    GESTRA Steam SystemsGESTRA

    Intermittent blowdown valve MPA / PA up to PN250

    IntermittentIntermittent BlowdownBlowdown ValveValve Special Design

    -Radial Multi-stages Nozzle--Spring Closing Force

    Fail Safe Function Boiler Pressure closes Valve Pneumatic Actuator Possible

      . .

    PN 40-250 DN 20-50

    ENERGY TECHNOLOGY CO., LTD.0-2721-3860

    GESTRA Steam SystemsGESTRA

    Boiler water discharge of different valves

    ENERGY TECHNOLOGY CO., LTD.0-2721-3860Page 31 of 74

  • 8/20/2019 Advance Boiler Control System

    2/44

    GESTRA Steam SystemsGESTRA

    Automated intermittend blowdown system conventional

    ENERGY TECHNOLOGY CO., LTD.0-2721-3860

    GESTRA Steam SystemsGESTRA

    Bottom Blowdown Range up to PN250

    ENERGY TECHNOLOGY CO., LTD.0-2721-3860Page 32 of 74

  • 8/20/2019 Advance Boiler Control System

    3/44

    GESTRA Steam SystemsGESTRA

    The Benefits of the New GESTRA Intermittent Blowdown Valves

    Improved blowdown effectiveness through integrated pressure chamber in the outletsection of the body rea er g ness roug a ona w per r ngs e ween e pac ng sea s Longer service life and availability through radial stage nozzle downstream of the valveseat Insensitive to waterhammer through absence of large body cover  Reduced wear through new arrangement of the seals on the low pressure side ons s en mp emen a on o e wor sa e y regu a ons roug nove s ance u e Quick and easy installation thanks to multifunction parts Reduced maintenance and service effort throu h additional cu s rin s actin on the

    compression spring and through the possibility of tensioning the seals from outside Better checking functionally through relief vent for leak detection from outside

     

    ENERGY TECHNOLOGY CO., LTD.0-2721-3860

    GESTRA Steam SystemsGESTRA

    Blowdown receiver  

    Cooling Water 

    Cooling Water  

    Mixed cooled water 

    Drain

    ENERGY TECHNOLOGY CO., LTD.0-2721-3860Page 33 of 74

  • 8/20/2019 Advance Boiler Control System

    4/44

    GESTRA Steam SystemsGESTRA

    Boiler blow down with sample cooler 

    For Safety

     

    [Result of Lab test from sampling

    high TDS, resulting in the excessive

    to atmosphere]

    ENERGY TECHNOLOGY CO., LTD.0-2721-3860

    GESTRA Steam SystemsGESTRA

    Excessive Blowdown from sampling without sample cooler 

    Ex : Boiler Pressure 10 barg with boiler TDS = 3500 ppm (mg/l)or TDS / water = 3,500 / 1,000,000 = 0.0035

    Sample water from 10 barg to ATM will flash by 16%so wa er rom , , g w e , g o as s eamTDS / water new = 3,500 / 840,000 = 0.0042

    ev a on = . - . x . ~   g er an e ac

     boiler is by 2,916 ppm excessive blowdown Energy Loss

    ENERGY TECHNOLOGY CO., LTD.0-2721-3860Page 34 of 74

  • 8/20/2019 Advance Boiler Control System

    5/44

    GESTRA Steam SystemsGESTRA

    Heat Recovery from Surface Blowdown

    ENERGY TECHNOLOGY CO., LTD.0-2721-3860

    GESTRA Steam SystemsGESTRA

    Flash vessel

    ENERGY TECHNOLOGY CO., LTD.0-2721-3860Page 35 of 74

  • 8/20/2019 Advance Boiler Control System

    6/44

    GESTRA Steam SystemsGESTRA

    Flash vessel

    GESTRA Steam SystemsGESTRA

    GESTRA Flash Vessel Design

    Velocity of evaporation rate is. - . m s o avo carry over.

    Condensate inlet over a

    Large diameter  

    the impact to the vessel.

    condensate inlet over

    ENERGY TECHNOLOGY CO., LTD.0-2721-3860Page 36 of 74

  • 8/20/2019 Advance Boiler Control System

    7/44

    GESTRA Steam SystemsGESTRA

    Heat Recovery Skid

    ENERGY TECHNOLOGY CO., LTD.0-2721-3860

    GESTRA Steam SystemsGESTRA

    Heat Recovery from Surface Blowdown

    ENERGY TECHNOLOGY CO., LTD.0-2721-3860Page 37 of 74

  • 8/20/2019 Advance Boiler Control System

    8/44

    GESTRA Steam SystemsGESTRA

    Heat Recovery from Surface Blowdown

    ENERGY TECHNOLOGY CO., LTD.0-2721-3860

    GESTRA Steam SystemsGESTRA

    Heat Recovery from Surface Blowdown

    Or conductivity (uS/cm)

    ENERGY TECHNOLOGY CO., LTD.0-2721-3860Page 38 of 74

  • 8/20/2019 Advance Boiler Control System

    9/44

    GESTRA Steam SystemsGESTRA

    BA(E) 46 PN40 Surface blow down valve discharge capacity

    GESTRA Steam SystemsGESTRA

    (M)PA46 PN40 Bottom blow down valve discharge capacity

    ENERGY TECHNOLOGY CO., LTD.0-2721-3860Page 39 of 74

  • 8/20/2019 Advance Boiler Control System

    10/44

    GESTRA Steam SystemsGESTRA

    Heat Recovery from Surface Blowdown

    261.82 x (781.66-450.51)/2236.86

    = . g

    = 38.76x 24 x 300 kg/year 

    = 279.07 ton/ ear 

    279,072 x4.18 x (107.434 - 30) kJ/year 

    = 90,328,384 kJ/year 

    ENERGY TECHNOLOGY CO., LTD.0-2721-3860

    = , , . = . on year  

    GESTRA Steam SystemsGESTRA

    Heat Recovery from Surface Blowdown

    223.06 x 4.18 x (107.434 - 40) kJ/h

    = 62,874.41 kJ/h

    62,874.41/2236.86 kg/h

    = 28.11 kg/h

     = 28.11 x 24 x 300 kg/year = 202,382.7 kg/year 

    ENERGY TECHNOLOGY CO., LTD.0-2721-3860Page 40 of 74

  • 8/20/2019 Advance Boiler Control System

    11/44

    GESTRA Steam SystemsGESTRA

    Heat Recovery from Surface Blowdown

    ENERGY TECHNOLOGY CO., LTD.0-2721-3860

    GESTRA Steam SystemsGESTRA

    Heat Recovery from Surface Blowdown

    ENERGY TECHNOLOGY CO., LTD.0-2721-3860Page 41 of 74

  • 8/20/2019 Advance Boiler Control System

    12/44

    GESTRA Steam SystemsGESTRA

    Heat Recovery from Surface Blowdown

    Sensible heat of blowdown water = 261.82 x 781.66 = 204,654.22 kJ/h

    at 10 barg (781.66 kJ/kg)Sensible heat of drain point of = 261.82 x 4.18 x 40 = 43,776.3 kJ/h

    ‘ (specific heat of water (C) ~ 4.18 kJ/kg)

    = - =  , . , . , .

    Equivalent to 0.3 barg steam = 160,877.92 /2,236.86 = 71.92 kg/h=  . , .

    Equivalent steam saving per year= 71.92 x 300 x 24 = 517,824 kg/year (steam cost = 985.12 B/t) = . x .

    ~ 510, 118 Baht + Water treatment cost

    ENERGY TECHNOLOGY CO., LTD.0-2721-3860

    GESTRA Steam SystemsGESTRA

    Level Level Control Control 

    Monitor Monitor 

     

    Page 42 of 74

  • 8/20/2019 Advance Boiler Control System

    13/44

    GESTRA Steam SystemsGESTRA

    Water Level Controls

    The regulations concerning the control of Boilers vary from

    .regulations require the Boiler to be fitted with :-

    • Two independent low water alarms

    • A device to control the boilerwater level

    os regu a ons a so requ re e o er arms o e

    tested daily.

    ENERGY TECHNOLOGY CO., LTD.0-2721-3860

    GESTRA Steam SystemsGESTRA

    Extracted from Transaction Volume 4Page 43 of 74

  • 8/20/2019 Advance Boiler Control System

    14/44

    GESTRA Steam SystemsGESTRA

    Water limiter – Mechanical Float

    body

    magnet

    magnet switch

    11

    rod

    measuring chamber 

    float

    ENERGY TECHNOLOGY CO., LTD.0-2721-3860

    GESTRA Steam SystemsGESTRA

     

    Water limiter – Mechanical Float 

    ENERGY TECHNOLOGY CO., LTD.0-2721-3860Page 44 of 74

  • 8/20/2019 Advance Boiler Control System

    15/44

    GESTRA Steam SystemsGESTRA

    Water limiter – Mechanical Float

    ro em no on y rom e mov ng par ualso the boiler water quality

    Float get struck from scale and dirt 

    Pitures extracted from other Safety Technology Bureau/ DIW

    ENERGY TECHNOLOGY CO., LTD.0-2721-3860

    GESTRA Steam SystemsGESTRA

    Former German Re ulationWater limiter – Mechanical Float

    body

    ma netmagnet switch

     

    Owing to the physical measurement principle

    and the experience obtained in practice, which

    11

    rods a so re ec e n e amage a a es,additional requirements for the operation wereissued in the later develo ment of the technical

    measuring chamber  rules; these included a reduction of themaximum permissible boiler-water conductivity

    floatrom , o cm, regu ar rep acemenof the magnetic switches etc. – measureswhich were intended to revent boiler dama e

    but at the same time in-creased the operatingcosts

    ENERGY TECHNOLOGY CO., LTD.0-2721-3860Page 45 of 74

  • 8/20/2019 Advance Boiler Control System

    16/44

    GESTRA Steam SystemsGESTRA

    Water limiter – Mechanical Float

    GESTRA Steam SystemsGESTRA

    Water limiter – Mechanical Float

    extracted from “National Board BULLETIN“ Issue : winter 1999

    ENERGY TECHNOLOGY CO., LTD.0-2721-3860Page 46 of 74

  • 8/20/2019 Advance Boiler Control System

    17/44

    GESTRA Steam SystemsGESTRA

    Water limiter – Mechanical Float

    extracted from “National Board BULLETIN“ Issue : winter 1999

    ENERGY TECHNOLOGY CO., LTD.0-2721-3860

    GESTRA Steam SystemsGESTRA

    Water limiter – Mechanical Float

    Test Requirement EN 1295-9 for Mechanical Float in EU

    Float Movement : min 250,000 test cyclesElectromechanical switches : min 100,000 cycleOutside float and inside chamber : min 10 mm 

    No float switches for LW in EU

    ENERGY TECHNOLOGY CO., LTD.0-2721-3860Page 47 of 74

  • 8/20/2019 Advance Boiler Control System

    18/44

    GESTRA Steam SystemsGESTRA

    Developement of GESTRA boiler control equipment

    2010

    NRG 261981

    ER 961978ER 55

    19771972

    1980ER 83-3

     SIL3

     MR 16First self monitoring

    ER 14 

    ENERGY TECHNOLOGY CO., LTD.0-2721-3860

    GESTRA Steam SystemsGESTRA

    Measuring Principals

      Low level limiters

     

    Conductivity Control

    apac ance: or mo u a ng eve on ro Level control

    n egra e g eve arm

    ENERGY TECHNOLOGY CO., LTD.0-2721-3860Page 48 of 74

  • 8/20/2019 Advance Boiler Control System

    19/44

    GESTRA Steam SystemsGESTRA

     

    PN 6 Tmax: 156°C / 313°F Pmax: 6 bar 

    PN 10 Tmax: 180°C / 356°F Pmax: 10 bar 

    PN 40 Tmax: 238°C / 460°F Pmax: 32 bar 

    ° °  max   max  

    PN 160 Tmax: 311°C / 592°F Pmax: 100 bar 

    PN 320 T 400°C /752°F P 183 bar 

    ENERGY TECHNOLOGY CO., LTD.0-2721-3860

    GESTRA Steam SystemsGESTRA

    Conductive - Simple low level alarm

     Isolator insulator 

    Meßspitze

     

    ENERGY TECHNOLOGY CO., LTD.0-2721-3860Page 49 of 74

  • 8/20/2019 Advance Boiler Control System

    20/44

    GESTRA Steam SystemsGESTRA

    Concept Design of Conductivity Electrode

    ENERGY TECHNOLOGY CO., LTD.0-2721-3860

    GESTRA Steam SystemsGESTRA

    Possible danger of limiter with ‘‘conventional design“

    insulator 

    11

    Probe tip

    easur ng c am er  

    Short curcuit by means of deposits1

    condensationafter steam penetration2

    ENERGY TECHNOLOGY CO., LTD.0-2721-3860Page 50 of 74

  • 8/20/2019 Advance Boiler Control System

    21/44

    GESTRA Steam SystemsGESTRA

    Simple low level alarm

     Isolator insulator 

    Meßspitze Electrode rod is covered byPTFE to protect the short circuit

     

    **spacer to lock for multipleElectrode tip

    ENERGY TECHNOLOGY CO., LTD.0-2721-3860

    GESTRA Steam SystemsGESTRA

    Selection of Controller 

    extracted from “National Board BULLETIN“ Issue : winter 1999

    Spacer to lock electrode tips

    ENERGY TECHNOLOGY CO., LTD.0-2721-3860Page 51 of 74

  • 8/20/2019 Advance Boiler Control System

    22/44

    GESTRA Steam SystemsGESTRA

    Water level limiter ”special design” self monitoring

    monitoring electrode

    rs nsu a or 

    second insulator 

    Monitoring electrodeinsulator 

     

    Probe tip

    ENERGY TECHNOLOGY CO., LTD.0-2721-3860

    GESTRA Steam SystemsGESTRA

    State of the Art Technology - Self Monitoring Level Limiter 

    Value

    DeviceStatus(Alarm,

    ,

    Watch Dog)

    ENERGY TECHNOLOGY CO., LTD.0-2721-3860Page 52 of 74

  • 8/20/2019 Advance Boiler Control System

    23/44

    GESTRA Steam SystemsGESTRA

    Basic of Self Monitoring : Wheatstone bridge

    RST = R of insulation across monitoring electrode

    IG => 0and boiler shell => insulation checkRK = R across monitoring electrode and boiler shell=> scale check

    RP1, RP2 = Fixed R of the design circuit

    ENERGY TECHNOLOGY CO., LTD.0-2721-3860

    GESTRA Steam SystemsGESTRA

    Failure Dianogsis of Periodic Self-Checking Controller 

    ENERGY TECHNOLOGY CO., LTD.0-2721-3860Page 53 of 74

  • 8/20/2019 Advance Boiler Control System

    24/44

    GESTRA Steam SystemsGESTRA

    Boiler Equipment acc. TRD

    For boiler operation acc.to TRD 604 (max. 72 hrs without supervision)two self-monitoring low –level limiters are required and for boiler operation toTRD602(max. 2 hrs) only one self-monitoring low-level limiter is necessary

    Boiler Equipment acc.to PED, EN 12952 and EN12953

    e -mon or ng equ pmen w per o c-se c ec ng s requ re or o erswith temperature/pressure rating > 1 bar and > 120’C and a volume > 50 l

      - -

    ENERGY TECHNOLOGY CO., LTD.0-2721-3860

    GESTRA Steam SystemsGESTRA

    Function Safety acc.to PED, EN 12952 and EN12953

    Since the international standards IEC 61508 and IEC 61511 for functionalsafet came into effect there has been an ever-increasin demand foranalysing equipment and process instruments that meet the requirements

    accordin to SIL Safet Inte rit Level classification. The Euro ean directivesEN12952 and 12953 demand that a hazard analysis shall be carried out foreach limiting device function and appropriate levels of functional safety beImplemented.Note 1 states :” Typical Safety Integrity Level (SIL) requirements for boilerprotective systems are not less than 2”

    ENERGY TECHNOLOGY CO., LTD.0-2721-3860Page 54 of 74

  • 8/20/2019 Advance Boiler Control System

    25/44

    GESTRA Steam SystemsGESTRA

    Safety Integrity Level (SIL) Overview

    ENERGY TECHNOLOGY CO., LTD.0-2721-3860

    GESTRA Steam SystemsGESTRA

    Safety Integrity Level (SIL) Overview

     

    Page 55 of 74

  • 8/20/2019 Advance Boiler Control System

    26/44

    GESTRA Steam SystemsGESTRA

    Safety Integrity Level (SIL) Overview

    ENERGY TECHNOLOGY CO., LTD.0-2721-3860

    GESTRA Steam SystemsGESTRA

    Safety Integrity Level (SIL) of GESTRA low water limiter 

    ENERGY TECHNOLOGY CO., LTD.0-2721-3860Page 56 of 74

  • 8/20/2019 Advance Boiler Control System

    27/44

    GESTRA Steam SystemsGESTRA

    ON-OFF LEVEL CONTROL APPLICATION

    Pump on/off 

    Pump off 

     

    Low Alarm 2 

    ENERGY TECHNOLOGY CO., LTD.0-2721-3860

    GESTRA Steam SystemsGESTRA

    Inside the Spector Compact NRGS 16-2

    ENERGY TECHNOLOGY CO., LTD.0-2721-3860Page 57 of 74

  • 8/20/2019 Advance Boiler Control System

    28/44

    GESTRA Steam SystemsGESTRA

    On- Off level control with self monitoring low level alarm

    ENERGY TECHNOLOGY CO., LTD.0-2721-3860

    GESTRA Steam SystemsGESTRA

    On/Off Level ControlAdvantages 

    Sim le suitable for low ca acit boiler

  • 8/20/2019 Advance Boiler Control System

    29/44

    GESTRA Steam SystemsGESTRA

    Comparison: Intermittend / Continous

    Intermittend with fixed switch points Continuous with variable switch points

    High level -Alarm

    Pump Off 

    High level-Alarm

    Pump OnSet point

    Low level -Alarm Low level - alarm

    ENERGY TECHNOLOGY CO., LTD.0-2721-3860

    GESTRA Steam SystemsGESTRA

    Capacitance level probe

    Measuring pipe20 mA

    insulator 4-20 mA adjustablefor the whole probelength

    Measuring chamber 

    4 mA

    plug

    ENERGY TECHNOLOGY CO., LTD.0-2721-3860Page 59 of 74

  • 8/20/2019 Advance Boiler Control System

    30/44

    GESTRA Steam SystemsGESTRA

    Principle capacitance measurement

    ENERGY TECHNOLOGY CO., LTD.0-2721-3860

    GESTRA Steam SystemsGESTRA

    Principle capacitance level measurement

     

    Page 60 of 74

  • 8/20/2019 Advance Boiler Control System

    31/44

    GESTRA Steam SystemsGESTRA

    Principle capacitance level measurement

    Capacitive Reactance XC

    ENERGY TECHNOLOGY CO., LTD.0-2721-3860

    GESTRA Steam SystemsGESTRA

    Measurement with Capacitance Probes

    Low Voltage

     AC Supply

    CurrentFlowsInsulated

    Probe

    Less CurrentFlows

    Rod

    Liquid

    in a

    Metal

    Vessel

    Probe Deeply Immersed Lower Water Level 

    between Probe rod and Water Less Current Flows

     

    Page 61 of 74

  • 8/20/2019 Advance Boiler Control System

    32/44

    GESTRA Steam SystemsGESTRA

    Level Calibration of Capacitance Probe

    D

    = Dielectric

    W

    T

    L

     

    W = Water 

    T = Teflon

    L = Air 

    Probe tip cannot be cutD  

    Durch den Einfluß des Druckes wird derLuftspalt zwischen Teflonisolation undMeßrohr verdrängt

    W

    Durch den Einfluß der Temperatur längtsich der Teflonschlauch und wird somitdünner 

    ENERGY TECHNOLOGY CO., LTD.0-2721-3860

    GESTRA Steam SystemsGESTRA

    Modulating level control-conventional

    ENERGY TECHNOLOGY CO., LTD.0-2721-3860Page 62 of 74

  • 8/20/2019 Advance Boiler Control System

    33/44

    GESTRA Steam SystemsGESTRA

    Pump speed control with compact probe NRGT 26-1

    Frequency driven feedwater control

    4...20 mA

    Speise-wasser Feed water 

    ENERGY TECHNOLOGY CO., LTD.0-2721-3860

    GESTRA Steam SystemsGESTRA

    Modulating Level Control

    van ages

    Economic Operation (economizer)

    Higher steam quality (reduce carry over)

    Steady steam pressure and flow rate. No strongly modulating operation of burner and more efficient

    burner operation.

    Less thermal stress on the boiler shell.

    Less wear and tear on the feed pump and burner.

    Capability of adapting to difficult situations regarding the

    controlled system e.g. sudden change of steam consuption

    Disadvantages

    Less suitable for ‘stand b ’ o eration. 

    ENERGY TECHNOLOGY CO., LTD.0-2721-3860Page 63 of 74

  • 8/20/2019 Advance Boiler Control System

    34/44

    GESTRA Steam SystemsGESTRA

    Influence of the boiler capacity on the low level switchpoint

    Main steam valve Main steam valveLow level limiter Low level limiter

    Steam area Steam area

    Combustion tube

    Fire tube

    Shell boiler without steam production Shell boiler with steam production

    ENERGY TECHNOLOGY CO., LTD.0-2721-3860

    GESTRA Steam SystemsGESTRA

    Sudden increasing steam consumption in the boiler leads to :

    Pressure drop in the boiler 

     

    Increasing water level

    Closure of the control valve

    Pressure drop leads to increasing burner output

    Steam bubbles are compressed

     

    Boiler is shut down due to low level alarm !

    Remedy ????

    ENERGY TECHNOLOGY CO., LTD.0-2721-3860Page 64 of 74

  • 8/20/2019 Advance Boiler Control System

    35/44

    GESTRA Steam SystemsGESTRA

    Mode of Boiler Operation

    Sudden increase in steam consumption

     economizer 

      .

    Three elements control for sudden change of steam

    ENERGY TECHNOLOGY CO., LTD.0-2721-3860

    GESTRA Steam SystemsGESTRA

    Three element control

    D

    NLIC

    Boiler 

    W

    ENERGY TECHNOLOGY CO., LTD.0-2721-3860Page 65 of 74

  • 8/20/2019 Advance Boiler Control System

    36/44

    GESTRA Steam SystemsGESTRA

    Boiler equipment with SPECTORbus

    GESTRA Steam SystemsGESTRA

    Recommendation for installation 40 mm

    ENERGY TECHNOLOGY CO., LTD.0-2721-3860Page 66 of 74

  • 8/20/2019 Advance Boiler Control System

    37/44

    GESTRA Steam SystemsGESTRA

    Recommendation for installation 40 mm

    ENERGY TECHNOLOGY CO., LTD.0-2721-3860

    GESTRA Steam SystemsGESTRA

    „Self monitoring“ External Low Level Limiter 

    Risks with externalmeasuring pots :

    • Sto -valve blockin

    • Mud inside level pot

    • a ure n c ang ng evedetection

     

    Page 67 of 74

  • 8/20/2019 Advance Boiler Control System

    38/44

    GESTRA Steam SystemsGESTRA

    Level probe installed in an external measuring pot with SRL

    ENERGY TECHNOLOGY CO., LTD.0-2721-3860

    GESTRA Steam SystemsGESTRA

    Level probe installed in an external measuring pot with SRL

    ENERGY TECHNOLOGY CO., LTD.0-2721-3860Page 68 of 74

  • 8/20/2019 Advance Boiler Control System

    39/44

    GESTRA Steam SystemsGESTRA

    Compact Design and compatible to conventional systemsEasily accessible connection terminalsCompact Design and compatible to conventional systemsSupply voltage 24 VDC, improved EMC control (other voltages with separate power unit)Switchable sensitivity : 0.5 or 10 µS/cm

     Intuitive operating using rotary pushbutton or color touch displaySPECTORmodule Touch with separate control unit and greatly extended

    functionalityNow also as modulating controller and three-element controlAll limiter systems with SIL3 certification

    GESTRA Steam SystemsGESTRA

    SPECTORmodul TOUCHContinous level controller 

      -

    ENERGY TECHNOLOGY CO., LTD.0-2721-3860Page 69 of 74

  • 8/20/2019 Advance Boiler Control System

    40/44

    GESTRA Steam SystemsGESTRA

    Screen shots of NRR 2-52 operating unit URB 50

    ENERGY TECHNOLOGY CO., LTD.0-2721-3860

    GESTRA Steam SystemsGESTRA

    Screen shots of NRR 2-52 operating unit URB 50

    ENERGY TECHNOLOGY CO., LTD.0-2721-3860Page 70 of 74

  • 8/20/2019 Advance Boiler Control System

    41/44

    GESTRA Steam SystemsGESTRA

    Condensate Monitoring

    ENERGY TECHNOLOGY CO., LTD.0-2721-3860

    GESTRA Steam SystemsGESTRA

    Diffuse or stray light in water 

    90° Streulicht Scattering light

    Lichtempfänger 

    15° Streulicht O to reciver 

    Lichtsender 

    Lichtempfänger Durchlicht Opto reciver 

    O to transmitter 

    Streuung von Fe ststoffen, daher Hauptanwend ungsgebiet in der Scattering of solids 90°Trinkwasser-Aufbereitung / -Versorgun g

    Streuung von Öltropfen, daher Anwendung desScatterin of oil 15°  teu c tver a rens zur er ennung

    ENERGY TECHNOLOGY CO., LTD.0-2721-3860Page 71 of 74

  • 8/20/2019 Advance Boiler Control System

    42/44

    GESTRA Steam SystemsGESTRA

    Functional principle of the OR

    Automatische Kompensation von Störgrößen wie:  Verfärbung

     

    Lam enalterun

    Automaticly compansation of

    Variable disturbance  Verschmutzung der Gläser   

    VentilUmschaltung

    AlarmTV AlarmValve switch over 

    3 – 12 V

    X Actual valueSollwert

    W Setpoint

    Lampenspannung12 V Voltage 12 V

    ENERGY TECHNOLOGY CO., LTD.0-2721-3860

    GESTRA Steam SystemsGESTRA

    Saving from Condensate Return

    Condition : Condensate 1 t/h, P1 = 5 barg, P2 = 0.3 barg

    Sensible heat of blowdown water = 1,000 x 671 = 671,000 kJ/h

    at 5 barg (671 kJ/kg)

    Feed water tem 30’C = 1 000 x 4.18 x 30 = 125 400 kJ/h (specific heat of water (C) ~ 4.18 kJ/kg)

    = - =  , , ,

    Equivalent to 0.3 barg steam = 545,600 /2,236.86 ~ 244 kg/h  . , .

    Equivalent steam saving per year= 244 x 300 x 24 = 1,756,800 kg/year 

    (if steam cost = 1,000 B/t) = , . x ,~ 1,756, 800 Baht + Water treatment cost

    ENERGY TECHNOLOGY CO., LTD.0-2721-3860Page 72 of 74

  • 8/20/2019 Advance Boiler Control System

    43/44

    GESTRA Steam SystemsGESTRA

    Example of saving from condensate return

    ENERGY TECHNOLOGY CO., LTD.0-2721-3860

    GESTRA Steam SystemsGESTRA

    Example of saving from condensate return

    ENERGY TECHNOLOGY CO., LTD.0-2721-3860Page 73 of 74

  • 8/20/2019 Advance Boiler Control System

    44/44

    GESTRA Steam SystemsGESTRA


Recommended