AGENDA BIM Opportunities for CMMSBIM Opportunities for CMMS Mark Falzarano, BIM Leader, AE Services...

Date post: 20-May-2020
Category:
Upload: others
View: 5 times
Download: 0 times
Share this document with a friend
6
BIM Opportunities for CMMS Mark Falzarano, BIM Leader, AE Services Group, Barton Malow Company Keith Vandenbussche, FMA, Director, Facilities Services, Barton Malow Company Jason Wells, Vice President, Computerized Facility Integration, LLC AGENDA BA BART RTON ON M MAL ALOW OW & & C CFI FI F : A A PA PART RTNE NERS RS RS R HI HI HI H P P P P BI BIM M OV OVER ERVI VIEW EW FR FROM OM C CM M to to F FM M WH WHAT AT L LIE IES S AH AHEA EAD D BE BENE NEFI FITS TS D DEL ELIV IVER ERED ED Barton Malow Company Since 1924 Barton Malow has provided excellent construction management solutions to customers in several markets. We Design and Build Excellent Solutions Our primary markets include: Manufacturing Healthcare Higher Education K12 Education Energy & Environmental Corporate/Industrial Sports & Special Events Concrete/Rigging/Interiors Computerized Facility Integration, LLC Since 1990, CFI has been providing consulting and information technology services to a host of public and private clients. 850M sq. ft. of client facilities solutions deployed & over 350M sq. ft. under management Our service offerings include three primary activities Strategic Consulting Services Implementation Services Business Process Outsource (BPO) Services BIM DEFINED BUILDING INFORMATION MODELING BIM is the process of generating and managing a virtual building information model throughout the life cycle of a building. BIM includes geometry, spatial relationships, geographic information, quantities and properties of building components. BIM extends conventional 3D modeling visualization with added object-oriented, intelligent and parametric functionality. BIM CONCEPT
Transcript

BIM Opportunities for CMMS

Mark Falzarano, BIM Leader, AE Services Group, Barton Malow CompanyKeith Vandenbussche, FMA, Director, Facilities Services, Barton Malow Company

Jason Wells, Vice President, Computerized Facility Integration, LLC

AGENDA

BABARTRTONON MMALALOWOW && CCFIFIF : A A PAPARTRTNENERSRSRSR HIHIHIH PPPPBIBIM M OVOVERERVIVIEWEWFRFROMOM CCM M toto FFMMWHWHATAT L LIEIES S AHAHEAEADDBEBENENEFIFITSTS D DELELIVIVEREREDED

Barton Malow CompanySince 1924 Barton Malow has provided excellent construction

management solutions to customers in several markets.We Design and Build Excellent Solutions

Our primary markets include:�Manufacturing� Healthcare� Higher Education� K12 Education� Energy & Environmental

� Corporate/Industrial� Sports & Special Events� Concrete/Rigging/Interiors

Computerized Facility Integration, LLCSince 1990, CFI has been providing consulting and information

technology services to a host of public and private clients.850M sq. ft. of client facilities solutions deployed & over 350M sq. ft. under management

Our service offerings include three primary activities� Strategic Consulting Services� Implementation Services� Business Process Outsource

(BPO) Services

BIM DEFINEDBUILDING INFORMATION MODELINGBIM is the process of generating and managing a virtual building information model throughout the life cycle of a building. BIM includes geometry, spatial relationships, geographic information, quantities and properties of building components. BIM extends conventional 3D modeling visualization with added object-oriented, intelligent and parametric functionality.

BIM CONCEPT

STRUCTURAL

ELECTRICAL

MECHANICAL

ARCHITECTURAL

INTEGRATED MODEL

Item Name

Manufacturer

Item Number

Unit Cost

Item Weight

Installation

Subcontractor

W 18 x 60 Beam

ABC Steel

216 of 4326

$1,800.00

1,200 lb

September 4

ACME Steel

BIM MODELS CAN BE USED FOR� ENTIRE PROJECTS� SELECT BUILDING AREAS� SELECT BUILDING SYSTEMS� SELECT APPLICATIONS� LOAD CMMS� ANY OF THE ABOVE

SCHEDULES

FLOOR PLANSELEVATIONS

BUILDING SECTIONSCONSTRUCTION DETAILS

ESTIMATESVISUALIZATION

MODEL OUTPUT

3D BIM APPLICATIONS

existing scans

PLANNING ENGINEERING FABRICATION CONSTRUCTION FACILITIES

value engineering

contract documents

schematics / design development

clash detection

on-board approvalsshop drawingscso

4D schedulingas-builts

5D estimatingRFI

4 maintenanceoperations

asset mgmt

SUPPLY CHAIN INTEGRATIONWITH INTEGRATED PROJECT DELIVERY (IPD)

LAYOUT/PROCESS

ARCHITECTURAL

STRUCTURALELECTRICAL

HVAC

PIPING

CIVIL

COMBINED MODELLAYOUT/PROCESS

ARCHITECTURAL

STRUCTURALELECTRICAL

HVAC

PIPING

CIVIL

COMBINED MODEL

SEAMLESS DATA TRANSFER TO INSTALL

� Direct exchange of A/E 3D model information to steel and HVAC fabricator� Eliminated 12,000 paper shop drawings (color coded approvals)� Eliminates requirements for 2D shop drawing reviews� Direct review of 3D Models and associated shop drawings in real time� Fabrication approved directly in the model

4D INITIATIVES� Improves the sequencing of work� Identifies spatial conflicts among trades� Maximizes resource utilization through visual

monitoring� Increases productivity through the sequencing of

optimal work packages at the trade level � Phasing coordination and overlap resolution� Reduce work by identifying and resolving issues

during design� Diffuses possible trade interferences – Safer� Automated “Collision Detection”

5D INITIATIVES� Improves accuracy of initial estimates� Links to the components and equations are

maintained by the BIM Software� Identifies alternate designs cost quickly� Maximizes resource utilization through visual

monitoring� Bill of materials

Clash Analysis� 3D Visualization of Problems� Tracking of Issues

Supply Chain Management� Visual Tracking of Material Status� Submittal/RFI Reports Imported into Model

Shop Drawings� Documentation of Collaboration� Field Use Sets

BIM OUTPUT

BUILDING INFORMATION MODELINGBIG PICTURE PERSPECTIVE:BIM is JUST a tool – enabling collaboration of the design/construction process. Collaboration: Team partnership, working in a continuous communication environment, under a win-win, solution based culture.

COLLABORATION TECHNIQUES� Qualifications based selection� Partnering sessions� Co-location� Early subcontractor involvement� Continuous budget / scope reconciliation� Document solutions - not problems� Shared legal / financial risk� Shared financial reward

TEAM WIN-WIN STRUCTURE

BIG PICTURE BENEFITS� Visualization� Graphic and engineering analysis� Reduction of field conflicts� Transferability of data� Less waste & increased

prefabrication, better quality� Integration with management tools

– 4D, 5D, XD

Initial Cost Model Refined Scope Cost GMP Cost Set After VESessions Final Cost

79%85%88%

95%100%

BASED ON FIVE RECENT DESIGN/BUILD PROJECTS

“NEW” DELIVERY APPROACH RESULTS

21%AVERAGE

88% 85%%79%7

9% HARD COST SAVINGS

30%IMPROVEMENT

SCHEDULE IMPACT(80+ weeks, 60 if fast tracked)DESIGN/BID/BUILD

REVIEWS3

GC BIDS4

AWARD2

CONSTRUCTION55

CHANGES4

DESIGN18

(60+ weeks, 50 if fast tracked)DESIGN/BUILDCONSTRUCTION48

CHANGES1

DESIGN12

(48+ weeks, 38 if fast tracked)COLLABORATIVE BIM DESIGN/BUILDCONSTRUCTION38

CHANGES0

DESIGN10

PRIME CONTRACTOR METRICSValue Engineering

2.97%

1.28%

Contingency12.0%

9.7%

RFIs/$1M3.4%

10.1%

PreCon Manhours/$1M30.4%

55.6%

Change Orders6.2%

15.4%

Traditional (8 projects, $781 M)BIM Coordination (12 projects, $1.025 B)

SUBCONTRACTOR METRICSShop Drawing

TimeFabrication

CostMaterial

CostInstallation

CostField

SupervisionOverall

Schedule

Piping -15% 0% 15% 10% 25% 20%

HVAC 15%

Steel 12% 5% 8% 9% 0% 30%

Fire Protection 10% 5% 5% 10% 5% 10%

Electrical 50% 0% 17% 15% 9% 25%

Steel 25% 5% 12% 4% 3% 20%

AVERAGE 21% 4% 14% 13% 11% 26%

� Reduction in RFIs� Pre-fabrication� Eliminates re-work� Improves productivity� Instant data transfer� Eliminates “re-draws”

TIME SAVINGS FACTORSCOST SAVINGS FACTORS� Reduced time frames� Eliminate field conflicts� Improved constructability� Reduced documentation� Fewer change orders

OTHER CHALLENGES� Lack of BIM enabled subcontractors� Internal staff resources� AE industry resistance� “Building to the Model”� Interoperability

BIM Virtual

Environment

FUTURE VISION

DESIGN & ENGINEERING•visualization•engineering•analysis•contract documents

CONSTRUCTION APPLICATIONS

•4D scheduling•5D estimating•shop drawings•constructability•RFI/submittals•fabrication

COMMERCE•procurement•invoicing•inventory•bar coding•GPS tracking

FACILITY MANAGEMENT•as-builts•operations•asset management•maintenance•security

Facility Management Applications

HISTORY

•Install date•Warranty•Data•Supplier•Cost•MSDS

PERFORMANCE

•Input flow•M/O Air•Output•Alarms•BAS Interface

MAINTENANCE

•PM schedule•Maintenance

performance•MWO history

What Lies Ahead� The Industry’s newest concerns:� A hole created by the outsourcing of Facilities Management Services� The potential gap in warranty periods� The cost & time of populating CMMS

The Future of FM: A Solution

BMC Vendor

Load from CAD

BIM Model

CMMS Model

Without BIMBUILD

COMMISSIONRUN EQUIPMENT

SOURCE FMRCE FMAWARD FM

LOAD CMMSBALANCE LABOR

6 MONTH GAP

BT

LOAD CMMS USING BIMS USING BIMBALANCE LABOR

With BIM

BT

= CMMS Operational

= Building Turnover

Manufacturer’s Information

Maximo CMMS CFI BIM Perspective

CM- RFP Specification

Require OEM Data via Excel

Spreadsheet

Manufacturers Submit to CM

Using Standardized FormsUsing Standardized Forms

CMMS Model

BIM Model

Excel/XML Forms Loaded in

BIM Model

BIM Asset Data Downloaded

into CMMS

Benefits Delivered� Reduce cost of commissioning� Reduce time in transition from GC to FM� Reduce potential warranty violations� Quality and completeness of information�More comprehensive� Cohesive, turnkey team