDITIONS

A. Maintain environmental conditions (temperature, humidity, and ventilation) within limits recommended by manufacturer for optimum results. Do not install products under environmental conditions outside manufacturer's absolute limits.

1.9 WARRANTY

A. Upon completion of the work, provide the Manufacturer's written and signed NDL Warranty, warranting that, if a leak develops in the roof during the term of this warranty, due either to defective material or defective workmanship by the installing contractor, the manufacturer shall provide the Owner, at the Manufacturer's expense, with the labor and material necessary to return the defective area to a watertight condition. 1. Warranty Period:

1. 30 years from date of acceptance. 2. Alternate 2: 40 years from the date of acceptance

a. The 40 year warranty must be a standard warranty issued by the manufacturer and include any provisions required by the Manufacturer to meet the 40 year warranty term such as materials, inspections and installation requirements.

B. Installer is to guarantee all work against defects in materials and workmanship for a period indicated following final acceptance of the Work. 1. Warranty Period:

1. 3 years from date of acceptance. Refer to University of Missouri Contractors Roofing/Flashing/Sheet Metal Guarantee form included in this manual.

Page 19: ADDENDUM #3 TO CONTRACT DOCUMENTS FOR: …operations-webapps.missouri.edu/pdc/adsite/projects/cp181001/add… · Page 1 of 4 August 02, 2018 ADDENDUM #3 TO CONTRACT DOCUMENTS FOR:

07550-5

PART 2 PRODUCTS

2.1 MANUFACTURERS

A. Subject to the Provisions of the specification, Basis of Design: Garland Company, Inc. (The); 3800 E. 91st St., Cleveland, OH 44105. ASD. Toll Free: 800-321-9336. Phone: 216-641-7500. Fax: 216-641-0633. Web Site: www.garlandco.com.

B. Approved Equals (Subject to the Provisions of the Specification): 1. Ecology Roof Systems 2. Tremco Roofing & Building Maintenance:

a. 3735 Green Road, Beachwood, Ohio 44122. Toll Free: 800-562-2728. Web Site: www.tremcoroofing.com. b . Products to be included: (1) Base Sheet and Flashing Base: POWERply Heavy Duty Base Sheet (2) Cap Sheet and Flashing Cap: POWERply Premium FR Cap Sheet (3) Membrane Adhesive: POWERply Endure BIO Adhesive (4) Insulation Adhesive: POWERply Endure BIO Adhesive (5) Tapered Insulation: Trisotech Insulation (6) Coverboard: Tremco GP Gypsum Dens-Deck (7) Aluminum Coating: Alumanation 301

C. The Products specified are intended and the Standard of Quality for the products required for this project. If other products are proposed the bidder must disclose in the bid the manufacturer and the products that they intend to use on the Project. If no manufacturer and products are listed, the bid may be accepted only with the use of products specified. 1. Project Management All on site project management duties by the roof system

manufacturer must be completed by an actual employee of the manufacturer and may not be subcontracted to an outside source. For example: consultants, product representatives, dealers, etc. are not acceptable. The manufacturer’s project manager must complete the following duties: 1. Conduct an additional preconstruction meeting with the owner, architect, roofing

contractor, sheet metal contractor in order to layout all expectations and requirements of the project. This shall be completed by the roofing manufacturer at least two weeks prior to start of the project. Provide 3 onsite inspections per week during construction to insure proper application of the roof system by the roofing contractor. Utilize the inspection form located at the end of this section of the specification which is to be filled out and emailed to the management and architects after each inspection.

2. Take photographic record of all conditions as related to the work during the three weekly inspections and include them with the Manufacturer’s Inspection Form..

3. Perform a final walk of all roof areas prior to installation of the aluminum coated surfacing.

4. The inspections are to continue throughout the duration of the construction progress including the sheet metal installation.

5. Perform a final inspection of all roof surfaces including low slope, copings & counter-flashings once the project is 100% complete by the roofing contractor.

6. Create a separate punch list for the owner / architect on all roofing / metal related issues that need to be corrected in order to complete the project.

7. Provide a final letter of completion to the owner / architect upon completion of the project. The letter must clearly explain that all of the work was conducted according to the manufacturer’s warranty requirements

8. The new roof systems as related to the 2018 roof replacement shall be inspected twice per year by the roof system manufacturer throughout the entire length of the warranty. The inspections will be followed by a Report to the

Page 20: ADDENDUM #3 TO CONTRACT DOCUMENTS FOR: …operations-webapps.missouri.edu/pdc/adsite/projects/cp181001/add… · Page 1 of 4 August 02, 2018 ADDENDUM #3 TO CONTRACT DOCUMENTS FOR:

07550-6

Facility Manager as to the condition of the roof and any recommendations as to maintenance. The inspections are to be performed at no charge to the owner.

Manufacturer’s Inspection Compliance Form

For compliance with the specification this form is to be completed and emailed daily with each inspection

which is required three days per week during construction. This must be filled out by a full-time employee

of the Manufacturer issuing the warranty and cannot be delegated or subcontracted to an independent

party due to the nature of the warranty and complexity of the project.

Manufacturer:

Manufacturer’s Employees Name:

Inspection Date:

Inspection Time:

Weather Conditions:

Contractor:

Crew Foreman:

Crew Size:

Roof Section that is being completed:

Amount of Tear-off:

Work being completed:

Condition of roof deck:

Condition of walls if flashing work is being completed:

Condition of material being used:

Note any issues arising on this date:

Note any complaints from the Hospital Staff on this date:

Note any quality issues with the installation:

Provide photographic evidence of any issues, questions and progress with this form. Submit this form

along with the appropriate photographs three times per week during construction. This form is to be

submitted to the Hospital, Campus and Consultants as directed by Campus Staff.

Manufacturer’s Employee’s Signature ________________________________

Page 21: ADDENDUM #3 TO CONTRACT DOCUMENTS FOR: …operations-webapps.missouri.edu/pdc/adsite/projects/cp181001/add… · Page 1 of 4 August 02, 2018 ADDENDUM #3 TO CONTRACT DOCUMENTS FOR:

07550-7

2.2 COLD APPLIED 2-PLY SOLVENT FREE ASPHALT ROOFING -

A. Base (Ply) Sheet: 1. 120 mil SBS (Styrene-Butadiene-Styrene) rubber modified roofing base sheet with

dual fiberglass reinforced scrim, performance requirements according to ASTM D 5147. 1. Tensile Strength, ASTM D 5147

1) 2 in/min. @ 0 +/- 3.6 deg. F MD 100 lbf/in XD 100 lbf/in 2. Tear Strength, ASTM D 5147

1) 2 in/min. @ 73.4 +/- 3.6 deg. F MD 100 lbf XD 85 lbf 3. Elongation at Maximum Tensile, ASTM D 5147

1) 2 in/min. @ 0 +/- 3.6 deg. F MD 4 % XD 4 % 4. Low Temperature Flexibility, ASTM D 5147, Passes -40 deg. F (-40 deg. C)

B. Modified Cap (Ply) Sheet: 1. 155 mil SBS (Styrene-Butadiene-Styrene) mineral surfaced, rubber modified

roofing membrane reinforced with a fiberglass and polyester composite scrim. ASTM D 6162, Type III Grade G 1) Tensile Strength, ASTM D 5147

a) 2 in/min. @ 73.4 +/- 3.6 deg. F MD 300 lbf/in XD 310 lbf/in b) 50 mm/min. @ 23 +/- 2 deg. C MD 54.25 kN/m XD 54.25 kN/m

2) Tear Strength, ASTM D 5147 a) 2 in/min. @ 73.4 +/- 3.6 deg. F MD 350 lbf XD 500 lbf b) 50 mm/min. @ 23 +/- 2 deg. C MD 2224 N XD 2224 N

3) Elongation at Maximum Tensile, ASTM D 5147 a) 2 in/min. @ 73.4 +/- 3.6 deg. F MD 8% XD 8% b) 50 mm/min. @ 23 +/- 2 deg. C MD 8% XD 8%

4) Low Temperature Flexibility, ASTM D 5147, Passes -30 deg. F (-34 deg. C)

C. Interply Adhesive: 1. Cold applied solvent free membrane adhesive: Low V.O.C. compliant performance

requirements (up to 5g/l VOC): 1. Non-Volatile Content ASTM D 4586 2. Density ASTM D 1475 11.4 lbs./gal. (1.36 g/m3) 3. Viscosity Brookfield 20,000-50,000 cPs. 4. Flash Point ASTM D 93 400 deg. F min. (232 deg. C) 5. Slope: up to 3:12

D. Flashing Base Ply: 1. 80 mil SBS (Styrene-Butadiene-Styrene) rubber modified roofing base sheet

reinforced with a fiberglass scrim, performance requirements according to ASTM D 5147. 1. Tensile Strength, ASTM D 5147

1) 2 in/min. @ 0 +/- 3.6 deg. F MD 100 lbf/in XD 100 lbf/in 2) 50 mm/min. @ -17.78 +/- 2 deg. C MD 17.5 kN/m XD 17.5 kN/m

2. Tear Strength, ASTM D 5147 1) 2 in/min. @ 73.4 +/- 3.6 deg. F MD 110 lbf XD 100 lbf 2) 50 mm/min. @ 23 +/- 2 deg. C MD 489 N XD 444 N

3. Elongation at Maximum Tensile, ASTM D 5147 1) 2 in/min. @ 0 +/- 3.6 deg. F MD 4 % XD 4 % 2) 50 mm/min. @ -17.78 +/- 2 deg. C MD 4 % XD 4 %

4. Low Temperature Flexibility, ASTM D 5147

Page 22: ADDENDUM #3 TO CONTRACT DOCUMENTS FOR: …operations-webapps.missouri.edu/pdc/adsite/projects/cp181001/add… · Page 1 of 4 August 02, 2018 ADDENDUM #3 TO CONTRACT DOCUMENTS FOR:

07550-8

1) Passes -40 deg. F (-40 deg. C)

E. Flashing Ply Adhesive: 1. Flashing Adhesive: Cold applied solvent free flashing adhesive: Low V.O.C. compliant

performance requirements (up to 5g/l VOC): 1. Non-Volatile Content ASTM D 4586 2. Density ASTM D 1475 11.8 lbs./gal. (1.17 g/m3) 3. Viscosity Brookfield 400,000 cPs. 4. Flash Point ASTM D 93 400 deg. F min. (232 deg. C)

2. Flashing Cap (Ply) Sheet: 1. 155 mil SBS and SIS (Styrene-Butadiene-Styrene and Styrene-Isoprene-

Styrene) rubber modified membrane incorporating post-consumer recycled rubber and reinforced with a fiberglass and polyester composite scrim. Surfaced with the highly reflective Sunburst white mineral. ASTM D 6162, Type III Grade G. 1) Tensile Strength, ASTM D 5147

a) 2 in/min. @ 73.4 +/- 3.6 deg. F MD 300f/in XD 310 lbf/in b) 50 mm/min. @ 23 +/- 2 deg. C MD 175 kN/m XD 192.5 kN/m

2) Tear Strength,, ASTM D 5147 a) 2 in/min. @ 73.4 +/- 3.6 deg. F MD 350 lbf XD 500 lbf b) 50 mm/min. @ 23 +/- 2 deg. C MD 6,672.3 N XD 7,561.6 N

3) Elongation at Maximum Tensile, ASTM D 5147 a) 2 in/min. @ 73.4 +/- 3.6 deg. F MD 16.0% XD 16.0% b) 50 mm/min. @ 23 +/- 2 deg. C MD 16.0% XD 16.0%

4) Low Temperature Flexibility, ASTM D 5147, Passes -40 deg. F (-40 deg. C)

5) Reflectivity, ASTM C 1549: 73% 3. Surface Coatings:

1. Surfacing: 1) ASTM D 2824 aluminum coating non-fibered aluminum roof coating non-

fibered aluminum roof coating having the following characteristics: a) Flash Point 103 deg. F (39 deg. C) min. b) Weight/Gallon 7.9 lbs./gal. (1.0 g/cm3) c) SRI-77 d) The field and flashings are to be coated with 2 coats applied

cross-directionally.

2.3 ACCESSORIES:

A. Roof Insulation: 1/4” tapered polyisocyanurate insulation with an average R-Value of 22 with a minimum thickness of 2 inches. All layers set in insulation Adhesive per the wind uplift calculations. The successful contractor is to provide an engineered tapered drawing approved by the owner and manufacturer’s rep.

B. Roof Cover Board Insulation: 1/2” Secur-Rock set in manufacturer’s insulation adhesive.

C. Nails and Fasteners: Non-ferrous metal or galvanized steel, except that hard copper nails shall be used with copper; aluminum or stainless steel nails shall be used with aluminum; and stainless steel nails shall be used with stainless steel, Fasteners shall be self-clinching type of penetrating type as recommended by the deck manufacturer. Fasten nails and fasteners flush-driven through flat metal discs not less than 1 inch (25 mm) diameter. Omit metal discs when one-piece composite nails or fasteners with heads not less than 1 inch (25 mm) diameter are used.

D. Walkway Pads - Commercial Innovations Walkway Pads: As recommended and furnished by the membrane manufacturer set in approved adhesive to control foot traffic on roof top

Page 23: ADDENDUM #3 TO CONTRACT DOCUMENTS FOR: …operations-webapps.missouri.edu/pdc/adsite/projects/cp181001/add… · Page 1 of 4 August 02, 2018 ADDENDUM #3 TO CONTRACT DOCUMENTS FOR:

07550-9

surface and provide a durable system compliant non-slip walkway. Installed at doorways and the bases & tops of ladders.

E. Urethane Sealant Hybrid – Green Lock Sealant: One part, non-sag sealant as approved and furnished by the membrane manufacturer for moving joints. 1. Tensile Strength, ASTM D 412: 250 psi 2. Elongation, ASTM D 412: 450% 3. Hardness, Shore A ASTM C 920: 35 4. Adhesion-in-Peel, ASTM C 92: 30 pli

F. Pitch Pocket Sealer - Seal-Tite: Two part, 100% solids, self-leveling, polyurethane sealant for filling pitch pans as recommended and furnished by the membrane manufacturer. 1. Durometer, ASTM D 2240: 40-50 Shore 2. Elongation, ASTM D 412: 250% 3. Tensile Strength, ASTM D 412: 200 @ 100 mil

G. Glass Fiber Cant - Glass Cant: Continuous triangular cross Section made of inorganic fibrous glass used as a cant strip as recommended and furnished by the membrane manufacturer.

H. Pitch pans, Rain Collar 24 gauge stainless or 20oz (567gram) copper. All joints should be welded/soldered watertight. See details for design.

I. Drain Flashings should be 4lb (1.8kg) sheet lead formed and rolled.

J. Plumbing stacks should be 4lb (1.8kg) sheet lead formed and rolled.

K. Liquid Flashing - Tuff-Flash: An asphaltic-polyurethane, low odor, liquid flashing material designed for specialized details unable to be waterproofed with typical modified membrane flashings. 1. Tensile Strength, ASTM D 412: 400 psi 2. Elongation, ASTM D 412: 300% 3. Density @77 deg. F 8.5 lb/gal typical

L. Fabricated Flashings: 1. Fabricated flashings and trim shall conform to the detail requirements of SMACNA

"Architectural Sheet Metal Manual" and/or the CDA Copper Development Association "Copper in Architecture - Handbook" as applicable.

M. Manufactured Roof Specialties: Shop fabricated copings, fascia, gravel stops, control joints, expansion joints, joint covers and related flashings and trim. 1. Manufactured roof specialties shall conform to the detail requirements of SMACNA

"Architectural Sheet Metal Manual" and/or the NRCA "Roofing and Waterproofing Manual" as applicable.

N. Wall Expansion Joints: 1. All joints shall be designed to meet the specified performance criteria of the SEISMIC

COLORSEAL product as manufactured by: (USA & International) EMSEAL JOINT SYSTEMS, LTD 25 Bridle Lane, Westborough, MA 01581-2603, Toll Free: 800-526-8365.

(Canada) EMSEAL, LLC 120 Carrier Drive, Toronto, Ontario, Canada M9W 5R1 Toll Free: 800-526-8365. www.emseal.com

2. Substitutions from alternate manufacturers must meet the following requirements: 1) All products must be certified by independent laboratory test report to

exceed the requirements of curtain wall performance tests ASTM E330, E283-04, and E331. Product must meet or exceed hurricane-force wind

Page 24: ADDENDUM #3 TO CONTRACT DOCUMENTS FOR: …operations-webapps.missouri.edu/pdc/adsite/projects/cp181001/add… · Page 1 of 4 August 02, 2018 ADDENDUM #3 TO CONTRACT DOCUMENTS FOR:

07550-10

loading with no deflection at both positive and negative pressures up to 4954 Pascals—equal to 200 mph winds (ASTM E330-02-procedure A).

2) All products must be certified by independent laboratory test report to ASTM E90-09 and to meet or exceed an STC 52 in STC 56 wall and OITC 38 rating in an OITC 38 wall.

3) All products must be certified by independent laboratory test report to be free in composition of any waxes or wax compounds using FTIR and DSC testing.

4) All products shall be certified in writing to be: a) capable of withstanding 150°F (65°C) for 3 hours while compressed down to the minimum of movement capability dimension of the basis of design product (-50% of nominal material size) without evidence of any bleeding of impregnation medium from the material; and b) that the same material after the heat stability test and after first being cooled to room temperature will subsequently self-expand to the maximum of movement capability dimension of the basis-of-design product (+50% of nominal material size) within 24 hours at room temperature 68°F (20°C).

5) Quality and Environmental control: Manufacturer shall be certified to both ISO-9001:2015 (quality management) and ISO-14001:2015 (environmental management), and shall provide written confirmation that formal Quality and Environmental management systems and processes have been adopted.

3. Provide watertight, energy-efficient exterior joints in vertical-plane walls (above-grade).

4. Material shall be capable of movements of +50%, -50% (100% total) of nominal material size.

5. Color to be standard “Light Gray”. Confirm color with owner prior to installation. 6. Install and seal per manufacturer installation instructions.

PART 3 EXECUTION

3.1 EXAMINATION

A. Do not begin installation until substrates have been properly prepared.

B. Inspect and approve the deck condition, slopes and fastener backing if applicable, parapet walls, expansion joints, roof drains, stack vents, vent outlets, nailers and surfaces and elements.

C. Verify that work penetrating the roof deck, or which may otherwise affect the roofing, has been properly completed.

D. If substrate preparation and other conditions are the responsibility of another installer, notify Architect of unsatisfactory preparation before proceeding.

3.2 PREPARATION

A. General: Clean surfaces thoroughly prior to installation. 1. Prepare surfaces using the methods recommended by the manufacturer for achieving

the best result for the substrate under the project conditions. 2. Fill substrate surface voids that are greater than 1/4 inch wide with an acceptable fill

material. 3. Roof surface to receive roofing system shall be smooth, clean, free from loose gravel,

dirt and debris, dry and structurally sound. 4. Wherever necessary, all surfaces to receive roofing materials shall be power broom

and vacuumed to remove debris and loose matter prior to starting work. 5. Do not apply roofing during inclement weather. Do not apply roofing membrane to

Page 25: ADDENDUM #3 TO CONTRACT DOCUMENTS FOR: …operations-webapps.missouri.edu/pdc/adsite/projects/cp181001/add… · Page 1 of 4 August 02, 2018 ADDENDUM #3 TO CONTRACT DOCUMENTS FOR:

07550-11

damp, frozen, dirty, or dusty surfaces. 6. Fasteners and plates for fastening components mechanically to the substrate shall

provide a minimum pull-out capacity of 300 lbs. (136 k) per fastener. Base or ply sheets attached with cap nails require a minimum pullout capacity of 40 lb. per nail.

7. Prime decks where required, in accordance with requirements and recommendations of the primer and deck manufacturer.

B. Precast concrete: 1. Decks shall be clean, dry, fully cured and free of flaws and attached securely to the

supporting structure as recommended by the deck manufacturer. 2. All joints shall be caulked or grouted. 3. Concrete surfaces to receive roofing shall be fully primed at the rate of 1 gallon per

100 sq. ft. 4. When applying roofing or insulation directly to the deck with asphalt, prime with

asphalt/concrete primer, ASTM D41, at a rate of 1 gal/square (.4 L/m2) and allow the primer to dry prior to the application of the roofing system. Hold back bitumen at the joints approximately 4 inches (102 mm) to prevent bitumen drippage.

5. Deck joints shall be stripped in with a 12 inch (305 mm) wide strip of modified membrane unadhered a minimum of 2 inches (51 mm) immediately on either side of the joint.

C. Re-Roofing Applications: 1. Remove existing roofing from curbs and parapet walls down to the surface of the

concrete roof deck. Remove existing flashings at roof drains and roof penetrations. 2. Remove all wet, deteriorated, blistered or delaminated roofing membrane or insulation

and fill in any low spots occurring as a result of removal work to create a smooth, even surface for application of new roof membranes.

3. Install new wood nailers as necessary to accommodate insulation/recovery board or new nailing patterns.

3.3 INSTALLATION - GENERAL

A. Install modified bitumen membranes and flashings in accordance with manufacturer's instructions and with the recommendations provided by the National Roofing Contractors Association's Roofing & Waterproofing Manual, the Asphalt Roofing Manufacturers Association, and applicable codes.

B. General: Avoid installation of modified bitumen membranes at temperatures lower than 40-45 degrees F. When work at such temperatures unavoidable use the following precautions: 1. Take extra care during cold weather installation and when ambient temperatures are

affected by wind or humidity, to ensure adequate bonding is achieved between the surfaces to be joined. Use extra care at material seam welds and where adhesion of the applied product to the appropriately prepared substrate as the substrate can be affected by such temperature constraints as well.

2. Unrolling of cold materials, under low ambient conditions must be avoided to prevent the likelihood of unnecessary stress cracking. Rolls must be at least 40 degrees F at the time of application. If the membrane roll becomes stiff or difficult to install, it must be replaced with roll from a heated storage area.

C. Commence installation of the roofing system at the lowest point of the roof (or roof area), working up the slope toward the highest point. Lap sheets shingle fashion so as to constantly shed water

D. All slopes greater than 2:12 require back-nailing to prevent slippage of the ply sheets. Use ring or spiral-shank 1 inch cap nails, or screws and plates at a rate of 1 fastener per ply (including the membrane) at each insulation stop. Place insulation stops at 16 ft o.c. for slopes less than 3:12 and 4 feet o.c. for slopes greater than 3:12. On non-insulated

Page 26: ADDENDUM #3 TO CONTRACT DOCUMENTS FOR: …operations-webapps.missouri.edu/pdc/adsite/projects/cp181001/add… · Page 1 of 4 August 02, 2018 ADDENDUM #3 TO CONTRACT DOCUMENTS FOR:

07550-12

systems, nail each ply directly into the deck at the rate specified above. When slope exceeds 2:12, install all plies parallel to the slope (strapping) to facilitate backnailing. Install 4 additional fasteners at the upper edge of the membrane when strapping the plies.

3.4 INSTALLATION COLD APPLIED ROOF SYSTEM

A. Base Ply: Cut base ply sheets into 18 foot lengths and allow plies to relax before installing. Install base sheet in Interply Adhesive: applied at the rate required by the manufacturer. Shingle base sheets uniformly to achieve one ply throughout over the prepared substrate. Shingle in proper direction to shed water on each large area of roofing. 1. Lap ply sheet ends 8 inches. Stagger end laps 12 inches minimum. 2. Solidly bond to the substrate and adjacent ply with specified cold adhesive at the rate

of 2 to 2-1/2 gallons per 100 square feet. 3. Roll must push a puddle of adhesive in front of it with adhesive slightly visible at all

side laps. Use care to eliminate air entrapment under the membrane. 4. Install subsequent rolls of modified across the roof as above with a minimum of 4 inch

side laps and 8 inch staggered end laps. Lay modified membrane in the same direction as the underlayers but the laps shall not coincide with the laps of the base layers.

5. Extend plies 2 inches beyond top edges of cants at wall and projection bases. 6. Install base flashing ply to all perimeter and projection details. 7. Allow the one ply of base sheet to cure at least 30 minutes before installing the

modified membrane. However, the modified membrane must be installed the same day as the base plies.

B. Modified Cap Ply(s): Cut cap ply sheets into 18 foot lengths and allow plies to relax before installing. Install in interplay adhesive applied at the rate required by the manufacturer. Shingle sheets uniformly over the prepared substrate to achieve the number of plys specified. Shingle in proper direction to shed water on each large area of roofing. 1. Lap ply sheet ends 8 inches. Stagger end laps 12 inches minimum. 2. Solidly bond to the base layers with specified cold adhesive at the rate of 2 to 2-1/2

gallons per 100 square feet. 3. Roll must push a puddle of adhesive in front of it with adhesive slightly visible at all

side laps. Care should be taken to eliminate air entrapment under the membrane. 4. Install subsequent rolls of modified across the roof as above with a minimum of 4 inch

side laps and 8 inch staggered end laps. Lay modified membrane in the same direction as the underlayers but the laps shall not coincide with the laps of the base layers.

5. Allow cold adhesive to set for 5 to 10 minutes before installing the top layer of modified membrane.

6. Extend membrane 2 inches beyond top edge of all cants in full moppings of the cold adhesive as shown on the Drawings.

C. Fibrous Cant Strips: Provide non-combustible perlite or glass fiber cant strips at all wall/curb detail treatments where angle changes are greater than 45 degrees. Cant may be set in approved cold adhesives, hot asphalt or mechanically attached with approved plates and fasteners.

D. Wood Blocking, Nailers and Cant Strips: Provide wood blocking, nailers and cant strips as specified. 1. Provide nailers at all roof perimeters and penetrations for fastening membrane

flashings and sheet metal components. 2. Wood nailers should match the height of any insulation, providing a smooth and even

transition between flashing and insulation areas. 3. Nailer lengths should be spaced with a minimum 1/8 inch gap for expansion and

contraction between each length or change of direction. 4. Nailers and flashings should be fastened in accordance with Factory Mutual "Loss

Page 27: ADDENDUM #3 TO CONTRACT DOCUMENTS FOR: …operations-webapps.missouri.edu/pdc/adsite/projects/cp181001/add… · Page 1 of 4 August 02, 2018 ADDENDUM #3 TO CONTRACT DOCUMENTS FOR:

07550-13

Prevention Data Sheet 1- 49, Perimeter Flashing" and be designed to be capable of resisting a minimum force of 200 lbs/lineal foot in any direction.

E. Metal Work: Provide metal flashings, counter flashings, parapet coping caps and thru-wall flashings as specified. Install in accordance with the SMACNA "Architectural Sheet Metal Manual" or the NRCA Roofing Waterproofing manual.

F. Termination Bar: Provide a metal termination bar or approved top edge securement at the terminus of all flashing sheets at walls and curbs. Fasten the bar a minimum of 8 inches (203 mm) o/c to achieve constant compression. Provide suitable, sealant at the top edge if required.

G. Flashing Base Ply: Install flashing sheets by the same application method used for the base ply. 1. Seal curb, wall and parapet flashings with an application of mastic and mesh on a

daily basis. Do not permit conditions to exist that will allow moisture to enter behind, around or under the roof or flashing membrane.

2. Prepare all walls, penetrations, expansion joints and where shown on the Drawings to be flashed with required primer at the rate of 100 square feet per gallon. Allow primer to dry tack free.

3. Adhere to the underlying base ply with specified flashing ply adhesive unless otherwise specified. Nail off at a minimum of 8 inches (203 mm) o.c. from the finished roof at all vertical surfaces.

4. Solidly adhere the entire flashing ply to the substrate. Secure the tops of all flashings that are not run up and over curb through termination bar fastened at 6 inches (152 mm) O.C. and sealed at top.

5. Seal all vertical laps of flashing ply with a three-course application of trowel-grade mastic and fiberglass mesh.

6. Coordinate counter flashing, cap flashings, expansion joints and similar work with modified bitumen roofing work as specified.

7. Coordinate roof accessories, miscellaneous sheet metal accessory items, including piping vents and other devices with the roofing system work.

8. Secure the top edge of the flashing sheet using a termination bar only when the wall surface above is waterproofed, or nailed 4 inches on center and covered with an acceptable counter flashing.

H. Flashing Cap Ply: 1. Seal curb, wall and parapet flashings with an application of mastic and mesh on a

daily basis. Do not permit conditions to exist that will allow moisture to enter behind, around or under the roof or flashing membrane.

2. Prepare all walls, penetrations, expansion joints and where shown on the Drawings to be flashed with required primer at the rate of 100 square feet per gallon. Allow primer to dry tack free.

3. Adhere to the underlying base flashing ply with specified flashing ply adhesive unless otherwise specified. Nail off at a minimum of 8 inches (203 mm) o.c. from the finished roof at all vertical surfaces.

4. Coordinate counter flashing, cap flashings, expansion joints and similar work with modified bitumen roofing work as specified.

5. Coordinate roof accessories, miscellaneous sheet metal accessory items with the roofing system work.

6. All stripping shall be installed prior to flashing cap sheet installation. 7. Heat and scrape granules when welding or adhering at cut areas and seams to

granular surfaces at all flashings. 8. Secure the top edge of the flashing sheet using a termination bar only when the wall

surface above is waterproofed, or nailed 4 inches on center and covered with an acceptable counter flashing.

Page 28: ADDENDUM #3 TO CONTRACT DOCUMENTS FOR: …operations-webapps.missouri.edu/pdc/adsite/projects/cp181001/add… · Page 1 of 4 August 02, 2018 ADDENDUM #3 TO CONTRACT DOCUMENTS FOR:

07550-14

I. Surface Coatings: Apply roof coatings in strict conformance with the manufacturer's recommended procedures.

3.5 INSTALLATION EDGE TREATMENT AND ROOF PENETRATION FLASHING

A. Scupper Through Roof Edge: 1. Inspect the nailer to assure proper attachment and configuration. 2. Run base ply over the edge. Assure coverage of all wood nailers. 3. Install a scupper box in a 1/4 inch (6 mm) bed of mastic. Assure all box seams are

soldered and have a minimum 4 inch (101 mm) flange. Make sure all corners are closed and soldered. Prime scupper and allow to dry.

4. Fasten flange of scupper box to nailer every 3 inches (76mm) o.c. staggered. 5. Strip in edge with base flashing ply covering entire area in bitumen with 6 inches (152

mm) on to the field of base ply of the roof. 6. Then install thermoplastic cap field ply run over the base flashing ply in bitumen or

foam adhesive. 7. Install a second ply of thermoplastic flashing cap ply heat welded over the

thermoplastic cap ply, 9 inches (228 mm) on to the field of the roof. 8. Heat weld a cover strip over all seams.

B. Coping Cap: 1. Minimum flashing height is 8 inches (203 mm) above finished roof height. Maximum

flashing height is 24 inches (609 mm). Prime vertical wall and allow to dry. 2. Set cant in bitumen. Run all base field plies over cant a minimum of 2 inches (50 mm). 3. Install base flashing ply covering entire wall and wrapped over top of wall and down

face with 6 inches (152 mm) on to the base field ply and set in bitumen. Nail base flashing ply at 8 inches (203 mm) o.c. on the back side of the parapet wall.

4. Then install thermoplastic cap field ply run over the base flashing ply in bitumen or foam adhesive.

5. Install a second ply of thermoplastic flashing cap ply heat welded over the thermoplastic cap field ply, 9 inches (228 mm) on to the field of the roof.

6. Heat weld a cover strip over all seams. 7. Install continuous cleat and fasten at 6 inches (152 mm) o.c. to outside wall. 8. Install new metal coping cap hooked to continuous cleat. 9. Fasten inside cap 24 inches (609 mm) o.c. with approved fasteners and neoprene

washers through slotted holes, which allow for expansion and contraction.

C. Surface Mounted Counterflashing: 1. Minimum flashing height is 8 inches (203 mm) above finished roof height. Maximum

flashing height is 24 inches (609 mm). Prime vertical wall and allow to dry. 2. Set cant in bitumen. Run all base field plies over cant a minimum of 2 inches (50 mm). 3. Install base flashing ply covering wall set in bitumen with 6 inches (152 mm) on to the

base field ply and set in bitumen. 4. Then install thermoplastic cap field ply run over the base flashing ply in bitumen or

foam adhesive. 5. Install the thermoplastic flashing ply in bitumen or foam over the base flashing ply, 9

inches (228 mm) on to the field of the roof. 6. Apply butyl tape to wall behind flashing. Secure termination bar through flashing, butyl

tape and into wall. Alternatively use caulk to replace the butyl tape. 7. Secure counterflashing set on butyl tape above flashing at 8 inches (203 mm) o.c. and

caulk top of counterflashing.

D. Reglet Mounted Counterflashing: 1. Minimum flashing height is 8 inches (203 mm) above finished roof height. Maximum

flashing height is 24 inches. Prime vertical wall and allow to dry. 2. Set cant in bitumen. Run all base field plies over cant a minimum of 2 inches (50 mm). 3. Install base flashing ply covering wall set in bitumen with 6 inches (152 mm) on to the

Page 29: ADDENDUM #3 TO CONTRACT DOCUMENTS FOR: …operations-webapps.missouri.edu/pdc/adsite/projects/cp181001/add… · Page 1 of 4 August 02, 2018 ADDENDUM #3 TO CONTRACT DOCUMENTS FOR:

07550-15

base field ply and set in bitumen. 4. Then install thermoplastic cap field ply run over the base flashing ply in bitumen or

foam adhesive. 5. Install the thermoplastic flashing ply in bitumen or foam over the base flashing ply, 9

inches (228 mm) on to the field of the roof. 6. Apply butyl tape to wall behind flashing. Secure termination bar through flashing, butyl

tape and into wall. Alternatively use caulk to replace the butyl tape. 7. Cut reglet in masonry one joint above flashing. 8. Secure reglet counterflashing with expansion fasteners and caulk reglet opening.

E. Through Wall Counterflashing: 1. Minimum flashing height is 8 inches (203 mm) above finished roof height. Prime

vertical wall and allow to dry. 2. Set cant in bitumen. Run all base field plies over cant a minimum of 2 inches (50 mm). 3. Install base flashing ply covering wall set in bitumen with 6 inches (152 mm) on to the

base field ply and set in bitumen. 4. Then install thermoplastic cap field ply run over the base flashing ply in bitumen or

foam adhesive. 5. Install the thermoplastic flashing ply in bitumen or foam over the base flashing ply, 9

inches (228 mm) on to the field of the roof. 6. Apply butyl tape to wall behind flashing. Secure termination bar through flashing, butyl

tape and into wall at 8 inches (203 mm) o.c. Alternatively use caulk to replace the butyl tape.

7. Install counterflashing in through wall reglet.

F. Expansion Joint: 1. Minimum curb height is 8 inches (203 mm) above finished roof height. Chamfer top of

curb. Prime vertical curb and allow to dry. 2. Mechanically attach wood cant to expansion joint nailers. Run all base field plies over

cant a minimum of 2 inches (50 mm). 3. Install compressible insulation in neoprene cradle. 4. Install base flashing ply covering curb set in bitumen with 6 inches (152 mm) on to

field of the roof. 5. Then install thermoplastic cap field ply run over the base flashing ply in bitumen or

foam adhesive. 6. Install the thermoplastic flashing ply in bitumen or foam over the base flashing ply, 9

inches (228 mm) on to the field of the roof. 7. Install pre-manufactured expansion joint cover. Fasten sides at 12 inches (609 mm)

o.c. with fasteners and neoprene washers. Furnish all joint cover laps with butyl tape between metal covers.

G. Area Divider: 1. Minimum curb height is 8 inches (203 mm) above finished roof height. Prime vertical

curb at a rate of 100 square feet per gallon and allow to dry. 2. Set cant in bitumen. Run all base field plies over cant a minimum of 2 inches (50 mm). 3. Install base flashing ply covering wall set in bitumen with 6 inches (152 mm) on to the

base field ply and set in bitumen. 4. Then install thermoplastic cap field ply run over the base flashing ply in bitumen or

foam adhesive. 5. Install the thermoplastic flashing ply in bitumen or foam over the base flashing ply, 9

inches (228 mm) on to the field of the roof. 6. Install pre-manufactured cover. Fasten sides at 24 inches (609 mm) o.c. with

fasteners and neoprene washers through slotted holes. Furnish all joint cover laps with butyl tape between metal covers.

Page 30: ADDENDUM #3 TO CONTRACT DOCUMENTS FOR: …operations-webapps.missouri.edu/pdc/adsite/projects/cp181001/add… · Page 1 of 4 August 02, 2018 ADDENDUM #3 TO CONTRACT DOCUMENTS FOR:

07550-16

H. Curb Detail/Air Handling Station: 1. Minimum curb height is 8 inches (203 mm) above finished roof height. Prime vertical

and allow to dry. 2. Set cant in bitumen. Run all base field plies over cant a minimum of 2 inches (50 mm). 3. Install base flashing ply covering the curb set in bitumen with 6 inches (152 mm) on to

the base field ply and set in bitumen. 4. Then install thermoplastic cap field ply run over the base flashing ply in bitumen or

foam adhesive. 5. Install the thermoplastic flashing ply in bitumen or foam over the base flashing ply, 9

inches (228 mm) on to the field of the roof. 6. Install pre-manufactured counterflashing with fasteners and neoprene washers or per

manufacturer's recommendations. 7. Set equipment on neoprene pad and fasten as required by equipment manufacturer.

I. Exhaust Fan: 1. Minimum curb height is 8 inches (203 mm) above finished roof height. Prime vertical

and allow to dry. 2. Set cant in bitumen. Run all base field plies over cant a minimum of 2 inches (50 mm). 3. Install base flashing ply covering wall set in bitumen with 6 inches (152 mm) on to the

base field ply and set in bitumen. 4. Then install thermoplastic cap field ply run over the base flashing ply in bitumen or

foam adhesive. 5. Install the thermoplastic flashing ply in bitumen or foam over the base flashing ply, 9

inches (228 mm) on to the field of the roof. 6. Install metal exhaust fan over the wood nailers and flashing to act as counterflashing.

Fasten per manufacturer's recommendation.

J. Roof Drain: 1. Plug drain to prevent debris from entering plumbing. 2. Taper insulation to drain minimum of 24 inches (609 mm) from center of drain. 3. Run roof system base plies over drain. Cut out plies inside drain bowl. 4. Set lead/copper flashing (30 inch square minimum) in 1/4 inch bed of mastic. Run

lead/copper into drain a minimum of 2 inches (50 mm). Prime lead/copper and allow to dry.

5. Install base flashing ply (40 inch square minimum) in bitumen. 6. Install thermoplastic cap ply (48 inch square minimum) in bitumen or foam adhesive. 7. Install clamping ring and assure that all plies are under the clamping ring. 8. Remove drain plug and install strainer.

K. Plumbing Stack: 1. Minimum stack height is 12 inches (609 mm). 2. Run roof base ply over the entire surface of the roof. Seal the base of the stack with

elastomeric sealant. 3. Prime flange of new sleeve. Install properly sized sleeves set in 1/4 inch (6 mm) bed

of roof cement. 4. Install base flashing ply in bitumen. 5. Install thermoplastic cap ply in bitumen or foam adhesive. 6. Caulk the intersection of the membrane with elastomeric sealant. 7. Turn sleeve a minimum of 1 inch (25 mm) down inside of stack.

L. Heat Stack: 1. Minimum stack height is 12 inches (609 mm). 2. Run roof base ply over the entire surface of the roof. Seal the base of the stack with

elastomeric sealant. 3. Prime flange of new sleeve. Install properly sized sleeves set in 1/4 inch (6 mm) bed

of roof cement.

Page 31: ADDENDUM #3 TO CONTRACT DOCUMENTS FOR: …operations-webapps.missouri.edu/pdc/adsite/projects/cp181001/add… · Page 1 of 4 August 02, 2018 ADDENDUM #3 TO CONTRACT DOCUMENTS FOR:

07550-17

4. Install base flashing ply in bitumen. 5. Install thermoplastic cap ply in bitumen or foam adhesive. 6. Caulk the intersection of the membrane with elastomeric sealant. 7. Install new collar over cape. Weld collar or install stainless steel draw brand.

M. Pitch Pocket Umbrella: 1. Run all base plies up to the penetration. 2. Place the pitch pocket over the penetration and prime all flanges. 3. Strip in flange of pitch pocket with one ply of base flashing ply. Extend 6 inches (152

mm) onto field of roof. 4. Then install thermoplastic cap field ply run over the base flashing ply in bitumen or

foam adhesive. 5. Install the thermoplastic flashing ply in bitumen or foam over the base flashing ply, 9

inches (228 mm) on to the field of the roof. 6. Fill pitch pocket half full with non-shrink grout. Let this cure and top off with pourable

sealant. 7. Caulk joint between roof system and pitch pocket with elastomeric sealant. 8. Place a watershedding type bonnet over the top of the pitch pocket and clamp the top

with a drawband collar. Caulk the upper edge of the band with an elastomeric sealant. 9.

3.6 CLEANING

A. Clean-up and remove daily from the site all wrappings, empty containers, paper, loose particles and other debris resulting from these operations.

B. Remove asphalt markings from finished surfaces.

C. Repair or replace defaced or disfigured finishes caused by Work of this section.

3.7 PROTECTION

A. Provide traffic ways, erect barriers, fences, guards, rails, enclosures, chutes and the like to protect personnel, roofs and structures, vehicles and utilities.

B. Protect exposed surfaces of finished walls with tarps to prevent damage.

C. Plywood for traffic ways required for material movement over existing roofs shall be not less than 5/8 inch (16 mm) thick.

D. In addition to the plywood listed above, an underlayment of minimum 1/2 inch (13 mm) recover board is required on new roofing.

E. Special permission shall be obtained from the Manufacturer before any traffic shall be permitted over new roofing.

3.8 FIELD QUALITY CONTROL 1. Warranty shall be issued upon manufacturer's acceptance of the installation. 2. Field observations shall be performed by a Sales Representative employed full-time

by the manufacturer and whose primary job description is to assist, inspect and approve membrane installations for the manufacturer.

3. Provide observation reports from the Sales Representative indicating procedures followed, weather conditions and any discrepancies found during inspection.

4. Provide a final report from the Sales Representative, certifying that the roofing system has been satisfactorily installed according to the project specifications, approved details and good general roofing practice.

Page 32: ADDENDUM #3 TO CONTRACT DOCUMENTS FOR: …operations-webapps.missouri.edu/pdc/adsite/projects/cp181001/add… · Page 1 of 4 August 02, 2018 ADDENDUM #3 TO CONTRACT DOCUMENTS FOR:

07550-18

END OF SECTION

Page 33: ADDENDUM #3 TO CONTRACT DOCUMENTS FOR: …operations-webapps.missouri.edu/pdc/adsite/projects/cp181001/add… · Page 1 of 4 August 02, 2018 ADDENDUM #3 TO CONTRACT DOCUMENTS FOR:

CRITICAL CARE ADDITION ROOF REPLACEMENTCP181001EXPANSION JOINT DETAILS08/02/18

stornellom
Text Box
REMOVE AND REPLACE ALL EXISTING EXPANSION JOINT MATERIAL THAT IS RELATED TO THE ROOF SECTIONS WITHIN THE ROOFING SCOPE OF WORK
Page 34: ADDENDUM #3 TO CONTRACT DOCUMENTS FOR: …operations-webapps.missouri.edu/pdc/adsite/projects/cp181001/add… · Page 1 of 4 August 02, 2018 ADDENDUM #3 TO CONTRACT DOCUMENTS FOR:

Recommended