AfDB Field’s office in Abuja Nigeria Lot 3: Vol 5 Commissioning Plan Prepared by: Apave Liban s.a.r.l. For : Aim Consultants Ltd.
Transcript
Page 1: AfDB Field’s office in Abuja Nigeria

AfDB Field’s office in Abuja ‐ Nigeria  

Lot 3: Vol 5 ‐ Commissioning Plan  

    

Prepared by: Apave Liban s.a.r.l. 

For : Aim Consultants Ltd.     

Page 2: AfDB Field’s office in Abuja Nigeria

AfDB Field office in Abuja 

Page 2/12Project ref : PI12.154 Report n° : 13.116 Date : 16/04/2013

 

                                              Table of contents 

Introduction  ……………………………  3 

I‐ Overview of the commissioning process  ……………………………  4 

II‐ Systems and assemblies included in the CA’s scope of 

work 

……………………………  4 

III‐ Commissioning team and its responsibilities  ……………………………  4 

IV‐ Description of management, communication and 

reporting of commissioning process 

……………………………  7 

V‐ Commissioning Plan  ……………………………  8 

VI‐ List of expected work products  ……………………………  9 

VII‐ Testing equipment  ……………………………  10 

VIII‐ Commissioning process milestones and schedules  ……………………………  10 

IX‐ Commissioning check‐lists and testing procedures  ……………………………  11 

     

Check‐lists annexes:     

Annex 1: T&C for Electrical Installation     

Annex 2: T&C for Generator Installation     

Annex 3: T&C for Split Unit System     

Annex 4: T&C for AHUs and VAVs     

Annex 5: T&C for Chillers and Accessories     

Annex 6: T&C for Cooling Pumps     

Annex 7: T&C for Domestic Water System     

Annex 8: T&C for FCU     

Annex 9: T&C for Fans     

Annex 10: T&C for BMS     

Annex 11: T&C for Metering Systems      

Annex 12: T&C for VRVs     

Annex 13: T&C for PV System     

Annex 14: T&C for Solar Heating System      

 

 

 

 

 

 

 

 

 

 

Page 3: AfDB Field’s office in Abuja Nigeria

AfDB Field office in Abuja 

Page 3/12Project ref : PI12.154 Report n° : 13.116 Date : 16/04/2013

 

Introduction   

       The commissioning plan is the reference document that identifies the strategies, aspects and 

responsibilities within the commissioning process for each phase of the project for all project team members. 

This document outlines the overall process, schedule, organization, responsibilities and documentation 

requirements of the commissioning process for all commissioning team members. 

 

        The commissioning plan is developed at the start of the commissioning process, and is updated during 

the course of the project to reflect any changes in planning, schedule or other aspect. 

 

        The required commissioning plan components as per LEED reference guide for green building design and 

construction are as follows:  

 

  Required commissioning plan components:

I  Brief overview of the commissioning process. 

II  List of all systems and assemblies included in commissioning authority’s scope of work. 

III  Identification of commissioning team and its responsibilities. 

IV  Description of management, communication and reporting of commissioning process. 

V  Overview of commissioning process activities for pre‐design, design, construction, 

occupancy and post‐occupancy phases. 

VI  List of expected work products. 

VII  List of commissioning process milestones. 

 

Page 4: AfDB Field’s office in Abuja Nigeria

AfDB Field office in Abuja 

Page 4/12Project ref : PI12.154 Report n° : 13.116 Date : 16/04/2013

 

 

I‐ Overview of the commissioning process  

Commissioning intent is to verify that the project’s energy related systems are installed, calibrated and 

perform according to the owner’s project requirements, basis of design and construction documents and to 

provide the owner with a high level of assurance that the mechanical and electrical systems have been 

installed in the prescribed manner, and operate within the capabilities of the documented design and specified 

equipment capacities. 

 

In order to comply with the LEED requirements, the commissioning plan will be divided into two levels called 

“Fundamental Commissioning” of building energy systems which is prerequisite for the system and 

“Enhanced Commissioning” with its optional credits. 

The prerequisite intent is to verify that the project’s energy related systems are installed, calibrated and 

perform according to the owner’s project requirements, basis of design and construction documents. 

 

The Commissioning authority will verify the installation and performance of the systems to be commissioned, 

and will complete a summary commissioning report as part of the Fundamental commissioning process. 

The commissioning authority will document all commissioning review process, submittals, system manual, 

verify O&M training and review building operation after 10 month of final acceptance. 

 

II‐ Systems and assemblies included in commissioning authority’s scope of work  

The scope of services for the commissioning authority is based on the owner’s project requirements.  

Thus, as requested by the owner, the mission will cover the following base building systems: 

  

Ventilation systems(Supply air, Return air, Exhaust air) 

HVAC and associated control systems  

Chilled water 

VRV system 

Domestic water heating 

Water distribution systems 

Domestic water treatment 

Electrical power generation and distribution systems 

Building Management System  

Sub‐meters and central electronic monitoring system 

Lighting and lighting controls 

Renewable energy systems 

 

III‐ Commissioning team and its responsibilities  

        “Commissioning team” as defined in ASHRAE’s commissioning guide; it’s “Those people responsible for 

working together in carrying out the commissioning process”.  

 

 

 

Page 5: AfDB Field’s office in Abuja Nigeria

AfDB Field office in Abuja 

Page 5/12Project ref : PI12.154 Report n° : 13.116 Date : 16/04/2013

 

 

Commissioning, at every stage of a project, is a collaborative effort between all parties to the construction 

project; it’s a team effort and requires communication, coordination and cooperation among all parties 

involved with the project. The commissioning authority is the leader of the team.  

By clearly establishing the Commissioning Team and individual responsibilities, the process execution 

becomes easier, more effective and more accountable. 

 

Below are the commissioning team members, along with their individual responsibilities in the commissioning 

process during project phases.  

 

A. Owner (The African development Bank)

1‐ Include a statement regarding commissioning responsibilities in request for design services. 

2‐ Develop and commit to the Ownerʹs Program for the facility and its use. 

3‐ Assign operations and maintenance personnel and schedule them to participate in the 

various meetings, training sessions, and observations/inspections. 

4‐ Review and approve any changes made to design intent. 

5‐ Review and approve the construction documents. 

6‐ Provide qualified personnel for videotaping and editing of training sessions. 

7‐Videotape construction progress. 

8‐ Review and comment on the commissioning authorityʹs verification report. 

9‐ Review and accept the commissioning authorityʹs commissioning report. 

 

B. Commissioning Authority (Apave) 

1‐ Organize and lead the commissioning team. 

2‐ Prepare a program‐phase Commissioning Plan that describes in general the extent of the 

commissioning process to accomplish the Ownerʹs Program and the initial design intent. 

3‐ Develop the design‐phase Commissioning Plan, which details the extent and activities of the 

commissioning process including commissioning team organization, schedule, training, and 

documentation requirements and all related testing, verification, and quality control 

procedures. 

4‐ Execute the commissioning process through attending meetings, tests, demonstrations, 

training events, and performance verifications. 

5‐ Review the plans and specifications with respect to their completeness in all areas relating to 

commissioned systems. This includes ensuring that the design phase Commissioning Plan has 

been followed and that there are adequate devices included in the design to ensure the ability to 

properly test, verify, and adjust the systems. Any items required but not shown shall be 

brought to the attention of the Owner. 

6‐ Receive and review the operations and maintenance (O&M) manuals as submitted by the 

contractor. Ensure that they follow the specified outline and format. Insert systems description 

as provided by the design professional in the Systems Manual. 

7‐ Witness equipment, subsystem, and system start‐up and testing. Ensure the results are 

documented, including a summary of deficiencies, and incorporated in the O&M manuals. 

8‐ Supervise the commissioning team members in the functional performance tests. The test 

data will be part of the commissioning report. 

9‐ Ensure that the O&M manuals and all other as‐built records have been updated to include all 

Page 6: AfDB Field’s office in Abuja Nigeria

AfDB Field office in Abuja 

Page 6/12Project ref : PI12.154 Report n° : 13.116 Date : 16/04/2013

 

modifications made during the construction phase. 

10‐ Prepare the final commissioning report and the systems manual. 

11‐ Review operation after 10 month of completion. 

 

 

C. Design / Technical Control Consultants

 

1‐ Provide system design parameters and revisions to the initial design intent document as 

necessary, obtaining approval of the owner. 

2‐ Prepare contract documents, including the commissioning specification and description of 

the commissioned systems. 

3‐ Attend construction‐phase coordination meeting. 

4‐ Specify and verify adequate maintenance accessibility for each piece of equipment in shop 

drawings and actual installation. Periodic inspections are part of the design professionalʹs 

construction administration duties. 

5‐ Develop an overview of system design and operation concepts for the Systems Manual. 

6‐ Review and accept as‐built records as required by contract documents and turn them over to 

the commissioning authority. 

 

D. Contractor/Sub‐contractor/Supplier 

 

1‐ Include costs for commissioning requirements in the contract price. 

2‐ Include requirements for submittal data, O&M data and O&M training in each purchase 

order or subcontract written. 

3‐ Ensure cooperation and participation of specialty subcontractors and controls contractors. 

4‐ Ensure coordination, installation, and operation of interfaces between commissioning team. 

5‐ Ensure participation of major equipment manufacturers in appropriate training and testing 

activities. 

6‐ Attend construction‐phase coordination meeting scheduled by the commissioning authority. 

7‐ Prepare necessary preliminary schedule for commissioned system orientation and 

inspections, O&M manual submission, training sessions, equipment and systems’ testing, for 

use by the commissioning authority. Update schedule as appropriate throughout the 

construction period. 

8‐ Attend initial training sessions, and conduct system orientation and inspection at the 

equipment placement completion stage. Update drawings to record condition to date, and 

review with the commissioning authority. 

9‐ Gather O&M data on all equipment and assemble in binders as required by the 

commissioning specification. Submit to commissioning authority prior to the completion of 

construction. 

10‐ Notify the commissioning authority when equipment and system start‐up and testing can be 

witnessed. 

11‐ Schedule equipment suppliers and contractors to participate in the O&M training sessions. 

12‐ Conduct a system orientation and inspection with hands‐on training. Update drawings to 

record condition to date, and review with the commissioning authority prior to the orientation. 

13‐ Provide written notification to the construction manager and commissioning authority that 

Page 7: AfDB Field’s office in Abuja Nigeria

AfDB Field office in Abuja 

Page 7/12Project ref : PI12.154 Report n° : 13.116 Date : 16/04/2013

 

the following work has been completed in accordance with the contract documents and that the 

equipment, systems, and subsystems are functioning as required. 

14‐ Demonstrate the operation of each piece of equipment to the commissioning authority. 

Schedule subcontractors as may apply to demonstrate the operation of the equipment and 

systems. 

15‐ Provide services of an engineer to participate in verification tests. 

16‐ Turn over a set of as‐built records to the commissioning authority. (Hard and soft copies) 

17‐ Provide filled checklist data sheets to document verification tests for the commissioning 

authority. 

18‐ Submit detailed verification test procedures and data sheets for review by the design team. 

19‐ Submit detailed list of test instrumentation with appropriate calibration records to be 

utilized for verification. Record data as necessary. 

20‐ Submit verification test data to the design team and the commissioning authority for review. 

21‐ Conduct tests and verifications including opposite season tests, as required. 

22‐ Retest if performance deficiencies are found and corrected and additional testing is 

requested. 

23‐ Repeat all required testing and verification procedures after 10 months of client’s 

occupancy. 

 

IV‐ Description of management, communication and reporting of commissioning process  

Whole Building Commissioning is a process that relies upon high levels of communications and collaboration 

between all parties to the construction process. By its nature, the levels of communication and cooperation 

between the Commissioning Authority and all other parties to the construction process (Design team, 

Engineers, Subcontractors, Vendors, third party testing agencies, etc.) is essential to the success of the 

Commissioning effort. In the absence of these relationships, cooperation and support created by this 

communication, the Commissioning Process will likely fail to achieve its ends. 

 

With this fundamental conflict in mind, this section has been developed to recognize that, in the execution of 

the Commissioning Process, the Commissioning Authority must develop effective methods to communicate 

with every member of the construction team involved in delivering commissioned systems while 

simultaneously respecting the exclusive contract authority of the Contracting Officer and his/her Designated 

Representative.  

 

The organizational process chart below shows lines of contractual authority in this project, yet 

communications are encouraged between all commissioning team members, within the limit of their contracts. 

 

Page 8: AfDB Field’s office in Abuja Nigeria

AfDB Field office in Abuja 

Page 8/12Project ref : PI12.154 Report n° : 13.116 Date : 16/04/2013

 

 

V‐ Commissioning Plan  

The commissioning plan is implemented during the construction phase. Direct interaction between the 

construction team and the commissioning authority and communication with the design team represents the 

cornerstone of successful commissioning. 

 

The commissioning authority provides leadership by communicating goals for the commissioning process, 

including identification of roles and responsibilities of team members, and clearly defining and documenting 

pass/fail criteria. Each commissioning team member shares a responsibility to support the commissioning 

process and achieve a quality installation. 

 

The sequence and timing of commissioning activities must be incorporated into the overall project schedule. 

The commissioning authority identifies the required commissioning activities. Coordination requires input 

from the owner, designer, and contractors. Cooperation among the parties facilitates integration of 

commissioning into the total construction program. 

 

At this stage, the commissioning authority obtains and reviews submittal data, and consults with the 

designers and contractors regarding conformance with the design intent. The designer provides final approval 

of all submittals. 

 

The commissioning authority should work with the general contractor to schedule commissioning meetings in 

conjunction with regular progress meetings, because many participants will attend both. The commissioning 

authority keeps meeting minutes.  

All commissioning team members are responsible for attending commissioning meetings and for completing 

assigned action items by the agreed dates. Cooperation by all parties contributes to successful commissioning. 

 

The contractor is responsible for preparing the O&M documentation and training program in accordance with 

specification requirements. 

 

Client

AfDB 

Main contractor   

To be defined 

Subcontractors / Suppliers

To be defined 

Project Manager

 

Design Consultants

Technical Control 

Consultants 

AIM 

LEED Consultant 

SEEDS 

Commissioning authority 

Apave 

Page 9: AfDB Field’s office in Abuja Nigeria

AfDB Field office in Abuja 

Page 9/12Project ref : PI12.154 Report n° : 13.116 Date : 16/04/2013

 

The O&M training program should include: 

 

Design intent. 

System limitations. 

Start‐up and shut‐down procedures. 

Modes of control and operation sequences. 

Detailed review of the information and organization of the O&M manual. 

Complete listing of contractors and manufacturer contact information. 

Complete listing of spare parts. 

Detailed instructions on the control system. 

Routine preventative maintenance procedures as specified by the designer or recommended by the 

manufacturer. 

Provisions for safety shutdowns, emergency conditions, and interfaces with building management 

systems (BMS) and life‐safety systems (such as fire protection). 

Video tapes of the training sessions to allow future use. 

 

At the last phase of this stage, the commissioning authority will be responsible of preparing a summary 

commissioning report. 

This report uses the final commissioning plan as its template. The report includes all system verification and 

start‐up checklists, and all functional performance test checklists, completed with all test observations, 

problems encountered, corrective actions taken, and re‐test results dated and signed by those carrying out and 

witnessing the tests. 

Where the checklists make reference to other test reports, copies of those reports must be appended. The final 

commissioning report should contain an executive summary addressing design intent conformance for all 

commissioned equipment and systems. The report should include references to all relevant commissioned 

system documentation, and should be organized and tabulated to facilitate access to specific information.  

 

The commissioning authority will make a site review within 10 months after substantial completion, along 

with the contractor and all concerned subcontractors. 

Functional tests and verification will be repeated in order to get the required information. 

Commissioning authority will then have to make another report concerning this site review. 

 

VI‐ List of expected work products  

Commissioning intent, as mentioned earlier in this report is to verify that the project’s energy related systems 

are installed, calibrated and perform according to the owner’s project requirements, basis of design and 

construction documents and to provide the owner with a high level of assurance that the mechanical and 

electrical systems have been installed in the prescribed manner, and operate within the capabilities of the 

documented design and specified equipment capacities. 

 

Therefore our mission will be to provide the owner, in our final commissioning report and our site review 

within 10 months of occupancy, with an objective point of view of the actual state of MEP equipment. 

 

 

 

Page 10: AfDB Field’s office in Abuja Nigeria

AfDB Field office in Abuja 

Page 10/12Project ref : PI12.154 Report n° : 13.116 Date : 16/04/2013

 

VII‐ Testing equipment  

It is be noted that all test equipment required for performing the specified tests shall be provided by 

contractors. Any proprietary vendor specific test equipment shall be provided by that vendor or manufacturer. 

Any portable or hand‐held setup / calibration devices required to initialize any control system shall be made 

available by the control vendor (at no cost) to the commissioning authority.  

 

The instrumentation shall meet the following requirements: 

   

‐ Be of sufficient quality and accuracy to measure system performance within the tolerances required. 

‐ Be calibrated with calibration tags permanently affixed to the instrument.  

 

All items needed to undertake testing and verification as described in the attached annexes should be 

provided by the contractor. 

 

 

VIII‐ Commissioning process milestones, schedules  

Commissioning milestones and schedules cannot be determined exactly for the time being, but will be 

integrated to this report during future revisions once we receive the detailed construction planning. 

 

The startup and testing of systems may proceed prior to final completion of systems. However, the 

commissioning authority shall not perform checkout services that are the primary responsibility of the 

contractor vendor in advance of their testing and checkout, whom in return are responsible to inform the 

commissioning team once their systems are ready to be verified and tested. 

Problems observed will be addressed immediately, responsible parties will be notified. 

Contractor schedules and scheduling is the responsibility of the construction manager. The commissioning 

authority shall provide commissioning scheduling information to the construction manager for review and 

planning activities.  

The commissioning process does not relieve any contractors from their obligations to complete all portions of 

work in a satisfactory manner.    

Throughout project construction, the following table including all systems to be commissioned will be 

updated. 

 

 

 

 

 

 

 

 

 

 

 

 

Page 11: AfDB Field’s office in Abuja Nigeria

AfDB Field office in Abuja 

Page 11/12Project ref : PI12.154 Report n° : 13.116 Date : 16/04/2013

 

Systems to be commissioned

System: Pre‐functional 

checklists 

Equipment 

startup 

Functional 

testing 

Sample 

size Target date: 

Supply air 

 Y/N  Y/N  Y/N  %  N/A 

Return air 

 Y/N  Y/N  Y/N  %  N/A 

Exhaust air 

 Y/N  Y/N  Y/N  %  N/A 

Chilled water 

 Y/N  Y/N  Y/N  %  N/A 

Hot water 

 Y/N  Y/N  Y/N  %  N/A 

HVAC and control  

 Y/N  Y/N  Y/N  %  N/A 

VRV  Y/N  Y/N  Y/N  %  N/A 

Domestic water heating 

&distribution Y/N  Y/N  Y/N  %  N/A 

Domestic water treatment 

 Y/N  Y/N  Y/N  %  N/A 

Electric power generation 

and distribution 

 

Y/N  Y/N  Y/N  %  N/A 

BMS  Y/N  Y/N  Y/N  %  N/A 

Sub‐metering & electronic 

monitoring  Y/N  Y/N  Y/N  %  N/A 

Lighting and related controls  Y/N  Y/N  Y/N  %  N/A 

 

IX‐ Commissioning check‐lists and testing procedures  

Commissioning check‐lists and systems’ testing and verification procedures shall be filled by the resident 

consultant engineer and the concerned subcontractor. 

The commissioning authority will direct and witness some verification operating tests and checks. 

The testing contractor’s technician will inspect and verify the position of each device and interlock that is 

identified on the checklist. Each item shall be signed off as acceptable or failed. 

This test will be repeated for each operating cycle that applies to the system being tested. 

Operating checks shall include all safety cutouts, alarms, and interlocks with smoke control and life safety 

systems during all modes of operation of the system.  

If, during a test, an operating deficiency is observed, appropriate comments shall be added to the checklist 

data sheet. 

The Interface of the monitoring and control system shall be verified. 

The proper response of monitoring and control system controllers and sensors shall be verified. 

 

 

Page 12: AfDB Field’s office in Abuja Nigeria

AfDB Field office in Abuja 

Page 12/12Project ref : PI12.154 Report n° : 13.116 Date : 16/04/2013

 

Final verification: 

 

APAVE will direct and witness the field verification of the final testing report. 

APAVE will select at random percentage of the report data for verification.  

The contractor shall be given sufficient advance notice of the date of field verification. However, he shall not 

be informed in advance of the data points to be verified. The test engineer must use the same instruments (by 

model and serial number) that were used when the original data were determined. 

Failure of an item is defined as the following : 

  ‐ For all readings other than sound, a deviation of more than 10%. 

  ‐ For sound pressure readings, a deviation of 3 decibels. 

  ‐ A failure of more than 10% of the selected items shall result in the failure of  acceptance of the final 

testing report. 

All these deviations are to be followed, unless otherwise referred to or specified. 

Failure of the final testing and balancing report shall require contractor to complete the following work. 

  ‐ Any system failing the verification procedure must be rechecked and corrected. 

  ‐ New total system testing and verification reports must be provided. 

  ‐ Field verification of the new testing and balancing report must be performed. 

If deficiencies are identified during verification, the construction manager will be notified and action taken 

to remedy the deficiency. Once verification is completed, the commissioning authority will provide a 

verification report to the owner. 

Check‐lists and testing procedures are found in the annexes of this report. 

 

Page 13: AfDB Field’s office in Abuja Nigeria

 

 

 

PI12.154   AfDB Field office in Abuja                                                                              Commissioning Plan ‐ April 2013 ‐  1 / 32 

 

 

 

 

 

Testing & Commissioning Procedure 

Electrical Installation 

   

Page 14: AfDB Field’s office in Abuja Nigeria

 

 

 

PI12.154   AfDB Field office in Abuja                                                                              Commissioning Plan ‐ April 2013 ‐  2 / 32 

Table of Contents 1 – Introduction: ........................................................................................................................................... 3 

2 – Objective of the T & C: ............................................................................................................................ 3 

3 – Scope of the T & C Works: ....................................................................................................................... 3 

3.1 – Preliminary Steps for Testing and Commissioning: .......................................................................... 3 

3.2 – Tests & Inspections during Construction: ........................................................................................ 4 

3.3 – Functional Performance Tests: ........................................................................................................ 4 

3.4 – Documentation and Deliverables: ................................................................................................... 4 

4 – Testing and Commissioning (T & C) Procedure: ...................................................................................... 5 

4.1 Tests and Inspections during Construction ......................................................................................... 5 

4.2 Inspection and Test for Low Voltage Installations .............................................................................. 5 

4.2.1 Inspection before Test ................................................................................................................. 5 

4.2.2 Sequence of Tests ........................................................................................................................ 5 

4.2.3 Conductor Continuity ................................................................................................................... 6 

4.2.4 Earth Electrode Resistance .......................................................................................................... 6 

4.2.5 Earth Fault Loop Resistance ......................................................................................................... 6 

4.4 Functional Test of System/Equipment ................................................................................................ 7 

4.4.1 Circuitry Check ............................................................................................................................. 7 

4.4.2 Lighting Installation ...................................................................................................................... 7 

4.4.3 Digital Multifunction Power Meter .............................................................................................. 8 

4.4.4 Equipment and Appliances .......................................................................................................... 9 

4.5 Assessment of Any Characteristics of Equipment Likely to have Harmful Effects .............................. 9 

Appendix A .................................................................................................................................................. 10 

Part1. Items Inspected and Tested ......................................................................................................... 11 

1.1.  StatutoryInspectionandTestforLowVoltage(L.V.)Installation .................................... 11 

1.2.  FunctionalTestofSystem/Equipment ............................................................................... 22 

Part 2: Test Record attached to the Test Certificate .............................................................................. 25 

2.1  TestforLowVoltage(L.V)Installation ................................................................................ 25 

2.2  FunctionalTestofSystem/Equipment’ .............................................................................. 25 

2.3  TestingEquipment ................................................................................................................ 25 

 

Page 15: AfDB Field’s office in Abuja Nigeria

 

 

 

PI12.154   AfDB Field office in Abuja                                                                              Commissioning Plan ‐ April 2013 ‐  3 / 32 

1 – Introduction:  

  The procedures stated in this document cover the activities in preliminary tests and 

inspections, functional performance tests and the commissioning of newly completed electrical 

installations. 

The Contractor shall carry out the T & C works for LEED as detailed in this document. 

2 – Objective of the T & C:  

The objectives of the T & C works are: 

To verify proper functioning of the equipment/system after installation. 

To verify that the performance of the installed equipment/systems meet with the 

specified design intent through a series of tests and adjustments. 

To capture and record performance data of the whole installation as the baseline for 

future operation and maintenance. 

3 – Scope of the T & C Works:    

3.1 – Preliminary Steps for Testing and Commissioning:    Before carrying out T&C, the Contractor shall take the following steps:  

a. Review approved shop drawings and equipment schedules; b. Check manufacturer’s operating instructions and statutory requirements; c. Physically inspect the installation and equipment to determine variations from designs 

and/or specifications. d. Check individual components, e.g. key switches, control equipment, circuit breaker 

status, etc. for proper position and settings for completeness of installation. e. Check inclusion of manufacturer’s typical equipment testing data or factors before T&C 

of particular equipment. 

 

Page 16: AfDB Field’s office in Abuja Nigeria

 

 

 

PI12.154   AfDB Field office in Abuja                                                                              Commissioning Plan ‐ April 2013 ‐  4 / 32 

3.2 – Tests & Inspections during Construction:   

The purpose of these tests is to ensure that all components and systems are in a satisfactory 

and safe condition before start up. Preliminary adjustment and setting of equipment at this 

stage also be carried out at the same time to pave way for the functional performance tests. 

Before carrying out any test, The Contractor shall ensure that the installation complies with all 

relevant statutory requirements and regulations. The T & C works shall also comply with all site 

safety regulatory requirements including but not limited to: 

(i) IEC 60364 “ Electrical Installations of Buildings” 

(ii) Electricity supply rules of the relevant power supply companies  

Or other approved codes and standards. 

  3.3 – Functional Performance Tests:  

The purpose of functional performance tests is to demonstrate that the equipment/installation 

can meet the functional and performance requirements as specified in the General/Particular 

specifications. Functional performance test should proceed from the testing of individual 

components to the testing of different systems in the installation. 

Any performance deficiencies revealed during the functional performance tests must be 

evaluated to determine the cause and whether they are part of the contractual obligations. 

After completion of the necessary corrective measures, the Contractor shall repeat the tests. 

If any test cannot be completed because of circumstances that are beyond the control of the 

Contractor, it shall be properly documented. The contractor shall resume his testing work 

immediately upon the attainment of a suitable testing environment. 

3.4 – Documentation and Deliverables: 

All inspection and T & C results shall be recorded in the data record forms. 

A functional performance test report covering all measured data, data sheets, and a comprehensive summary describing the operation of the system at the time of the functional performance tests shall be prepared and submitted. Deviations in performance from the General/Particular Specifications or the design intent should be recorded, with a description and analysis included. 

 

 

Page 17: AfDB Field’s office in Abuja Nigeria

 

 

 

PI12.154   AfDB Field office in Abuja                                                                              Commissioning Plan ‐ April 2013 ‐  5 / 32 

4 – Testing and Commissioning (T & C) Procedure: 

4.1 Tests and Inspections during Construction 

 

For those tests to be carried out on different systems of the installation during construction to ensure their suitability for operating at the design conditions, certificates of such tests shall be issued together with certificates of any work tests.  The tests and inspection shall include, but not limited to, the followings: (a) Visual inspection; (b) Earth electrode resistance; and (c) Continuity of protective conductor. (d) Voltage measurements. (e) Lux measurements. 

 Details of these tests shall be in accordance with relevant sections of this procedure. 

  4.2 Inspection and Test for Low Voltage Installations 

4.2.1 Inspection before Test 

 

A visual inspection shall be made to verify that the electrical installation /equipment as installed is correctly selected and erected and that there is no apparent damage. The visual inspection shall include a check on the following items, where appropriate:  a. Adequacy of working space, access, and maintenance facilities; b. Connections of conductors; c. Identification of conductors; d. Adequacy of the sizes of conductor in relation to current carrying capacity and voltage 

drop; e. Correct connections of all equipment with special attention to socket outlets, lamp 

holders, isolators, switches, and protective conductors, f. Presence of appropriate devices for isolation and switching; g. Presence of diagrams, instructions and other similar information; 

4.2.2 Sequence of Tests 

The following items, where relevant, are to be tested preferably in the sequence indicated below: 

a. Continuity of protective conductors, including main and supplementary equipotential bonding, 

b. Earth electrode resistance, 

Page 18: AfDB Field’s office in Abuja Nigeria

 

 

 

PI12.154   AfDB Field office in Abuja                                                                              Commissioning Plan ‐ April 2013 ‐  6 / 32 

c. Earth fault loop impedance,  In the event of any test indicating failure to comply, that test and those preceding, the results of which may have been influenced by the fault indicated, shall be repeated after the fault has been rectified. 

4.2.3 Conductor Continuity 

 

Continuity of Protective Conductors Every protective conductor, including all conductors and any extraneous conductive parts used for equipotential bonding should be tested for continuity. The test should be made by connecting together the neutral and protective conductors at the mains position and checking between earth and neutral at every outlet by a continuity tester, which should show a reading near zero. 

4.2.4 Earth Electrode Resistance 

A proper earth electrode resistance tester should be used to measure earth electrode resistance. An alternating current at 50 Hz of a steady value is passed between the earth electrode T and an auxiliary earth electrode T1 placed at a separation distance recommended by the manufacturer of the tester but in any case should not be less than 20 metres away. A second auxiliary earth electrode T2, which may be a metal spike driven into the ground, is then inserted half‐way between T and T1, and the voltage drop between T and T2, divided by the current flowing between T and T1, gives a measured earth electrode resistance of earth electrode T.  For an electrical installation having four or more earth electrodes which are installed more or less in line, following a general direction not exceeding 15� deviation and with separation between adjacent electrodes not less than the recommended distance by the manufacturer of the tester but in any case not less than 20 meters, these electrodes can be used in turn as the auxiliary electrodes for the purpose of measuring the earth electrode resistances.  The following alternative method for measuring the earth electrode resistance may be used if the electricity supply is connected. A loop impedance tester should be connected between the phase conductor at the origin of the installation and the earth electrode with the test link open, and a test performed. This impedance reading could be treated as the electrode resistance. 

4.2.5 Earth Fault Loop Resistance 

The earth fault loop impedance should be measured by a phase‐earth loop tester with a scale calibrated in ohms.  

Page 19: AfDB Field’s office in Abuja Nigeria

 

 

 

PI12.154   AfDB Field office in Abuja                                                                              Commissioning Plan ‐ April 2013 ‐  7 / 32 

The earth fault loop impedance should not exceed the requirements of applicable code.  Before the test begins, it is essential to establish, by inspection, that the earthing conductor and all relevant earth connections are in place, and that the bonding connection to electricity supplier’s earthing facilities is disconnected. Measures should be taken, during the impedance tests especially when the earth leakage protective devices are effectively removed for the duration of the tests, to ensure that the installation is not being used other than by person(s) carrying out the tests. 

4.4 Functional Test of System/Equipment 

 

4.4.1 Circuitry Check 

 

All circuits shall be verified through switching operation to ensure that the circuits are installed in accordance with the designated circuit. The tests shall include but not be limited to the following:  

a. On/off switching of the lighting circuit to ensure that the lighting circuit is installed corresponding to the lighting switch, protective device and labeling; 

b. Switching of the general power circuit to ensure that the circuit corresponds to the protective device such as RCD, RCBO and MCB, and that the protective device performs in accordance with the designated duty; 

c. Switching of the main switch / isolator to ensure the corresponding circuit is properly controlled by the main switch / isolator; 

d. Switching of all sub‐main and main distribution circuits, e.g. bus ducts, cable feeders, underground cables, etc. to ensure the correct isolation of the connected circuit; 

e. Switching of all changeover switches to ensure the changing over sequence corresponds to the design criteria; 

f. Ensuring all the protective devices perform properly against the designated circuit.  

4.4.2 Lighting Installation 

 

Lighting installation shall be tested in terms of its light quality and control as following: a. Before carrying out the lighting measurement and test, all luminaries shall be checked 

against the specified color temperature, beaming angle of spot lamp and aiming angle for exterior floodlights. 

b. The aiming angle of external lighting or planter lighting shall be commissioned so as not to create glare or any obstructive light to external environment. 

Page 20: AfDB Field’s office in Abuja Nigeria

 

 

 

PI12.154   AfDB Field office in Abuja                                                                              Commissioning Plan ‐ April 2013 ‐  8 / 32 

c. Before commissioning and /or setting of lighting control devices which including but not limited to timer switch, occupancy sensor, photocell and infra‐red sensor, the Contractor shall submit commissioning /setting proposal for approval. 

d. Illumination level of lighting installation for individual areas/rooms shall be measured to verify the light output. The Contractor shall submit the proposed locations and height levels for carrying out the measurement of illuminance level for approval before commencement of measurement. Presentation of the measurement result shall be in the form of marked up layout plan for the particular area. 

e. Base on the measured illuminance results for individual areas/rooms, the lighting uniformity of the respective areas /rooms shall be evaluated in terms of minimum to average illuminance ratio. 

f. All grouping of luminaries shall be tested by hand operation of the corresponding switches or timers. 

g. For lighting installation with interface connection to building management system (BMS), or central control and monitoring system (CCMS) or similar central computer control system, the Contractor shall co‐ordinate with other contractors responsible for such computer control system, if required, to demonstrate proper control function of the lighting installation. 

 

4.4.3 Digital Multifunction Power Meter 

 

The digital multifunction power meter shall be tested to verify the measurement, recording and interfacing functions as required in the General Specification.  Prior to the test for every digital multifunction power meter, the Contractor shall provide manufacturer’s calibration certificate for each meter for checking on the accuracy. The Contractor shall provide testing kit to verify the reading accuracy of the digital multifunction power meter.  For installation of digital multifunction power meter with connection to building management system (BMS), or central control and monitoring system (CCMS) or similar central computer monitoring system, the Contractor shall co‐ordinate with other contractor responsible for such computer monitoring system, if required, to demonstrate proper functioning and interfacing of the meter.  For installation of digital multifunction power meter without external connection to building management system or CCMS, the interface functions including digital and analogue output shall be tested by means of plugging in communication module provided by the Contractor.  The replacement mechanism of the meter shall be tested. The test shall demonstrate that the replacement of the meter does not require the switching off of the respective switchgear. 

Page 21: AfDB Field’s office in Abuja Nigeria

 

 

 

PI12.154   AfDB Field office in Abuja                                                                              Commissioning Plan ‐ April 2013 ‐  9 / 32 

Current transformers shorting block to prevent open circuiting the current transformers shall also be tested.  

4.4.4 Equipment and Appliances 

 

Testing on electrical equipment and appliances supplied within the electrical installation, e.g. meters, fans, etc. shall be carried out in accordance with the relevant sections of other Building Services Branch Testing and Commissioning Procedures for other building services installations and manufacturer’s recommended testing procedures.  

4.5 Assessment of Any Characteristics of Equipment Likely to have Harmful Effects 

 

Before carrying out the T&C, the Contractor shall conduct assessment for any characteristics of equipment likely to have harmful effects upon other electrical equipment or other services, or impair the supply. Those characteristics include the following:  

a. Overvoltages; b. Undervoltages; c. Fluctuating loads; d. Unbalanced loads; e. Power factor; f. Starting currents; g. Harmonic currents; h. Direct current (d.c.) feedback; i. High frequency oscillations; and j. Necessity for additional connection to earth. 

The Contractor shall, after conduct the assessment, submit an assessment report for consideration.  

 

 

 

 

   

Page 22: AfDB Field’s office in Abuja Nigeria

 

 

 

PI12.154   AfDB Field office in Abuja                                                                              Commissioning Plan ‐ April 2013 ‐  10 / 32 

 

 

 

 

 

 

AppendixA 

 

 

 

 

 

 

 

 

 

Page 23: AfDB Field’s office in Abuja Nigeria

 

 

 

PI12.154   AfDB Field office in Abuja                                                                              Commissioning Plan ‐ April 2013 ‐  11 / 32 

  Item tested / checked by: Contractor 

Item witnesses by:  

Part1. Items Inspected and Tested    

1.1. StatutoryInspectionandTestforLowVoltage(L.V.)Installation   

1.1.1.  Visual Inspection      

1.1.1.1 Working Space and Facilities     a. Adequacy working space and safe access provided for switch room and /or

electrical facilities.

Yes/No/N.A.  Yes/No/N.A. 

b. Entrance /exit to switch room and/or electrical facilities are free of obstruction

Yes/No/N.A.  Yes/No/N.A. 

c. Suitable locking facilities provided for switch room and /or electrical facilities.

Yes/No/N.A.  Yes/No/N.A. 

d. Suitable lighting provision provided for switch room and /or electrical

facilities.

Yes/No/N.A.  Yes/No/N.A. 

e. Suitable ventilation provision provided for switch room and /or electrical facilities.

Yes/No/N.A.  Yes/No/N.A. 

f. Suitable tools for withdrawal of fuses at fuse board provided.

Yes/No/N.A.  Yes/No/N.A. 

g. A warning notice ‘DANGER—SUBSTATION, UNAUTHORISED ENTRY PROHIBITED’ provided at every entrance of switch room.

Yes/No/N.A.  Yes/No/N.A. 

h. Fire barriers and other measures for protection against thermal effects are properly installed.

Yes/No/N.A.  Yes/No/N.A. 

i. Danger notices, warning notices, schematic diagrams, instructions and similar information are correctly and adequately provided.

Yes/No/N.A.  Yes/No/N.A. 

j. Warning notices for substations and switchrooms provided

Yes/No/N.A.  Yes/No/N.A. 

k. Warning notices for earthing and main bonding connections provided

Yes/No/N.A.  Yes/No/N.A. 

l. All switchgears, distribution boards and electrical equipment properly labelled.

Yes/No/N.A.  Yes/No/N.A. 

 

Tested / Checked by : (Name of Contractor’s Representative)  

Signature:  

Witnessed by : (Name(s)) 

Signature   

Page 24: AfDB Field’s office in Abuja Nigeria

 

 

 

PI12.154   AfDB Field office in Abuja                                                                              Commissioning Plan ‐ April 2013 ‐  12 / 32 

   Item tested / 

checked by: Contractor 

Item witnesses by:  

1.1.1.2 Switchboard, Main Switch and Circuit Breaker  

   

a. An up-to-date notice of periodic inspection and testing provided at point of supply (i.e. a switchboard, a circuit breaker or a distribution board) of the installation.

Yes/No/N.A.  Yes/No/N.A. 

b. Circuits, fuses, switches, terminals, etc. are provided with a legible and durable identification label.

Yes/No/N.A.  Yes/No/N.A. 

c. No visible damage to impair safety.

Yes/No/N.A.  Yes/No/N.A. 

d. Work done properly recorded in logbook.

Yes/No/N.A.  Yes/No/N.A. 

e. An up-to-date schematic diagram displayed.

Yes/No/N.A.  Yes/No/N.A. 

f. All accessible live parts screened with insulating plate or earthed metal.

Yes/No/N.A.  Yes/No/N.A. 

g. All exposed conductive parts effectively earthed.

Yes/No/N.A.  Yes/No/N.A. 

h. Earthing system effectively connected.

Yes/No/N.A.  Yes/No/N.A. 

i. Warning notice displayed at main bonding connections

Yes/No/N.A.  Yes/No/N.A. 

j. All protective devices are functioned properly and correctly set.

Yes/No/N.A.  Yes/No/N.A. 

k. Suitable interlock scheme provided to prevent parallel operation of two or more sources of supply and 4-pole incoming and interconnecting circuit breakers provided for supply to be taken from more than one source and is interconnected.

Yes/No/N.A.  Yes/No/N.A. 

l. Electrically and mechanically interlocked 4-pole changeover device(s) where standby generator set(s) is installed.

Yes/No/N.A.  Yes/No/N.A. 

m. The breaking capacities of all circuit breakers / interconnection devices are able to withstand the prospective fault current.

Yes/No/N.A.  Yes/No/N.A. 

n. Protective relays have been correctly set and overcurrent protective devices suitably set for all circuits.

Yes/No/N.A.  Yes/No/N.A. 

 

Tested / Checked by : (Name of Contractor’s Representative)  

Signature:  

Witnessed by : (Name(s)) 

Signature   

Page 25: AfDB Field’s office in Abuja Nigeria

 

 

 

PI12.154   AfDB Field office in Abuja                                                                              Commissioning Plan ‐ April 2013 ‐  13 / 32 

   Item tested / 

checked by: Contractor 

Item witnesses by:  

o. Protective type current transformers are used for protective relays.

Yes/No/N.A.  Yes/No/N.A. 

p. A means of isolation provided for every circuit.

Yes/No/N.A.  Yes/No/N.A. 

q. Operation of circuit breakers and main switches checked.

Yes/No/N.A.  Yes/No/N.A. 

r. Control, indication and alarm functions checked.

Yes/No/N.A.  Yes/No/N.A. 

s. No undersized conductor used between the main busbar and fuse/MCB.

Yes/No/N.A.  Yes/No/N.A. 

t. Fuses/MCB’s matching the lowest rated conductor in the circuit.

Yes/No/N.A.  Yes/No/N.A. 

u. Suitable cable terminations provided.

Yes/No/N.A.  Yes/No/N.A. 

v. Cable conductors of correct phases connected.

Yes/No/N.A.  Yes/No/N.A. 

w. Single-pole devices for protection or switching connected in phase conductors only.

Yes/No/N.A.  Yes/No/N.A. 

   1.1.1.3 Distribution Board  

   

a. A warning notice ‘DANGER’ provided on the front panel of every distribution board.

Yes/No/N.A.  Yes/No/N.A. 

b. A notice of periodic testing provided at or near the main distribution board incorporating a residual current device.

Yes/No/N.A.  Yes/No/N.A. 

c. Distribution boards securely mounted on suitable supports.

Yes/No/N.A.  Yes/No/N.A. 

d. A suitable switch provided to control each distribution board.

Yes/No/N.A.  Yes/No/N.A. 

e. Phase barriers for 3-phase distribution board provided.

Yes/No/N.A.  Yes/No/N.A. 

f. The breaking capacity of MCB is correct according to calculation

Yes/No/N.A.  Yes/No/N.A. 

g. Suitable tools for withdrawal of fuses at a fuse board provided, where necessary.

Yes/No/N.A.  Yes/No/N.A. 

h. Circuits connected to MCB or fuse in accordance with the schematic diagram.

Yes/No/N.A.  Yes/No/N.A. 

 

Tested / Checked by : (Name of Contractor’s Representative)  

Signature:  

Witnessed by :  Signature  

Page 26: AfDB Field’s office in Abuja Nigeria

 

 

 

PI12.154   AfDB Field office in Abuja                                                                              Commissioning Plan ‐ April 2013 ‐  14 / 32 

  

  Item tested / checked by: Contractor 

Item witnesses by:  

1.1.1.4 Conductors, Cables and wirings  

   

a. No visible damage to impair safety.

Yes/No/N.A.  Yes/No/N.A. 

b. All live conductors and their methods of insulation, in relation to design currents of circuits and to the operating currents of the protective devices, are properly selected and erected.

Yes/No/N.A.  Yes/No/N.A. 

c. All cables, flexible cords, switches, plugs and socket outlets, accessories and equipment are found to be in good working conditions.

Yes/No/N.A.  Yes/No/N.A. 

d. All conductors are correctly and securely connected and identified.

Yes/No/N.A.  Yes/No/N.A. 

e. Armoured cables properly terminated to metal casing or trunking by proper cable glands.

Yes/No/N.A.  Yes/No/N.A. 

f. Cables passing through smoke lobby protected by enclosures of adequate fire rating.

Yes/No/N.A.  Yes/No/N.A. 

g. Non-sheathed cables protected by conduit, trunking or ducting.

Yes/No/N.A.  Yes/No/N.A. 

h. Cables and ductings adequately supported.

Yes/No/N.A.  Yes/No/N.A. 

i. Cables at distribution board or busbar terminated with cable lugs.

Yes/No/N.A.  Yes/No/N.A. 

j. Main cables connected up with correct polarity

Yes/No/N.A.  Yes/No/N.A. 

k. Cables protected against mechanical damage and suitably supported.

Yes/No/N.A.  Yes/No/N.A. 

l. All exposed metal parts including the armour effectively earthed. Yes/No/N.A.  Yes/No/N.A.  

Tested / Checked by : (Name of Contractor’s Representative)  

Signature:  

Witnessed by : (Name(s))  

Signature   

 

 

 

Page 27: AfDB Field’s office in Abuja Nigeria

 

 

 

PI12.154   AfDB Field office in Abuja                                                                              Commissioning Plan ‐ April 2013 ‐  15 / 32 

  Item tested / checked by: Contractor 

Item witnesses by:  

1.1.1.5 Busbar trunking system including rising mains  

   

a. The rising mains, lateral mains and meter boards positioned at places accessible from public area.

Yes/No/N.A.  Yes/No/N.A. 

b. Fire barriers provided where the busbar trunking system passes through floor slabs or walls designated as fire barriers.

Yes/No/N.A.  Yes/No/N.A. 

c. Cables passing through smoke lobby protected by enclosures of adequate fire rating.

Yes/No/N.A.  Yes/No/N.A. 

d. Non-sheathed cables protected by conduit, trunking or ducting.

Yes/No/N.A.  Yes/No/N.A. 

e. Busbar trunking systems, cables and ductings adequately supported.

Yes/No/N.A.  Yes/No/N.A. 

f. The bolts, nuts, screws, etc. for busbar supports, busbar connections have been checked for correct tightness in accordance with manufacturers’ recommendations.

Yes/No/N.A.  Yes/No/N.A. 

g. The busbar trunking system is properly and correctly installed and aligned.

Yes/No/N.A.  Yes/No/N.A. 

h. No dust, foreign particles and deleterious substances are accumulated on the busbar trunking system.

Yes/No/N.A.  Yes/No/N.A. 

i. The busbar trunking system is free from condensation.

Yes/No/N.A.  Yes/No/N.A. 

j. Armoured cables properly terminated to metal casing or trunking by proper cable glands.

Yes/No/N.A.  Yes/No/N.A. 

k. Suitable cable lugs used for terminating cables.

Yes/No/N.A.  Yes/No/N.A. 

l. Precaution against corrosion taking on aluminium conductor joined to copper conductor.

Yes/No/N.A.  Yes/No/N.A. 

m. Cutout fuses for tapping off supply fitted with insulated carriers. Yes/No/N.A.  Yes/No/N.A.  

Tested / Checked by : (Name of Contractor’s Representative)  

Signature:  

Witnessed by : (Name(s))  

Signature   

 

 

Page 28: AfDB Field’s office in Abuja Nigeria

 

 

 

PI12.154   AfDB Field office in Abuja                                                                              Commissioning Plan ‐ April 2013 ‐  16 / 32 

 

  Item tested / checked by: Contractor 

Item witnesses by:  

1.1.1.6 Final circuits  

   

a. All fuses and single pole switches connected to the phase conductors only with correct polarity.

Yes/No/N.A.  Yes/No/N.A. 

b. Wiring for emergency lightings and fire services installation segregated from other wirings.

Yes/No/N.A.  Yes/No/N.A. 

c. Low voltage circuits segregated from extra low voltage circuits.

Yes/No/N.A.  Yes/No/N.A. 

d. Cables of all phases and neutral of the circuit bunched and contained in the same conduit.

Yes/No/N.A.  Yes/No/N.A. 

e. Exposed insulated non-sheathed cables protected.

Yes/No/N.A.  Yes/No/N.A. 

f. Wiring inside false ceiling protected by conduit/trunking or metallic sheath.

Yes/No/N.A.  Yes/No/N.A. 

g. Socket outlets installed below 1.5m from floor being shuttered type complying with the prescribed requirements.

Yes/No/N.A.  Yes/No/N.A. 

h. No socket outlet installed close to water tap, gas tap or cooker so as to avoid danger.

Yes/No/N.A.  Yes/No/N.A. 

i. Floor socket outlets protected with suitable cover.

Yes/No/N.A.  Yes/No/N.A. 

j. No 2-pin sockets installed. All socket outlets connected with protective conductors and live conductors terminated at correct terminals.

Yes/No/N.A.  Yes/No/N.A. 

k. Radial final circuits using socket outlets.

Yes/No/N.A.  Yes/No/N.A. 

l. Final circuits using socket outlets.

Yes/No/N.A.  Yes/No/N.A. 

m. Final circuits using industrial socket outlets.

Yes/No/N.A.  Yes/No/N.A. 

n. Circuit protective conductor is formed by the enclosure and a separate protective conductor between the earthing terminal of socket outlet and its associated metal box provided.

Yes/No/N.A.  Yes/No/N.A. 

 

Tested / Checked by : (Name of Contractor’s Representative)  

Signature:  

Witnessed by : (Name(s)) 

Signature   

Page 29: AfDB Field’s office in Abuja Nigeria

 

 

 

PI12.154   AfDB Field office in Abuja                                                                              Commissioning Plan ‐ April 2013 ‐  17 / 32 

   Item Tested/ 

checked by: Contractor 

Witnessed by: 

o. Circuit protective conductor is not formed by the enclosure and a separate protective conductor to the earthing terminal of socket outlet provided.

Yes/No/N.A.  Yes/No/N.A. 

a. Residual current device having a rated residual operating current not exceeding 30mA provided for all socket outlets.

Yes/No/N.A.  Yes/No/N.A. 

b. Minimum sizes of protective conductors are provided for limitation of protective conductor impedance.

Yes/No/N.A.  Yes/No/N.A. 

c. Means of isolation provided for every fixed appliance.

Yes/No/N.A.  Yes/No/N.A. 

d. All chokes, starters and capacitors of discharge lamps enclosed in earthed metal box(es) and suitably ventilated.

Yes/No/N.A.  Yes/No/N.A. 

 e. Phase conductors connected to the centre contact of the Edison-type screw

lamp holders.

 Yes/No/N.A. 

 Yes/No/N.A. 

f. No switches other than a switch fed from a safety source or operated by an insulation cord or rod or a push-button type of switch having an insulated button of a large surface area provided in bathrooms.

Yes/No/N.A.  Yes/No/N.A. 

g. Shaver supply unit complying with EN 60742 or equivalent.

Yes/No/N.A.  Yes/No/N.A. 

h. Socket outlet in bathroom installed in zone 3 (i.e. 0.6m away from shower basin or bathtub); and protected by a 30mA residual current device or protected by an isolating transformer to EN 60742.

Yes/No/N.A.  Yes/No/N.A. 

i. No fixed luminaire nor fixed heater having unguarded heating elements installed within reach of a person using the bath or shower.

Yes/No/N.A.  Yes/No/N.A. 

j. Appliances exposed to weather being splash-proof type.

Yes/No/N.A.  Yes/No/N.A. 

k. Luminaires, switches, sockets and plugs, cable couplers installed outdoor, being splashproof type.

Yes/No/N.A.  Yes/No/N.A. 

l. General/site lighting readily accessible to the public supplied from a safety source.

Yes/No/N.A.  Yes/No/N.A. 

m. General/site lighting not readily accessible to the public and not supplied from a safety source, protected by RCD having a rated residual operating current not exceeding 30mA.

Yes/No/N.A.  Yes/No/N.A. 

 

Tested / Checked by : (Name of Contractor’s Representative)  

Signature:  

Witnessed by :  Signature  

Page 30: AfDB Field’s office in Abuja Nigeria

 

 

 

PI12.154   AfDB Field office in Abuja                                                                              Commissioning Plan ‐ April 2013 ‐  18 / 32 

     Item tested / 

checked by: Contractor 

Item witnesses by:  

1.1.1.7 Earthing and Bonding  

   

a. Earth rod electrode(s) having a diameter as shown on the drawing

Yes/No/N.A.  Yes/No/N.A. 

b. Copper tape earth electrode having a cross section of not less than 25 mm x 3 mm.

Yes/No/N.A.  Yes/No/N.A. 

c. Copper plate earth electrode not less than 3mm in thickness and having a maximum dimension of 1200mm x 1200mm

Yes/No/N.A.  Yes/No/N.A. 

d. No gas/water pipe used as earth electrodes..

Yes/No/N.A.  Yes/No/N.A. 

e. A test link provided at the main earthing terminal.

Yes/No/N.A.  Yes/No/N.A. 

f. Minimum size of protective conductor used

Yes/No/N.A.  Yes/No/N.A. 

g. Protective conductor up to and including 6mm2 with green and yellow insulation sheath used throughout its length.

Yes/No/N.A.  Yes/No/N.A. 

h. Proper bonding conductors copper or equivalent used for connection to the earthing terminal of the electricity supplier’s transformer(s) or underground cable(s).

Yes/No/N.A.  Yes/No/N.A. 

i. Copper links provided at joints of metallic trunking which forms part of a protective conductor.

Yes/No/N.A.  Yes/No/N.A. 

j. Separate protective conductors provided for all flexible conduits.

Yes/No/N.A.  Yes/No/N.A. 

k. A warning notice ‘SAFETY ELECTRICAL CONNECTION—DO NOT REMOVE provided at all main earthing and bonding connections.

Yes/No/N.A.  Yes/No/N.A. 

l. Main equipotential bonding conductors effectively connected to main water pipes, main gas pipes, other services pipes/ducting and exposed metallic parts of structural framework.

Yes/No/N.A.  Yes/No/N.A. 

 

Tested / Checked by : (Name of Contractor’s Representative)  

Signature:  

Witnessed by : (Name(s))  

Signature   

    

 

Page 31: AfDB Field’s office in Abuja Nigeria

 

 

 

PI12.154   AfDB Field office in Abuja                                                                              Commissioning Plan ‐ April 2013 ‐  19 / 32 

  Item Tested/ checked by: Contractor 

Witnessed by: 

m. Supplementary equipotential bonding effectively provided between exposed conductive parts and extraneous conductive parts.

Yes/No/N.A.  Yes/No/N.A. 

n. Exposed conductive parts of fixed equipment installed outside equipotential zone effectively earthed for 0.4 sec. disconnection.

Yes/No/N.A.  Yes/No/N.A. 

o. Exposed conductive parts of fixed equipment installed within equipotential zone effectively earthed for 5 sec. disconnection.

Yes/No/N.A.  Yes/No/N.A. 

p. Effectiveness of the main equipotential bonding connection to the main earthing terminal and lightning protection system.

Yes/No/N.A.  Yes/No/N.A. 

q. Earthing conductors of adequate size. Yes/No/N.A.  Yes/No/N.A. 

   

Tested / Checked by : (Name of Contractor’s Representative)  

Signature:  

Witnessed by : (Name(s))  

Signature   

       

Page 32: AfDB Field’s office in Abuja Nigeria

 

 

 

PI12.154   AfDB Field office in Abuja                                                                              Commissioning Plan ‐ April 2013 ‐  20 / 32 

  Item Tested/ 

checked by: Contractor 

Witnessed by: 

 1.1.1.9 Motors /Transformers

   

a. No visible damage to impair safety

Yes/No/N.A.  Yes/No/N.A. 

b. A local switch was provided to control every motor

Yes/No/N.A.  Yes/No/N.A. 

c. Means provided to prevent unexpected restarting of motors where such restarting might cause danger

Yes/No/N.A.  Yes/No/N.A. 

d. Flexible conduits terminated with suitable brass bushes

Yes/No/N.A.  Yes/No/N.A. 

e. Separate supply to motor heaters having its terminals screened, with warning notice provided.

Yes/No/N.A.  Yes/No/N.A. 

f. All accessible live parts screened with insulating plate or g. earthed metal

Yes/No/N.A.  Yes/No/N.A. 

h. Proper ventilation provided to avoid excessive temperature rise Yes/No/N.A.  Yes/No/N.A.                  

Tested / Checked by : (Name of Contractor’s Representative)  

Signature:  

Witnessed by : (Name(s))  

Signature   

    

Page 33: AfDB Field’s office in Abuja Nigeria

 

 

 

PI12.154   AfDB Field office in Abuja                                                                              Commissioning Plan ‐ April 2013 ‐  21 / 32 

  Item Tested/ checked by: Contractor 

Witnessed by: 

1.1.2  Conductor Continuity

   

1. All protective conductors including all conductors and any extraneous conductive parts used for equipotential bonding have been tested for continuity.

Yes/No/N.A.  Yes/No/N.A. 

2. All final ring circuit conductors including the protective conductors have been tested for continuity

Yes/No/N.A.  Yes/No/N.A. 

3. Conductor continuity test results recorded in Annex I.

Yes/No/N.A.  Yes/No/N.A. 

 

1.1.3  Earth Electrode Resistance    1. The resistance to earth has been measured at the position of every earth

electrode and of the main earth terminal. The results are satisfactory.

Yes/No/N.A.  Yes/No/N.A. 

2. Details of earth electrode and resistance test results recorded in Annex I

Yes/No/N.A.  Yes/No/N.A. 

1.1.4  Earth Fault Loop Impedance    1. The earth fault loop impedance of all circuits has been found satisfactory

for operation of the protective devices for earth fault protection.

Yes/No/N.A.  Yes/No/N.A. 

2. Earth fault loop impedance measurement results recorded on Annex I

Yes/No/N.A.  Yes/No/N.A. 

 

 

 

 

 

Tested / Checked by : (Name of Contractor’s Representative)  

Signature:  

Witnessed by : (Name(s))  

Signature   

    

 

Page 34: AfDB Field’s office in Abuja Nigeria

 

 

 

PI12.154   AfDB Field office in Abuja                                                                              Commissioning Plan ‐ April 2013 ‐  22 / 32 

  Item tested / checked by: Contractor 

Item witnesses by:  

1.2. FunctionalTestofSystem/Equipment   

1.3.1.  Lightning Protection System      

a. The continuity between air terminations and earthing terminations is tested.

Yes/No/N.A.  Yes/No/N.A. 

b. Measured earth termination network resistance to earth not more than 10 Ohm when the connection to main earthing terminal disconnected.

Yes/No/N.A.  Yes/No/N.A. 

c. Test results recorded in Annex I Yes/No/N.A.  Yes/No/N.A. 

1.3.2.  Circuitry Check 

   

a. All circuits including lighting and power circuits have been verified through switching operation that they are installed in accordance with the designated circuits.

Yes/No/N.A.  Yes/No/N.A. 

1.3.3.  Charger and Battery Set

   

a. The original factory test certificates of the charger and battery have been checked and found satisfactory.

Yes/No/N.A.  Yes/No/N.A. 

b. The charger is connected to the mains supply through a suitable rated fuse.

Yes/No/N.A.  Yes/No/N.A. 

c. Batteries connections have been done properly.

Yes/No/N.A.  Yes/No/N.A. 

d. Instruments, indicating lamps, fuses, relays and labels on battery charger are provided and installed properly.

Yes/No/N.A.  Yes/No/N.A. 

e. The capacity of the charger is capable of recharging the batteries from fully discharged to fully charged within the specified duration.

Yes/No/N.A.  Yes/No/N.A. 

f. The charger output on load with batteries disconnected is satisfactory.

Yes/No/N.A.  Yes/No/N.A. 

g. The charger current on load with batteries disconnected is satisfactory. Yes/No/N.A.  Yes/No/N.A.  

Tested / Checked by : (Name of Contractor’s Representative)  

Signature:  

Witnessed by : (Name(s))  

Signature   

   

Page 35: AfDB Field’s office in Abuja Nigeria

 

 

 

PI12.154   AfDB Field office in Abuja                                                                              Commissioning Plan ‐ April 2013 ‐  23 / 32 

h. The capacity of batteries has been checked and tested by interrupting the mains input to the charger and actuation / operation of the connected devices and the results are satisfactory.

Yes/No/N.A.  Yes/No/N.A. 

i. The functions and indications of charger fail / main fail / battery disconnected / boost charge / trickle charge, mains and battery have been checked and tested and the results are satisfactory.

Yes/No/N.A.  Yes/No/N.A. 

1.3.4  Lighting Installation

   

1.3.4.1  Switchboard and Circuit Breakers  

   

a. Colour temperature of light fittings was checked and as specified.

Yes/No/N.A.  Yes/No/N.A. 

b. All lamps are the correct wattage and voltage ratings Yes/No/N.A.  Yes/No/N.A. 

c. Beam angle of spot lamp is commissioned. Yes/No/N.A.  Yes/No/N.A. 

d. Aiming angle of external lighting or planter lighting is commissioned so as not to create glare or any obstructive light to external environment.

Yes/No/N.A.  Yes/No/N.A. 

e. Exterior floodlights have been aimed according to requirements

Yes/No/N.A.  Yes/No/N.A. 

f. Fluorescent lamps have the correct phosphor.

Yes/No/N.A.  Yes/No/N.A. 

1.3.4.2  Lighting Control (On/Off and Dimming)

   

a. Groups of luminaries are assigned to the correct position in grid switch or grid single circuit dimmer and tested by hand operation.

Yes/No/N.A.  Yes/No/N.A. 

b. Lighting control system (e.g. timer switch, occupancy sensor, photocell and infra-red sensor, etc.) are correctly commissioned and set.

Yes/No/N.A.  Yes/No/N.A. 

c. Timer switch operated lighting control system can properly operate as commissioned.

Yes/No/N.A.  Yes/No/N.A. 

d. Photocell operated lighting control system can properly operate as commissioned.

Yes/No/N.A.  Yes/No/N.A. 

 

Tested / Checked by : (Name of Contractor’s Representative)  

Signature:  

Witnessed by : (Name(s)) 

Signature   

 

 

Page 36: AfDB Field’s office in Abuja Nigeria

 

 

 

PI12.154   AfDB Field office in Abuja                                                                              Commissioning Plan ‐ April 2013 ‐  24 / 32 

  Item Tested/ checked by: Contractor 

Witnessed by: 

   e. Infra-red sensor operated lighting control system can properly operate as

commissioned.

Yes/No/N.A.  Yes/No/N.A. 

f. Occupancy sensor operated lighting control system can properly operate as commissioned.

Yes/No/N.A.  Yes/No/N.A. 

g. FM radio switches have been configured to the relevant receivers

Yes/No/N.A.  Yes/No/N.A. 

h. Lighting control by CCMS or BMS is tested and properly functioned.

Yes/No/N.A.  Yes/No/N.A. 

1.3.4.3  Lighting Measurement  

   

a. Illuminance level of lighting installation for individual areas /rooms is measured under its design condition.

Yes/No/N.A.  Yes/No/N.A. 

b. Measurement results recorded. Yes/No/N.A.  Yes/No/N.A. 

1.3.5  Digital Multifunction Power Meter

   

a. Manufacturer’s calibration certificate for each meter is provided. Yes/No/N.A.  Yes/No/N.A. 

b. The readings of electrical parameters by the meter and by test kit are recorded in Annex I

Yes/No/N.A.  Yes/No/N.A. 

c. Remote monitoring functions by CCMS or BMS are tested and found satisfactory..

Yes/No/N.A.  Yes/No/N.A. 

d. Interfacing functions for self-contained meter are tested by using plug-in communication module and found satisfactory.

Yes/No/N.A.  Yes/No/N.A. 

e. Replacement mechanism of meter is tested and found satisfactory.

Yes/No/N.A.  Yes/No/N.A. 

f. Current transformer (C.T.) shorting block to prevent open circuiting the C.T. is provided and tested.

Yes/No/N.A.  Yes/No/N.A. 

 

 

Tested / Checked by : (Name of Contractor’s Representative)  

Signature:  

Witnessed by : (Name(s)) 

Signature   

 

Page 37: AfDB Field’s office in Abuja Nigeria

 

 

 

PI12.154   AfDB Field office in Abuja                                                                              Commissioning Plan ‐ April 2013 ‐  25 / 32 

  Test record attached 

Part 2: Test Record attached to the Test Certificate  

2.1 TestforLowVoltage(L.V)Installation 

2.1.1.  Conductor continuity Measurement    Yes/No/N.A. 

2.1.2.  Earth Electrode Resistance Measurement 

Yes/No/N.A. 

2.1.3.  Earth Fault Loop Impedance Measurement 

Yes/No/N.A. 

   

2.2 FunctionalTestofSystem/Equipment’ 

 

2.2.1.   Earth Electrode Resistance Measurement for Lightning Protection System 

 

Yes/No/N.A. 

2.2.2.  Test of Digital Multifunction Power Meter /Power Analyzer  

Yes/No/N.A. 

2.3 TestingEquipment

2.3.1. List of Testing equipment

Yes/No/N.A. 

 

 

 

 

 

 

 

 

Page 38: AfDB Field’s office in Abuja Nigeria

 

 

 

PI12.154   AfDB Field office in Abuja                                                                              Commissioning Plan ‐ April 2013 ‐  26 / 32 

2.1.1.  Conductor continuity Measurement   

Circuit No. or Detailed 

Equipment 

Continuity of protective Conductors 

  

Measured Resistance (Ohm) at outlet 

Continuity of Ring Final Circuit   

Measured Resistance (Ohm) for 

 Remarks 

Phase Conductor 

Neutral Conductor 

Protective Conductor 

           

Note: The test method for ring final circuit is only applicable when the circuit has been inspected throughout, prior to the test, to ascertain that no interconnection (multi-loops) exists on the ring circuit. Otherwise, the testing methods stipulated in the previous Part of the Guidance Note 3 to BS7671, should be adopted instead.

Tested / Checked by : (Name of Contractor’s Representative)  

Signature:  

Witnessed by : (Name(s))  

Signature   

Page 39: AfDB Field’s office in Abuja Nigeria

 

 

 

PI12.154   AfDB Field office in Abuja                                                                              Commissioning Plan ‐ April 2013 ‐  27 / 32 

2.1.2.  Earth Electrode Resistance Measurement   

Earth Electrode Designation 

Types, Materials and Sizes/Dimensions of Earth 

Electrode 

Resistance to Earth at Position of main 

Electrode (Ohm) 

Resistance to Earth at Position of main Earth Terminal 

(Ohm) 

 Remarks 

  Rod / Tape / Plate / Others: ( ) Copper / Stainless Steel / Galvanised Steel/ Others: ( ) Size /dimension /diameter: __________ 

     

Separation of Earth Electrodes (for installation having multiple rod electrodes): _________________ (m) Description of Bonding Connections to the Point of Supply: __________________________________________________________________________________________________________________________________________________________________________

_____________________________________________________________________________________________

Tested / Checked by : (Name of Contractor’s Representative)  

Signature:  

Witnessed by : (Name(s))  

Signature   

Page 40: AfDB Field’s office in Abuja Nigeria

 

 

 

PI12.154   AfDB Field office in Abuja                                                                              Commissioning Plan ‐ April 2013 ‐  28 / 32 

2.1.3.  Earth fault Loop Impedance Measurement   

 

Circuit No. or Detailed Equipment 

Earth Fault Loop Impedance (Ohm) 

Remarks 

     

Tested / Checked by : (Name of Contractor’s Representative)  

Signature:  

Witnessed by : (Name(s))  

Signature   

Page 41: AfDB Field’s office in Abuja Nigeria

 

 

 

PI12.154   AfDB Field office in Abuja                                                                              Commissioning Plan ‐ April 2013 ‐  29 / 32 

2.2.2.  Test of Digital Multifunction Power Meter /Power Analyzer

A. Equipment Details

Circuit Designation : _______________________ Brand and Model Number : _______________________ Current Transformer Ratio : _______________________ Voltage Transformer Ratio : _______________________

B. Reading Accuracy Test

Parameters Meter reading Test Kit reading % error

R.M.S Voltage (V)

L1-N L2-N L3-N L1-L2 L2-L3 L3-L1

R.M.S Current (A)

L1 L2 L3 N

3 phase average

Active Power (kW)

L1 L2 L3

3 phase total

Reactive Power (kVAr)

L1 L2 L3

3 phase total

Apparent Power (kVA)

L1 L2 L3

3 phase total

Active Energy (kWh)

Instantaneous Cumulated

Page 42: AfDB Field’s office in Abuja Nigeria

 

 

 

PI12.154   AfDB Field office in Abuja                                                                              Commissioning Plan ‐ April 2013 ‐  30 / 32 

2.2.2.  Test of Digital Multifunction Power Meter /Power Analyzer

B. Reading Accuracy Test (continued)

Parameters Meter reading Test Kit reading % error

Frequency

Power Factor

L1 L2 L3

Demand Current (A)

L1 L2 L3

Demand Active Power (kW)

3 phase total

Demand Apparent Power (kVA)

3 phase total

THD (%)

Voltage Current

Voltage THD of Order (%)

3 5 7 9 11 13 15 17 19 21 23 25 27 29 31

Page 43: AfDB Field’s office in Abuja Nigeria

 

 

 

PI12.154   AfDB Field office in Abuja                                                                              Commissioning Plan ‐ April 2013 ‐  31 / 32 

2.2.2.  Test of Digital Multifunction Power Meter /Power Analyzer

B. Reading Accuracy Test (continued)

Parameters Meter reading Test Kit reading % error

Current THD of Order (%)

3 5 7 9 11 13 15 17 19 21 23 25 27 29 31

Tested / Checked by : (Name of Contractor’s Representative)  

Signature:  

Witnessed by : (Name(s))  

Signature   

Page 44: AfDB Field’s office in Abuja Nigeria

 

 

 

PI12.154   AfDB Field office in Abuja                                                                              Commissioning Plan ‐ April 2013 ‐  32 / 32 

2.3.1.  List of Testing Equipment 

 

Type Model Serial No. Of Instrument

Date of Calibration

Tested / Checked by : (Name of Contractor’s Representative)  

Signature:  

Witnessed by : (Name(s))  

Signature   

Page 45: AfDB Field’s office in Abuja Nigeria

 

PI12.154   AfDB Field office in Abuja                                                                              Commissioning Plan ‐ April 2013 ‐  1 / 19 

 

 

 

 

 

Testing & Commissioning Procedure 

Emergency Generator Installation 

   

Page 46: AfDB Field’s office in Abuja Nigeria

 

PI12.154   AfDB Field office in Abuja                                                                              Commissioning Plan ‐ April 2013 ‐  2 / 19 

1 – Introduction: 

  The Procedures stated in this document cover the activities in preliminary tests and 

inspections, functional performance tests and the commissioning of newly completed 

installations and existing ones after major alteration.  

The contractor shall carry out the T & C works as detailed in this document. 

2 – Objective of the T & C: 

The objectives of the T & C works are: 

To verify proper functioning of the equipment/system after installation. 

To verify that the performance of the installed equipment/systems meet with the 

specified design intent through a series of tests and adjustments. 

To capture and record performance data of the whole installation as the baseline for 

future operation and maintenance. 

3 – Scope of the T & C Works: 

  3.1 – Tests & Inspections during Construction:   

The purpose of these tests is to ensure that all components and systems are in a satisfactory 

and safe condition before start up. Preliminary adjustment and setting of equipment at this 

stage also be carried out at the same time to pave way for the functional performance tests. 

Before carrying out any test, The Contractor shall ensure that the installation complies with all 

relevant statutory requirements and regulations. The T & c works shall also comply with all site 

safety regulatory requirements.   

 

  3.2 – Functional Performance Tests:  

The purpose of functional performance tests is to demonstrate that the equipment/installation 

can meet the functional and performance requirements as specified in the General/Particular 

specifications. Functional performance test should proceed from the testing of individual 

components to the testing of different systems in the installation. 

Any performance deficiencies revealed during the functional performance tests must be 

evaluated to determine the cause and whether they are part of the contractual obligations. 

After completion of the necessary corrective measures, the Contractor shall repeat the tests. 

Page 47: AfDB Field’s office in Abuja Nigeria

 

PI12.154   AfDB Field office in Abuja                                                                              Commissioning Plan ‐ April 2013 ‐  3 / 19 

If any test cannot be completed because of circumstances that are beyond the control of the 

Contractor, it shall be properly documented. The contractor shall resume his testing work 

immediately upon the attainment of a suitable testing environment. 

  3.3 – Commissioning and Statutory Inspection:   

Commissioning is the advancement of an installation from the stage static completion to full working conditions and to meet the performance requirements as specified in the General/Particular Specification. This will include setting into operation and regulation of the installation. It is expected that fine‐tuning of the commissioned system shall be done by the Contractor to match system performance to the actual needs of the building occupier more closely. 

  3.4 – Documentation and Deliverables: 

All inspection and T & C results shall be recorded in the data record forms. 

A functional performance test report covering all measured data, data sheets, and a comprehensive summary describing the operation of the system at the time of the functional performance tests shall be prepared and submitted. Deviations in performance from the General/Particular Specifications or the design intent should be recorded, with a description and analysis included. 

4 – T & C Procedure: 

  4.1 Tests and Inspections during Construction 

Certain tests will be carried out on different systems of the installation during construction to ensure their suitability for operating at the design conditions. Certificates of such tests have to be issued together with certificates of any work tests.  N.B: The following tests should be conducted in accordance with the procedures as specified by the manufacturers.    

Page 48: AfDB Field’s office in Abuja Nigeria

 

PI12.154   AfDB Field office in Abuja                                                                              Commissioning Plan ‐ April 2013 ‐  4 / 19 

  4.1.1 Emergency Generator 

a. Visual inspection on engine, alternator, radiator, and various systems of the generating set 

b. Full operating test c. Control function test d. Circuit & engine protection tests e. Fuel consumption test f. Step load acceptance test 

 

  4.1.2 Control Cubicle 

a. Visual inspection on control panel b. Performance tests on individual components c. Temperature rise test 

 

  4.1.3 Underground/ Daily Services Fuel Tank 

a. Visual inspection on welding surfaces and primer coating b. Hydraulic test 

 

4.2 Functional Performance Tests 

  4.2.1 Emergency Generator 

a. Pre‐commissioning inspection on various components / systems b. Control function test c. Dummy load test d. Battery charger output test e. Step load acceptance test 

  4.2.2 Control Cubicle 

a. Pre‐commissioning inspection on various components / systems b. Performance tests of individual components such as voltmeter, ammeter, frequency 

meter, wattmeter, indicating lamps, buttons and switches c. Circuit protection & load transfer tests 

 

Page 49: AfDB Field’s office in Abuja Nigeria

 

PI12.154   AfDB Field office in Abuja                                                                              Commissioning Plan ‐ April 2013 ‐  5 / 19 

  4.2.3 Main/Daily Services Fuel Tank 

a. Pre‐commissioning inspection on the construction, welding, painting and components of tank & pipe work 

b. Hydraulic test  

4.3 Commissioning and Statutory Inspections 

In Addition to tests performed in the previous sections. 

4.3.1EmergencyGeneratora. Insulation test b. Earthing protection test c. Noise level measurement 

   

Page 50: AfDB Field’s office in Abuja Nigeria

 

PI12.154   AfDB Field office in Abuja                                                                              Commissioning Plan ‐ April 2013 ‐  6 / 19 

 

 

 

 

 

AppendixA

   

Page 51: AfDB Field’s office in Abuja Nigeria

 

PI12.154   AfDB Field office in Abuja                                                                              Commissioning Plan ‐ April 2013 ‐  7 / 19 

TestingandCommissioningForms

ForEmergencyGeneratorInstallation 

 

Part1:DetailofProject1.1 Project title (with location):  

1.2 Contractor/Sub –contractor: 

 

Part2:ItemsInspectedandTested

  Item tested/ checked     by Contractor 

Items witnesses by 

2.1 Main tank The welding has been examined and the effectiveness of the welding and standard of workmanship is satisfactory.  

Yes / No  Yes / No 

The metal surface has been properly prepared in accordance with the specification.  

Yes / No  Yes / No 

The manufacturer’s application procedure for the primer has been followed and the type of primer, the numbers of coatings are in accordance with the specification.  

Yes / No  Yes / No 

The Main tank has been subjected to hydraulic test to a pressure as specified and the results are satisfactory.  

Yes / No  Yes / No 

2.2 Daily service fuel tank  

The daily service fuel tank has been fabricated and welded in accordance with the specifications and drawings.  

Yes / No  Yes / No 

The pipe work & socket connections (for filling, overflow, drainage, return and vent) have been properly installed at the fuel tank in accordance with the specifications and drawings.  

Yes / No  Yes / No 

One quick closing valve has been installed properly with all necessary linkage for operation from outside the building.  

Yes / No  Yes / No 

The fuel tank has been fitted with an approved content gauge unit and level sensing equipment.  

Yes / No  Yes / No 

The fuel tank has been subjected to hydraulic test to a pressure as specified and the results are satisfactory.

Yes / No Yes / No

Page 52: AfDB Field’s office in Abuja Nigeria

 

PI12.154   AfDB Field office in Abuja                                                                              Commissioning Plan ‐ April 2013 ‐  8 / 19 

Tested / Checked by : (Name of Contractor’s Representative)  

Signature:  

Witnessed by : (Name(s))  

Signature   

2.3 Visual inspection  

The Generating Set has been properly fixed on a common steel section base frame. 

Yes / No  Yes / No 

Protection screen has been provided on all moving parts.  Yes / No  Yes / No 

Protection guard has been provided on hot exhaust.  Yes / No  Yes / No 

The fresh‐water‐cooled radiator has been properly fixed and there is no water leakage. 

Yes / No  Yes / No 

The radiator cooling fins and water tank are in good condition and properly fixed. 

Yes / No  Yes / No 

The water circulation pump with thermostatically controlled temperature regulator has been properly fixed. 

Yes / No  Yes / No 

The engine mounted instrument panel has been fixed properly and c/w lubrication oil temp. and cooling temp. gauges, tachometer and hour meter. 

Yes / No  Yes / No 

The lubrication oil system with replaceable element type’s filter has been properly fixed. 

Yes / No  Yes / No 

The fuel oil system c/w filter, fuel transfer pumps has been properly installed. 

Yes / No  Yes / No 

The fuel control solenoid c/w emergency shut off valve has been provided and properly installed. 

Yes / No  Yes / No 

The tubular exhaust silencer has been properly installed.  Yes / No  Yes / No 

For remote radiator, if applicable, c/w break tank booster pump, heat exchanger etc. has been properly installed. 

Yes / No  Yes / No 

The enclosure to the alternator satisfy IP21 or as specified  Yes / No  Yes / No 

Anti‐condensate heater for the alternator has been provided and proper fixed. 

Yes / No  Yes / No 

Where specified, facilities for generation at 380/220V have been provided. 

Yes / No  Yes / No 

Starting batteries have been provided and properly installed.  Yes / No  Yes / No 

     

Page 53: AfDB Field’s office in Abuja Nigeria

 

PI12.154   AfDB Field office in Abuja                                                                              Commissioning Plan ‐ April 2013 ‐  9 / 19 

  Tested / Checked by : (Name of Contractor’s Representative)  

  Signature:  

Witnessed by : (Name(s))  

Signature   

  Item tested/ checked by  

Contractor 

Items witnesses    by 

2.4 Pre‐commissioning inspection   Fuel engine Radiator water is at right level.  Yes / No  Yes / No Lubrication oil is at right level and with replaceable filter.  Yes / No  Yes / No The engine exhaust has been properly fixed and covered with asbestos‐fee insulation. 

Yes / No  Yes / No 

The engine anti‐vibration mounting is effective.  Yes / No  Yes / No Proper replaceable air filter has been installed.  Yes / No  Yes / No Effective and adequate earth bonding have been provided for the engine and alternator. 

Yes / No  Yes / No 

Alternator Batteries electrolyte is at right level.  Yes / No  Yes / No Batteries output voltage is as specified.  Yes / No  Yes / No The alternator output terminal is at correct phase sequence.  Yes / No Yes / No

Control cubicle Permanent engraved labels have been provided for all accessories, fixed with machined brass screws.

Yes / No  Yes / No 

All control wirings are fitted with ferrules. Yes / No  Yes / No The following devices are provided in the control cubicle: a) Voltmeter & selector switch Yes / No  Yes / No b) Ammeter & selector switch Yes / No  Yes / No c) Frequency meter Yes / No  Yes / No d) Wattmeter Yes / No  Yes / No e) Auto/off/manual selector switch Yes / No  Yes / No f) Emergency stop Yes / No  Yes / No g) Engine starting Yes / No  Yes / No h) Engine stopping Yes / No  Yes / No i) Lamp test Yes / No  Yes / No Indicating lamp & reset button for: a) Engine fault Yes / No  Yes / No b) Alarm sounder Yes / No  Yes / No     

Page 54: AfDB Field’s office in Abuja Nigeria

 

PI12.154   AfDB Field office in Abuja                                                                              Commissioning Plan ‐ April 2013 ‐  10 / 19 

  Item tested/ checked by Contractor 

Items witnesses by  

Indication lamp for: Emergency stop operated (Red)  Yes / No  Yes / No System failure (Amber)  Yes / No  Yes / No No voltage (Amber)  Yes / No  Yes / No Low DC voltage (Amber)  Yes / No  Yes / No High DC voltage (Amber)  Yes / No  Yes / No Fail to sync (Amber)  Yes / No  Yes / No Overcurrent alarm (Amber)  Yes / No  Yes / No High oil temperature (Amber)  Yes / No  Yes / No Breaker failure (ON/OFF) (Red)  Yes / No  Yes / No Breaker tripped (Red)  Yes / No  Yes / No Overcurrent (Red)  Yes / No  Yes / No Short circuit (Red)  Yes / No  Yes / No Reverse power (Red)  Yes / No  Yes / No Overcrank (Red)  Yes / No  Yes / No Under frequency (Red)  Yes / No  Yes / No Over frequency (Red)  Yes / No  Yes / No Under voltage (Red)  Yes / No  Yes / No Over voltage (Red)  Yes / No  Yes / No Phase rotation (Red)  Yes / No  Yes / No Generator running (Green)  Yes / No  Yes / No Breaker open (Green)  Yes / No  Yes / No Breaker closed (Green)  Yes / No  Yes / No Water temperature failure   Yes / No  Yes / No Oil pressure failure   Yes / No  Yes / No Over speed  Yes / No Yes / No

No starting  Yes / No  Yes / No 

Daily fuel tank low level  Yes / No  Yes / No 

Daily fuel tank high level  Yes / No  Yes / No 

Test lamp switch is provided  Yes / No  Yes / No The following tests has been done and delivered to the Commissioning authority: 

   

Insulation test  Yes / No  Yes / No Control functions test  Yes / No  Yes / No Dummy load test  Yes / No  Yes / No Earthing protection test  Yes / No  Yes / No Battery charger output test  Yes / No  Yes / No Step‐load acceptance test  Yes / No  Yes / No 

Page 55: AfDB Field’s office in Abuja Nigeria

 

PI12.154   AfDB Field office in Abuja                                                                              Commissioning Plan ‐ April 2013 ‐  11 / 19 

Alternator overload protection test Yes / No Yes / No Alternator output protection test Yes / No Yes / No Reverse power protection test Yes / No Yes / No Metering equipments test for accuracy Yes / No Yes / No Synchronizing and load sharing test Yes / No Yes / No Totalizing panelboard: Yes / No  Yes / No System status panel Yes / No   Yes / No  Alarm silence push button Yes / No   Yes / No  Alarm horn Yes / No   Yes / No  Lamp test Yes / No   Yes / No  LED indication lamps Yes / No   Yes / No  

 

 

  Tested / Checked by : (Name of Contractor’s Representative)  

  Signature:  

Witnessed by : (Name(s))  

Signature   

Page 56: AfDB Field’s office in Abuja Nigeria

 

PI12.154   AfDB Field office in Abuja                                                                              Commissioning Plan ‐ April 2013 ‐  12 / 19 

Part3:TestRecordattachedtotheTestForms3.1 EmergencyGeneratorInstallation

3.1.1 Equipment Details (i) Generating Set 

1. Manufacturer 2. Model 3. Net prime rating (MCR) (kW) 

(ii) Fuel Engine 1. Make 2. Model 3. Serial No. 4. Rated power (kW) 5. Speed (rpm) 6. Governor 7. Turbocharger (type/model) 

(iii) Alternator 1. Make 2. Model 3. Serial No. 4. Rated kVA 5. Voltage (V) / Full load current (A) 6. Phase / Rated p.f. 7. Insulation class 

(iv) Starting Battery 1. Manufacturer 2. Make/Model No. 3. No. of battery / Voltage (V) 4. Ampere hour 5. Starting time (sec) 

(v) Lifting Hoist 1. Manufacturer 2. Make / Model No. 3. Safe working load (kg) 4. Lifting height (m) 5. Test Certificate *Yes/No (vi) Other Accessories  

 

 Tested / Checked by : (Name of Contractor’s Representative)  

  Signature:  

Witnessed by : (Name(s)) 

Signature   

Page 57: AfDB Field’s office in Abuja Nigeria

 

PI12.154   AfDB Field office in Abuja                                                                              Commissioning Plan ‐ April 2013 ‐  13 / 19 

 

3.1.2 Type of Control 

Starting               *Automatic/Manual Loading Transfer to Generating Set         *Automatic/Manual Stopping              *Automatic/Manual Load Transfer to Mains           *Automatic/Manual  

3.1.3 Insulation Resistance Test (Temporarily open alternator star point) 

1. Brown phase (L1) to earth          Megaohm‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐ 2. Black phase (L2) to earth           Megaohm‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐ 3. Grey phase (L3) to earth           Megaohm‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐ 4. Brown phase (L1) to Black phase (L2)         Megaohm‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐ 5. Black phase (L2) to Grey phase (L3)         Megaohm‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐ 6. Grey phase (L3) to Brown phase (L1)        Megaohm‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐ 

 

 

 Tested / Checked by : (Name of Contractor’s Representative)  

  Signature:  

Witnessed by : (Name(s))  

Signature   

Page 58: AfDB Field’s office in Abuja Nigeria

 

PI12.154   AfDB Field office in Abuja                                                                              Commissioning Plan ‐ April 2013 ‐  14 / 19 

3.1.4

Control Function Test  Tested  Results  Remarks 

1. Starting  Manual       

Simulate Mains Failure 

Test 1       

Test 2        

Delay Start Timer       

Delay Repeat Start       

       

2. Stopping  Manual       

Resumption of Mains       

Delay Stop Timer       

3. Engine Protection 

Overload Trip (MCCB)       

Engine Overspeed  HL       

LL       

Low Lub‐oil Pressure (kPa) 

HL       

LL       

High Water Temp.0(C) 

HL       

LL       

Under Voltage Trip       

Overvoltage Trip       

Under Frequency (Hz)       

4. Others  Response Time from Mains  Failure to Changeover (Sec) 

     

Battery 3 Attempt Start      Quick closing Mechanism      Governor Function      Voltage Regulator (346V - 380V)      Auto-starting of Vent. Fan      Manual Override Facilities      Phase Sequence of Alternator Output      Frequency Setting      

  TDH (% should be less than 5%)      

  Presence of multiples of the 3rd harmonic (shouldn’t be)

     

  Each harmonic should be less than 3 %      

 

 Tested / Checked by : (Name of Contractor’s Representative)  

  Signature:  

Witnessed by : (Name(s))  

Signature   

Page 59: AfDB Field’s office in Abuja Nigeria

 

PI12.154   AfDB Field office in Abuja                                                                              Commissioning Plan ‐ April 2013 ‐  15 / 19 

 3.1.5. Dummy Load Test (Parameters to be recorded at 15 min interval during the whole dummy load test period) 

 

Time from start                                     

Duration (HR)  

1/2  1/2  1  1  1  ½ 

Duration (HR)(actual)                                     

Frequency (Hz)                                     

Current (Amp) 

L1                                     

L2                                     

L3                                     

Voltage (Volts) 

L1‐L2/ L1‐N 

                                   

L2‐L3/ L2‐N 

                                   

L3‐L1/ L3‐N 

                                   

Dummy Load 

KW                                     

% Full Load  0%  25%  50%  100%  100%  `110% Engine Speed (RPM)                                    Cooling Water Temp.                                    Engine Oil Temp. (oC)                                    Engine Oil Pressure (kPa)                                    Fuel Consumption (L)                                    Engine Room Temp. (OC)                                    System operation has been tested according to the specification, and results were delivered to the CxA:

Remarks: 

  

 

 Tested / Checked by : (Name of Contractor’s Representative)  

  Signature:  

Witnessed by : (Name(s))  

Signature   

 

 

Page 60: AfDB Field’s office in Abuja Nigeria

 

PI12.154   AfDB Field office in Abuja                                                                              Commissioning Plan ‐ April 2013 ‐  16 / 19 

3.1.6. Earthing Protection Test 

 

Measured Earthing Resistance   

Earthing Relay Make                  ____________  Model                ____________  Serial No            ____________  Rated Current   ____________   

Current Setting   

Time Setting   

Function Test   

 

3.1.7. Noise Level Measurements Values should be less than 65 dbA at 1 m outside the room all around (As per specifications) 

Location  Mean Sound Level (dBA)

Background  Inside Generator Room (1m from Generator Set)

 

Outside Generator Room (1m from Radiator Exhaust)

 

Outside Generator Room (1m from Door)

 

Outside Generator Room (1m from Louvre)

 

Outside Generator Room (1m from flue discharge if possible)

 

Outside Generator Room (at the nearest Noise Sensitive Receiver)

 

 

 

 Tested / Checked by : (Name of Contractor’s Representative)  

  Signature:  

Witnessed by : (Name(s))  

Signature   

 

 

 

 

Page 61: AfDB Field’s office in Abuja Nigeria

 

PI12.154   AfDB Field office in Abuja                                                                              Commissioning Plan ‐ April 2013 ‐  17 / 19 

This section is dedicated to the efficiency of the generators: 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 Tested / Checked by : (Name of Contractor’s Representative)  

  Signature:  

Witnessed by : (Name(s))  

Signature   

 

   

Page 62: AfDB Field’s office in Abuja Nigeria

 

PI12.154   AfDB Field office in Abuja                                                                              Commissioning Plan ‐ April 2013 ‐  18 / 19 

AppendixB   

Page 63: AfDB Field’s office in Abuja Nigeria

 

PI12.154   AfDB Field office in Abuja                                                                              Commissioning Plan ‐ April 2013 ‐  19 / 19 

ListofCalibratedInstrumentNecessary

FortheT&CWorks 

Performance Specification  Accuracy  Maximum period between calibrations 

Tachometer 30‐5000 rpm     

Multi‐tester AVO) 0‐1000V 0‐10A 0‐W 

   

Clamp on ammeter 0-1000A    Insulation tester 500V-1000V    

Pressure Gauge  0‐100kPa               0‐1000kPa 

   

Sound meter 0-120 dbA    Other necessary testing equipment    

 

Page 64: AfDB Field’s office in Abuja Nigeria

 

PI12.154   AfDB Field office in Abuja                                                                              Commissioning Plan ‐ April 2013 ‐  1 / 11 

 

 

 

 

 

Testing & Commissioning Procedure 

Split Unit System 

   

Page 65: AfDB Field’s office in Abuja Nigeria

 

PI12.154   AfDB Field office in Abuja                                                                              Commissioning Plan ‐ April 2013 ‐  2 / 11 

TableofContents1 – General: ................................................................................................................................................... 3 

1.1 – Purpose of the Testing & Commissioning Procedures ..................................................................... 3 

1.2 – Reference to Other Controlling Documents .................................................................................... 3 

1.3 – Responsibility ................................................................................................................................... 3 

2 – Tests & Inspections to be Carried Out : .................................................................................................. 3 

3 – Testing Equipment : ................................................................................................................................ 3 

Appendix A .................................................................................................................................................... 4 

Appendix B .................................................................................................................................................... 6 

Split Unit Checklist Inspection (1) ............................................................................................................. 7 

Split Unit Checklist Inspection(2) .............................................................................................................. 8 

 

   

Page 66: AfDB Field’s office in Abuja Nigeria

 

PI12.154   AfDB Field office in Abuja                                                                              Commissioning Plan ‐ April 2013 ‐  3 / 11 

1–General:

1.1–PurposeoftheTesting&CommissioningProceduresHaving already been inspected as material in their reserved location, the purpose of this 

document is to ensure that all split units are in a good condition and operating properly.  

1.2–ReferencetoOtherControllingDocuments 1.2.1 –ReferenceDocuments

      ‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐ 

1.2.2 –ReferenceDrawings

      Refer to Appendix A                 

1.3–ResponsibilityThe main contractor will carry out the testing and commissioning  with association of this 

subcontractor and the related supplier.  

2–Tests&InspectionstobeCarriedOut:Visual inspection and performance test of split unit will be carried out and recorded on the 

relative forms.  

3–TestingEquipment:The following instruments are to be provided before proceeding in the testing and 

commissioning of the split unit system.  

  a. Clamp‐multimeter  

  b. Ballometer  

  c. Temperature and humidity meter  

The testing equipment should be approved by the Engineer. 

   

Page 67: AfDB Field’s office in Abuja Nigeria

 

PI12.154   AfDB Field office in Abuja                                                                              Commissioning Plan ‐ April 2013 ‐  4 / 11 

 

 

 

 

 

AppendixA

List of References Drawings  

   

Page 68: AfDB Field’s office in Abuja Nigeria

 

PI12.154   AfDB Field office in Abuja                                                                              Commissioning Plan ‐ April 2013 ‐  5 / 11 

 

 

 

 

   

Building Drawing No. Rev Drawing Name

Status Date Comments

Page 69: AfDB Field’s office in Abuja Nigeria

 

PI12.154   AfDB Field office in Abuja                                                                              Commissioning Plan ‐ April 2013 ‐  6 / 11 

 

 

 

 

 

AppendixB

Testing & Commissioning Forms  

   

Page 70: AfDB Field’s office in Abuja Nigeria

 

PI12.154   AfDB Field office in Abuja                                                                              Commissioning Plan ‐ April 2013 ‐  7 / 11 

SplitUnitChecklistInspection(1)Building: __________            Date:________ 

Floor:__________            Related Drawings:_________ 

Room No:_________ 

 

Item  Description  Complying  Not 

Complying 

Comments 

1  Indoor unit installation      

2  Indoor unit fixation      

3  Outdoor unit installation      

4  Outdoor unit fixation      

5  Condensate drain pipe installation      

6  Refrigerant pipes installation      

7  Pipes insulation      

8  Filters condition      

9  Thermostat Condition      

10  Electrical connection & disconnect

switch      

11  Grounding is installed      

12  Physical condition      

13  Tagging & Labeling      

14  Cleanliness      

Comments: 

___________________________________________________________________

___________________________________________________________________ 

Sub‐Contractor Representative  

 

Name 

 

Signature 

 

Date 

Main Contractor Representative  

 

Name 

 

Signature 

 

Date 

Engineer Representative  

 

Name 

 

Signature 

 

Date 

Page 71: AfDB Field’s office in Abuja Nigeria

 

PI12.154   AfDB Field office in Abuja                                                                              Commissioning Plan ‐ April 2013 ‐  8 / 11 

SplitUnitChecklistInspection(2)Building: _________            Date:_________ 

Location: _________      Related Drawings:_________   Room: ________  

Number of filters: _______ 

Refrigerant type: ________ 

 

Indoor Unit    Outdoor Unit  

Manufacturer     Motor data    

Model Number     Manufacturer    

Serial Number     Model Number    

Type     Serial Number    

    Power    

Motor data     FLC    

Manufacturer     Power factor    

Model Number        

Serial Number     Compressor    

Power     Manufacturer    

FLC     Model Number    

Power factor     Serial Number    

    Power    

    Low pressure cut‐off    

    High pressure cut‐off   

 

   

Page 72: AfDB Field’s office in Abuja Nigeria

 

PI12.154   AfDB Field office in Abuja                                                                              Commissioning Plan ‐ April 2013 ‐  9 / 11 

Fan       Fan    

No. of fan     No. of fan    

Fan type     Fan type    

Fan CFM     Fan CFM    

       

       

Performance test   Design   Actual   Performance test   Design   Actual  

Current      Suction pressure      

Voltage       Discharge pressure      

Total air flow       Voltage      

Ent. Air DB/WB      Compressor Amps      

Lvg. Air DB/WB      Fan Motor Amps      

 

Comments:  

____________________________________________________________________________________________________________________ 

_____________________________________________________________________________________________________________________ 

 

Sub‐Contractor Representative  

 

Name 

 

Signature 

 

Date 

Main Contractor Representative  

 

Name 

 

Signature 

 

Date 

Engineer Representative  

 

Name 

 

Signature 

 

Date  

 

Page 73: AfDB Field’s office in Abuja Nigeria

 

PI12.154   AfDB Field office in Abuja                                                                              Commissioning Plan ‐ April 2013 ‐  10 / 11 

 

This section is dedicated to the power efficiency test for each split unit:  

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Sub‐Contractor Representative  

 

Name 

 

Signature 

 

Date 

Main Contractor Representative  

 

Name 

 

Signature 

 

Date 

Engineer Representative  

 

Name 

 

Signature 

 

Date  

Page 74: AfDB Field’s office in Abuja Nigeria

 

PI12.154   AfDB Field office in Abuja                                                                              Commissioning Plan ‐ April 2013 ‐  11 / 11 

 

This section is dedicated to the test of noise level: 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

   

Sub‐Contractor Representative  

 

Name 

 

Signature 

 

Date 

Main Contractor Representative  

 

Name 

 

Signature 

 

Date 

Engineer Representative  

 

Name 

 

Signature 

 

Date  

Page 75: AfDB Field’s office in Abuja Nigeria

 

PI12.154   AfDB Field office in Abuja                                                                              Commissioning Plan ‐ April 2013 ‐  1 / 20 

 

 

 

 

 

Testing & Commissioning Procedure 

AHU & VAV 

   

Page 76: AfDB Field’s office in Abuja Nigeria

 

PI12.154   AfDB Field office in Abuja                                                                              Commissioning Plan ‐ April 2013 ‐  2 / 20 

TableofContents1 – General : .................................................................................................................................................. 3 

1.1 – Purpose of the Testing & Commissioning Procedures ..................................................................... 3 

1.2 – Reference to Other Controlling Documents .................................................................................... 3 

1.3 – Responsibility ................................................................................................................................... 3 

2 – Tests & Inspections to be Carried Out : .................................................................................................. 3 

2.1 – Visual Inspection: ............................................................................................................................. 3 

2.2 – Operational Tests: ............................................................................................................................ 3 

2.5 – Tolerance .......................................................................................................................................... 4 

3 – Testing Equipment : ................................................................................................................................ 5 

4 – Safety: ..................................................................................................................................................... 5 

Appendix A .................................................................................................................................................... 6 

Appendix B .................................................................................................................................................... 8 

FCU’s Checklist & Start‐up Inspection ....................................................................................................... 9 

VAV’s visual Inspection Checklist ............................................................................................................ 11 

AHU Fan Performance Test Sheet ........................................................................................................... 12 

Duct Traverse Readings ........................................................................................................................... 14 

Terminal Air Distribution Readings ......................................................................................................... 16 

Coil Performance Test Sheet ................................................................................................................... 17 

Variable Air Volume Boxes ...................................................................................................................... 18 

AHU Schematic ........................................................................................................................................ 19 

 

   

Page 77: AfDB Field’s office in Abuja Nigeria

 

PI12.154   AfDB Field office in Abuja                                                                              Commissioning Plan ‐ April 2013 ‐  3 / 20 

1–General:

1.1–PurposeoftheTesting&CommissioningProceduresHaving already been inspected as materials and installed in their reserved location the purpose 

of this document is to ensure that:  

  ‐ The AHU(s) are in a good condition and operating properly. 

  ‐ Airflows in relevant ducts & air terminals are as per design drawings.   

1.2–ReferencetoOtherControllingDocuments 1.2.1 –ReferenceDocuments

      ‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐ 

1.2.2 –ReferenceDrawings

      Refer to Appendix A                 

1.3–ResponsibilityThe main contractor will carry out the testing and commissioning with the related supplier.  

2–Tests&InspectionstobeCarriedOut:The following tests and inspections will be carried out and recorded on the relative forms.  

 

2.1–VisualInspection:Before Fan operation, Visual Inspection shall be carried out to ensure that the material has no 

defects and installation is proper. Refer to visual inspection checklist for fans.  

   

2.2–OperationalTests:Before running the fan, make sure that all fire dampers, duct volume dampers, splitters 

dampers and outlets dampers, splitters dampers and outlets dampers are fully opened. Run the 

fan and check if it is giving the required design flow. Then proceed airflow‐balancing starting 

with the terminals with least resistance & work towards the terminals with greater resistance. 

The terminal with the greatest resistance might be the most remote one it the one that have a 

lot of duct direction changes.  

   

Page 78: AfDB Field’s office in Abuja Nigeria

 

PI12.154   AfDB Field office in Abuja                                                                              Commissioning Plan ‐ April 2013 ‐  4 / 20 

Using the Airflow Meter (Hood for ceiling diffusers and rotating vane for side grilles), airflow 

rate can be measured at each terminal. Duct volume dampers & splitter dampers shall be 

adjusted to distribute the required flow in the various branches. Airflow velocity in duct (Duct 

Traverse reading) shall be measured by a Pitot Traverse; several velocities should be taken to 

get the average velocity. Volumetric airflow rate can then be calculated by multiplying the final 

average velocity by the duct area. Fan static pressure (inlet, outlet, total) shall be measured by 

Micro‐Manometer. Fan & Motor speed, electric Current, Voltage etc…. Shall be measured as 

well.  

For AHU’s serving VAV’s units, system shall be balanced at maximum design data, and then 

remeasured at simulated partial load conditions. Each VAV box will be considered as a small 

independent system by itself.  

All measurements and readings shall be recorded in the relevant performance sheets. 

For AHU’s coils water balancing refer to (Secondary chilled and hot water systems).  

 

2.5–ToleranceFor air system, the tolerances on terminals and fans are as follows: 

1. Supply, return and exhaust fans shall not be less than 95%.  

2. For any space the flow should be within – 5% and – 10%.  

    ‐ Space with one outlet, the tolerance is as above.  

    ‐ Space with two outlets, the tolerance is + or – 10%.  

    ‐ Space with 3 outlets or more, the tolerances is + or – 10%.  

3. Return and exhaust inlets, the tolerance is + or – 10%.   

   

Page 79: AfDB Field’s office in Abuja Nigeria

 

PI12.154   AfDB Field office in Abuja                                                                              Commissioning Plan ‐ April 2013 ‐  5 / 20 

3–TestingEquipment:The following instruments are to be provided before proceeding in the testing and 

commissioning of the system:  

  a. Tachometer  

  b. Clamp‐multimeter  

  c. Ballometer  

  d. Micro Manemeter / Pitot tube  

  e. Anemometer  

  f. Temperature & Pressure gauges 

The testing equipment should be approved by the Engineer.  

4–Safety: Skilled Technicians should do all tests operation under the supervision of Senior 

Mechanical Engineer. 

The Operator should be fully equipped with safety equipment as per the Safety 

Manual Applied in the project  

   

Page 80: AfDB Field’s office in Abuja Nigeria

 

PI12.154   AfDB Field office in Abuja                                                                              Commissioning Plan ‐ April 2013 ‐  6 / 20 

 

 

 

 

 

AppendixA

List of References Drawings  

   

Page 81: AfDB Field’s office in Abuja Nigeria

 

PI12.154   AfDB Field office in Abuja                                                                              Commissioning Plan ‐ April 2013 ‐  7 / 20 

 

 

 

 

   

Building Drawing No. Rev Drawing Name

Status Date Comments

Page 82: AfDB Field’s office in Abuja Nigeria

 

PI12.154   AfDB Field office in Abuja                                                                              Commissioning Plan ‐ April 2013 ‐  8 / 20 

 

 

 

 

 

AppendixB

Testing & Commissioning Forms  

   

Page 83: AfDB Field’s office in Abuja Nigeria

 

PI12.154   AfDB Field office in Abuja                                                                              Commissioning Plan ‐ April 2013 ‐  9 / 20 

AHU’sChecklist&Start‐upInspectionBuilding: __________            Date:________ 

Floor:__________            Related Drawings:_________  Room No:_________ 

Item  Description  Complying Not 

Complying

Comments 

1  AHU located as per drawings  

2  AHU is clean and undamaged  

3  Anti‐vibration  system  installed properly  

4  AHU  is  totally  isolated  from  support base  

5  Joints  in  between  sections  properly made and airtight  

6  Access  doors  &  sealing  gaskets properly fitted  

7  Locking handles are working properly  

8  Heating and cooling coils connections 

9  Valves,  motorized  valves  and accessories  

10  Filters  are  clean,  accessible  and undamaged  

11  Condensate  drain  pipe  and  pan connections  

12  Fan  and  fan  motor  anti‐vibration system  

13  Fan drive (pulleys, belts, alignment & tension) 

14  Supply,  return  and  fresh  air  duct connections  

15  Fire  &  volume  dampers  are  totally open  

16  Outlets dampers are totally open  

17  Electrical  connections,  disconnect switch are made properly  

18  Grounding  

19  Frequency  modulator  installed properly (VAV – AHU) 

 

 20  Economizing fan is inter‐lock with       

Page 84: AfDB Field’s office in Abuja Nigeria

 

PI12.154   AfDB Field office in Abuja                                                                              Commissioning Plan ‐ April 2013 ‐  10 / 20 

AHU (Eco. AHU) 21  Ventilation Duct is connected 

properly (Eco. AHU) 

     

22  Motorized Volume Damper is connected properly  

     

23  Lubrication        

24  Tagging & Labeling        

AHU Start‐Up 25  Provisions are made for TAB 

measurements  

     

26  Star delta timer setting correctly        

27  Motor current reaching design value  

     

28  Fan rotation is correct       

29  Motor and fan free from vibration        

30  No seepage of lubricant from the housing  

     

 

Comments: 

___________________________________________________________________ 

___________________________________________________________________ 

 

Sub‐Contractor Representative  

 

Name 

 

Signature 

 

Date 

Main Contractor Representative  

 

Name 

 

Signature 

 

Date 

Engineer Representative  

 

Name 

 

Signature 

 

Date    

Page 85: AfDB Field’s office in Abuja Nigeria

 

PI12.154   AfDB Field office in Abuja                                                                              Commissioning Plan ‐ April 2013 ‐  11 / 20 

VAV’svisualInspectionChecklistBuilding: _________              Date: _________ 

Location: _________          Related Drawings: _________     

Room: ________           Serving Room: _________ 

Item  Description  Complying Not 

Complying 

Comments 

1  VAV installation 

2  Accessibility 

3  VAV support 

4  Duct connections 

5  VAV Damper is totally opened  

6  Thermostat condition 

7  Electrical Connection  

8  Grounding  

9  Tagging & labeling  

10  Cleanliness  

11   

12   

 

Comments:  

____________________________________________________________________________________________________________________ 

_____________________________________________________________________________________________________________________ 

Sub‐Contractor Representative  

 

Name 

 

Signature 

 

Date 

Main Contractor Representative  

 

Name 

 

Signature 

 

Date 

Engineer       

Page 86: AfDB Field’s office in Abuja Nigeria

 

PI12.154   AfDB Field office in Abuja                                                                              Commissioning Plan ‐ April 2013 ‐  12 / 20 

Representative   Name  Signature  Date  

AHUFanPerformanceTestSheetBuilding: _________              Date: _________ 

Location: _________          Related Drawings: _________     

Room: ________            

Filter: _________      Type: _________    Size: ________     

Electric heater capacity: ________ Kw   

AHU No.  AHU Manufacturer   AHU Model No. 

 Fan 

Manufacturer:  Type: 

Serial Number:  Size: 

Model Number:  Pitch Angle: 

 Motor 

Manufacturer:  Frame No. 

Serial Number:  Power: 

Type:  FLC: 

  

Drive 

Manufacturer:  Fan Pulley Dia:  Type:  Fan Shaft Dia:  Belt Size:  Motor Pulley Dia:  No. of Belts:  Motor Shaft Dia  

 Starter 

Manufacturer:  O/L Range  Type:  Timer setting:  O/L setting:  Fuse Rating:  

      Performance 

    

Fan 

Design  Actual 

Discharge airflow  L/s  L/s  %

Outlet airflow  L/s  L/s  %

Return airflow  L/s  L/s  %

Fresh airflow  L/s  L/s  %

Coils section pressure drop  Pa    Pa

Filters section pressure drop  Pa    Pa

Discharge static pressure Pa    Pa

Inlet static pressure  Pa    Pa

Velocity pressure  Pa    Pa

Total pressure  Pa    Pa

RPM   RPM    RPM

 Motor 

Voltage:  Volt               Volt

Current:  Amps  L1                L2  L3           Amps 

Speed:  RPM    RPM

Page 87: AfDB Field’s office in Abuja Nigeria

 

PI12.154   AfDB Field office in Abuja                                                                              Commissioning Plan ‐ April 2013 ‐  13 / 20 

 

Page 88: AfDB Field’s office in Abuja Nigeria

 

PI12.154   AfDB Field office in Abuja                                                                              Commissioning Plan ‐ April 2013 ‐  14 / 20 

DuctTraverseReadingsBuilding: _________              Date: _________ 

Location: _________          Related Drawings: _________     

Room: ________            

       Vel. Read Section 

1st  2nd  3rd  4th 5th 6th 7th  8th  Average Velocity 

A         

B         

C         

D         

E         

F         

G         

H         

  Final Average Velocity (m/s) 

Comments:  

____________________________________________________________________________________________________________________ 

_____________________________________________________________________________________________________________________ 

Sub‐Contractor Representative  

 

Name 

 

Signature 

 

Date 

Main Contractor Representative  

 

Name 

 

Signature 

 

Date 

Engineer Representative  

 

Name 

 

Signature 

 

Date 

 

Design Flow   Duct Size   Duct Area Design Velocity

X  Average Velocity   Actual Flow   % design Static Pressure

Page 89: AfDB Field’s office in Abuja Nigeria

 

PI12.154   AfDB Field office in Abuja                                                                              Commissioning Plan ‐ April 2013 ‐  15 / 20 

   

Page 90: AfDB Field’s office in Abuja Nigeria

 

PI12.154   AfDB Field office in Abuja                                                                              Commissioning Plan ‐ April 2013 ‐  16 / 20 

TerminalAirDistributionReadingsBuilding: _________            Date:_________ 

Location: _________      Related Drawings:_________   Room: ________  

Terminal Ref.  

Terminal   Maximum  Actual  

Type  Size Free Area 

Factor 

Design 

ips 

Actual 

Ips % 

Design 

Design 

ips 

Actual 

Ips % 

Design 

Total Airflow (L/S) 

 

Comments:  

____________________________________________________________________________________________________________________ 

_____________________________________________________________________________________________________________________ 

Sub‐Contractor Representative  

 

Name 

 

Signature 

 

Date 

Main Contractor Representative  

 

Name 

 

Signature 

 

Date 

Engineer Representative  

 

Name 

 

Signature 

 

Date  

   

Page 91: AfDB Field’s office in Abuja Nigeria

 

PI12.154   AfDB Field office in Abuja                                                                              Commissioning Plan ‐ April 2013 ‐  17 / 20 

CoilPerformanceTestSheetBuilding: _________             Date:_________ 

Location: _________          Related Drawings:_________    

Coil Data  Cooling  coil  

Heating  Coil 

Comments 

Manufacturer        

Model number        

Coil type        

Face area (m2)       

Number of rows        

Number of fins        

Coil material        

 

   

Air Side 

Test Data  Design Actual  Design Actual   

Air Flow            

Air velocity            

Pressure drop            

Out. Air DB/WB            

Ret. Air DB/WB            

Ent. Air DB/WB           

Lvg. Air DB/WB            

Coil Air T (C)            

 Water Side 

Water flow (lps)           

Pressure drop (Pa)           

Ent. Water temp (C)            

Lvg. Water temp (C)            

Coil water T (C)            

Comments:  

_____________________________________________________________________________________________________________________ 

Sub‐Contractor Representative  

 

Name 

 

Signature 

 

Date 

Main Contractor Representative  

 

Name 

 

Signature 

 

Date 

Engineer Representative  

 

Name 

 

Signature 

 

Date  

Page 92: AfDB Field’s office in Abuja Nigeria

 

PI12.154   AfDB Field office in Abuja                                                                              Commissioning Plan ‐ April 2013 ‐  18 / 20 

VariableAirVolumeBoxesBuilding: _________             Date:_________ 

Location: _________          Related Drawings:_________ 

PRE-START-UP INSPECTION

Check the following equipment for:

local valving and piping local ductwork mounting support and seismic system maintenance access valve operation damper operation sensor location and operation Control system - point to point checks complete Building cleanliness

START-UP

Start air handling system (see separate checklist) Local air leakage acceptable

Unit ID

Room Reheat Ducting Valving

& Piping

Mounting Support Seismic

Maint. access

Valve operation

Damper operation

Airflow Sensor

Temp. Sensor

 

Page 93: AfDB Field’s office in Abuja Nigeria

 

PI12.154   AfDB Field office in Abuja                                                                              Commissioning Plan ‐ April 2013 ‐  19 / 20 

AHUSchematic 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

   

 

 

 

 

Page 94: AfDB Field’s office in Abuja Nigeria

 

PI12.154   AfDB Field office in Abuja                                                                              Commissioning Plan ‐ April 2013 ‐  20 / 20 

 

This section is dedicated to the efficiency of AHUs and VAVs: 

 

 

 

 

 

 

 

 

 

 

 

 

Sub‐Contractor Representative  

 

Name 

 

Signature 

 

Date 

Main Contractor Representative  

 

Name 

 

Signature 

 

Date 

Engineer Representative  

 

Name 

 

Signature 

 

Date 

Page 95: AfDB Field’s office in Abuja Nigeria

 

PI12.154   AfDB Field office in Abuja                                                                              Commissioning Plan ‐ April 2013 ‐  1 / 11 

 

 

 

 

 

Testing & Commissioning Procedure 

Chillers and Accessories  

   

Page 96: AfDB Field’s office in Abuja Nigeria

 

PI12.154   AfDB Field office in Abuja                                                                              Commissioning Plan ‐ April 2013 ‐  2 / 11 

TableofContents1 – General : .................................................................................................................................................. 3 

1.1 – Purpose of the Testing & Commissioning Procedures ..................................................................... 3 

1.2 – Reference to Other Controlling Documents .................................................................................... 3 

1.3 – Responsibility ................................................................................................................................... 3 

2 – Tests & Inspections to be Carried Out : .................................................................................................. 3 

2.1 – Visual Inspection .............................................................................................................................. 3 

2.2 – Tests To Be Carried Out (Before or During Chiller operation) ......................................................... 3 

2.4 – Operational Tests ............................................................................................................................. 4 

3 – Testing Equipment: ................................................................................................................................. 4 

4 – Safety: ..................................................................................................................................................... 4 

Appendix A .................................................................................................................................................... 5 

Appendix B .................................................................................................................................................... 7 

Checklist & Start‐up Inspection ................................................................................................................. 8 

Chillers ....................................................................................................................................................... 8 

Primary Pump Performance Test Sheet .................................................................................................... 9 

System Verification/Start up Check List .................................................................................................. 10 

Chillers ..................................................................................................................................................... 10 

 

   

Page 97: AfDB Field’s office in Abuja Nigeria

 

PI12.154   AfDB Field office in Abuja                                                                              Commissioning Plan ‐ April 2013 ‐  3 / 11 

1–General:

1.1–PurposeoftheTesting&CommissioningProcedures

Having already been inspected as materials and installed in their reserved locations, the purpose of this document is to ensure that the Chillers and their components are installed as required, are in a good condition, and operating properly.   

1.2–ReferencetoOtherControllingDocuments 1.2.1 –ReferenceDocuments

      ‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐ 

1.2.2 –ReferenceDrawings

      Refer to Appendix A                   

1.3–ResponsibilityThe main contractor will carry out the testing and commissioning with the association of his 

subcontractor and the related supplier.  

2–Tests&InspectionstobeCarriedOut:

2.1–VisualInspection

When  the  installation of  the Chillers  is complete, a visual  inspection should be carried out  to ensure that the workmanship  is satisfactory, and that the system complies with the approved design and project specifications. Checklists that should be used with visual  inspection for the system are included in this document. 

 

2.2–TestsToBeCarriedOut(BeforeorDuringChilleroperation)Some tests should be carried out before or during chiller operation as follows: 

1- Primary chilled water system. 2- Expansion tanks system. 3- Water treatment systems. 4- Chilled water system. 5- Fan Coil Units. 6- Air Handling Units. 

   

Page 98: AfDB Field’s office in Abuja Nigeria

 

PI12.154   AfDB Field office in Abuja                                                                              Commissioning Plan ‐ April 2013 ‐  4 / 11 

2.4–OperationalTestsThis test should be held on a summer day (hot and humid weather) as follows: 

1. Provide required cooling load in building. 2. Operate the primary and secondary pumps. 3. Test shall be done on chillers one by one. 4. Wait for several hours till the system is stabilized. The actual performance for chillers 

components as evaporator, condenser, compressor, motor, and others shall be checked by recording readings and measurements as per the performance test sheets included in this document. 

5. Verify that all controls are operational.  

 

3–TestingEquipment:The following instruments will be used in the testing and commissioning of the Domestic Water 

System.  

a. Multi‐meter. b. Halogen detector. c. Electronic leak detector. d. Manometer (mercury type). e. Noise level meter f. Pressure gauges & thermometers  

The testing equipment should have been approved by the Engineer.  

4–Safety: Skilled technicians should do all tests operation under the supervision of a Senior 

Mechanical Engineer.  

The Operator should be fully equipped with all safety equipment as per the Safety 

Manual applied in the project.  

   

Page 99: AfDB Field’s office in Abuja Nigeria

 

PI12.154   AfDB Field office in Abuja                                                                              Commissioning Plan ‐ April 2013 ‐  5 / 11 

 

 

 

 

 

AppendixA

List of References Drawings  

   

Page 100: AfDB Field’s office in Abuja Nigeria

 

PI12.154   AfDB Field office in Abuja                                                                              Commissioning Plan ‐ April 2013 ‐  6 / 11 

 

 

 

 

   

Building Drawing No. Rev Drawing Name

Status Date Comments

Page 101: AfDB Field’s office in Abuja Nigeria

 

PI12.154   AfDB Field office in Abuja                                                                              Commissioning Plan ‐ April 2013 ‐  7 / 11 

 

 

 

 

 

AppendixB

Testing & Commissioning Forms  

   

Page 102: AfDB Field’s office in Abuja Nigeria

 

PI12.154   AfDB Field office in Abuja                                                                              Commissioning Plan ‐ April 2013 ‐  8 / 11 

Checklist&Start‐upInspection

ChillersBuilding: __________        Date: ________ 

Location: __________        Related Drawings: _________  chillers No: _________ 

Item  Description  Complying Not 

Complying 

Comments 

1  All snags are removed

2  Chillers installation

3  Anti-vibration installation

4  Pipes connections to evaporator side

5  Valves installation

6  Modulating valve installation & operational

7  Chillers insulation conditions

8  Differential pressure installation & operation

9  Connection to expansion tanks is as per approved detail

10  Expansion tanks operation and setting

11  Starter installation and calibration

12  Connection to power supply

13  Tightness of electrical connections

14  Grounding is installed and tested

15  Tagging and labeling

16  Name plate

17  Control panel 

Comments: 

___________________________________________________________________

___________________________________________________________________ 

 

Page 103: AfDB Field’s office in Abuja Nigeria

 

PI12.154   AfDB Field office in Abuja                                                                              Commissioning Plan ‐ April 2013 ‐  9 / 11 

PrimaryPumpPerformanceTestSheetBuilding: _________            Date:_________ 

Location:_________      Related Drawings:_________ 

 Pump 

Manufacturer:  Size: 

Serial Number:  Stages: 

Model Number:  Seal Type: 

Type:  Base: 

 Motor 

Manufacturer:  Type: 

Serial Number:  Output(HP): 

Model Number:  FLC: 

 

    Performance 

  

Pump 

Design  Actual 

Flow Rate:  I/s        I/s 

Pump Head:  Bar  ‐  ‐    Bar 

Shut off Head:  Bar  ‐  ‐  ΔP:  Bar 

Speed:  RPM      ΔP:  RPM 

NSPH:  Bar         

 Motor 

Voltage:  Volts        Volts 

Current:  Amps L1  L2  L3  Amps

Speed:  RPM        RPM 

Power:           

 

Comments: 

___________________________________________________________________ 

___________________________________________________________________ 

___________________________________________________________________ 

Sub‐Contractor Representative  

 

Name 

 

Signature 

 

Date 

Main Contractor Representative  

 

Name 

 

Signature 

 

Date 

Engineer Representative  

 

Name 

 

Signature 

 

Date 

Page 104: AfDB Field’s office in Abuja Nigeria

 

PI12.154   AfDB Field office in Abuja                                                                              Commissioning Plan ‐ April 2013 ‐  10 / 11 

SystemVerification/StartupCheckList

ChillersBuilding: __________        Date: ________ 

Location: __________        Related Drawings: _________  chillers No: _________ 

ITEM    COMMENTS 

PRE-START-UP INSPECTION    

Commissioning lock-out procedures reviewed Operation and maintenance information Mounting/support system Seismic restraints Maintenance clearance Local valves/piping correct (including expansion tanks, make-up water and identification).

Pressurization and leak tests Supplier pre-start (including charging the system) (report attached)

Chemical cleaning and treatment (report attached) Insulation/lagging Refrigerant relief valve Temperature and pressure gauges Flow switches - safety interlocks Temperature sensors - safety interlocks UL and ASME approvals Control/diagnostic/programmable module Electrical wiring Overload protection (sized correctly) Disconnect switch (tested) Control system - point to point checks complete

START-UP    

Start chilled cooling system to create load    

Chiller startup by supplier    

Modulation through specified range    

Safety interlocks    

Supplier certificate or log provided for start-up and all specified and regulatory tests

   

   

 

 

Page 105: AfDB Field’s office in Abuja Nigeria

 

PI12.154   AfDB Field office in Abuja                                                                              Commissioning Plan ‐ April 2013 ‐  11 / 11 

This section is dedicated to the electrical efficiency: 

 

 

 

 

 

 

 

 

 

   

 

Sub‐Contractor Representative  

 

Name 

 

Signature 

 

Date 

Main Contractor Representative  

 

Name 

 

Signature 

 

Date 

Engineer Representative  

 

Name 

 

Signature 

 

Date 

Page 106: AfDB Field’s office in Abuja Nigeria

 

PI12.154   AfDB Field office in Abuja                                                                              Commissioning Plan ‐ April 2013 ‐  1 / 13 

 

 

 

 

 

Testing & Commissioning Procedure 

Cooling Pumps, Piping, & Accessories 

   

Page 107: AfDB Field’s office in Abuja Nigeria

 

PI12.154   AfDB Field office in Abuja                                                                              Commissioning Plan ‐ April 2013 ‐  2 / 13 

TableofContents1 – General : .................................................................................................................................................. 3 

1.1 – Purpose of the Testing & Commissioning Procedures ..................................................................... 3 

1.2 – Reference to Other Controlling Documents .................................................................................... 3 

1.3 – Responsibility ................................................................................................................................... 3 

2 – Tests & Inspections to be Carried Out : .................................................................................................. 3 

2.1 – Visual Inspection .............................................................................................................................. 3 

2.2 – Pipe Pressure Leak Test .................................................................................................................... 3 

2.3 – Pipe Flushing Process ....................................................................................................................... 3 

2.4 – Operational Tests ............................................................................................................................. 4 

2.5 – Tolerance .......................................................................................................................................... 5 

3 – Testing Equipment : ................................................................................................................................ 5 

4 – Safety: ..................................................................................................................................................... 5 

Appendix A .................................................................................................................................................... 6 

Appendix B .................................................................................................................................................... 8 

Checklist & Start‐up Inspection ................................................................................................................. 9 

Chilled Water Systems .............................................................................................................................. 9 

Pump Performance Test Sheet ............................................................................................................... 11 

Water Flow Balancing Sheet ................................................................................................................... 12 

Chilled Water System .............................................................................................................................. 12 

 

   

Page 108: AfDB Field’s office in Abuja Nigeria

 

PI12.154   AfDB Field office in Abuja                                                                              Commissioning Plan ‐ April 2013 ‐  3 / 13 

1–General:

1.1–PurposeoftheTesting&CommissioningProceduresHaving already been inspected as materials in their reserved locations, the purpose of this 

document is to ensure that all Pumps, Piping, & Accessories are in a good condition and 

operating properly.  

1.2–ReferencetoOtherControllingDocuments 1.2.1 –ReferenceDocuments

      ‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐ 

1.2.2 –ReferenceDrawings

      Refer to Appendix A               

1.3–ResponsibilityThe main contractor will carry out the testing and commissioning with the association of his 

subcontractor and the related supplier.  

2–Tests&InspectionstobeCarriedOut:

2.1–VisualInspectionWhen the installation of the Water Pumps, Piping, & Accessories is complete, a visual 

inspection should be carried out to ensure that the workmanship is satisfactory, and that the 

system complies with the approved design and project specifications. Checklists that should be 

used with visual inspection for the system are included in this document. 

2.2–PipePressureLeakTestWater Pipes lines shall all undergo hydraulic pressure leak test at 1.5 working pressure for 24 

hours.     

2.3–PipeFlushingProcessPipes should be cleaned and flushed in accordance with the method statement for flushing by 

the specialist.  

   

Page 109: AfDB Field’s office in Abuja Nigeria

 

PI12.154   AfDB Field office in Abuja                                                                              Commissioning Plan ‐ April 2013 ‐  4 / 13 

2.4–OperationalTestsAfter the flushing process of cooling water Pipes is complete, the system will be filled with clean treated water and air is scavenged out through automatic air vents and air relief valves. Cooling pumps are then operated to verify the operational performance by checking the actual measured performance against the design data via the following steps: 

1. With the pump operating, assure that piping system. AHU's. FCU's are vented properly. 2. Connect a suitable differential pressure gauge across the suction and discharge pressure 

test points of pumps. 3. Take measurements for voltage, current. & speed for pump motor. 4. Check the operation of variable frequency drive by closing partially the main valve. 5. With the pump running, close the discharge valve slowly for several minutes. 6. Determine the "Shut‐off" head and check against manufacturer's data for zero flow. 7. If the test shut‐off head does not coincide with the manufacturer's figure, draw a 

corrected curve parallel to the manufacturer's curve starting from the measured shut‐off head. 

8. Open discharge valve slowly to fully open position. 9. Record the total head with the D.P Gauge at full flow rate & read the actual flow from 

the manufacturer's data, or from the corrected graph curve. If the flow is more than 5%  above the design flow then regulate by closing slightly the globe valve. 

10. If performance is inadequate refer to installation Contractor & Designer. 11. Record all readings & measurements in the pump performance test sheet attached in 

this document.  

After verifying the required pump flow, water balancing shall proceed as follows: 

 12. Check the operation of two/three ways valves. 13. Verify that the farthest FCU or AHU from the pump is receiving the correct design water 

flow or more (by using the flow meter at the DRV of this unit) 14. Adjust the FCU's and AHU's flow rates by regulating the DRV's starting with the units of 

least resistance and work towards the units with the greater resistance. 15. On cooling system and where three‐way motorized valves are used, balance the globe 

valves at the bypass line to restrict the by‐ passed flow to 90% of the maximum value at the relevant coil.  

16. Make a final check of pressures and flows of the pumps and terminal units. 17. Record all flow measurements corresponding to each FCU, AHU. HWST & HEX in the 

flow balancing sheets attached in this document which are classified as per type of system control as chilled water system.  

 

   

Page 110: AfDB Field’s office in Abuja Nigeria

 

PI12.154   AfDB Field office in Abuja                                                                              Commissioning Plan ‐ April 2013 ‐  5 / 13 

2.5–ToleranceThe tolerance on the performance of pumps and coils are as per specification the following: 

Pumps: ‐0%, + 5%. 

Coils: plus/minus 5%.  

 

3–TestingEquipment:The following instruments will be used in the testing and commissioning of the Domestic Water 

System.  

a. Tachometer 

b. Liquid Manometer 

c. Clamp‐multimeter  

d. Pressure gauges   

The testing equipment should be approved by the Engineer.  

4–Safety: 

Skilled technicians should do all tests operation under the supervision of a Senior 

Mechanical Engineer.  

The Operator should be fully equipped with all safety equipment as per the Safety 

Manual applied in the project.  

   

Page 111: AfDB Field’s office in Abuja Nigeria

 

PI12.154   AfDB Field office in Abuja                                                                              Commissioning Plan ‐ April 2013 ‐  6 / 13 

 

 

 

 

 

AppendixA

List of References Drawings  

   

Page 112: AfDB Field’s office in Abuja Nigeria

 

PI12.154   AfDB Field office in Abuja                                                                              Commissioning Plan ‐ April 2013 ‐  7 / 13 

 

 

 

 

   

Building Drawing No. Rev Drawing Name

Status Date Comments

Page 113: AfDB Field’s office in Abuja Nigeria

 

PI12.154   AfDB Field office in Abuja                                                                              Commissioning Plan ‐ April 2013 ‐  8 / 13 

 

 

 

 

 

AppendixB

Testing & Commissioning Forms  

   

Page 114: AfDB Field’s office in Abuja Nigeria

 

PI12.154   AfDB Field office in Abuja                                                                              Commissioning Plan ‐ April 2013 ‐  9 / 13 

Checklist&Start‐upInspection

ChilledWaterSystemsBuilding: __________             Date:________ 

Location:__________        Related Drawings:_________ 

Pumps No:_________ 

Item  Description  Complying Not 

Complying 

Comments 

1  Pump located as per drawings

2  Piping and insulation 

3  Pipes flushing 

4  Pump base & supporting system 

5  Valves are open or set 

6  Strainers are clean 

7  Two way valve operational 

8  Bypass modulation valve operational 

9  VFD installation & operational

10  Difference pressure transducer operational 

11  Gauges & thermometer 

12  Flexible connections 

13  Shaft alignment 

14  Guard in place 

15  Completeness of components  

16  Grounding is installed and tested 

17  Tightness of electrical connections 

18  Labeling and tagging 

19  Lubricant  

   

 

Page 115: AfDB Field’s office in Abuja Nigeria

 

PI12.154   AfDB Field office in Abuja                                                                              Commissioning Plan ‐ April 2013 ‐  10 / 13 

Pump Start‐up 

20  All normally open valves are fully open 

21  All bypass valves are closed 

22  Starter is setting correctly 

23  Motor current reaching design value 

24  Impeller rotation direction 

25  Provisions are made for TAB measurments 

 

Comments: 

___________________________________________________________________ 

___________________________________________________________________ 

___________________________________________________________________ 

 

 

 

 

 

Sub‐Contractor Representative  

 

Name 

 

Signature 

 

Date 

Main Contractor Representative  

 

Name 

 

Signature 

 

Date 

Engineer Representative  

 

Name 

 

Signature 

 

Date    

Page 116: AfDB Field’s office in Abuja Nigeria

 

PI12.154   AfDB Field office in Abuja                                                                              Commissioning Plan ‐ April 2013 ‐  11 / 13 

PumpPerformanceTestSheetBuilding: _________            Date:_________ 

Location:_________      Related Drawings:_________ 

 Pump 

Manufacturer:  Size: 

Serial Number:  Stages: 

Model Number:  Seal Type: 

Type:  Base: 

 Motor 

Manufacturer:  Type: 

Serial Number:  Output(HP): 

Model Number:  FLC: 

 

    Performance 

  

Pump 

Design  Actual 

Flow Rate:  I/s        I/s 

Pump Head:  Bar  ‐  ‐    Bar 

Shut off Head:  Bar  ‐  ‐  ΔP:  Bar 

Speed:  RPM      ΔP:  RPM 

NSPH:  Bar         

 Motor 

Voltage:  Volts        Volts 

Current:  Amps L1  L2  L3  Amps

Speed:  RPM        RPM 

Power:           

 

Comments: 

___________________________________________________________________ 

___________________________________________________________________ 

___________________________________________________________________ 

Sub‐Contractor Representative  

 

Name 

 

Signature 

 

Date 

Main Contractor Representative  

 

Name 

 

Signature 

 

Date 

Engineer Representative  

 

Name 

 

Signature 

 

Date 

Page 117: AfDB Field’s office in Abuja Nigeria

 

PI12.154   AfDB Field office in Abuja                                                                              Commissioning Plan ‐ April 2013 ‐  12 / 13 

WaterFlowBalancingSheetChilledWaterSystemBuilding: _________              Date:_________ 

Pump No:_________          Related Drawings:_________ 

Item  FCU/AHU  DRV  Design  Actual  DRV Setting 

Remarks 

Size  Model  LPS  ΔP Kpa  ΔP Kpa  LPS  % 

1                     

2                     

3                     

4                     

5                     

6                     

7                     

8                     

9                     

10                     

11                     

12                     

13                     

14                     

15                     

16                     

17                     

18                     

19                     

20                     

Comments: 

___________________________________________________________________

___________________________________________________________________ 

Sub‐Contractor Representative  

 

Name 

 

Signature 

 

Date 

Main Contractor Representative  

 

Name 

 

Signature 

 

Date 

Engineer Representative  

 

Name 

 

Signature 

 

Date 

Page 118: AfDB Field’s office in Abuja Nigeria

 

PI12.154   AfDB Field office in Abuja                                                                              Commissioning Plan ‐ April 2013 ‐  13 / 13 

 

 

This section is dedicated for the electrical efficiency of the components: 

Page 119: AfDB Field’s office in Abuja Nigeria

 

PI12.154   AfDB Field office in Abuja                                                                              Commissioning Plan ‐ April 2013 ‐  1 / 11 

 

 

 

 

 

Testing & Commissioning Procedure 

Domestic Water System 

   

Page 120: AfDB Field’s office in Abuja Nigeria

 

PI12.154   AfDB Field office in Abuja                                                                              Commissioning Plan ‐ April 2013 ‐  2 / 11 

TableofContents1 – General : .................................................................................................................................................. 3 

1.1 – Purpose of the Testing & Commissioning Procedures ..................................................................... 3 

1.2 – Reference to Other Controlling Documents .................................................................................... 3 

1.3 – Responsibility ................................................................................................................................... 3 

2 – Tests & Inspections to be Carried Out : .................................................................................................. 3 

2.1 – Visual Inspection .............................................................................................................................. 3 

2.2 – Pipe Pressure Leak Test .................................................................................................................... 3 

2.3 – Pipe Flushing Process ....................................................................................................................... 3 

2.4 – Operational Tests ............................................................................................................................. 4 

2.5 – Tolerance .......................................................................................................................................... 5 

3 – Testing Equipment : ................................................................................................................................ 5 

4 – Safety  : .................................................................................................................................................... 5 

Appendix A .................................................................................................................................................... 6 

Appendix B .................................................................................................................................................... 8 

Checklist & Start‐up Inspection ................................................................................................................. 9 

Domestic Water Systems .......................................................................................................................... 9 

Pump Performance Test Sheet ............................................................................................................... 11 

 

   

Page 121: AfDB Field’s office in Abuja Nigeria

 

PI12.154   AfDB Field office in Abuja                                                                              Commissioning Plan ‐ April 2013 ‐  3 / 11 

1–General:

1.1–PurposeoftheTesting&CommissioningProceduresHaving already been inspected as materials in their reserved locations, the purpose of this 

document is to ensure that all Pumps, Piping, & Accessories are in a good condition and 

operating properly.  

1.2–ReferencetoOtherControllingDocuments 1.2.1 –ReferenceDocuments

      ‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐ 

1.2.2 –ReferenceDrawings

      Refer to Appendix A                    

1.3–ResponsibilityThe main contractor will carry out the testing and commissioning with the association of his 

subcontractor and the related supplier.  

2–Tests&InspectionstobeCarriedOut:

2.1–VisualInspectionWhen the installation of the Water Pumps, Piping, & Accessories is complete, a visual 

inspection should be carried out to ensure that the workmanship is satisfactory, and that the 

system complies with the approved design and project specifications. Checklists that should be 

used with visual inspection for the system are included in this document. 

 

2.2–PipePressureLeakTestWater Pipes lines shall all undergo hydraulic pressure leak test at 1.5 working pressure for 24 

hours.  

              

2.3–PipeFlushingProcessPipes should be cleaned and flushed in accordance with the method statement for flushing by 

the specialist.  

   

Page 122: AfDB Field’s office in Abuja Nigeria

 

PI12.154   AfDB Field office in Abuja                                                                              Commissioning Plan ‐ April 2013 ‐  4 / 11 

2.4–OperationalTestsAfter the flushing process for water line is complete, the system will be filled clean water and 

air is scavenged out through automatic air vents and air relief valves. The Pumps are then 

operated to verify the operational performance by checking the actual measured performance 

against the design data via the following steps: 

1.  Connect a suitable differential pressure gauge across the suction and discharge 

pressure test points of pumps.  

2.  With the pump running, close the discharge valve slowly for several minutes. (Do not 

close any valves in the discharge piping of a positive displacement pump).  

3.  Determine the “Shut‐off” head and check against manufacturer’s data for zero flow.  

4.  If measured shut‐off head does not coincide with the manufacturer’s figure. Draw a 

corrected curve parallel to the manufacturer’s curve starting from the measured shut‐

off head.  

5. Open discharge valve slowly to fully open position.  

6. Record the total head with the D.P. Gauge at full flow rate & read the actual flow from 

the manufacturer’s data, or from the corrected graph curve.  

7. If total head of pump is higher than design data, the water flow will be lower than 

designed. Solution will be prepared and submitted to the Engineer for approval.  

8. If the total head of pump is less than design data, the water flow will be higher than 

designed. Closing of the globe valve at the pump discharge will increase the pressure 

drop of system and reduce the flow until reach 110% of the design flow. Motor current 

shall be checked and be kept within the nameplate indication.  

9. Take measurements for voltage, current, & speed for pump motor.  

10.  Record all readings & measurements in the pump performance test sheet attached in 

this document.  

      Once pumps are tested, overall domestic water system will be operated tested as per 

procedure described in the test sheet enclosed to this document.  

   

Page 123: AfDB Field’s office in Abuja Nigeria

 

PI12.154   AfDB Field office in Abuja                                                                              Commissioning Plan ‐ April 2013 ‐  5 / 11 

2.5–ToleranceThe tolerance on the performance of pumps is as per specification plus/minus 5%.  

3–TestingEquipment:The following instruments will be used in the testing and commissioning of the Domestic Water 

System.  

  a. Tachometer  

  b. Clamp‐multimeter  

  c. Pressure gauges   

The testing equipment should be approved by the Engineer.  

 

4–Safety:  ‐ Skilled technicians should do all tests operation under the supervision of a Senior 

Mechanical Engineer.  

  ‐ The Operator should be fully equipped with all safety equipment as per the Safety 

Manual applied in the project.  

   

Page 124: AfDB Field’s office in Abuja Nigeria

 

PI12.154   AfDB Field office in Abuja                                                                              Commissioning Plan ‐ April 2013 ‐  6 / 11 

 

 

 

 

 

AppendixA

List of References Drawings  

   

Page 125: AfDB Field’s office in Abuja Nigeria

 

PI12.154   AfDB Field office in Abuja                                                                              Commissioning Plan ‐ April 2013 ‐  7 / 11 

 

 

 

 

   

Building Drawing No. Rev Drawing Name

Status Date Comments

Page 126: AfDB Field’s office in Abuja Nigeria

 

PI12.154   AfDB Field office in Abuja                                                                              Commissioning Plan ‐ April 2013 ‐  8 / 11 

 

 

 

 

 

AppendixB

Testing & Commissioning Forms  

   

Page 127: AfDB Field’s office in Abuja Nigeria

 

PI12.154   AfDB Field office in Abuja                                                                              Commissioning Plan ‐ April 2013 ‐  9 / 11 

Checklist&Start‐upInspection

DomesticWaterSystemsBuilding: __________             Date:________ 

Location:__________        Related Drawings:_________  Pumps No:_________ 

Item  Description  Complying Not Complying Comments 

1  Pump location    

2  Pipe layout    

3  Pipes flushing    

4  System is vented properly    

5  Pump base & supporting system    

6  Flexible connections    

7  Suction and discharge connections    

8  Strainers are clean    

9  Shaft alignment    

10  Guards in place    

11  Float valve installation    

12  Pump location    

13  Pipe layout    

14  Pipes flushing    

15  System is vented properly    

16  Pump base & supporting system    

17  Flexible connections    

18  Suction and discharge connections    

19  Strainers are clean    

20  Shaft alignment    

21  Guards in place    

22  Float valve installation    

Page 128: AfDB Field’s office in Abuja Nigeria

 

PI12.154   AfDB Field office in Abuja                                                                              Commissioning Plan ‐ April 2013 ‐  10 / 11 

Comments: 

___________________________________________________________________ 

___________________________________________________________________ 

___________________________________________________________________ 

 

 

 

 

 

 

 

 

 

 

 

 

Sub‐Contractor Representative  

 

Name 

 

Signature 

 

Date 

Main Contractor Representative  

 

Name 

 

Signature 

 

Date 

Engineer Representative  

 

Name 

 

Signature 

 

Date    

Page 129: AfDB Field’s office in Abuja Nigeria

 

PI12.154   AfDB Field office in Abuja                                                                              Commissioning Plan ‐ April 2013 ‐  11 / 11 

PumpPerformanceTestSheetBuilding: _________            Date:_________ 

Location:_________      Related Drawings:_________ 

 Pump 

Manufacturer:  Size: 

Serial Number:  Stages: 

Model Number:  Seal Type: 

Type:  Base: 

 Motor 

Manufacturer:  Type: 

Serial Number:  Output(HP): 

Model Number:  FLC: 

 

    Performance 

  

Pump 

Design  Actual 

Flow Rate:  I/s        I/s 

Pump Head:  Bar  ‐  ‐    Bar 

Shut off Head:  Bar  ‐  ‐  ΔP:  Bar 

Speed:  RPM      ΔP:  RPM 

NSPH:  Bar         

 Motor 

Voltage:  Volts        Volts 

Current:  Amps L1  L2  L3  Amps

Speed:  RPM        RPM 

Power:           

Comments: 

___________________________________________________________________ 

___________________________________________________________________ 

___________________________________________________________________ 

Sub‐Contractor Representative  

 

Name 

 

Signature 

 

Date 

Main Contractor Representative  

 

Name 

 

Signature 

 

Date 

Engineer Representative  

 

Name 

 

Signature 

 

Date  

Page 130: AfDB Field’s office in Abuja Nigeria

 

PI12.154   AfDB Field office in Abuja                                                                              Commissioning Plan ‐ April 2013 ‐  1 / 11 

 

 

 

 

 

Testing & Commissioning Procedure 

Fan Coil Units 

   

Page 131: AfDB Field’s office in Abuja Nigeria

 

PI12.154   AfDB Field office in Abuja                                                                              Commissioning Plan ‐ April 2013 ‐  2 / 11 

TableofContents1 – General : .................................................................................................................................................. 3 

1.1 – Purpose of the Testing & Commissioning Procedures ..................................................................... 3 

1.2 – Reference to Other Controlling Documents .................................................................................... 3 

1.3 – Responsibility ................................................................................................................................... 3 

2 – Tests & Inspections to be Carried Out : .................................................................................................. 3 

2.1 – Visual Inspection: ............................................................................................................................. 3 

2.2 – Operational Tests: ............................................................................................................................ 3 

2.5 – Tolerance .......................................................................................................................................... 4 

3 – Testing Equipment : ................................................................................................................................ 4 

4 – Safety: ..................................................................................................................................................... 4 

Appendix A .................................................................................................................................................... 5 

Appendix B .................................................................................................................................................... 7 

FCU’s Checklist & Start‐up Inspection ....................................................................................................... 8 

FCU Performance Test Sheet .................................................................................................................. 10 

Terminal Air Distribution Readings ......................................................................................................... 11 

 

   

Page 132: AfDB Field’s office in Abuja Nigeria

 

PI12.154   AfDB Field office in Abuja                                                                              Commissioning Plan ‐ April 2013 ‐  3 / 11 

1–General:

1.1–PurposeoftheTesting&CommissioningProceduresHaving already been inspected as materials and installed in their reserved location, the purpose 

of this document is to ensure that all FCU’s are in a good conditions and operating properly 

1.2–ReferencetoOtherControllingDocuments 1.2.1 –ReferenceDocuments

      ‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐ 

1.2.2 –ReferenceDrawings

      Refer to Appendix A                     

1.3–ResponsibilityThe main contractor will carry out the testing and commissioning  with association of this 

subcontractor and the related supplier.  

2–Tests&InspectionstobeCarriedOut:The following tests and inspections will be carried out and recorded on the relative form. 

 

2.1–VisualInspection:Before FCU Operation, visual inspection shall be carried out to ensure that the material has no 

defects & the installation is proper. Refer to visual inspection checklist for FCU (s).  

   

2.2–OperationalTests:Operate the FCU from the thermostat at medium speed at the required preset temperature. 

Get the air flow rates at grilles or diffusers by using the Airflow Meter (Hood for Ceiling 

diffusers and rotating vane for side grilles). Measure the voltage, current & speed, record them 

in performance test sheet.  

Three speeds flow rate shall be tested for each size of FCU on a selected percentage of 10 to 

15% of all units since these units are mass produced and factory tested   

    

   

Page 133: AfDB Field’s office in Abuja Nigeria

 

PI12.154   AfDB Field office in Abuja                                                                              Commissioning Plan ‐ April 2013 ‐  4 / 11 

2.5–ToleranceFor air system, the tolerances on terminals and fans are as follows:  

1. Supply and return of fan‐coil units shall not be less than 95%.  

2. For any space the flow should be within – 5 %and 10 + 10%.  

  ‐ Space with one outlet, the tolerance is as above.  

  ‐ Space with two outlets, the tolerance is – or – 10%.  

  ‐ Space with 3 outlets or more, the tolerances are – or – 10%.  

3–TestingEquipment:The following instruments are to be provided before proceeding in the testing and 

commissioning of the system:  

  a. Tachometer  

  b. Clamp‐multimeter  

  c. Ballometer  

  d. Anemometer  

The testing equipment should be approved by the Engineer. 

4–Safety: Skilled Technicians should do all tests operation under the supervision of Senior 

Electrical Engineer.  

The Operator should be fully equipped with safety equipment as per the Safety 

Manual Applied in the project.  

   

Page 134: AfDB Field’s office in Abuja Nigeria

 

PI12.154   AfDB Field office in Abuja                                                                              Commissioning Plan ‐ April 2013 ‐  5 / 11 

 

 

 

 

 

AppendixA

List of References Drawings  

   

Page 135: AfDB Field’s office in Abuja Nigeria

 

PI12.154   AfDB Field office in Abuja                                                                              Commissioning Plan ‐ April 2013 ‐  6 / 11 

 

 

 

 

   

Building Drawing No. Rev Drawing Name

Status Date Comments

Page 136: AfDB Field’s office in Abuja Nigeria

 

PI12.154   AfDB Field office in Abuja                                                                              Commissioning Plan ‐ April 2013 ‐  7 / 11 

 

 

 

 

 

AppendixB

Testing & Commissioning Forms  

   

Page 137: AfDB Field’s office in Abuja Nigeria

 

PI12.154   AfDB Field office in Abuja                                                                              Commissioning Plan ‐ April 2013 ‐  8 / 11 

FCU’sChecklist&Start‐upInspectionBuilding: __________            Date:________ 

Floor:__________            Related Drawings:_________ 

Room No:_________ 

 

Item  Description  Complying  Not 

Complying 

Comments 

1  FCU installation        

2  Supporting system       

3  Anti‐vibration system       

4  Fan shaft alignment       

5  Filters condition       

6  Condensate drain pan and pipes       

7  Connections to HVAC pipes       

8  Pipes and valves are properly insulated        

9  Valves, 3 way valve and accessories       

10  Strainers are clean       

11  FCU duct connection       

12  Duct are clean       

13  Thermostat condition       

14  Electrical connection & disconnect 

switch  

     

15  Physical condition       

16  Tagging & Labeling       

17  Cleanliness       

   

FCU Start‐Up 

Page 138: AfDB Field’s office in Abuja Nigeria

 

PI12.154   AfDB Field office in Abuja                                                                              Commissioning Plan ‐ April 2013 ‐  9 / 11 

Item  Description  Complying  Not 

Complying 

Comments 

18  Motor current reaching design value        

19  Fan rotation       

20  Motor & Fan free from vibration       

21  No. Seepage of lubricant from the 

housing 

     

22  Related F/A fan operated and tested       

23  Related exhaust fan operated and 

tested 

     

 

Comments: 

___________________________________________________________________ 

___________________________________________________________________ 

___________________________________________________________________ 

 

 

Sub‐Contractor Representative  

 

Name 

 

Signature 

 

Date 

Main Contractor Representative  

 

Name 

 

Signature 

 

Date 

Engineer Representative  

 

Name 

 

Signature 

 

Date    

Page 139: AfDB Field’s office in Abuja Nigeria

 

PI12.154   AfDB Field office in Abuja                                                                              Commissioning Plan ‐ April 2013 ‐  10 / 11 

FCUPerformanceTestSheetBuilding: _________            Date:_________ 

Location: _________      Related Drawings:_________   Room: ________  

 Fan Coil Tag 

 Fan Coil Manufacturer  

 Fan Coil Model No. 

 Fan 

Manufacturer:   

Serial Number:  Type: 

Model Number:  Size: 

 Motor 

Manufacturer:   

Serial Number:  Power: 

Model Number:  FLC: 

    Performance 

  

Fan 

Design  Actual 

Fan airflow high speed   L/s L/s  %

Outlet airflow high speed   L/s L/s  %

Fan airflow medium speed  L/s L/s  %

Outlet airflow medium 

speed  

L/s L/s  %

Fan airflow low speed   L/s L/s  %

Outlet airflow low speed   L/s L/s  %

Static pressure (for ducted fan‐coil) 

Pa  

 Motor 

Voltage:  Volt   Volt

Current:  Amps   Amps

Speed:  RPM   RPM

Power:     

Comments:  

____________________________________________________________________________________________________________________ 

_____________________________________________________________________________________________________________________ 

Sub‐Contractor Representative  

 

Name 

 

Signature 

 

Date 

Main Contractor Representative  

 

Name 

 

Signature 

 

Date 

Engineer Representative  

 

Name 

 

Signature 

 

Date 

Page 140: AfDB Field’s office in Abuja Nigeria

 

PI12.154   AfDB Field office in Abuja                                                                              Commissioning Plan ‐ April 2013 ‐  11 / 11 

TerminalAirDistributionReadingsBuilding: _________            Date:_________ 

Location: _________      Related Drawings:_________   Room: ________  

Terminal Ref.  

Location  

Terminal   Design   Actual  

Type   Size  Free Area Factor  

lps  m/s High   Medium   Low  

% Design  m/s  lps  m/s  lps   m/s   lps  

Total Airflow (LS)  

 

Comments:  

____________________________________________________________________________________________________________________ 

_____________________________________________________________________________________________________________________ 

Sub‐Contractor Representative  

 

Name 

 

Signature 

 

Date 

Main Contractor Representative  

 

Name 

 

Signature 

 

Date 

Engineer Representative  

 

Name 

 

Signature 

 

Date  

Page 141: AfDB Field’s office in Abuja Nigeria

 

PI12.154   AfDB Field office in Abuja                                                                              Commissioning Plan ‐ April 2013 ‐  1 / 14 

 

 

 

 

 

Testing & Commissioning Procedure 

Fans 

   

Page 142: AfDB Field’s office in Abuja Nigeria

 

PI12.154   AfDB Field office in Abuja                                                                              Commissioning Plan ‐ April 2013 ‐  2 / 14 

TableofContents1 – General : .................................................................................................................................................. 3 

1.1 – Purpose of the Testing & Commissioning Procedures ..................................................................... 3 

1.2 – Reference to Other Controlling Documents .................................................................................... 3 

1.3 – Responsibility ................................................................................................................................... 3 

2 – Tests & Inspections to be Carried Out : .................................................................................................. 3 

2.1 – Visual Inspection: ............................................................................................................................. 3 

2.2 – Operational Tests: ............................................................................................................................ 3 

2.5 – Tolerance .......................................................................................................................................... 4 

2.4 – Acceptable Duct Air leackage ........................................................................................................... 4 

3 – Testing Equipment : ................................................................................................................................ 5 

4 – Safety: ..................................................................................................................................................... 5 

Appendix A .................................................................................................................................................... 6 

Appendix B .................................................................................................................................................... 8 

Fan’s Checklist & Start‐up Inspection ....................................................................................................... 9 

Fan Performance Test Sheet ................................................................................................................... 11 

Duct Traverse Readings ........................................................................................................................... 12 

Terminal Air Distribution Readings ......................................................................................................... 13 

 

   

Page 143: AfDB Field’s office in Abuja Nigeria

 

PI12.154   AfDB Field office in Abuja                                                                              Commissioning Plan ‐ April 2013 ‐  3 / 14 

1–General:

1.1–PurposeoftheTesting&CommissioningProceduresHaving already been inspected as materials and installed in their reserved location the purpose 

of this document is to ensure that:  

  ‐ The Fans are in a good condition and operating properly. 

  ‐ Airflows in relevant ducts & air terminals are as per design drawings.   

1.2–ReferencetoOtherControllingDocuments 1.2.1 –ReferenceDocuments

      ‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐ 

1.2.2 –ReferenceDrawings

      Refer to Appendix A               

1.3–ResponsibilityThe main contractor will carry out the testing and commissioning with the related supplier.  

2–Tests&InspectionstobeCarriedOut:The following tests and inspections will be carried out and recorded on the relative forms.  

2.1–VisualInspection:Before Fan operation, Visual Inspection shall be carried out to ensure that the material has no 

defects and installation is proper. Refer to visual inspection checklist for fans.  

2.2–OperationalTests:Before running the fan, make sure that all fire dampers, duct volume dampers, splitters 

dampers and outlets dampers, splitters dampers and outlets dampers are fully opened. Run the 

fan and check if it is giving the required design flow. Then proceed airflow‐balancing starting 

with the terminals with least resistance & work towards the terminals with greater resistance. 

The terminal with the greatest resistance might be the most remote one or the one that have a 

lot of duct direction changes.  

   

Page 144: AfDB Field’s office in Abuja Nigeria

 

PI12.154   AfDB Field office in Abuja                                                                              Commissioning Plan ‐ April 2013 ‐  4 / 14 

Using the Airflow Meter (Hood for ceiling diffusers and rotating vane for side grilles), airflow 

rate can be measured at each terminal. Duct volume dampers & splitter dampers shall be 

adjusted to distribute the required flow in the various branches. Airflow velocity in duct (Duct 

Traverse reading) shall be measured by a Pitot Traverse; several velocities should be taken to 

get the average velocity. Volumetric airflow rate can then be calculated by multiplying the final 

average velocity by the duct area. Fan static pressure (inlet, outlet, total) shall be measured by 

Micro‐Manometer. Fan & Motor speed, electric Current, Voltage etc…. Shall be measured as 

well.  

2.5–ToleranceFor air system, the tolerances on terminals and fans are as follows: 

1. Supply, return and exhaust fans shall not be less than 95%.  

2. For any space the flow should be within – 5% and – 10%.  

    ‐ Space with one outlet, the tolerance is as above.  

    ‐ Space with two outlets, the tolerance is + or – 10%.  

    ‐ Space with 3 outlets or more, the tolerances is + or – 10%.  

3. Return and exhaust inlets, the tolerance is + or – 10%.   

2.4–AcceptableDuctAirleackageAs per specification, duct static pressure and seal classes are defined as below: 

Low pressure: 0 to 5 mm w.g., seal class C. 

Medium pressure: 50 to 75 mm w.g., seal class B.   

Page 145: AfDB Field’s office in Abuja Nigeria

 

PI12.154   AfDB Field office in Abuja                                                                              Commissioning Plan ‐ April 2013 ‐  5 / 14 

3–TestingEquipment:The following instruments are to be provided before proceeding in the testing and 

commissioning of the system:  

  a. Tachometer  

  b. Clamp‐multimeter  

  c. Ballometer  

  d. Micro Manometer / Pitot tube  

  e. Anemometer  

  f.dB meter  

The testing equipment should be approved by the Engineer.  

4–Safety: Skilled Technicians should do all tests operation under the supervision of Senior 

Mechanical Engineer. 

The Operator should be fully equipped with safety equipment as per the Safety 

Manual Applied in the project  

   

Page 146: AfDB Field’s office in Abuja Nigeria

 

PI12.154   AfDB Field office in Abuja                                                                              Commissioning Plan ‐ April 2013 ‐  6 / 14 

 

 

 

 

 

AppendixA

List of References Drawings  

   

Page 147: AfDB Field’s office in Abuja Nigeria

 

PI12.154   AfDB Field office in Abuja                                                                              Commissioning Plan ‐ April 2013 ‐  7 / 14 

 

 

 

 

   

Building Drawing No. Rev Drawing Name

Status Date Comments

Page 148: AfDB Field’s office in Abuja Nigeria

 

PI12.154   AfDB Field office in Abuja                                                                              Commissioning Plan ‐ April 2013 ‐  8 / 14 

 

 

 

 

 

AppendixB

Testing & Commissioning Forms  

   

Page 149: AfDB Field’s office in Abuja Nigeria

 

PI12.154   AfDB Field office in Abuja                                                                              Commissioning Plan ‐ April 2013 ‐  9 / 14 

Fan’sChecklist&Start‐upInspectionBuilding: __________            Date:________ 

Floor:__________            Related Drawings:_________  Room No:_________ 

Item  Description  Complying  Not 

Complying 

Comments 

1  Fan installation        

2  Fan base and support       

3  Alignment of Pulleys and belts       

4  Belts Tension       

5  Filters condition       

6  Electrical Connection       

7  Disconnect switch installation       

8  Duct are connections       

9  Duct are clean       

10  Dampers & outlets are totally 

opened 

     

11  Access Doors are in correct location       

12  Vibration isolators installation       

13  Grounding        

14  Tagging & labeling        

15  Cleanliness        

   

   

Page 150: AfDB Field’s office in Abuja Nigeria

 

PI12.154   AfDB Field office in Abuja                                                                              Commissioning Plan ‐ April 2013 ‐  10 / 14 

Fan Start‐Up Item  Description  Complying  Not 

Complying 

Comments 

16  All Dampers are fully open       

17  Outside air louvers are clean       

18  Star delta timer setting correctly       

19  Motor current reaching design value        

20  Fan rotation       

21  Motor & Fan free from vibration       

22  No. Seepage of lubricant from the 

housing 

     

23  Doors and windows are closed        

 

Comments: 

___________________________________________________________________ 

___________________________________________________________________ 

___________________________________________________________________ 

 

 

Sub‐Contractor Representative  

 

Name 

 

Signature 

 

Date 

Main Contractor Representative  

 

Name 

 

Signature 

 

Date 

Engineer Representative  

 

Name 

 

Signature 

 

Date    

Page 151: AfDB Field’s office in Abuja Nigeria

 

PI12.154   AfDB Field office in Abuja                                                                              Commissioning Plan ‐ April 2013 ‐  11 / 14 

FanPerformanceTestSheetBuilding: _________              Date: _________ 

Location: _________          Related Drawings: _________     

Room: ________            

Filter: _________      Type: _________    Size: ________     

Electric heater capacity: ________ Kw   

 Fan 

Manufacturer:  Type: 

Serial Number:  Size: 

Model Number:  Pitch Angle: 

 Motor 

Manufacturer:  Frame No. 

Serial Number:  Power: 

Type:  FLC: 

  

Drive 

Manufacturer:  Fan Pulley Dia:  Type:  Fan Shaft Dia:  Belt Size:  Motor Pulley Dia:  No. of Belts:  Motor Shaft Dia  

 Starter 

Manufacturer:  O/L Range  Type:  Timer setting:  O/L setting:  Fuse Rating:  

      Performance 

    

Fan 

Design  Actual 

Discharge airflow  L/s  L/s  %

Outlet airflow  L/s  L/s  %

Discharge static pressure Pa    Pa

Inlet static pressure  Pa    Pa

Total pressure  Pa    Pa

RPM   RPM    RPM

 Motor 

Voltage:  Volt               Volt

Current:  Amps  L1                L2  L3           Amps 

Speed:  RPM    RPM

 

Page 152: AfDB Field’s office in Abuja Nigeria

 

PI12.154   AfDB Field office in Abuja                                                                              Commissioning Plan ‐ April 2013 ‐  12 / 14 

DuctTraverseReadingsBuilding: _________              Date: _________ 

Location: _________          Related Drawings: _________     

Room: ________            

       Vel. Read Section 

1st  2nd  3rd  4th 5th 6th 7th  8th  Average Velocity 

A         

B         

C         

D         

E         

F         

G         

H         

  Final Average Velocity (m/s) 

Comments:  

____________________________________________________________________________________________________________________ 

_____________________________________________________________________________________________________________________ 

Sub‐Contractor Representative  

 

Name 

 

Signature 

 

Date 

Main Contractor Representative  

 

Name 

 

Signature 

 

Date 

Engineer Representative  

 

Name 

 

Signature 

 

Date 

 

Design Flow:   Duct Size:   Duct Area: Design Velocity:

Average Velocity:   Actual Flow:   % design: Static Pressure:

Page 153: AfDB Field’s office in Abuja Nigeria

 

PI12.154   AfDB Field office in Abuja                                                                              Commissioning Plan ‐ April 2013 ‐  13 / 14 

TerminalAirDistributionReadingsBuilding: _________            Date:_________ 

Location: _________      Related Drawings:_________   Room: ________  

Terminal Ref.  

Terminal   Maximum  Actual  

Type  Size Free Area 

Factor 

Design 

lps 

Actual 

Ips % 

Design 

Design 

lps 

Actual 

Ips % 

Design 

Total Airflow (L/S) 

 

Comments:  

____________________________________________________________________________________________________________________ 

_____________________________________________________________________________________________________________________ 

Sub‐Contractor Representative  

 

Name 

 

Signature 

 

Date 

Main Contractor Representative  

 

Name 

 

Signature 

 

Date 

Engineer Representative  

 

Name 

 

Signature 

 

Date  

   

Page 154: AfDB Field’s office in Abuja Nigeria

 

PI12.154   AfDB Field office in Abuja                                                                              Commissioning Plan ‐ April 2013 ‐  14 / 14 

Fan Schematic 

Building: _________        Date:_________ 

Location: _________        Related Drawings:_________    

Fan: ________ 

 

This section is dedicated to the efficiency of the fans: 

 

 

 

 

 

 

 

 

 

 

Sub‐Contractor Representative  

 

Name 

 

Signature 

 

Date 

Main Contractor Representative  

 

Name 

 

Signature 

 

Date 

Engineer Representative  

 

Name 

 

Signature 

 

Date  

Page 155: AfDB Field’s office in Abuja Nigeria

 

PI12.154   AfDB Field office in Abuja                                                                              Commissioning Plan ‐ April 2013 ‐  1 / 3 

 

 

 

 

 

Testing & Commissioning Procedure 

BMS 

Page 156: AfDB Field’s office in Abuja Nigeria

 

PI12.154   AfDB Field office in Abuja                                                                              Commissioning Plan ‐ April 2013 ‐  2 / 3 

 

This section will be discussing the BMS system testing and commissioning according to the specifications 

and design drawings: 

  Tested by: Contractor: 

Witnessed by: 

Management and control  Yes /No / N.A.  Yes /No / N.A. 

Monitoring and control of controllers 

Yes /No / N.A.  Yes /No / N.A. 

Programmable logic controllers including sensors, actuators, environmental delivery systems 

Yes /No / N.A.  Yes /No / N.A. 

Operator interface  Yes /No / N.A.  Yes /No / N.A. 

Video display integration  Yes /No / N.A.  Yes /No / N.A. 

Data collection and filing  Yes /No / N.A.  Yes /No / N.A. 

Alarm management  Yes /No / N.A.  Yes /No / N.A. 

Trending  Yes /No / N.A.  Yes /No / N.A. 

Report generation  Yes /No / N.A.  Yes /No / N.A. 

Networl integration  Yes /No / N.A.  Yes /No / N.A. 

Data exchange and integration with a diverse range of other computing and facilities system 

Yes /No / N.A.  Yes /No / N.A. 

Energy monitoring  Yes /No / N.A.  Yes /No / N.A. 

Efficiency monitoring  Yes /No / N.A.  Yes /No / N.A. 

     

Accessible data in each room: 

Space temperature  Yes /No / N.A.  Yes /No / N.A. 

Space temperature set point  Yes /No / N.A.  Yes /No / N.A. 

Occupancy status  Yes /No / N.A.  Yes /No / N.A. 

Operating mode  Yes /No / N.A.  Yes /No / N.A. 

Window status  Yes /No / N.A.  Yes /No / N.A. 

Valve position  Yes /No / N.A.  Yes /No / N.A. 

Air volume flow  Yes /No / N.A.  Yes /No / N.A. 

Percent terminal load  Yes /No / N.A.  Yes /No / N.A. 

Time schedules  Yes /No / N.A.  Yes /No / N.A. 

Zero energy bands  Yes /No / N.A.  Yes /No / N.A. 

Room name  Yes /No / N.A.  Yes /No / N.A. 

Terminal type (e.g. fan coil)  Yes /No / N.A.  Yes /No / N.A. 

 

Systems connected to the BMS are properly checked, and all feature required by the specification and the drawings are fulfilled: 

  

Yes /No / N.A. 

  

Yes /No / N.A. 

 

Page 157: AfDB Field’s office in Abuja Nigeria

 

PI12.154   AfDB Field office in Abuja                                                                              Commissioning Plan ‐ April 2013 ‐  3 / 3 

Tested by: 

Signature 

 

Witnessed by: 

Signature 

Page 158: AfDB Field’s office in Abuja Nigeria

 

PI12.154   AfDB Field office in Abuja                                                                              Commissioning Plan ‐ April 2013 ‐  1 / 2 

 

 

 

 

 

Testing & Commissioning Procedure 

Metering Systems  

Page 159: AfDB Field’s office in Abuja Nigeria

 

PI12.154   AfDB Field office in Abuja                                                                              Commissioning Plan ‐ April 2013 ‐  2 / 2 

Test of the meter: 

A.  Equipment Details 

  Designation                   : _______________________ Brand and Model Number          : _______________________  

B.   Reading Accuracy Test 

Parameters (All parameters shall be 

tested as per specifications and 

drawings) 

Meter reading  Test Kit reading  % error 

  Tested by: 

 Whitnessed by: 

Connection and wiring of the meter:     

Proper installation:     

Connection to the BMS:     

     

     

     

     

     

 

 

 

Tested by: 

Signature 

Witnessed by: 

Signature 

Page 160: AfDB Field’s office in Abuja Nigeria

 

PI12.154   AfDB Field office in Abuja                                                                              Commissioning Plan ‐ April 2013 ‐  1 / 10 

 

 

 

 

 

Testing & Commissioning Procedure 

VRVs 

   

Page 161: AfDB Field’s office in Abuja Nigeria

 

PI12.154   AfDB Field office in Abuja                                                                              Commissioning Plan ‐ April 2013 ‐  2 / 10 

TableofContents1 – General : .................................................................................................................................................. 3 

1.1 – Purpose of the Testing & Commissioning Procedures ..................................................................... 3 

1.2 – Reference to Other Controlling Documents .................................................................................... 3 

1.3 – Responsibility ................................................................................................................................... 3 

2 – Tests & Inspections to be Carried Out : .................................................................................................. 3 

2.1 – Visual Inspection: ............................................................................................................................. 3 

2.2 – Operational Tests: ............................................................................................................................ 3 

2.5 – Tolerance ........................................................................................... Error! Bookmark not defined. 

3 – Testing Equipment : ................................................................................................................................ 4 

4 – Safety: ..................................................................................................................................................... 4 

Appendix A .................................................................................................................................................... 5 

Appendix B .................................................................................................................................................... 7 

 

   

Page 162: AfDB Field’s office in Abuja Nigeria

 

PI12.154   AfDB Field office in Abuja                                                                              Commissioning Plan ‐ April 2013 ‐  3 / 10 

1–General:

1.1 –PurposeoftheTesting&CommissioningProceduresHaving already been inspected as materials and installed in their reserved location the purpose 

of this document is to ensure that:  

  ‐ The VRV(s) are in a good condition and operating properly. 

  ‐ Airflows in relevant ducts & air terminals are as per design drawings.   

1.2–ReferencetoOtherControllingDocuments 1.2.1 –ReferenceDocuments

      ‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐ 

1.2.2 –ReferenceDrawings

      Refer to Appendix A                 

1.3–ResponsibilityThe main contractor will carry out the testing and commissioning with the related supplier.  

2–Tests&Inspectionstobecarriedout:The following tests and inspections will be carried out and recorded on the relative forms.  

2.1–VisualInspection:Before Fan operation, Visual Inspection shall be carried out to ensure that the material has no 

defects and installation is proper. Refer to visual inspection checklist for fans.  

2.2–OperationalTests:Before running the fan, make sure that all fire dampers, duct volume dampers, splitters 

dampers and outlets dampers, splitters dampers and outlets dampers are fully opened. Run the 

fan and check if it is giving the required design flow.  

All measurements and readings shall be recorded in the relevant performance sheets. 

 

 

    

Page 163: AfDB Field’s office in Abuja Nigeria

 

PI12.154   AfDB Field office in Abuja                                                                              Commissioning Plan ‐ April 2013 ‐  4 / 10 

3–TestingEquipment:The following instruments are to be provided before proceeding in the testing and 

commissioning of the system:  

  a. Tachometer  

  b. Clamp‐multimeter  

  c. Balometer  

  d. Micro Manometer / Pitot tube  

  e. Anemometer  

  f. Temperature & Pressure gauges 

The testing equipment should be approved by the Engineer.  

4–Safety: 

Skilled Technicians should do all tests operation under the supervision of Senior 

Mechanical Engineer. 

The Operator should be fully equipped with safety equipment as per the Safety 

Manual Applied in the project  

   

Page 164: AfDB Field’s office in Abuja Nigeria

 

PI12.154   AfDB Field office in Abuja                                                                              Commissioning Plan ‐ April 2013 ‐  5 / 10 

 

 

 

 

 

AppendixA

List of References Drawings  

   

Page 165: AfDB Field’s office in Abuja Nigeria

 

PI12.154   AfDB Field office in Abuja                                                                              Commissioning Plan ‐ April 2013 ‐  6 / 10 

 

 

 

 

   

Building Drawing No. Rev Drawing Name

Status Date Comments

Page 166: AfDB Field’s office in Abuja Nigeria

 

PI12.154   AfDB Field office in Abuja                                                                              Commissioning Plan ‐ April 2013 ‐  7 / 10 

 

 

 

 

 

AppendixB

Testing & Commissioning Forms  

   

Page 167: AfDB Field’s office in Abuja Nigeria

 

PI12.154   AfDB Field office in Abuja                                                                              Commissioning Plan ‐ April 2013 ‐  8 / 10 

VRV’sChecklist&Start‐upInspection 

Building: __________            Date: ________ 

Floor: __________            Related Drawings: _________  Room No: _________ 

 

Manufacturer:  Location: 

Air Distribution System: 

Pressure testing of pipe servicing system or any section 

of a completed system, shall be completed prior to the 

application of any thermal insulation to the cleaned pipe 

surfaces. The pressure test for this system is 

recommended by the Manufacturer’s. 

Yes/No/N.A  Yes/No/N.A 

The system is required to vacuum by a vacuum pump.  Yes/No/N.A  Yes/No/N.A

Add the refrigerant to the indoor unit through the 

refrigerant pipe. Yes/No/N.A  Yes/No/N.A 

The refrigerant is extracted by the new vacuum pump.  Yes/No/N.A  Yes/No/N.A

     

Refrigerant  High Side Test Pressure, kPa  Low Side Test Pressure, kPa 

  General 

Specification 

Requirement 

Test Result  General 

Specification 

Requirement 

Test Result 

         

         

         

         

         

         

         

         

 

 

 

 

 

Page 168: AfDB Field’s office in Abuja Nigeria

 

PI12.154   AfDB Field office in Abuja                                                                              Commissioning Plan ‐ April 2013 ‐  9 / 10 

Evacuation Test ‐ (Remark: The evacuation shall be pulled down to between 170 Pa absolute and 340 Pa absolute) 

1st Duration of Test 4 hours 

       

2nd Duration of Test 3 hours 

       

3rd Duration of Test 2 hours 

       

Refrigerant Type         

 

Variable Refrigerant Volume System (VRV) (Cont’d) 

  Design 

Data 

Test Result  Remark 

Operating Voltage (V)       

Capacity (kW)       

Compressor Operating 

Current (A) 

     

Evaporator Operating 

Current (A) 

     

Discharge Pressure (kPa)       

Suction Pressure (kPa)       

Discharge Gas Temperature 

(°C) 

     

Heat Exchanger Liquid Pipe 

Temperature (°C) 

     

Emergency Stop Operation       

High Pressure Cut‐out (kPa)       

Low Pressure Cut‐out (kPa)       

Frequency Inverter (Hz)       

Outdoor Fan Step       

Outdoor Unit Expansion 

Valve Opening 

     

Indoor Unit (Unit No.)       

Expansion Valve Opening       

Heat Exchanger Liquid Pipe 

Temperature (°C) 

     

Discharge Gas Temperature 

(°C) 

     

Intake Air Temperature (°C)       

Page 169: AfDB Field’s office in Abuja Nigeria

 

PI12.154   AfDB Field office in Abuja                                                                              Commissioning Plan ‐ April 2013 ‐  10 / 10 

Outlet Air Temperature (°C)       

Capacity (kW)       

Return Air Temperature (°C)       

Supply Air Temperature (°C)       

Room Air Temperature (°C)       

Air Flow Rate (l/s)       

 

 

Tested / Checked 

by: 

Signature: 

 

  

  Witnessed by: 

 

Signature: 

 

Page 170: AfDB Field’s office in Abuja Nigeria

 

PI12.154   AfDB Field office in Abuja                                                                              Commissioning Plan ‐ April 2013 ‐  1 / 4 

 

 

 

 

 

Testing & Commissioning Procedure 

PV System 

Page 171: AfDB Field’s office in Abuja Nigeria

 

PI12.154   AfDB Field office in Abuja                                                                              Commissioning Plan ‐ April 2013 ‐  2 / 4 

 

This section will be discussing the PV system testing and commissioning according to the 

specifications and design drawings: 

 

Building: __________            Date: ________ 

Floor: __________            Related Drawings: _________  Room No: _________ 

 

  Tested by: 

Contractor: 

Witnessed 

by: 

Notes: 

PV Modules and Array       

Utility has given permission to interconnect the PV 

system‐if applicable. 

Yes /No / 

N.A. 

Yes /No / 

N.A. 

 

As‐built electrical drawings received  Yes /No / 

N.A. 

Yes /No / 

N.A. 

 

PV system plans and drawings received (showing 

array layout, balance‐of‐system (BOS) locations, 

components, disconnects, wiring, and conduit 

specifications) 

Yes /No / 

N.A. 

Yes /No / 

N.A. 

 

PV module specifications  Yes /No / 

N.A. 

Yes /No / 

N.A. 

 

PV module mounting details (tilt, orientation)  Yes /No / 

N.A. 

Yes /No / 

N.A. 

 

Inverter specifications  Yes /No / 

N.A. 

Yes /No / 

N.A. 

 

Combiner‐box specifications  Yes /No / 

N.A. 

Yes /No / 

N.A. 

 

Solar resource is documented from location where 

array shading will be most significant 

Yes /No / 

N.A. 

Yes /No / 

N.A. 

 

Total Solar Resource Fraction (TSRF) is 75% or greater 

at all points on the collector(s) 

Yes /No / 

N.A. 

Yes /No / 

N.A. 

 

PV modules are physically installed per plans 

(number and layout), and have been fastened to the 

roof to support weight and wind loads. 

Yes /No / 

N.A. 

Yes /No / 

N.A. 

 

Trees and plants will not grow tall enough to shade 

array 

Yes /No / 

N.A. 

Yes /No / 

N.A. 

 

Array installation is neat and permanent  Yes /No / 

N.A. 

Yes /No / 

N.A. 

 

String fuses or circuit breakers are DC‐rated and no  Yes /No /  Yes /No /   

Page 172: AfDB Field’s office in Abuja Nigeria

 

PI12.154   AfDB Field office in Abuja                                                                              Commissioning Plan ‐ April 2013 ‐  3 / 4 

larger than module fuse rating  N.A.  N.A. 

PV modules are in good condition (no broken glass or 

cells, no discoloration, frames not damaged) 

Yes /No / 

N.A. 

Yes /No / 

N.A. 

 

Wire and conduit sizes installed per plans  Yes /No / 

N.A. 

Yes /No / 

N.A. 

 

Module connectors tight and secure  Yes /No / 

N.A. 

Yes /No / 

N.A. 

 

Proper grounding of all other metallic surfaces that 

might possibly become energized (conduit, combiner 

boxes, disconnect enclosures, etc.) 

Yes /No / 

N.A. 

Yes /No / 

N.A. 

 

Inverter, batteries and Electrical       

Confirm inverter model number, and batteries model 

and number matches plans 

Yes /No / 

N.A. 

Yes /No / 

N.A. 

 

Wire and conduit sizes installed per plans  Yes /No / 

N.A. 

Yes /No / 

N.A. 

 

Inverter and batteries is easily accessible, and securely 

mounted 

Yes /No / 

N.A. 

Yes /No / 

N.A. 

 

Electrical room is properly ventilated. Ventilation is 

activated. 

Yes /No / 

N.A. 

Yes /No / 

N.A. 

 

DC disconnect is DC‐rated and permanently installed 

and readily accessible 

Yes /No / 

N.A. 

Yes /No / 

N.A. 

 

AC disconnect is permanently installed and accessible  Yes /No / 

N.A. 

Yes /No / 

N.A. 

 

Utility power connected  Yes /No / 

N.A. 

Yes /No / 

N.A. 

 

Check the Meter data: 

Manufacturer 

Model 

Serial Number 

Meter Register Read kWh 

Yes /No / 

N.A. 

Yes /No / 

N.A. 

 

System Labeling       

All equipment and parts are labeled as required 

(check polarity labels…) 

Yes /No / 

N.A. 

Yes /No / 

N.A. 

 

Label identifies PV power source attributes at DC 

disconnect 

Yes /No / 

N.A. 

Yes /No / 

N.A. 

 

Label identifies AC point of connection  Yes /No / 

N.A. 

Yes /No / 

N.A. 

 

Outdoor labels designed to withstand the elements  Yes /No / 

N.A. 

Yes /No / 

N.A. 

 

Performance Testing       

Solar irradiance level:  Yes /No / 

N.A. 

Yes /No / 

N.A. 

 

Ambient temperature:  Yes /No / 

N.A. 

Yes /No / 

N.A. 

 

Page 173: AfDB Field’s office in Abuja Nigeria

 

PI12.154   AfDB Field office in Abuja                                                                              Commissioning Plan ‐ April 2013 ‐  4 / 4 

Array temperature:  Yes /No / 

N.A. 

Yes /No / 

N.A. 

 

Measure and record open‐circuit voltage (Voc) and 

polarity of each string (verify all strings have the same 

number of modules) 

Yes /No / 

N.A. 

Yes /No / 

N.A. 

 

Measure and record short‐circuit current (Isc) of each 

string  

Yes /No / 

N.A. 

Yes /No / 

N.A. 

 

Inverter startup sequence – follow manufacturer’s 

instructions for initial startup 

Yes /No / 

N.A. 

Yes /No / 

N.A. 

 

Confirm inverter’s power reading using independent 

meters. (Afterwards, inverter power readings may be 

used for subsequent reporting.) 

Yes /No / 

N.A. 

Yes /No / 

N.A. 

 

 

 

Tested by: 

Signature 

 

Witnessed by: 

Signature 

Page 174: AfDB Field’s office in Abuja Nigeria

 

PI12.154   AfDB Field office in Abuja                                                                              Commissioning Plan ‐ April 2013 ‐  1 / 3 

 

 

 

 

 

Testing & Commissioning Procedure 

Solar Heating System 

Page 175: AfDB Field’s office in Abuja Nigeria

 

PI12.154   AfDB Field office in Abuja                                                                              Commissioning Plan ‐ April 2013 ‐  2 / 3 

 

This section will be discussing the solar thermal testing and commissioning according to the 

specifications and design drawings: 

Building: __________            Date: ________ 

Floor: __________            Related Drawings: _________  Room No: _________ 

 

  Tested by: 

Contractor: 

Witnessed by:  Notes: 

Installation of Collectors       

Collectors have been fastened to the roof to support 

collector weight and wind load 

Yes /No / N.A.  Yes /No / N.A.   

Collectors are properly oriented  Yes /No / N.A.  Yes /No / N.A.   

Potential for shading of collectors (trees, buildings, 

etc ) is limited 

Yes /No / N.A.  Yes /No / N.A.   

Waterproofing and air sealing of collectors to roof 

connection and pipe penetrations 

Yes /No / N.A.  Yes /No / N.A.   

Solar Loop       

Solar loop pipe work is watertight/airtight under 

pressure 

Yes /No / N.A.  Yes /No / N.A.   

Pipe work in the solar loop has been insulated 

thoroughly(no significant gaps in slits or clips or 

joints) 

Yes /No / N.A.  Yes /No / N.A.   

Solar loop external pipe and fittings insulated with 

UV resistant insulation  

Yes /No / N.A.  Yes /No / N.A.   

Pipes securely fixed but allowing for thermal 

movement 

Yes /No / N.A.  Yes /No / N.A.   

Expansion and pressure release valve sized and 

installed correctly 

Yes /No / N.A.  Yes /No / N.A.   

Connection of solar loop to storage tank heat 

exchanger is correct 

Yes /No / N.A.  Yes /No / N.A.   

Indicate pressure temperature and flow rate in the 

solar loop 

Yes /No / N.A.  Yes /No / N.A.   

Check valves are correctly installed  Yes /No / N.A.  Yes /No / N.A.   

Air bleeding of the loop: no audible or visible gases 

left 

Yes /No / N.A.  Yes /No / N.A.   

Controller and electrical work       

Sensors correctly placed and sensor wire correctly 

fastened 

Yes /No / N.A.  Yes /No / N.A.   

Electrical installation is properly secured and  Yes /No / N.A.  Yes /No / N.A.   

Page 176: AfDB Field’s office in Abuja Nigeria

 

PI12.154   AfDB Field office in Abuja                                                                              Commissioning Plan ‐ April 2013 ‐  3 / 3 

mounted 

Circulation indicator for the solar loop is present  Yes /No / N.A.  Yes /No / N.A.   

Temperature readings and controller settings 

correct 

Yes /No / N.A.  Yes /No / N.A.   

Domestic hot water installation       

Anti‐water boiling controls are in place  Yes /No / N.A.  Yes /No / N.A.   

Pressure relief valve operating correctly  Yes /No / N.A.  Yes /No / N.A.   

Overflow safety valve sent to the drainage  Yes /No / N.A.  Yes /No / N.A.   

Hot water tank and pipes properly insulated  Yes /No / N.A.  Yes /No / N.A.   

Temperature interlock present between solar heated 

storage and auxiliary heating 

Yes /No / N.A.  Yes /No / N.A.   

Auxiliary heating set up to allow rising water 

temperature above 60 C regularly to avoid 

legionella risk 

Yes /No / N.A.  Yes /No / N.A.   

 

 

Tested by: 

Signature 

Witnessed by: 

Signature 


Recommended