+ All Categories
Home > Documents > ADMINISTRATOR’S RECORD OF DECISION POWER SALES AGREEMENT OFFER TO ALCOA, INC. · 2012. 12. 6. ·...

ADMINISTRATOR’S RECORD OF DECISION POWER SALES AGREEMENT OFFER TO ALCOA, INC. · 2012. 12. 6. ·...

Date post: 30-Aug-2020
Category:
Upload: others
View: 1 times
Download: 0 times
Share this document with a friend
72
B O N N E V I L L E P O W E R A D M I N I S T R A T I O N AUTHENTICATED ADMINISTRATOR’S RECORD OF DECISION POWER SALES AGREEMENT OFFER TO ALCOA, INC. December 6, 2012
Transcript
Page 1: ADMINISTRATOR’S RECORD OF DECISION POWER SALES AGREEMENT OFFER TO ALCOA, INC. · 2012. 12. 6. · ALCOA, INC. ADMINISTRATOR’S RECORD OF DECISION December 6, 2012 I. INTRODUCTION

B O N N E V I L L E P O W E R A D M I N I S T R A T I O N

AUTHENTICATED

ADMINISTRATOR’S RECORD OF DECISION

POWER SALES AGREEMENT OFFER TO ALCOA, INC.

December 6, 2012

Page 2: ADMINISTRATOR’S RECORD OF DECISION POWER SALES AGREEMENT OFFER TO ALCOA, INC. · 2012. 12. 6. · ALCOA, INC. ADMINISTRATOR’S RECORD OF DECISION December 6, 2012 I. INTRODUCTION

i

TABLE OF CONTENTS

I. INTRODUCTION .................................................................................................. 1

II. BACKGROUND .................................................................................................... 2

a. 2009 Agreement .......................................................................................... 2

b. Alcoa v. BPA ............................................................................................... 2

III. POLICY DISCUSSION.......................................................................................... 5

1. Sales to Alcoa will have a downward impact on rates for future rate

periods. ........................................................................................................ 5

2. The Agreement will guarantee a revenue stream based on the IP rate, the

statutorily defined rate for DSI sales. ......................................................... 5

3. A shorter term contract was not possible given Alcoa’s access to more

attractive alternative power supplies for a shorter term. ......................................... 5

IV. THE EQUIVALENT BENEFITS DETERMINATION FOR THE PERIOD

BEGINNING JANUARY 1, 2013, THROUGH SEPTEMBER 30, 2022 ............. 6

a. Models and Data Used in EBT for the Agreement ..................................... 6

b. IP Rate Forecast Used in EBT for the Agreement ...................................... 7

c. BPA expects to be surplus during the Agreement Period ........................... 7

d. Economic benefits to BPA will equal or exceed costs for the period of the

Agreement ................................................................................................... 9

e. Forecast of revenues that would be obtained by selling an equivalent

amount of surplus power. .......................................................................... 11

f. Calculation of the net financial value of tangible economic benefits of

selling power to Alcoa which would not be obtained by selling an

equivalent amount of power on the market............................................... 11

g. Conclusion of Equivalent Benefits Test ................................................... 14

V. RESPONSE TO COMMENTS: SPECIFIC CONTRACT ISSUES .................... 14

a. Whether the ten year term of the Agreement is reasonable and consistent

with sound business principles.................................................................. 14

b. Whether the termination and curtailment provisions of the Agreement are

appropriate. ............................................................................................... 22

c. Whether section 15.2, Uncontrollable Forces, should be adjusted in

response to comments received. ............................................................... 24

d. Whether section 5.5, No Purchases from Third Parties During Curtailment,

should be changed in response to comments received. ............................. 25

e. Whether section 19.2, BPA’s Right to Terminate, should be changed in

response to comments received. ............................................................... 26

f. Whether clarification of the effect of a court ruling that partially

invalidates the Agreement is needed......................................................... 27

g. Whether Section 18.11, Waiver of Damages, should be included in the

Agreement. ................................................................................................ 28

h. Whether Section 11, Employment Levels, should be included in the

Agreement. ................................................................................................ 30

i. Whether BPA should include the capital investment requirement in the

Agreement. ................................................................................................ 32

Page 3: ADMINISTRATOR’S RECORD OF DECISION POWER SALES AGREEMENT OFFER TO ALCOA, INC. · 2012. 12. 6. · ALCOA, INC. ADMINISTRATOR’S RECORD OF DECISION December 6, 2012 I. INTRODUCTION

ii

VI. RESPONSE TO COMMENTS: GENERAL POLICY COMMENTS ................. 34

a. Whether the EBT should be revised to measure actual benefits. .............. 34

b. Whether continued service to Alcoa will exacerbate PSANI transmission

congestion. ................................................................................................ 35

c. Whether the Agreement should be BPA’s last contract for service to

Alcoa. ........................................................................................................ 37

d. Whether BPA is offering the Agreement “solely because Alcoa sued the

agency on the Residential Exchange Settlement Agreement.” ................. 39

XI. ENVIRONMENTAL EFFECTS .......................................................................... 41

X. CONCLUSION ..................................................................................................... 42

Page 4: ADMINISTRATOR’S RECORD OF DECISION POWER SALES AGREEMENT OFFER TO ALCOA, INC. · 2012. 12. 6. · ALCOA, INC. ADMINISTRATOR’S RECORD OF DECISION December 6, 2012 I. INTRODUCTION

1

POWER SALES AGREEMENT OFFER TO

ALCOA, INC.

ADMINISTRATOR’S RECORD OF DECISION

December 6, 2012

I. INTRODUCTION

On December 7, 2012, the Bonneville Power Administration (BPA) will sign a Power

Sales Agreement, BPA Contract Number 13PM-10978 (Agreement), with Alcoa, Inc.

(Alcoa), for power service to Alcoa’s Intalco Plant in Ferndale, Washington. This

Agreement provides 300 aMW of electric power to Alcoa’s Intalco Plant for a term of

nine years and nine months1, from January 1, 2013, until September 30, 2022, at BPA’s

industrial firm power rate (IP rate).

Prior to making its final determination to enter into the Agreement, BPA provided an

opportunity for public review and comment on the draft Agreement and BPA’s

evaluation of the economic benefits and costs of serving Alcoa (“Equivalent Benefits

Test” or “EBT”). The methodology and results of the EBT analysis are fully discussed in

section IV. The public review and comment period began on October 9, 2012, and

continued through November 7, 2012. BPA received 73 comments during this public

comment period including comments from individuals, public power interest groups, and

Alcoa.

This Record of Decision (ROD) documents BPA’s conclusion that offering a tenyear

contract for the sale of power to Alcoa at the IP rate is consistent with BPA’s legal

authorities and sound business principles. First, the EBT analysis forecasts that BPA will

derive significant financial benefit from the contract. Second, due to BPA’s rate-making

requirements, a sale at the IP rate will assure that BPA recovers its costs for the entire

term of the contract. Third, the ten-year term of the contract is within the parameters

established by Congress for service to Direct Service Industry (DSI) customers pursuant

to the Pacific Northwest Electric Power Planning and Conservation Act (Northwest

Power Act) and consistent with standard industry practices. Finally, Alcoa was clear

during negotiations that, due to the company’s ability to obtain power at a lower price

than IP for several years, any offer of a shorter term contract would be rejected, and BPA

would be deprived of the significant margin by which the IP rate exceeds forecasted

market prices for the next several years. For these reasons, the Administrator determined

that the Agreement is consistent with sound business principles, consistent with BPA’s

statutory authority, and a win-win proposition for BPA, Alcoa, and BPA’s customers.

1 The nine year nine month contract term will be rounded up to and refered to as ten years within this

document for ease of reference.

Page 5: ADMINISTRATOR’S RECORD OF DECISION POWER SALES AGREEMENT OFFER TO ALCOA, INC. · 2012. 12. 6. · ALCOA, INC. ADMINISTRATOR’S RECORD OF DECISION December 6, 2012 I. INTRODUCTION

2

II. BACKGROUND

a. 2009 Agreement

This Agreement will replace Alcoa’s previous Power Sales Agreement, Contract No.

10PB-12175 (2009 Agreement). Under the 2009 Agreement, BPA agreed to sell Alcoa up

to 320 aMW of firm power. The term of the 2009 Agreement was divided into four

potential “periods”: the Initial Period, the Extended Initial Period, the Transition Period,

and the Second Period. The Initial Period began December 22, 2009, and ran through

May 26, 2011. The 2009 Agreement contained an option for Alcoa to request an

Extended Initial Period. BPA determined that it would be consistent with sound business

principles to offer Alcoa an Extended Initial Period of twelve months, from May 27,

2011, to May 26, 2012, and documented that option in an accompanying Record of

Decision. See Administrator’s Record of Decision Granting Alcoa’s Request to Extend

the Initial Period of Alcoa’s Power Sales Agreement, Contract No. 10PB-12175, Oct. 29,

2010 [hereinafter Alcoa Extension ROD].

The occurrence of the Transition and Second periods of the 2009 Agreement depended

on the United States Court of Appeals for the Ninth Circuit (Court) issuing an opinion,

prior to May 26, 2012, holding that the EBT standard does not apply to power sales

under the 2009 Agreement. As the May 26 deadline approached and the Court had not

issued an opinion, it appeared that the 2009 Agreement was likely to expire by its own

terms. Therefore, Alcoa and BPA agreed to begin negotiations on a new power sales

agreement. To provide the parties with adequate time to negotiate, Alcoa and BPA

entered into a series of short-term extensions to the 2009 Agreement, based upon new

EBT determinations by BPA. Because the new agreement would replace the 2009

Agreement, the parties also agreed to amend the 2009 Agreement to remove the

contingent Transition and Second periods.

b. Alcoa v. BPA

On January 22, 2010, Alcoa filed a petition for review in the Ninth Circuit challenging

(a) the 2009 Agreement, and (b) BPA’s Record of Decision in support of the 2009

Agreement, dated December 21, 2009. See Power Sale to Alcoa Inc. Commencing

December 22, 2009 Administrator’s Record of Decision, Dec. 21, 2009 [hereinafter 2009

Alcoa ROD]. Petitions for review challenging the same actions were filed by the Pacific

Northwest Generating Cooperative, the Public Power Council, Northwest Requirements

Utilities, the Industrial Customers of Northwest Utilities, and Canby Utility Board

(collectively, the preference customers). Avista Corporation, Portland General Electric,

PacifiCorp, Idaho Power Company, Oregon Public Utilities Commission, and Puget

Sound Energy intervened. All petitioners challenged BPA’s interpretation of PNGC I

and PNGC II, in particular BPA’s development and application of the Equivalent

Page 6: ADMINISTRATOR’S RECORD OF DECISION POWER SALES AGREEMENT OFFER TO ALCOA, INC. · 2012. 12. 6. · ALCOA, INC. ADMINISTRATOR’S RECORD OF DECISION December 6, 2012 I. INTRODUCTION

3

Benefits Test for purposes of determining whether the economics of the transaction are

favorable to providing service to a DSI.

On October 16, 2012, the Ninth Circuit issued its decision in Alcoa, Inc. v. Bonneville

Power Administration (Alcoa), 698 F.3d 774 (9th Cir. 2012). The Court unanimously

held that the Initial Period of the 2009 Agreement was consistent with BPA’s statutory

authorities and that BPA’s rationale for entering into the 2009 Agreement was not

arbitrary or capricious. Id. at 789. The Court addressed the numerous issues raised by

the petitioners and held that “[a]ll these arguments are wrong.” Id. at 785.

In particular, the Court stated that it would grant deference to BPA in making its business

decisions when, as in this case, these decisions are supported in the administrative record.

Id. at 789. The Court repeatedly stated that it would not second guess the wisdom of

BPA’s decisions, especially when BPA is making technical determinations within its

particular area of expertise. Id. at 790.

With regard to the Second Period, the majority found that the Second Period was not

reviewable, while the dissent determined that it should have been considered and set

aside.

On November 30, 2012, Alcoa and the preference customers each filed a petition for

rehearing.

1. The Initial Period

As noted above, with respect to service during the Initial Period, the Court unanimously

upheld BPA’s determinations and rejected every challenge.

The preference customers argued that: (1) service to Alcoa at the IP rate during the Initial

Period violated BPA’s obligations to act in accordance with sound business principles by

foregoing profits that could be made by selling surplus power on the market; (2) BPA’s

analysis was flawed and did not support a finding that BPA would make a modest profit;

and (3) the damage waiver provision of the contract violated BPA’s statutory and

constitutional authorities. Alcoa at 788. Alcoa argued that BPA’s decision to adopt the

EBT was arbitrary and capricious because the EBT is too restrictive and imposes a rigid

test that is not required by case law or statute. Id.

In response to the preference customers’ arguments that BPA violated sound business

principles by selling power to Alcoa at the IP rate rather than into the market at market

rates, the Court held that “[w]e disagree that BPA is required to maximize its profits . . .

As we have previously noted, BPA’s governing statutes ‘do not dictate that BPA always

charge the lowest possible rates.’” Id. at 789. The Court further noted:

In light of the deference we are to give BPA, we cannot say that BPA’s

decision to enter into the [2009 Agreement] was so arbitrary and

capricious as to violate its statutory obligation.

Page 7: ADMINISTRATOR’S RECORD OF DECISION POWER SALES AGREEMENT OFFER TO ALCOA, INC. · 2012. 12. 6. · ALCOA, INC. ADMINISTRATOR’S RECORD OF DECISION December 6, 2012 I. INTRODUCTION

4

Id. The Court found that BPA was selling power at the IP rate as required by statute, it

anticipated earning a modest profit, and there was no evidence to support the claim that

BPA was subsidizing Alcoa. Id.

Next, the Court turned to the arguments that BPA’s EBT was flawed. The Court noted

that “[w]e again approach these methodological challenges with deference to BPA’s

decision making.” Id. at 790. The Court reviewed the petitioners’ multiple challenges to

virtually every facet of BPA’s analysis and determined that BPA responded to all of these

issues in the administrative record and fully explained its rationale:

In sum, BPA’s analysis of these issues was thorough. No factor or

argument identified by the petitioners went unaddressed in the ROD, and

all of BPA’s explanations are plausible and rationally connected to the

facts that were before it at the time.

Id. Similarly, the Court addressed and rejected PNGC’s arguments that the 2009

Agreement was an effort by BPA to provide jobs: “The ROD expressly disclaimed

reliance on job impacts as a factor in its decision and declined to include such impacts in

its Equivalent Benefits Test. PNGC’s speculation is an insufficient basis for upsetting the

agency’s contracting decision.” Id. at 789.

Most notably, the Court declined to rule on whether the EBT “as an abstract proposition,

is wholly in accord with BPA’s governing statutes.” Id. at 792. Rather, the Court

explained that “we must evaluate whether BPA has violated its statutory obligation to

adhere to sound business principles on a case-by-case basis.” Id. In the case of the 2009

Agreement, based on the accompanying record, the Court found that BPA did not. Id.

The Court also addressed petitioners’ challenges to the damage waiver provision of the

2009 Agreement, holding that the damage waiver provision does not violate either

statutory or constitutional provisions. Alcoa at 791–92; see infra Part V.g. With respect

to the former, the Court referred specifically to the Administrator’s broad contracting and

settlement authority.

2. Second Period

The majority dismissed all challenges to service during the Second Period for lack of

jurisdiction based on a confluence of jurisdictional defects involving standing, ripeness,

and mootness. Alcoa at 793–94. The Court found that service during the Second Period

was strictly contingent on events that may never happen, and after the May 2012

amendment to the contract, would never happen. Id. Therefore, the Court held that any

potential injury to petitioners was too remote and speculative to justify invoking the

jurisdiction of the Court to review this portion of the contract. Id. The dissenting judge

rejected the majority’s perspective and would have set aside the Second Period, even

though it had already been cancelled by agreement of the parties.

Page 8: ADMINISTRATOR’S RECORD OF DECISION POWER SALES AGREEMENT OFFER TO ALCOA, INC. · 2012. 12. 6. · ALCOA, INC. ADMINISTRATOR’S RECORD OF DECISION December 6, 2012 I. INTRODUCTION

5

3. NEPA Claims

The Court rejected arguments that BPA violated NEPA by preparing a categorical

exclusion rather than an Environmental Impact Statement (EIS) on the power sale. Alcoa

at 794–96. The Court held that BPA correctly invoked the relevant categorical exclusion

in the 2009 Alcoa ROD as well as explaining the reasons for its reliance on the

categorical exclusion and BPA’s decision to satisfy NEPA through a categorical

exclusion was not arbitrary and capricious. Id.

III. POLICY DISCUSSION

The Agreement will provide numerous benefits, as more fully described in the next

sections. At the outset, however, understanding the reasonableness of the

Administrator’s decision requires consideration of two key economic factors and a

practical assessment of two businesses conducting arm’s length negotiations with the

goal of reaching a final agreement that provides value to both parties:

1. Sales to Alcoa will have a downward impact on rates for future rate periods.

Given expected economic conditions in the power market for the next several years, the

IP rate is likely to remain well above the market price of power for quite some time. See

infra section IV.b. During this time, BPA will earn greater revenues from selling 300

aMW of power to Alcoa than it would from selling that power on the market. The

economic advantage of making this sale will keep BPA’s rates lower than they would

have been otherwise for the next several rate periods and better enable BPA to recover its

costs. Therefore, even though BPA is not statutorily obligated to maximize profit, BPA’s

decision to offer this Agreement will promote BPA’s ability to achieve the “lowest rates

possible consistent with sound business principles” and meet its cost-recovery

responsibilities. Federal Columbia River Transmission System Act of 1974, 16 U.S.C.

§§ 838–838h, 838g; Northwest Power Act, 16 U.S.C. § 893e(a)(1).

2. The Agreement will guarantee a revenue stream based on the IP rate, the

statutorily defined rate for DSI sales.

Assuming the Agreement is performed for its entire term, BPA will receive a guaranteed

revenue stream based on the IP rate. The IP rate is established pursuant to BPA’s

statutory rate-making authority and is currently adjusted every two years. BPA’s ability

to adjust the rate in this manner will mitigate any market uncertainties in the longer term

and support BPA’s Treasury payment obligation and statutory obligation to recover its

costs. BPA’s statutory authority to adjust the IP rate for power service provided under

the Agreement is unaffected by the Agreement.

3. A shorter term contract was not possible given Alcoa’s access to more

attractive alternative power supplies for a shorter term.

Page 9: ADMINISTRATOR’S RECORD OF DECISION POWER SALES AGREEMENT OFFER TO ALCOA, INC. · 2012. 12. 6. · ALCOA, INC. ADMINISTRATOR’S RECORD OF DECISION December 6, 2012 I. INTRODUCTION

6

Because market prices for energy are currently below the IP rate, Alcoa has access to

other power suppliers that are willing to offer prices and terms that are more favorable to

Alcoa than those offered by BPA. In negotiations, Alcoa maintained that it could make a

market purchase for seven years that would be preferable to purchasing from BPA. BPA

staff found that assertion to be credible. Thus, negotiations quickly turned to the

possibility of a ten year contract—even though Alcoa would have preferred a still longer

term—which would allow BPA to earn greater revenues during the first two to five years

of the contract and provide a predictable revenue stream during the later years.

Ultimately, the Administrator determined that the ten-year term of the Agreement serves

BPA’s business interests and the interest of BPA’s preference customers.

IV. THE EQUIVALENT BENEFITS DETERMINATION FOR THE PERIOD

BEGINNING JANUARY 1, 2013, THROUGH SEPTEMBER 30, 2022

BPA developed the Equivalent Benefits Test in response to Pacific Northwest Generating

Cooperative v. Department of Energy (PNGC I), 550 F.3d 846 (9th Cir. 2008), amended

on denial of reh’g, 580 F.3d 792 (9th Cir. 2009), and Pacific Northwest Generating

Cooperative v. Bonneville Power Administration (PNGC II), 580 F.3d 828 (9th Cir.

2009), amended on denial of reh’g, 596 F.3d 1065 (9th Cir. 2010), to determine whether

a power sale to serve a DSI customer is consistent with sound business principles. The

EBT is a tool used by the Administrator to determine whether the economic benefits to

BPA of serving the DSI load are forecast to equal or exceed BPA’s cost of serving the

load during the period of service. See Alcoa ROD at 8–9; see also 20.5 aMW Power Sale

to Port Townsend Paper Company for the Period November 15, 2009 through December

31, 2009, Administrator’s Record of Decision, released November 13, 2009 [hereinafter

Port Townsend ROD].

BPA’s EBT evaluation shows that BPA can supply firm power to Alcoa for the proposed

term under most water conditions. In determining its forecast of positive net benefits

from providing service to Alcoa for the full term of the contract, BPA followed the steps

described below. As in prior EBT analyses, BPA’s methodology for making this

determination is based, to the extent possible, on modeling tools used in BPA’s rate

cases. The rate case process includes discovery, testimony, rebuttal testimony, and cross

examination prior to a final determination by the Administrator. BPA believes this

process enhances the reliability of the modeling tools.

a. Models and Data Used in EBT for the Agreement

In prior analyses of equivalent benefits, BPA employed rate case models and data from

the most current BPA rate proceeding. This was possible because prior EBTs resulted in

relatively short contract terms. Due to current market conditions, which have been

particularly impacted by low natural gas prices, the EBT analysis shows that the power

sale will provide economic benefits to BPA beyond the current rate period.

Page 10: ADMINISTRATOR’S RECORD OF DECISION POWER SALES AGREEMENT OFFER TO ALCOA, INC. · 2012. 12. 6. · ALCOA, INC. ADMINISTRATOR’S RECORD OF DECISION December 6, 2012 I. INTRODUCTION

7

As a consequence, this EBT extends beyond the range of the modeling tools and

methodologies used in the BP-12 rate proceeding. Therefore, BPA used data and

methodologies from the BP-12 rate proceeding for the EBT through September 30, 2013,

and thereafter, to the extent possible, BPA used values and methodologies from the REP-

12 rate proceeding through September 30, 2022, including escalation factors from

October 1, 2017, through September 30, 2022. The REP-12 rate proceeding followed all

the procedural safeguards of all other rate proceedings, such as discovery, testimony,

rebuttal testimony and cross-examination, as required by Section 7(i) of the Northwest

Power Act.

b. IP Rate Forecast Used in EBT for the Agreement

In prior analyses of equivalent benefits, BPA has assumed that IP rates remain unchanged

for the entire term of the Agreement. See Alcoa Extension ROD at 7–9. BPA does not

believe that this assumption is reasonable for a ten year contract term because holding the

IP rate static does not account for the effects of BPA’s updated natural gas price forecast

on the values of the secondary energy revenue credits, balancing power purchase

expenses, augmentation expenses and 4(h)(10)(c) credits used when projecting BPA’s

cost-based power rates. Therefore, in the EBT for the Agreement, BPA used an IP rate

forecast that relies on models and cost inputs consistent with the REP-12 proceeding,

which incorporates results of the completed 7(i) process, and agency decisions regarding

capital and program spending as of the completed 2010 Internal Program Review (IPR).

BPA has incorporated all assumptions as used in the REP-12 proceeding with the

exception of revisions impacted by the updated natural gas price forecast. BPA’s

methodology for determining the IP rate forecast is further explained in section IV.d

below.

c. BPA expects to be surplus during the Agreement Period

BPA does not forecast the need to make purchases specifically to serve Alcoa during the

Agreement under most water conditions. BPA has forecast a need to make some power

purchases, including some normal “balancing” purchases in some months, to meet its

total load obligations during the remainder of FY 2013 through September 30, 2022,

particularly under critical water conditions.2

BPA’s most recent load and resources studies are contained in the 2011 Pacific Northwest

Loads & Resources Study (the “2011 White Book”), which forecasts loads and resources

for both the federal system and the region as a whole for the 10-year period (Operating

Years (OY) 2012–2021). BPA is forecast to have a surplus on an average annual basis

under the middle 80 percent of historical water conditions for OY 2012 through OY 2021

2 Balancing purchases are market purchases that BPA makes either before or within a particular month in

order to balance its forecast load and resource position within that month. Whether BPA makes any

balancing purchases, and in what amounts, is dependent, among other things, on updated water flow

forecasts which inform the amount of hydroelectric generation that can be expected in the month, and on

within-month weather conditions impacting BPA customer load levels.

Page 11: ADMINISTRATOR’S RECORD OF DECISION POWER SALES AGREEMENT OFFER TO ALCOA, INC. · 2012. 12. 6. · ALCOA, INC. ADMINISTRATOR’S RECORD OF DECISION December 6, 2012 I. INTRODUCTION

8

as illustrated in Figure 1 below.3 The 2011 White Book forecast includes 340 aMW of

service to the DSIs through September 30, 2017. Using the same studies used to compile

the 2011 White Book, the values for the average middle 80% water conditions in OY 2022

and OY 2023, are 1,243 aMW and 1,090 aMW of surplus power, respectively.

Figure 1 – Excerpt from 2011 White Book

2011 White Book at 39, tbl.8; see also Exhibits 11–12 at 104–11.

The term of the Agreement includes: 7 months in OY 2013, all months in OY 2014 through

OY 2022; and 2 months in OY 2023. The 300 aMW of power that will be sold to Alcoa

under the Agreement represents approximately twenty-two percent of the forecast

surpluses. As also illustrated, the 2011 White Book reflects a deficit on an average annual

basis under extremely low water conditions, the 1937-Critical Water Conditions, during

OY 2012 through OY 2021 respectively, and does so assuming 340 aMW of service to the

DSIs through September 30, 2017. See 2011 White Book at 39.

While BPA has established a portion of its costs for the period of the BP-12 rate

proceeding based on 1937-Critical Water Conditions, the secondary energy revenue

credits, balancing power purchase expenses and 4(h)(10)(c) credits for the same period

were set based on average values for the 70 water years. See BP-12-FS-BPA-03A at

138–139 (regarding Critical Water Conditions); BP-12-FS-BPA-04A at 45–46, tbls.19 &

3 Operating Year (OY) in the 2011 White Book is the 12-month period August 1 through July 31. For

example, OY 2012 is August 1, 2011, through July 31, 2012.

Page 12: ADMINISTRATOR’S RECORD OF DECISION POWER SALES AGREEMENT OFFER TO ALCOA, INC. · 2012. 12. 6. · ALCOA, INC. ADMINISTRATOR’S RECORD OF DECISION December 6, 2012 I. INTRODUCTION

9

20, (regarding Secondary Sales revenues and Balancing Purchase costs); BP-12-FS-BPA-

04A at 40, tbl.16 (regarding 4(h)(10)(c) credits).

For rate design and rate calculation purposes Power Services set power rates by

allocating the costs of resources to loads and assumes firm resource availability under

critical water. If firm resources are inadequate, it is assumed that the shortfall will be met

by augmentation purchases, with these costs being recovered from both Slice and Non-

Slice customers. When computing the PF and IP rates, additional adjustments are made

to account for secondary energy revenue credits, balancing power purchase expenses and

4(h)(10)(c) credits, which are based on average values for the 70 water years. While this

is the approach used for rate setting purposes, Power Service’s marketing decisions in its

typical operations are seldom conducted based on hydro generation under critical water

conditions. The approach used in the EBT analysis is more aligned with expected

conditions, and how Power Services would actually serve the Alcoa load, and is therefore

a reasonable approach.

In sum, this analysis of the Equivalent Benefits Test is reasonably based on BPA’s

foregoing forecasts of for OY 2013 through OY 2021 in the 2011 White Book (Average

Middle 80% Water Conditions) and BPA’s Final Proposals in the BP-12 and REP-12 rate

proceedings. BPA does not anticipate the need to alter its purchasing strategy for the

power sold to Alcoa during the term of the Agreement.

Some parties expressed concern about BPA’s use of the above forecasts in the EBT. See,

e.g., WGMT at 1 (“Under critical streamflow and the bottom 10% of water conditions,

BPA faces an energy deficit that could exceed 400 MW. With a contract extending nearly

ten years, the risk associated with energy deficits and the associated rate impacts are

transferred to preference customers.”). For the most part, these concerns are the same as

those raised in connection with the prior 2009 Agreement. As was the case in that

proceeding, BPA has fully considered relevant information. See Alcoa at 790 (rejecting

the argument that BPA was arbitrary and capricious in its consideration of how weather

and water flows would affect its profits during the Initial Period of the 2009 Agreement

and holding that BPA “gave adequate consideration to these matters”). Moreover, BPA

has explained above why its assumptions in this connection are reasonable and

appropriate. Finally, commenters’ concerns about the additional risk posed by the ten

year term of the Agreement are addressed below in section V.a.

d. Economic benefits to BPA will equal or exceed costs for the period of the

Agreement

BPA forecasts that the economic benefits it will accrue from the sale of 300 aMW of firm

power to Alcoa at the IP rate, under the Agreement, will exceed by approximately

$89,905,111.00 the forecasted benefits BPA could otherwise obtain from selling that

power into the market. See Attachment A, tbls.3–8. BPA notes that more than half of

these benefits ($48,633,782) are projected to accrue between the beginning of the

Agreement and the end of BPA’s next rate period (September 30, 2015). See Attachment

A, tbl.6. Thus, the Agreement provides a stable revenue stream to hedge against low

Page 13: ADMINISTRATOR’S RECORD OF DECISION POWER SALES AGREEMENT OFFER TO ALCOA, INC. · 2012. 12. 6. · ALCOA, INC. ADMINISTRATOR’S RECORD OF DECISION December 6, 2012 I. INTRODUCTION

10

natural gas and electricity prices and any associated low secondary revenues throughout

the next rate period. This stable revenue stream continues throughout the entirety of this

Agreement, further hedging against variability in BPA’s secondary revenues by fixing a

guaranteed revenue stream and helping to make BPA’s rates more stable and predictable.

Consistent with BPA’s EBT methodology established in the Alcoa ROD and the Port

Townsend ROD, BPA’s projected monthly revenues are determined by multiplying the

heavy load hour (HLH) and light load hour (LLH) energy entitlements and demand

entitlement by their respective IP rate components for each month. This analysis uses the

IP-12 energy and demand rates estimated by the Rates Analysis Model (RAM) and

adopted in the BP-12 rate proceeding through September 30, 2013. Thereafter, BPA’s

updated forecast of IP rates follows the methodology and inputs established in the REP-

12 rate proceeding (REP-12).4 Forecasted IP rates from FY 2014 to FY 2022 were

recalculated in the Long-Term Rates Model (LTRM) using the inputs for REP-12 and

revised surplus energy revenues, balancing purchase expenses, augmentation expenses,

and 4(h)(10)(c) credits estimated by RiskMod for FY 2014–FY 2017. These updated

values for 4(h)(10)(c) credits from RiskMod were based on updated spot market

electricity prices (modeled by AURORA) associated with BPA’s updated natural gas

price forecast discussed in Attachment B.

Surplus energy revenues, balancing purchase expenses, augmentation expenses, and

4(h)(10)(c) credits for FY 2018–22 were derived by escalating the FY 2017 values using

the Common Agency Assumption5 forecast for inflation, plus 2%, as was done in the

REP-12 proceeding. See REP-12-FS-BPA-01 at 69. The monthly–diurnal shape

computed for FY 2012–13 in the BP-12 case was then imposed upon the annual rate

forecast from the LTRM to create a monthly–diurnal forecast for the IP rate through the

10-year term. The annual growth rate implied by the change in the annual IP rate was

applied to the known monthly-diurnal rates for FY 2012–13 from BP-12. See

Attachment A, tbls.1 & 2 (reporting the IP rate forecast adopted in REP-12 and the IP

rate forecast used in the EBT analysis for the Agreement).

BPA has calculated revenues under the Agreement based on a sale of 300 aMW of firm

power each hour to Alcoa under the IP rate schedule beginning January 1, 2013, and

ending September 30, 2022. See Attachment A, tbl.3. The energy and demand

entitlements are the projected amounts to be sold by diurnal period each month in the

Agreement. Since under the Agreement BPA expects to make 300 aMW available each

4 The BP-14 Initial Proposal, released on November 14, 2012, contains an updated forecast that was

developed for the upcoming rate case. Because this forecast was developed for the purpose of setting rates

over a two year period and includes assumptions that are less conservative than those that went into the

EBT, this forecast is less suitable for use in the EBT for the Agreement. In the interest of due diligence,

however, BPA conducted an EBT analysis using the Initial Proposal numbers and determined that using

this updated forecast in the EBT for the Agreement would not result in a shorter contract term. In fact, the

forecast based on the Initial Proposal numbers showed a substantial increase in EBT benefits. Thus, the

release of the Initial Proposal numbers does not affect BPA’s decision to use the REP-12 forecasts for this

EBT analysis. 5 The Common Agency Assumption is a BPA forecast of various financial variables that is used by the

Agency to produce a consistent economic view of the future.

Page 14: ADMINISTRATOR’S RECORD OF DECISION POWER SALES AGREEMENT OFFER TO ALCOA, INC. · 2012. 12. 6. · ALCOA, INC. ADMINISTRATOR’S RECORD OF DECISION December 6, 2012 I. INTRODUCTION

11

month, 300 megawatts (MW) is the monthly demand amount specified in Table 3.

BPA’s projected monthly revenues are calculated using the IP rate components specified

in Table 3, and then accumulated as illustrated in Table 4. See Attachment A, tbls.3 & 4.

e. Forecast of revenues that would be obtained by selling an equivalent amount

of surplus power.

BPA routinely shapes its inventory to meet the need of its portfolio of contracts and sells

its surplus inventory in the Pacific Northwest power market as described in BPA’s BP-12

rate proceeding.6 Additionally, BPA routinely forecasts Mid-Columbia trading hub

(Mid-C) electricity prices consistent with the methodology described in the BP-12 rate

proceeding to value these purchases and sales.7

In the absence of selling 300 MW of firm power to Alcoa in every hour, BPA would have

one less firm power requirement sale in its aggregated portfolio load shape. Therefore,

BPA assumes, for purposes of the EBT analysis, that it would have 300 aMW of surplus

energy to sell in the market on an average annual basis. As illustrated in Attachment A,

Table 5, BPA has forecast the revenues it would otherwise obtain from the market for the

term of the Agreement using a forecast for the market price of electricity based on the

methodology used in the BP-12 rate proceeding, the incorporation of BPA’s updated

natural gas price forecast, and the extension of the rate case methodology through

September 30, 2022. See Attachment B, fig.1 (illustrating BPA’s updated natural gas

price forecast as compared to other recent forecasts of natural gas prices).

BPA determined its net benefit of serving Alcoa at the IP rate for each month by

subtracting the forecasted opportunity cost of foregone surplus energy revenues detailed

in Attachment A, Table 5, from the projected IP revenues described in Attachment A,

Table 4. BPA’s net benefit, before accounting for the benefits associated with

adjustments described in section IV.f below, is illustrated in Attachment A, Table 6.

f. Calculation of the net financial value of tangible economic benefits of selling

power to Alcoa which would not be obtained by selling an equivalent amount

of power on the market.

Consistent with the methodology described in the 2009 Alcoa ROD and the Port

Townsend ROD, BPA has identified a number of tangible economic benefits to BPA that

would be achieved by selling 300 MW to Alcoa during the term of the Agreement which

would not be achieved by selling an equivalent amount of power on the market. BPA

conducted an economic analysis to determine the net value of those benefits.

6 For a more complete description of the operating risk factors BPA faces in the course of doing business,

refer generally to the Power Risk and Market Price Study in the BP-12 rate proceeding; and specifically to

section 2.5.2 and section 2.6.3 for surplus energy sales and revenue. See BP-12-FS-BPA-04 at 37–39; 47–

49. 7 BPA employed its electricity price forecast for multiple purposes in the BP-12 rate proceeding as outlined

in the Power Risk and Market Price Study. The study also details how BPA established its forecast of Mid-

C electricity prices in the BP-12 rate proceeding. See BP-12-FS-BPA-04 at 15–36.

Page 15: ADMINISTRATOR’S RECORD OF DECISION POWER SALES AGREEMENT OFFER TO ALCOA, INC. · 2012. 12. 6. · ALCOA, INC. ADMINISTRATOR’S RECORD OF DECISION December 6, 2012 I. INTRODUCTION

12

1. Value of Reserves

Like Alcoa’s previous contracts, the Agreement requires Alcoa to make supplemental

operating reserves for power system contingencies available to BPA during the contract

period. Such reserves would not be available from making a typical market sale. Sales at

the IP rate reflect the value of BPA’s right to obtain supplemental operating reserves.8

Specifically, the energy rate tables in the IP-12 rate schedule adopted in the BP-12 rate

proceeding include a $0.94 per MWh credit for the value of these reserves. For this EBT,

BPA used the value of reserves credit from the BP-12 rate proceeding for the EBT

through September 30, 2013, and thereafter, BPA used the value of reserves credit from

the REP-12 rate proceeding through September 30, 2022. Both the energy rate tables in

the IP-12 rate schedule adopted in the BP-12 rate proceeding and the REP-12 rate

proceeding include a $0.94 per MWh credit for the value of these reserves.9 Therefore,

BPA’s net benefit above compares a surplus power sale to a sale of power at the IP rate

with reserves. BPA adjusted for this in each month through FY 2022 by adding back a

value of reserves that provides an equal and opposite offset to the $0.94 per MWh credit

for the value of reserves in the IP-12 rate schedule. In other words, BPA has increased

the IP rate by the value of reserves credit for purposes of this analysis so that the

comparison to a surplus sale into the market is on an “apples to apples” basis. See

Attachment A, tbl.7a.

2. Avoided Transmission and Ancillary Services Expenses

When BPA makes a sale to a DSI, that DSI customer covers the cost of transmission and

ancillary services through their own transmission contracts. Market prices, on the other

hand, assume power is delivered by the seller to the Mid-Columbia trading hub (Mid-C);

thus, the seller pays for the cost of transmission to that delivery point.

Power Services (PS), the organization within BPA that is responsible for the marketing of

federal power, must pay the transmission and ancillary services costs to move surplus

power to the Mid-C delivery point in order to realize the full market value for its surplus

sales. PS maintains an inventory of transmission products and services to deliver the

surplus power it intends to sell. However, this transmission product inventory is not

sufficient to deliver all of the surplus power PS might sell under all load and resource

conditions, especially during periods of high stream flows. As a result, there is a subset

of load and resource conditions under which PS would incur incremental costs for

transmission and ancillary services to deliver incremental surplus energy sales. The

incremental transmission and ancillary services costs are avoided when BPA sells power

to the DSIs because DSIs contract for their own transmission and ancillary services. The

planned transmission and ancillary services expenses to address both the expected

8 Sales at the IP rate require the provision of the DSI Minimum Operating Reserve – Supplemental. See

2012 Power Rates Schedules and General Rate Schedule Provisions, October 2011, at 21. The Agreement

is a sale at the IP rate and, accordingly, Alcoa is required to make such supplemental operating reserves

available to BPA, as specified in section 6.1 and Exhibit E to the Agreement. 9 For the purposes of this EBT analysis, BPA has not forecast a change in the value of reserves credit to be

included in future IP rate schedules.

Page 16: ADMINISTRATOR’S RECORD OF DECISION POWER SALES AGREEMENT OFFER TO ALCOA, INC. · 2012. 12. 6. · ALCOA, INC. ADMINISTRATOR’S RECORD OF DECISION December 6, 2012 I. INTRODUCTION

13

expenses and their uncertainty were addressed in the WP-10 and BP-12 rate proceedings

and are expected to be similarly addressed in each subsequent BPA rate proceeding.10

PS valued these avoided transmission and ancillary services costs for the period of the

Agreement using the same methodology employed in the BP-12 rate proceeding to

establish the total costs and risks associated with PS’s inventory of transmission products

and services.11

For this EBT analysis, BPA has not forecast a change in the tariff costs

even though there is a likelihood of a transmission rate increase sometime before

September 30, 2022, especially considering BPA’s recently proposed transmission rate

increase for the next rate period.12

BPA believes that this approach will produce the most

conservative results under the EBT analysis.

In these computations, both fixed, take-or-pay costs and variable incremental

transmission and ancillary services costs were computed under 3,500 load and resource

conditions for each month. Incremental transmission and ancillary services costs were

computed by comparing the amount of surplus energy available to the monthly excess

amount of firm transmission products in the PS inventory.

BPA continues to value avoided transmission and ancillary services costs for the entire

period of the Agreement using the tariff costs adopted by BPA’s Transmission Services

organization in the BP-12 rate proceeding.13

These tariff costs were applied to the

amount of surplus energy in excess of the PS transmission products inventory. Total

monthly transmission and ancillary services costs were computed assuming no service to

the DSIs and DSI service at 480 aMW continuing from January 1, 2013, through

September 30, 2022.14

The average total monthly expense values of the 3,500 games

were computed with and without service to the DSIs and the differences were taken to

determine the avoided PS transmission and ancillary services costs when PS makes these

IP sale(s) to the DSIs. For purposes of this analysis, Alcoa has been allotted 62.5% in

each month through September 2022, as illustrated in Attachment A, Table 7b. This

10

For further information on BPA’s methodology for addressing planned transmission and ancillary service

expenses, refer to Revenue Requirement Study, WP-10-FS-BPA-02 at 13-28; Risk Analysis and Mitigation

Study WP-10-FS-BPA-04 at 30–31. See also Power Revenue Requirement Study Documentation, BPA-12-

FS-BPA-02A at 29 tbl.3A, line 121; Power Risk and Market Price Study, BP-12-FS-BPA-04 at 42–43. 11

The megawatt amounts of surplus energy for FY 2013–FY 2017 were computed using RiskMod. The

megawatt amounts of surplus energy were extended beyond FY 2017 by using megawatt amounts of

surplus energy for FY 2016 (non-planned outage year for CGS) for FY 2018, FY 2020, and FY 2022 and

megawatt amounts of surplus energy for FY 2017 (planned outage year for CGS) for FY 2019 and FY

2021. 12

For additional information on the proposed transmission rate increase, see generally BP-14 Initial

Proposal, released Nov. 14, 2012, available at http://www.bpa.gov/Finance/RateCases/BP-

14RateAdjustmentProceeding/Pages/Initial-Proposal.aspx. See also Transmission, Ancillary and Control

Area Service Rate Schedules, BP-14-E-BPA-10, released Nov. 14, 2012. 13

For the purposes of this EBT analysis, BPA has not forecast a change in the tariff costs that may be

adopted in future BPA rate proceedings. 14

The current assumption for DSI service of 480 aMW includes 320 aMW for Alcoa, 20 aMW for Port

Townsend Paper Company, and 140 aMW for Columbia Falls Aluminum Company. These amounts may

vary depending on the amount defined in the individual DSI power sales contracts.

Page 17: ADMINISTRATOR’S RECORD OF DECISION POWER SALES AGREEMENT OFFER TO ALCOA, INC. · 2012. 12. 6. · ALCOA, INC. ADMINISTRATOR’S RECORD OF DECISION December 6, 2012 I. INTRODUCTION

14

percent allotment represents Alcoa’s portion of the total MW of DSI service assumed

during the period of the Agreement.

3. Demand Shift

The Demand Shift, as discussed in previous EBT analyses, assumes that the DSIs would

not operate in the absence of BPA service. See 2009 Alcoa ROD at 44, 68–70. In its

draft EBT analysis for the Agreement, BPA reduced the benefits of the Demand Shift to

zero because BPA believed that Alcoa would continue to operate in the absence of BPA

service since current market conditions suggest that it is possible for Alcoa to maintain

operations through another supplier if BPA was unable to supply Alcoa’s Intalco smelter.

In such circumstances, the demand shift would not materialize because the Intalco load

could not be considered incremental based solely on BPA’s ability to provide service.

In its comments filed on the draft Agreement, Alcoa disagreed with BPA’s conclusion,

stating that BPA “misunderstands the nature of aluminum smelter operations” and

believes that consideration of the demand is justified and would support extending the

term even beyond the present EBT protection and perhaps warrant extending the term

beyond ten years.” AAIP12 0072, Alcoa Intalco Works (Alcoa) at 19. Thus, Alcoa

requested that BPA include the demand shift benefit in its EBT analysis. Alcoa at 20.

BPA declines to do so. BPA understands that continuing or discontinuing smelter

operations are often based on factors unrelated to the condition in the power market.

However, the EBT is largely geared toward considerations relevant to the power market.

More importantly, since the EBT already supports the ten year term of the Agreement

that the Administrator is willing to offer without the inclusion of the demand shift

benefit, consideration of the issue is essentially moot.

g. Conclusion of Equivalent Benefits Test

Attachment A, Table 8, illustrates that the financial benefits BPA expects to receive from

selling 300 aMW at the IP rate to Alcoa during the period of the Agreement (from

January 1, 2013 through September 30, 2022) exceed the forecasted revenues that BPA

would otherwise obtain from selling the same amount of power on the wholesale

electricity market by approximately $89,905,111.00.

V. RESPONSE TO COMMENTS: SPECIFIC CONTRACT ISSUES

This section responds to comments regarding specific terms of the Agreement.

a. Whether the ten year term of the Agreement is reasonable and consistent

with sound business principles.

Summary of Comments

Many of the comments offered by preference customers and interest groups centered on

the risks associated with the ten-year term of the Agreement. See AAIP12 0073, Canby

Page 18: ADMINISTRATOR’S RECORD OF DECISION POWER SALES AGREEMENT OFFER TO ALCOA, INC. · 2012. 12. 6. · ALCOA, INC. ADMINISTRATOR’S RECORD OF DECISION December 6, 2012 I. INTRODUCTION

15

Utility (Canby); AAIP12 0069, Industrial Customers of Northwest Utilities (ICNU);

AAIP12 0064, Northwest Requirements Utilities (NRU); AAIP12 0067, Western

Montana Electric Generating & Transmission Cooperative, Inc. (WMGT); AAIP12 0068,

Seattle City Light (Seattle); AAIP12 0070, Public Power Council (PPC); and AAIP12

0071, Pacific Northwest Generating Cooperative (PNGC).

A primary concern, raised by several commenters, is the risk that BPA’s market

forecasts, which are the basis of BPA’s EBT, will prove incorrect. ICNU states:

BPA has forecast that under certain market conditions, it will obtain

economic benefits, but almost half the benefits accrue during the first two

years of the contract. This places significant risk on BPA if current gas

price forecasts prove to be inaccurate.

ICNU at 2. WMGT echoes this concern, stating that BPA’s conclusion that revenues will

exceed those expected from the wholesale power market over the ten year term is “highly

questionable.” WMGT at 2. PNGC notes that “BPA can be fairly certain of the range of

power prices for the next year or two but, by 2022, things become murky.” PNGC at 2.

Commenters also expressed concern about BPA’s forecasts of water conditions. See,

e.g., PPC at 3 (stating that “BPA’s assertion that it can serve Alcoa out of BPA’s existing

inventory over most water conditions only increases BPA’s risks”).

Because of the uncertainty associated with long term forecasts, several commenters

suggest that if BPA elects to enter into a contract with Alcoa, it should be for a shorter

term. See, e.g., NRU at 2, PNGC at 2. In their view, a shorter term contract would

mitigate the risk associated with the principle that the farther out one goes in time, the

more unknown variables could come into play with the potential for significant adverse

consequences. NRU recommends that the term be no longer than five years, while

PNGC suggests that two years and nine months would be an acceptable term. See NRU

at 2; PNGC at 2.

Alcoa, in contrast, believes that BPA’s use of the EBT artificially and unfairly truncates

the term of the contract and the term should be extended to the point that the EBT

forecasts only a small benefit to BPA. Alcoa at 13–14.

BPA’s Position

Offering a ten-year term for a sale of power to Alcoa at the IP rate is reasonable and

consistent with sound business principles for the following reasons: (1) a ten-year

contract is consistent with the statutory framework designed by Congress; (2) the EBT

analysis forecasts that at the end of ten years BPA will have derived a significant

financial benefit from the contract; (3) a sale at the IP rate provides a guaranteed revenue

stream based on the IP rate and, due to BPA’s rate-making requirements, will help to

assure that BPA recovers its costs; (4) BPA would be unable to obtain a shorter term

contract due to Alcoa’s ability to obtain preferable arrangements from other suppliers;

and (5) the Agreement will provide operational benefits to BPA.

Page 19: ADMINISTRATOR’S RECORD OF DECISION POWER SALES AGREEMENT OFFER TO ALCOA, INC. · 2012. 12. 6. · ALCOA, INC. ADMINISTRATOR’S RECORD OF DECISION December 6, 2012 I. INTRODUCTION

16

Discussion

1. A ten year contract is consistent with the statutory framework

designed by Congress.

When it enacted the Northwest Power Act, Congress understood that aluminum smelting

and other then-existing directly served industries were, for the large part, electric power-

intensive operations. See H.R. Rep. No. 96-976, pt. 1, at 28–29 (1980). At the time of

enactment, DSI customers accounted for approximately 3400 MW (approximately one-

third) of the Administrator’s total load obligation. Id. at 29.

In order to provide planning certainty for those customers with respect to their power

supply needs, the Northwest Power Act provided that the Administrator would be

required to offer an “initial long term power contract” based on the amount of power

BPA was supplying pursuant to the contract in existence immediately prior to enactment.

Northwest Power Act, 16 U.S.C. §§ 839–839h, 839c(d)(1)(B); 839c(g)(1). These

contracts were anticipated to be contracts that would not exceed 20 years in duration. 16

U.S.C. § 839c(g)(1); 832d(a). In response, the Administrator offered, and BPA’s

customers accepted, 20-year power sales contracts.

As to what would occur after expiration of the initial contracts, Congress left that

decision to the Administrator’s discretion. As confirmed by the Ninth Circuit on more

than one occasion, the Administrator is authorized, but not required, to sell power to

DSIs, consistent with other statutory requirements, when in his business judgment it is

appropriate to do so. See, e.g., PNGC II at 1073 (“BPA is certainly authorized to sell

power to the DSIs at the IP rate. But that authority . . . is cabined by its obligation to

‘operate with a business-oriented philosophy.’”)(citation omitted). In this instance, the

Administrator was faced with the expiration of Alcoa’s 2009 Agreement, fully

appreciating that the 2009 Agreement resulted in very significant economic benefits to

BPA relative to market. He considered the results of staff’s EBT analysis, and

determined that it was in BPA’s economic interests to pursue negotiating a contract for

the sale of power to Alcoa.

After deciding to pursue a power sales agreement with Alcoa, the Administrator has

broad discretion to negotiate appropriate terms and conditions for such a sale pursuant to

contracting authority provided by statute. See Bonneville Project Act of 1937, 16 U.S.C.

§§ 832–832j, 832a(f) (Administrator is authorized to enter into contracts “upon such

terms and conditions . . . as he may deem necessary”); see also Alcoa at 792 (“While in

certain extreme circumstances we may conclude that BPA has strayed too far afield from

business like operations, in the ordinary case we will not usurp BPA’s judgment

regarding whether to sell surplus power to DSIs, or on what terms.”)(citation omitted).

This authority extends to negotiating the length of the power sales agreement. Given the

economic benefits provided by the Agreement, as discussed more fully below, it is

plausible to assume that a contract half the length of the initial DSI contracts

Page 20: ADMINISTRATOR’S RECORD OF DECISION POWER SALES AGREEMENT OFFER TO ALCOA, INC. · 2012. 12. 6. · ALCOA, INC. ADMINISTRATOR’S RECORD OF DECISION December 6, 2012 I. INTRODUCTION

17

contemplated by Congress would not be inconsistent with the intent of Congress when it

enacted the Northwest Power Act and could be within the Administrator’s discretion.

Despite PNGC’s suggestion that Congress and the courts have contemplated a “phasing

out” of DSI service, PNGC at 3, BPA finds no evidence to that effect in the statutes,

legislative history, or court opinions. As noted above, when the Northwest Power Act

was passed, DSI customers accounted for approximately 3400 MW of the

Administrator’s total load obligation and BPA, at the time, was the only viable supplier in

the region given the then-existing power grid. Markets were not deregulated in order to

create greater competition among potential suppliers until many years after the passage of

the Northwest Power Act. It is far more likely that Congress assumed that much of that

load would continue to exist and that BPA would continue to supply power to the DSIs.

In conclusion, given the broad scope of his contracting, settlement, and compromise

authority, the particular term of a DSI contract (including the one establishing the length

of the contract) is well within the scope of the Administrator’s contracting discretion and

should be upheld unless it is arbitrary, capricious, an abuse of discretion, or otherwise not

in accordance with the law.15

2. The EBT analysis forecasts that at the end of ten years, BPA will have

derived a significant financial benefit from the contract.

The analysis conducted under the Equivalent Benefits Test shows that BPA is highly

likely to obtain revenues well in excess of a sale at market prices for the first three to five

years of the Agreement. For a full and detailed discussion of the EBT methodology and

results, see section IV. These projected increased revenues from Alcoa will reduce the

PF rate for at least the next two to three rate periods.

A number of commenters point out that any forecast inherently contains some degree of

uncertainty and the actual state of the market in the future depends on events that are not

yet known. In their comments, preference customers tend to focus on the possibility that

the market could be higher than the IP rate in the later years of the contract and BPA

might not, therefore, maximize its revenue stream. However, the opposite could be true

and the IP could remain higher than anticipated for a longer period than contemplated by

EBT analysis. If, for example, demand for power remains flat due to a continuing

depressed economy, the market price for power could be lower than forecast by the EBT

over the long term. Similarly, if gas supplies continue to increase as they have in recent

years, that could also have a long term effect of lower than anticipated power prices

because the marginal cost resource for the West Coast is currently the gas-fired

15

It is also important to note that long term contracts for aluminum smelters are a common industry

practice. For example, the New York Power Authority’s power contract with Alcoa’s Messena Plant is a

20 year contract with an option for an additional 10 years and Chelan County PUD has a17-year contract

with Alcoa to serve the Wenatchee Plant. See New Long-Term Power Supply Contract With Alcoa

Approved By N.Y. Power Authority Trustees (Dec. 16, 2008),

http://www.nypa.gov/press/2008/081216a.htm; Alcoa Reaches New Renewable Power Deal for

Wenatchee, WA Smelter (July 15, 2008),

http://www.alcoa.com/global/en/news/news_detail.asp?pageID=20080715005215en&newsYear=2008.

Page 21: ADMINISTRATOR’S RECORD OF DECISION POWER SALES AGREEMENT OFFER TO ALCOA, INC. · 2012. 12. 6. · ALCOA, INC. ADMINISTRATOR’S RECORD OF DECISION December 6, 2012 I. INTRODUCTION

18

combustion turbine. Thus, the stable revenue stream generated by the IP rate is, as

discussed elsewhere, an effective risk mitigation strategy.

More importantly, however, while the preference customers state general concerns about

risk and uncertainty, they have not demonstrated that BPA’s reliance on these forecasts is

misplaced. The fact that the future is uncertain does not make the decision to offer the

Agreement unreasonable nor does it create any kind of legal infirmity because the Court

does not expect more from BPA than it has done here. BPA does not need to have

“perfect information before it takes any action.” N. Carolina v. Fed. Energy Regulatory

Comm’n, 112 F.3d 1175, 1190 (D.C. Cir. 1997) (quoting Dep’t of the Interior v. Fed.

Energy Regulatory Comm’n, 952 F.2d 538, 546 (D.C. Cir. 1992)). “In the face of

‘serious uncertainties,’ an agency need only ‘explain the evidence which is available, and

. . . offer a rational connection between the facts found and the choice made.’” Id.

(citation omitted). As explained above, BPA has met this standard.

Moreover, there is nothing unusual about the ten-year term for the Agreement that BPA

has considered in this proceeding. BPA routinely relies on long-term forecasts to

evaluate long-term transactions, whether between itself and its customers or others. For

example, BPA relied on forecasts that looked forward 17 years to test the reasonableness

of the 2012 Residential Exchange Program Settlement Agreement (“REP Settlement”),

which settled several controversial components of the REP until 2028. Based on long-

term projections of BPA’s costs, market conditions, loads, and other factors, the

Administrator was able to conclude that the REP Settlement was in the region’s interests,

lawful, and met the agency’s other identified goals, and agreed to sign the REP

Settlement with six investor-owned utilities, a variety of interest groups and parties, and

many preference customers (including many of the preference customers that have

submitted comments in this proceeding).

Finally, the preference customers have not identified any defects in the forecasts BPA is

relying on to evaluate the Agreement. This is not surprising because the underlying data

BPA used to evaluate the Agreement was thoroughly vetted in the REP-12 proceeding,

the proceeding that BPA established to evaluate the REP Settlement. No party identified

any fundamental problems with BPA’s long-term forecasts in the REP-12 proceeding

and, similarly, no party in this proceeding has identified any problems with the data that

BPA is using in its EBT analysis.

Commenter Alcoa contends that the Administrator’s decision to offer ten years of service

“artificially truncates the term” of the Agreement. Alcoa at 13. That claim is incorrect.

The Administrator has considered the risks of the ten-year term and, accordingly, elected

to limit the term of the contract offer to ten years, when the EBT shows a significant

$89,000,000 cushion in net financial benefits, rather than take the risk of extending the

contract term further. In previous applications of the EBT, the Administrator was willing

to allow benefits to decline further, but previous EBTs resulted in much shorter contract

terms. Limiting the term of the Agreement to ten years is another way of mitigating the

risk associated with the longer term of this contract, as opposed to previous ones.

Page 22: ADMINISTRATOR’S RECORD OF DECISION POWER SALES AGREEMENT OFFER TO ALCOA, INC. · 2012. 12. 6. · ALCOA, INC. ADMINISTRATOR’S RECORD OF DECISION December 6, 2012 I. INTRODUCTION

19

3. A sale at the IP rate provides a guaranteed revenue stream based on

the IP rate that will help to assure that BPA recovers its costs.

Under the Agreement, Alcoa will purchase power from BPA at the IP rate, which is the

statutorily defined rate for the sale of Industrial Firm Power to DSI customers.16

The IP

rate is adjusted every time BPA sets its power rates by conducting a rate proceeding

pursuant to Section 7(i) of the Northwest Power Act. In section 1.1 of BPA’s Tiered Rate

Methodology, BPA committed itself to set power rates every two years through the 2028

ending date of its preference customers’ Contract High Water Mark Contracts. See

Tiered Rate Methodology, TRM-12S-A-03, Sept. 2009, at 1–2. Therefore, BPA will be

able to assure that its costs are recovered through the IP rate, even in the event that

market or resource conditions change.

The IP rate is also subject to various risk mitigation policies that BPA has in place. For

example, BPA’s rates include planned net revenues for risk, a portion of which are

recovered through the IP rate. The IP rate is also subject to various Cost Recovery

Adjustment Clauses that go into effect when certain triggers are met, e.g., financial

reserves drop to a point that could jeopardize cost recovery and Treasury repayment.

For planning purposes, selling a fixed amount of power over a fixed period of time and

receiving predictable revenues at the IP rate is a sound business strategy. It insulates

BPA from exposure to prices in the wholesale power market which, unlike the IP rate

level, BPA has no control over. As noted above, BPA must periodically establish rates

that are “based upon the Administrator’s total system costs” and “are sufficient to assure

repayment of the Federal investment in the Federal Columbia River Power System over a

reasonable number of years after first meeting the Administrator’s other costs.” 16

U.S.C. §§ 839e(a)(2)(A), (B).

Some comments suggest that BPA should forego this opportunity to lock in a long-term

source of predictable revenues, effectively proposing a “wait and see” approach. See,

e.g., PNGC at 2 (suggesting a term of two years and nine months instead of ten years).

Such an approach does not represent a sound business practice. As noted elsewhere, such

comments focus only on the market situation where the IP rate is less than the price of

power in the market. In such situations, the commenters argue, BPA would miss an

opportunity to maximize revenues. However, it is also possible that market conditions

like those that currently exist could continue or recur. In that situation, the “wait and see”

16

See 16 U.S.C. § 839e(c). BPA notes that some parties have raised issues about whether Alcoa will be

charged a rate that is above the rate paid by BPA’s preference customers. To the extent that this is still a

question, BPA notes that, as has been noted by the Ninth Circuit, the IP rate is developed pursuant to the

formula for developing the IP rate that is clearly prescribed by Congress in sections 7(c) and 7(b)(2) of the

Northwest Power Act, 16 U.S.C § 839e(c), a formula that should result in an IP rate that is higher than the

PF Tier 1 rate. First, the IP is subject to an adder known as the industrial margin. See 16 U.S.C. §

839e(c)(2). Second, the IP rate is subject to further increase due to rate protection afforded to preference

customers with respect to recovering costs associated with the Residential Exchange Program, which

provides benefits to residential and small farm customers of regional investor-owned utilities. 16 U.S.C. §

839e(b)(2).

Page 23: ADMINISTRATOR’S RECORD OF DECISION POWER SALES AGREEMENT OFFER TO ALCOA, INC. · 2012. 12. 6. · ALCOA, INC. ADMINISTRATOR’S RECORD OF DECISION December 6, 2012 I. INTRODUCTION

20

approach places the agency at risk of under-recovering the revenues it had forecast in a

prior rate proceeding from secondary market sales. BPA believes that it is reasonable to

avoid that potential outcome by locking in sufficient revenues to recover costs through a

firm power sale priced at the IP rate. As previously indicated, Alcoa was unwilling to

enter into a contract for a term less than ten years and, in fact, sought a longer-term

contract.

4. A shorter term contract was not possible due to Alcoa’s ability to

obtain preferable arrangements from other suppliers.

As described above, a number of comments indicated that a term well short of ten years

would better mitigate risks in the outyears and create greater certainty. These comments

recommend that BPA revise the contract to make the term much shorter than ten years,

usually the three to five year range. See, e.g., NRU at 2 (suggesting a term of five years);

PNGC at 2 (suggesting a term of two years, nine months).

Without conceding the argument that a short term is not always better from a risk

mitigation standpoint, the suggestion that BPA could dictate the term of the contract in

this instance is greatly oversimplified. Currently, market prices are well below the IP rate

and BPA stands to maximize revenues for the next several years by selling at the IP rate

rather than selling on the open market. That means Alcoa, which has access to power

providers other than BPA, could have and would have obtained a better price and terms

in a market transaction for a term less than ten years in the absence of a BPA contract.

As noted in its comments, Alcoa is not interested in a BPA contract because it enjoys

paying an IP rate that is considerably higher than the market prices that are expected to

continue for the next several years. Instead, Alcoa is only willing to accept that situation

in exchange for the certainty of a long-term power supply at a cost based rate that may or

may not be lower than market prices during the later years of the contract. Alcoa at 5.

Thus, Alcoa has concluded, based on its own business judgment, that the Agreement

must have a term of at least ten years in order for it to make sense to forego the more

favorable market prices at which it could presently acquire power. Id. (stating that a ten

year term is the minimum period that would allow Alcoa to amortize its expected capital

investments in the Intalco plant).

In consideration of both the likelihood of significant financial benefits to BPA in the first

several years of the transaction and the business interests of Alcoa, negotiations quickly

turned to the possibility of a ten-year contract that would protect BPA’s ability to

maximize revenues in the early years and provide a stable revenue stream in the later

years. Given Alcoa’s position and current market conditions, BPA continues to believe

there were only two potential outcomes: a ten year agreement or no agreement at all.

In sum, while sales to DSI customers like Alcoa are now discretionary, that does not

mean Alcoa is a “captive” customer of BPA that must accept whatever terms and

conditions BPA chooses to dictate. To the contrary, Alcoa has access to the same

markets that BPA might be selling into in the absence of this contract. Without this

Page 24: ADMINISTRATOR’S RECORD OF DECISION POWER SALES AGREEMENT OFFER TO ALCOA, INC. · 2012. 12. 6. · ALCOA, INC. ADMINISTRATOR’S RECORD OF DECISION December 6, 2012 I. INTRODUCTION

21

contract, Alcoa would be paying less and BPA’s secondary revenues would be lower. It

was only possible to proceed with this negotiation process by reckoning with the reality

that Alcoa had some amount of bargaining power due to its access to other suppliers

willing to charge prices significantly lower than the IP rate.

5. The Agreement will provide additional operational benefits to BPA.

Alcoa commented that BPA has declined to take into account the operational advantages

that sales to Alcoa (and other DSIs) have provided since the 1930s when determining the

term of its proposed sale to Alcoa. See Alcoa at 18. Although Alcoa is correct that BPA

has not included the value of such operational benefits in the EBT, the Administrator has

nonetheless considered these benefits and they have bolstered his decision to offer a ten-

year term. As described elsewhere in this section, the EBT analysis is not the sole

determinative factor in the Administrator’s decision to offer a ten-year term. The

operational benefits which can be provided by Alcoa to BPA support the Administrator’s

decision to offer Alcoa a ten-year term by offsetting some of the risk posed by the length

of the term and providing additional assurance that the Agreement will have an overall

benefit to BPA and therefore to BPA’s customers.

As BPA has readily acknowledged, DSI load has historically provided value to BPA in

connection with the Administrator’s statutory obligation to assure an adequate, efficient,

economical, and reliable power supply, by providing the Administrator with flexibility to

help manage the complexities and uncertainties of marketing large quantities of federal

power. See 2009 Alcoa ROD at 72–82. BPA has referred to these operational benefits as

“intangible benefits” in past RODs. These operational benefits include: 1) operational

flexibility during oversupply events; 2) balancing reserves; and 3) potential demand

response arrangements.

First, the sale to Alcoa will provide BPA with a flat, continuously operating load, which

acts to level the shape of BPA’s overall load. Alcoa’s load is also able to increase or

decrease with a fair degree of certainty when called upon, providing valuable operational

flexibility to BPA. This ability helps BPA during periods of oversupply, when large

volumes of water flows in the Columbia River system and large amounts of wind

generation connected to BPA’s transmission system require BPA and federal dam

operators to balance both the federal power system and transmission system to meet

environmental requirements (protection of endangered salmon listed under the

Endangered Species Act) and the provision of transmission services. The concentration

of wind resources within BPA’s balancing area authority has created operational

challenges during these high water and high wind events. BPA is taking steps to manage

generation during these events, but adding load (particularly during light load hours) is

another way to help bring the system into balance during oversupply events.17

Alcoa has

the ability to consume more power, within plant operating limits, during light load hours,

thereby producing more aluminum at night and less during the day. Alcoa has already

provided such benefits on a short-term basis during the 2009 Agreement. At BPA’s

17

For more information about BPA’s oversupply management and wind integration efforts, see BPA’s

website at http://www.bpa.gov/Projects/Initiatives/Pages/default.aspx.

Page 25: ADMINISTRATOR’S RECORD OF DECISION POWER SALES AGREEMENT OFFER TO ALCOA, INC. · 2012. 12. 6. · ALCOA, INC. ADMINISTRATOR’S RECORD OF DECISION December 6, 2012 I. INTRODUCTION

22

request, Alcoa purchased additional surplus power and began consuming approximately

25 MW more per hour in light load hours from 11 pm to 6 am. By offering Alcoa a long

term contract BPA will be able to pursue these operational benefits in the future.

Second, continuing BPA’s long-time relationship with Alcoa provides potential

opportunities for BPA to purchase additional contingency reserves from Alcoa. During

the spring of 2011 and 2012, Alcoa provided support for BPA’s efforts to deal with

oversupply by making additional load interruptible (in excess of the contingency reserve

requirement in the 2009 Agreement). Alcoa at 17.

Third, BPA and Alcoa have discussed the potential for additional collaboration on

demand response projects. BPA is currently pursuing several demand response pilot

projects that do not include Alcoa.18

Alcoa’s operational flexibility makes it an ideal

candidate for demand response, especially as it relates to industrial process load control.

In conclusion, the Administrator has considered the operational benefits of service to

Alcoa when deciding to offer the ten year Agreement.

Final Decision

For all of these reasons, the record demonstrates that providing service to Alcoa for a

term of ten years is a reasonable business decision.

b. Whether the termination and curtailment provisions of the Agreement are

appropriate.

Comments

A number of parties raised concerns regarding Alcoa’s curtailment and termination rights

under the Agreement. Several of BPA’s preference customers (PNGC, PPC, Canby,

NRU and ICNU) argued that Alcoa’s termination and curtailment rights in the Agreement

were unacceptable risks and should either be amended or eliminated from the Agreement.

This sentiment is typified by PNGC’s statement:

Alcoa would be able to terminate the contract for “any reason” at any

time, provided it pays limited liquidated damages tied, in part, to the price

of aluminum at the time on the London Metal Exchange. Alcoa would

also be able to terminate if it becomes subject to certain environmental

regulations or emissions requirements. In addition, Alcoa would be able to

twice “curtail” some or all of its power purchases during the contract for a

period of up to two years, subject only to limited liquidated damages.

It should go without saying that these extensive termination and

curtailment rights would significantly undermine the take-or-pay nature of

18

For more information about BPA’s demand response program, see BPA’s website at

http://www.bpa.gov/Energy/N/Smart_Grid-Demand_Response/index.cfm.

Page 26: ADMINISTRATOR’S RECORD OF DECISION POWER SALES AGREEMENT OFFER TO ALCOA, INC. · 2012. 12. 6. · ALCOA, INC. ADMINISTRATOR’S RECORD OF DECISION December 6, 2012 I. INTRODUCTION

23

the new contract. The provisions would also create unacceptable risk and

uncertainty for Bonneville, significantly undermining the value of

Bonneville entering into the contract in the first place.

PNGC at 5; see also Canby at 1, ICNU at 2, PPC at 1–2, NRU at 3.

Along these same lines, ICNU argued that if Alcoa were to have these curtailment and

termination rights that BPA should similarly enjoy broad termination and curtailment

rights:

This will allow Alcoa to walk away but require BPA to continue selling

power to Alcoa in the event that conditions change, so that it becomes a

significant money losing transaction. BPA should alter the contract to

allow BPA to terminate, and reduce Alcoa’s ability to walk away from the

contract if market conditions change.

ICNU at 2.

BPA’s Position

Including these limited termination rights for Alcoa in return for the assurance of higher-

than-market revenues and long term stability is a sound business decision.

Discussion

First, the preference customers’ comments fail to recognize BPA’s termination rights,

which are found in section 19.2 of the Agreement. Section 19.2 includes rights to

terminate for Alcoa’s: (1) failure to pay, (2) failure to provide payment assurance, (3)

failure to maintain employment levels, (4) reselling of Firm Power, (5) failure to provide

a letter of credit, and (6) failure to provide documentation showing 35 million dollars in

capital investment to the plant. None of these termination rights require BPA to make

Alcoa financially whole by paying liquidated damages or providing any other form of

compensation to Alcoa. In contrast, all three of Alcoa’s termination rights require Alcoa

to provide notice ahead of termination, and to compensate BPA either by purchasing

power through the notice period or paying liquidated damages.

Second, the comments neither appear to recognize that these termination and curtailment

rights are the product of lengthy negotiations between Alcoa and BPA, nor do they

recognize the value that BPA receives in exchange for these rights. As BPA’s preference

customers are aware and Alcoa references in its own comment, the EBT shows that BPA

and Alcoa are entering into this contract at a time when the IP rate is significantly higher

than the market price of power. Alcoa at 5. On average, the IP rate is expected to remain

higher than market prices for more than seven years, according to BPA’s forecasts

included in the EBT. Given these circumstances, Alcoa could easily choose to forego

power service from BPA in order to purchase less expensive power from market

suppliers.

Page 27: ADMINISTRATOR’S RECORD OF DECISION POWER SALES AGREEMENT OFFER TO ALCOA, INC. · 2012. 12. 6. · ALCOA, INC. ADMINISTRATOR’S RECORD OF DECISION December 6, 2012 I. INTRODUCTION

24

BPA worked with Alcoa to negotiate an agreement that would be acceptable to both

parties because BPA believes that the Agreement will benefit both BPA and its

preference customers. In essence, BPA has asked Alcoa “to forgo the more favorable

market prices at which it could presently (and for some time) acquire power.” Id. In

exchange, Alcoa negotiated for several termination and curtailment rights but also agreed

to BPA’s requested liquidated damages provision. These liquidated damages provisions

are designed to assure that BPA will receive a significant percentage of the EBT’s

forecast benefits even if Alcoa exercises one of the termination rights afforded it by the

Agreement. By protecting the benefits BPA will accrue during the first three years of the

Agreement, BPA protects the PF rate paid by BPA’s preference customers.

Lastly, BPA notes that these termination and curtailment rights are in fact an

improvement over the termination and curtailment rights Alcoa held under the 2009

Agreement. Under the 2009 Agreement, which had a potential term of seven years or

longer, Alcoa would not have been liable for any liquidated damages during any period

of curtailment. Furthermore, Alcoa held termination rights that were either more liberal

than or equivalent to the termination rights in this Agreement. 19

Final Decision

Alcoa’s termination and curtailment provisions will included in the Agreement without

changes.

c. Whether section 15.2, Uncontrollable Forces, should be adjusted in response

to comments received.

Comments

NRU comments regarding section 15.2:

Under section 15.2, Uncontrollable Forces includes, “any failure of Alcoa’s

production, distribution or transmission facilities that prevents Alcoa from taking

Firm Power delivered to the Point of Receipt.” This language is far too broad

regarding Alcoa’s “production”. This provision should be modified to clearly

define what circumstances constitutes an uncontrollable force regarding Alcoa’s

production.

NRU at 2.

19

The previous contract allowed Alcoa to terminate for any reason during the first several years of the

contract with six month’s notice, with liability limited to 90 percent of the Firm Power obligated under the

contract for the first three months of the notice and then only for power taken in the last three months

period and Alcoa could then choose to purchase power amounts at or below the Firm Power amount the last

three months of the notice period. Under the terms of the previous contract, during the last five years of the

contract (had the contract continued), Alcoa was allowed the same termination right it enjoys after

September 30, 2015, in the Agreement: requiring twelve months’ notice of termination and compensation

to BPA for any Firm Power amount not taken during those twelve months.

Page 28: ADMINISTRATOR’S RECORD OF DECISION POWER SALES AGREEMENT OFFER TO ALCOA, INC. · 2012. 12. 6. · ALCOA, INC. ADMINISTRATOR’S RECORD OF DECISION December 6, 2012 I. INTRODUCTION

25

BPA’s Position

BPA believes that this contract provision adequately defines what circumstances

constitute an uncontrollable force.

Discussion

The Uncontrollable Forces provision is an agency standard provision which has been

developed and approved pursuant to BPA’s internal processes. A nearly identical

provision is used in BPA’s Regional Dialogue contracts, including those signed by

NRU’s members. Additionally, BPA disagrees with NRU that the language is far too

broad. Though not mentioned in NRU’s comments, the events allowed as uncontrollable

forces under section 15 are very limited. Specifically, section 15.2 states that the event

must be:

[B]eyond the reasonable control of, and without the fault or negligence of

the Party claiming the Uncontrollable Force that prevents that Party from

performing its contractual obligations under this Agreement and which by

exercise of that Party’s reasonable care, diligence, and foresight such Party

was unable to avoid.

Based on the successful past use of this agency standard clause, combined with the

protections afforded by the clause that were not mentioned in NRU’s comments, BPA

believes that this contract language is adequate and need not be changed.

Final Decision

Section 15.2 will not be changed.

d. Whether section 5.5, No Purchases from Third Parties During Curtailment,

should be changed in response to comments received.

Comments

NRU expressed concern regarding section 5.5, No Purchases from Third Parties During

Curtailment, of the Agreement, stating:

Under section 5.5 regarding curtailments, the contract states that, “Alcoa shall not

make any market purchases from third party suppliers to replace all or any

portion of the amount curtailed.” It is unclear why Bonneville would limit this

clause to market purchases. Alcoa should not be allowed to make any power

purchases, including but not limited to market purchases, if it is in a period of

curtailment. Therefore, NRU advises Bonneville to replace the term “market

purchase” with “power purchase.”

Page 29: ADMINISTRATOR’S RECORD OF DECISION POWER SALES AGREEMENT OFFER TO ALCOA, INC. · 2012. 12. 6. · ALCOA, INC. ADMINISTRATOR’S RECORD OF DECISION December 6, 2012 I. INTRODUCTION

26

NRU at 3–4.

BPA’s Position

BPA agrees with NRU’s comment.

Discussion

In order to eliminate any ambiguity, section 5.5, No Purchases from Third Parties During

Curtailment, will be changed to read:

During any period of curtailment, Alcoa shall not make any power

purchases from third party suppliers to replace all or any portion of the

amount curtailed.

Final Decision

BPA will make the changes stated above.

e. Whether section 19.2, BPA’s Right to Terminate, should be changed in

response to comments received.

Comments

NRU commented on section 19.2, BPA’s Right to Terminate, specifically, section 19.2.7:

Under section 19.2.7, Alcoa must demonstrate that it has invested 35 million

dollars, or more, in capital projects at the Intalco Plant by September 30, 2019, or

Bonneville may terminate the contract. In order to put the appropriate parameters

around such a requirement, Bonneville should include a starting date for such

investment.

NRU at 4.

BPA Position

BPA agrees with NRU’s comment.

Discussion

In order to eliminate any ambiguity, section 19.2.7 will be changed to read:

Alcoa fails to provide BPA with documentation showing that it has invested 35

million dollars or more in capital projects at the Intalco Plant between January 1,

Page 30: ADMINISTRATOR’S RECORD OF DECISION POWER SALES AGREEMENT OFFER TO ALCOA, INC. · 2012. 12. 6. · ALCOA, INC. ADMINISTRATOR’S RECORD OF DECISION December 6, 2012 I. INTRODUCTION

27

2013 and September 30, 2019. In order to facilitate the administration of this

provision, Alcoa shall provide BPA with a yearly accounting of capital project

expenditures at the Intalco Plant on September 1 of every year under this

Agreement. BPA reserves the right to determine, at its own discretion, the

adequacy of the documents provided by Alcoa under this section.

Final Decision

BPA will change the provision as shown above.

f. Whether clarification of the effect of a court ruling that partially invalidates

the Agreement is needed.

Comments

PNGC asked BPA to clarify the effects of a court ruling on section 4.3 and 18.7 of the

contract. Specifically, PNGC states:

Section 4.3 of the draft new contract addresses termination of the contract if a

court were to invalidate the contract. The section addresses what happens in the

event of a complete invalidation of the contract but it is not clear what would

happen if a court were to only partially invalidate the contract. Further, it is not

clear how section 4.3 is meant to interact with section 18.7, which addresses

severability.

Should the parties decide to go forward with the new contract, they should clarify

sections 4.3 and 18.7.

PNGC at 6.

BPA Position

The contract language as drafted adequately addresses the effects of a partial invalidation

of the Agreement. BPA clarifies its reasons for including both provisions below.

Discussion

Section 4.3, Termination Upon Court Opinion or Other Ruling, reads as follows:

Notwithstanding anything in this Agreement to the contrary, in the event

that the Ninth Circuit issues an opinion or other ruling that holds, or that

otherwise renders, this Agreement unlawful and prevents BPA from

performing its obligations hereunder, this Agreement shall terminate upon

issuance of the Court’s mandate, unless the Court further stays the

issuance of the mandate or otherwise extends the period that BPA can

Page 31: ADMINISTRATOR’S RECORD OF DECISION POWER SALES AGREEMENT OFFER TO ALCOA, INC. · 2012. 12. 6. · ALCOA, INC. ADMINISTRATOR’S RECORD OF DECISION December 6, 2012 I. INTRODUCTION

28

provide service to Alcoa or unless this Agreement can be amended to

comply with the Court’s holdings. The Parties agree that they will confer

prior to issuance of the mandate regarding issues arising from or related to

any such Court order. BPA agrees not to challenge any effort by Alcoa to

obtain a stay of the mandate or otherwise extend the period that BPA can

provide service to Alcoa.

The contract language specifies that this section applies only if the Ninth Circuit holds

the Agreement unlawful and prevents BPA from continuing to serve Alcoa under the

Agreement. PNGC is correct that this provision does not address a “partial invalidation”

of the Agreement.

On the other hand, section 18.7 applies to situations where specific terms of the

Agreement are invalidated by a court but other portions of the agreement remain

undisturbed, i.e., a “partial invalidation” of the Agreement. Section 18.7, Severability,

states:

If any term of this Agreement is found or rendered invalid or

unenforceable by a court of competent jurisdiction, then, unless that term

is not severable from all other provisions of this Agreement, such

invalidity or unenforceability shall not otherwise affect any remaining

lawful obligations under this Agreement. Neither Party shall be liable to

the other Party for any damages associated with any term being severed

from this Agreement.

BPA does not believe it is feasible to clarify what would happen if a court were to only

partially invalidate this contract at this time. The effect on performance of the contract

would be dependent on which term of the agreement was found invalid or unenforceable.

Finally, BPA does not understand PNGC’s comment that it is not clear how section 4.3 is

meant to interact with section 18.7. The two provisions were intentionally drafted to

address different circumstances, and therefore the interaction of the two provisions

should not be problematic.

Final Decision

Sections 4.3 and 18.7 are sufficiently clear and will not be changed.

g. Whether Section 18.11, Waiver of Damages, should be included in the

Agreement.

Comments

Several parties object to the inclusion of section 18.11, Waiver of Damages. A common

concern among the commenters is that including a damages waiver provision will leave

BPA with no ability to recover funds from Alcoa in the event that the Agreement is

Page 32: ADMINISTRATOR’S RECORD OF DECISION POWER SALES AGREEMENT OFFER TO ALCOA, INC. · 2012. 12. 6. · ALCOA, INC. ADMINISTRATOR’S RECORD OF DECISION December 6, 2012 I. INTRODUCTION

29

invalidated, and thus deprives BPA’s customers of a remedy. See, e.g., PNGC; PPC;

NRU; WMGT.

BPA’s Position

BPA believes that inclusion of the damages waiver provision is mutually beneficial to

both the agency (and thus its preference customers) and Alcoa.

Discussion

The Ninth Circuit recently upheld the use of a nearly identical damages waiver provision

in the 2009 Agreement, stating that the damages waiver provision falls within BPA’s

claim-settling authority and does not violate either statutory or constitutional provisions.

Alcoa, 698 F.3d at 791–92. Further, because BPA explained in the ROD that the damage

waiver protects BPA from claims that Alcoa may raise against BPA, the Court held that,

“[i]t is not our place to second-guess the agency’s considered judgment regarding the

balance of risks embodied in a damage waiver or similar release or settlement provision.”

Id. at 792.

The rationale for including the damages waiver provision in the 2009 Agreement is

largely applicable today, and may be even more compelling in light of current market

conditions. As noted in Alcoa’s comments, BPA is not Alcoa’s only power supply

option. Alcoa at 5. Alcoa is willing to pay the IP rate, even though the IP rate is above

market, in exchange for the certainty of a long-term power supply. If, however, the

Agreement is invalidated two or three years from the beginning of power deliveries,

Alcoa may feel that it has a valid grievance with respect to lost market opportunities

during the initial years of the Agreement and lost protection from the vagaries of the

market in the long term. Any Ninth Circuit opinion invalidating the Agreement would

most likely be issued within two to three years of the beginning of the contract. During

this period, market forecasts indicate that BPA should receive revenues well in excess of

those it would otherwise receive from a market sale. Therefore, Alcoa will almost

certainly have paid higher prices for power in reliance on the validity of the Agreement.

Moreover, given expected market conditions for the next several years, the damage

waiver provision is more likely to protect the interests of BPA’s preference customers

than Alcoa’s. There can be only be one challenge to the decision to offer the contract, and

that challenge must commence within ninety days of the date the Agreement is executed.

See Blachly-Lane Elec. Coop. Ass’n v. U.S. Dep’t of Energy, 79 Fed. Appx. 975, 977 (9th

Cir. 2003); see also 16 U.S.C. § 839f(e)(1)(B) (providing that power sales are final

agency actions subject to judicial review). Consequently, the validity of the Agreement

will most likely be decided within the first two to three years of the contract term. As

noted above, during that two to three year period, Alcoa is likely to pay higher-than-

market prices for power service, and the preference customers’ rates will be lower as a

result.

Page 33: ADMINISTRATOR’S RECORD OF DECISION POWER SALES AGREEMENT OFFER TO ALCOA, INC. · 2012. 12. 6. · ALCOA, INC. ADMINISTRATOR’S RECORD OF DECISION December 6, 2012 I. INTRODUCTION

30

NRU suggests that this damage waiver is not a two-way provision because “there are not

likely to be third parties suing Alcoa over the terms of the contract.” NRU at 2. This

comment misunderstands the intent of the damage waiver provision. The damage waiver

is a provision in a contract between two parties, Alcoa and BPA. It is designed to

provide mutual protection. If the Ninth Circuit finds the contract unsustainable, Alcoa

could allege that it was injured by BPA’s actions and attempt to raise a claim in the Court

of Federal Claims. At this time, it is not possible to know whether such a claim would

have merit, but even an ultimately unsustainable claim would require BPA to expend

time, money, and human resources to address it. The damage waiver provision allows

the Administrator to avoid such a prospect by agreeing that, if the contract is set aside as

unlawful, the parties walk away without a right to claim damages against the other. The

Administrator finds nothing inappropriate about such a negotiated result in light of his

broad contracting and settlement authorities. See supra section V.a.1 (discussing the

Administrator’s contracting authority).

PNGC supports its argument against the inclusion of the damages waiver by stating that

“if Bonneville undercharges Alcoa under the new contract at the expense of other

customers, then Bonneville could be unable to recover funds that rightfully belong to

other customers.” PNGC’s example is unpersuasive. Under the terms of the Agreement,

Alcoa will be charged the IP rate, which is the appropriate statutory rate for service to the

DSIs. 16 U.S.C. § 832e(c)(1). The Court has been very clear that any offer of service to

a DSI must be priced at the IP rate. PNGC I at 807 (“[I]f the agency chooses to offer

firm power to the DSIs . . . it must first offer them the IP rate.”). It is therefore

implausible that the Court would, at a later date, determine that BPA has “undercharged”

Alcoa under the Agreement by applying the very rate that the Congress has prescribed

and that the Court has endorsed as the sole basis for any initial offer. Since PNGC has

provided no credible support for its assertion that BPA could, as a matter of fact or law,

“undercharge” Alcoa by charging the IP rate, BPA sees no justification for eliminating

the damage waiver provision on that basis.

Final Decision

The inclusion of the damages waiver provision is a sound business decision and the

clause will be included in the Agreement.

h. Whether Section 11, Employment Levels, should be included in the

Agreement.

Comments

A number of commenters raised questions about BPA’s motives for including Section 11,

Employment Levels, in the Agreement. Canby commented, based on BPA’s press

release materials, that the purpose of the Agreement is ‘preserving hundreds of family-

wage jobs’ and ‘long term certainty to Alcoa and its employees.’” Canby at 2. PPC

points out that the Ninth Circuit has previously rejected “BPA’s attempts to use

employment levels to justify entering into contracts with the DSIs because Congress did

Page 34: ADMINISTRATOR’S RECORD OF DECISION POWER SALES AGREEMENT OFFER TO ALCOA, INC. · 2012. 12. 6. · ALCOA, INC. ADMINISTRATOR’S RECORD OF DECISION December 6, 2012 I. INTRODUCTION

31

not intend for BPA to consider such factors in deciding whether or not to sign a power

sales agreement with a DSI customer.” PPC at 4. PNGC also reminds BPA that it may

not enter into a new contract with Alcoa in order to preserve jobs at the Intalco plant.

PNGC at 4. PNGC states that “to the extent that this is the reason, or even part of the

reason, that Bonneville is considering entering into the new contract, Bonneville must

cease negotiations with Alcoa and decline to enter into the new contract.” Id.

BPA’s Position

To the extent that commenters imply that job creation is the actual basis for BPA’s

decision, they are incorrect. The Administrator has the discretion to include terms in the

DSI contracts that are not directly related to the tangible benefits included in the EBT

analysis.

Discussion

BPA agrees that the Ninth Circuit has held that creation of jobs, does not provide legal

justification for offering a power sale to the DSIs. However, the Court recently upheld

the validity of the 2009 Agreement, which contained an identical Minimum Employment

provision. The Court stated, in reviewing the 2009 Agreement that:

[W]e consider merely whether ‘the agency considered the relevant factors

and articulated a rational connection between the facts found and the

choices made,’ we do not second-guess its policy judgments.

Alcoa at 788 (citation omitted). The Court also found that BPA’s ROD “expressly

disclaimed reliance on job impacts as a factor in its decision and declined to include such

impacts in its Equivalent Benefits analysis.” Id. at 789. However, nothing in the opinion

states that BPA may not even broach the subject of employment in the contract as long as

BPA’s decision to make the sale is in accord with sound business principles. Id. at 792

(“[I]n the ordinary case, we will not usurp BPA’s judgment regarding whether to sell

surplus power to DSIs, or on what terms.”).

As BPA has thoroughly explained above, its decision to offer the Agreement is consistent

with sound business principles. The employment levels at the Intalco plant are not part of

BPA’s business justification for offering the Agreement. Rather, the Agreement is

supported by tangible, financial benefits to BPA which are forecast to exceed the cost of

providing service to Alcoa during the contract term, and therefore, the Agreement is

consistent with sound business principles.

Although supporting employment at the Intalco plant is not part of the business

justification for this Agreement, the Administrator is not precluded from considering the

numerous comments filed in support of this Agreement, many of which stress that very

point. For example, many comments expressed that the continued operation of Intalco is

valuable to the regional economy and the Ferndale community. See, e.g., AAIP12 0005,

Superintendent, Ferndale School District (“Intalco Works is enormously important to the

Page 35: ADMINISTRATOR’S RECORD OF DECISION POWER SALES AGREEMENT OFFER TO ALCOA, INC. · 2012. 12. 6. · ALCOA, INC. ADMINISTRATOR’S RECORD OF DECISION December 6, 2012 I. INTRODUCTION

32

health of our local economy.”); AAIP12 0057, Washington State Senator Doug Ericksen

(“This agreement is vital to the people of Whatcom County, and to the people of

Washington State. Alcoa at Ferndale provides 625 family-wage jobs in Northwest

Washington and over 1,800 indirect jobs in the region. The value of Intalco employee

wages, benefits, leave, etc. totals over $65 million, and Intalco’s contribution to

Washington’s GDP is over $210 million.”); AAIP12 0004, Northwest Workforce Council

(“The economic impact of the plant is vital to all of the communities in Whatcom County

and our local schools. Whatcom County’s unemployment rate continues to remain high,

7.7% in August, and Washington State’s unemployment rate is currently 8.6%. We

cannot afford to lose this plant or the family-wage jobs it provides.”). The Administrator

appreciates these comments and believes that, given the current economic situation, it

would not be appropriate for the Administrator to ignore concerns expressed by the

public and others regarding the economic well-being of the region.

Moreover, employment requirements are not unheard of in long-term contracts for power

supply to industrial customers. For example, the New York Power Authority’s power

sales contract for service to Alcoa’s Massena East smelter in New York State specifies

that Alcoa will maintain at least 900 jobs at their two Massena smelters. New Long-Term

Power Supply Contract With Alcoa Approved By N.Y. Power Authority Trustees (Dec. 16,

2008), http://www.nypa.gov/press/2008/081216a.htm.

Additionally, the employment requirement incentivizes Alcoa to take physical power

from BPA and not utilize its curtailment rights under the Agreement. As established in

Exhibit F of the Agreement, even if Alcoa were to curtail its power load down to zero,

Intalco would still be required to employ 120 people. As a result, Alcoa will be less likely

to curtail load at the Intalco Plant compared to its other aluminum smelters operating in

the United States that do not have the same provision working against them, due to the

additional continuing costs required by Exhibit F.

Final Decision

The Minimum Employment Requirements provision will be included in the Agreement.

i. Whether BPA should include the capital investment requirement in the

Agreement.

Comments

PPC commented on the “capital investment provision” which requires Alcoa to invest

$35 million in the Intalco Plant during the first seven years of the Agreement. See

Section 19.2.7. (providing that BPA may terminate the Agreement if Alcoa fails to

provide BPA with documentation showing that it has invested 35 million dollars or more

in capital projects at the Intalco Plant by September 30, 2019). PPC comments that:

Despite the Court’s admonishments, BPA appears to continue to rely on

factors that should be irrelevant to its consideration of this contract. . . .

[A]s a precondition for receiving service from BPA, Alcoa would be

Page 36: ADMINISTRATOR’S RECORD OF DECISION POWER SALES AGREEMENT OFFER TO ALCOA, INC. · 2012. 12. 6. · ALCOA, INC. ADMINISTRATOR’S RECORD OF DECISION December 6, 2012 I. INTRODUCTION

33

required to invest $35 million in the Intalco smelter. It is unclear how [this

requirement] would further BPA’s business interests or promote a

business-oriented philosophy.

PPC at 4.

NRU’s similar comment focuses on a recital included the Agreement which states that “if

Alcoa commits to expend strategic capital in excess of the capital expenditures required

in Section 19 that would require a period of amortization exceeding the remaining term of

this Agreement, the parties will consult concerning whether it might be in their mutual

interest to extend the term of this Agreement.” NRU at 3. NRU asserts that this recital

should be removed because BPA’s interest in whether Alcoa makes capital investments is

unclear. Id.

BPA’s Position

BPA has not relied on Alcoa’s capital investment as part of the legal justification for

offering the Agreement. BPA agreed to include the capital investment recital as part of

its negotiations with Alcoa. Both the capital investment provision and recital provide

additional assurance to BPA that Alcoa is motivated to continue to operate the Intalco

Plant for the duration of the Agreement, which BPA perceives as having economic value

to BPA.

Discussion

In response to PPC’s comment, BPA has not relied on Alcoa’s capital investment as part

of the legal justification for offering the Agreement. No benefits to BPA from Alcoa’s

capital investment are included in the EBT. BPA has required this investment

requirement as a means of Alcoa demonstrating a commitment to the long-term viability

of the plant and the continued benefit of this Agreement to BPA and its preference

customers. Alcoa will be far less likely to shut down the plant after investing additional

capital into it since Alcoa would then have to consider the capital invested in the plant as

a complete loss. This is one of the reasons why failure to maintain capital investment

requirement was included as a termination right for BPA after seven years (and not as a

“precondition for receiving service” as was incorrectly suggested by PNGC). According

to the EBT forecast, the market rate may become higher than the IP rate during the

seventh year of the Agreement. See Attachment A, tbl.6. In such conditions, if Alcoa is

not making investments to assure the long term stability of the plant then BPA has the

ability to terminate the contract if it would be economically advantageous to do so.

Lastly, PPC appears to be suggesting that each individual provision of a DSI contract

must further BPA’s business interests. BPA disagrees with this interpretation of the Ninth

Circuit’s holdings. As noted above, the Court has indicated the Administrator has

discretion to determine the terms of BPA’s agreements with DSIs, as long as overall

BPA’s decision to make the sale is in accord with sound business principles. Alcoa at

Page 37: ADMINISTRATOR’S RECORD OF DECISION POWER SALES AGREEMENT OFFER TO ALCOA, INC. · 2012. 12. 6. · ALCOA, INC. ADMINISTRATOR’S RECORD OF DECISION December 6, 2012 I. INTRODUCTION

34

792 (“[I]n the ordinary case, we will not usurp BPA’s judgment regarding whether to sell

surplus power to DSIs, or on what terms.”).

With regard to NRU’s comment about the recital, BPA included this recital as a result of

negotiations between Alcoa and BPA. During negotiations, Alcoa raised the question of

whether it would be possible to discuss a contract extension in the event that Alcoa has

made significant capital investments at Intalco, above the requirements of Section 19.2.7.

Rather than include a provision in the Agreement itself, the parties concluded that a

recital would be an appropriate way to memorialize the parties’ commitment to future

discussions in the event that an extension of the contract term is mutually beneficial to

both parties. It is difficult to see how an acknowledgement that some situations might

result in the parties to the Agreement talking to one another about certain matters has any

detrimental bearing on the exercise of business judgment.

Final Decision

Section 19.2.7 will be included in the Agreement and the recital concerning capital

investment will also be retained.

VI. RESPONSE TO COMMENTS: GENERAL POLICY COMMENTS

Comments also raised issues not specific to a particular contract provision, but which

instead dealt with more general policy concerns. Those comments are addressed in this

section.

a. Whether the EBT should be revised to measure actual benefits.

Comments

PNGC comments that the EBT should measure actual benefits to Bonneville, not just

forecasted benefits, and that Bonneville should be able to exit the contract if actual

benefits fail to materialize. PNGC at 4. PNGC goes on to suggest that BPA should re-

draft the EBT to provide for an ongoing analysis of the actual benefits of serving Alcoa

over the life of the contract and should modify the new contract to allow BPA to exit the

contract if there should cease to be a real net benefit to Bonneville at any time during the

life of the contract. PNGC at 5.

BPA’s Position

Implementation of PNGC’s suggestion would be inconsistent with sound business

principles.

Discussion

PNGC’s suggestion that BPA should provide for an ongoing analysis of the actual

benefits of serving Alcoa over the life of the contract and that BPA should modify the

Page 38: ADMINISTRATOR’S RECORD OF DECISION POWER SALES AGREEMENT OFFER TO ALCOA, INC. · 2012. 12. 6. · ALCOA, INC. ADMINISTRATOR’S RECORD OF DECISION December 6, 2012 I. INTRODUCTION

35

new contract to allow BPA to exit the contract if there should cease to be a real net

benefit to BPA at any time during the life of the contract is inconsistent with sound

business principles. As our preference customers are keenly aware, business contracts

are instruments that allocate risks between the parties negotiating them. Parties to a

business contract typically enter a contractual agreement based on the facts available and

forecasted at the time of contracting, and therefore, risk is allocated between the parties at

the time of the agreement. If BPA were to insist that it would bear none of the risk but

reap all of the rewards, BPA’s marketing opportunities would be largely eliminated.

Such an approach would reduce the Administrator’s discretion to make DSI sales to no

discretion at all, an absurd result that would be inconsistent with principles of statutory

interpretation. Negotiated contracts, as in this case, require the parties to deal with one

another in good faith to achieve mutually acceptable benefits and an equitable allocation

of risks, as this Agreement does.

Final Decision

BPA declines to implement PNGC’s suggestion because it would be inconsistent with

sound business principles.

b. Whether continued service to Alcoa will exacerbate PSANI transmission

congestion.

Comments

The City of Seattle expressed concerns that the Agreement would “perpetuate a power

delivery that exacerbates transmission congestion through the greater-Seattle area.”

Seattle then goes on to describe the Puget Sound Area Northern Intertie (PSANI)

transmission capacity limitations and concludes with the following:

Therefore, Seattle feels that it is essential that BPA, prior to entering into any

power sales agreement, determine that such sale will not exacerbate transmission

congestion in the region during the term of the agreement

Seattle at 2. Seattle also argued that Alcoa should be susceptible to PSANI curtailments

along with other Puget Sound area power customers.

BPA’s Position

BPA’s continued service to Alcoa will not exacerbate transmission congestion in the

Puget Sound region.

Discussion

The PSANI area consists of BPA’s network transmission facilities interconnected with

the electric systems of customers in the Puget Sound area and BPA’s Northern Intertie

(NI) facilities interconnected with the BC Hydro system to the north. BPA monitors the

Page 39: ADMINISTRATOR’S RECORD OF DECISION POWER SALES AGREEMENT OFFER TO ALCOA, INC. · 2012. 12. 6. · ALCOA, INC. ADMINISTRATOR’S RECORD OF DECISION December 6, 2012 I. INTRODUCTION

36

system operating limits (SOL) of the monitored facilities in the south to north direction to

determine if the SOL levels will be sufficient for the transactions using those facilities in

the operating hour. The transactions contributing to the SOL excedences of the monitored

facilities include south to north scheduled deliveries to Puget Sound Area customers

north of Covington and scheduled deliveries over the NI. The measures that are

monitored have been identified as the PSANI mitigation or congestion measures. A

PSANI congestion problem is a south to north problem that arises when multiple factors

interact at the same time to affect the power flow and the SOL in this direction. These

factors include: planned and/or unplanned facility outages; temperature; the forecasted

generation patterns in Puget Sound Area, the forecasted load in the Puget Sound Area,

and all of the scheduled deliveries in the south to north direction to serve the load in the

area and deliveries to Canada, taking into account any north to south deliveries (i.e.,

counterflows) from Canada.

BPA’s continued service to Alcoa will not exacerbate transmission congestion in the area

above existing firm uses for two reasons. First, the load level at Alcoa’s Intalco plant, by

itself, is not the source of the PSANI congestion. All deliveries of power in a south to

north direction contribute to the congestion problems in the area, including south to north

deliveries to serve Alcoa’s load. If Alcoa or any other load in the area acquires power

from the north, in most cases those counter flows help to alleviate any PSANI congestion

problems. However, even if Alcoa’s Intalco Plant were to be served by another power

marketer, that by itself is not likely to do anything to help relieve the area congestion.

Instead, BPA would continue to be obligated to manage the south to north deliveries to

any load in the area including Snohomish PUD, Seattle, BPA's transfer customers, Puget

Sound Energy or deliveries to Canada.

Second, Alcoa has a long-term firm transmission contract which is separate from the

Agreement. BPA has already concluded that even if BPA were not to serve Alcoa, the

Intalco Plant would continue to operate on power purchased at the market. In all

likelihood, that power would be purchased at Mid-C and transferred to the Intalco Plant

utilizing Alcoa’s existing firm transmission rights. Furthermore, even if the Alcoa load

disappears, Alcoa holds those transmission rights and would be able to permanently

transfer them to any eligible and willing buyer. Moreover, if any transmission capability

reverted to BPA and is available, BPA must release it to the market under its open access

transmission service policies. Since multiple factors contribute to the problem, and the

congestion is specific to all of the conditions that apply at the time, BPA cannot

definitively say that if Alcoa did not operate the plant, the congestion problem would

disappear. Therefore, entering into this Agreement is likely to have no incremental effect

on PSANI congestion.

BPA has worked closely with Puget Sound Energy, Snohomish PUD and Seattle City

Light (“Puget Sound Area customers”) on issues contributing to congestion in the PSANI

area, including coordinating planned maintenance outages to minimize impacts, and

undertaking efforts to encourage the Puget Sound Area customers to increase generation

in the area during periods of congestion. BPA, Seattle City Light and Puget have also

agreed to invest in transmission reinforcements in the area. In addition, BPA has

Page 40: ADMINISTRATOR’S RECORD OF DECISION POWER SALES AGREEMENT OFFER TO ALCOA, INC. · 2012. 12. 6. · ALCOA, INC. ADMINISTRATOR’S RECORD OF DECISION December 6, 2012 I. INTRODUCTION

37

conducted training for operations and technical staff of the Puget Sound Area customers

so all entities understand implementation and operation of the PSANI curtailment

procedures. BPA is continuing to work with the Puget Sound Area customers to increase

understanding of the interconnected systems and operations practices that will help to

meet the future service needs.

Additionally, in response to Seattle’s second comment, Alcoa is, in fact, affected by

PSANI related curtailments and has been curtailed for PSANI events in the past and will

continue to be curtailed when deemed necessary in the future, consistent with NERC

priorities and on a pro rata basis.

Final Decision

BPA’s continued service to Alcoa will not exacerbate transmission congestion in the

Puget Sound region.

c. Whether the Agreement should be BPA’s last contract for service to Alcoa.

Comments

PNGC suggests that if BPA decides to go forward with the Agreement, it should be the

last contract for service to Alcoa. PNGC at 3. PNGC asserts that this approach would

provide “adequate notice and certainty” to Alcoa, other DSIs, and other regional

stakeholders regarding DSI service going forward. Id. PNGC goes on to say that

“preference customers would have certainty that they no longer will have to live with the

specter of Bonneville attempting to subsidize BPA’s service to Alcoa through preference

rates.” Id.

BPA’s Position

Deciding that this will be the last contract for service to Alcoa would be an unreasonable,

unbusiness-like decision made without the benefit of consideration of relevant facts and

conditions.

Discussion

BPA does not understand how making a determination that this will be the last contract

with Alcoa would be anything other than arbitrary, capricious, and inconsistent with any

sound business principles. BPA’s approach to DSI service since PNGC II has been to

assess each contract individually, together with the facts available at the time in order to

make a reasoned decision on whether or not to offer the contract. The court recently

upheld this approach with respect to BPA service to Alcoa. See Alcoa at 791 (“BPA’s

explanations are plausible and rationally connected to the facts that were before it at the

time.”). Declaring that this will be the last contract with Alcoa would be the opposite of

assessing the business case for each contract. The Administrator will not foreclose the

Page 41: ADMINISTRATOR’S RECORD OF DECISION POWER SALES AGREEMENT OFFER TO ALCOA, INC. · 2012. 12. 6. · ALCOA, INC. ADMINISTRATOR’S RECORD OF DECISION December 6, 2012 I. INTRODUCTION

38

possibility of future power sales contracts with Alcoa when such future contracts may be

beneficial to BPA and its preference customers.

As for the “specter of Bonneville attempting to subsidize BPA’s service to Alcoa through

preference rates,” PNGC’s concerns are unsupported by the facts and record of this case.

First, under the EBT, BPA anticipates garnering substantially more revenue from the

Agreement than would otherwise be achieved so there is no basis upon which to claim

that there is a subsidy. Second, as reaffirmed in the recent Alcoa decision, the

Administrator may lawfully sell physical power to Alcoa at the IP rate. See, e.g., PNGC

II at 1073; Alcoa at 789. While BPA does not expect it to be the case for the duration of

this contract, the Court has further held that it is lawful for BPA to include the costs of

federal base system replacement resources in the PF rate, even if those resources are

purchased to meet DSI contract obligations. See Golden Nw. Aluminum v. Bonneville

Power Admin., 501 F.3d 1037, 1045–46 (9th Cir. 2007). In the recent Alcoa decision, the

Court held that there is no evidence “supporting PNGC’s claim that BPA entered into the

Alcoa Contract to subsidize Alcoa.” Alcoa at 789. The Court also rejected PNGC’s

argument that the terms of the 2009 Agreement required BPA to subsidize Alcoa’s rate

by providing a credit for Alcoa’s provision of contingency power reserves to BPA, as

required by statute, which explicitly requires that BPA obtain such reserves and provides

for a credit to the IP rate to reflect their value. Id. at 791; see also 16 U.S.C. §

839e(c)(3). BPA believes that the allegations regarding subsidies to Alcoa are

unfounded. It should also be noted that the revenues accruing from the prior sale to

Alcoa outpaced even the EBT projected financial benefits.

Furthermore, BPA notes that PNGC’s comment is premised upon a clearly misleading

restatement of Ninth Circuit case law. PNGC states:

As the Ninth Circuit clarified in PNGC I, although the Northwest Power

Act envisioned a phasing out of Bonneville service to DSIs after 2000,

Bonneville may, but is not obligated to, continue to provide service to

Alcoa and the other DSIs . . . .

PNGC at 3. The Ninth Circuit did not state in its PNGC I opinion that the Northwest

Power Act “envisioned a phasing out of Bonneville service to DSIs after 2000.” Rather,

the Court found that Congress’s use of the phrase “initial contract” gives rise to a

reasonable inference that other contracts may follow the initial long term agreements, and

held that BPA is authorized to offer additional contracts. PNGC I at 808–09. In addition,

PNGC provides no citation for its proposition that the Northwest Power Act envisioned a

phasing out of BPA service to DSIs after 2000. In fact, this proposition is contrary to the

legislative history cited by the Court in PNGC I to support its conclusion that BPA is

authorized, but not obligated, to offer additional contracts to the DSIs:

The House Interior Committee’s report on S. 885 states that “[s]ection

5(d)(1) authorizes [BPA] to sell power to its existing direct-service

industrial customers and requires [the agency] to offer to such customers

initial long-term power sale contracts.” H.R. Rep. No. 96-976, pt. 2, at 34

Page 42: ADMINISTRATOR’S RECORD OF DECISION POWER SALES AGREEMENT OFFER TO ALCOA, INC. · 2012. 12. 6. · ALCOA, INC. ADMINISTRATOR’S RECORD OF DECISION December 6, 2012 I. INTRODUCTION

39

(1980) (emphasis added). . . . The report goes on to explain that, in

addition to mandating that “[i]nitial long-term 20-year contracts are to be

offered by BPA” to the DSIs, “[s]ubsequent contract . . . are authorized

but not mandated. H. Rep. 96-976, pt.1, at 61 (1980).

Id. at 809.

Third, despite repeated allegations that BPA is attempting to subsidize Alcoa’s rate for

power through preference rates, the converse is actually closer to the truth. The statutory

rate directives set forth in section 7(c) of the Northwest Power Act assure that the IP rate

will continue to be higher than the rate paid by preference customers. Section 7(c)

provides that the IP rate is to be equal to the applicable wholesale rate (the rate paid by

preference customers), plus the industrial margin, less the value of reserves, plus any

section 7(b)(3) reallocation of the 7(b)(2) rate protection amount. The formula for

developing the IP rate in this manner is clearly prescribed by Congress in Sections 7(c)

and 7(b)(2) of the Northwest Power Act. See 16 U.S.C § 839e(c).

The IP rate increase for the industrial margin reflects the “overhead” costs that are paid

by industrial customers who purchase power from BPA’s preference customer utilities

and so such amounts are not even a part of BPA’s overall cost structure. The IP rate is

subject to further increase due to rate protection afforded to preference customers with

respect to recovering costs associated with the Residential Exchange Program, which

provides a benefit to residential and small farm customers of regional investor-owned

utilities. See 16 U.S.C. § 839e(b)(2). The IP and the PF-Exchange rate are both

formulated, in certain defined circumstances, to move costs associated with the

Residential Exchange Program away from preference customers.

For the foregoing reasons, BPA believes that the allegations regarding subsidies to Alcoa

are unfounded.

Final Decision

BPA will not make a determination that the Agreement is the last contract for service to

Alcoa. Further, BPA believes that the argument that the Agreement may result in

preference customers subsidizing the Agreement is unfounded, contrary to the

Agreement, and refuted by the record.

d. Whether BPA is offering the Agreement “solely because Alcoa sued the

agency on the Residential Exchange Settlement Agreement.”

Comments

PNGC states that “Bonneville should not offer Alcoa this contract solely because Alcoa

sued the agency on the Residential Exchange Settlement Agreement.” PNGC at 3.

Page 43: ADMINISTRATOR’S RECORD OF DECISION POWER SALES AGREEMENT OFFER TO ALCOA, INC. · 2012. 12. 6. · ALCOA, INC. ADMINISTRATOR’S RECORD OF DECISION December 6, 2012 I. INTRODUCTION

40

BPA’s Position

BPA is not offering the Agreement “solely” to dismiss Alcoa’s REP Settlement petition.

Alcoa’s agreement to dismiss its REP Settlement petition played only a minimal part in

the negotiations of this Agreement.

Discussion

BPA’s motivations for offering the Agreement are described in detail in the preceding

sections of this ROD. As described above, BPA expects to receive (at least) $42 million

in net revenue over the term of the Agreement, in addition to the various other

operational and risk mitigation benefits attributable to serving Alcoa’s load. It is for

these tangible reasons that BPA has decided to offer the Agreement to Alcoa.

An additional requirement of the Agreement is described in section 18.12, which requires

Alcoa to dismiss its current challenges to the REP Settlement and prohibits future

challenges to BPA’s decision to implement the REP Settlement. The REP waiver

provides value to BPA by removing some challenges to the REP Settlement pending

before the Ninth Circuit, thereby narrowing the issues the Court must consider. With

fewer petitioners challenging the REP Settlement, and fewer issues for the Court to

consider, the likelihood that the REP Settlement will be upheld by the Court increases.

Inclusion of the REP waiver is in BPA’s business interest as a sound exercise of the

Administrator’s settlement authority.

Certain commenters have apparently misconstrued BPA’s motives for including this

provision and allege that BPA’s “sole” rationale for offering Alcoa the Agreement is to

remove them from the pending REP litigation. This assertion is untrue.

BPA requested the inclusion of the REP waiver and dismissal during the course of the

negotiations. BPA does not believe Alcoa would have ultimately prevailed.

It would have made no practical sense for BPA to place the inordinate value on obtaining

the waiver that PNGC ascribes when it alleges the waiver was the “sole” motivation. By

the time the issue came up in negotiations, BPA had already fully briefed and responded

to every issue Alcoa raised in its own brief. Beyond that, the value from a legal

perspective is that certain issues that Alcoa had raised will no longer be present, allowing

the Court to render an opinion based on a somewhat smaller number of issues and

simplifying the challenges to the REP Settlement that the Court must hear.

However, even with the departure of Alcoa, the REP litigation will proceed to a decision

because of the presence of another active petitioner that raised many of the same issues

Alcoa raised. To propose that BPA would have offered Alcoa a ten year power

arrangement in order to simply narrow issues pending before the Court is illogical. In

effect, PNGC is criticizing BPA for including in the Agreement a requirement that Alcoa

dismiss its challenges to the REP Settlement, a settlement that regional parties (including

PNGC) spent over a year to develop and which ends a decade worth of litigation. The

Page 44: ADMINISTRATOR’S RECORD OF DECISION POWER SALES AGREEMENT OFFER TO ALCOA, INC. · 2012. 12. 6. · ALCOA, INC. ADMINISTRATOR’S RECORD OF DECISION December 6, 2012 I. INTRODUCTION

41

alternative to the REP waiver language, however, would have been to omit any mention

of Alcoa’s REP challenges, thereby permitting Alcoa to continue its suit against the REP

Settlement, while also receiving a long-term power arrangement from BPA. This

outcome, to BPA, would have been far more unreasonable. Indeed, it is highly likely that

if the REP waiver had not been included in the Agreement, PNGC and the other

preference customers would have sent in comments demanding that language should be

added to the contract requiring Alcoa to drop the lawsuit and stressing that without the

inclusion of this language BPA should not enter into the Agreement.

In conclusion, BPA sees no basis for PNGC’s allegation that that Alcoa “filed its petition

on the REP Settlement solely to gain leverage against BPA in negotiating a new power

sales contract” for the simple reason that economic considerations were the primary

factor and the waiver, in and of itself, did not provide any compelling basis for offering

the contract. That is not to say that the waiver is of no value in terms of streamlining the

litigation by eliminating some issues from the Court’s consideration, a result that BPA

believes the Court will find desirable.

Final Decision

BPA is offering this contract based on sound business considerations and the negotiated

waiver of the REP Settlement litigation supports these business considerations.

XI. ENVIRONMENTAL EFFECTS

BPA has reviewed the Agreement for potential environmental effects that could result

from its implementation, consistent with the National Environmental Policy Act (NEPA),

42 U.S.C. § 4321, et seq. Executing this Agreement would involve providing continued

service to a facility (the Intalco smelter) that is already in existence and currently

operating. This Agreement does not require BPA to take any action that would have a

potential effect on the environment. BPA expects to provide power from existing

generation sources that would continue to operate within their normal operating limits.

This power would be supplied over existing transmission lines that connect Intalco to

BPA’s electrical transmission system and no physical changes to this system would

occur. In addition, the proposed Agreement would not cause a change in Intalco’s

existing operations in such a way that environmental impacts would significantly differ

from the currently existing situation. Further, BPA anticipates that Alcoa will comply

with applicable statutory, regulatory, and permit requirements for environment, safety,

and health.

For these reasons, BPA has determined that the Agreement falls within a class of actions

excluded from further NEPA review pursuant to U.S. Department of Energy NEPA

regulations, which are applicable to BPA. More specifically, this Agreement falls within

Categorical Exclusion B4.1, found at 10 CFR 1021, Subpart D, Appendix B, which

provides for the categorical exclusion from NEPA of actions involving “[e]stablishment

and implementation of contracts, policies, and marketing and allocation plans related to

electric power acquisition that involve only the use of the existing transmission system

Page 45: ADMINISTRATOR’S RECORD OF DECISION POWER SALES AGREEMENT OFFER TO ALCOA, INC. · 2012. 12. 6. · ALCOA, INC. ADMINISTRATOR’S RECORD OF DECISION December 6, 2012 I. INTRODUCTION

42

and existing generation resources operating within their normal operating limits.” The

Environmental Clearance Memorandum that documents this categorical exclusion for the

contract has been posted at BPA’s website at: http://efw.bpa.gov/environmental_services/categoricalexclusions.aspx.

X. CONCLUSION

For the foregoing reasons, BPA will has sign the Agreement on December 7th

, 2012.

Issued at Portland, Oregon, this 6th day of December, 2012.

_/S/ STEPHEN J. WRIGHT_ __12/6/12_______

Stephen J. Wright Date

Administrator and Chief Executive Officer

Page 46: ADMINISTRATOR’S RECORD OF DECISION POWER SALES AGREEMENT OFFER TO ALCOA, INC. · 2012. 12. 6. · ALCOA, INC. ADMINISTRATOR’S RECORD OF DECISION December 6, 2012 I. INTRODUCTION

ATTACHMENT A

EBT ANALYSIS

1

TABLE 1 – IP Rate Forecast from REP-12

REP-12

FY 2013 FY 2014 FY 2015 FY 2016 FY 2017 Avg Electricity Prices ($/MWh) 28.53 $

39.78 $ 42.20 $

43.00 $ 44.52 $

Henry Hub Natural Gas Prices ($/mmBtu) $3.34 $4.96 $5.12 $5.38 $5.62

IP Rate ($/MWh) $36.31 $38.87 $38.87 $41.28 $41.28 7b3 Surcharge ($/MWh) $7.72 $8.14 $8.21 $8.65 $8.70 Net Margin ($/MWh) ($0.26) ($0.26) ($0.26) ($0.26) ($0.26)

Flat PF Rate ($/MWh) $28.84 $30.95 $30.95 $32.86 $32.86

Surplus Energy Revenues including Slice Secondary ($000) $626,339 $613,005 $592,901 $602,036 $614,441 Balancing Power Purchase Expenses ($000) $72,632 $74,120 $37,554 $42,536 $29,805

Augmentation Expenses ($000) $66,155 $52,864 $130,704 $93,396 $174,463 Net ($000) $487,552 $486,022 $424,642 $466,104 $410,173

4h10c Credits ($000) $95,847 $100,859 $104,727 $107,165 $109,699 Surplus energy revenues after Slice is removed $458,141 $448,389 $433,683 $440,365 $449,438

REP-12 (continued)

FY 2018 FY 2019 FY 2020 FY 2021 FY 2022 Avg Electricity Prices ($/MWh) 45.85 $

47.23 $ 48.65 $

50.11 $ 51.61 $

Henry Hub Natural Gas Prices ($/mmBtu) $5.79 $5.96 $6.14 $6.33 $6.52

IP Rate ($/MWh) $42.96 $42.96 $41.45 $41.45 $43.49 7b3 Surcharge ($/MWh) $9.14 $9.13 $7.21 $7.25 $7.60 Net Margin ($/MWh) ($0.26) ($0.26) ($0.26) ($0.26) ($0.26)

Flat PF Rate ($/MWh) $34.09 $34.09 $34.47 $34.47 $36.14

Surplus Energy Revenues including Slice Secondary ($000) $632,874 $651,860 $673,256 $691,559 $712,305 Balancing Power Purchase Expenses ($000) $30,700 $31,620 $32,658 $33,546 $34,553

Augmentation Expenses ($000) $119,302 $204,004 $123,411 $198,081 $132,018 Net ($000) $482,872 $416,236 $517,186 $459,931 $545,735

4h10c Credits ($000) $113,967 $118,377 $122,970 $127,692 $132,468 Surplus energy revenues after Slice is removed $462,922 $476,809 $492,459 $505,847 $521,022

Page 47: ADMINISTRATOR’S RECORD OF DECISION POWER SALES AGREEMENT OFFER TO ALCOA, INC. · 2012. 12. 6. · ALCOA, INC. ADMINISTRATOR’S RECORD OF DECISION December 6, 2012 I. INTRODUCTION

ATTACHMENT A

EBT ANALYSIS

2

TABLE 2 – IP Rate Forecast used in this EBT Analysis

See Revenue at Proposed Rates, BP-12-FS-BPA-01A at 136, tbl.4.2 (regarding secondary

energy revenues, balancing power purchase expenses, augmentation expenses, and 4h10c

credits for FY 2013). See Market Price Inputs and Secondary Energy, REP-12-FS-BPA-

01A at 203–04, tbl.10.4.2.3.1 (regarding secondary energy revenues, balancing power

purchase expenses, and augmentation expenses for FY 2014 – FY 2022).

See Cost of Service Analysis, General and Other Revenue Credits,

REP-12-FS-BPA-01A at 202, tbl.10.4.2.2.1 (regarding 4(h)(10)(c) credits for FY 2014 –

FY 2017); see also REP-12-FS-BPA-01 at 69 (regarding escalation of 4(h)(10)(c) credits

for FY 2018 – FY 2022).

ALCOA EBT Analysis

FY 2013 FY 2014 FY 2015 FY 2016 FY 2017 Avg Electricity Prices ($/MWh) $28.53 $34.15 $37.99 $39.31 $40.42 Henry Hub Natural Gas Prices ($/mmBtu) $3.34 $3.97 $4.35 $4.61 $4.86

IP Rate ($/MWh) $36.31 $40.14 $40.14 $42.32 $42.32 7b3 Surcharge ($/MWh) $7.72 $8.26 $8.38 $8.82 $8.87 Net Margin ($/MWh) ($0.26) ($0.26) ($0.26) ($0.26) ($0.26)

Flat PF Rate ($/MWh) $28.84 $32.46 $32.46 $34.13 $34.13

Surplus Energy Revenues including Slice Secondary ($000) $626,339 $507,339 $531,284 $543,203 $538,958 Balancing Power Purchase Expenses ($000) $72,632 $65,869 $31,209 $36,292 $27,646

Augmentation Expenses ($000) $66,155 $45,191 $123,549 $87,015 $162,587 Net ($000) $487,552 $396,279 $376,525 $419,896 $348,725

4h10c Credits ($000) $95,847 $96,472 $101,213 $104,265 $107,110 Surplus energy revenues after Slice is removed $458,141 $371,098 $388,613 $397,331 $394,226

ALCOA EBT Analysis (continued)

FY 2018 FY 2019 FY 2020 FY 2021 FY 2022 Avg Electricity Prices ($/MWh) $41.61 $42.88 $44.18 $45.48 $46.85 Henry Hub Natural Gas Prices ($/mmBtu) $5.01 $5.16 $5.31 $5.47 $5.64

IP Rate ($/MWh) $44.12 $44.12 $42.58 $42.58 $46.10 7b3 Surcharge ($/MWh) $9.31 $9.30 $7.34 $7.39 $7.75 Net Margin ($/MWh) ($0.26) ($0.26) ($0.26) ($0.26) ($0.26)

Flat PF Rate ($/MWh) $35.49 $35.49 $35.80 $35.80 $38.92

Surplus Energy Revenues including Slice Secondary ($000) $555,127 $571,780 $590,547 $606,602 $624,800 Balancing Power Purchase Expenses ($000) $28,475 $29,329 $30,292 $31,115 $32,049

Augmentation Expenses ($000) $111,181 $190,118 $115,011 $184,598 $123,031 Net ($000) $415,470 $352,333 $445,244 $390,888 $469,720

4h10c Credits ($000) $111,277 $115,583 $120,068 $124,678 $129,341 Surplus energy revenues after Slice is removed $406,053 $418,234 $431,961 $443,705 $457,016

Page 48: ADMINISTRATOR’S RECORD OF DECISION POWER SALES AGREEMENT OFFER TO ALCOA, INC. · 2012. 12. 6. · ALCOA, INC. ADMINISTRATOR’S RECORD OF DECISION December 6, 2012 I. INTRODUCTION

ATTACHMENT A

EBT ANALYSIS

3

TABLE 3 - Usage and Rates

Alcoa Ferndale Usage Projected IP Rates

Month Demand

(kW) HLH

(MWh) LLH

(MWh) Demand ($ / kW)

HLH ($ /

MWh)

LLH ($ /

MWh)

Jan-13 300,000

124,800 98,400 $9.70 $40.68 $32.35

Feb-13 300,000

115,200 86,400 $9.92 $41.58 $33.82

Mar-13 300,000

124,800 98,100 $9.60 $40.22 $32.98

Apr-13 300,000

124,800 91,200 $9.10 $38.18 $31.06

May-13 300,000

124,800 98,400 $8.50 $35.71 $25.05

Jun-13 300,000

120,000 96,000 $8.72 $36.62 $23.67

Jul-13 300,000

124,800 98,400 $10.20 $42.72 $30.56

Aug-13 300,000

129,600 93,600 $10.75 $45.00 $32.80

Sep-13 300,000

115,200 100,800 $10.53 $44.10 $34.24

Oct-13 300,000

129,600 93,600 $9.18 $42.50 $35.10

Nov-13 300,000

120,000 96,300 $9.31 $43.06 $35.32

Dec-13 300,000

120,000 103,200 $9.97 $46.10 $37.53

Jan-14 300,000

124,800 98,400 $9.70 $44.91 $35.65

Feb-14 300,000

115,200 86,400 $9.92 $45.91 $37.29

Mar-14 300,000

124,800 98,100 $9.60 $44.40 $36.35

Apr-14 300,000

124,800 91,200 $9.10 $42.13 $34.22

May-14 300,000

124,800 98,400 $8.50 $39.39 $27.54

Jun-14 300,000

120,000 96,000 $8.72 $40.40 $26.01

Jul-14 300,000

124,800 98,400 $10.20 $47.18 $33.66

Aug-14 300,000

124,800 98,400 $10.75 $49.71 $36.15

Sep-14 300,000

120,000 96,000 $10.53 $48.71 $37.75

Oct-14 300,000

129,600 93,600 $9.18 $42.61 $35.21

Nov-14 300,000

115,200 101,100 $9.31 $43.18 $35.43

Dec-14 300,000

124,800 98,400 $9.97 $46.21 $37.64

Jan-15 300,000

124,800 98,400 $9.70 $45.02 $35.77

Page 49: ADMINISTRATOR’S RECORD OF DECISION POWER SALES AGREEMENT OFFER TO ALCOA, INC. · 2012. 12. 6. · ALCOA, INC. ADMINISTRATOR’S RECORD OF DECISION December 6, 2012 I. INTRODUCTION

ATTACHMENT A

EBT ANALYSIS

4

TABLE 3 - Usage and Rates

Alcoa Ferndale Usage Projected IP Rates

Month Demand

(kW) HLH

(MWh) LLH

(MWh) Demand ($ / kW)

HLH ($ /

MWh)

LLH ($ /

MWh)

Feb-15 300,000

115,200 86,400 $9.92 $46.02 $37.40

Mar-15 300,000

124,800 98,100 $9.60 $44.51 $36.47

Apr-15 300,000

124,800 91,200 $9.10 $42.24 $34.33

May-15 300,000

120,000 103,200 $8.50 $39.50 $27.66

Jun-15 300,000

124,800 91,200 $8.72 $40.51 $26.12

Jul-15 300,000

124,800 98,400 $10.20 $47.29 $33.78

Aug-15 300,000

124,800 98,400 $10.75 $49.82 $36.27

Sep-15 300,000

120,000 96,000 $10.53 $48.82 $37.87

Oct-15 300,000

129,600 93,600 $9.18 $44.83 $37.05

Nov-15 300,000

115,200 101,100 $9.31 $45.43 $37.28

Dec-15 300,000

124,800 98,400 $9.97 $48.62 $39.61

Jan-16 300,000

120,000 103,200 $9.70 $47.37 $37.63

Feb-16 300,000

120,000 88,800 $9.92 $48.42 $39.35

Mar-16 300,000

129,600 93,300 $9.60 $46.83 $38.37

Apr-16 300,000

124,800 91,200 $9.10 $44.44 $36.13

May-16 300,000

120,000 103,200 $8.50 $41.56 $29.10

Jun-16 300,000

124,800 91,200 $8.72 $42.62 $27.49

Jul-16 300,000

120,000 103,200 $10.20 $49.75 $35.54

Aug-16 300,000

129,600 93,600 $10.75 $52.41 $38.16

Sep-16 300,000

120,000 96,000 $10.53 $51.36 $39.84

Oct-16 300,000

124,800 98,400 $9.18 $44.88 $37.10

Nov-16 300,000

120,000 96,300 $9.31 $45.48 $37.33

Dec-16 300,000

124,800 98,400 $9.97 $48.66 $39.66

Jan-17 300,000

120,000 103,200 $9.70 $47.41 $37.68

Feb-17 300,000

115,200 86,400 $9.92 $48.47 $39.40

Page 50: ADMINISTRATOR’S RECORD OF DECISION POWER SALES AGREEMENT OFFER TO ALCOA, INC. · 2012. 12. 6. · ALCOA, INC. ADMINISTRATOR’S RECORD OF DECISION December 6, 2012 I. INTRODUCTION

ATTACHMENT A

EBT ANALYSIS

5

TABLE 3 - Usage and Rates

Alcoa Ferndale Usage Projected IP Rates

Month Demand

(kW) HLH

(MWh) LLH

(MWh) Demand ($ / kW)

HLH ($ /

MWh)

LLH ($ /

MWh)

Mar-17 300,000

129,600 93,300 $9.60 $46.88 $38.42

Apr-17 300,000

120,000 96,000 $9.10 $44.49 $36.18

May-17 300,000

124,800 98,400 $8.50 $41.61 $29.15

Jun-17 300,000

124,800 91,200 $8.72 $42.67 $27.54

Jul-17 300,000

120,000 103,200 $10.20 $49.80 $35.59

Aug-17 300,000

129,600 93,600 $10.75 $52.46 $38.21

Sep-17 300,000

120,000 96,000 $10.53 $51.41 $39.89

Oct-17 300,000

124,800 98,400 $9.18 $46.77 $38.68

Nov-17 300,000

120,000 96,300 $9.31 $47.39 $38.92

Dec-17 300,000

120,000 103,200 $9.97 $50.70 $41.34

Jan-18 300,000

124,800 98,400 $9.70 $49.40 $39.28

Feb-18 300,000

115,200 86,400 $9.92 $50.50 $41.07

Mar-18 300,000

129,600 93,300 $9.60 $48.85 $40.05

Apr-18 300,000

120,000 96,000 $9.10 $46.37 $37.72

May-18 300,000

124,800 98,400 $8.50 $43.37 $30.41

Jun-18 300,000

124,800 91,200 $8.72 $44.47 $28.74

Jul-18 300,000

120,000 103,200 $10.20 $51.88 $37.11

Aug-18 300,000

129,600 93,600 $10.75 $54.65 $39.83

Sep-18 300,000

115,200 100,800 $10.53 $53.56 $41.58

Oct-18 300,000

129,600 93,600 $9.18 $46.75 $38.66

Nov-18 300,000

120,000 96,300 $9.31 $47.37 $38.90

Dec-18 300,000

120,000 103,200 $9.97 $50.69 $41.32

Jan-19 300,000

124,800 98,400 $9.70 $49.39 $39.27

Feb-19 300,000

115,200 86,400 $9.92 $50.48 $41.06

Mar-19 300,000

124,800 98,100 $9.60 $48.83 $40.03

Page 51: ADMINISTRATOR’S RECORD OF DECISION POWER SALES AGREEMENT OFFER TO ALCOA, INC. · 2012. 12. 6. · ALCOA, INC. ADMINISTRATOR’S RECORD OF DECISION December 6, 2012 I. INTRODUCTION

ATTACHMENT A

EBT ANALYSIS

6

TABLE 3 - Usage and Rates

Alcoa Ferndale Usage Projected IP Rates

Month Demand

(kW) HLH

(MWh) LLH

(MWh) Demand ($ / kW)

HLH ($ /

MWh)

LLH ($ /

MWh)

Apr-19 300,000

124,800 91,200 $9.10 $46.35 $37.70

May-19 300,000

124,800 98,400 $8.50 $43.35 $30.40

Jun-19 300,000

120,000 96,000 $8.72 $44.46 $28.72

Jul-19 300,000

124,800 98,400 $10.20 $51.87 $37.09

Aug-19 300,000

129,600 93,600 $10.75 $54.64 $39.82

Sep-19 300,000

115,200 100,800 $10.53 $53.55 $41.57

Oct-19 300,000

129,600 93,600 $9.18 $45.13 $36.96

Nov-19 300,000

120,000 96,300 $9.31 $45.75 $37.21

Dec-19 300,000

120,000 103,200 $9.97 $49.10 $39.65

Jan-20 300,000

124,800 98,400 $9.70 $47.78 $37.58

Feb-20 300,000

120,000 88,800 $9.92 $48.89 $39.38

Mar-20 300,000

124,800 98,100 $9.60 $47.22 $38.35

Apr-20 300,000

124,800 91,200 $9.10 $44.72 $36.00

May-20 300,000

120,000 103,200 $8.50 $41.69 $28.63

Jun-20 300,000

124,800 91,200 $8.72 $42.81 $26.94

Jul-20 300,000

124,800 98,400 $10.20 $50.28 $35.38

Aug-20 300,000

124,800 98,400 $10.75 $53.08 $38.13

Sep-20 300,000

120,000 96,000 $10.53 $51.98 $39.89

Oct-20 300,000

129,600 93,600 $9.18 $45.17 $37.01

Nov-20 300,000

115,200 101,100 $9.31 $45.79 $37.25

Dec-20 300,000

124,800 98,400 $9.97 $49.14 $39.69

Jan-21 300,000

120,000 103,200 $9.70 $47.83 $37.62

Feb-21 300,000

115,200 86,400 $9.92 $48.93 $39.42

Mar-21 300,000

129,600 93,300 $9.60 $47.26 $38.39

Apr-21 300,000

124,800 91,200 $9.10 $44.76 $36.04

Page 52: ADMINISTRATOR’S RECORD OF DECISION POWER SALES AGREEMENT OFFER TO ALCOA, INC. · 2012. 12. 6. · ALCOA, INC. ADMINISTRATOR’S RECORD OF DECISION December 6, 2012 I. INTRODUCTION

ATTACHMENT A

EBT ANALYSIS

7

TABLE 3 - Usage and Rates

Alcoa Ferndale Usage Projected IP Rates

Month Demand

(kW) HLH

(MWh) LLH

(MWh) Demand ($ / kW)

HLH ($ /

MWh)

LLH ($ /

MWh)

May-21 300,000

120,000 103,200 $8.50 $41.74 $28.67

Jun-21 300,000

124,800 91,200 $8.72 $42.85 $26.98

Jul-21 300,000

124,800 98,400 $10.20 $50.33 $35.43

Aug-21 300,000

124,800 98,400 $10.75 $53.12 $38.17

Sep-21 300,000

120,000 96,000 $10.53 $52.02 $39.94

Oct-21 300,000

124,800 98,400 $9.18 $48.85 $39.98

Nov-21 300,000

120,000 96,300 $9.31 $49.53 $40.24

Dec-21 300,000

124,800 98,400 $9.97 $53.17 $42.89

Jan-22 300,000

120,000 103,200 $9.70 $51.74 $40.64

Feb-22 300,000

115,200 86,400 $9.92 $52.94 $42.60

Mar-22 300,000

129,600 93,300 $9.60 $51.13 $41.48

Apr-22 300,000

124,800 91,200 $9.10 $48.41 $38.92

May-22 300,000

120,000 103,200 $8.50 $45.12 $30.92

Jun-22 300,000

124,800 91,200 $8.72 $46.33 $29.08

Jul-22 300,000

120,000 103,200 $10.20 $54.46 $38.26

Aug-22 300,000

129,600 93,600 $10.75 $57.50 $41.24

Sep-22 300,000

120,000 96,000 $10.53 $56.30 $43.16

Page 53: ADMINISTRATOR’S RECORD OF DECISION POWER SALES AGREEMENT OFFER TO ALCOA, INC. · 2012. 12. 6. · ALCOA, INC. ADMINISTRATOR’S RECORD OF DECISION December 6, 2012 I. INTRODUCTION

ATTACHMENT A

EBT ANALYSIS

8

TABLE 4 - BPA's Projected Revenue

Revenues by Rate Determinant Projected IP Revenue

Month Demand

($) HLH ($)

LLH ($)

Month ($)

Cumulative Total Contract-

to-Date ($)

Jan-13 $0 $5,076,552 $3,182,994 $8,259,546 $8,259,546

Feb-13 $0 $4,789,728 $2,921,832 $7,711,560 $15,971,106

Mar-13 $0 $5,019,144 $3,235,093 $8,254,237 $24,225,343

Apr-13 $0 $4,764,552 $2,832,444 $7,596,996 $31,822,339

May-13 $0 $4,456,296 $2,464,674 $6,920,970 $38,743,309

Jun-13 $0 $4,394,100 $2,272,080 $6,666,180 $45,409,489

Jul-13 $0 $5,331,144 $3,006,858 $8,338,002 $53,747,491

Aug-13 $0 $5,831,676 $3,069,846 $8,901,522 $62,649,013

Sep-13 $0 $5,080,032 $3,451,140 $8,531,172 $71,180,185

Oct-13 $0 $5,507,636 $3,285,085 $8,792,721 $79,972,905

Nov-13 $0 $5,167,664 $3,401,247 $8,568,911 $88,541,817

Dec-13 $0 $5,531,670 $3,873,141 $9,404,811 $97,946,628

Jan-14 $0 $5,604,561 $3,508,219 $9,112,779 $107,059,407

Feb-14 $0 $5,288,643 $3,221,509 $8,510,152 $115,569,560

Mar-14 $0 $5,540,773 $3,566,194 $9,106,967 $124,676,527

Apr-14 $0 $5,257,888 $3,120,797 $8,378,686 $133,055,212

May-14 $0 $4,915,376 $2,710,072 $7,625,447 $140,680,660

Jun-14 $0 $4,847,658 $2,496,770 $7,344,428 $148,025,088

Jul-14 $0 $5,887,446 $3,312,508 $9,199,954 $157,225,042

Aug-14 $0 $6,203,611 $3,557,419 $9,761,031 $166,986,073

Sep-14 $0 $5,845,009 $3,624,256 $9,469,264 $176,455,337

Oct-14 $0 $5,522,436 $3,295,774 $8,818,210 $185,273,547

Nov-14 $0 $4,974,113 $3,582,326 $8,556,439 $193,829,986

Dec-14 $0 $5,767,189 $3,704,232 $9,471,421 $203,301,407

Jan-15 $0 $5,618,813 $3,519,456 $9,138,269 $212,439,676

Feb-15 $0 $5,301,799 $3,231,376 $8,533,175 $220,972,851

Mar-15 $0 $5,555,025 $3,577,397 $9,132,422 $230,105,273

Apr-15 $0 $5,272,141 $3,131,212 $8,403,353 $238,508,626

May-15 $0 $4,740,027 $2,854,056 $7,594,082 $246,102,709

Jun-15 $0 $5,055,817 $2,382,346 $7,438,163 $253,540,872

Jul-15 $0 $5,901,698 $3,323,746 $9,225,444 $262,766,315

Aug-15 $0 $6,217,863 $3,568,657 $9,786,520 $272,552,835

Sep-15 $0 $5,858,713 $3,635,219 $9,493,932 $282,046,767

Oct-15 $0 $5,809,988 $3,467,795 $9,277,783 $291,324,550

Nov-15 $0 $5,233,075 $3,769,287 $9,002,362 $300,326,912

Dec-15 $0 $6,067,219 $3,897,401 $9,964,619 $310,291,532

Jan-16 $0 $5,683,851 $3,883,752 $9,567,603 $319,859,135

Feb-16 $0 $5,810,030 $3,494,342 $9,304,372 $329,163,507

Mar-16 $0 $6,068,908 $3,579,856 $9,648,764 $338,812,271

Apr-16 $0 $5,546,687 $3,294,702 $8,841,389 $347,653,659

May-16 $0 $4,987,060 $3,003,581 $7,990,642 $355,644,301

Jun-16 $0 $5,319,227 $2,507,286 $7,826,514 $363,470,815

Jul-16 $0 $5,969,857 $3,667,929 $9,637,787 $373,108,602

Aug-16 $0 $6,792,673 $3,571,683 $10,364,356 $383,472,957

Page 54: ADMINISTRATOR’S RECORD OF DECISION POWER SALES AGREEMENT OFFER TO ALCOA, INC. · 2012. 12. 6. · ALCOA, INC. ADMINISTRATOR’S RECORD OF DECISION December 6, 2012 I. INTRODUCTION

ATTACHMENT A

EBT ANALYSIS

9

TABLE 4 - BPA's Projected Revenue

Revenues by Rate Determinant Projected IP Revenue

Month Demand

($) HLH ($)

LLH ($)

Month ($)

Cumulative Total Contract-

to-Date ($)

Sep-16 $0 $6,163,332 $3,824,774 $9,988,106 $393,461,064

Oct-16 $0 $5,600,933 $3,650,464 $9,251,397 $402,712,461

Nov-16 $0 $5,457,014 $3,595,060 $9,052,074 $411,764,535

Dec-16 $0 $6,073,349 $3,902,234 $9,975,583 $421,740,118

Jan-17 $0 $5,689,745 $3,888,821 $9,578,566 $431,318,684

Feb-17 $0 $5,583,287 $3,404,144 $8,987,432 $440,306,116

Mar-17 $0 $6,075,274 $3,584,439 $9,659,712 $449,965,828

Apr-17 $0 $5,339,247 $3,472,822 $8,812,069 $458,777,898

May-17 $0 $5,192,673 $2,868,713 $8,061,386 $466,839,283

Jun-17 $0 $5,325,357 $2,511,766 $7,837,123 $474,676,407

Jul-17 $0 $5,975,752 $3,672,998 $9,648,750 $484,325,157

Aug-17 $0 $6,799,039 $3,576,280 $10,375,319 $494,700,476

Sep-17 $0 $6,169,227 $3,829,489 $9,998,716 $504,699,192

Oct-17 $0 $5,836,618 $3,805,705 $9,642,323 $514,341,515

Nov-17 $0 $5,686,491 $3,747,886 $9,434,377 $523,775,892

Dec-17 $0 $6,084,526 $4,265,949 $10,350,475 $534,126,367

Jan-18 $0 $6,165,660 $3,865,483 $10,031,143 $544,157,510

Feb-18 $0 $5,817,350 $3,548,397 $9,365,747 $553,523,257

Mar-18 $0 $6,330,367 $3,736,554 $10,066,922 $563,590,179

Apr-18 $0 $5,564,019 $3,620,737 $9,184,756 $572,774,934

May-18 $0 $5,412,048 $2,992,723 $8,404,770 $581,179,705

Jun-18 $0 $5,550,033 $2,620,828 $8,170,861 $589,350,566

Jul-18 $0 $6,225,952 $3,829,598 $10,055,550 $599,406,116

Aug-18 $0 $7,083,047 $3,728,099 $10,811,145 $610,217,261

Sep-18 $0 $6,170,070 $4,191,235 $10,361,305 $620,578,566

Oct-18 $0 $6,059,299 $3,618,757 $9,678,056 $630,256,622

Nov-18 $0 $5,684,820 $3,746,545 $9,431,366 $639,687,988

Dec-18 $0 $6,082,855 $4,264,512 $10,347,367 $650,035,355

Jan-19 $0 $6,163,922 $3,864,113 $10,028,035 $660,063,390

Feb-19 $0 $5,815,746 $3,547,194 $9,362,940 $669,426,330

Mar-19 $0 $6,094,172 $3,927,423 $10,021,594 $679,447,924

Apr-19 $0 $5,784,842 $3,438,430 $9,223,272 $688,671,196

May-19 $0 $5,410,310 $2,991,352 $8,401,663 $697,072,859

Jun-19 $0 $5,334,900 $2,757,429 $8,092,329 $705,165,188

Jul-19 $0 $6,473,252 $3,650,107 $10,123,359 $715,288,547

Aug-19 $0 $7,081,242 $3,726,795 $10,808,037 $726,096,584

Sep-19 $0 $6,168,466 $4,189,832 $10,358,298 $736,454,882

Oct-19 $0 $5,848,281 $3,459,836 $9,308,118 $745,763,000

Nov-19 $0 $5,490,073 $3,583,242 $9,073,315 $754,836,315

Dec-19 $0 $5,891,534 $4,091,655 $9,983,189 $764,819,504

Jan-20 $0 $5,963,552 $3,697,557 $9,661,109 $774,480,612

Feb-20 $0 $5,866,535 $3,496,786 $9,363,320 $783,843,933

Mar-20 $0 $5,893,201 $3,762,021 $9,655,222 $793,499,154

Apr-20 $0 $5,581,209 $3,282,831 $8,864,040 $802,363,194

Page 55: ADMINISTRATOR’S RECORD OF DECISION POWER SALES AGREEMENT OFFER TO ALCOA, INC. · 2012. 12. 6. · ALCOA, INC. ADMINISTRATOR’S RECORD OF DECISION December 6, 2012 I. INTRODUCTION

ATTACHMENT A

EBT ANALYSIS

10

TABLE 4 - BPA's Projected Revenue

Revenues by Rate Determinant Projected IP Revenue

Month Demand

($) HLH ($)

LLH ($)

Month ($)

Cumulative Total Contract-

to-Date ($)

May-20 $0 $5,003,321 $2,954,713 $7,958,033 $810,321,227

Jun-20 $0 $5,342,626 $2,456,910 $7,799,537 $818,120,764

Jul-20 $0 $6,275,545 $3,481,709 $9,757,253 $827,878,017

Aug-20 $0 $6,624,242 $3,751,820 $10,376,062 $838,254,079

Sep-20 $0 $6,237,114 $3,829,720 $10,066,833 $848,320,912

Oct-20 $0 $5,853,816 $3,463,834 $9,317,649 $857,638,561

Nov-20 $0 $5,275,390 $3,766,163 $9,041,553 $866,680,114

Dec-20 $0 $6,132,525 $3,905,548 $10,038,073 $876,718,187

Jan-21 $0 $5,739,309 $3,882,332 $9,621,642 $886,339,829

Feb-21 $0 $5,636,793 $3,405,968 $9,042,761 $895,382,589

Mar-21 $0 $6,125,397 $3,581,931 $9,707,328 $905,089,917

Apr-21 $0 $5,586,538 $3,286,725 $8,873,264 $913,963,181

May-21 $0 $5,008,445 $2,959,120 $7,967,565 $921,930,746

Jun-21 $0 $5,347,956 $2,460,805 $7,808,761 $929,739,507

Jul-21 $0 $6,280,874 $3,485,911 $9,766,785 $939,506,292

Aug-21 $0 $6,629,571 $3,756,022 $10,385,593 $949,891,885

Sep-21 $0 $6,242,238 $3,833,819 $10,076,057 $959,967,943

Oct-21 $0 $6,096,437 $3,933,606 $10,030,043 $969,997,986

Nov-21 $0 $5,943,503 $3,875,320 $9,818,823 $979,816,808

Dec-21 $0 $6,635,207 $4,220,739 $10,855,946 $990,672,755

Jan-22 $0 $6,208,923 $4,194,243 $10,403,166 $1,001,075,920

Feb-22 $0 $6,098,712 $3,680,688 $9,779,400 $1,010,855,321

Mar-22 $0 $6,626,202 $3,870,207 $10,496,409 $1,021,351,730

Apr-22 $0 $6,041,562 $3,549,783 $9,591,344 $1,030,943,075

May-22 $0 $5,414,262 $3,190,444 $8,604,706 $1,039,547,781

Jun-22 $0 $5,782,154 $2,651,768 $8,433,922 $1,047,981,703

Jul-22 $0 $6,535,101 $3,948,106 $10,483,207 $1,058,464,910

Aug-22 $0 $7,451,626 $3,860,203 $11,311,829 $1,069,776,739

Sep-22 $0 $6,755,752 $4,143,377 $10,899,129 $1,080,675,868

Page 56: ADMINISTRATOR’S RECORD OF DECISION POWER SALES AGREEMENT OFFER TO ALCOA, INC. · 2012. 12. 6. · ALCOA, INC. ADMINISTRATOR’S RECORD OF DECISION December 6, 2012 I. INTRODUCTION

ATTACHMENT A

EBT ANALYSIS

11

TABLE 5 - BPA's Forecasted Revenues Obtained from the Market

Forecasted

Market Price Forecasted Revenues Obtained from the Market

Month

HLH Price ($ /

MWh)

LLH Price ($ /

MWh) HLH ($)

LLH ($)

Month ($) (HLH + LLH)

Cumulative Total Contract-to-Date

($)

Jan-13 $31.81 $25.26 $3,970,382 $2,485,730 $6,456,112 $6,456,112

Feb-13 $33.57 $26.81 $3,867,510 $2,316,219 $6,183,729 $12,639,841

Mar-13 $32.44 $26.08 $4,048,504 $2,558,317 $6,606,821 $19,246,663

Apr-13 $29.49 $23.94 $3,680,527 $2,183,663 $5,864,190 $25,110,853

May-13 $28.80 $21.06 $3,593,642 $2,072,413 $5,666,056 $30,776,909

Jun-13 $29.48 $20.06 $3,537,629 $1,925,985 $5,463,614 $36,240,523

Jul-13 $33.36 $24.79 $4,162,734 $2,439,629 $6,602,363 $42,842,886

Aug-13 $38.39 $28.02 $4,974,807 $2,622,983 $7,597,789 $50,440,675

Sep-13 $37.70 $29.29 $4,342,933 $2,952,460 $7,295,393 $57,736,067

Oct-13 $37.70 $30.82 $4,886,074 $2,884,795 $7,770,869 $65,506,936

Nov-13 $36.79 $29.45 $4,414,332 $2,835,739 $7,250,072 $72,757,008

Dec-13 $39.24 $31.11 $4,709,368 $3,210,897 $7,920,265 $80,677,273

Jan-14 $40.26 $31.18 $5,024,878 $3,067,812 $8,092,689 $88,769,962

Feb-14 $42.03 $33.12 $4,841,727 $2,861,261 $7,702,987 $96,472,950

Mar-14 $40.16 $31.97 $5,012,304 $3,135,966 $8,148,271 $104,621,221

Apr-14 $35.96 $27.54 $4,487,375 $2,511,986 $6,999,361 $111,620,582

May-14 $31.35 $20.24 $3,912,664 $1,991,541 $5,904,205 $117,524,786

Jun-14 $32.04 $19.43 $3,845,218 $1,864,976 $5,710,194 $123,234,980

Jul-14 $38.80 $27.16 $4,842,832 $2,672,933 $7,515,766 $130,750,746

Aug-14 $43.55 $30.95 $5,435,123 $3,045,640 $8,480,763 $139,231,508

Sep-14 $42.50 $32.82 $5,099,896 $3,150,602 $8,250,498 $147,482,006

Oct-14 $42.82 $35.03 $5,549,698 $3,279,024 $8,828,723 $156,310,729

Nov-14 $42.38 $34.12 $4,882,448 $3,449,990 $8,332,438 $164,643,167

Dec-14 $44.99 $35.34 $5,615,335 $3,476,998 $9,092,333 $173,735,500

Jan-15 $43.86 $33.44 $5,473,120 $3,290,073 $8,763,194 $182,498,694

Feb-15 $44.79 $35.12 $5,159,431 $3,034,494 $8,193,926 $190,692,619

Mar-15 $44.53 $35.20 $5,557,891 $3,453,028 $9,010,919 $199,703,538

Apr-15 $39.93 $29.94 $4,983,448 $2,730,957 $7,714,405 $207,417,944

May-15 $36.07 $22.26 $4,328,406 $2,297,302 $6,625,708 $214,043,652

Jun-15 $37.05 $22.20 $4,624,448 $2,024,562 $6,649,010 $220,692,662

Jul-15 $44.29 $29.78 $5,527,597 $2,930,633 $8,458,230 $229,150,892

Aug-15 $47.72 $33.00 $5,955,764 $3,247,231 $9,202,995 $238,353,887

Sep-15 $46.60 $35.14 $5,592,563 $3,373,060 $8,965,622 $247,319,509

Oct-15 $46.38 $37.33 $6,011,282 $3,494,210 $9,505,492 $256,825,001

Nov-15 $45.60 $36.00 $5,252,848 $3,639,261 $8,892,109 $265,717,110

Dec-15 $46.43 $36.33 $5,794,873 $3,574,626 $9,369,499 $275,086,609

Jan-16 $46.08 $34.64 $5,529,818 $3,574,529 $9,104,346 $284,190,956

Feb-16 $47.93 $37.60 $5,752,068 $3,338,459 $9,090,527 $293,281,483

Mar-16 $45.14 $35.22 $5,849,993 $3,286,077 $9,136,070 $302,417,553

Apr-16 $41.49 $31.71 $5,177,404 $2,892,174 $8,069,578 $310,487,131

May-16 $37.09 $23.64 $4,451,099 $2,439,230 $6,890,329 $317,377,460

Jun-16 $36.20 $20.69 $4,517,432 $1,886,578 $6,404,010 $323,781,470

Jul-16 $45.20 $29.80 $5,423,518 $3,075,190 $8,498,709 $332,280,178

Aug-16 $48.27 $33.09 $6,255,374 $3,096,867 $9,352,241 $341,632,420

Page 57: ADMINISTRATOR’S RECORD OF DECISION POWER SALES AGREEMENT OFFER TO ALCOA, INC. · 2012. 12. 6. · ALCOA, INC. ADMINISTRATOR’S RECORD OF DECISION December 6, 2012 I. INTRODUCTION

ATTACHMENT A

EBT ANALYSIS

12

TABLE 5 - BPA's Forecasted Revenues Obtained from the Market

Forecasted

Market Price Forecasted Revenues Obtained from the Market

Month

HLH Price ($ /

MWh)

LLH Price ($ /

MWh) HLH ($)

LLH ($)

Month ($) (HLH + LLH)

Cumulative Total Contract-to-Date

($)

Sep-16 $48.73 $35.81 $5,847,213 $3,438,173 $9,285,385 $350,917,805

Oct-16 $49.33 $39.06 $6,156,120 $3,843,117 $9,999,237 $360,917,042

Nov-16 $46.46 $36.55 $5,574,863 $3,519,899 $9,094,763 $370,011,804

Dec-16 $48.83 $38.47 $6,094,444 $3,785,427 $9,879,871 $379,891,675

Jan-17 $48.43 $36.69 $5,811,396 $3,786,488 $9,597,884 $389,489,560

Feb-17 $49.36 $38.93 $5,686,487 $3,363,617 $9,050,103 $398,539,663

Mar-17 $46.72 $36.75 $6,055,416 $3,429,155 $9,484,571 $408,024,234

Apr-17 $41.41 $30.78 $4,968,793 $2,954,487 $7,923,280 $415,947,514

May-17 $37.81 $23.26 $4,718,508 $2,288,840 $7,007,347 $422,954,861

Jun-17 $38.93 $23.12 $4,859,020 $2,108,871 $6,967,892 $429,922,753

Jul-17 $45.67 $30.23 $5,480,381 $3,120,208 $8,600,589 $438,523,342

Aug-17 $48.69 $33.06 $6,309,855 $3,094,093 $9,403,948 $447,927,290

Sep-17 $48.55 $35.38 $5,825,486 $3,396,410 $9,221,896 $457,149,186

Oct-17 $50.01 $40.00 $6,240,799 $3,936,442 $10,177,241 $467,326,427

Nov-17 $48.79 $38.30 $5,855,070 $3,688,645 $9,543,715 $476,870,142

Dec-17 $50.20 $39.15 $6,024,251 $4,039,859 $10,064,110 $486,934,252

Jan-18 $49.88 $37.79 $6,225,167 $3,718,684 $9,943,851 $496,878,103

Feb-18 $50.84 $40.10 $5,857,081 $3,464,525 $9,321,606 $506,199,709

Mar-18 $48.13 $37.86 $6,237,078 $3,532,030 $9,769,108 $515,968,818

Apr-18 $42.65 $31.70 $5,117,857 $3,043,121 $8,160,978 $524,129,796

May-18 $38.94 $23.96 $4,860,063 $2,357,505 $7,217,568 $531,347,364

Jun-18 $40.10 $23.82 $5,004,791 $2,172,138 $7,176,928 $538,524,292

Jul-18 $47.04 $31.14 $5,644,793 $3,213,814 $8,858,607 $547,382,899

Aug-18 $50.15 $34.05 $6,499,151 $3,186,915 $9,686,066 $557,068,965

Sep-18 $50.00 $36.44 $5,760,241 $3,673,218 $9,433,458 $566,502,424

Oct-18 $51.51 $41.20 $6,675,254 $3,856,753 $10,532,008 $577,034,431

Nov-18 $50.26 $39.45 $6,030,722 $3,799,304 $9,830,026 $586,864,457

Dec-18 $51.71 $40.32 $6,204,979 $4,161,054 $10,366,033 $597,230,491

Jan-19 $51.38 $38.93 $6,411,922 $3,830,244 $10,242,167 $607,472,657

Feb-19 $52.37 $41.30 $6,032,794 $3,568,461 $9,601,254 $617,073,912

Mar-19 $49.57 $38.99 $6,186,257 $3,825,155 $10,011,412 $627,085,324

Apr-19 $43.93 $32.65 $5,482,248 $2,977,694 $8,459,943 $635,545,266

May-19 $40.11 $24.68 $5,005,865 $2,428,230 $7,434,095 $642,979,361

Jun-19 $41.31 $24.53 $4,956,668 $2,355,054 $7,311,722 $650,291,084

Jul-19 $48.45 $32.08 $6,046,702 $3,156,264 $9,202,966 $659,494,050

Aug-19 $51.65 $35.07 $6,694,125 $3,282,523 $9,976,648 $669,470,698

Sep-19 $51.50 $37.53 $5,933,048 $3,783,414 $9,716,462 $679,187,160

Oct-19 $53.05 $42.44 $6,875,512 $3,972,456 $10,847,968 $690,035,128

Nov-19 $51.76 $40.64 $6,211,643 $3,913,284 $10,124,927 $700,160,055

Dec-19 $53.26 $41.53 $6,391,128 $4,285,886 $10,677,014 $710,837,069

Jan-20 $52.92 $40.09 $6,604,280 $3,945,152 $10,549,432 $721,386,501

Feb-20 $53.94 $42.54 $6,472,685 $3,777,612 $10,250,297 $731,636,798

Mar-20 $51.06 $40.16 $6,371,845 $3,939,909 $10,311,754 $741,948,552

Apr-20 $45.25 $33.63 $5,646,716 $3,067,025 $8,713,741 $750,662,293

Page 58: ADMINISTRATOR’S RECORD OF DECISION POWER SALES AGREEMENT OFFER TO ALCOA, INC. · 2012. 12. 6. · ALCOA, INC. ADMINISTRATOR’S RECORD OF DECISION December 6, 2012 I. INTRODUCTION

ATTACHMENT A

EBT ANALYSIS

13

TABLE 5 - BPA's Forecasted Revenues Obtained from the Market

Forecasted

Market Price Forecasted Revenues Obtained from the Market

Month

HLH Price ($ /

MWh)

LLH Price ($ /

MWh) HLH ($)

LLH ($)

Month ($) (HLH + LLH)

Cumulative Total Contract-to-Date

($)

May-20 $41.31 $25.42 $4,957,731 $2,623,081 $7,580,812 $758,243,106

Jun-20 $42.54 $25.27 $5,309,583 $2,304,421 $7,614,003 $765,857,109

Jul-20 $49.90 $33.04 $6,228,103 $3,250,952 $9,479,055 $775,336,165

Aug-20 $53.20 $36.12 $6,639,580 $3,554,383 $10,193,964 $785,530,128

Sep-20 $53.05 $38.66 $6,365,666 $3,711,349 $10,077,015 $795,607,143

Oct-20 $54.64 $43.71 $7,081,777 $4,091,630 $11,173,407 $806,780,550

Nov-20 $53.32 $41.86 $6,142,073 $4,231,588 $10,373,661 $817,154,211

Dec-20 $54.86 $42.78 $6,846,176 $4,209,139 $11,055,315 $828,209,527

Jan-21 $54.51 $41.30 $6,540,777 $4,261,726 $10,802,503 $839,012,030

Feb-21 $55.56 $43.82 $6,400,191 $3,785,780 $10,185,971 $849,198,001

Mar-21 $52.59 $41.37 $6,815,424 $3,859,545 $10,674,968 $859,872,969

Apr-21 $46.60 $34.64 $5,816,117 $3,159,036 $8,975,153 $868,848,122

May-21 $42.55 $26.18 $5,106,463 $2,701,773 $7,808,237 $876,656,359

Jun-21 $43.82 $26.03 $5,468,870 $2,373,553 $7,842,424 $884,498,783

Jul-21 $51.40 $34.03 $6,414,946 $3,348,481 $9,763,427 $894,262,210

Aug-21 $54.80 $37.21 $6,838,768 $3,661,015 $10,499,783 $904,761,992

Sep-21 $54.64 $39.82 $6,556,636 $3,822,690 $10,379,325 $915,141,318

Oct-21 $56.28 $45.03 $7,024,074 $4,430,500 $11,454,574 $926,595,892

Nov-21 $54.92 $43.11 $6,589,932 $4,151,602 $10,741,535 $937,337,427

Dec-21 $56.50 $44.06 $7,051,562 $4,335,413 $11,386,975 $948,724,402

Jan-22 $56.14 $42.53 $6,737,001 $4,389,578 $11,126,579 $959,850,980

Feb-22 $57.22 $45.13 $6,592,197 $3,899,353 $10,491,550 $970,342,530

Mar-22 $54.17 $42.61 $7,019,886 $3,975,331 $10,995,217 $981,337,748

Apr-22 $48.00 $35.68 $5,990,601 $3,253,807 $9,244,408 $990,582,155

May-22 $43.83 $26.97 $5,259,657 $2,782,827 $8,042,484 $998,624,639

Jun-22 $45.14 $26.81 $5,632,936 $2,444,760 $8,077,696 $1,006,702,335

Jul-22 $52.94 $35.05 $6,353,264 $3,617,176 $9,970,440 $1,016,672,775

Aug-22 $56.44 $38.32 $7,314,851 $3,586,901 $10,901,753 $1,027,574,528

Sep-22 $56.28 $41.01 $6,753,335 $3,937,370 $10,690,705 $1,038,265,233

Page 59: ADMINISTRATOR’S RECORD OF DECISION POWER SALES AGREEMENT OFFER TO ALCOA, INC. · 2012. 12. 6. · ALCOA, INC. ADMINISTRATOR’S RECORD OF DECISION December 6, 2012 I. INTRODUCTION

ATTACHMENT A

EBT ANALYSIS

14

TABLE 6 - BPA's Net Benefit before Adjustment

Net Revenue or (Cost)

Month Month

($)

Cumulative Total Contract-to-Date

($)

Jan-13 $1,803,434 $1,803,434

Feb-13 $1,527,831 $3,331,265

Mar-13 $1,647,415 $4,978,680

Apr-13 $1,732,806 $6,711,486

May-13 $1,254,914 $7,966,400

Jun-13 $1,202,566 $9,168,966

Jul-13 $1,735,639 $10,904,605

Aug-13 $1,303,733 $12,208,338

Sep-13 $1,235,779 $13,444,117

Oct-13 $1,021,852 $14,465,969

Nov-13 $1,318,839 $15,784,808

Dec-13 $1,484,546 $17,269,355

Jan-14 $1,020,090 $18,289,445

Feb-14 $807,165 $19,096,610

Mar-14 $958,696 $20,055,306

Apr-14 $1,379,325 $21,434,631

May-14 $1,721,243 $23,155,874

Jun-14 $1,634,234 $24,790,108

Jul-14 $1,684,189 $26,474,297

Aug-14 $1,280,268 $27,754,564

Sep-14 $1,218,767 $28,973,331

Oct-14 ($10,513) $28,962,818

Nov-14 $224,001 $29,186,819

Dec-14 $379,089 $29,565,907

Jan-15 $375,075 $29,940,983

Feb-15 $339,249 $30,280,232

Mar-15 $121,503 $30,401,735

Apr-15 $688,948 $31,090,683

May-15 $968,374 $32,059,057

Jun-15 $789,153 $32,848,209

Jul-15 $767,214 $33,615,423

Aug-15 $583,525 $34,198,948

Sep-15 $528,309 $34,727,257

Oct-15 ($227,709) $34,499,549

Nov-15 $110,253 $34,609,802

Dec-15 $595,120 $35,204,922

Jan-16 $463,257 $35,668,179

Feb-16 $213,845 $35,882,024

Mar-16 $512,694 $36,394,718

Apr-16 $771,810 $37,166,529

May-16 $1,100,313 $38,266,841

Jun-16 $1,422,504 $39,689,345

Jul-16 $1,139,078 $40,828,423

Aug-16 $1,012,114 $41,840,538

Sep-16 $702,721 $42,543,259

Page 60: ADMINISTRATOR’S RECORD OF DECISION POWER SALES AGREEMENT OFFER TO ALCOA, INC. · 2012. 12. 6. · ALCOA, INC. ADMINISTRATOR’S RECORD OF DECISION December 6, 2012 I. INTRODUCTION

ATTACHMENT A

EBT ANALYSIS

15

TABLE 6 - BPA's Net Benefit before Adjustment

Net Revenue or (Cost)

Month Month

($)

Cumulative Total Contract-to-Date

($)

Oct-16 ($747,839) $41,795,419

Nov-16 ($42,688) $41,752,731

Dec-16 $95,712 $41,848,442

Jan-17 ($19,318) $41,829,124

Feb-17 ($62,671) $41,766,453

Mar-17 $175,141 $41,941,594

Apr-17 $888,789 $42,830,384

May-17 $1,054,038 $43,884,422

Jun-17 $869,232 $44,753,654

Jul-17 $1,048,161 $45,801,814

Aug-17 $971,371 $46,773,186

Sep-17 $776,820 $47,550,005

Oct-17 ($534,918) $47,015,087

Nov-17 ($109,337) $46,905,750

Dec-17 $286,365 $47,192,115

Jan-18 $87,292 $47,279,407

Feb-18 $44,141 $47,323,548

Mar-18 $297,813 $47,621,361

Apr-18 $1,023,777 $48,645,138

May-18 $1,187,203 $49,832,341

Jun-18 $993,932 $50,826,273

Jul-18 $1,196,943 $52,023,216

Aug-18 $1,125,079 $53,148,295

Sep-18 $927,847 $54,076,143

Oct-18 ($853,952) $53,222,191

Nov-18 ($398,660) $52,823,531

Dec-18 ($18,666) $52,804,864

Jan-19 ($214,132) $52,590,732

Feb-19 ($238,314) $52,352,418

Mar-19 $10,182 $52,362,601

Apr-19 $763,329 $53,125,930

May-19 $967,568 $54,093,498

Jun-19 $780,606 $54,874,104

Jul-19 $920,393 $55,794,497

Aug-19 $831,389 $56,625,886

Sep-19 $641,836 $57,267,722

Oct-19 ($1,539,850) $55,727,871

Nov-19 ($1,051,612) $54,676,260

Dec-19 ($693,825) $53,982,434

Jan-20 ($888,323) $53,094,111

Feb-20 ($886,977) $52,207,135

Mar-20 ($656,533) $51,550,602

Apr-20 $150,299 $51,700,900

May-20 $377,221 $52,078,122

Jun-20 $185,533 $52,263,655

Page 61: ADMINISTRATOR’S RECORD OF DECISION POWER SALES AGREEMENT OFFER TO ALCOA, INC. · 2012. 12. 6. · ALCOA, INC. ADMINISTRATOR’S RECORD OF DECISION December 6, 2012 I. INTRODUCTION

ATTACHMENT A

EBT ANALYSIS

16

TABLE 6 - BPA's Net Benefit before Adjustment

Net Revenue or (Cost)

Month Month

($)

Cumulative Total Contract-to-Date

($)

Jul-20 $278,198 $52,541,853

Aug-20 $182,098 $52,723,951

Sep-20 ($10,182) $52,713,769

Oct-20 ($1,855,758) $50,858,011

Nov-20 ($1,332,108) $49,525,903

Dec-20 ($1,017,243) $48,508,660

Jan-21 ($1,180,862) $47,327,799

Feb-21 ($1,143,210) $46,184,588

Mar-21 ($967,641) $45,216,948

Apr-21 ($101,889) $45,115,058

May-21 $159,329 $45,274,387

Jun-21 ($33,663) $45,240,724

Jul-21 $3,358 $45,244,082

Aug-21 ($114,189) $45,129,893

Sep-21 ($303,268) $44,826,625

Oct-21 ($1,424,532) $43,402,093

Nov-21 ($922,712) $42,479,381

Dec-21 ($531,028) $41,948,353

Jan-22 ($723,413) $41,224,940

Feb-22 ($712,150) $40,512,790

Mar-22 ($498,808) $40,013,983

Apr-22 $346,937 $40,360,919

May-22 $562,222 $40,923,142

Jun-22 $356,226 $41,279,367

Jul-22 $512,767 $41,792,134

Aug-22 $410,076 $42,202,211

Sep-22 $208,424 $42,410,634

Page 62: ADMINISTRATOR’S RECORD OF DECISION POWER SALES AGREEMENT OFFER TO ALCOA, INC. · 2012. 12. 6. · ALCOA, INC. ADMINISTRATOR’S RECORD OF DECISION December 6, 2012 I. INTRODUCTION

ATTACHMENT A

EBT ANALYSIS

17

TABLE 7a - BPA's Net Benefit Adjustments

Value of Reserves

Month Month

($)

Cumulative Total Contract-to-Date

($)

Jan-13 $209,808 $209,808

Feb-13 $189,504 $399,312

Mar-13 $209,526 $608,838

Apr-13 $203,040 $811,878

May-13 $209,808 $1,021,686

Jun-13 $203,040 $1,224,726

Jul-13 $209,808 $1,434,534

Aug-13 $209,808 $1,644,342

Sep-13 $203,040 $1,847,382

Oct-13 $209,808 $2,057,190

Nov-13 $203,322 $2,260,512

Dec-13 $209,808 $2,470,320

Jan-14 $209,808 $2,680,128

Feb-14 $189,504 $2,869,632

Mar-14 $209,526 $3,079,158

Apr-14 $203,040 $3,282,198

May-14 $209,808 $3,492,006

Jun-14 $203,040 $3,695,046

Jul-14 $209,808 $3,904,854

Aug-14 $209,808 $4,114,662

Sep-14 $203,040 $4,317,702

Oct-14 $209,808 $4,527,510

Nov-14 $203,322 $4,730,832

Dec-14 $209,808 $4,940,640

Jan-15 $209,808 $5,150,448

Feb-15 $189,504 $5,339,952

Mar-15 $209,526 $5,549,478

Apr-15 $203,040 $5,752,518

May-15 $209,808 $5,962,326

Jun-15 $203,040 $6,165,366

Jul-15 $209,808 $6,375,174

Aug-15 $209,808 $6,584,982

Sep-15 $203,040 $6,788,022

Oct-15 $209,808 $6,997,830

Nov-15 $203,322 $7,201,152

Dec-15 $209,808 $7,410,960

Jan-16 $209,808 $7,620,768

Feb-16 $196,272 $7,817,040

Mar-16 $209,526 $8,026,566

Apr-16 $203,040 $8,229,606

May-16 $209,808 $8,439,414

Jun-16 $203,040 $8,642,454

Jul-16 $209,808 $8,852,262

Aug-16 $209,808 $9,062,070

Sep-16 $203,040 $9,265,110

Page 63: ADMINISTRATOR’S RECORD OF DECISION POWER SALES AGREEMENT OFFER TO ALCOA, INC. · 2012. 12. 6. · ALCOA, INC. ADMINISTRATOR’S RECORD OF DECISION December 6, 2012 I. INTRODUCTION

ATTACHMENT A

EBT ANALYSIS

18

TABLE 7a - BPA's Net Benefit Adjustments

Value of Reserves

Month Month

($)

Cumulative Total Contract-to-Date

($)

Oct-16 $209,808 $9,474,918

Nov-16 $203,322 $9,678,240

Dec-16 $209,808 $9,888,048

Jan-17 $209,808 $10,097,856

Feb-17 $189,504 $10,287,360

Mar-17 $209,526 $10,496,886

Apr-17 $203,040 $10,699,926

May-17 $209,808 $10,909,734

Jun-17 $203,040 $11,112,774

Jul-17 $209,808 $11,322,582

Aug-17 $209,808 $11,532,390

Sep-17 $203,040 $11,735,430

Oct-17 $209,808 $11,945,238

Nov-17 $203,322 $12,148,560

Dec-17 $209,808 $12,358,368

Jan-18 $209,808 $12,568,176

Feb-18 $189,504 $12,757,680

Mar-18 $209,526 $12,967,206

Apr-18 $203,040 $13,170,246

May-18 $209,808 $13,380,054

Jun-18 $203,040 $13,583,094

Jul-18 $209,808 $13,792,902

Aug-18 $209,808 $14,002,710

Sep-18 $203,040 $14,205,750

Oct-18 $209,808 $14,415,558

Nov-18 $203,322 $14,618,880

Dec-18 $209,808 $14,828,688

Jan-19 $209,808 $15,038,496

Feb-19 $189,504 $15,228,000

Mar-19 $209,526 $15,437,526

Apr-19 $203,040 $15,640,566

May-19 $209,808 $15,850,374

Jun-19 $203,040 $16,053,414

Jul-19 $209,808 $16,263,222

Aug-19 $209,808 $16,473,030

Sep-19 $203,040 $16,676,070

Oct-19 $209,808 $16,885,878

Nov-19 $203,322 $17,089,200

Dec-19 $209,808 $17,299,008

Jan-20 $209,808 $17,508,816

Feb-20 $196,272 $17,705,088

Mar-20 $209,526 $17,914,614

Apr-20 $203,040 $18,117,654

May-20 $209,808 $18,327,462

Jun-20 $203,040 $18,530,502

Page 64: ADMINISTRATOR’S RECORD OF DECISION POWER SALES AGREEMENT OFFER TO ALCOA, INC. · 2012. 12. 6. · ALCOA, INC. ADMINISTRATOR’S RECORD OF DECISION December 6, 2012 I. INTRODUCTION

ATTACHMENT A

EBT ANALYSIS

19

TABLE 7a - BPA's Net Benefit Adjustments

Value of Reserves

Month Month

($)

Cumulative Total Contract-to-Date

($)

Jul-20 $209,808 $18,740,310

Aug-20 $209,808 $18,950,118

Sep-20 $203,040 $19,153,158

Oct-20 $209,808 $19,362,966

Nov-20 $203,322 $19,566,288

Dec-20 $209,808 $19,776,096

Jan-21 $209,808 $19,985,904

Feb-21 $189,504 $20,175,408

Mar-21 $209,526 $20,384,934

Apr-21 $203,040 $20,587,974

May-21 $209,808 $20,797,782

Jun-21 $203,040 $21,000,822

Jul-21 $209,808 $21,210,630

Aug-21 $209,808 $21,420,438

Sep-21 $203,040 $21,623,478

Oct-21 $209,808 $21,833,286

Nov-21 $203,322 $22,036,608

Dec-21 $209,808 $22,246,416

Jan-22 $209,808 $22,456,224

Feb-22 $189,504 $22,645,728

Mar-22 $209,526 $22,855,254

Apr-22 $203,040 $23,058,294

May-22 $209,808 $23,268,102

Jun-22 $203,040 $23,471,142

Jul-22 $209,808 $23,680,950

Aug-22 $209,808 $23,890,758

Sep-22 $203,040 $24,093,798

Page 65: ADMINISTRATOR’S RECORD OF DECISION POWER SALES AGREEMENT OFFER TO ALCOA, INC. · 2012. 12. 6. · ALCOA, INC. ADMINISTRATOR’S RECORD OF DECISION December 6, 2012 I. INTRODUCTION

ATTACHMENT A

EBT ANALYSIS

20

TABLE 7b - BPA's Net Benefit Adjustments

Avoided Tx and Ancillary Service Costs

Month Month

($)

Proportional Month

($)

Cumulative Total Contract-to-Date

($)

Jan-13 $359,890 $224,931 $224,931

Feb-13 $305,454 $190,909 $415,840

Mar-13 $312,962 $195,601 $611,441

Apr-13 $624,506 $390,316 $1,001,758

May-13 $903,774 $564,859 $1,566,617

Jun-13 $713,103 $445,689 $2,012,306

Jul-13 $402,631 $251,644 $2,263,950

Aug-13 $92,382 $57,739 $2,321,689

Sep-13 $29,385 $18,366 $2,340,054

Oct-13 $22,053 $13,783 $2,353,837

Nov-13 $39,072 $24,420 $2,378,257

Dec-13 $108,059 $67,537 $2,445,794

Jan-14 $355,084 $221,928 $2,667,722

Feb-14 $302,740 $189,212 $2,856,934

Mar-14 $311,639 $194,774 $3,051,708

Apr-14 $625,085 $390,678 $3,442,386

May-14 $953,527 $595,954 $4,038,340

Jun-14 $838,514 $524,071 $4,562,412

Jul-14 $375,118 $234,449 $4,796,861

Aug-14 $75,160 $46,975 $4,843,836

Sep-14 $26,102 $16,314 $4,860,150

Oct-14 $18,325 $11,453 $4,871,603

Nov-14 $23,560 $14,725 $4,886,328

Dec-14 $94,437 $59,023 $4,945,350

Jan-15 $334,966 $209,354 $5,154,705

Feb-15 $273,273 $170,796 $5,325,500

Mar-15 $289,318 $180,824 $5,506,324

Apr-15 $596,784 $372,990 $5,879,314

May-15 $893,002 $558,126 $6,437,440

Jun-15 $657,224 $410,765 $6,848,205

Jul-15 $346,939 $216,837 $7,065,042

Aug-15 $63,957 $39,973 $7,105,015

Sep-15 $21,579 $13,487 $7,118,502

Oct-15 $17,387 $10,867 $7,129,369

Nov-15 $17,495 $10,935 $7,140,304

Dec-15 $84,043 $52,527 $7,192,831

Jan-16 $320,500 $200,313 $7,393,143

Feb-16 $314,540 $196,588 $7,589,731

Mar-16 $281,957 $176,223 $7,765,954

Apr-16 $583,753 $364,846 $8,130,800

May-16 $948,318 $592,699 $8,723,499

Jun-16 $793,253 $495,783 $9,219,282

Jul-16 $385,512 $240,945 $9,460,227

Aug-16 $63,316 $39,572 $9,499,799

Sep-16 $19,624 $12,265 $9,512,065

Page 66: ADMINISTRATOR’S RECORD OF DECISION POWER SALES AGREEMENT OFFER TO ALCOA, INC. · 2012. 12. 6. · ALCOA, INC. ADMINISTRATOR’S RECORD OF DECISION December 6, 2012 I. INTRODUCTION

ATTACHMENT A

EBT ANALYSIS

21

TABLE 7b - BPA's Net Benefit Adjustments

Avoided Tx and Ancillary Service Costs

Month Month

($)

Proportional Month

($)

Cumulative Total Contract-to-Date

($)

Oct-16 $17,047 $10,654 $9,522,719

Nov-16 $17,574 $10,984 $9,533,703

Dec-16 $81,706 $51,066 $9,584,769

Jan-17 $316,921 $198,076 $9,782,844

Feb-17 $263,464 $164,665 $9,947,510

Mar-17 $280,514 $175,321 $10,122,831

Apr-17 $582,452 $364,032 $10,486,863

May-17 $872,758 $545,474 $11,032,337

Jun-17 $683,776 $427,360 $11,459,697

Jul-17 $350,438 $219,024 $11,678,720

Aug-17 $53,553 $33,471 $11,712,191

Sep-17 $16,933 $10,583 $11,722,774

Oct-17 $20,315 $12,697 $11,735,471

Nov-17 $21,284 $13,303 $11,748,774

Dec-17 $89,679 $56,050 $11,804,824

Jan-18 $328,449 $205,281 $12,010,104

Feb-18 $295,387 $184,617 $12,194,721

Mar-18 $287,530 $179,706 $12,374,427

Apr-18 $593,861 $371,163 $12,745,590

May-18 $955,830 $597,394 $13,342,984

Jun-18 $806,210 $503,881 $13,846,865

Jul-18 $385,512 $240,945 $14,087,810

Aug-18 $63,316 $39,572 $14,127,382

Sep-18 $19,624 $12,265 $14,139,648

Oct-18 $17,047 $10,654 $14,150,302

Nov-18 $17,574 $10,984 $14,161,286

Dec-18 $81,706 $51,066 $14,212,352

Jan-19 $316,921 $198,076 $14,410,427

Feb-19 $263,464 $164,665 $14,575,093

Mar-19 $280,514 $175,321 $14,750,414

Apr-19 $582,452 $364,032 $15,114,446

May-19 $872,758 $545,474 $15,659,920

Jun-19 $683,776 $427,360 $16,087,280

Jul-19 $350,438 $219,024 $16,306,303

Aug-19 $53,553 $33,471 $16,339,774

Sep-19 $16,933 $10,583 $16,350,357

Oct-19 $20,315 $12,697 $16,363,054

Nov-19 $21,284 $13,303 $16,376,357

Dec-19 $89,679 $56,050 $16,432,406

Jan-20 $328,449 $205,281 $16,637,687

Feb-20 $304,772 $190,482 $16,828,170

Mar-20 $287,530 $179,706 $17,007,876

Apr-20 $593,861 $371,163 $17,379,039

May-20 $955,830 $597,394 $17,976,432

Jun-20 $806,210 $503,881 $18,480,313

Page 67: ADMINISTRATOR’S RECORD OF DECISION POWER SALES AGREEMENT OFFER TO ALCOA, INC. · 2012. 12. 6. · ALCOA, INC. ADMINISTRATOR’S RECORD OF DECISION December 6, 2012 I. INTRODUCTION

ATTACHMENT A

EBT ANALYSIS

22

TABLE 7b - BPA's Net Benefit Adjustments

Avoided Tx and Ancillary Service Costs

Month Month

($)

Proportional Month

($)

Cumulative Total Contract-to-Date

($)

Jul-20 $385,512 $240,945 $18,721,258

Aug-20 $63,316 $39,572 $18,760,831

Sep-20 $19,624 $12,265 $18,773,096

Oct-20 $17,047 $10,654 $18,783,750

Nov-20 $17,574 $10,984 $18,794,734

Dec-20 $81,706 $51,066 $18,845,800

Jan-21 $316,921 $198,076 $19,043,876

Feb-21 $263,464 $164,665 $19,208,541

Mar-21 $280,514 $175,321 $19,383,862

Apr-21 $582,452 $364,032 $19,747,895

May-21 $872,758 $545,474 $20,293,368

Jun-21 $683,776 $427,360 $20,720,728

Jul-21 $350,438 $219,024 $20,939,751

Aug-21 $53,553 $33,471 $20,973,222

Sep-21 $16,933 $10,583 $20,983,806

Oct-21 $20,315 $12,697 $20,996,503

Nov-21 $21,284 $13,303 $21,009,805

Dec-21 $89,679 $56,050 $21,065,855

Jan-22 $328,449 $205,281 $21,271,136

Feb-22 $295,387 $184,617 $21,455,753

Mar-22 $287,530 $179,706 $21,635,459

Apr-22 $593,861 $371,163 $22,006,622

May-22 $955,830 $597,394 $22,604,015

Jun-22 $806,210 $503,881 $23,107,896

Jul-22 $385,512 $240,945 $23,348,841

Aug-22 $63,316 $39,572 $23,388,414

Sep-22 $19,624 $12,265 $23,400,679

Page 68: ADMINISTRATOR’S RECORD OF DECISION POWER SALES AGREEMENT OFFER TO ALCOA, INC. · 2012. 12. 6. · ALCOA, INC. ADMINISTRATOR’S RECORD OF DECISION December 6, 2012 I. INTRODUCTION

ATTACHMENT A

EBT ANALYSIS

23

TABLE 8 - BPA's Net Benefit after Adjustments

BPA's Adjusted Net Revenue or (Cost)

Month

Net Revenue or (Cost) (A) Month

($)

Value of Reserves (B) Month

($)

Avoided Tx Costs (C) Month

($)

Demand Shift

(D) Month ($)

A + B + C + D Month

($)

Cumulative Total Contract-to-Date

($) Jan-13 $1,803,434 $209,808 $224,931 $0 $2,238,173 $2,238,173

Feb-13 $1,527,831 $189,504 $190,909 $0 $1,908,244 $4,146,417

Mar-13 $1,647,415 $209,526 $195,601 $0 $2,052,543 $6,198,959

Apr-13 $1,732,806 $203,040 $390,316 $0 $2,326,162 $8,525,121

May-13 $1,254,914 $209,808 $564,859 $0 $2,029,581 $10,554,703

Jun-13 $1,202,566 $203,040 $445,689 $0 $1,851,295 $12,405,998

Jul-13 $1,735,639 $209,808 $251,644 $0 $2,197,091 $14,603,089

Aug-13 $1,303,733 $209,808 $57,739 $0 $1,571,280 $16,174,369

Sep-13 $1,235,779 $203,040 $18,366 $0 $1,457,185 $17,631,554

Oct-13 $1,021,852 $209,808 $13,783 $0 $1,245,442 $18,876,996

Nov-13 $1,318,839 $203,322 $24,420 $0 $1,546,582 $20,423,578

Dec-13 $1,484,546 $209,808 $67,537 $0 $1,761,891 $22,185,469

Jan-14 $1,020,090 $209,808 $221,928 $0 $1,451,826 $23,637,295

Feb-14 $807,165 $189,504 $189,212 $0 $1,185,881 $24,823,176

Mar-14 $958,696 $209,526 $194,774 $0 $1,362,997 $26,186,173

Apr-14 $1,379,325 $203,040 $390,678 $0 $1,973,043 $28,159,215

May-14 $1,721,243 $209,808 $595,954 $0 $2,527,005 $30,686,220

Jun-14 $1,634,234 $203,040 $524,071 $0 $2,361,346 $33,047,566

Jul-14 $1,684,189 $209,808 $234,449 $0 $2,128,446 $35,176,011

Aug-14 $1,280,268 $209,808 $46,975 $0 $1,537,051 $36,713,062

Sep-14 $1,218,767 $203,040 $16,314 $0 $1,438,120 $38,151,182

Oct-14 ($10,513) $209,808 $11,453 $0 $210,748 $38,361,931

Nov-14 $224,001 $203,322 $14,725 $0 $442,047 $38,803,978

Dec-14 $379,089 $209,808 $59,023 $0 $647,920 $39,451,898

Jan-15 $375,075 $209,808 $209,354 $0 $794,237 $40,246,135

Feb-15 $339,249 $189,504 $170,796 $0 $699,549 $40,945,684

Mar-15 $121,503 $209,526 $180,824 $0 $511,853 $41,457,537

Apr-15 $688,948 $203,040 $372,990 $0 $1,264,978 $42,722,515

May-15 $968,374 $209,808 $558,126 $0 $1,736,308 $44,458,823

Jun-15 $789,153 $203,040 $410,765 $0 $1,402,958 $45,861,781

Jul-15 $767,214 $209,808 $216,837 $0 $1,193,859 $47,055,640

Aug-15 $583,525 $209,808 $39,973 $0 $833,306 $47,888,945

Sep-15 $528,309 $203,040 $13,487 $0 $744,836 $48,633,782

Oct-15 ($227,709) $209,808 $10,867 $0 ($7,034) $48,626,748

Nov-15 $110,253 $203,322 $10,935 $0 $324,510 $48,951,258

Dec-15 $595,120 $209,808 $52,527 $0 $857,455 $49,808,713

Jan-16 $463,257 $209,808 $200,313 $0 $873,377 $50,682,090

Feb-16 $213,845 $196,272 $196,588 $0 $606,705 $51,288,795

Mar-16 $512,694 $209,526 $176,223 $0 $898,443 $52,187,238

Apr-16 $771,810 $203,040 $364,846 $0 $1,339,696 $53,526,935

May-16 $1,100,313 $209,808 $592,699 $0 $1,902,819 $55,429,754

Jun-16 $1,422,504 $203,040 $495,783 $0 $2,121,327 $57,551,081

Jul-16 $1,139,078 $209,808 $240,945 $0 $1,589,831 $59,140,912

Aug-16 $1,012,114 $209,808 $39,572 $0 $1,261,494 $60,402,407

Sep-16 $702,721 $203,040 $12,265 $0 $918,026 $61,320,433

Page 69: ADMINISTRATOR’S RECORD OF DECISION POWER SALES AGREEMENT OFFER TO ALCOA, INC. · 2012. 12. 6. · ALCOA, INC. ADMINISTRATOR’S RECORD OF DECISION December 6, 2012 I. INTRODUCTION

ATTACHMENT A

EBT ANALYSIS

24

TABLE 8 - BPA's Net Benefit after Adjustments

BPA's Adjusted Net Revenue or (Cost)

Month

Net Revenue or (Cost) (A) Month

($)

Value of Reserves (B) Month

($)

Avoided Tx Costs (C) Month

($)

Demand Shift

(D) Month ($)

A + B + C + D Month

($)

Cumulative Total Contract-to-Date

($) Oct-16 ($747,839) $209,808 $10,654 $0 ($527,377) $60,793,056

Nov-16 ($42,688) $203,322 $10,984 $0 $171,618 $60,964,674

Dec-16 $95,712 $209,808 $51,066 $0 $356,586 $61,321,259

Jan-17 ($19,318) $209,808 $198,076 $0 $388,566 $61,709,825

Feb-17 ($62,671) $189,504 $164,665 $0 $291,498 $62,001,322

Mar-17 $175,141 $209,526 $175,321 $0 $559,989 $62,561,311

Apr-17 $888,789 $203,040 $364,032 $0 $1,455,862 $64,017,173

May-17 $1,054,038 $209,808 $545,474 $0 $1,809,320 $65,826,493

Jun-17 $869,232 $203,040 $427,360 $0 $1,499,632 $67,326,124

Jul-17 $1,048,161 $209,808 $219,024 $0 $1,476,992 $68,803,117

Aug-17 $971,371 $209,808 $33,471 $0 $1,214,650 $70,017,767

Sep-17 $776,820 $203,040 $10,583 $0 $990,443 $71,008,210

Oct-17 ($534,918) $209,808 $12,697 $0 ($312,413) $70,695,797

Nov-17 ($109,337) $203,322 $13,303 $0 $107,287 $70,803,084

Dec-17 $286,365 $209,808 $56,050 $0 $552,222 $71,355,306

Jan-18 $87,292 $209,808 $205,281 $0 $502,381 $71,857,687

Feb-18 $44,141 $189,504 $184,617 $0 $418,262 $72,275,949

Mar-18 $297,813 $209,526 $179,706 $0 $687,046 $72,962,995

Apr-18 $1,023,777 $203,040 $371,163 $0 $1,597,980 $74,560,975

May-18 $1,187,203 $209,808 $597,394 $0 $1,994,404 $76,555,379

Jun-18 $993,932 $203,040 $503,881 $0 $1,700,853 $78,256,232

Jul-18 $1,196,943 $209,808 $240,945 $0 $1,647,696 $79,903,928

Aug-18 $1,125,079 $209,808 $39,572 $0 $1,374,459 $81,278,388

Sep-18 $927,847 $203,040 $12,265 $0 $1,143,152 $82,421,540

Oct-18 ($853,952) $209,808 $10,654 $0 ($633,489) $81,788,051

Nov-18 ($398,660) $203,322 $10,984 $0 ($184,354) $81,603,696

Dec-18 ($18,666) $209,808 $51,066 $0 $242,208 $81,845,904

Jan-19 ($214,132) $209,808 $198,076 $0 $193,752 $82,039,656

Feb-19 ($238,314) $189,504 $164,665 $0 $115,855 $82,155,511

Mar-19 $10,182 $209,526 $175,321 $0 $395,030 $82,550,541

Apr-19 $763,329 $203,040 $364,032 $0 $1,330,402 $83,880,942

May-19 $967,568 $209,808 $545,474 $0 $1,722,849 $85,603,792

Jun-19 $780,606 $203,040 $427,360 $0 $1,411,006 $87,014,798

Jul-19 $920,393 $209,808 $219,024 $0 $1,349,224 $88,364,022

Aug-19 $831,389 $209,808 $33,471 $0 $1,074,668 $89,438,690

Sep-19 $641,836 $203,040 $10,583 $0 $855,459 $90,294,149

Oct-19 ($1,539,850) $209,808 $12,697 $0 ($1,317,345) $88,976,804

Nov-19 ($1,051,612) $203,322 $13,303 $0 ($834,987) $88,141,816

Dec-19 ($693,825) $209,808 $56,050 $0 ($427,968) $87,713,849

Jan-20 ($888,323) $209,808 $205,281 $0 ($473,234) $87,240,615

Feb-20 ($886,977) $196,272 $190,482 $0 ($500,222) $86,740,392

Mar-20 ($656,533) $209,526 $179,706 $0 ($267,301) $86,473,092

Apr-20 $150,299 $203,040 $371,163 $0 $724,501 $87,197,593

May-20 $377,221 $209,808 $597,394 $0 $1,184,423 $88,382,016

Jun-20 $185,533 $203,040 $503,881 $0 $892,454 $89,274,470

Jul-20 $278,198 $209,808 $240,945 $0 $728,951 $90,003,421

Page 70: ADMINISTRATOR’S RECORD OF DECISION POWER SALES AGREEMENT OFFER TO ALCOA, INC. · 2012. 12. 6. · ALCOA, INC. ADMINISTRATOR’S RECORD OF DECISION December 6, 2012 I. INTRODUCTION

ATTACHMENT A

EBT ANALYSIS

25

TABLE 8 - BPA's Net Benefit after Adjustments

BPA's Adjusted Net Revenue or (Cost)

Month

Net Revenue or (Cost) (A) Month

($)

Value of Reserves (B) Month

($)

Avoided Tx Costs (C) Month

($)

Demand Shift

(D) Month ($)

A + B + C + D Month

($)

Cumulative Total Contract-to-Date

($) Aug-20 $182,098 $209,808 $39,572 $0 $431,478 $90,434,899

Sep-20 ($10,182) $203,040 $12,265 $0 $205,123 $90,640,023

Oct-20 ($1,855,758) $209,808 $10,654 $0 ($1,635,296) $89,004,727

Nov-20 ($1,332,108) $203,322 $10,984 $0 ($1,117,802) $87,886,925

Dec-20 ($1,017,243) $209,808 $51,066 $0 ($756,369) $87,130,557

Jan-21 ($1,180,862) $209,808 $198,076 $0 ($772,978) $86,357,578

Feb-21 ($1,143,210) $189,504 $164,665 $0 ($789,041) $85,568,537

Mar-21 ($967,641) $209,526 $175,321 $0 ($582,793) $84,985,744

Apr-21 ($101,889) $203,040 $364,032 $0 $465,183 $85,450,927

May-21 $159,329 $209,808 $545,474 $0 $914,610 $86,365,537

Jun-21 ($33,663) $203,040 $427,360 $0 $596,737 $86,962,274

Jul-21 $3,358 $209,808 $219,024 $0 $432,190 $87,394,464

Aug-21 ($114,189) $209,808 $33,471 $0 $129,090 $87,523,553

Sep-21 ($303,268) $203,040 $10,583 $0 ($89,645) $87,433,909

Oct-21 ($1,424,532) $209,808 $12,697 $0 ($1,202,027) $86,231,882

Nov-21 ($922,712) $203,322 $13,303 $0 ($706,087) $85,525,795

Dec-21 ($531,028) $209,808 $56,050 $0 ($265,171) $85,260,624

Jan-22 ($723,413) $209,808 $205,281 $0 ($308,324) $84,952,300

Feb-22 ($712,150) $189,504 $184,617 $0 ($338,029) $84,614,271

Mar-22 ($498,808) $209,526 $179,706 $0 ($109,576) $84,504,695

Apr-22 $346,937 $203,040 $371,163 $0 $921,139 $85,425,835

May-22 $562,222 $209,808 $597,394 $0 $1,369,424 $86,795,259

Jun-22 $356,226 $203,040 $503,881 $0 $1,063,147 $87,858,406

Jul-22 $512,767 $209,808 $240,945 $0 $963,520 $88,821,926

Aug-22 $410,076 $209,808 $39,572 $0 $659,456 $89,481,382

Sep-22 $208,424 $203,040 $12,265 $0 $423,729 $89,905,111

Page 71: ADMINISTRATOR’S RECORD OF DECISION POWER SALES AGREEMENT OFFER TO ALCOA, INC. · 2012. 12. 6. · ALCOA, INC. ADMINISTRATOR’S RECORD OF DECISION December 6, 2012 I. INTRODUCTION

ATTACHMENT B

GAS PRICE FORECAST

1

The gas price forecast component of BPA’s electricity price forecast is important because

natural gas price movements contribute to price movements in electric power markets in

the Pacific Northwest, as a preponderance of the generating resources establishing

marginal prices for electric power are fueled by natural gas. BPA’s natural gas price

forecast used in the BP-12 rate proceeding, the methodology for its development and its

use as an input to BPA’s electricity price forecasts, are outlined in section 2.3.1 of the

Power Risk and Market Price Study. See BP-12-FS-BPA-04 at 15. That natural gas price

forecast was released July 26, 2011. BPA has updated its forecast of natural gas prices

for use in this analysis of the Agreement in FY 2013 and all subsequent periods. BPA’s

updated natural gas price forecast was completed at the end of February 2012, during

BPA’s fiscal second quarter.

BPA has compared its updated forecast of spot market natural gas prices at the Henry

Hub to the recent forecasts produced by other forecasters in the industry. The

comparison, shown in Figure 2 below, includes a history of the Henry Hub spot prices –

as opposed to the more frequently referenced NYMEX (now CME Group) forward

market for Henry Hub natural gas prices – BPA’s forecast of natural gas prices from the

BP-12 Final Proposal, and other forecasters’ views of the future. The forecasters, in

alphabetical order, typically included in our comparisons are: Bentek Energy LLC

(Bentek), Cambridge Energy Research Associates (CERA), the United States Department

of Energy’s Energy Information Administration (EIA), PIRA Energy Group, and Wood

Mackenzie. With the exception of the EIA, each of these forecasters considers their

information to be proprietary. The vintage of these forecasts is August 2012. The

historical observations reflect the monthly average of the daily spot market prices for

natural gas at the Henry Hub quoted on the Intercontinental Exchange (ICE) for the

months from October 2008 through April 2012.

Page 72: ADMINISTRATOR’S RECORD OF DECISION POWER SALES AGREEMENT OFFER TO ALCOA, INC. · 2012. 12. 6. · ALCOA, INC. ADMINISTRATOR’S RECORD OF DECISION December 6, 2012 I. INTRODUCTION

ATTACHMENT B

GAS PRICE FORECAST

2

Figure 1: Henry Hub Natural Gas Spot Price Forecast

Figure 1 demonstrates that recent spot market prices for natural gas at the Henry Hub

have been less than $5 per MMBtu on an annual average basis in FY 2009, FY 2010 and

FY 2011, and has averaged less than $3 per MMBtu in FY 2012 through April 30, 2012.

This illustration also demonstrates that the forecasts of five other industry experts are

between $3.02 per MMBtu and $3.90 per MMBtu for FY 2013 – the starting fiscal years

of BPA’s evaluation of equivalent benefits for the Agreement – and the forecasts of all

five (5) of the other industry forecasters remain lower than $5 per MMBtu through at

least FY 2016. BPA’s updated forecast of spot prices for natural gas at the Henry Hub is

consistent with the views reflected by these five industry experts. As a result, BPA

believes its updated natural gas price forecast is reasonable compared to a recent history

of monthly average Henry Hub spot prices for natural gas and compared to the

expectations of other industry experts. Figure 1 also depicts the extent to which BPA’s

updated natural gas price forecast has progressed downward since the Final Proposal in

BP-12.

Henry Hub Natural Gas Spot Price History and Price Forecasts

$2.00

$2.50

$3.00

$3.50

$4.00

$4.50

$5.00

$5.50

$6.00

$6.50

$7.00

$7.50

$8.00

2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022

Fiscal Year

$/M

Mb

tu

Forecaster A Forecaster B Forecaster C Forecaster D

Avg of ICE Daily Spot EIA STEO - Aug-12 BPA (BP-12 Final) BPA (Feb-12)


Recommended