Date post: | 30-Dec-2015 |
Category: |
Documents |
Upload: | september-harrington |
View: | 16 times |
Download: | 1 times |
Eva Barbara HolzerBLM Audit Sequel, CERN July 15, 2009 1
Agenda
9:00-10:00 Beam Interlock System Changes Following the 2006 Audit
Benjamin Todd
10:00-11:00 Beam Dump System follow-up from the 2008 Audit
Jan Uythoven
11:00-11:30 BLM 2008 audit follow-up Bernd Dehning
11:30-11:50 BLM: comparison threshold settings with loss measurements and management of threshold storage
Mariusz Sapinski
11:50-12:10 BLM ionization chamber space charge and procedures for changes of system settings during LHC running period
E. Barbara Holzer
Eva Barbara HolzerBLM Audit Sequel, CERN June 15, 2009 2
Eva Barbara Holzer, CERN
BLM Audit Sequel
CERN, June 15, 2009
BLM ionization chamber space charge and procedures for changes of system settings during LHC running period
Eva Barbara HolzerBLM Audit Sequel, CERN June 15, 2009 3
Content
1. Procedures for changes of system settings during LHC running period
2. Beam tests for threshold verification
3. Space charge induced saturation effects in the LHC BLM Ionization chambers (limits of operational range)
4. Archiving of documentation
Eva Barbara HolzerBLM Audit Sequel, CERN July 15, 2009 4
MPS Commissioning Procedure: The commissioning of the LHC machine protection system - MPS aspects of the Beam Loss Monitor system commissioning; EDMS: LHC-OP-MPS-0009. Close to being released (approval of magnet group).
Item: 5 (verification of thresholds during commissioning – beam tests), 6 (test procedures, provoked losses)
Procedures for changes of BLM system settings during LHC running period. Preliminary version available.
Item: 5 (changing thresholds during the run), 7 (changes to Master Table and propagation of changes)
Space charge induced saturation effects in the LHC BLM Ionization chambers. Treated in PhD thesis of M. Stockner and D. Kramer
Item: 2 (saturation effects, limits of current monitor design) Covered by Mariuzs’ talk:
Item: 5 (threshold verification by 2008 beam loss measurements & improved simulations), 7 (definition of initial values of the Master Table)
Documents – Audit Items (2, 5, 6 and 7)
Eva Barbara HolzerBLM Audit Sequel, CERN July 15, 2009 5
Procedures for changes of BLM system settings during LHC running period. Preliminary version available.
Item: 5 (changing thresholds during the run), 7 (changes to Master Table and propagation of changes)
Procedures (plus additional software needed) defined Additional software Approval process by all involved parties Test of the procedures during “dry run”
Procedures
Eva Barbara HolzerBLM Audit Sequel, CERN July 15, 2009 6
BLM representative: The role of the BLM representative will be filled 24/7 by one person, according to a
pre-defined rota, reachable by one “BLM telephone line” (forwarded to the mobile of the BLM representative).
Execution of procedures: The procedures will be executed by the BLM representative on request of the MPP
representative (role to be defined); or on request of the BLM representative after agreement of MPP representative or the machine supervisor (to be defined)
The procedures can only be executed from the CCC by the BLM representative together with the machine supervisor (two persons for cross checking).
Agreement of BLM representative: A written and documented agreement of the BLM representative is needed for:
1. Any change in the structure of a database (MTF, Layout, LSA, M&L DB)
2. Any change in RBAG (concerning BLM) The changes shall be requested by an EMDS document using EDMS approval
procedure.
Procedures
Eva Barbara HolzerBLM Audit Sequel, CERN July 15, 2009 7
Introduce a new monitor in the BLM system
MTF Layout LSA FEC
concentrator
measurement& logging DB
DCUMslot
expert
name
(Pascal)
MTF specific data
(Sonia)Update
(Sonia)
Settingsof BLM + electronics equipment (Slava)
Update
Slot-equipment link
+error detection (Julien or automatic at night)
Generation of parameter space and settings
(Mariusz or BLM rep.)
Update
(Mariusz)
Propagation of changes and online check
Restart (OP)
Restart
(OP)
Introducingmissing slots
(Julien)
Thresholds + Settings (Mariusz and Jonathan)
request ofsettings
request ofsettings
fixed
displays
Creationvariables(Chris R.) Manual input of data
Manually triggered procedure
Automatic procedure
E-mail on errors
comparison of variables
Eva Barbara HolzerBLM Audit Sequel, CERN July 15, 2009 8
scenario 1 2 3 4 5 1 2 3 4 5 6 1 duration
new monitor X X X X X X X X X X X X 1 day
disable monitorX X X X 1 hour
Remove from DB X X X X X X X 1 day
change connection X X X X X X 1 day (possible to make
faster?
change master X X 1 hour
change family X X 1 day
1. DCUM slot expert name (Pascal)2. MTF specific data (Sonia)
3. Settings of BLM & electronics or disable flag (Slava)
4. Introducing missing slots or changing structure (Julien)
5. Thresholds and/or Settings (Mariusz and/or Jonathan)
1. Generation of parameter space and/or settings, propagation to HW and online check using Trim application (Mariusz or BLM rep.)
2. Update MTF (Sonia)3. Update LSA (Mariusz)
4. Creation of logging variables (Chris)
5. Restart Concentrator (OP)
6. Restart fixed display (OP)
1. MTF->Layout automatic nightly synchronization
Summary of actions needed to be taken in use cases
Eva Barbara HolzerBLM Audit Sequel, CERN July 15, 2009 9
MPS Commissioning Procedure: The commissioning of the LHC machine protection system - MPS aspects of the Beam Loss Monitor system commissioning; EDMS: LHC-OP-MPS-0009. Close to being released (approval of magnet group).
Item: 5 (verification of thresholds during commissioning – beam tests), 6 (test procedures, provoked losses)
Commissioning Procedures defined Approved by all involved parties (under approval by magnet group)
Beam Tests
Eva Barbara HolzerBLM Audit Sequel, CERN July 15, 2009 10
Verifies the correct functioning of the entire BLM BIS-LBDS systems chain by provoking very small losses
Test 1: MPS functionality of the BLM with beam Decrease thresholds, create local bump Measure delay between the time where the loss signal exceeds the threshold and
the time of the beam dump Time estimate: 2h
Test 2: Interface of direct BLMs with the beam dumping system Reduce the voltage setting of the abort threshold. Dump the injected beam on the collimator TCDQ and TCSG From the amount of lost beam and the threshold setting, deduce the nominal
threshold setting. Time estimate: 2h
Beam Tests: Basic BLM system functionality
Eva Barbara HolzerBLM Audit Sequel, CERN July 15, 2009 11
Verify that thresholds are adequate to protect the superconducting magnets against quenches. Must be performed for fast and slow losses; Ideally repeated for different types of magnets
Performed for one beam only. Test 3: Provoked quench for transient losses
The beam is steered into the selected magnet. The losses are recorded and compared to the expected quench level. The intensity is increased step by step until the magnet quenches. Time estimate: 1h per magnet
Test 4: Provoked quench for steady state losses with circulating beam. The beam is slowly ‘bumped’ towards the selected magnet. The losses are recorded and compared to the expected quench level. The beam is brought closer to the magnet step by step until the magnet quenches. Time estimate: 1h per magnet
Beam Tests: BLM thresholds and quench level
Eva Barbara HolzerBLM Audit Sequel, CERN July 15, 2009 12
Collimators are defining the aperture of the machine - Losses should occur first at the collimators or downstream of the collimation sections.
The BLMs at the collimators or downstream of the collimation sections in IR7 and IR3 are the first devices to detect the losses (for fast losses).
Typical fast failure scenarios must be provoked with low intensity beams to verify that BLM thresholds and reaction times are adequate.
Beam Tests: BLM thresholds and reaction times in collimation sections
Eva Barbara HolzerBLM Audit Sequel, CERN July 15, 2009 13
Space charge induced saturation effects in the LHC BLM Ionization chambers. In preparation.
Based on PhD thesis of M. Stockner and D. Kramer
Space charge
Eva Barbara HolzerBLM Audit Sequel, CERN July 15, 2009 14
Slow ions form a quasi field free region next to the cathode, which reduces the active detector volume. From: R.M. Zwaska, PhD thesis, 2005:
Critical ionization rate for space charge:
LHC IC current at onset of space charge: 26 mA
Electronics max input: 1 mA (23 Gy/s for IC)
Space charge correction:
Saturation effect due to space charge build-up
μ … ion mobility
φ … ionization rate
U … applied chamber voltage
d … distance between the electrodes
q … elementary charge
V … active detector volume
tc … irradiation time
Eva Barbara HolzerBLM Audit Sequel, CERN July 15, 2009 15
Max LHC signal range (limit of LHC IC readout electronics: 23 Gy/s) ~ factor 100 below the SPS dump dose
~8% between SEM signal and space charge corrected IC signal
IC to SEM comparison SPS internal beam dump
Eva Barbara HolzerBLM Audit Sequel, CERN July 15, 2009 16
Measured IC signal vs beam current, estimated error due to correction: ~11%
before correction space charge corrected
HERA internal beam dump measurementsb
eam
en
erg
y:
920
Ge
V
39
GeV
Eva Barbara HolzerBLM Audit Sequel, CERN July 15, 2009 17
BI group wants to adopt a common archiving system A proposal has been made and needs to be approved by the group:
EDMS plus SharePoint webpage for static documents and SVN for scripts, software codes etc.
BL plans to move existing documentation to EDMS
Archiving of Documentation – Item 46