+ All Categories
Home > Documents > AEP - C3 - Week 4 Slides

AEP - C3 - Week 4 Slides

Date post: 06-Jul-2018
Category:
Upload: cuny-bpl
View: 224 times
Download: 0 times
Share this document with a friend

of 18

Transcript
  • 8/17/2019 AEP - C3 - Week 4 Slides

    1/18

    CERTIFICATE PROGRAM

    Developed by:

    With generous support from:

  • 8/17/2019 AEP - C3 - Week 4 Slides

    2/18

    MEASUREMENT & VERIFICATION

    COLLABORATIVE INTEGRATED SKILLS

    PROJECT PREP

    WEEK 4

  • 8/17/2019 AEP - C3 - Week 4 Slides

    3/18

    WEEK 4: LEARNING OBJECTIVES

    Compare the three basic M&V methods

    Choose which M&V method is best suited for particular situationsand understand the associated costs

    Understand how to comply with local and national reporting andoperating standards

    Demonstrate an understanding of metering, measurement, andperformance data

  • 8/17/2019 AEP - C3 - Week 4 Slides

    4/18

    Required Readings:

    1. The Energy Management Handbook : Chapter 27: Measurement &

    Verification of Energy Systems

     2. M&V Guidelines: Measurement and Verification for Federal Energy

    Projects: U.S. Department of Energy

    3. The International Performance Measurement and Verification Protocol 

    WEEK 4: READINGS

  • 8/17/2019 AEP - C3 - Week 4 Slides

    5/18

    “The process of using measurement to reliably

    determine actual savings created within an individual

    facility by an energy management program.”

    - International Performance Measurement and Verification Protocol

    (IPMVP)

    WHAT IS MEASUREMENT & VERIFICATION?

  • 8/17/2019 AEP - C3 - Week 4 Slides

    6/18

    Purposes of M&V

    Increase energy savings

    Document spending

    Enhance financing

    Improve engineering, design, facility operations, and

    maintenance

    Manage budgets

    Support evaluation of regional efficiency programs

    Increase public understanding of energy management 

    Source: Patrick Crittenden, University of Technology, Sydney.

    M & V: PURPOSES

  • 8/17/2019 AEP - C3 - Week 4 Slides

    7/18

    Fundamental principles of good M&V practice:

    Accurate

    Complete

    Conservative

    Consistent 

    Relevant 

    Transparent 

    Photo: Simon A Eugster, via Wikimedia Commons.

    M & V: PRINCIPLES

  • 8/17/2019 AEP - C3 - Week 4 Slides

    8/18

    (Note: Steps 7-9 will be repeated every time a savings report is needed.)1. Consider the needs of the user

    2. Select the IPMVP option that is most consistent with

    a. The scope of ECMs

    b. The need for accuracy and

    c. The M&V budget 3. Gather relevant data from the baseline period and record it in a

    way that can be accessed in the future

    4. Prepare an M&V Plan

    Source: IPMVP

    M & V: DESIGN & REPORTING PROCESS

  • 8/17/2019 AEP - C3 - Week 4 Slides

    9/18

    5. Design, install, calibrate, and commission special measurementequipment 

    6. Inspect installed equipment and revised operating proceduresto ensure that they conform to design intent 

    7. Gather data from the reporting period in accordance with M&Vplan

    8. Compute savings

    9. Report savings

    (Optional ) Obtain third-party verification that:

    • Plan adheres to IPMVP and/or performance contracts

    • Savings reports comply with the approved M&V Plan

    Source: IPMVP

    M & V: DESIGN & REPORTING PROCESS

  • 8/17/2019 AEP - C3 - Week 4 Slides

    10/18

    According to the International Performance Measurement & VerificationProtocol (IPMVP), there are four major approaches to M & V for energyperformance:

    1. Retrofit Isolation: Key Parameter Measurement . Savings are determined byfield measurement of the key performance parameter(s) which define theenergy use of the ECM’s affected system(s) and/or the success of the project.

    2. Retrofit Isolation: All Parameter Measurement . Savings are determined byfield measurement of the energy use of the ECM-affected system.

    3. Whole Facility. Savings are determined by measuring energy use at the wholefacility or sub-facility level. Continuous measurements of the entire facility’senergy use are taken throughout the reporting period.

    4. Calibrated Simulation. Savings are determined through simulation of theenergy use of the whole facility or of a sub-facility. Simulation routines aredemonstrated to model actual energy performance measured in the facility

    adequately.

    (Descriptions from IPMVP.)

    Source: IPMVP

    IPMVP: M & V METHODS

  • 8/17/2019 AEP - C3 - Week 4 Slides

    11/18

    Scope of Study: Savings are determined by field measurement of the keyperformance parameters which define the energy use of the affected systems

    and/or success of the project.

    Frequency of Measurement : Measurement frequency ranges from short-term to

    continuous, depending on the expected variations in the measured parameter and

    length of the reporting period.

    Typical application: A lighting retrofit where power draw is the key

    performance parameter that is measured periodically; estimate operating hours

    of the lights based on building schedules and occupant behavior.

    How Savings are Calculated: Baseline and reporting period energy uses are

    calculated from short-term or continuous measurements of key operating

    parameters. Parameters not selected for field measurement are estimated.

    Estimates can based on historical data, manufacturer’s specifications, or

    engineering judgment.. Routine and non-routine adjustments must be made asrequired.

    Source: IPMVP.

    IPMVP: RETROFIT ISOLATION:KEY PARAMETERS

  • 8/17/2019 AEP - C3 - Week 4 Slides

    12/18

    Scope of Study: Savings are determined by field measurement of the energy use

    of the ECM-affected system.

    Frequency of Measurement : Measurement frequency ranges from short-term to

    continuous, depending on the expected variations in the savings and the length of

    the reporting period.

    Typical application: Application of a variable speed drive to a motor. In the

    baseline period this meter is used for a week to verify constant loading. In the

    reporting period, the meter is in place throughout the study to track variations.

    How Savings are Calculated: Analyzing Short-term or continuous

    measurements of baseline and reporting period computations using

    measurements or proxies of energy use. Routine and non-routine adjustments as

    required.

    (Source: IPMVP)

    IPMVP: RETROFIT ISOLATION: ALL PARAMETERS

  • 8/17/2019 AEP - C3 - Week 4 Slides

    13/18

    Scope of Study: Savings are determined by measuring energy use at the whole

    facility or sub-facility level.

    Frequency of Measurement : Continuous measurements of the entire facility’s

    energy use are taken throughout the reporting period.

    Typical Application: A multifaceted energy management program affecting many

    systems in a facility. Energy use is measured with the gas and electric utility

    meters for a 12 month baseline period and throughout the reporting period.

    How Savings are Calculated: Analyzing the entire facility ’s baseline and reporting

    period usage data. Routine and non-routine adjustments must be made, as

    required.

    (Source: IPMVP)

    IPMVP:WHOLE FACILITY

  • 8/17/2019 AEP - C3 - Week 4 Slides

    14/18

    Scope of Study: Savings are determined through simulation of the energy use bythe whole facility, or a sub-facility.

    Frequency of Measurement : Simulated routines are demonstrated to adequately

    model actual energy performance measured in the facility. Intervals may vary by

    project.

    Typical Applications: Study of a multifaceted energy management program that

    affects many systems in a facility, but where no meter existed in the baselineperiod.

    How Savings are Calculated: Simulation is calibrated with hourly or monthly

    utility billing data, where possible; differences are measured.

    Source: IPMVP

    IPMVP: CALIBRATED SIMULATION

  • 8/17/2019 AEP - C3 - Week 4 Slides

    15/18

    DETERMINING WHICH M&V METHOD TO USE

    A. Retrofit Isolation: Key Parameters

    B. Retrofit Isolation: All Parameters

    C. Whole Facility

    D. Calibrated Simulation

    Source: IPMVP

  • 8/17/2019 AEP - C3 - Week 4 Slides

    16/18

    WEEK 4: IN-CLASS EXERCISES

    1. When did the measurement and verification (M&V) of utility usagebegin? What were the key reasons for its initial implementation?

    2. Describe the role of M & V in the viability of performance contracts

    and/or other financing mechanisms.

    3. Consider the three major methods of M & V that are covered by the

    International Performance Measurement & Verification Protocol(IPMVP): Retrofit Isolation, Whole Building, and Calibrated

    Simulation.

    a) What are the major differences between the methods?

    b) What are the two types of Retrofit Isolation studies? Why are they

    different?

    c) Discuss some basic considerations that might cause parties to choose

    one method over another for a particular study objective.

  • 8/17/2019 AEP - C3 - Week 4 Slides

    17/18

    WEEK 4: HOMEWORK: COLLABORATIVE

    INTEGRATED SKILLS PROJECT

    Your Integrated Skills Project Presentation will provide an opportunity to broadly

    demonstrate what you’ve learned in your AEP studies.

    A building from the AEP Portfolio may be used, or you may choose another

    development subject. Please note that if you choose a building that is not an AEP

    Portfolio property, then you will need to develop an equivalent depth of data and

    documentation for your subject. Once you have selected a property to work with:

    Develop an energy management (EM) program for your property, and create a pitch foryour proposal. You may use one of the EM programs covered in the AEP course

    materials, or you may develop a hybrid model that addresses the key elements of

    effective EM. Credit will be awarded for thoroughness and creativity in such key

    elements as: (1) developing an initial plan; (2) setting targets; (3) proposing how you

    will measure performance/results; and (4) explaining how your findings will be used

    to make improvements.

    Presentations on EM proposals will incorporate analysis of each of the following topics

    that were covered during the AEP sequence: (1) building technologies and energy-

    efficient retrofits; (2) real estate strategy (e.g., project impacts on market and financial

    performance); (3) financial analysis (e.g., cash flows & returns on investment); (4)

    stakeholder analysis; (5) operations & maintenance; and (5) performance assurance

  • 8/17/2019 AEP - C3 - Week 4 Slides

    18/18

    Deliverables will include a PowerPoint presentation, sufficient supporting

    documents, and a written report; the pitch will be made live via WebEx.

    Your team presentation will be approximately 10-12 minutes long; your PowerPoint

    presentation must include at least 10 slides; more than 20 are not recommended.

    Your written report, which will pull together the covered material, will be

    approximately 6-8 pages in length, double-spaced, in 11 or 12 point font. Data

    sources (including portfolio material and in-class readings) must be referenced inyour endnotes.

    To complete the document submission, prior to presentation, upload a Folder via the

    Pathwright module according to these instructions:

    Include the following in your folder:

    PowerPoint presentation

    MS Word document of your written report 

    Electronic files (scanned, if necessary) of any supporting documentation that:

    You've referenced in the slides or the written report; or

    That you intend to refer to in your live presentations.

    WEEK 4: HOMEWORK: COLLABORATIVE

    INTEGRATED SKILLS PROJECT


Recommended