Attachment 1
Summary of Changes to the 2017 FTIP
16/17 $1,170,309 16/17 $1,170,309 HBP
16/17 $129,038 16/17 $129,038 Local Match
17/18 $10,460,240 17/18 $10,460,420 HBP
17/18 $843,848 17/18 $843,848 Local Match
17/18 $463,732 17/18 $463,732 State Bond
18/19 $2,388,250 18/19 $0 HBP
18/19 $0 18/19 $0 Local Match
18/19 $0 18/19 $0 State Bond
19/20 $26,231,335 19/20 $20,821,151 HBP
19/20 $780,029 19/20 $1,745,849 Local Match
19/20 $1,972,886 19/20 $573,500 State Bond
Beyond $80,401,919 Beyond $88,200,353 HBP
Beyond $6,218,644 Beyond $6,652,210 Local Match
Beyond $1,553,077 Beyond $1,553,077 State Bond
16/17 $2,387,385 16/17 $2,087,385 CMAQ
16/17 $1,699,250 16/17 $214,250 Local Match
17/18 $2,518,158 17/18 $2,818,158 CMAQ
17/18 $1,855,472 17/18 $3,340,472 Local Match
16/17 $1,159,095 16/17 $1,071,281 CMAQ
16/17 $1,311,305 16/17 $454,516 Local Match
16/17 $363,991 16/17 $584,860 RSTP
17/18 $943,038 17/18 $1,030,852 CMAQ
17/18 $948,212 17/18 $630,028 Local Match
19/20 $0 19/20 $363,991 RSTP
19/20 $0 19/20 $3,005,590 Local Match
16/17 $3,625,775 16/17 $3,647,537 RSTP
16/17 $271,246 16/17 $242,631 Local Match
19/20 $6,849,326 19/20 $6,485,335 RSTP
19/20 $3,064,799 19/20 $3,015,164 Local Match
Grouped Projects for Pavement
Resurfacing/Rehab (Grouped Projects for pavement resurfacing and/or rehabilitation:
Projects are consistent with 40 CFR Part
93.126 Exempt Tables 2 and Table 3
Categories - Pavement resurfacing and/or
rehabilitation (Using Toll Credits ))
CON Grouped Listing Updated
-$663,110 -1.10%Existing 21400000566
$2,415,477 19.41% Grouped Listing Updated
Project Identification
2017 FTIP
CTIPS ID# Sponsor Agency Project Title Current CTIPS Amount COMMENTS
SUMMARY OF CHANGES Agency: Various
Amendment #: 3 Amendment Type: Administrative Modification (Type I)
Current Total Project Cost Prior
FFY Fund Source
Funding
Total Project Change
Total Project%
Increase/Decrease
Prior CTIPS Amount
Current FFY
Various Agencies $0 0.00%
CON
21400000447
Grouped Projects for Highway Bridge
Program (Grouped Projects for Bridge Rehabilitation and
Reconstruction - HBP Program: Projects are
consistent with 40 CFR Part 93.126 Exempt Tables 2 Categories.
Widening narrow pavements or
reconstructing Bridges (No additional Travel
Lanes))
Existing
Prior Total Project Cost
Existing or New Project
CON
Phase
Updated CTIPS$165,309,808$165,309,808
CON
CON
CON
CON
$0 0.00% Grouped Listing UpdatedCON
Grouped Projects for Intersection
Signalization: Grouped Projects for Intersection Signalization projects
consistent with 40 CFR Part 93.126 Exempt
Table 3 category (Using Toll Credits)
Existing 21400000594 Various Agencies $31,356,670
Various Agencies $60,150,120 $59,487,010
$31,356,670
Existing 21400000565 Various Agencies
Grouped Projects for Intersection
Channelization: (Grouped Projects for
Intersection Channelization:
Projects are consistent with 40 CFR Part
93.126 Exempt Table 3 Categories - Intersection
Channelization Projects. (Using Toll
Credits))
$12,445,020 $14,860,497
Project Identification
CTIPS ID# Sponsor Agency Project Title Current CTIPS Amount COMMENTS
Current Total Project Cost Prior
FFY Fund Source
Funding
Total Project Change
Total Project%
Increase/Decrease
Prior CTIPS Amount
Current FFY
Prior Total Project Cost
Existing or New Project Phase
16/17 $79,000 16/17 $78,792 CMAQ
16/17 $10,000 16/17 $10,208 Local Match
17/18 $83,000 17/18 $83,218 CMAQ
17/18 $11,000 17/18 $10,782 Local Match
16/17 $65,000 16/17 $73,000 CMAQ
16/17 $8,000 16/17 $0 Local Match
17/18 $72,000 17/18 $81,000 CMAQ
17/18 $9,000 17/18 $0 Local Match
16/17 $182,000 16/17 $182,372 CMAQ
16/17 $24,000 16/17 $23,628 Local Match
17/18 $186,000 17/18 $185,913 CMAQ
17/18 $24,000 17/18 $24,087 Local Match
CONExisting 21400000254 Stanislaus County
Transit Fare Subsidy Program (Transit Fare
SubsidyProgram (TFS)
StaRT/MAX Employee Ride Program)
$793,000 $793,000 $0 0.00% Updated CTIPS
CON $0 0.00% Updated CTIPSExisting 21400000510 City of Modesto
Rideshare Program, City of Modesto
(Rideshare Program, City of Modesto (Toll
Credits))
$479,000 $479,000
CON $0 0.00% Updated CTIPSExisting 21400000479 Stanislaus Council of Governments
Regional Rideshare (Regional Rideshare
Program)$1,876,000 $1,876,000
Attachment 2
CTIPS Pages
Stanislaus Council of Governments - Federal Transportation Improvement Program(Dollars in Whole)
Local Highway SystemDIST:10
PPNO:
EA:
CTIPS ID:214-0000-0447
CT PROJECT ID:
MPO ID.:STANCOG
COUNTY:Stanislaus County
ROUTE:
PM:
TITLE (DESCRIPTION):Grouped Projects for Highway Bridge Program (GroupedProjects for Bridge Rehabilitation and Reconstruction -HBP Program; Projects are consistent with 40 CFR Par93.126 Exempt Tables 2 categories. Widening narrowpavements or reconstructing Bridges (No AdditionalTravel Lanes))
MPO Aprv: 05/12/2017
State Aprv:
Federal Aprv:
EPA TABLE II or III EXEMPT CATEGORY
Safety Improvement Program.
IMPLEMENTING AGENCY: Various Agencies PROJECT MANAGER: DEBBIE TRUJILLO PHONE: (209) 525-4639 EMAIL: [email protected]
PROJECT VERSION HISTORY (Printed Version is Shaded) (Dollars in whole)
Version Status Date Updated By Change Reason Amend No. Prog Con Prog RW PE
19 Official 05/12/2017 DTRUJILL Amendment - Cost/Scope/Sch. Change 3 165,309,808
18 Official 02/06/2017 DTRUJILL Amendment - Cost/Scope/Sch. Change 1 165,309,808
17 Official 09/21/2016 MTUCKER Adoption - Carry Over 137,430,549
16 Official 05/24/2016 JFABELA Amendment - Cost/Scope/Sch. Change 11
15 Official 04/29/2015 JFABELA Amendment - Cost/Scope/Sch. Change 4 141,858,633
14 Official 03/02/2015 JFABELA Amendment - Cost/Scope/Sch. Change 3 141,859,186
13 Official 06/18/2014 JFABELA Adoption - Carry Over 140,955,570
12 Official 07/14/2014 JFABELA Amendment - Cost/Scope/Sch. Change 15 37,609,143
11 Official 01/09/2014 JFABELA Amendment - Cost/Scope/Sch. Change 9 36,459,610
* Highway Bridge Program - State - * Fund Source 1 of 3 * Fund Type: Bridge - State (HBRR) * Funding Agency: Federal Highway Administration(FHWA)
PRIOR 16/17 17/18 18/19 19/20 20/21 21/22 BEYOND TOTAL
PE
RW
CON 29,217,144 1,170,309 10,460,420 20,821,151 88,200,353 149,869,377
Total: 29,217,144 1,170,309 10,460,420 20,821,151 88,200,353 149,869,377
* Local Funds - * Fund Source 2 of 3 * Fund Type: Local Transportation Funds * Funding Agency:
PRIOR 16/17 17/18 18/19 19/20 20/21 21/22 BEYOND TOTAL
PE
RW
CON 1,998,932 129,038 843,848 1,745,849 6,652,210 11,369,877
Total: 1,998,932 129,038 843,848 1,745,849 6,652,210 11,369,877
* State Bond - * Fund Source 3 of 3 * Fund Type: Local Bridge Seismic Retrofit Account * Funding Agency: Caltrans
PRIOR 16/17 17/18 18/19 19/20 20/21 21/22 BEYOND TOTAL
PE
RW
CON 1,480,245 463,732 573,500 1,553,077 4,070,554
Total: 1,480,245 463,732 573,500 1,553,077 4,070,554
Project Total: PRIOR 16/17 17/18 18/19 19/20 20/21 21/22 BEYOND TOTAL
PE
RW
CON 32,696,321 1,299,347 11,768,000 23,140,500 96,405,640 165,309,808
Total: 32,696,321 1,299,347 11,768,000 23,140,500 96,405,640 165,309,808
Products of CTIPS Page 1 05/12/2017 04:44:47
Stanislaus Council of Governments - Federal Transportation Improvement Program(Dollars in Whole)
Local Highway SystemComments:******** Version 19 - 05/12/2017 **************** Version 18 - 12/15/2016 **************** Version 1 - 06/09/16 ********Project data transfered from 2014 FTIP.******** Version 16 - 04/15/2016 ********Updated per HBP Backup-List 3/25/25 from Caltrans******** Version 15 - 04/20/2015 **************** Version 14 - 01/05/2015 ********RTP# SC04 - SC74Back-up List: 2015 FTIP Appendix J******** Version 1 - 03/12/14 ********Project data transfered from 2012 FTIP.******** Version 11 - 01/09/2014 **************** Version 10 - 05/20/2013 **************** Version 9 - 01/24/2013 ********RTP Appendix # M-1/Page 1-2******** DFTIP Version 1 - 05/02/2012 **************** Version 7 - 04/30/2012 ********Updates based on 10/20/2011, 4:15 PM Caltrans 2010/11-2015/16 HBP Program List******** Version 6 - 11/02/2011 ********Updates based on 03/28/2011, 10:18 AM Caltrans 2008/9-2013/14 Highway Bridge Program List)******** Version 5 - 05/11/2011 **************** Version 4 - 12/15/2010 ********RTP Appendix # M-1/Page 1******** Version 3 - 07/08/2010 **************** Version 2 - 04/29/2010 **************** Version 1 - 05/15/2008 ********
Products of CTIPS Page 2 05/12/2017 04:44:47
Stanislaus Council of Governments - Federal Transportation Improvement Program(Dollars in Whole)
Local Highway SystemDIST:10
PPNO:
EA:
CTIPS ID:214-0000-0594
CT PROJECT ID:
MPO ID.:STANCOG
COUNTY:Stanislaus County
ROUTE:
PM:
TITLE (DESCRIPTION):Grouped Projects for Intersection Signalization (GroupedProjects for Intersection Signalization projects consistentwith 40 CFR Part 93.126 Exempt Table 3 category(Using Toll Credits))
MPO Aprv: 05/12/2017
State Aprv:
Federal Aprv:
EPA TABLE II or III EXEMPT CATEGORY
Intersection signalization projects.
IMPLEMENTING AGENCY: Various Agencies PROJECT MANAGER: DEBBIE TRUJILLO PHONE: (209) 525-4639 EMAIL: [email protected]
PROJECT VERSION HISTORY (Printed Version is Shaded) (Dollars in whole)
Version Status Date Updated By Change Reason Amend No. Prog Con Prog RW PE
24 Official 05/12/2017 DTRUJILL Amendment - Cost/Scope/Sch. Change 3 31,356,670
23 Official 02/06/2017 DTRUJILL Amendment - Cost/Scope/Sch. Change 1 31,356,670
22 Official 09/21/2016 MTUCKER Adoption - Carry Over 31,356,670
21 Official 07/28/2016 MTUCKER Amendment - Cost/Scope/Sch. Change 12
20 Official 03/29/2016 JFABELA Amendment - Cost/Scope/Sch. Change 9 31,356,670
19 Official 05/27/2015 JFABELA Amendment - Cost/Scope/Sch. Change 7 31,356,670
18 Official 05/20/2015 JFABELA Amendment - Cost/Scope/Sch. Change 5 31,428,220
17 Official 04/29/2015 JFABELA Amendment - Cost/Scope/Sch. Change 4 31,252,450
16 Official 01/21/2015 JFABELA Amendment - Cost/Scope/Sch. Change 2 31,208,428
* CMAQ - * Fund Source 1 of 4 * Fund Type: Congestion Mitigation * Funding Agency: Federal Highway Administration(FHWA)
PRIOR 16/17 17/18 18/19 19/20 20/21 21/22 BEYOND TOTAL
PE
RW
CON 12,750,730 2,087,385 2,818,158 909,090 18,565,363
Total: 12,750,730 2,087,385 2,818,158 909,090 18,565,363
* Local Funds - * Fund Source 2 of 4 * Fund Type: City Funds * Funding Agency: Various Agencies
PRIOR 16/17 17/18 18/19 19/20 20/21 21/22 BEYOND TOTAL
PE
RW
CON 8,758,315 214,250 3,340,472 12,313,037
Total: 8,758,315 214,250 3,340,472 12,313,037
* CT Minor Pgm. - * Fund Source 3 of 4 * Fund Type: SHOPP Advance Construction (AC) * Funding Agency: Caltrans
PRIOR 16/17 17/18 18/19 19/20 20/21 21/22 BEYOND TOTAL
PE
RW
CON 250,000 250,000
Total: 250,000 250,000
* RSTP - * Fund Source 4 of 4 * Fund Type: STP Local * Funding Agency: Federal Highway Administration(FHWA)
PRIOR 16/17 17/18 18/19 19/20 20/21 21/22 BEYOND TOTAL
PE
RW
CON 157,500 70,770 228,270
Total: 157,500 70,770 228,270
Project Total: PRIOR 16/17 17/18 18/19 19/20 20/21 21/22 BEYOND TOTAL
PE
RW
CON 21,916,545 2,372,405 6,158,630 909,090 31,356,670
Total: 21,916,545 2,372,405 6,158,630 909,090 31,356,670
Products of CTIPS Page 1 05/12/2017 04:46:12
Stanislaus Council of Governments - Federal Transportation Improvement Program(Dollars in Whole)
Local Highway SystemComments:******** Version 24 - 05/12/2017 **************** Version 23 - 02/03/2017 **************** Version 1 - 06/09/16 ********Project data transfered from 2014 FTIP.******** Version 20 - 03/21/2016 **************** Version 19 - 05/26/2015 **************** Version 18 - 05/19/2015 **************** Version 17 - 04/23/2015 **************** Version 16 - 12/19/2014 ********RTP# C03 - SC38Back-up List: 2015 FTIP Appendix D******** Version 1 - 03/12/14 ********Project data transfered from 2012 FTIP.******** Version 14 - 02/28/2014 **************** Version 13 - 06/18/2013 **************** Version 12 - 01/04/2013 ********RTP Appendix # M-1/Page 1-9******** DFTIP Version 1 - 05/02/2012 **************** Version 8 - 04/30/2012 **************** Version 7 - 04/04/2012 ********Toll Credity FFY 11/12 $3,441 City of Turlock******** Version 6 - 11/21/2011 ********Toll Credits FFY 11/12 $30,970 City of Oakdale******** Version 5 - 09/26/2011 ********100% CMAQ funding per energy act provisions will be used, relieving local agency of match requirement: FFY10/11 City of Modesto "New Traffic Signal 2013" ($90,000)******** Version 4 - 07/21/2011 **************** Version 3 - 03/25/2011 **********An additional $250,000 is being applied from State Minor B funds to the City of Waterford "Western Ave & SR 132" Project******** Version 2 - 03/10/2011 **************** Version 1 - 12/20/2010 ********RTP, Appendix M-1
Products of CTIPS Page 2 05/12/2017 04:46:12
Stanislaus Council of Governments - Federal Transportation Improvement Program(Dollars in Whole)
Local Highway SystemDIST:10
PPNO:
EA:
CTIPS ID:214-0000-0565
CT PROJECT ID:
MPO ID.:VA01
COUNTY:Stanislaus County
ROUTE:
PM:
TITLE (DESCRIPTION):Grouped Projects for Intersection Channelization(Grouped Projects for Intersection Channelization:Projects are consistent with 40 CFR Part 93.126 ExemptTable 3 Categories - Intersection ChannelizationProjects. (Using Toll Credits))
MPO Aprv: 05/12/2017
State Aprv:
Federal Aprv:
EPA TABLE II or III EXEMPT CATEGORY
Non signalization traffic control and operatng.
IMPLEMENTING AGENCY: Various Agencies PROJECT MANAGER: DEBBIE TRUJILLO PHONE: (209) 525-4639 EMAIL: [email protected]
PROJECT VERSION HISTORY (Printed Version is Shaded) (Dollars in whole)
Version Status Date Updated By Change Reason Amend No. Prog Con Prog RW PE
25 Official 05/12/2017 DTRUJILL Amendment - Cost/Scope/Sch. Change 3 14,860,497
24 Official 02/06/2017 DTRUJILL Amendment - Cost/Scope/Sch. Change 1 12,445,020
23 Official 09/21/2016 MTUCKER Adoption - Carry Over 12,662,020
22 Official 07/28/2016 MTUCKER Amendment - Cost/Scope/Sch. Change 12
21 Official 05/24/2016 JFABELA Amendment - Cost/Scope/Sch. Change 11 12,662,020
20 Official 03/29/2016 JFABELA Amendment - Cost/Scope/Sch. Change 9 11,207,119
19 Official 05/27/2015 JFABELA Amendment - Cost/Scope/Sch. Change 7 11,452,549
18 Official 05/20/2015 JFABELA Amendment - Cost/Scope/Sch. Change 5 15,836,539
17 Official 04/29/2015 JFABELA Amendment - Cost/Scope/Sch. Change 4 15,271,054
* CMAQ - * Fund Source 1 of 3 * Fund Type: Congestion Mitigation * Funding Agency: Federal Highway Administration(FHWA)
PRIOR 16/17 17/18 18/19 19/20 20/21 21/22 BEYOND TOTAL
PE
RW
CON 6,042,226 1,071,281 1,030,852 8,144,359
Total: 6,042,226 1,071,281 1,030,852 8,144,359
* Local Funds - * Fund Source 2 of 3 * Fund Type: City Funds * Funding Agency: Various Agencies
PRIOR 16/17 17/18 18/19 19/20 20/21 21/22 BEYOND TOTAL
PE
RW
CON 1,487,153 454,516 630,028 3,005,590 5,577,287
Total: 1,487,153 454,516 630,028 3,005,590 5,577,287
* RSTP - * Fund Source 3 of 3 * Fund Type: STP Local * Funding Agency: Federal Highway Administration(FHWA)
PRIOR 16/17 17/18 18/19 19/20 20/21 21/22 BEYOND TOTAL
PE
RW
CON 190,000 584,860 363,991 1,138,851
Total: 190,000 584,860 363,991 1,138,851
Project Total: PRIOR 16/17 17/18 18/19 19/20 20/21 21/22 BEYOND TOTAL
PE
RW
CON 7,719,379 2,110,657 1,660,880 3,369,581 14,860,497
Total: 7,719,379 2,110,657 1,660,880 3,369,581 14,860,497
Products of CTIPS Page 1 05/12/2017 04:47:03
Stanislaus Council of Governments - Federal Transportation Improvement Program(Dollars in Whole)
Local Highway SystemComments:******** Version 25 - 05/12/2017 **************** Version 24 - 02/03/2017 **************** Version 1 - 06/09/16 ********Project data transfered from 2014 FTIP.******** Version 21 - 05/23/2016 **************** Version 20 - 03/21/2016 **************** Version 19 - 05/20/2015 **************** Version 18 - 05/14/2015 **************** Version 17 - 04/22/2015 **************** Version 16 - 12/19/2014 ********RTP# RE02 - SC32Back-up List : 2015 FTIP Appendix D******** Version 1 - 03/12/14 ********Project data transfered from 2012 FTIP.******** Version 13 - 02/28/2014 **************** Version 12 - 01/04/2013 ********RTP Appendix # M-1/Page 1-9******** DFTIP Version 1 - 05/02/2012 **************** Version 9 - 04/30/2012 **************** Version 8 - 04/04/2012 ********Toll Credits FFY 11/12 $9,176 City of Turlock******** Version 7 - 11/21/2011 ********Toll Credits FFY 11/12 $43,586 City of Modesto******** Version 6 - 09/26/2011 **************** Version 5 - 07/20/2011 **************** Version 4 - 05/11/2011 ********Toll Credits in FFY 10/11 CON $574 for City of Oakdale "G Street & Maag Ave"
Toll Credits in FFY 10/11 PE $6,882 for "SB Prescott at Plaza"
Toll Credits in FFY 10/11 PE $14,337 for "SB McHenry/Briggsmore Prescott at Plaza"
Toll Credits in FFY 11/12 CON $30,396 for City of Oakdale "G Street & Maag Ave"******** Version 3 - 03/25/2011 ********
******** Version 2 - 03/10/2011 **************** Version 1 - 07/26/2010 ********RTP Appendix # M-1/Page 3-8
Products of CTIPS Page 2 05/12/2017 04:47:03
Stanislaus Council of Governments - Federal Transportation Improvement Program(Dollars in Whole)
Local Highway SystemDIST:10
PPNO:
EA:
CTIPS ID:214-0000-0566
CT PROJECT ID:
MPO ID.:VA02
COUNTY:Stanislaus County
ROUTE:
PM:
TITLE (DESCRIPTION):Grouped Projects for Pavement Resurfacing/Rehab(Grouped Projects for pavement resurfacing and/orrehabilitation: Projects are consistent with 40 CFR Part93.126 Exempt Tables 2 and Table 3 Categories -Pavement resurfacing and/or rehabilitation (Using TollCredits))
MPO Aprv: 05/12/2017
State Aprv:
Federal Aprv:
EPA TABLE II or III EXEMPT CATEGORY
Pavement resurfacing and/or rehabilitation.
IMPLEMENTING AGENCY: Various Agencies PROJECT MANAGER: DEBBIE TRUJILLO PHONE: (209) 525-4639 EMAIL: [email protected]
PROJECT VERSION HISTORY (Printed Version is Shaded) (Dollars in whole)
Version Status Date Updated By Change Reason Amend No. Prog Con Prog RW PE
27 Official 05/12/2017 DTRUJILL Amendment - Cost/Scope/Sch. Change 3 59,487,010
26 Official 02/06/2017 DTRUJILL Amendment - Cost/Scope/Sch. Change 1 60,150,120
25 Official 09/21/2016 MTUCKER Adoption - Carry Over 48,122,581
24 Official 05/24/2016 JFABELA Amendment - Cost/Scope/Sch. Change 11
23 Official 03/29/2016 JFABELA Amendment - Cost/Scope/Sch. Change 9 48,190,071
22 Official 05/27/2015 JFABELA Amendment - Cost/Scope/Sch. Change 7 46,620,598
21 Official 05/20/2015 JFABELA Amendment - Cost/Scope/Sch. Change 5 46,920,598
20 Official 04/29/2015 JFABELA Amendment - Cost/Scope/Sch. Change 4 49,337,793
19 Official 01/21/2015 JFABELA Amendment - Cost/Scope/Sch. Change 2 45,418,358
* RSTP - * Fund Source 1 of 2 * Fund Type: STP Local * Funding Agency: Federal Highway Administration(FHWA)
PRIOR 16/17 17/18 18/19 19/20 20/21 21/22 BEYOND TOTAL
PE
RW
CON 32,092,575 3,404,906 5,241,275 6,533,747 6,485,335 53,757,838
Total: 32,092,575 3,404,906 5,241,275 6,533,747 6,485,335 53,757,838
* Local Funds - * Fund Source 2 of 2 * Fund Type: City Funds * Funding Agency: Various Agencies
PRIOR 16/17 17/18 18/19 19/20 20/21 21/22 BEYOND TOTAL
PE
RW
CON 2,038,664 242,631 286,874 145,839 3,015,164 5,729,172
Total: 2,038,664 242,631 286,874 145,839 3,015,164 5,729,172
Project Total: PRIOR 16/17 17/18 18/19 19/20 20/21 21/22 BEYOND TOTAL
PE
RW
CON 34,131,239 3,647,537 5,528,149 6,679,586 9,500,499 59,487,010
Total: 34,131,239 3,647,537 5,528,149 6,679,586 9,500,499 59,487,010
Comments:******** Version 27 - 05/12/2017 **************** Version 26 - 02/03/2017 **************** Version 1 - 06/09/16 ********Project data transfered from 2014 FTIP.******** Version 24 - 05/23/2016 **************** Version 23 - 03/22/2016 **************** Version 22 - 05/26/2015 **************** Version 21 - 05/19/2015 **************** Version 20 - 04/23/2015 **************** Version 19 - 12/19/2014 ********RTP# RE01 - SC32Back-up List: 2015 FTIP Appendix F******** Version 1 - 03/12/14 ********Project data transfered from 2012 FTIP.******** Version 15 - 03/03/2014 **************** Version 14 - 10/17/2013 **************** Version 13 - 05/20/2013 **************** Version 12 - 01/07/2013 ********RTP Appendix # M-1/Page 1-9******** DFTIP Version 1 - 05/02/2012 **************** Version 7 - 04/30/2012 ********Toll Credits in FFY 11/12 Stanislaus County******** Version 6 - 04/03/2012 ********Toll Credits FFY 11/12 $21,554 for City of Riverbank & $64,825 for StanCOG******** Version 5 - 11/21/2011 ********Toll Credits FFY 11/12 $63,085 - for 2 City of Modesto projects******** Version 4 - 09/26/2011 **************** Version 3 - 08/12/2011 ********
Products of CTIPS Page 1 05/12/2017 04:47:49
******** Version 2 - 03/29/2011 **************** Version 1 - 07/27/2010 ********RTP Appendix # M-1/Page 3-8
Products of CTIPS Page 2 05/12/2017 04:47:49
Stanislaus Council of Governments - Federal Transportation Improvement Program(Dollars in Whole)
Transit SystemDIST:10
PPNO:
EA:
CTIPS ID:214-0000-0254
CT PROJECT ID:
MPO ID.:04STA048C
COUNTY:Stanislaus County
ROUTE:
PM:
TITLE (DESCRIPTION):Transit Fare Subsidy Program (Transit Fare SubsidyProgram (TFS) StaRT/MAX Employee Ride Program)
MPO Aprv: 05/12/2017
State Aprv:
Federal Aprv:
EPA TABLE II or III EXEMPT CATEGORY
Non construction related activities.
IMPLEMENTING AGENCY: Stanislaus County PROJECT MANAGER: JUAN PORTILLO PHONE: (209) 525-7504 EMAIL: [email protected]
PROJECT VERSION HISTORY (Printed Version is Shaded) (Dollars in whole)
Version Status Date Updated By Change Reason Amend No. Prog Con Prog RW PE
10 Official 05/12/2017 DTRUJILL Amendment - Cost/Scope/Sch. Change 3 698,000 95,000
9 Official 09/21/2016 MTUCKER Adoption - Carry Over 698,000 95,000
8 Official 06/18/2014 JFABELA Adoption - Carry Over 515,187 95,243
7 Official 07/25/2012 MPOBAGDE Adoption - Carry Over 95,243 95,243
6 Official 07/21/2010 DNGUYEN2 Adoption - Carry Over 349,636 95,243
5 Official 08/19/2009 SPHILIPS Amendment - Cost/Scope/Sch. Change 9 199,475 95,243
4 Official 04/17/2009 SPHILIPS Amendment - New Project 5 95,243
3 Official 07/12/2006 BABANATH Adoption - Carry Over 62,400
2 Official 08/11/2004 BABANATH Adoption - Carry Over 62,400
* CMAQ - * Fund Source 1 of 2 * Fund Type: Congestion Mitigation * Funding Agency: Stanislaus Council of Governments
PRIOR 16/17 17/18 18/19 19/20 20/21 21/22 BEYOND TOTAL
PE 95,000 95,000
RW
CON 456,000 78,792 83,218 618,010
Total: 551,000 78,792 83,218 713,010
* Local Funds - * Fund Source 2 of 2 * Fund Type: Local Transportation Funds * Funding Agency: Stanislaus County
PRIOR 16/17 17/18 18/19 19/20 20/21 21/22 BEYOND TOTAL
PE
RW
CON 59,000 10,208 10,782 79,990
Total: 59,000 10,208 10,782 79,990
Project Total: PRIOR 16/17 17/18 18/19 19/20 20/21 21/22 BEYOND TOTAL
PE 95,000 95,000
RW
CON 515,000 89,000 94,000 698,000
Total: 610,000 89,000 94,000 793,000
Comments:******** Version 10 - 05/09/2017 **************** Version 1 - 04/11/16 ********Project data transfered from 2014 FTIP.RTP # SC86******** Version 1 - 03/12/14 ********Project data transfered from 2012 FTIP.RTP Appendix # M-2/Page 1******** Version 1 - 05/01/12 ********Project data transfered from 2010 FTIP.******** Version 6 - 05/12/2010 **************** Version 5 - 06/14/2009 **************** Version 4 - 02/23/2009 **************** Version 3 - 05/27/2006 **************** Version 2 - 06/30/2004 **************** Version 1 - 06/30/2004 ********
Products of CTIPS Page 1 05/12/2017 04:48:44
Stanislaus Council of Governments - Federal Transportation Improvement Program(Dollars in Whole)
Local Highway SystemDIST:10
PPNO:
EA:
CTIPS ID:214-0000-0510
CT PROJECT ID:
MPO ID.:08STA104
COUNTY:Stanislaus County
ROUTE:
PM:
TITLE (DESCRIPTION):Rideshare Program, City of Modesto (RideshareProgram, City of Modesto (Toll Credits))
MPO Aprv: 05/12/2017
State Aprv:
Federal Aprv:
EPA TABLE II or III EXEMPT CATEGORY
Ride-sharing and van-pooling program.
IMPLEMENTING AGENCY: Modesto, City of PROJECT MANAGER: MEGAN DISTASO PHONE: (209) 571-5193 EMAIL: [email protected]
PROJECT VERSION HISTORY (Printed Version is Shaded) (Dollars in whole)
Version Status Date Updated By Change Reason Amend No. Prog Con Prog RW PE
7 Official 05/12/2017 DTRUJILL Amendment - Cost/Scope/Sch. Change 3 479,000
6 Official 09/21/2016 MTUCKER Adoption - Carry Over 479,000
5 Official 06/18/2014 JFABELA Adoption - Carry Over 325,000
4 Official 07/25/2012 MPOBAGDE Adoption - Carry Over
3 Official 05/04/2011 JFABELA Amendment - Cost/Scope/Sch. Change 9 65,000
2 Official 11/17/2010 JFABELA Amendment - 2 130,000
1 Official 05/19/2010 JFABELA Amendment - New Project 21 130,000
* CMAQ - * Fund Source 1 of 2 * Fund Type: Congestion Mitigation * Funding Agency: Federal Highway Administration(FHWA)
PRIOR 16/17 17/18 18/19 19/20 20/21 21/22 BEYOND TOTAL
PE
RW
CON 304,000 73,000 81,000 458,000
Total: 304,000 73,000 81,000 458,000
* Local Funds - * Fund Source 2 of 2 * Fund Type: City Funds * Funding Agency: Modesto, City of
PRIOR 16/17 17/18 18/19 19/20 20/21 21/22 BEYOND TOTAL
PE
RW
CON 21,000 21,000
Total: 21,000 21,000
Project Total: PRIOR 16/17 17/18 18/19 19/20 20/21 21/22 BEYOND TOTAL
PE
RW
CON 325,000 73,000 81,000 479,000
Total: 325,000 73,000 81,000 479,000
Comments:******** Version 7 - 04/05/2017 **************** Version 1 - 04/11/16 ********Project data transfered from 2014 FTIP.RTP# M34******** Version 1 - 03/12/14 ********Project data transfered from 2012 FTIP.RTP Appendix # M-2/Page 2Using Toll Credits******** Version 1 - 05/01/12 ********Project data transfered from 2010 FTIP.******** Version 3 - 03/24/2011 **************** Version 2 - 07/22/2010 ********100% CMAQ ($7,455 Local Match - FFY 09/10 CON)******** Version 1 - 04/15/2010 ********
Products of CTIPS Page 1 05/12/2017 04:49:28
Stanislaus Council of Governments - Federal Transportation Improvement Program(Dollars in Whole)
Transit SystemDIST:10
PPNO:
EA:
CTIPS ID:214-0000-0479
CT PROJECT ID:
MPO ID.:ST07
COUNTY:Stanislaus County
ROUTE:
PM:
TITLE (DESCRIPTION):Regional Rideshare (Regional Rideshare Program)
MPO Aprv: 05/12/2017
State Aprv:
Federal Aprv:
EPA TABLE II or III EXEMPT CATEGORY
Ride-sharing and van-pooling program.
IMPLEMENTING AGENCY: Stanislaus Council of Governments PROJECT MANAGER: DEBBIE TRUJILLO PHONE: (209) 525-4639 EMAIL: [email protected]
PROJECT VERSION HISTORY (Printed Version is Shaded) (Dollars in whole)
Version Status Date Updated By Change Reason Amend No. Prog Con Prog RW PE
12 Official 05/12/2017 DTRUJILL Amendment - Cost/Scope/Sch. Change 3 1,876,000
11 Official 09/21/2016 MTUCKER Adoption - Carry Over 1,876,000
10 Official 05/27/2015 JFABELA Amendment - Cost/Scope/Sch. Change 7 1,875,000
9 Official 04/29/2015 JFABELA Amendment - Cost/Scope/Sch. Change 4
8 Official 03/02/2015 JFABELA Amendment - Cost/Scope/Sch. Change 3 1,875,000
7 Official 06/18/2014 JFABELA Adoption - Carry Over 1,460,000
6 Official 07/25/2012 MPOBAGDE Adoption - Carry Over 1,460,000
5 Official 07/21/2010 DNGUYEN2 Adoption - Carry Over 1,065,000
4 Official 01/20/2010 SPHILIPS Amendment - 8 690,195
* CMAQ - * Fund Source 1 of 2 * Fund Type: Congestion Mitigation * Funding Agency: Stanislaus Council of Governments
PRIOR 16/17 17/18 18/19 19/20 20/21 21/22 BEYOND TOTAL
PE
RW
CON 1,312,000 182,372 185,913 1,680,285
Total: 1,312,000 182,372 185,913 1,680,285
* Local Funds - * Fund Source 2 of 2 * Fund Type: Local Transportation Funds * Funding Agency:
PRIOR 16/17 17/18 18/19 19/20 20/21 21/22 BEYOND TOTAL
PE
RW
CON 148,000 23,628 24,087 195,715
Total: 148,000 23,628 24,087 195,715
Project Total: PRIOR 16/17 17/18 18/19 19/20 20/21 21/22 BEYOND TOTAL
PE
RW
CON 1,460,000 206,000 210,000 1,876,000
Total: 1,460,000 206,000 210,000 1,876,000
Comments:******** Version 12 - 05/09/2017 **************** Version 1 - 04/11/16 ********Project data transfered from 2014 FTIP.******** Version 10 - 05/26/2015 ********-Removed Federal some CMAQ Funds & added Local Funds to meet the 11.47% local match requirement for this program.
******** Version 9 - 04/20/2015 **************** Version 8 - 02/19/2015 ********RTP# RE11******** Version 1 - 03/12/14 ********Project data transfered from 2012 FTIP.RTP Appendix M-2/Page 1******** Version 1 - 05/01/12 ********Project data transfered from 2010 FTIP.RTP Appendix # M-1/Page 8******** Version 5 - 04/19/2010 **************** Version 4 - 10/13/2009 **************** Version 3 - 06/11/2009 **************** Version 2 - 04/22/2009 ********RTP pg 81******** Version 1 - 12/14/2008 ********
Products of CTIPS Page 1 05/12/2017 04:50:12
Attachment 3
Highway Bridge Program (HBP) Backup Listing:
http://www.stancog.org/pdf/ftip-amendments/2017/hbp.pdf
2014/15-2019/20 Highway Bridge Program
See the appropriate FTIP/FSTIP for current funding commitments. This listing provides the backup project information to support the lump sum amountsprogrammed in the FTIP.
Note id: 24
1) This is the FTIP lump sum “backup” list for HBP funded projects. Please see the Local Assistance web site for the most currentlistings:
http://www.dot.ca.gov/hq/LocalPrograms/hbrr99/HBP_FSTIP.html
2) The purpose of this list is to show which projects being advanced by local agencies have met the eligibility requirements of thefederal Highway Bridge Program and have been prioritized for funding by the Department in cooperation with local agencies for funding.
3) Contractual funding levels are determined at time of federal authorization/obligation for given phase of work. For details seeChapter 3 of the Local Assistance Procedures Manual.
4) For FTIP/FSTIP purposes, Federal Highway Bridge Program (HBP) funding constraint is managed by Caltrans.
5) Prop 1B bond funds for the Local Seismic Safety Retrofit Program (LSSRP) used for matching federal funds are also managed byCaltrans.
6) Financial constraint of LOCAL matching funds (including regional STIP funds) and LOCAL Advance Construction (AC) is theresponsibility of the MPOs and their local agencies.
7) Some projects show that they are programmed using State STP funds. These funds are HBP funds transferred to the STP forbridge work that is not ordinarily eligible for HBP funds. See the HB Program Guidelines for details. Do not confuse these STPfunds with Regional STP funds.
8) Corrections to this report should be addressed to the District Local Assistance Engineer:
http://www.dot.ca.gov/hq/LocalPrograms/dlae.htm
Notes:
3/29/2017, 5:28 PM
Caltrans, Division of Local Assistance Page 13/29/2017, 5:28 PM Det2 FL4 SmlTxt brf
2014/15-2019/20 Highway Bridge Program
District: County:Responsible Agency
10 Stanislaus
See the appropriate FTIP/FSTIP for current funding commitments. This listing provides the backup project information to support the lump sum amountsprogrammed in the FTIP.
HBP-ID Project Description
Patterson BRIDGE NO. 38C0214, ROGERS ROAD OVER DELTA-MENDOTA CANAL, 0.5 MI N/O SPERRY AVE. Rehabilitate existing 2-lane bridge;Widen to standard 2-lane width.
Fund Source Summary:
PER/W
Total
CON
Total
4,246,200
100,000 450,000 550,000
100,000 100,000
100,000 450,000 100,000 4,896,2004,246,2004,246,200
Phase Summary:
Fed $
Local AC
Local Match
Total
LSSRP Bond
Total88,530 398,385 88,530 4,334,606
11,470 51,615 11,470 561,594
100,000 450,000 100,000 4,896,200
3,759,161
487,039
4,246,200
Prior 14/15 15/16 16/17 17/18 18/19 19/20 Beyond
Prior 14/15 15/16 16/17 17/18 18/19 19/20 Beyond
4097
5244(032)Project #:
PE Summary:
Fed $
Local AC
Local Match
Total
LSSRP Bond
Total88,530 398,385 486,915
11,470 51,615 63,085
100,000 450,000 550,000
Prior 14/15 15/16 16/17 17/18 18/19 19/20 Beyond
R/W Summary:
Fed $
Local AC
Local Match
Total
LSSRP Bond
Total88,530 88,530
11,470 11,470
100,000 100,000
Prior 14/15 15/16 16/17 17/18 18/19 19/20 Beyond
CON Summary:
Fed $
Local AC
Local Match
Total
LSSRP Bond
Total3,759,161
487,039
4,246,200
3,759,161
487,039
4,246,200
Prior 14/15 15/16 16/17 17/18 18/19 19/20 Beyond
Caltrans, Division of Local Assistance Page 23/29/2017, 5:28 PM Det2 FL4 SmlTxt brf
2014/15-2019/20 Highway Bridge Program
District: County:Responsible Agency
10 Stanislaus
See the appropriate FTIP/FSTIP for current funding commitments. This listing provides the backup project information to support the lump sum amountsprogrammed in the FTIP.
HBP-ID Project Description
Stanislaus County BRIDGE NO. 38C0003, SANTA FE AVENUE OVER TUOLUMNE RIVER, 1.0 MI S OF S.H. 132. Replacement with combination of LSSRPSeismic Retrofit funds.. No adding lane capacity.
Fund Source Summary:
PER/W
Total 820,000
CON
Total
11,400,000 11,400,000
312,531 400,000 1,532,531
150,000 150,000
462,531 400,000 11,400,000 13,082,531
820,000
Phase Summary:
Fed $
Local AC
Local Match
Total
94,054
820,000
LSSRP Bond
Total
463,732 463,732
409,479 354,120 10,092,420 11,581,965
53,052 45,880 843,848 1,036,834
462,531 400,000 11,400,000 13,082,531
725,946
Prior 14/15 15/16 16/17 17/18 18/19 19/20 Beyond
Prior 14/15 15/16 16/17 17/18 18/19 19/20 Beyond
2271
5938(080)5938(188)
Project #:
PE Summary:
Fed $
Local AC
Local Match
Total
94,054
820,000
LSSRP Bond
Total276,684 354,120 1,356,750
35,847 45,880 175,781
312,531 400,000 1,532,531
725,946
Prior 14/15 15/16 16/17 17/18 18/19 19/20 Beyond
R/W Summary:
Fed $
Local AC
Local Match
Total
LSSRP Bond
Total132,795 132,795
17,205 17,205
150,000 150,000
Prior 14/15 15/16 16/17 17/18 18/19 19/20 Beyond
CON Summary:
Fed $
Local AC
Local Match
Total
LSSRP Bond
Total
463,732 463,732
10,092,420 10,092,420
843,848 843,848
11,400,000 11,400,000
Prior 14/15 15/16 16/17 17/18 18/19 19/20 Beyond
Caltrans, Division of Local Assistance Page 33/29/2017, 5:28 PM Det2 FL4 SmlTxt brf
2014/15-2019/20 Highway Bridge Program
District: County:Responsible Agency
10 Stanislaus
See the appropriate FTIP/FSTIP for current funding commitments. This listing provides the backup project information to support the lump sum amountsprogrammed in the FTIP.
HBP-ID Project Description
Stanislaus County BRIDGE NO. 38C0004A, HICKMAN ROAD OVER TUOLUMNE RIVER, 0.15 MI S STATE ROUTE 132. Replace existing 2-lane bridge with astandard 2-lane bridge. (LSSRP contribution)
Fund Source Summary:
PER/W
Total 1,840,000
CON
Total
21,000,000
1,840,000
370,000 370,000
370,000 23,210,000
1,840,000
21,000,00021,000,000
Phase Summary:
Fed $
Local AC
Local Match
Total
211,048
1,840,000
LSSRP Bond
Total
-0 582,103
327,561 20,547,813
42,439 2,080,085
370,000 23,210,000
1,628,952
582,103
18,591,300
1,826,598
21,000,000
Prior 14/15 15/16 16/17 17/18 18/19 19/20 Beyond
Prior 14/15 15/16 16/17 17/18 18/19 19/20 Beyond
Change!2272
5938(199)Project #:
PE Summary:
Fed $
Local AC
Local Match
Total
211,048
1,840,000
LSSRP Bond
Total1,628,952
211,048
1,840,000
1,628,952
Prior 14/15 15/16 16/17 17/18 18/19 19/20 Beyond
R/W Summary:
Fed $
Local AC
Local Match
Total
LSSRP Bond
Total327,561 327,561
42,439 42,439
370,000 370,000
Prior 14/15 15/16 16/17 17/18 18/19 19/20 Beyond
CON Summary:
Fed $
Local AC
Local Match
Total
LSSRP Bond
Total
-0 582,103
18,591,300
1,826,598
21,000,000
582,103
18,591,300
1,826,598
21,000,000
Prior 14/15 15/16 16/17 17/18 18/19 19/20 Beyond
Caltrans, Division of Local Assistance Page 43/29/2017, 5:28 PM Det2 FL4 SmlTxt brf
2014/15-2019/20 Highway Bridge Program
District: County:Responsible Agency
10 Stanislaus
See the appropriate FTIP/FSTIP for current funding commitments. This listing provides the backup project information to support the lump sum amountsprogrammed in the FTIP.
HBP-ID Project Description
Stanislaus County BRIDGE NO. 38C0009, CRABTREE ROAD OVER DRY CREEK, 1.8 MI. S/O WARNERVILLE RD. Replace 2-lane bridge with a standard 2-lane bridge. 9/14/2010: Toll Credits programmed for PE & CON. 10/1/2015: Toll credits used for R/W.
Fund Source Summary:
PER/W
Total 795,000
CON
Total
4,452,000
795,000
75,000 75,000
75,000 5,322,000
795,000
4,452,0004,452,000
Phase Summary:
Fed $
Local AC
Local Match
Total 795,000
LSSRP Bond
Total75,000 5,322,000
75,000 5,322,000
795,000 4,452,000
4,452,000
Prior 14/15 15/16 16/17 17/18 18/19 19/20 Beyond
Prior 14/15 15/16 16/17 17/18 18/19 19/20 Beyond
3610
5938(227)Project #:
PE Summary:
Fed $
Local AC
Local Match
Total 795,000
LSSRP Bond
Total795,000
795,000
795,000
Prior 14/15 15/16 16/17 17/18 18/19 19/20 Beyond
R/W Summary:
Fed $
Local AC
Local Match
Total
LSSRP Bond
Total75,000 75,000
75,000 75,000
Prior 14/15 15/16 16/17 17/18 18/19 19/20 Beyond
CON Summary:
Fed $
Local AC
Local Match
Total
LSSRP Bond
Total4,452,000
4,452,000
4,452,000
4,452,000
Prior 14/15 15/16 16/17 17/18 18/19 19/20 Beyond
Caltrans, Division of Local Assistance Page 53/29/2017, 5:28 PM Det2 FL4 SmlTxt brf
2014/15-2019/20 Highway Bridge Program
District: County:Responsible Agency
10 Stanislaus
See the appropriate FTIP/FSTIP for current funding commitments. This listing provides the backup project information to support the lump sum amountsprogrammed in the FTIP.
HBP-ID Project Description
Stanislaus County BRIDGE NO. 38C0010, CROWS LANDING ROAD OVER SAN JOAQUIN RIVER, NEAR W. CARPENTER RD. Bridge replacement with limtedLSSRP Seismic Retrofit funds
Fund Source Summary:
PER/W
Total
150,000
1,758,000
CON
Total
17,200,400 17,200,400
625,000 2,233,000
500,000 650,000
1,125,000 17,200,400 20,083,400
1,608,000
Phase Summary:
Fed $
Local AC
Local Match
Total
201,643
1,758,000
LSSRP Bond
Total
573,500 573,500
995,963 15,227,514 17,779,834
129,038 1,399,386 1,730,066
1,125,000 17,200,400 20,083,400
1,556,357
Prior 14/15 15/16 16/17 17/18 18/19 19/20 Beyond
Prior 14/15 15/16 16/17 17/18 18/19 19/20 Beyond
Change!2273
5938(071)5938(076)
Project #:
PE Summary:
Fed $
Local AC
Local Match
Total
184,438
1,608,000
LSSRP Bond
Total553,313 1,976,875
71,688 256,125
625,000 2,233,000
1,423,562
Prior 14/15 15/16 16/17 17/18 18/19 19/20 Beyond
R/W Summary:
Fed $
Local AC
Local Match
Total
17,205
150,000
LSSRP Bond
Total442,650 575,445
57,350 74,555
500,000 650,000
132,795
Prior 14/15 15/16 16/17 17/18 18/19 19/20 Beyond
CON Summary:
Fed $
Local AC
Local Match
Total
LSSRP Bond
Total
573,500 573,500
15,227,514 15,227,514
1,399,386 1,399,386
17,200,400 17,200,400
Prior 14/15 15/16 16/17 17/18 18/19 19/20 Beyond
Caltrans, Division of Local Assistance Page 63/29/2017, 5:28 PM Det2 FL4 SmlTxt brf
2014/15-2019/20 Highway Bridge Program
District: County:Responsible Agency
10 Stanislaus
See the appropriate FTIP/FSTIP for current funding commitments. This listing provides the backup project information to support the lump sum amountsprogrammed in the FTIP.
HBP-ID Project Description
Stanislaus County BRIDGE NO. 38C0033, LAS PALMAS AVENUE OVER SAN JOAQUIN RIVER, 3 MI N/E STATE ROUTE 33. Preventive Maintenance project.
Fund Source Summary:
PER/W
Total 100,000
CON
Total
16,710,400
2,984,000
19,694,400
100,000
16,710,400
2,884,000
19,594,400
Phase Summary:
Fed $
Local AC
Local Match
Total
11,470
100,000
LSSRP Bond
Total17,435,452
2,258,948
19,694,400
88,530 17,346,922
2,247,478
19,594,400
Prior 14/15 15/16 16/17 17/18 18/19 19/20 Beyond
Prior 14/15 15/16 16/17 17/18 18/19 19/20 Beyond
3883
5938(200)Project #:
PE Summary:
Fed $
Local AC
Local Match
Total
11,470
100,000
LSSRP Bond
Total2,641,735
342,265
2,984,000
88,530 2,553,205
330,795
2,884,000
Prior 14/15 15/16 16/17 17/18 18/19 19/20 Beyond
CON Summary:
Fed $
Local AC
Local Match
Total
LSSRP Bond
Total14,793,717
1,916,683
16,710,400
14,793,717
1,916,683
16,710,400
Prior 14/15 15/16 16/17 17/18 18/19 19/20 Beyond
Caltrans, Division of Local Assistance Page 73/29/2017, 5:28 PM Det2 FL4 SmlTxt brf
2014/15-2019/20 Highway Bridge Program
District: County:Responsible Agency
10 Stanislaus
See the appropriate FTIP/FSTIP for current funding commitments. This listing provides the backup project information to support the lump sum amountsprogrammed in the FTIP.
HBP-ID Project Description
Stanislaus County BRIDGE NO. 38C0048, GEER ROAD OVER TUOLUMNE RIVER, 1.3 MI S STATE ROUTE 132. LSSRP Seismic Retrofit.
Fund Source Summary:
PER/W
Total 301,000
CON
Total
1,615,036 1,615,036
301,000
1,615,036 1,916,036
301,000
Phase Summary:
Fed $
Local AC
Local Match
Total
34,525
301,000
LSSRP Bond
Total
185,245 185,245
1,429,791 1,696,267
34,525
1,615,036 1,916,036
266,475
Prior 14/15 15/16 16/17 17/18 18/19 19/20 Beyond
Prior 14/15 15/16 16/17 17/18 18/19 19/20 Beyond
2278
5938(071)5938(106)5938(154)
Project #:
PE Summary:
Fed $
Local AC
Local Match
Total
34,525
301,000
LSSRP Bond
Total266,475
34,525
301,000
266,475
Prior 14/15 15/16 16/17 17/18 18/19 19/20 Beyond
CON Summary:
Fed $
Local AC
Local Match
Total
LSSRP Bond
Total
185,245 185,245
1,429,791 1,429,791
1,615,036 1,615,036
Prior 14/15 15/16 16/17 17/18 18/19 19/20 Beyond
Caltrans, Division of Local Assistance Page 83/29/2017, 5:28 PM Det2 FL4 SmlTxt brf
2014/15-2019/20 Highway Bridge Program
District: County:Responsible Agency
10 Stanislaus
See the appropriate FTIP/FSTIP for current funding commitments. This listing provides the backup project information to support the lump sum amountsprogrammed in the FTIP.
HBP-ID Project Description
Stanislaus County BRIDGE NO. 38C0073, TIM BELL ROAD OVER DRY CREEK, 0.8 MI. S/O CLARIBEL ROAD. Replace historic 2-lane bridge with a standard2-lane bridge. 9/14/2010: Toll Credits programmed for PE & CON. 1/27/2016: Toll credits used for R/W.
Fund Source Summary:
PER/W
Total 575,000
CON
Total
9,857,951
947,000 368,000 1,890,000
110,000 110,000
947,000 368,000 110,000 11,857,951
575,000
9,857,9519,857,951
Phase Summary:
Fed $
Local AC
Local Match
Total 575,000
LSSRP Bond
Total947,000 368,000 110,000 11,857,951
947,000 368,000 110,000 11,857,951
575,000 9,857,951
9,857,951
Prior 14/15 15/16 16/17 17/18 18/19 19/20 Beyond
Prior 14/15 15/16 16/17 17/18 18/19 19/20 Beyond
3628
5938(189)Project #:
PE Summary:
Fed $
Local AC
Local Match
Total 575,000
LSSRP Bond
Total947,000 368,000 1,890,000
947,000 368,000 1,890,000
575,000
Prior 14/15 15/16 16/17 17/18 18/19 19/20 Beyond
R/W Summary:
Fed $
Local AC
Local Match
Total
LSSRP Bond
Total110,000 110,000
110,000 110,000
Prior 14/15 15/16 16/17 17/18 18/19 19/20 Beyond
CON Summary:
Fed $
Local AC
Local Match
Total
LSSRP Bond
Total9,857,951
9,857,951
9,857,951
9,857,951
Prior 14/15 15/16 16/17 17/18 18/19 19/20 Beyond
Caltrans, Division of Local Assistance Page 93/29/2017, 5:28 PM Det2 FL4 SmlTxt brf
2014/15-2019/20 Highway Bridge Program
District: County:Responsible Agency
10 Stanislaus
See the appropriate FTIP/FSTIP for current funding commitments. This listing provides the backup project information to support the lump sum amountsprogrammed in the FTIP.
HBP-ID Project Description
Stanislaus County BRIDGE NO. 38C0078, OAKDALE-WATERFORD OVER CLARIBEL LATERAL, 0.5 MI N/O CLARIBEL RD. Replace existing 2-lane bridgewith a 2-lane bridge. 10/12/2016 10:40:13 AM.
Fund Source Summary:
PER/W
Total
CON
Total
1,509,200
269,500 269,500
150,000
269,500 1,928,7001,509,200
150,000
1,659,200
Phase Summary:
Fed $
Local AC
Local Match
Total
LSSRP Bond
Total238,588 1,707,478
30,912 221,222
269,500 1,928,700
1,468,890
190,310
1,659,200
Prior 14/15 15/16 16/17 17/18 18/19 19/20 Beyond
Prior 14/15 15/16 16/17 17/18 18/19 19/20 Beyond
4502
Project #:
PE Summary:
Fed $
Local AC
Local Match
Total
LSSRP Bond
Total238,588 238,588
30,912 30,912
269,500 269,500
Prior 14/15 15/16 16/17 17/18 18/19 19/20 Beyond
R/W Summary:
Fed $
Local AC
Local Match
Total
LSSRP Bond
Total132,795
17,205
150,000
132,795
17,205
150,000
Prior 14/15 15/16 16/17 17/18 18/19 19/20 Beyond
CON Summary:
Fed $
Local AC
Local Match
Total
LSSRP Bond
Total1,336,095
173,105
1,509,200
1,336,095
173,105
1,509,200
Prior 14/15 15/16 16/17 17/18 18/19 19/20 Beyond
Caltrans, Division of Local Assistance Page 103/29/2017, 5:28 PM Det2 FL4 SmlTxt brf
2014/15-2019/20 Highway Bridge Program
District: County:Responsible Agency
10 Stanislaus
See the appropriate FTIP/FSTIP for current funding commitments. This listing provides the backup project information to support the lump sum amountsprogrammed in the FTIP.
HBP-ID Project Description
Stanislaus County BRIDGE NO. 38C0080, VALLEY HOME ROAD, OVER LONE TREE CREEK, 0.68 MI S/E LONE TREE RD. Bridge Rehabilitation. Widen2-lane bridge to standard lanes and shoulders. (Not capacity increasing) 10/10/16.
Fund Source Summary:
PER/W
Total
CON
Total
1,878,800
335,500 335,500
100,000
335,500 2,314,3001,878,800
100,000
1,978,800
Phase Summary:
Fed $
Local AC
Local Match
Total
LSSRP Bond
Total297,018 2,048,850
38,482 265,450
335,500 2,314,300
1,751,832
226,968
1,978,800
Prior 14/15 15/16 16/17 17/18 18/19 19/20 Beyond
Prior 14/15 15/16 16/17 17/18 18/19 19/20 Beyond
4493
Project #:
PE Summary:
Fed $
Local AC
Local Match
Total
LSSRP Bond
Total297,018 297,018
38,482 38,482
335,500 335,500
Prior 14/15 15/16 16/17 17/18 18/19 19/20 Beyond
R/W Summary:
Fed $
Local AC
Local Match
Total
LSSRP Bond
Total88,530
11,470
100,000
88,530
11,470
100,000
Prior 14/15 15/16 16/17 17/18 18/19 19/20 Beyond
CON Summary:
Fed $
Local AC
Local Match
Total
LSSRP Bond
Total1,663,302
215,498
1,878,800
1,663,302
215,498
1,878,800
Prior 14/15 15/16 16/17 17/18 18/19 19/20 Beyond
Caltrans, Division of Local Assistance Page 113/29/2017, 5:28 PM Det2 FL4 SmlTxt brf
2014/15-2019/20 Highway Bridge Program
District: County:Responsible Agency
10 Stanislaus
See the appropriate FTIP/FSTIP for current funding commitments. This listing provides the backup project information to support the lump sum amountsprogrammed in the FTIP.
HBP-ID Project Description
Stanislaus County BRIDGE NO. 38C0150, GILBERT ROAD OVER TURLOCK IRRIGATION DISTRICT (TID) CERES MAIN CANAL, S/O HATCH ROAD. Replace2-lane bridge with a new 2-lane bridge. 9/16/2010: Toll Credits programmed for PE & CON.
Fund Source Summary:
PER/W
Total 150,000
CON
Total
1,208,665
293,000 443,000
293,000 1,651,665
150,000
1,208,6651,208,665
Phase Summary:
Fed $
Local AC
Local Match
Total 150,000
LSSRP Bond
Total293,000 1,651,665
293,000 1,651,665
150,000 1,208,665
1,208,665
Prior 14/15 15/16 16/17 17/18 18/19 19/20 Beyond
Prior 14/15 15/16 16/17 17/18 18/19 19/20 Beyond
3619
5938(190)Project #:
PE Summary:
Fed $
Local AC
Local Match
Total 150,000
LSSRP Bond
Total293,000 443,000
293,000 443,000
150,000
Prior 14/15 15/16 16/17 17/18 18/19 19/20 Beyond
CON Summary:
Fed $
Local AC
Local Match
Total
LSSRP Bond
Total1,208,665
1,208,665
1,208,665
1,208,665
Prior 14/15 15/16 16/17 17/18 18/19 19/20 Beyond
Caltrans, Division of Local Assistance Page 123/29/2017, 5:28 PM Det2 FL4 SmlTxt brf
2014/15-2019/20 Highway Bridge Program
District: County:Responsible Agency
10 Stanislaus
See the appropriate FTIP/FSTIP for current funding commitments. This listing provides the backup project information to support the lump sum amountsprogrammed in the FTIP.
HBP-ID Project Description
Stanislaus County BRIDGE NO. 38C0154, PLEASANT VALLEY ROAD OVER SOUTH SAN JOAQUIN MAIN CANAL, 0.3 MI. E/O VICTORY ROAD. Replace2-lane bridge with a standard 2-lane bridge. 9/20/2010: Toll Credits programmed for PE & CON.
Fund Source Summary:
PER/W
Total 270,000
CON
Total
1,512,000
343,000 613,000
343,000 2,125,000
270,000
1,512,0001,512,000
Phase Summary:
Fed $
Local AC
Local Match
Total 270,000
LSSRP Bond
Total343,000 2,125,000
343,000 2,125,000
270,000 1,512,000
1,512,000
Prior 14/15 15/16 16/17 17/18 18/19 19/20 Beyond
Prior 14/15 15/16 16/17 17/18 18/19 19/20 Beyond
3652
5938(226)Project #:
PE Summary:
Fed $
Local AC
Local Match
Total 270,000
LSSRP Bond
Total343,000 613,000
343,000 613,000
270,000
Prior 14/15 15/16 16/17 17/18 18/19 19/20 Beyond
CON Summary:
Fed $
Local AC
Local Match
Total
LSSRP Bond
Total1,512,000
1,512,000
1,512,000
1,512,000
Prior 14/15 15/16 16/17 17/18 18/19 19/20 Beyond
Caltrans, Division of Local Assistance Page 133/29/2017, 5:28 PM Det2 FL4 SmlTxt brf
2014/15-2019/20 Highway Bridge Program
District: County:Responsible Agency
10 Stanislaus
See the appropriate FTIP/FSTIP for current funding commitments. This listing provides the backup project information to support the lump sum amountsprogrammed in the FTIP.
HBP-ID Project Description
Stanislaus County BRIDGE NO. 38C0157, MONTPELIER ROAD, OVER T.I.D. MAIN CANAL, AT DALLAS RD. Replace existing 2-lane bridge with 2-lane bridge.10/11/2016 3:33:50 PM.
Fund Source Summary:
PER/W
Total
CON
Total
2,179,800
389,250 389,250
100,000
389,250 2,669,0502,179,800
100,000
2,279,800
Phase Summary:
Fed $
Local AC
Local Match
Total
LSSRP Bond
Total344,603 2,362,910
44,647 306,140
389,250 2,669,050
2,018,307
261,493
2,279,800
Prior 14/15 15/16 16/17 17/18 18/19 19/20 Beyond
Prior 14/15 15/16 16/17 17/18 18/19 19/20 Beyond
4497
Project #:
PE Summary:
Fed $
Local AC
Local Match
Total
LSSRP Bond
Total344,603 344,603
44,647 44,647
389,250 389,250
Prior 14/15 15/16 16/17 17/18 18/19 19/20 Beyond
R/W Summary:
Fed $
Local AC
Local Match
Total
LSSRP Bond
Total88,530
11,470
100,000
88,530
11,470
100,000
Prior 14/15 15/16 16/17 17/18 18/19 19/20 Beyond
CON Summary:
Fed $
Local AC
Local Match
Total
LSSRP Bond
Total1,929,777
250,023
2,179,800
1,929,777
250,023
2,179,800
Prior 14/15 15/16 16/17 17/18 18/19 19/20 Beyond
Caltrans, Division of Local Assistance Page 143/29/2017, 5:28 PM Det2 FL4 SmlTxt brf
2014/15-2019/20 Highway Bridge Program
District: County:Responsible Agency
10 Stanislaus
See the appropriate FTIP/FSTIP for current funding commitments. This listing provides the backup project information to support the lump sum amountsprogrammed in the FTIP.
HBP-ID Project Description
Stanislaus County BRIDGE NO. 38C0168, KILBURN ROAD OVER ORESTIMBA CREEK, .45 MI S CROWS LANDING RD. Replace historic 2-lane bridge with astandard 2-lane bridge on improved alignment (No Added Lane Capacity). 4/1/2010: Toll Credits programmed for PE, R/W, & Con.
Fund Source Summary:
PER/W
Total 683,000
CON
Total
1,534,500 1,534,500
683,000
853,750 853,750
2,388,250 3,071,250
683,000
Phase Summary:
Fed $
Local AC
Local Match
Total 683,000
LSSRP Bond
Total2,388,250 3,071,250
2,388,250 3,071,250
683,000
Prior 14/15 15/16 16/17 17/18 18/19 19/20 Beyond
Prior 14/15 15/16 16/17 17/18 18/19 19/20 Beyond
359
5938(157)Project #:
PE Summary:
Fed $
Local AC
Local Match
Total 683,000
LSSRP Bond
Total683,000
683,000
683,000
Prior 14/15 15/16 16/17 17/18 18/19 19/20 Beyond
R/W Summary:
Fed $
Local AC
Local Match
Total
LSSRP Bond
Total853,750 853,750
853,750 853,750
Prior 14/15 15/16 16/17 17/18 18/19 19/20 Beyond
CON Summary:
Fed $
Local AC
Local Match
Total
LSSRP Bond
Total1,534,500 1,534,500
1,534,500 1,534,500
Prior 14/15 15/16 16/17 17/18 18/19 19/20 Beyond
Caltrans, Division of Local Assistance Page 153/29/2017, 5:28 PM Det2 FL4 SmlTxt brf
2014/15-2019/20 Highway Bridge Program
District: County:Responsible Agency
10 Stanislaus
See the appropriate FTIP/FSTIP for current funding commitments. This listing provides the backup project information to support the lump sum amountsprogrammed in the FTIP.
HBP-ID Project Description
Stanislaus County BRIDGE NO. 38C0170, COOPERSTOWN ROAD OVER GALLUP CREEK, 2.8 MI. NW/O LA GRANGE ROAD. Replace 2-lane bridge with astandard 2-lane bridge. 9/21/2010: Toll Credits programmed for PE & CON. 7/23/2013: Toll credits used for R/W.
Fund Source Summary:
PER/W
Total 455,000
CON
Total
1,155,000
455,000
25,000 25,000
25,000 1,635,000
455,000
1,155,0001,155,000
Phase Summary:
Fed $
Local AC
Local Match
Total 455,000
LSSRP Bond
Total25,000 1,635,000
25,000 1,635,000
455,000 1,155,000
1,155,000
Prior 14/15 15/16 16/17 17/18 18/19 19/20 Beyond
Prior 14/15 15/16 16/17 17/18 18/19 19/20 Beyond
3666
5938(191)Project #:
PE Summary:
Fed $
Local AC
Local Match
Total 455,000
LSSRP Bond
Total455,000
455,000
455,000
Prior 14/15 15/16 16/17 17/18 18/19 19/20 Beyond
R/W Summary:
Fed $
Local AC
Local Match
Total
LSSRP Bond
Total25,000 25,000
25,000 25,000
Prior 14/15 15/16 16/17 17/18 18/19 19/20 Beyond
CON Summary:
Fed $
Local AC
Local Match
Total
LSSRP Bond
Total1,155,000
1,155,000
1,155,000
1,155,000
Prior 14/15 15/16 16/17 17/18 18/19 19/20 Beyond
Caltrans, Division of Local Assistance Page 163/29/2017, 5:28 PM Det2 FL4 SmlTxt brf
2014/15-2019/20 Highway Bridge Program
District: County:Responsible Agency
10 Stanislaus
See the appropriate FTIP/FSTIP for current funding commitments. This listing provides the backup project information to support the lump sum amountsprogrammed in the FTIP.
HBP-ID Project Description
Stanislaus County BRIDGE NO. 38C0180, SHIELLS ROAD OVER CENTRAL CALIFORNIA IRRIGATION DISTRICT (CCID) MAIN CANAL, 0.42 MI. E/O EASTINROAD. Replace 2-lane bridge with a standard 2-lane bridge. 9/22/2010: Toll Credits programmed for PE & CON. 9/27/2016: Toll credits usedfor R/W.
Fund Source Summary:
PER/W
Total 225,000
CON
Total
1,260,000
215,000 440,000
40,000 40,000
215,000 40,000 1,740,000
225,000
1,260,0001,260,000
Phase Summary:
Fed $
Local AC
Local Match
Total 225,000
LSSRP Bond
Total215,000 40,000 1,740,000
215,000 40,000 1,740,000
225,000 1,260,000
1,260,000
Prior 14/15 15/16 16/17 17/18 18/19 19/20 Beyond
Prior 14/15 15/16 16/17 17/18 18/19 19/20 Beyond
3675
5938(192)Project #:
PE Summary:
Fed $
Local AC
Local Match
Total 225,000
LSSRP Bond
Total215,000 440,000
215,000 440,000
225,000
Prior 14/15 15/16 16/17 17/18 18/19 19/20 Beyond
R/W Summary:
Fed $
Local AC
Local Match
Total
LSSRP Bond
Total40,000 40,000
40,000 40,000
Prior 14/15 15/16 16/17 17/18 18/19 19/20 Beyond
CON Summary:
Fed $
Local AC
Local Match
Total
LSSRP Bond
Total1,260,000
1,260,000
1,260,000
1,260,000
Prior 14/15 15/16 16/17 17/18 18/19 19/20 Beyond
Caltrans, Division of Local Assistance Page 173/29/2017, 5:28 PM Det2 FL4 SmlTxt brf
2014/15-2019/20 Highway Bridge Program
District: County:Responsible Agency
10 Stanislaus
See the appropriate FTIP/FSTIP for current funding commitments. This listing provides the backup project information to support the lump sum amountsprogrammed in the FTIP.
HBP-ID Project Description
Stanislaus County BRIDGE NO. 38C0199, MILTON ROAD, OVER ROCK CREEK TRIBUTARY BRIDGE. Replace existing 2-lane bridge with 2- lane new bridge(No added capacity).
Fund Source Summary:
PER/W
Total
CON
Total
1,624,000
290,000 290,000
75,000
290,000 1,989,0001,624,000
75,000
1,699,000
Phase Summary:
Fed $
Local AC
Local Match
Total
LSSRP Bond
Total256,737 1,760,862
33,263 228,138
290,000 1,989,000
1,504,125
194,875
1,699,000
Prior 14/15 15/16 16/17 17/18 18/19 19/20 Beyond
Prior 14/15 15/16 16/17 17/18 18/19 19/20 Beyond
4508
Project #:
PE Summary:
Fed $
Local AC
Local Match
Total
LSSRP Bond
Total256,737 256,737
33,263 33,263
290,000 290,000
Prior 14/15 15/16 16/17 17/18 18/19 19/20 Beyond
R/W Summary:
Fed $
Local AC
Local Match
Total
LSSRP Bond
Total66,398
8,603
75,000
66,398
8,603
75,000
Prior 14/15 15/16 16/17 17/18 18/19 19/20 Beyond
CON Summary:
Fed $
Local AC
Local Match
Total
LSSRP Bond
Total1,437,727
186,273
1,624,000
1,437,727
186,273
1,624,000
Prior 14/15 15/16 16/17 17/18 18/19 19/20 Beyond
Caltrans, Division of Local Assistance Page 183/29/2017, 5:28 PM Det2 FL4 SmlTxt brf
2014/15-2019/20 Highway Bridge Program
District: County:Responsible Agency
10 Stanislaus
See the appropriate FTIP/FSTIP for current funding commitments. This listing provides the backup project information to support the lump sum amountsprogrammed in the FTIP.
HBP-ID Project Description
Stanislaus County BRIDGE NO. 38C0231, MILTON ROAD OVER ROCK CREEK TRIBUTARY, 3.7 MI. N/O SR 4. Replace 2-lane bridge with a standard 2-lanebridge.
Fund Source Summary:
PER/W
Total 675,000
CON
Total
3,780,000
675,000
75,000 75,000
75,000 4,530,000
675,000
3,780,0003,780,000
Phase Summary:
Fed $
Local AC
Local Match
Total
77,423
675,000
LSSRP Bond
Total66,398 4,010,409
8,603 519,591
75,000 4,530,000
597,578 3,346,434
433,566
3,780,000
Prior 14/15 15/16 16/17 17/18 18/19 19/20 Beyond
Prior 14/15 15/16 16/17 17/18 18/19 19/20 Beyond
3872
5938(201)Project #:
PE Summary:
Fed $
Local AC
Local Match
Total
77,423
675,000
LSSRP Bond
Total597,578
77,423
675,000
597,578
Prior 14/15 15/16 16/17 17/18 18/19 19/20 Beyond
R/W Summary:
Fed $
Local AC
Local Match
Total
LSSRP Bond
Total66,398 66,398
8,603 8,603
75,000 75,000
Prior 14/15 15/16 16/17 17/18 18/19 19/20 Beyond
CON Summary:
Fed $
Local AC
Local Match
Total
LSSRP Bond
Total3,346,434
433,566
3,780,000
3,346,434
433,566
3,780,000
Prior 14/15 15/16 16/17 17/18 18/19 19/20 Beyond
Caltrans, Division of Local Assistance Page 193/29/2017, 5:28 PM Det2 FL4 SmlTxt brf
2014/15-2019/20 Highway Bridge Program
District: County:Responsible Agency
10 Stanislaus
See the appropriate FTIP/FSTIP for current funding commitments. This listing provides the backup project information to support the lump sum amounts programmed in the FTIP.
HBP-ID Project Description
Stanislaus County BRIDGE NO. 38C0232, MILTON ROAD, OVER HOODS CREEK, 1.6 MI S/O SR4. Replace existing 2- lane functionally obsolete bridge withstandard 2-lanes bridge. (non capacity increase).
Fund Source Summary:
PER/W
Total
CON
Total
3,088,400
551,500 551,500
75,000
551,500 3,714,9003,088,400
75,000
3,163,400
Phase Summary:
Fed $
Local AC
Local Match
Total
LSSRP Bond
Total488,243 3,288,801
63,257 426,099
551,500 3,714,900
2,800,558
362,842
3,163,400
Prior 14/15 15/16 16/17 17/18 18/19 19/20 Beyond
Prior 14/15 15/16 16/17 17/18 18/19 19/20 Beyond
4500
Project #:
PE Summary:
Fed $
Local AC
Local Match
Total
LSSRP Bond
Total488,243 488,243
63,257 63,257
551,500 551,500
Prior 14/15 15/16 16/17 17/18 18/19 19/20 Beyond
R/W Summary:
Fed $
Local AC
Local Match
Total
LSSRP Bond
Total66,398
8,603
75,000
66,398
8,603
75,000
Prior 14/15 15/16 16/17 17/18 18/19 19/20 Beyond
CON Summary:
Fed $
Local AC
Local Match
Total
LSSRP Bond
Total2,734,161
354,239
3,088,400
2,734,161
354,239
3,088,400
Prior 14/15 15/16 16/17 17/18 18/19 19/20 Beyond
Caltrans, Division of Local Assistance Page 203/29/2017, 5:28 PM Det2 FL4 SmlTxt brf
2014/15-2019/20 Highway Bridge Program
District: County:Responsible Agency
10 Stanislaus
See the appropriate FTIP/FSTIP for current funding commitments. This listing provides the backup project information to support the lump sum amountsprogrammed in the FTIP.
HBP-ID Project Description
Stanislaus County BRIDGE NO. 38C0236, ST. FRANCIS AVENUE OVER MODESTO IRRIGATION DISTRICT (MID) MAIN CANAL, 0.1 MI. W/O McHENRYAVENUE. Replace 2-lane bridge with a standard 2-lane bridge. 9/22/2010: Toll Credits programmed for PE & CON. 9/17/2014: Toll creditsused for R/W.
Fund Source Summary:
PER/W
Total 200,000
CON
Total
1,120,000
160,000 360,000
25,000 25,000
160,000 25,000 1,505,000
200,000
1,120,0001,120,000
Phase Summary:
Fed $
Local AC
Local Match
Total 200,000
LSSRP Bond
Total160,000 25,000 1,505,000
160,000 25,000 1,505,000
200,000 1,120,000
1,120,000
Prior 14/15 15/16 16/17 17/18 18/19 19/20 Beyond
Prior 14/15 15/16 16/17 17/18 18/19 19/20 Beyond
3677
5938(193)Project #:
PE Summary:
Fed $
Local AC
Local Match
Total 200,000
LSSRP Bond
Total160,000 360,000
160,000 360,000
200,000
Prior 14/15 15/16 16/17 17/18 18/19 19/20 Beyond
R/W Summary:
Fed $
Local AC
Local Match
Total
LSSRP Bond
Total25,000 25,000
25,000 25,000
Prior 14/15 15/16 16/17 17/18 18/19 19/20 Beyond
CON Summary:
Fed $
Local AC
Local Match
Total
LSSRP Bond
Total1,120,000
1,120,000
1,120,000
1,120,000
Prior 14/15 15/16 16/17 17/18 18/19 19/20 Beyond
Caltrans, Division of Local Assistance Page 213/29/2017, 5:28 PM Det2 FL4 SmlTxt brf
2014/15-2019/20 Highway Bridge Program
District: County:Responsible Agency
10 Stanislaus
See the appropriate FTIP/FSTIP for current funding commitments. This listing provides the backup project information to support the lump sum amountsprogrammed in the FTIP.
HBP-ID Project Description
Stanislaus County BRIDGE NO. 38C0257, COOPERSTOWN ROAD OVER RYDBERG CREEK, 3.9 MI. NW/O LA GRANGE ROAD. Replace 2-lane bridge with astandard 2-lane bridge. 9/28/2010: Toll Credits programmed for PE & CON. 7/23/2013: Toll credits used for R/W.
Fund Source Summary:
PER/W
Total 450,000
CON
Total
1,463,000
450,000
75,000 75,000
75,000 1,988,000
450,000
1,463,0001,463,000
Phase Summary:
Fed $
Local AC
Local Match
Total 450,000
LSSRP Bond
Total75,000 1,988,000
75,000 1,988,000
450,000 1,463,000
1,463,000
Prior 14/15 15/16 16/17 17/18 18/19 19/20 Beyond
Prior 14/15 15/16 16/17 17/18 18/19 19/20 Beyond
3682
5938(194)Project #:
PE Summary:
Fed $
Local AC
Local Match
Total 450,000
LSSRP Bond
Total450,000
450,000
450,000
Prior 14/15 15/16 16/17 17/18 18/19 19/20 Beyond
R/W Summary:
Fed $
Local AC
Local Match
Total
LSSRP Bond
Total75,000 75,000
75,000 75,000
Prior 14/15 15/16 16/17 17/18 18/19 19/20 Beyond
CON Summary:
Fed $
Local AC
Local Match
Total
LSSRP Bond
Total1,463,000
1,463,000
1,463,000
1,463,000
Prior 14/15 15/16 16/17 17/18 18/19 19/20 Beyond
Caltrans, Division of Local Assistance Page 223/29/2017, 5:28 PM Det2 FL4 SmlTxt brf
2014/15-2019/20 Highway Bridge Program
District: County:Responsible Agency
10 Stanislaus
See the appropriate FTIP/FSTIP for current funding commitments. This listing provides the backup project information to support the lump sum amountsprogrammed in the FTIP.
HBP-ID Project Description
Stanislaus County BRIDGE NO. 38C0262, PIONEER AVENUE, OVER LONE TREE CREEK, 100FT S/O FREELOVE ROAD. Replace existing 2-lane functionallyobsolete bridge with standard 2-lane bridge (non capacity increase). 10/12/2016: Toll Credits programmed for PE, R/W, & CON.
Fund Source Summary:
PER/W
Total
CON
Total
1,379,000
246,250 246,250
100,000
246,250 1,725,2501,379,000
100,000
1,479,000
Phase Summary:
Fed $
Local AC
Local Match
Total
LSSRP Bond
Total246,250 1,725,250
246,250 1,725,250
1,479,000
1,479,000
Prior 14/15 15/16 16/17 17/18 18/19 19/20 Beyond
Prior 14/15 15/16 16/17 17/18 18/19 19/20 Beyond
4504
Project #:
PE Summary:
Fed $
Local AC
Local Match
Total
LSSRP Bond
Total246,250 246,250
246,250 246,250
Prior 14/15 15/16 16/17 17/18 18/19 19/20 Beyond
R/W Summary:
Fed $
Local AC
Local Match
Total
LSSRP Bond
Total100,000
100,000
100,000
100,000
Prior 14/15 15/16 16/17 17/18 18/19 19/20 Beyond
CON Summary:
Fed $
Local AC
Local Match
Total
LSSRP Bond
Total1,379,000
1,379,000
1,379,000
1,379,000
Prior 14/15 15/16 16/17 17/18 18/19 19/20 Beyond
Caltrans, Division of Local Assistance Page 233/29/2017, 5:28 PM Det2 FL4 SmlTxt brf
2014/15-2019/20 Highway Bridge Program
District: County:Responsible Agency
10 Stanislaus
See the appropriate FTIP/FSTIP for current funding commitments. This listing provides the backup project information to support the lump sum amountsprogrammed in the FTIP.
HBP-ID Project Description
Stanislaus County BRIDGE NO. 38C0268, LAKE ROAD, OVER T.I.D. MAIN CANAL, 1.5 MI E/O HAWKINS RD. Replace existing 2-lane functionally obsoletebridge with standard 2-lane new bridge (non capacity increase).
Fund Source Summary:
PER/W
Total
CON
Total
3,495,800
624,250 624,250
175,000
624,250 4,295,0503,495,800
175,000
3,670,800
Phase Summary:
Fed $
Local AC
Local Match
Total
LSSRP Bond
Total552,649 3,802,408
71,601 492,642
624,250 4,295,050
3,249,759
421,041
3,670,800
Prior 14/15 15/16 16/17 17/18 18/19 19/20 Beyond
Prior 14/15 15/16 16/17 17/18 18/19 19/20 Beyond
4505
Project #:
PE Summary:
Fed $
Local AC
Local Match
Total
LSSRP Bond
Total552,649 552,649
71,601 71,601
624,250 624,250
Prior 14/15 15/16 16/17 17/18 18/19 19/20 Beyond
R/W Summary:
Fed $
Local AC
Local Match
Total
LSSRP Bond
Total154,928
20,073
175,000
154,928
20,073
175,000
Prior 14/15 15/16 16/17 17/18 18/19 19/20 Beyond
CON Summary:
Fed $
Local AC
Local Match
Total
LSSRP Bond
Total3,094,832
400,968
3,495,800
3,094,832
400,968
3,495,800
Prior 14/15 15/16 16/17 17/18 18/19 19/20 Beyond
Caltrans, Division of Local Assistance Page 243/29/2017, 5:28 PM Det2 FL4 SmlTxt brf
2014/15-2019/20 Highway Bridge Program
District: County:Responsible Agency
10 Stanislaus
See the appropriate FTIP/FSTIP for current funding commitments. This listing provides the backup project information to support the lump sum amountsprogrammed in the FTIP.
HBP-ID Project Description
Stanislaus County BRIDGE NO. 38C0272, SONORA ROAD OVER MARTELLS CREEK, 0.1 MI E/O FRANKENHEIMER RD. SCOUR COUNTERMEASURE.3/11/2011: Toll Credits programmed for PE & CON.
Fund Source Summary:
PER/W
Total 17,969
CON
Total
100,625
13,000 30,969
13,000 131,594
17,969
100,625100,625
Phase Summary:
Fed $
Local AC
Local Match
Total 17,969
LSSRP Bond
Total13,000 131,594
13,000 131,594
17,969 100,625
100,625
Prior 14/15 15/16 16/17 17/18 18/19 19/20 Beyond
Prior 14/15 15/16 16/17 17/18 18/19 19/20 Beyond
3805
5938(203)Project #:
PE Summary:
Fed $
Local AC
Local Match
Total 17,969
LSSRP Bond
Total13,000 30,969
13,000 30,969
17,969
Prior 14/15 15/16 16/17 17/18 18/19 19/20 Beyond
CON Summary:
Fed $
Local AC
Local Match
Total
LSSRP Bond
Total100,625
100,625
100,625
100,625
Prior 14/15 15/16 16/17 17/18 18/19 19/20 Beyond
Caltrans, Division of Local Assistance Page 253/29/2017, 5:28 PM Det2 FL4 SmlTxt brf
2014/15-2019/20 Highway Bridge Program
District: County:Responsible Agency
10 Stanislaus
See the appropriate FTIP/FSTIP for current funding commitments. This listing provides the backup project information to support the lump sum amountsprogrammed in the FTIP.
HBP-ID Project Description
Stanislaus County BRIDGE NO. 38C0302, TEGNER ROAD OVER TURLOCK IRRIGATION DISTRICT (TID) LATERAL #5, AT JCT W/ HARDING ROAD. Replace 2-lane bridge with a standard 2-lane bridge. 9/23/2010: Toll Credits programmed for PE & CON. 9/17/2013: Toll credits used for R/W.
Fund Source Summary:
PER/W
Total 87,500
CON
Total
1,260,457
208,153 84,347 380,000
50,000 50,000
208,153 134,347 1,690,457
87,500
1,260,4571,260,457
Phase Summary:
Fed $
Local AC
Local Match
Total 87,500
LSSRP Bond
Total208,153 134,347 1,690,457
208,153 134,347 1,690,457
87,500 1,260,457
1,260,457
Prior 14/15 15/16 16/17 17/18 18/19 19/20 Beyond
Prior 14/15 15/16 16/17 17/18 18/19 19/20 Beyond
3687
5938(196)Project #:
PE Summary:
Fed $
Local AC
Local Match
Total 87,500
LSSRP Bond
Total208,153 84,347 380,000
208,153 84,347 380,000
87,500
Prior 14/15 15/16 16/17 17/18 18/19 19/20 Beyond
R/W Summary:
Fed $
Local AC
Local Match
Total
LSSRP Bond
Total50,000 50,000
50,000 50,000
Prior 14/15 15/16 16/17 17/18 18/19 19/20 Beyond
CON Summary:
Fed $
Local AC
Local Match
Total
LSSRP Bond
Total1,260,457
1,260,457
1,260,457
1,260,457
Prior 14/15 15/16 16/17 17/18 18/19 19/20 Beyond
Caltrans, Division of Local Assistance Page 263/29/2017, 5:28 PM Det2 FL4 SmlTxt brf
2014/15-2019/20 Highway Bridge Program
District: County:Responsible Agency
10 Stanislaus
See the appropriate FTIP/FSTIP for current funding commitments. This listing provides the backup project information to support the lump sum amountsprogrammed in the FTIP.
HBP-ID Project Description
Stanislaus County BRIDGE NO. 39C0001, RIVER ROAD OVER SAN JOAQUIN RIVER, STANISLAUS COUNTY LINE. LSSRP Seismic Retrofit
Fund Source Summary:
PER/W
Total 964,400
CON
Total
8,465,342
731,600 1,696,000
15,600 15,600
731,600 15,600 10,176,942
964,400
8,465,3428,465,342
Phase Summary:
Fed $
Local AC
Local Match
Total
110,617
964,400
LSSRP Bond
Total
970,975
647,685 13,811 9,009,647
83,915 1,789 196,321
731,600 15,600 10,176,942
853,783
970,975
7,494,367
8,465,342
Prior 14/15 15/16 16/17 17/18 18/19 19/20 Beyond
Prior 14/15 15/16 16/17 17/18 18/19 19/20 Beyond
2282
5938(037)5938(176)
Project #:
PE Summary:
Fed $
Local AC
Local Match
Total
110,617
964,400
LSSRP Bond
Total647,685 1,501,469
83,915 194,531
731,600 1,696,000
853,783
Prior 14/15 15/16 16/17 17/18 18/19 19/20 Beyond
R/W Summary:
Fed $
Local AC
Local Match
Total
LSSRP Bond
Total13,811 13,811
1,789 1,789
15,600 15,600
Prior 14/15 15/16 16/17 17/18 18/19 19/20 Beyond
CON Summary:
Fed $
Local AC
Local Match
Total
LSSRP Bond
Total
970,975
7,494,367
8,465,342
970,975
7,494,367
8,465,342
Prior 14/15 15/16 16/17 17/18 18/19 19/20 Beyond
Caltrans, Division of Local Assistance Page 273/29/2017, 5:28 PM Det2 FL4 SmlTxt brf
2014/15-2019/20 Highway Bridge Program
District: County:Responsible Agency
10 Stanislaus
See the appropriate FTIP/FSTIP for current funding commitments. This listing provides the backup project information to support the lump sum amountsprogrammed in the FTIP.
HBP-ID Project Description
Number of Projects:
MPO Summary:
Fed $
Local AC
Local Match
Total for all Phases
740,778
10,366,869
LSSRP Bond
Total
-0 185,245 463,732 573,500 2,775,554
3,041,486 2,490,658 1,170,309 10,460,420 20,821,151 135,810,468
148,437 97,495 129,038 843,848 1,745,849 10,357,654
3,375,167 2,588,153 1,299,347 11,768,000 23,140,500 148,943,676
9,626,091
1,553,077
88,200,353
6,652,210
96,405,640
Totals:
Stanislaus Area Association Of Governments
Prior 14/15 15/16 16/17 17/18 18/19 19/20 Beyond
26
Caltrans, Division of Local Assistance Page 283/29/2017, 5:28 PM Det2 FL4 SmlTxt brf
Attachment 4
Surface Transportation Block Grant Program (STBGP) Backup Listing:
http://www.stancog.org/pdf/ftip-amendments/2017/rstp-bk-up-
list-2017-ftip.pdf
Agency Project Description Project Location STBGPFederal Funds Local Funds Total Project Cost
Ceres Overlay Blaker Road from Service Road to Hackett Road 70,000$ 9,069$ 79,069$
Ceres OverlayMitchell Road Overlay Phase IV- Roeding Rd. to Service Rd. 551,618$ 78,245$ 629,863$
Hughson Pavement Rehabilitation Whitmore Avenue- Tully to Charles Street 200,000$ 25,912$ 225,912$
Modesto Pavement Rehabilitation
La Loma Ave. from James St. to Rowland Ave., Miller Ave. from El Vista Ave. to N. Riverside Dr.,Burney St. from 18th St. to Jennie St., 17th ST. from G St. to Burney St.,J St. from 9th St. to 17th St. 1,584,493$ Toll Credits 1,584,493$
Oakdale Pavement RehabilitationC Street Pavement Rehab Phase 2- from Yosemite to 1st St 237,526$ 30,774$ 268,300$
Turlock Rehabilitation E. Monte Vista Ave., from Geer Rd. to eastern city limits 761,269$ 98,631$ 859,900$
Totals 3,404,906$ 242,631$ 3,647,537$
Pavement Resurfacing and/or RehabilitationGrouped Projects
FFY 2016/17
Updated Per 2017 FTIP Administrative Modificaiton No. 3
Agency Project Description Project Location STBGPFederal Funds Local Funds Total Project Cost
Ceres Overlay Service Road from Blaker Road to Morgan Road 536,241$ 69,475$ 605,716$
Ceres OverlayService Road Overlay Phase II- Central Ave. to Blaker Rd. 458,305$ 59,379$ 517,684$
Modesto Pavement Rehabilitation Pelandale Ave. from Sisk Rd. to Dale Rd. 1,734,493$ Toll Credits 1,734,493$
Modesto Traffic Flow Improvements Oakdale Road and Scenic Drive Intersection Improvements 200,000$ Toll Credits 200,000$
Newman Rehabilitation The Intersection of Inyo Avenue & Canal School Road 373,076$ Toll Credits 373,076$
Oakdale Pavement Maintenance Program G Street (Maag to Ventanas) pavement Maintenance 237,526$ 30,774$ 268,300$
Patterson Roadway Reconstruction / OverlaySperry Avenue Improvements: Various locations along Sperry Avenue between Baldwin Rd. and American Eagle 220,869$ 28,615$ 249,484$
Riverbank OverlayOakdale Road between Patterson Road and Silver Rock Road 269,496$ Toll Credits 269,496$
Turlock Rehabilitation
1. Hawkeye Ave., between N. Olive Ave. and Daubenberger Rd.2. Lander Ave., between South Ave. and E. Glenwood Ave. 761,269$ 98,631$ 859,900$
Turlock Rehabilitation West Main Street from SR 99 to Lander Avenue 450,000$ Toll Credits 450,000$
Totals 5,241,275$ 286,874$ 5,528,149$
Pavement Resurfacing and/or RehabilitationGrouped Projects
FFY 2017/18
Updated Per 2017 FTIP Administrative Modificaiton No. 3
Agency Project Description Project Location STBGPFederal Funds Local Funds Total Project Cost
Ceres Overlay Blaker Road from Service Road to Hackett Road 489,304$ 63,394$ 552,698$
Hughson Pavement Rehabilitation Whitmore Avenue - Tully to Charles 100,000$ 12,956$ 112,956$
Modesto Pavement Rehabilitation
El Vista Avenue from Yosemite Boulevard (SR 132) to Scenic Drive; Coffee Road from Scenic Drive to Briggsmore Avenue 300,000$ Toll Credits 300,000$
Modesto Pavement Rehabilitation
Pavement Rehabilitation on Pelandale from Sisk to Dale; and on Standiford Ave. from McHenry to Sisk; Crows Landing Rd. from S 7th St. to W. Whitmore Ave. 2,101,983$ Toll Credits 2,101,983$
Newman Pavement Rehabilitation Main Street 145,131$ Toll Credits 145,131$
Oakdale Overlay Maag & E Street Overlay 277,918$ 36,007$ 313,925$
Patterson Roadway Reconstruction / OverlaySperry Avenue: Various locations from Rogers Rd to the west and Baldwin Rd to the east. 258,428$ 33,482$ 291,910$
Riverbank Overlay Eighth Street: Patterson Road to Kentucky Avenue 270,572$ Toll Credits 270,572$
Turlock Rehabilitation West Main Street from SR 99 to Lander Avenue 440,725$ Toll Credits 440,725$
Stanislaus County Overlay
Phase O:1. Milnes Road - Albers to Santa Fe2. Bradbury Road - Crows Landing Road to Merced County Line.3. Beckwith Road - Gates to HWY 994. Tully Road - Ladd Road to Bangs Ave.5. Carpenter Road - W. Main to Grayson Ave. 2,149,686$ Toll Credits 2,149,686$
Totals 6,533,747$ 145,839$ 6,679,586$
Pavement Resurfacing and/or RehabilitationGrouped Projects
FFY 2018/19
Updated Per 2017 FTIP Administrative Modificaiton No. 3
Agency Project Description Project Location STBGPFederal Funds Local Funds Total Project Cost
Modesto Pavement Rehabilitation
El Vista Avenue from Yosemite Boulevard (SR 132) to Scenic Drive; Coffee Road from Scenic Drive to Briggsmore Avenue 2,182,843$ Toll Credits 2,182,843$
Modesto Pavement Rehabilitation Paradise Road from Sheridan Street to Carpenter Road 2,080,464$ Toll Credits 2,080,464$
Modesto Pavement Rehabilitation
Tuolumne Boulevard from Sutter Ave to Neece Dr, Paradise Rd from Chicago Ave to 1st St, 1st St from Washington St to G St, andG St from 1st St to 2nd St 300,000$ Toll Credits 300,000$
Newman Pavement Rehabilitation Main Street 151,373$ Toll Credits 151,373$
Oakdale Pavement Reconstruction First Avenue - F Street to G Street 289,870$ Toll Credits 289,870$
Patterson Roadway Reconstruction / OverlaySperry Avenue: Various locations from Rogers Rd to the west and Baldwin Rd to the east. 269,543$ 34,922$ 304,465$
Riverbank Overlay Kentucky Avenue: Eighth Street to Claus Road 282,209$ Toll Credits 282,209$
Turlock Rehabilitation West Main Street from SR 99 to Lander Avenue 929,033$ 1,180,242$ 2,109,275$
Stanislaus County Reconstruction/Overlay
Phase M:1.Albers Rd. - Hwy 132 to Claribel Ave. 2. Patterson Rd. - Riverbank City limits to Albers Rd.3. E. Whitmore Ave. - Hughson City Limits to Hickman Rd.4. Hickman Rd. - E. Whitmore Ave. to 400 south of bridge5. 9th St. - River Rd. to 1400' North of Hatch Rd.6. Golden State Blvd. - Taylor Rd. to Nunes Rd.7. Nunes Rd. - Keyes Rd to Keyes Rd.8. Mitchell Rd. - Ceres Bridge to Yosemite Blvd. -$ 1,800,000$ 1,800,000$
Totals 6,485,335$ 3,015,164$ 9,500,499$
FFY 2019/20
Pavement Resurfacing and/or RehabilitationGrouped Projects
Updated Per 2017 FTIP Administrative Modificaiton No. 3
Attachment 5
Congestion Mitigation Air Quality Program (CMAQ) Intersection Signalization
Backup Listing:
http://www.stancog.org/pdf/ftip-amendments/2017/cmaq-signalization.pdf
Agency Project Description Project Location CMAQFederal Funds
STBGPFederal Funds Local Funds Project Cost
Ceres Signalize Morgan and Service Road 33,250$ -$ 14,250$ 47,500$
Riverbank SignalizePatterson Road & Roselle & Coordinated Pedestrian Railroad Safety Crossing Including Sidewalks 990,453$ 70,770$ Toll Credits 1,061,223$
Turlock Signalize N. Denair Ave. and Hawkeye Ave. 28,640$ -$ Toll Credits 28,640$
Turlock Signalize W. Main St. and West Ave. 35,042$ -$ Toll Credits 35,042$
Stanislaus County Signalize Keyes Rd/ Faith Home Rd Intersection 1,000,000$ -$ 200,000$ 1,200,000$
Totals 2,087,385$ 70,770$ 214,250$ 2,372,405$
Intersection Signalization
FFY 2016/17Grouped Projects
Updated Per 2017 FTIP Administrative Modificaiton No. 3
Agency Project Description Project Location CMAQFederal Funds
STBGPFederal Funds Local Funds Project Cost
Ceres Traffic Signal Morgan and Service Road 304,150$ -$ 130,350$ 434,500$
Modesto Traffic Signal
Upgrade Traffic Signal-2017: Tully Rd. at 9 St., 1 St. at H St., Paradise Rd. at H St., and 11 St. at Needham Ave. 868,750$ -$ (Toll Credits) 868,750$
Turlock Traffic Signal N. Denair Ave. and Hawkeye Ave. 329,360$ -$ (Toll Credits) 329,360$
Turlock Traffic Signal W. Main St. and West Ave. 427,513$ -$ (Toll Credits) 427,513$
Turlock Traffic Signal F St and Lander 288,385$ -$ (Toll Credits) 288,385$
Stanislaus County Signalize Crows Landing/Grayson Intersection 300,000$ -$ 1,485,000$ 1,785,000$
Stanislaus County Traffic SignalCarpenter Rd/Whitmore Ave. Intersection Signalization 300,000$ -$ 1,725,122$ 2,025,122$
Totals 2,818,158$ -$ 3,340,472$ 6,158,630$
Intersection Signalization
FFY 2017/18Grouped Projects
Updated Per 2017 FTIP Administrative Modificaiton No. 3
Agency Project Description Project Location CMAQFederal Funds
STBGPFederal Funds Local Funds Project Cost
Turlock Signalize Walnut/Taylor Intersection Improvements 909,090$ -$ Toll Credits 909,090$ Totals 909,090$ -$ -$ 909,090$
FFY 2019/20Grouped Projects
Intersection Signalization
Updated Per 2017 FTIP Administrative Modificaiton No. 3
Attachment 6
Congestion Mitigation Air Quality Program (CMAQ) Intersection Channelization
Backup Listing:
http://www.stancog.org/pdf/ftip-amendments/2017/cmaq-channelization.pdf
Agency Project Description Project Location CMAQFederal Funds
STBGPFederal Funds Local Funds Project Cost
Ceres Traffic Flow Improvements Traffic Signal Modification at Roeding Road and Mitchell Road 334,112$ -$ 43,288$ 377,400$
Ceres Traffic Flow ImprovementsRoundabout at Central Ave/ Pine St/ Industrial Way and Morgan/Aristocrat 471,865$ -$ 61,135$ 533,000$
Patterson Traffic Flow Improvements
Roadway improvements at Sperry Ave., and S. Del Puerto Ave. to configure turn lanes in all directions and improve traffic flow 212,186$ 584,860$ 343,211$ 1,140,257$
Riverbank Traffic Flow Improvements
Traffic Management Intersection Improvements at Roselle Ave. and Morrill Rd., sidewalk infill to link pedestrian commute access along Morrill Road 53,118$ -$ 6,882$ 60,000$
Totals 1,071,281$ 584,860$ 454,516$ 2,110,657$
Agency Project Description Project Location CMAQFederal Funds
STBGPFederal Funds Local Funds Project Cost
Modesto Traffic Flow ImprovementsRight Turn Lane from eastbound Standiford Ave.to southbound Sisk Rd. 500,000$ -$ 400,000$ 900,000$
Riverbank Traffic Flow Improvements
Traffic Management Intersection Improvements at Roselle Ave. and Morrill Rd., sidewalk infill to link pedestrian commute access along Morrill Road 230,852$ -$ 195,618$ 426,470$
Stanislaus County Traffic Flow Improvements Claribel Rd/Roselle Ave Intersection 300,000$ -$ 34,410$ 334,410$
Totals 1,030,852$ -$ 630,028$ 1,660,880$
Agency Project Description Project Location CMAQFederal Funds
STBGPFederal Funds Local Funds Project Cost
Stanislaus County Traffic Flow Improvements Claribel Rd/Roselle Ave Intersection -$ 363,991$ 3,005,590$ 3,369,581$
Totals -$ 363,991$ 3,005,590$ 3,369,581$
Intersection ChannelizationGrouped Projects
FFY 2019/20
Intersection Channelization
Intersection Channelization
FFY 2017/18
FFY 2016/17Grouped Projects
Grouped Projects
Updated Per 2017 FTIP Administrative Modification No. 3