The WACC adjustment factor for the Gas to the West Pipeline Final report for Mutual Energy
March 2014
© Economic Insight Ltd 2014
Economic Insight EstimatingtheWACCadjustmentfactor Confidential
2
Report contents
1. Summary ......................................................................................................... 3
2. Introduction ................................................................................................... 4
3. The amount of controllable opex .................................................................. 6
3.1.TheNIAUR’sapproach 6
3.2.OurreviewoftheNIAUR’sapproach 7
3.3.Additionalanalysisregardingtheamountcontrollableopex 7
3.4.Ourconclusionsregardingtheamountofcontrollableopex 8
4. The variability of controllable opex .............................................................. 9
4.1.TheNIAUR’sapproach 10
4.2.OurreviewoftheNIAUR’sapproach 11
4.3.Additionalanalysisregardingthevariabilityofopex 13
4.4.Ourconclusionsregardingthevariabilityofcontrollableopex 20
5. Conclusion ..................................................................................................... 22
Economic Insight EstimatingtheWACCadjustmentfactor Confidential
3
1. Summary In order to compare applications for the Gas to the West Pipeline on a like-for like basis, a WACC adjustment factor must be calculated to reflect the fact that equity holders will be exposed to opex risk under revenue cap models, but not under cost pass through models.
The Northern Ireland Authority for Utility Regulation has proposed that the appropriate WACC adjustment factor is between 0.09% and 0.53%, with a medium point of 0.22%. Our analysis and evidence gathering, undertaken on behalf of Mutual Energy, suggests that the appropriate WACC adjustment factor is between 0.04% and 0.14%, with a medium point of 0.11%.
We therefore recommend that a figure of 0.11% is applied to the pre-tax WACC of those applications proposing a cost pass-through model.
Economic Insight EstimatingtheWACCadjustmentfactor Confidential
4
2. Introduction TheNorthernIrelandExecutivehasapprovedthesubventionofupto£32.5mfortheextensionofthegasnetworktotheWest.Relatedly,theNorthernIrelandAuthorityforUtilityRegulation(NIAUR)isoverseeingtheapplicationprocessfortheawardofthelicensetoundertaketheextension(andsubsequentlytooperatethepipeline).GiventhevarietyofregulatorymodelsthatcurrentlyexistinNorthernIreland,theNIAURisproposingtoallowapplicationsonthebasisofeither:
therevenuecapmodel;or theopexcostpass‐throughmodel.
Thecomplicationthisraisesisthatapplicationsunderthedifferentmodelsarelikelytohavedifferingriskprofiles,whichmakesalike‐for‐likecomparisonoflicenseapplicationschallenging.Thekeyissueisthatapplicationsundertherevenuecapmodelwillimplicitlyinclude‘opexrisk’withintheassumedweightedaveragecostofcapital(WACC),whereasapplicationsunderthecostpass‐throughmodelwillnot(andso,allelseequal,theWACCassociatedwithanycostpassthroughmodelislikelytobelowerthanthatofarevenuecapbasedmodel).TheNIAURhasthereforeidentifiedthatitwouldbeappropriatetomakeanupwardsadjustmenttotheWACCassociatedwithanycostpass‐throughapplicationtoreflectthedifferenceinriskprofile,sothatapplicationsarecomparedonafairbasis.
Inpractice,preciselyidentifyingtheappropriateWACCadjustmentfactorischallenging.ThisisbecauseoneisultimatelyattemptingtoisolatetheequityriskwithinaWACCsolelyarisingfromopexvariance.However,theWACCcapturesawidespectrumofrisks,including:
capexrisk; volumerisk; financingrisk; regulatoryrisk; strandingrisk;and theriskassociatedwithdivergencesbetweenactualandallowedopex.
Giventheabove,appropriatemethodologiesforidentifyingopexrelatedequityriskwouldseemtodependonthebenchmarkingofkeyparametersusingcomparators.Indeed,theNIAUR’sproposedmethodologyisconsistentwiththis–andhasthreemainsteps:
» Firstly,theNIAURbenchmarksthepotentialcontrollableopexassociatedwiththeGastotheWestPipelinebyusingboth:(i)top‐downcomparatorstoidentifyratiosofopextoassetvalues(thenapplyingthoseratiostotheassetvalueoftheGastotheWestPipeline);and(ii)bottom‐upcostestimatesfromcomparators.
» Secondly,theNIAURreviewsevidenceonopexvolatilityfromthehistoricalperformanceofoperators,suchasBGEandOfgem'sanalysisintheUK.TheNIAURhasassumed10%volatilityasitsmediumcase(withanupperboundof20%andalowerboundof5%)andassumedanormaldistribution.
» Thirdly,toconverttheopexvarianceintoavarianceinequityreturns(assuminganormaldistribution),theNIAURcalculatesabetabydividingthestandarddeviationintheimpliedreturnonequity(arisingfromtheopexvariance)bythatofthemarketasawhole.TheimpliedbetaisfinallyconvertedintotheWACCadjustmentbyapplyingthegearingratio.
Economic Insight EstimatingtheWACCadjustmentfactor Confidential
5
Usingtheabovemethodology,theNIAURisproposingthatthepotentialrangefortheWACCadjustmentfactorshouldbebetween0.09%and0.53%,withamediumpointof0.22%.OnFebruary6th,theNIAURpublishedaconsultationsettingoutboththeseproposedadjustmentfactorsandthedetailsofthemethodologyithasappliedtoderivethem.1
Intheabovecontext,MutualEnergycommissionedEconomicInsighttodevelopevidenceandanalysisastowhattheappropriateWACCadjustmentshouldbe.Thisreportsetsouttheresultsofourassessmentandisstructuredaroundthethreekeymethodologicalstepsdescribedabove–namely:
evidenceregardingthebenchmarkingofcontrollableopex; evidenceregardingthevariabilityofopex;and theimplicationsofopexriskforequityreturnsandtheWACC.
Foreachofthesethreestepswesetoutboth:(i)ourviewsregardingtheNIAUR’sanalysisandtheappropriateinterpretationofthatanalysis;and(ii)ouradditionalevidenceandanalysis.
1 Gas Network Extensions in Northern Ireland: Approach to Comparing High Pressure Licence Applications. A consultation
Paper.’ NIAUR (2014).
Economic Insight EstimatingtheWACCadjustmentfactor Confidential
6
3. The amount of controllable opex InthissectionweexaminetheevidencerelatingtotheappropriateamountofcontrollableopexfortheGastotheWestPipeline.WefirstlysummarisetheNIUAR’sapproachandevidence.WethenprovideourviewsontheevidenceprovidedbytheNIAURbeforesettingoutadditionalevidenceandanalysisrelevanttodeterminingcontrollableopex.
3.1. The NIAUR’s approach
InordertoestimatethecontrollableopexassociatedwiththeGastotheWestPipeline,theNIAURusesbotha‘top‐down’and‘bottom‐up’approach.
Thetop‐downapproachisbasedoncalculatingtheratioofcontrollableopextoassetvaluesforasetofcomparators,andthenappliesthatratiototheopeningassetvalueofthepipeline.TheNIAURsuggeststhatthethreeexistinggashighpressurelicenseholdersinNorthernIrelandarethemostrelevantcomparators;andinitsconsultationdocumentreportstheirratiosofcontrollableopextoopeningassetvaluestobe:
BGE(NI):1.51%; PremierTransmission:3.05%;and BelfastGasTransmission:0.85%.
TheNIAURproposesthatBGErepresentsthebestcomparatoras,consistentwiththeGastotheWestpipeline,itismainlylocatedwithinaruralenvironment.Ontheotherhand,theNIAURnotesthatthePremierTransmissionassetissub‐seaandsoislikelytohavea“radicallydifferent”operatingcostbase.2FinallytheNIAURalsonotesthattheBelfastGasTransmissionhassub‐seaelementsandamuchhigheropeningassetvaluethantheothercomparators.Consequently,takingtheBGEratioof1.51%andapplyingittotheGastotheWestPipelineopeningassetvalueof£96.67mgivesanimpliedannualcontrollableopexfigureof£1.46mforthetop‐downmethodology.
Thebottom‐upapproachemployedbytheNIAURconsistsofexaminingthecontrollableopexofBGEfortheperiod2012‐2017.TheNIAUR’srationaleforthisisthat“wearenotawareofanyreasonwhythestructureofcostsoftheGastotheWestPipelinewouldbemateriallydifferentfromthoseofanotheronlandhighpressuregaspipelineinNI.”TheNIAURstatesthatthemajorityofBGE’scostsconsistofmaintenanceandagriculturalliaisoncostsandthat,whilsttheremightbesomeeconomiesofscale,itisreasonabletoassumethatthesearescalablewithpipelinelength.AstheGastotheWestPipelinewillbe58%ofthelengthofthecurrentBGEnetwork,theNIAURassumesthatthecontrollableopexforthenewpipelinecanbeassumedtobe58%ofthoseofBGENIforthesecostcategories.Inaddition,theNIAURassumesthat:
theGastotheWestPipelinewillalsohavesomemarginalsystemoperationcosts,whichareassumedtobe25%ofthoseforBGE;and
theremaybesomenon‐routineprojectcost(suchascompliancewithEUdirectives).Theseareassumedtoamountto£0.1monanannualisedbasis.
Consistentwiththetop‐downmethodology,theNIAUR’sbottom‐upapproachsuggeststotalannualcontrollableopexof£1.505mfortheGastotheWestPipelineasacentral
2 ‘Gas Network Extensions in Northern Ireland: Approach to Comparing High Pressure Licence Applications. A consultation
Paper.’ NIAUR (2014). Page 15.
Economic Insight EstimatingtheWACCadjustmentfactor Confidential
7
case.TheNIAURfurthersuggestsalowerboundof£1.2mandanupperboundof£1.8m,givingaspreadof+/‐20%onthebasecaseforthecontrollableopexestimate.
3.2. Our review of the NIAUR’s approach
Thetop‐downandbottom‐upapproachesemployedbytheNIAURgivealmostthesameestimatesoftheimpliedannualcontrollableopexof£1.460mand£1.505m.However,astheNIAURnotes,theGastotheWestPipelinewillnotincludeanyentry/exitpointswithotherjurisdictions,meaningthat“…itwillnotrequirecostsassociatedwithcrossborderflowswhichcanbesignificante.g.regulatoryandITcosts.”3Onthisbasis,onewouldexpectthecontrollableopexoftheGastotheWestPipelinetobelowerthan£1.5m(becausethe£1.5misbasedonBGE(NI’s)costs,inclusiveofentry/exitpoints).Therefore,weconsiderbelowwhatfurtheradjustmentscouldbemadetoreflectthis.
WeagreewiththeNIAURthatthefeaturesofPTLmeanthatitisunlikelytorepresentarobustcomparatorforthereasonssetoutintheconsultation.
3.3. Additional analysis regarding the amount controllable opex
TherearetwooptionsformakingadjustmentstothefiguresestimatedbytheNIAURinordertobetterreflecttheavailableevidence.
3.3.1. Top-down estimate
OneoptionwouldbetotaketheaverageoftheBGE(NI)andBelfastGasTransmissionfiguresof1.51%and0.85%‐thiswouldresultinafigureof1.18%,or£1.14m.ThisisonthebasisthattherearefeaturesoftheBGE(NI)comparatorthatleadtotoohighafigure,andfeaturesoftheBelfastGasTransmissionfigurethatleadtotoolowafigure,butthatthereisalittleevidencetosaywhichoneis‘moreright.’
3.3.2. Bottom-up estimate
Theotheroptionistomakefurtheradjustmentstothebottom‐upfigure.Inparticular,wenotethattheNIAURexpectsanycosts“associatedwithsystemoperationtobemarginalandproposethattheyequal25%oftheBGE(NI)allowance.”WenotethattheopeningassetvalueofBGE(NI)is£205mandtheopeningassetvalueoftheGastotheWestPipelineisexpectedtobe£64m–aratioof31%.Therefore,anassumptionof25%seemsparticularlyhigh–itisequivalenttoassumingthata100%increaseinassetvaluegivesrisetoan80%increaseinsystemoperationcosts(25%/31%)–andsoisinconsistentwiththeviewthatsystemoperationcostswillbemarginal.
Tohelparriveatamoreappropriateassumption,MutualEnergyhastoldusthatwhenittookonBGTLinadditiontoPTL,itssystemoperationcostsincreasedby10%.TheassetvaluesofBGTLandPTLareroughlythesame.Therefore,inthisinstance,a100%increaseinassetvaluewasassociatedtoa10%increaseinsystemoperationcosts,whichismoreconsistentwiththeviewthatsystemoperationcostswillbemarginal.SincetheincreaseinassetvalueinrelationtotheGastotheWestPipelineis31%,abottom‐upapproachwouldimplythatsystemsoperationscostsforthepipelinewouldbe3.1%(i.e.10%x
3 ‘Gas Network Extensions in Northern Ireland: Approach to Comparing High Pressure Licence Applications. A consultation
Paper.’ NIAUR (2014). Paragraph 4.17.
“…as the NIAUR notes, the Gas to the West Pipeline will not include any entry/exit points with other jurisdictions…On this basis, one would expect the controllable opex of the Gas to the West Pipeline to be lower than £1.5m.”
Economic Insight EstimatingtheWACCadjustmentfactor Confidential
8
31%)ofBGE(NI’s)systemoperationcosts,ratherthan25%.Alternatively,onecouldusepipelinelengthasthecostdriver,astheNIAURhasdoneinrelationtothecomponents.Thiswouldgiveafigureof5.8%(i.e.10%x58%).Giventherangeimpliedbyouradjustednumbers,weproposetoapplyaroundedfigureof5%toestimatesystemoperationcosts(whichisconservativecomparedtothefigureof3.1%basedonassetvalue).
Inaddition,wehavebeentoldbyMutualEnergythatmanyoftheothercostsincludedin“Other”–training,safetycampaign,admin,consultancy/legalservicesandsharedservices–wouldbemarginaltoo–andsoinlinetheabove,afigureof5%wouldseemtobemoreappropriate.Thisgivesarevisedfigureof£1.27masshowninthefollowingtable.
Table1Revisedbottom‐upopexamount
Component BGE(NI) % NewPipeline
Maintenance £1.744m 58% £1.012m
AgriculturalLiaisons £0.167m 58% £0.097m
SystemOperation £0.433m 5% £0.022m
Other £0.752m 5% £0.038m
NonRoutine £0.100m
Total £1.268m
Source:EconomicInsightanalysis
Wenotethattheabovefiguresincludeinsurancecosts(£0.21mincludedin“Other”)astheyarecurrentlyclassifiedas‘controllable’bytheNIAURinotherrelevantpricecontrols,suchasBGE(NI).However,theNIAURcoulddecidetoreclassifythesecostsandthiswouldfurtherreducetheproportionofcontrollablecosts.
3.4. Our conclusions regarding the amount of controllable opex
Ourrevisedtop‐downestimatefortheamountofcontrollableopexis£1.141mandourrevisedbottom‐upestimateis£1.268m.Theaverageis£1.20m.Weconsiderthatthis,whichisthesameastheNIAUR’s‘low’estimate,representsabettermidwayorcentralestimateofthecontrollableopexinvolvedintheGastotheWestPipeline.Amoreappropriatelowestimatemightbe£1.0mandahighestimatemightbe£1.4m.
Economic Insight EstimatingtheWACCadjustmentfactor Confidential
9
4. The variability of controllable opex InthefollowingweconsidertheevidenceregardingthelikelyopexvarianceriskassociatedwiththeGastotheWestPipeline.Inturnweaddress:(i)theNIAUR’sapproachtoassessingthevariance;(ii)ourviewsregardingtheNIAUR’sevidence;and(iii)furtherevidenceonopexvarianceusingadditionalcomparators.
AttheoutsetwenotethatthevariabilityanddistributionofopexarecriticalassumptionsintheNIAUR’sanalysis.Toillustratethis,thebelowshowsthe(pre‐tax)riskfactoradjustmentsusingtheNIAUR’slow,mediumandhighassumptionsforboth:(a)theamountofcontrollableopexand;(b)thevariabilityofopex.Allotherassumptionsareaspertheconsultation.
Table2Sensitivityofpre‐taxriskadjustmentfactorstoopexvariabilityassumption
Assumedcontrollableopex Low(5%) Medium(10%) High(20%)
Low£1.2m 0.09% 0.18% 0.35%
Medium£1.5m 0.11% 0.22% 0.44%
High£1.8m 0.13% 0.27% 0.53%
Source:EconomicInsightanalysis
TheredfiguresarethesameasthosepresentedinTable7oftheconsultation.Theblackfiguresshowtheriskfactoradjustmentresultingfromdifferentoperatingexpenditureamountandvariabilityassumptions.Forexample,thefigurehighlightedinboldshowsthatthe‘riskfactoradjustment’wouldbe0.11%usingthe‘low’variabilityassumption(5%),butthe‘medium’amountassumption(£1.5m).Theaboveindicatesthattheriskadjustmentfactorisprimarilydrivenbytheassumedvariabilityofopex.TofurtherdemonstratethisthefollowingtableshowsthebreakdownofthechangeintheWACCadjustmentfactorfromtheNIAUR’slowtomediumscenarios(0.09%to0.22%).Thisrevealsthat67%oftheincreaseintheadjustmentfactorbetweenthetwoscenariosisduetotheassumedincreaseinopexvariability(andonly17%duetotheincreaseintheabsoluteamountofcontrollableopex).
Economic Insight EstimatingtheWACCadjustmentfactor Confidential
10
Table3BreakdownofchangeinWACCadjustmentfromtheNIAUR’slowtomediumscenarios
ScenarioWACC
adjustmentfactor
ChangeinWACCadjustment(%
points)
%ofchangeaccountedfor
NIAURlowscenario 0.09%
+increaseinopexvariability +0.09% (66.7%)
+increaseinopexamount +0.02% (16.7%)
+combinedeffectofincreasedvarianceandamountofopex
+0.02% (16.7%)
NIAURmediumscenario 0.22%
Source:EconomicInsightanalysis
4.1. The NIAUR’s approach
Initsanalysisofthevariabilityanddistributionofopex,theNIAURpresentsthreescenarios:
thelowscenarioassumesthat9timesoutof10,opexwillbewithin+/‐5%oftheopexallowedintherelevantpricecontrols;
themediumscenarioassumesthatopexwillbewithin+/‐10%;and thehighscenarioassumesthatopexwillbewithin+/‐20%.
Furthermore,allscenariosassumethatthegapbetweenactualopexandthosethatwouldbeallowedinrelevantpricecontrolsarenormallydistributed.Thisisequivalenttoassumingthat:(a)largergapsbetweenactualandallowedopexarelesslikelytoarisethansmallergaps;and(b)apositivegapbetweenactualandallowedopexisaslikelytoariseanegativegapofthesamesize.
Toarriveatthescenariosandassumptionssetoutabove,theNIAURhasreliedonfoursourcesofevidencefromtheenergysector.
» BGE(NI).TheNIAURfoundthatBGE’sactualcontrollableoperatingexpenditurewas4.1%lowerthanitsallowancebetween2007and2012.
» PowerNI.TheNIAURstatesthatitfoundagapbetweenactualandallowedcontrollableoperatingexpenditureof10%initsworkonthePowerNIretailpricecontrol,althoughitnotesthat“…PowerNIactualcostsshowedmuchhighervariancethanwehaveevidenceforingaspipelinecostswithalotofthisbeendrivenbybaddebtissueswhichwouldnotpertaintotheGastotheWestlicence.”
» Ofgemmodellingassumptions.TheNIAURnotesthatinitsrecentworkongasandelectricitytransmissionpricecontrols,Ofgemassumedagapof+/‐10%initsfinanceabilitymodellingwork.
» Reopenerparameters.Finally,theNIAURnotesthatthepricecontrolwouldbereopenedifactualopexdeviatesfromallowancesbymorethan15%(whichtheNIAUR
Economic Insight EstimatingtheWACCadjustmentfactor Confidential
11
statesisequivalenttoavariancebetweenactualandallowedcontrollableopexof+/‐20%).
4.2. Our review of the NIAUR’s approach
OverallweagreewiththeapproachadoptedbytheNIAUR,inthesensethatthemostrobustwayofconsideringthescopeforopexvarianceregardingtheGastotheWestPipelineistoexamineevidenceonactualopexvarianceforsuitablycomparableprojectsorindustries.However,regardingthedetailoftheNIAUR’smethodology,wewouldmakethefollowingobservations:
» First,thattheassumptionof+/‐10%varianceinthecentralcaseisbaseduponOfgem’sapproachunderRIIO‐T1.However,onexaminationofOfgem’sevidence,the10%figureisitselfanassumption,ratherthanpurelyreflectingactualmarketdata.
» Second,Ofgem’sownanalysissuggeststhatcostvarianceislikelytobelowerforgastransmissionthanforelectricity,indicatingthattheappropriateinterpretationofthedatawouldbeacentralestimateoflessthan+/‐10%inanycase.
» Third,theNIAUR’sownqualitativeassessmentofthisissueindicatesthatitexpectsonlyalowlevelofopexvariabilityriskfortheGastotheWestPipeline.
» Finally,theevidencebasedonactualmarketdata(i.e.thevarianceforBGE)isconsistentwithamuchlowerlevelofvariancethan+/‐10%.
Inthefollowingwebrieflyexpanduponeachoftheaboveissuesinturn.
4.2.1. Ofgem’s 10% variance figure is an assumption
OurunderstandingisthattheNIAUR’schoiceofmidwayestimateof+/‐10%issignificantlyinfluencedbyOfgem’smodellingassumptions:“Overall,wetaketheviewthattheOfgemapproachrepresentsanappropriateestimateforvariationthatcanbeappliedinthecaseoftheGastotheWestPipeline.”4
InordertoevaluatethebasisforOfgem’sassumptionof+/‐10%,wehavereviewedtheImrecon/ECAreportreferencedintheconsultationpaperandrelevantdocumentspublishedbyOfgemaspartofRIIO‐T1.TheImrecon/ECAreportdoesnotsetoutthedatathatOfgemreliedupon,butsuggeststhata“broadjudgement”wasused:“Ofgemhasexplainedtoushowithasreachedabroadjudgementthat+/‐10percentfortotexvariabilityfairlyrepresentsplausibleupsidesanddownsides.Itisnoticeablyaroundsumamount.Inourview,reflectingourcommentonhighlevelassumptionsabove,usingaroundsumamountdoesnotinvalidatethejudgementbutitdoeshighlightthefactitisajudgement.”5
Similarly,theappendicestoOfgem’sFinalProposalsinRIIO‐T1donotcontainactualmarketdatatosupporttheassumption,butnotethat“Theseassumptionswerebasedonamixtureofhistoricalperformanceandprojectedplausiblevalues.”6Clearly,wherepossibleandcomparable,itwouldclearlybebesttobasedecisionsonactualmarketdata–andwe
4 ‘Gas Network Extensions in Northern Ireland: Approach to Comparing High Pressure Licence Applications’, NIAUR (2014),
paragraph 4.30.
5 ‘RIIO reviews – Financeability study’, Imrecon/ECA (2012), page 6.
6 ‘RIIO‐T1 Final Proposals for National Grid Electricity Transmission and National Grid Gas’, Ofgem (2012), Finance Supporting Document, Appendix 4, paragraph 1.3.
Economic Insight EstimatingtheWACCadjustmentfactor Confidential
12
providefurtherevidenceofthisbelowandinouranalysisofadditionalcomparators(seelater).
4.2.2. A review of the evidence relied upon by Ofgem indicates a lower volatility for gas than for electricity, indicating the appropriate interpretation is a mid-point for variance of less than +/-10%
Ofgem’s‘FinanceSupportingDocument’containsfurtherscenario‐basedanalyses(alsoincorporatinganumberofassumptions),whichcanbeusedtohelpinformthejudgementastothelikelyscopeforopexvariability.Inparticular,thedocumentshowsthevariabilityoftoteximpliedbyOfgem’sanalysesforelectricityandgastransmissionseparately.Notably,Ofgemconcludesthat“NGGTfaceslessriskintermsoftotexvariabilitythantheelectricitytransmissioncompanies,andsimilarrisktotheGDNs[GasDistributionNetworks].”7Figure3.2showsthattheestimatedtotexvariabilityforNGGTisaround+3%to‐5%.Althoughwearenotsuggesting(basedonthisevidencealone)that+3%to‐5%representstherightrangeinthiscase(asitreflectsanumberofassumptionsandfeaturesoftheGBregulatoryregime)wethinkthatitisimportanttheNIAURreflectstheevidencethatexpenditurevariabilityriskforgastransmissionislowerthanforelectricitytransmission.
4.2.3. The NIAUR expects a low level of opex variance
Initsconsultationdocument,theNIAURstatesthat“thebulkofthecostsmadeupbymaintenanceandagriculturalliaisonsofficersarepredictableandbasedonregulartenders.”TheNIAURfurtherstatesthat“systemoperationandregulatorymanagementcostswouldbeexpectedtoberelativelyflatandpredictable.”8Thissuggeststhat,atleastqualitatively,theNIAURexpectsthevariabilityofcontrollableoperatingexpendituretobelow.
4.2.4. Actual market data is consistent with a central estimate for opex variance of lower than +/- 10%
Inourviewitisimportanttoensurethatanybenchmarkingofopexvarianceisprimarilybasedonactual(andverifiable)marketdataonvariancethathasoccurredelsewhere.Giventhis,wethinkthattheevidencepresentedbytheNIAURregardingtheopexvarianceofBGE(NI),whichshowsvariabilityofjust4.1%,ishighlyrelevant.Asageneralprinciple,wesuggestthatmarketdatashouldcarrymoreweightthananalysisthatisprimarilyassumptionbased,suchasthe+/‐10%figurereferencedbyOfgem.
4.2.5. Summary of our review of the NIAUR’s approach
Insummary,weagreewiththeoverarchingapproachadoptedbytheNIAURregardingthedeterminationofthelikelyscopeforopexvarianceregardingtheGastotheWestPipeline.Inparticular,weconsideritsensibletoexaminedataonopexvarianceforcomparators.However,weconsiderthatthat:(i)moreweightshouldbeattachedtocomparatorsthatreflectactualmarketdata,ratherthanassumptions.Consequently,theopexvarianceforBGE(NI)isthemostrelevantdatapoint;and(ii)theappropriateinterpretationoftheOfgemanalysiscitedbytheNIAURisthatthecentralpointforopexvarianceregardinggastransmissionshould,inanycase,belessthan+/‐10%.Insummary,therefore,weconsiderthattheevidencepresentedbytheNIAURintheconsultationdocumentisitself7 ‘RIIO‐T1 Final Proposals for National Grid Electricity Transmission and National Grid Gas’, Ofgem (2012), Finance Supporting
Document, paragraph 3.37.
8 ‘Gas Network Extensions in Northern Ireland: Approach to Comparing High Pressure Licence Applications. A consultation Paper.’ NIAUR (2014). Page 16.
“We think that it is important the NIAUR reflects the evidence that expenditure variability risk for gas transmission is lower than for electricity transmission.”
Economic Insight EstimatingtheWACCadjustmentfactor Confidential
13
consistentwithanopexvarianceassumptionoflowerthan+/‐10%and,mostlikely,thattheappropriatefigurecouldbeaslowas+/‐4%(althoughinthefollowingsectionweprovideevidencefromadditionalmarketcomparatorstoexaminethisfurther).
4.3. Additional analysis regarding the variability of opex
InadditiontoreviewingtheNIAUR’sanalysisofopexvariance,wehavedevelopedfurtherevidenceofthescopeforvariability(andtheimplicationsforequityreturns)basedonawidersetofcomparators.Inparticular,wehavelookedatvariationsinactualversusallowedopexfor:
energycomparators; waterindustrycomparators;and airportandrailcomparators.
Basedonourcomparatoranalysis(whichissetoutinmoredetailintheremainderofthissection)wesuggestthattheappropriaterangeforopexvarianceisbetween3%and7%,witha‘midway’estimateof6%.Ourviewisthat,ofthecomparatorswehaveexamined,energyandwatercomparatorsarethemostappropriateforthepurposeofbenchmarkingopexvariability,astheriskprofilesofairportsandrailnetworkoperatorsarelesscloselyalignedtothoseofgastransmission.
4.3.1. Additional energy related comparators
Thissectionsetsoutouranalysisofenergysectorcomparators.Specifically,weanalyse:
» GastransmissioninGB.Inparticular,weevaluatewhattheactualmarketevidencesaysaboutthedifferencebetweenactualandallowedcontrollableoperatingexpenditureofNationalGridGasTransmission(NGGT).
» GastransmissioninNI.Specifically,wecomparetheactualcontrollableopexofBGTLandPTLtotheshadowpricecontrolbetween2008/09and2012/13.
4.3.1.1. Gas transmission in GB
SinceOfgem’smodellingworksuggeststhatcostvariabilitymaybelowerforgastransmissionthanforelectricitytransmission;andthe+/‐10%figurerelatestoboth(andisitself,atleastinpart,ajudgement),itisimportanttotakeintoaccountoftheactualmarketdatarelatingtogastransmissioninGB.
Helpfully,OfgempublisheddataNGGT’sactualcontrollableoperatingexpenditurecomparedtoitsallowedcontrollableoperatingexpenditureforthelastpricecontrol–coveringtheyears2007/08to2010/11.9Asillustratedbythetablebelow,thedatashowsthatNGGT’sactualexpenditurewas£65.6monaverageoverthefouryears,whereasitsallowancein2010/11was£70.1m–adifferenceof‐6.4%.
9 ‘Transmission Annual Report for 2010/11’, Ofgem (2012), Figure 8.
Economic Insight EstimatingtheWACCadjustmentfactor Confidential
14
Figure1NGGTactualversusallowedcontrollableopex2007/08‐2010/11
Source:EconomicInsightanalysisofOfgemdata
Thisfigureissignificantlylowerthanthe10%figureusedintheNIAUR’smidwayscenarioand,indeed,isclosertoboththefigureusedintheNIAUR’slowscenarioandthefigureimpliedbytheBGE(NI)data.
4.3.1.2. Gas transmission in NI
Ourclient,MutualEnergy,hasprovideduswithdataontheactualand‘allowed’controllableoperatingexpenditure(undertheshadowpricecontrol)ofPremierTransmissionandBelfastGasTransmissionbetween2008/09and2012/13.Thefigurebelowshowsthat:
BelfastGasTransmission’sactualexpenditureoverthefiveyearswas£6.18manditsallowedexpenditurewas£6.24m–agapof‐0.9%;and
PremierTransmission’sactualexpenditureoverthefiveyearswas£18.2manditsallowedexpenditurewas£19.4m–agapof‐6.2%
£70.1
£65.6
£0.0
£10.0
£20.0
£30.0
£40.0
£50.0
£60.0
£70.0
£80.0
Allowedcontrollableopexin2010/11 Actualaverageannualcontrollableopex2007/08‐2010/11
AllowedandactualcontrollableNGGTopex(£m)
Difference = ‐6.4%
Economic Insight EstimatingtheWACCadjustmentfactor Confidential
15
Figure2BGTLactualversusallowedcontrollableopex2008/09‐2012/13
Source:EconomicInsightanalysisofMutualEnergydata
Figure3PTLactualversusallowedcontrollableopex2008/09‐2012/13
Source:EconomicInsightanalysisofMutualEnergydata
Again,bothfiguresaresignificantlylowerthanthe10%figureusedintheNIAUR’smidwayscenario.Asnotedpreviouslyinthisreport,therearereasonstothinkthattheBelfastGasTransmissionisaclosercomparatortotheGastotheWestPipelinethanPremierTransmission,indicatingthatitmightbemoreappropriatetorelyonthelowerfigure.
4.3.2. Conclusion on energy industry comparators
Thetablebelowsummarisestherecentactualmarketevidenceofcontrollableoperatingexpenditurevariabilityfromtheenergysectorcomparators.
£6.24 £6.18
£0.00
£1.00
£2.00
£3.00
£4.00
£5.00
£6.00
£7.00
Allowedcontrollableopex(total)between2008/09and2012/13
Actualcontrollableopex(total)between2008/09and2012/13
AllowedandactualcontrollableBGTLopex(£m
)Difference = ‐0.9%
£19.4£18.2
£0.0
£5.0
£10.0
£15.0
£20.0
£25.0
Allowedcontrollableopex(total)between2008/09and2012/13
Actualcontrollableopex(total)between2008/09and2012/13
AllowedandactualcontrollablePTLopex(£m
)
Difference = ‐6.2%
Economic Insight EstimatingtheWACCadjustmentfactor Confidential
16
Table5Summaryofenergysectorcomparators
Source Actual/Allowed%
BGE(NI) ‐4.1%(5years,2007/08‐2011/12)
NGGT ‐6.4%(4years,2007/08‐2010/11)
BelfastGasTransmission ‐0.9%(5years,2008/09‐2012/13)
PremierTransmission ‐6.2%(5years,2008/09‐2012/13)
Source:EconomicInsightanalysis
Thetableshowsthat:
noneofthe‘projects’exhibitvariabilityoftheNIAUR’sproposedmidwayestimateof+/‐10%;
alloftheprojectarebelow+/‐7%;and twooftheprojectsarebelowthecurrentlowestimateof+/‐5%.
Therefore,thisevidencesuggeststhatthecurrentmidwayestimateof+/‐10%istoohigh.Theactualmarketevidencesuggeststhatvariabilityinexcessof+/‐7%isunlikely,andsomaybeamoreappropriate‘upper‐bound’estimate.Moreover,asnotedabove,Ofgem’sscenario‐basedanalysessuggestthatthecontrollableoperatingcostvariabilityforgastransmissionislowerthanforelectricitytransmission,andsoafigurelowerthantheaverage10%wouldalsobeappropriateonthisbasis.
4.3.3. Water industry comparators
InourviewthewaterindustryisahelpfulcomparatortoconsiderwithregardtothepotentialscopeofopexriskwithintheWACCinrelationtotheGastotheWestPipeline.Inparticular,wenotethattheImrecon/ECAreportforOfgem(which,asnotedabove,isakeysourcefortheNIAUR’sownassessmentofopexvariability)specificallymakesreferencetothewatersector,statingthatit:“isgenerallythoughttohaveasimilarriskprofiletoenergynetworks.”10Wefurthernotethat:(i)OfwatplacedweightonenergyretailermarginswhendeterminingappropriateallowednetretailmarginsinthewatersectorforPR14;and(ii)whendetermininganappropriaterangeforthereturnonregulatoryequity(RORE),whichishighlypertinenttotheissuesunderconsiderationhere,OfwatexplicitlyexaminedRORErangesforgasdistribution,notingthat:“wewouldexpecttoseeaconsistencyintheoverallrangeforROREforregulatedutilitieswithcomparablereturns.”11
Indeed,wenotethat(similartogastransmission)thewaterindustryischaracterisedby:
ahighlevelofcapitalintensity(i.e.alowrelativeamountofopex); stableandrelativelypredictabledemand;and apredictableandstableregulatoryregime.
Forthisreasonwehavecomparedallowedopex(assetduringpricecontrols)withactualcompanyopexovertimeforthewaterindustry.OurstartpointwastoexaminethedifferencebetweenactualandallowedopexforNorthernIrelandWater(NIW),asthefactthatitsoperatingareaisNorthernIrelandislikelytofurtherimprovecomparability.
10 ‘RIIO Reviews: Financeability study.’ Imrecon and ECA report submitted to Ofgem (November 2012). Page 4.
11 ‘Setting price controls for 2015‐20 – risk and reward guidance.’ Ofwat (2013). Page 47.
Economic Insight EstimatingtheWACCadjustmentfactor Confidential
17
4.3.3.1. Northern Ireland Water
TheNIAURpublishesinformationonNIW’sactualandallowedopexinitsCostandPerformancereports.Inparticular,fortheperiod2010‐13,theNIAURsetoutitsassessmentoftheextenttowhichNIWhasgenuinelyoutperformeditsopextargetsforreasonsofefficiency(ratherthansay,bydeferringprojects).Inourviewthisisahighlyrelevantmeasure,asweareseekingtoidentifytheextenttowhichcontrollableopexcouldvaryfromthatoriginallyassumedbytheregulator(asultimately,thisistherisktowhichequityisgenuinelyexposed).UsingthedatapublishedbytheNIAURwethereforecalculatedthevariationinopexarisingfromoutperformanceasapercentageofallowedopexineachyear,asshowninthefollowingtable.
Table6NorthernIrelandWaterallowedandactualopex
Calculationstep 2010‐11 2011‐12 2012‐13 Total
Allowedopex‐PC10FDTarget(£m)
£220.4 £215.1 £207.2 £642.7
NIWtotalopexunderspend(£m) ‐£17.1 ‐£25.0 ‐£15.5 ‐£57.6
NIAUR'sassessmentofunderspendduetooutperformance(£m)
‐£6.1 ‐£6.9 ‐£6.5 ‐£19.5
Allowedopexadjustedforoutperformance(£m)
£209.4 £197.0 £198.2 £604.6
NIWactualopexspend(£m) £203.3 £190.1 £191.7 £585.1
Opexvariancefromoutperformance(%)
‐2.9% ‐3.5% ‐3.3% ‐3.2%
Source:NIAUR12
OuranalysisshowsthatthetotalopexvarianceforNIW(arisingfromoutperformance)was‐3.2%overthethreeyearsto2012/13.Overthisperiod,opexvariancefromoutperformancewasnomorethan‐3.5%inanyindividualyear.
4.3.3.2. England and Wales Water and Sewerage Companies
Inadditiontotheabove,weexaminedtheopexvarianceofwaterandseweragecompanies(WASCs)inEnglandandWales,whicharesubjecttoarevenuebasedpricecontrolmodel,asperNIW.Specifically,we:
» ExaminedtheaverageannualallowedopexsetbyOfwat(theregulator)atthelastpricereview(PR09).13
» ObtaineddataonWASCactualopexineachofthethreeyearssincethecontrolperiodstarted(2010/11,2011/12and2012/13)–asreportedintheirregulatoryaccounts.14
12 ‘Cost and Performance Report For NI Water ‐ PC10.’ NIAUR (2013). Tables 2.2 and 2.3
13 As reported in: ‘Ofwat PR09 Final Determination.’ See Table 37: Operating expenditure by company (annual average post‐efficiency). Ofwat has advised us that the data is in 2007/08 prices and so the reported allowed opex of £3,323m as published has been inflated by RPI in each subsequent year and then averaged (giving £3,664m).
14 Actual WASC opex figures are taken from ‘operating cost analysis’ tables as reported in the notes to company’s regulatory accounts. These provide a breakdown of opex by area. Ofwat advised us that both third party services costs and retail costs
Economic Insight EstimatingtheWACCadjustmentfactor Confidential
18
» Then,finally,wecalculatedthe%differencebetweenactualandallowedopexfortheindustryasawholeacrossthethreeyearstodate,asshowninthechartbelow.
Figure4WASCactualversusallowedopexoverPR09
Source:EconomicInsightanalysisofOfwatdataandWASCregulatoryaccounts15
Ouranalysisshowsthatacrosstheindustry,actualopexhasvariedby‐2.3%relativetoallowedopexoverthepricecontrolperiodtodate.Regardingthemethodologywehaveemployedtocalculatethisvariance,therearethreeimportantpointstohighlight:
» First,wethinkthatitisappropriatetolookatthevarianceoverthethreeyearscombined,asequityholderswouldgenerallytendtothinkabouttherisktoreturnsfromtheperspectiveofapricecontrolperiod(i.e.thefactthatopexorequityreturnscouldvarybemoreorlessthanthisinanygivenyearisnotparticularlyinformativeoftheactualrisktowhichequityholdersareexposed).
» Second,wethinkthatitisappropriatetolookatthevariancefortheindustryasawholeovertime(ratherthanindividualcompanies),ascapitalisreadilysubstitutableacrossindividualcompanieswithintheindustryand,assuch,theriskprofileacrosscompaniesisunlikelytovaryinanymeaningfulway.WenotethatthiswasOfwat’srationale(consistentwithadvicefromPwC)forretainingasinglenotionalindustryWACCfortheforthcomingPR14pricecontrol.16Notwithstandingthispoint,ouranalysisalsoshowsthat8ofthe10WASCsincludedinouranalysishadavarianceoflessthan+/‐3%andonlyonehadavarianceofgreaterthan+/‐10%.
» Third,becausetheavailabledatadoesnotallowustospecificallyisolatevarianceincontrollableopexinrelationtoWASCsinEnglandandWales,theopexvariancefactor
are included in the allowed opex figures above, and so we have also included these in our actuals (noting that Ofwat’s total allowed opex at the start of PR09 would have included retail costs, even though the requirement to report them separately only came into effect during the price control period). WASCs included in the analysis were: Anglian Water, Dwy Cymru, Northumbrian Water, Severn Trent, South West Water, Southern Water, Thames Water, United Utilities, Wessex Water and Yorkshire Water.
15 Analysis is in nominal outturn prices.
16 See: ‘Cost of capital for PR14: Methodological considerations.’ PwC report for Ofwat (July 2013).
£3,664£3,581
£0
£500
£1,000
£1,500
£2,000
£2,500
£3,000
£3,500
AllowedaverageannualopexarPR09(£m)
Actualaverageannualopex(£m)
AllowedandactualW
ASCopex(£m)
Difference = ‐2.3%
Economic Insight EstimatingtheWACCadjustmentfactor Confidential
19
wehavecalculatedmayover‐statethetrueopexvolatilityrisktowhichequityholdersareexposed(thisisthecasesolongasonesupposesthatitistheuncontrollableelementofopexthatismostsubjecttovolatilityrisk,whichweconsidertobelikelyinmostinstances).
Insummary,ouranalysisofopexvariabilityinthewatersectorsuggestsarangeofbetween+/‐2.3%to+/‐3.2%.
4.3.4. Airport and rail comparators
Thissectionbrieflysetsoutadditionalevidencefromotherregulatedsectors,namelyHeathrowandGatwickairports(whicharesubjecttopricecontrolsbytheCivilAviationAuthority)andNetworkRail(whichissubjecttopricecontrolsbytheOfficeofRailRegulation).Asnotedabove,weconsiderthesesectorstobelesscomparablethanthegasandwatersectors,andsoattachlessweighttotheminourconclusions.
4.3.4.1. Airports
ThetablebelowshowstheactualandallowedoperatingexpenditureofHeathrowandGatwickairportsbetween2008/09and2012/13.
Table7ComparisonofHeathrowandGatwickairports’allowedandactualopex
£m2011/12prices 08/09 09/10 10/11 11/12 12/13 Total
Heathrowallowed 968 952 956 962 969 4,807
Heathrowactual 1,071 1,052 996 1,001 997 5,117
Difference% 6.4%
Gatwickallowed 315 313 314 315 312 1,569
Gatwickactual 312 319 281 281 285 1,478
Difference ‐5.8%
Source:EconomicInsightanalysisofCAAdata,
Thetableshowsthat:
forHeathrow,actualoperatingexpenditurewashigherthanallowedoperatingexpenditureby6.4%;and
forGatwick,actualoperatingexpenditurewaslowerthanallowedoperatingexpenditureby‐5.8%.
Again,bothfiguresaresignificantlylowerthanthe10%figureusedintheNIAUR’smidwayscenario.
4.3.4.2. Rail
NetworkRail’sregulatoryaccountsshowthatitsactualcontrollableoperatingexpenditurebetween2009/10andbetween2011/12was£2,887manditsallowedcontrollableoperatingexpenditurewas£2,581–adifferenceof11.5%.17
Wenotethatpartofthereasonforthisrelativelyhighdifference,whichisclosertotheNIAUR’smidwayestimate,maybecausedbytheshorttimeperiodoverwhichthe
17 ‘Network Rail Infrastructure Limited Regulatory Financial Statements’, (2012), Statement 7a.
Economic Insight EstimatingtheWACCadjustmentfactor Confidential
20
differenceiscalculated.Wehavethereforecheckedthedifferenceforentiretyofthepreviouspricecontrol,runningfrom2004/05to2008/09.18Thedatashowsthat:
thegapbetweenactualandallowedoperatingexpenditure(controllableanduncontrollable)wasmuchlowerat+1.2%;and
accordingtoNetworkRail“TheACR2003splitsoperatingexpenditureintocontrollableandnon‐controllablecostsanditisthelatterthathasexceededthedeterminationacrossthecontrolperiod.”19
4.3.4.3. Conclusion on airport and rail comparators
Althoughweconsidertheaboveairportandrailregulatedsectorstobelesscomparablethanenergyandwater,thisevidenceisalsoconsistentwiththeviewthatafigureof+/‐10%istoohighforamidwayestimate.
4.4. Our conclusions regarding the variability of controllable opex
Basedontheaboveanalysis,thefigurebelowsummarisestheactualmarketdataoncontrollableoperatingcostvariability.Therangeisbetween0.9%and11.5%.
Figure5SummaryofcomparatorevidenceonopexvariancerelativetoNIAURrange
Source:EconomicInsightanalysis
Onthebasisofthisdataweconsiderthat:
» Anappropriatelowestimateofvariabilitywouldbearound+/‐3%.ThisisbasedonthefactthattheaverageopexvariabilityofBGE(NI),NIW,BGTLandE&WWASCstogetherisjustunderthislevel.
» Asuitablemidwayorcentralestimateofvariabilitywouldbearound+/‐6%.Thisisbasedonthefactthatmostcomparatorshaveoperatingcostvariabilityatorbelowthislevel(anditisalsomidwaybetweentheminimumandmaximumestimatesof0.9%and11.5%).
» Themaximumestimateshouldbe+/‐7%.ThisisbasedonthefactthatallbutNetworkRailarebelowthislevel–andthatNetworkRailfiguremay:(a)notbeasgoodacomparatorastheothers;and(b)mayexhibitalowerlevelofvariabilityoveralongertimeperiod.
18 ‘Network Rail Infrastructure Limited Regulatory Financial Statements’, (2009)
19 ‘Network Rail Infrastructure Limited Regulatory Financial Statements’, (2009), page 4.
0% 2% 4% 6% 8% 10% 12% 14% 16% 18% 20%NIAUR Low NIAUR Mid NIAUR High
BGTL, 0.9%
NIW, 3.2%
BGE (NI) 4.1%
NR, 11.5%
E&W WASCs, 2.3%
Gatwick, 5.8%
PTL, 6.2%
NGGT, 6.4%
Heathrow, 6.4% Blue cross = Stronger comparatorOrange cross = Weaker comparator
Yellow shading = Our proposed range
Economic Insight EstimatingtheWACCadjustmentfactor Confidential
21
Finally,wenotethattheNIAUR’s‘high’estimateisinconsistentwiththeevidenceandshouldbedisregarded.Thatis,thehighestimatesuggeststhatthatitismorelikelythannot(specificallya56.5%chance)thatopexvariabilitywouldbegreaterthan7%.
Economic Insight EstimatingtheWACCadjustmentfactor Confidential
22
5. Conclusions Theevidenceandanalysissetoutabovesuggeststhemoreappropriatealternativeassumptionsforthelevelandvariabilityofcontrollableopexare:
£1.0mand3%inthelowscenario; £1.2mand6%inthemediumscenario;and £1.4mand7%inthehighscenario.
Thetablebelowshowstherevisedpre‐taxWACCadjustmentfactorsusingthesealternativeassumptionsandthesamecalculationmethodologyastheNIAUR.Itshowsthatthepre‐taxWACCadjustmentfactorsrangebetween0.04%and0.14%.
Table8Revisedpre‐taxriskadjustmentfactorswithalternativeassumptions
Assumptions Low(3%) Medium(6%) High(7%)
Low(£1.0m) 0.04% 0.09% 0.10%
Medium(£1.2m) 0.05% 0.11% 0.12%
High(£1.4m) 0.06% 0.12% 0.14%
Source:EconomicInsightanalysis
Ourviewisthattheappropriatemidwayorcentralestimatetouseis0.11%,whichishalfofthecurrentmidwayorcentralestimateof0.22%.Alternatively,thedataismoresupportiveoftheNIAUR’s‘low’estimateof0.09%thanitisofitscentralestimateof0.22%,andwithoutfurtheranalysis,werecommendthatthisisused.Finally,thetableshownoverleafprovidesfulldetailsofthecalculationstepsusedtoderivetheaboveadjustmentfactors.
Economic Insight EstimatingtheWACCadjustmentfactor Confidential
23
Table9CalculationstepsforWACCadjustmentfactor
Calculationstep Lowcase Mediumcase Highcase
Controllableopex(£m) £1.000 £1.200 £1.400
Variation(%) 3.00% 6.00% 7.00%
Variationvalue(£m) £0.030 £0.072 £0.098
Expectedequityreturn(£m)
£0.818 £1.818 £2.818
Min(£m) £0.788 £1.746 £2.720
Max(£m) £0.848 £1.890 £2.916
MinRORE(%) 6.55% 14.51% 22.61%
MaxRORE(%) 7.05% 15.71% 24.24%
Spread(%) 0.50% 1.20% 1.63%
Standarddeviations 1.65 1.65 1.65
SDEquity 0.15% 0.36% 0.49%
SDMarket 8.50% 8.50% 8.50%
Equitybeta 0.02 0.04 0.06
ERP(%) 5.30% 5.30% 5.30%
ECA(%) 0.09% 0.23% 0.31%
Gearing(%) 62.50% 62.50% 62.50%
WACCAdj 0.04% 0.08% 0.12%
WACCAdj‐pre‐tax 0.04% 0.11% 0.14%Source:EconomicInsightanalysis
Economic Insight WACCadjustmentfortheGastotheWestPipeline privilegedandconfidential
24
Further information
EconomicInsightLimited88WoodStreetLondonEC2V7RS
www.economic‐insight.com
EconomicInsightLtdisregisteredinEnglandNo.760829.
Whilsteveryefforthasbeenmadetoensuretheaccuracyofthematerialandanalysiscontainedinthisdocument,theCompanyacceptsnoliabilityforanyactiontakenonthebasisofitscontents.EconomicInsightisnotlicensedintheconductofinvestmentbusinessasdefinedintheFinancialServicesandMarketsAct2000.
Anyindividualorfirmconsideringaspecificinvestmentshouldconsulttheirownbrokerorotherinvestmentadviser.TheCompanyacceptsnoliabilityforanyspecificinvestmentdecision,whichmustbeattheinvestor’sownrisk.
©EconomicInsight,2013.Allrightsreserved.Otherthanthequotationofshortpassagesforthepurposesofcriticismorreview,nopartofthisdocumentmaybeusedorreproducedwithoutexpresspermission.
© Economic Insight Ltd 2014