BOARD OF DIRECTORS' WORKSHOP MEETING AGENDA Friday, September 27, 2013 County Government Center 70 West Hedding Street San Jose, CA 95110 9:00 AM Closed Session 10 th Floor Conference Room Public Employment [Pursuant to Government Code Section 54957] Title of position to be filled: General Manager The VTA Board of Directors will hold an open session workshop meeting immediately following Closed Session or at 10:00 a.m., whichever is first. 10:00 AM Workshop Meeting Board of Supervisors’ Chambers 3331 North First Street San Jose, CA 95134-1927 Administration 408.321.5555 Customer Service 408.321.2300 To help you better understand, follow, and participate in the meeting, the following information is provided: Persons wishing to address the Board of Directors on any item on the agenda or not on the agenda should complete a blue card located at the public information table and hand it to the Board Secretary staff prior to the meeting or before the item is heard. Speakers will be called to address the Board when their agenda item(s) arise during the meeting and are asked to limit their comments to 2 minutes. The amount of time allocated to speakers may vary at the Chairperson's discretion depending on the number of speakers and length of the agenda. If presenting handout materials, please provide 25 copies to the Board Secretary for distribution to the Board of Directors. All reports for items on the open meeting agenda are available for review in the Board Secretary’s Office, 3331 North First Street, San Jose, California, (408) 321-5680, the Monday, Tuesday, and Wednesday prior to the meeting. This information is available on our website, www.vta.org, and also at the meeting. Any document distributed less than 72-hours prior to the meeting will also be made available to the public at the time of distribution. Copies of items provided by members of the public at the meeting will be made available following the meeting upon request.
Transcript
Page 1: Agenda - Friday, September 27, 2013vtaorgcontent.s3-us-west-1.amazonaws.com/...packet.pdf · Title VI (codified at 42 U.S.C. §2000d et seq.)was enacted as part of the landmark Civil

BOARD OF DIRECTORS' WORKSHOP MEETING AGENDA

Friday, September 27, 2013

County Government Center

70 West Hedding Street

San Jose, CA 95110

9:00 AM

Closed Session 10

th Floor Conference Room

Public Employment

[Pursuant to Government Code Section 54957]

Title of position to be filled: General Manager

The VTA Board of Directors will hold an open session workshop meeting immediately

following Closed Session or at 10:00 a.m., whichever is first.

10:00 AM

Workshop Meeting

Board of Supervisors’ Chambers

3331 North First Street ∙ San Jose, CA 95134-1927 ∙ Administration 408.321.5555 ∙ Customer Service 408.321.2300

To help you better understand, follow, and participate in the meeting, the following information

is provided:

Persons wishing to address the Board of Directors on any item on the agenda or

not on the agenda should complete a blue card located at the public information

table and hand it to the Board Secretary staff prior to the meeting or before the

item is heard.

Speakers will be called to address the Board when their agenda item(s) arise

during the meeting and are asked to limit their comments to 2 minutes. The

amount of time allocated to speakers may vary at the Chairperson's discretion

depending on the number of speakers and length of the agenda. If presenting

handout materials, please provide 25 copies to the Board Secretary for

distribution to the Board of Directors.

All reports for items on the open meeting agenda are available for review in the

Board Secretary’s Office, 3331 North First Street, San Jose, California, (408)

321-5680, the Monday, Tuesday, and Wednesday prior to the meeting. This

information is available on our website, www.vta.org, and also at the meeting.

Any document distributed less than 72-hours prior to the meeting will also be

made available to the public at the time of distribution. Copies of items provided

by members of the public at the meeting will be made available following the

meeting upon request.

Page 2: Agenda - Friday, September 27, 2013vtaorgcontent.s3-us-west-1.amazonaws.com/...packet.pdf · Title VI (codified at 42 U.S.C. §2000d et seq.)was enacted as part of the landmark Civil

WORKSHOP AGENDA

VTA Board of Directors

Friday, September 27, 2013

Page 2 of 3

In accordance with the Americans with Disabilities Act (ADA) and Title VI of the Civil

Rights Act of 1964, VTA will make reasonable arrangements to ensure meaningful access to

its meetings for persons who have disabilities and for persons with limited English

proficiency who need translation and interpretation services. Individuals requiring ADA

accommodations should notify the Board Secretary’s Office at least 48-hours prior to the

meeting. Individuals requiring language assistance should notify the Board Secretary’s

Office at least 72-hours prior to the meeting. The Board Secretary may be contacted at

(408) 321-5680 or e-mail: [email protected] or (408) 321-2330 (TTY only).

VTA’s home page is on the web at: www.vta.org or visit us on Facebook at:

www.facebook.com/scvta. (408) 321-2300: 中文 / Español / 日本語 / 한국어 / tiếng

Việt / Tagalog.

NOTE: THE BOARD OF DIRECTORS MAY ACCEPT, REJECT OR MODIFY

ANY ACTION RECOMMENDED ON THIS AGENDA.

70 West Hedding St., San Jose, California is served by bus lines *61, 62, 66, 181, and Light Rail.

(*61 Southbound last trip is at 8:55 pm for this location.)

For trip planning information, contact our Customer Service Department at (408) 321-2300

between the hours of 6:00 a.m. to 7:00 p.m. Monday through Friday and 7:30 a.m. to 4:00 p.m.

on Saturday. Schedule information is also available on our website, www.vta.org.

Page 3: Agenda - Friday, September 27, 2013vtaorgcontent.s3-us-west-1.amazonaws.com/...packet.pdf · Title VI (codified at 42 U.S.C. §2000d et seq.)was enacted as part of the landmark Civil

WORKSHOP AGENDA

VTA Board of Directors

Friday, September 27, 2013

Page 3 of 3

1. CALL TO ORDER AND ROLL CALL

1.1. ROLL CALL

2. CLOSED SESSION REPORT

3. PUBLIC COMMENT

This portion of the meeting is reserved for persons desiring to address the Board of

Directors on any item within the Board's jurisdiction. Speakers are limited to 2 minutes.

The law does not permit Board action or extended discussion of any item not on the

agenda except under special circumstances. If Board action is requested, the matter can

be placed on a subsequent agenda. All statements that require a response will be referred

to staff for reply in writing.

4. WORKSHOP ITEMS

4.1. INFORMATION ITEM - Receive an update on the Title VI Program. (Fabela)

4.2. INFORMATION ITEM - SVRT Annual Update. (Gonot)

4.3. INFORMATION ITEM - Review the Silicon Valley Express Lanes.

(Ristow/Smith)

5. OTHER ITEMS

5.1. General Manager's Report

A. INFORMATION ITEM - Receive an update on the Public Employee

Pension Reform Act (PEPRA). (Fabela)

5.2. ANNOUNCEMENTS

6. ADJOURN

Page 4: Agenda - Friday, September 27, 2013vtaorgcontent.s3-us-west-1.amazonaws.com/...packet.pdf · Title VI (codified at 42 U.S.C. §2000d et seq.)was enacted as part of the landmark Civil

Date: September 11, 2013

Current Meeting: September 27, 2013

Board Meeting: September 27, 2013

BOARD MEMORANDUM

TO: Santa Clara Valley Transportation Authority

Board of Directors

THROUGH: N/A

FROM: General Counsel Robert R Fabela

SUBJECT: Title VI - Update

3331 North First Street ∙ San Jose, CA 95134-1927 ∙ Administration 408.321.5555 ∙ Customer Service 408.321.2300

FOR INFORMATION ONLY

BACKGROUND:

The Valley Transportation Authority is a recipient of Federal Transit Administration (FTA)

financial assistance. One of the prerequisites for receiving FTA assistance is that the VTA must

comply with Title VI regulations issued by the U.S. Department of Transportation.

Title VI regulations prohibits a recipient from discrimination on the basis of race, color, or

national origin in the provision of public transportation services. Title VI policies also prohibit

the adverse impacts of changes to fares or services to be predominately borne by low-income or

minority individuals.

The FTA Title VI regulations, which have been updated recently, require the public

transportation provider’s governing board to approve system-wide service standards and policies

and the results of their monitoring program relative to those standards and policies. Governing

Boards also need to approve policies to determine when a fare or major service change occurs

that would trigger an equity analysis, which is used to identify disparate impacts and

disproportionate burdens on minority and low income populations. The development of Major

Service Change, Disparate Policy, and Disproportionate Burden policies will need to include

participation and input from the public.

DISCUSSION:

In light of these developments, the VTA General Counsel and VTA staff will provide a verbal

report of the key provisions of Title VI, the newer regulations requiring Board action, and the

schedule for upcoming Board items.

Prepared By: Robert Fabela

Memo No. 4206

4.1

Page 5: Agenda - Friday, September 27, 2013vtaorgcontent.s3-us-west-1.amazonaws.com/...packet.pdf · Title VI (codified at 42 U.S.C. §2000d et seq.)was enacted as part of the landmark Civil

Title VI Program

VTA Board of Directors’ WorkshopSeptember 27, 2013

Presented by:

Robert Fabela, Chief CounselSylvester Fadal, Human Resources Manager

4.1.a

Page 6: Agenda - Friday, September 27, 2013vtaorgcontent.s3-us-west-1.amazonaws.com/...packet.pdf · Title VI (codified at 42 U.S.C. §2000d et seq.)was enacted as part of the landmark Civil

Presentation Overview

What is Title VI? Why is Title VI Important? Required Board Action Schedule

2

4.1.a

Page 7: Agenda - Friday, September 27, 2013vtaorgcontent.s3-us-west-1.amazonaws.com/...packet.pdf · Title VI (codified at 42 U.S.C. §2000d et seq.)was enacted as part of the landmark Civil

Title VI (codified at 42 U.S.C. §2000d et seq.) was enacted as part of the landmark Civil Rights Act of 1964 signed by President Lyndon B.  Johnson.  It prohibits discrimination on the basis of race, color, and national origin in programs and activities receiving federal financial assistance.  

“Overview of Title VI of the Civil Rights Act of 1964,” last updated May 14, 2013, Department of Justice website: http://www.justice.gov/crt/about/cor/coord/titlevi.php

What is Title VI?

3

4.1.a

Page 8: Agenda - Friday, September 27, 2013vtaorgcontent.s3-us-west-1.amazonaws.com/...packet.pdf · Title VI (codified at 42 U.S.C. §2000d et seq.)was enacted as part of the landmark Civil

Title VI Applicability to VTA

As clarified  by the Civil Rights Restoration Act of 1987, Title VI covers all  of the operations of federal aid recipients, without regard to whether specific portions of the recipients’ programs or activities are federally funded. 

As a federal assistance recipient, all VTA programs are subject to Title VI.

4

4.1.a

Page 9: Agenda - Friday, September 27, 2013vtaorgcontent.s3-us-west-1.amazonaws.com/...packet.pdf · Title VI (codified at 42 U.S.C. §2000d et seq.)was enacted as part of the landmark Civil

Why is Title VI Important?Title VI… Ensures that public services, including transportation, are provided in a 

nondiscriminatory manner

Requires opportunities for public participation in decision‐making without regard to race, color, national origin, including populations with limited English proficiency

Removes barriers to public transportation for persons who are limited in English proficiency

Is the subject of renewed focus at the federal level

Non‐compliance with Title VI can cause federal funding to be conditioned or withheld

5

4.1.a

Page 10: Agenda - Friday, September 27, 2013vtaorgcontent.s3-us-west-1.amazonaws.com/...packet.pdf · Title VI (codified at 42 U.S.C. §2000d et seq.)was enacted as part of the landmark Civil

FTA Title VI Monitoring

Review of the Title VI Programs submitted by transit agencies every three years– Includes documentation showing compliance, development and 

implementation of required policies and plans

Investigation of Title VI complaints

Title VI is included as part of FTA Triennial Reviews

6

4.1.a

Page 11: Agenda - Friday, September 27, 2013vtaorgcontent.s3-us-west-1.amazonaws.com/...packet.pdf · Title VI (codified at 42 U.S.C. §2000d et seq.)was enacted as part of the landmark Civil

FTA Title VI Circular: New Primary Requirements

Conduct updated survey of passengers– Collect customer demographic and travel pattern data through passenger 

surveys at least every five years

Develop a formal Public Participation Plan

Minority representation on Planning and Advisory Bodies– Provide a table depicting the racial breakdown of district‐appointed 

planning and advisory committees

Adopt policy on major service changes

Adopt policies on disparate impact and disproportionate burden on specific populations

7

4.1.a

Page 12: Agenda - Friday, September 27, 2013vtaorgcontent.s3-us-west-1.amazonaws.com/...packet.pdf · Title VI (codified at 42 U.S.C. §2000d et seq.)was enacted as part of the landmark Civil

Title VI Service and Fare Equity Analysis

Agencies have to conduct equity analyses whenever they are proposing a fare change or major service change to evaluatethe impacts of their proposed changes on minority and low‐income customers separately.  

Agencies should ensure that there is an equitable distribution of benefits or burdens associated with proposed fare or service changes.

Proposed changes which will have disparate impacts cannot beimplemented by agencies unless:1. There is substantial legitimate justification2. There are no less discriminatory alternatives

Upon completion of a service or fare equity analysis, VTA willbrief its Board and seek approval of the equity analysis and  proposed change.

8

4.1.a

Page 13: Agenda - Friday, September 27, 2013vtaorgcontent.s3-us-west-1.amazonaws.com/...packet.pdf · Title VI (codified at 42 U.S.C. §2000d et seq.)was enacted as part of the landmark Civil

FTA Title VI Circular:  Service Standards and Policies

Adopt system‐wide service standards and policies  – Quantitative standards,  qualitative policies– Requires Board approval prior to submission  to the FTA

Monitor compliance with standards and policies– Present service monitoring results to the Board every three years– Board is required to approve results and provide input on 

mitigations for potential negative findings

9

4.1.a

Page 14: Agenda - Friday, September 27, 2013vtaorgcontent.s3-us-west-1.amazonaws.com/...packet.pdf · Title VI (codified at 42 U.S.C. §2000d et seq.)was enacted as part of the landmark Civil

Board of Director Actions

Review and adopt:

Major Service Change Policy Disparate Impact Policy Disproportionate Burden Policy System‐wide Service Standards and Policies Monitoring  of Transit Service Title VI Program

10

4.1.a

Page 15: Agenda - Friday, September 27, 2013vtaorgcontent.s3-us-west-1.amazonaws.com/...packet.pdf · Title VI (codified at 42 U.S.C. §2000d et seq.)was enacted as part of the landmark Civil

Proposed Title VI Schedule  September 16th‐20th: Public Engagement for Policy 

Development (dates are subject to change)

September 27th: Title VI Overview at Board Workshop

November 7th:  Present Title VI Policies to Board for Approval

December 12th : Present Monitoring Program and Title VI Program to Board for Approval

December  2013: Submit Title VI Program to FTA11

4.1.a

Page 16: Agenda - Friday, September 27, 2013vtaorgcontent.s3-us-west-1.amazonaws.com/...packet.pdf · Title VI (codified at 42 U.S.C. §2000d et seq.)was enacted as part of the landmark Civil

Date: September 18, 2013

Current Meeting: September 27, 2013

Board Meeting: September 27, 2013

BOARD MEMORANDUM

TO: Santa Clara Valley Transportation Authority

Board of Directors

THROUGH: General Manager, Michael T. Burns

FROM: Chief SVRT Program Officer, Carolyn M. Gonot

SUBJECT: SVRT Program Update - BOD Workshop

3331 North First Street ∙ San Jose, CA 95134-1927 ∙ Administration 408.321.5555 ∙ Customer Service 408.321.2300

FOR INFORMATION ONLY

BACKGROUND:

BART Silicon Valley involves a program of transportation improvements throughout the Silicon

Valley Rapid Transit (SVRT) corridor that generally extends from the southern boundary of

Alameda County in the City of Fremont through the cities of Milpitas, San Jose, and Santa Clara.

These improvements include a planned 16-mile, six-station extension of the existing San

Francisco Bay Area Rapid Transit District (BART) system into Silicon Valley. The BART

Silicon Valley program includes the Silicon Valley Berryessa Extension (SVBX), extending the

BART system to Milpitas and the Berryessa area of North San Jose, as well as the Silicon Valley

Santa Clara Extension (SVSX), completing the extension into San Jose and Santa Clara. The

SVRT Program also includes other related projects and activities required to prepare the rail

corridor for BART, such as relocation of existing UPRR tracks and utilities, drainage

improvements, and grade separation projects within the alignment that are funded through other

sources.

DISCUSSION:

Staff will present an update on SVRT Program activities. Discussion items will include an

overview of the overall SVRT budget, and summary of major program activities currently

underway.

Staff will also provide an update on the SVBX project, reviewing the project budget, schedule

and contract plan, as well as providing information on current and near-term construction

activities throughout the corridor, including those pertaining to environmental aspects of the

project and the Residential Noise Insulation program, which provides noise insulation for the

upper floors of residences that may experience potentially severe noise impacts from the BART.

4.2

Page 17: Agenda - Friday, September 27, 2013vtaorgcontent.s3-us-west-1.amazonaws.com/...packet.pdf · Title VI (codified at 42 U.S.C. §2000d et seq.)was enacted as part of the landmark Civil

Page 2 of 2

Additional topics that will be discussed include VTA’s participation in projects that are being

planned and designed in the vicinity of the SVBX project, which will impact project design and

access, BART coordination and activities underway in relation to SVSX.

Prepared By: Carolyn Gonot

Memo No. 4225

4.2

Page 18: Agenda - Friday, September 27, 2013vtaorgcontent.s3-us-west-1.amazonaws.com/...packet.pdf · Title VI (codified at 42 U.S.C. §2000d et seq.)was enacted as part of the landmark Civil

September 27, 2013

Santa Clara Valley Transportation Authority Board of Directors Workshop

1

BART Silicon Valley Update

4.2.a

Page 19: Agenda - Friday, September 27, 2013vtaorgcontent.s3-us-west-1.amazonaws.com/...packet.pdf · Title VI (codified at 42 U.S.C. §2000d et seq.)was enacted as part of the landmark Civil

BART Silicon Valley Summary

- Carolyn Gonot

2

4.2.a

Page 20: Agenda - Friday, September 27, 2013vtaorgcontent.s3-us-west-1.amazonaws.com/...packet.pdf · Title VI (codified at 42 U.S.C. §2000d et seq.)was enacted as part of the landmark Civil

BART Silicon Valley Program

3

• 16-Mile BART Silicon Valley Extension • Corridor Preparation and Maintenance

– Property Acquisition – Freight Rail Relocation – Creek Mitigation

• BART Core System Improvements

4.2.a

Page 21: Agenda - Friday, September 27, 2013vtaorgcontent.s3-us-west-1.amazonaws.com/...packet.pdf · Title VI (codified at 42 U.S.C. §2000d et seq.)was enacted as part of the landmark Civil

$Millions - Year of Expenditure SVRT Program Element Estimate

Incurred To-Date* Status

SVRT Project Development Project Development Through 2009 209.8 209.8 Closed Project Development 2010 and Ongoing 45.3 22.9 Ongoing Project Development Total 255.1 $ 232.7 SVRT Corridor Establishment And Maintenance CEM Programwide (CEMPW) 2.8 2.8 Closed UPRR-Performed Activities (UPRR) 65.4 57.3 Ongoing Newhall Yard Property (NHY) 42.6 41.6 Ongoing Mitchell Block Property (MBP) 39.6 37.1 Ongoing Kato Grade Separation Project (KGS) 52.7 47.6 Under Construction Mission Warren truck-Rail (MWT) 156.0 88.4 Under Construction Lower Berryessa Creek Project (LBC) 82.1 73.8 Substantially Complete

Montague Reconstruction Project (MRP) 17.1 0.1 Design/ROW Corridor Establishment And Maintenance Total $ 458.2 $ 348.7 BART Silicon Valley Extension SVBX - Berryessa Extension Project 2,421.3 567.9 Under Construction SVSX - Future Extension to Santa Clara*1 4,122.5 160.7 Under Development BART Core System Modifications (BCS) 269.2 58.0 Ongoing BART Silicon Valley Extension Total $ 6,813.0 $ 786.6 BART Warm Springs Extension Warm Springs Extension (WSX)*2 8.0 2.5 VTA Funding Committment SVRT PROGRAM TOTALS $ 7,534.4 $ 1,370.5

* Incurred through July 31, 2013; The totals may differ from SAP totals due to rounding. *1 Source: Metropolitan Transportation Commission’s Transportation 2035 Plan for the San Francisco Bay Area: $3,962.0 (m) to-go, $160.5 incurred to-date (m). *2 Program Estimates adjusted to reflect assignment of grant funds appropriated between VTA and BART.

4

BART Silicon Valley Budget/Status

4.2.a

Page 22: Agenda - Friday, September 27, 2013vtaorgcontent.s3-us-west-1.amazonaws.com/...packet.pdf · Title VI (codified at 42 U.S.C. §2000d et seq.)was enacted as part of the landmark Civil

BART Silicon Valley Berryessa Extension (SVBX) Update

- Mark Massman

5

4.2.a

Page 23: Agenda - Friday, September 27, 2013vtaorgcontent.s3-us-west-1.amazonaws.com/...packet.pdf · Title VI (codified at 42 U.S.C. §2000d et seq.)was enacted as part of the landmark Civil

SVBX Schedule

6

1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4

SVBX Summary Schedule - FFGA (Baseline) with Forecast (Data Date: August 2013) Date: 09/06/13

Campus, Roadways, & Parking

Design

Construction

Pre-Revenue Operations Testing

Revenue Vehicles - Design

Hayward Yard Primary Shop Conversion

BART provided Materials, Software and Equipment

Manufacture & Delivery Pilot & Production Vehicles

Guideway Construction

Stations Construction

Systems Procurement & Construction

Systems Integration Testing

2017

ROW Parcel Acquisition

Longitudinal Utility Relocation

C700 LTSS Design/Build

Design

Milestones

C101 Mission, Warren BART Bridges

C222 Kato Rd BART Bridge

C610 Piper Dr Utilities

BART

2012 2013 2014 2015 2016

1 2 3 4

2018

Forecast Actual Progress

C700 LNTP

FFGA

C101 MWT T/O to C700 BART Warm Springs T/O to C700

Forecast Revenue Operations

FTA Baseline

FFGA Revenue Operations

First Vehicles Last Vehicles

Last VehiclesFirst

August2013

Start Dynamic

Complete Dynamic Testing

Start Dynamic Testing

Complete Dynamic Testing

Construction

Procurement

Procurement

Forecast C101 T/O to C700 (C700 Contract Date)Forecast WSX T/O to C700 (C700 Contract Date)

C222 Kato T/O to C222 T/O to C700

Start Construction

Buffer ~ 9 months

BEG

IN R

EVEN

UE

SERV

ICES

4.2.a

Page 24: Agenda - Friday, September 27, 2013vtaorgcontent.s3-us-west-1.amazonaws.com/...packet.pdf · Title VI (codified at 42 U.S.C. §2000d et seq.)was enacted as part of the landmark Civil

Construction Plan Update

7

4.2.a

Page 25: Agenda - Friday, September 27, 2013vtaorgcontent.s3-us-west-1.amazonaws.com/...packet.pdf · Title VI (codified at 42 U.S.C. §2000d et seq.)was enacted as part of the landmark Civil

66” SCV Water Line San Jose Construction Activities

4.2.a

Page 26: Agenda - Friday, September 27, 2013vtaorgcontent.s3-us-west-1.amazonaws.com/...packet.pdf · Title VI (codified at 42 U.S.C. §2000d et seq.)was enacted as part of the landmark Civil

San Jose Construction Activities

4.2.a

Page 27: Agenda - Friday, September 27, 2013vtaorgcontent.s3-us-west-1.amazonaws.com/...packet.pdf · Title VI (codified at 42 U.S.C. §2000d et seq.)was enacted as part of the landmark Civil

4.2.a

Page 28: Agenda - Friday, September 27, 2013vtaorgcontent.s3-us-west-1.amazonaws.com/...packet.pdf · Title VI (codified at 42 U.S.C. §2000d et seq.)was enacted as part of the landmark Civil

Construction Planned for Next 6 Months Berryessa Aerial Guideway

Berryessa Station - Structure Las Plumas Substation

Approach Structures at Berryessa Hostetter Trench

Hostetter Substation Hostetter Overhead Structure

Utilities at Maybury & Berryessa

4.2.a

Page 29: Agenda - Friday, September 27, 2013vtaorgcontent.s3-us-west-1.amazonaws.com/...packet.pdf · Title VI (codified at 42 U.S.C. §2000d et seq.)was enacted as part of the landmark Civil

Construction Planned for Next 6 Months Montague Trench

Industrial Lead Bridge T-Wall Adjacent to Support New UPRR Industrial Lead Track

At Grade BART 34.5KV Ductbank Montague Expressway Overhead Structure

Milpitas Station Substructure Capital Ave Overhead Structure

4.2.a

Page 30: Agenda - Friday, September 27, 2013vtaorgcontent.s3-us-west-1.amazonaws.com/...packet.pdf · Title VI (codified at 42 U.S.C. §2000d et seq.)was enacted as part of the landmark Civil

Subcontractor Status : Current Commitments & To Be Procured

SCOPE PACKAGE DESCRIPTION FOR FUTURE CONTRACTS ESTIMATED SCOPE VALUE

CMU $ 3,000,000

Coatings/Paintings $ 2,000,000

Drywall/Insulation/Ceilings $ 5,000,000

Duct Bank $ 5,000,000

Floating Track Slab and Bearings $ 12,000,000

Flooring, Skylights, Ceilings, Millwork, Doors, Caulking $ 2,000,000

Glazing $ 3,000,000

Metal Siding/Roofing $ 5,000,000

Metal Wall Panets, Ceilings, and Roof $ 1,000,000

Misc Metals $ 2,000,000

Permanent Fencing $ 3,000,000

Poured in Place Retaining Walls $ 6,000,000

Stone Columns $ 1,000,000

Structural Concrete / Stations $ 3,000,000

Structural Steel/Ornamental Steel $ 15,000,000

Temp Walls & Barricades $ 1,000,000

Trucking $ 8,000,000

Utilities $ 15,000,000

Waterproofing - Furnish & Install $ 6,000,000

FUTURE SUBS TOTAL $ 98,000,000

SCOPE PACKAGE DESCRIPTION FOR EXISTING SUBCONTRACTORS ESTIMATED SCOPE VALUE

Misc Subcontracts - Project to Date $ 35,000,000

Aggregates, Including Ballast $ 12,000,000

Asphalt-Concrete Paving Sub $ 3,000,000

Cable Trench Trough $ 5,000,000

Concrete - Minor/Site $ 4,000,000

Concrete Material - Furnish $ 25,000,000

Concrete Piling, Furnish and Install $ 3,000,000

Design $ 45,000,000

Electrical and Systems $ 170,000,000

Fire Protection $ 3,000,000

Fuel $ 3,000,000

Furnish Track Material - Running Rail, Third Rail, Ties, Special Track… $ 25,000,000

Potholing $ 1,000,000

QC/QA $ 10,000,000

Rebar - Furnish and Install $ 40,000,000

Sheet Piles $ 14,000,000

Survey $ 3,000,000

SWPPP (Sweeper, Water Truck, Dewatering, etc) $ 3,000,000

ENGAGED SUBS TOTAL $ 305,000,000

13

4.2.a

Page 31: Agenda - Friday, September 27, 2013vtaorgcontent.s3-us-west-1.amazonaws.com/...packet.pdf · Title VI (codified at 42 U.S.C. §2000d et seq.)was enacted as part of the landmark Civil

DBE Subcontracts: Committed to Date

SCOPE OF WORK SUBCONTRACTOR / VENDOR Wayside Signs A Plus Signs, Inc. Asphalt Grinding ABSL Construction Voice and data, surveillance, communications AEKO Consulting - SSH TI Message and Arrow Boards All American Rentals 3rd Party Utility Design Review Alliance Engineering Consultants Noise and Vibration Monitoring - UPC Analysis & Solutions Consultants Security Guard Services Ani Private Security & Patrol Electrical Supplies for MCI FOC Relocation (CN#2) Azco Supply, Inc. Potholing Bess Testlab, Inc. Removal and Disposal of Underground Tank Burke Construction Concrete Pumping Services Cal-Con Pumping Fire Protection EMF Fire Protection First Responder Fire Protection Resilient and Concrete Tie JP and Concepts Staffing Services JLM Staffing Solutions Staffing Services Josephine Staffing Pile Fabrication Kus'tum Steel Distributor for Third Rail Package Lanier Steel Water Truck on Site Lavell Water Truck Services Pre-Con Survey Morgner Construction Management Street Sweeper MRB California Design Services for Wayside Stations NBA Quality Assurance Services Quality Engineering, Inc. Temp Fencing Oliveria Fence, Inc. Survey Rail Surveyors and Engineers, Inc. Janitorial S.J. General Building Maintenance, Inc. Water and Sweeper Truck Tri-Valley Water Truck Community Relations Officer VSCE,Inc

SCOPE OF WORK

LAN / TYLIN

Architecture/Stations Anil Verma Associates, Inc. Traffic Marks Traffic Data Services, Inc. Fire Protection NBA Engineers Geotechnical Parikh Consultants, Inc.

Engineering Consutlants Alliance Engineering Consultants (2nd tier to Anil)

Systems Colmena Engineering (2nd tier to LTK Eng)

Lead and Asbestos Work Kellco (2nd tier to ENGEO) Structural Engineering SOHA Engineers (1st tier to TYLin) Groundwater Model QC Todd Engineers Lab Testing Torrent (2nd tier to ENGEO)

TOTALS FOR LAN TY LIN SUBS TO DATE

ALDRIDGE / ROSENDIN JV

Install ground traction power building Bass Electric Pulling,Splicing,terminting and testing of AC & DC high voltage cables HI-Voltage Splicing Co, Inc.

TOTAL VALUE OF COMMITMENTS To DATE: $67M

4.2.a

Page 32: Agenda - Friday, September 27, 2013vtaorgcontent.s3-us-west-1.amazonaws.com/...packet.pdf · Title VI (codified at 42 U.S.C. §2000d et seq.)was enacted as part of the landmark Civil

Residential Noise Insulation Program

C750 C751 C752 C753

15

4.2.a

Page 33: Agenda - Friday, September 27, 2013vtaorgcontent.s3-us-west-1.amazonaws.com/...packet.pdf · Title VI (codified at 42 U.S.C. §2000d et seq.)was enacted as part of the landmark Civil

Residential Noise Insulation Program Contract Status

• 246 units in the program • Four construction contracts (Total estimated value: $3.5M)

C750 (49 units) – Verification of Measurements completed. C751 (65 units) – Board memo approved by the TP&O Committee. C752 (63 units) – 100% design completed. C753 (69 units) – 95% design completed.

16

4.2.a

Page 34: Agenda - Friday, September 27, 2013vtaorgcontent.s3-us-west-1.amazonaws.com/...packet.pdf · Title VI (codified at 42 U.S.C. §2000d et seq.)was enacted as part of the landmark Civil

Residential Noise Insulation Program Project Schedule

2011 2012 2013 2014 2015 2016 2017

RNIP Outreach

RNIP Design

RNIP Construction

Silicon Valley Berrysessa Extension Construction Activities

Heavy construction begins

17

4.2.a

Page 35: Agenda - Friday, September 27, 2013vtaorgcontent.s3-us-west-1.amazonaws.com/...packet.pdf · Title VI (codified at 42 U.S.C. §2000d et seq.)was enacted as part of the landmark Civil

Archeological Update

Penitencia Creek Site • Approximately 400 years old and occupied for

around 50 years. • Recovered 16 burials with funerary objects--shell

beads; cultural artifacts--bone tools, mortars, pestles; and features--hearths and pits.

18

Documentation and recovery of a pit feature

Great Mall Site • Approximately 3,000 to 5,000 years old. • To date, recovered 3 burials with

funerary objects--slate pendants, charmstones, ceremonial spear points, and an abalone shell.

Stone spear points; pendants; charmstones; pestles

4.2.a

Page 36: Agenda - Friday, September 27, 2013vtaorgcontent.s3-us-west-1.amazonaws.com/...packet.pdf · Title VI (codified at 42 U.S.C. §2000d et seq.)was enacted as part of the landmark Civil

Biological Update

Upper Penitencia Creek Restoration • Creek realignment complete • Wetland, riparian, and upland habitat

developing nicely • Wildlife returning to the site – fish

species, herons, egrets, ducks, Pacific lamprey (special status)

• Monitoring for steelhead begins in September

19

Burrowing Owls In Fremont • Pair of owls nested a few feet from UPRR

tracks near SVBX construction • Buffer zone established • 7 chicks hatched in June (5 shown in photo) • All chicks fledged by August

4.2.a

Page 37: Agenda - Friday, September 27, 2013vtaorgcontent.s3-us-west-1.amazonaws.com/...packet.pdf · Title VI (codified at 42 U.S.C. §2000d et seq.)was enacted as part of the landmark Civil

SVBX Budget

20

Period Jul-13

Report Date 23-Aug-13

Standard Cost Category Description Estimate1

(A)

Forecast @ Completion

(C)

Variance (D) = (C) – (A)

Incurred to Date

(E)

10 Guideway and Track Elements $ 416.1 $ 308.3 $ (107.80) $ 43.1

20 Stations , Stops , Terminals , & Intermodal $ 250.3 $ 259.2 $ 8.90 $ 7.6

30 Support Faci l i ties : Yards , Shops , Admin. Bldgs $ 46.5 $ 46.5 $ - $ 3.7

40 Si tework & Specia l Conditions $ 220.1 $ 231.2 $ 11.10 $ 33.1

50 Systems $ 260.7 $ 230.3 $ (30.40) $ 18.9

60 ROW, Land and Exis ting Improvements $ 261.0 $ 249.7 $ (11.30) $ 133.7

70 Vehicles $ 174.3 $ 158.0 $ (16.30) $ -

80 Profess ional Services $ 548.3 $ 548.3 $ - $ 319.8

90 Unal located Contingency $ 40.2 $ 186.0 $ 145.80 $ -

100 Finance Charges $ 112.5 $ 112.5 $ - $ -

Total New Starts Project $ 2,330.0 $ 2,330.0 $ (0.00) $ 559.9

Total Concurrent Non-New Starts Project Activities $ 91.3 $ 91.3 $ - $ 8.0

Total SVBX Project Cost $ 2,421.3 $ 2,421.3 $ (0.00) $ 567.9

Silicon Valley Berryessa Extension ProjectCost Report by Standard Cost Category

In Millions

1. Source: USDOT FTA - VTA Full Funding Grant Agreement CA-03-0818-00 of March 12, 2012

2. Totals may vary from the VTA cost account system (SAP) totals due to rounding

NEW STARTS PROJECT

CONCURRENT NON-NEW STARTS PROJECT ACTIVITIES

4.2.a

Page 38: Agenda - Friday, September 27, 2013vtaorgcontent.s3-us-west-1.amazonaws.com/...packet.pdf · Title VI (codified at 42 U.S.C. §2000d et seq.)was enacted as part of the landmark Civil

BART Silicon Valley Outreach

- Bernice Alaniz

21

4.2.a

Page 39: Agenda - Friday, September 27, 2013vtaorgcontent.s3-us-west-1.amazonaws.com/...packet.pdf · Title VI (codified at 42 U.S.C. §2000d et seq.)was enacted as part of the landmark Civil

22

Activity Year-to-Date

Project Communications and Outreach

Presentation/Representation at Local Events

52 Events/Meetings

Traffic Advisories and Construction Updates/Notices

19 Notifications

Mailers and Quarterly Project Newsletters

92,100 Residences and Businesses

Salesforce/Customer Records Management

29,100 Constituents

Door-to-Door Outreach Ongoing

Project Media

News Releases 6 distributed, generating 94 print articles and 226 broadcast mentions

Project Videos 6 produced with nearly 14,600 views on the project channel

Facebook/Twitter Ongoing presence with hundreds of likes and followers

4.2.a

Page 40: Agenda - Friday, September 27, 2013vtaorgcontent.s3-us-west-1.amazonaws.com/...packet.pdf · Title VI (codified at 42 U.S.C. §2000d et seq.)was enacted as part of the landmark Civil

Joint Media Event and Tour, June 26

Milpitas Community Meeting, June 19

23

4.2.a

Page 42: Agenda - Friday, September 27, 2013vtaorgcontent.s3-us-west-1.amazonaws.com/...packet.pdf · Title VI (codified at 42 U.S.C. §2000d et seq.)was enacted as part of the landmark Civil

Other Projects

- Carolyn Gonot

25

4.2.a

Page 43: Agenda - Friday, September 27, 2013vtaorgcontent.s3-us-west-1.amazonaws.com/...packet.pdf · Title VI (codified at 42 U.S.C. §2000d et seq.)was enacted as part of the landmark Civil

Montague Expressway Reconstruction Project

26

• Project partners - Santa Clara County, Santa Clara Valley Water District, City of Milpitas, and VTA

• VTA to manage and construct; Santa Clara County and Santa Clara Valley Water District to fund

• Project includes widening of Montague Expwy. and raising Montague Expwy. over Upper Berryessa Creek

• Accommodates future Upper Berryessa Creek Flood Control Project.

4.2.a

Page 44: Agenda - Friday, September 27, 2013vtaorgcontent.s3-us-west-1.amazonaws.com/...packet.pdf · Title VI (codified at 42 U.S.C. §2000d et seq.)was enacted as part of the landmark Civil

SVBX Curtis Park Mitigation/ Montague Pedestrian Overcrossing at BART Station

27

Curtis Park Mitigation

• VTA relocating UPRR freight tracks to clear sufficient right-of-way for BART

• Relocation requires acquisition of 20 foot strip (0.1 acre) from Curtis Park

• Acquisition environmentally cleared in SVBX Environmental Impact Statement

• As mitigation, VTA is preparing preliminary engineering for a pedestrian overcrossing over Montague Expressway at Milpitas BART Station.

• Included on VTA OBAG project list for final design and environmental clearance in the amount of $744,000

4.2.a

Page 45: Agenda - Friday, September 27, 2013vtaorgcontent.s3-us-west-1.amazonaws.com/...packet.pdf · Title VI (codified at 42 U.S.C. §2000d et seq.)was enacted as part of the landmark Civil

SVBX Curtis Park Mitigation/ Montague Pedestrian Overcrossing at BART Station

28

4.2.a

Page 46: Agenda - Friday, September 27, 2013vtaorgcontent.s3-us-west-1.amazonaws.com/...packet.pdf · Title VI (codified at 42 U.S.C. §2000d et seq.)was enacted as part of the landmark Civil

Upper Penitencia Creek Trail Connection

Trail Project Elements

• Top rated project on VTA OBAG project list

• 18-foot wide shared use trail

• Provision for equestrians/Bay Ridge Trail

• Full traffic signal on King Road

• Trailhead gateways

• Interpretive signs for UPC mitigation site

• CSJ and VTA owns required right-of-way

• Design 2013/14, construction planned 2015/16 with campus contracts

• Included on VTA OBAG project list in the amount of $1,514,000 for construction

29

CSJ Sample Trailhead Gateways

4.2.a

Page 47: Agenda - Friday, September 27, 2013vtaorgcontent.s3-us-west-1.amazonaws.com/...packet.pdf · Title VI (codified at 42 U.S.C. §2000d et seq.)was enacted as part of the landmark Civil

Upper Penitencia Creek Trail Connection Map

30

4.2.a

Page 48: Agenda - Friday, September 27, 2013vtaorgcontent.s3-us-west-1.amazonaws.com/...packet.pdf · Title VI (codified at 42 U.S.C. §2000d et seq.)was enacted as part of the landmark Civil

BART Coordination

- Dennis Ratcliffe

31

4.2.a

Page 49: Agenda - Friday, September 27, 2013vtaorgcontent.s3-us-west-1.amazonaws.com/...packet.pdf · Title VI (codified at 42 U.S.C. §2000d et seq.)was enacted as part of the landmark Civil

32

Key Activities

• SVBX Project - BART support through the phases of the extension - Implementation Letters related to reimbursing BART for costs incurred to support the project (Ongoing) - Amount authorized to date: $29 million • BART Supplied Equipment - Supply of select equipment/software for SVBX - Implementation Letters for cost reimbursement (Ongoing) - Amount authorized to date: $9 million • Hayward Maintenance Complex - Expansion of the existing facility necessary to support SVBX and elements of future SVRT extension - Side Agreement establishing the scope and cost share (Executed) - Implementation Letters for environmental clearance, engineering, right-of-way acquisition, and construction (Ongoing) - Expansion estimated to be $175 million and $17 million has been authorized to date

4.2.a

Page 50: Agenda - Friday, September 27, 2013vtaorgcontent.s3-us-west-1.amazonaws.com/...packet.pdf · Title VI (codified at 42 U.S.C. §2000d et seq.)was enacted as part of the landmark Civil

33

Key Activities

• Vehicle Procurement Agreement - Procurement of new rolling stock - Side Agreement for procurement, ownership and operation (Being finalized) - Implementation Letter for the procurement of 60 vehicles for SVBX (Draft) - Cost of vehicle procurement is estimated to be $215 million • Operations Control Center - Expansion/Replacement of BART’s existing Operation Control Center - Side Agreement defining VTA’s financial commitment (Future) • Core System Improvements - Capital improvements addressing SVRT system impacts on existing BART infrastructure - Implementation Letters defining VTA’s financial commitment (Future) • Operations and Maintenance Agreement - Side Agreement establishing the basis of proportional cost sharing for ongoing Operations and Maintenance costs (Future)

4.2.a

Page 51: Agenda - Friday, September 27, 2013vtaorgcontent.s3-us-west-1.amazonaws.com/...packet.pdf · Title VI (codified at 42 U.S.C. §2000d et seq.)was enacted as part of the landmark Civil

BART Silicon Valley Santa Clara Extension (SVSX)

- Carolyn Gonot

34

4.2.a

Page 52: Agenda - Friday, September 27, 2013vtaorgcontent.s3-us-west-1.amazonaws.com/...packet.pdf · Title VI (codified at 42 U.S.C. §2000d et seq.)was enacted as part of the landmark Civil

35

• Environmental Studies for BART Silicon Valley Santa Clara Extension (SVSX) initiated

- Scoping period to begin in Late-January with Notice of Intent in the Federal Register

- Public Circulation of Administrative Draft of environmental documents to begin in November 2014

- Preparation of final environmental documents to begin in 1Q2015

- Federal Record of Decision expected in Winter of 2015

• Preparation for entry into the Federal New Starts Program planned for 1Q2014

• FTA’s approval of VTA’s request for entry into New Starts anticipated in 3Q2014

Major SVSX Activities 4.2.a

Page 53: Agenda - Friday, September 27, 2013vtaorgcontent.s3-us-west-1.amazonaws.com/...packet.pdf · Title VI (codified at 42 U.S.C. §2000d et seq.)was enacted as part of the landmark Civil

12-Month Look Ahead

- Carolyn Gonot

36

4.2.a

Page 54: Agenda - Friday, September 27, 2013vtaorgcontent.s3-us-west-1.amazonaws.com/...packet.pdf · Title VI (codified at 42 U.S.C. §2000d et seq.)was enacted as part of the landmark Civil

37

Major Activities over next 12 months

• Substantially complete design by C700 Line, Track, Stations and Systems (LTSS) Contractor

• Turnover of the corridor north of Kato Road by C101 Mission, Warren, Truck-Rail Contractor to C700 LTSS Contractor

• Complete UPRR Industrial Lead Bridge at Piper Drive.

• Significantly progress trench construction at Montague and Hostetter

• Award parking structure contractor; contractor substantially complete design

• Significantly progress construction of Berryessa Aerial Structure and Station

• Complete the grade separation and open Warren Avenue to traffic

• Approve agreement on BART Operations Control Center cost share and funding

• Enter News Starts process for next phase of BART Silicon Valley extension

4.2.a

Page 55: Agenda - Friday, September 27, 2013vtaorgcontent.s3-us-west-1.amazonaws.com/...packet.pdf · Title VI (codified at 42 U.S.C. §2000d et seq.)was enacted as part of the landmark Civil

Date: September 17, 2013

Current Meeting: September 27, 2013

Board Meeting: September 27, 2013

BOARD MEMORANDUM

TO: Santa Clara Valley Transportation Authority

Board of Directors

THROUGH: General Manager, Michael T. Burns

FROM: Chief CMA Officer, Ristow, Chief Financial Officer, Smith

SUBJECT: Silicon Valley Express Lanes

3331 North First Street ∙ San Jose, CA 95134-1927 ∙ Administration 408.321.5555 ∙ Customer Service 408.321.2300

FOR INFORMATION ONLY

BACKGROUND:

At the December 2008 Board Meeting, Santa Clara Valley Transportation Authority (VTA)

Board of Directors approved the Silicon Valley Express Lanes Program. The Program has been

undertaken to provide long-term mobility benefits and to provide another funding stream for

transportation improvements. Specifically, the primary objectives of the Program are the

following:

1. Provide congestion relief through more effective use of existing roadways;

2. Provide commuters with a new mobility option; and

3. Provide a new funding source for transportation improvements including public transit.

At the December 2008 Board Meeting, the Board of Directors also directed staff to develop

funding plan options for the completion of the Program for future consideration. This

memorandum highlights the general approach planned to deliver and fund the Express Lanes

Program with details to be presented at the September 27, 2013 Board workshop.

DISCUSSION:

Following Board approval of the Silicon Valley Express Lanes Program, staff began

implementation following an incremental approach based on available funding to move project

phases forward. The implementation included US 101/SR 85 moving into an environmental

clearance phase and SR 237 into a full development, construction and operations phase.

As a result, the first phase of the SR 237 Express Lanes project that converted the carpool lane

direct connector ramps at the SR 237/I-880 interchange to Express Lanes operations (Attachment

A) as the first express lanes project implemented as part of the Program. The opening of this

project on March 20, 2012 represents the first major milestone in delivery of the Silicon Valley

4.3

Page 56: Agenda - Friday, September 27, 2013vtaorgcontent.s3-us-west-1.amazonaws.com/...packet.pdf · Title VI (codified at 42 U.S.C. §2000d et seq.)was enacted as part of the landmark Civil

Page 2 of 4

Express Lanes Program. The $11.8 million project was funded from $3.5 million American

Recovery and Reinvestment Act (ARRA), $4 million Federal Value Pricing Pilot Program

(VPPP) and $4.3 million of local funding. The project has been a success by providing both a

new option for solo drivers to improve travel times up to 15 minutes in the corridor and has

revenues exceeding expenses. The project has also been recognized by both the California

Transportation Foundation (CTF) and the Institute of Transportation Engineers (ITE) as “Project

of the Year" for 2012.

The implementation of this initial Express Lanes project reflects the characteristics of the

Program implementation to date: incremental delivery, VTA to maintain control of the

operations and taking steps to minimize financial risk. The result has been a project that has

been able to produce travel time benefits to commuters while generating revenues that exceed its

day-to-day operational costs. The recommended approach is to continue the incremental

implementation for the remaining corridors on US 101/SR 85.

The incremental approach includes the ongoing work to complete environmental clearance for

the US 101/SR 85 and SR 237 Corridors. This includes extending Express Lane operations for

SR 237 west to near Mathilda Avenue in the City of Sunnyvale, conversion of US 101 carpool

lanes to express lanes operations (about 34 miles between the City of Morgan Hill and the City

of Palo Alto) and the same for SR 85 (about 24 miles along its entire length from the southern

reaches of the City of San Jose to the City of Mountain View).

The remainder of this memorandum provides information on how the ongoing Express Lanes

work on SR 237, US 101 and SR 85 can be delivered.

Silicon Valley Express Lanes Program Delivery Considerations

As previously described in this memorandum, to date the Program has taken an incremental

approach for delivery of Express Lanes in Santa Clara County. The plan moving forward is to

remain consistent with such an incremental approach and is proposed to build upon the

following:

Use Traditional Design-Bid-Build Approach. This is the most common approach for delivery

of highway projects. In recent informational memorandums, alternative delivery methods have

been shared as possible options. However, methods such as design-build or those that involve a

public-private partnership could require the passage of legislation or the resolution of other

issues not in VTA's control for these approaches to be feasible. The Express Lane system

improvements can be built incrementally by designing and building the system segment-by-

segment based on available funding/financing and highest travel benefits to motorists.

VTA Board Retains Control of the Program and the Delivery Process. A key working

assumption is that operational control of the Program would remain with VTA. This means that

decisions related to funding and delivery of the Program and risks related to delivery of the

Program would essentially remain with VTA. Particularly when it comes to the construction of

the Express Lanes improvements, the financial risks would be different than those related to

capital projects funded through a transit sales tax measure. It would also mean that VTA and the

4.3

Page 57: Agenda - Friday, September 27, 2013vtaorgcontent.s3-us-west-1.amazonaws.com/...packet.pdf · Title VI (codified at 42 U.S.C. §2000d et seq.)was enacted as part of the landmark Civil

Page 3 of 4

Santa Clara County transportation system also stands to benefit from the improved travel option

and potentially positive revenue generated by the system.

Design Incrementally Using Funds from Grants and/or Fund Exchanges. In 2014,

environmental clearance is expected for US 101/SR 85 and SR 237 (Phase 2) Express Lanes.

The preliminary engineering that is being completed in support of the environmental clearance

work will also provide cost estimates for future phases of these improvements. On the basis of

this information, the proposal is to start final design work for SR 237 (Phase 2) and for a

segment of the US 101/SR 85 Express Lanes. The estimated design development cost for the

initial incremental portion of the Program is estimated to be $20 million. Final design

development for remaining segments of the US101/ SR 85 Corridors is estimated at an additional

$30 million.

Fund Exchange for Design/Development: Provide design/development funds through VTA

controlled processes and sources. The recommended approach is to utilize the same

STIP/Measure A fund exchange employed in 2006 and 2007 which provided flexible funds to

compete the $190 million Proposition 1B highway projects on I-880, US 101, I-280/880 Stevens

Creek interchange in San Jose, Mountain View and Palo Alto. The fund exchange allows VTA to

maintain control over the process and provide flexible funding which can be used now to

advance the projects in the final design development phase.

Construct Incrementally Using a Variety of Funds. The total estimated cost for construction

for US 101/SR 85 and SR 237 (Phase 2) Express Lanes is $600 million. As each segment is

designed, each incremental segment would move forward for construction. The improvements

could be constructed in multiple segments. The underlying challenge that VTA has in moving

the Program forward is that the VTA Highway Program does not have a dedicated local source

of revenue similar to the dedicated sales tax source that VTA Transit Program utilizes. As a

result, the funding would come from a combination of toll revenue bonds, federal loans and local

sources as needed. The exact composition of the funding will vary based on construction cost

bids, projected toll revenues, bond market conditions and VTA risk tolerance. The following are

examples of the multiple components needed for funding sources:

VTA Obtained Contributions: The SR 237 express lanes in operation received federal

grants. Other possible sources already mentioned are STIP funds.

Senior Revenue Bonds: Long -term tax exempt bonds backed by future traffic and

revenue forecasts from express lanes.

Subordinated Debt: The Transportation Infrastructure Finance and Innovation Act of

1998 (TIFIA) established a federal program under which transportation authorities can

borrow directly from or use the credit of the U.S. Treasury to finance up to 49% of the

cost of major transportation projects.

Public Contributions: Third party funding consisting of Federal grants, local grants and

third party loans.

4.3

Page 58: Agenda - Friday, September 27, 2013vtaorgcontent.s3-us-west-1.amazonaws.com/...packet.pdf · Title VI (codified at 42 U.S.C. §2000d et seq.)was enacted as part of the landmark Civil

Page 4 of 4

Credit Enhancement: Credit enhancement in the form of bond insurance that would

lower interest expense and increase financial feasibility.

Next Steps

There are two next actions for the VTA Board of Directors to consider:

November 7, 2013, VTA Board of Directors meeting:

Approval of STIP programming for FY 2014 combined with the Measure A fund

exchange of STIP funds for the Express Lanes Program to undertake design/development

Approval of existing Local Program Reserve funds for Express Lanes Program

design/development effort also at the November 2013 meeting.

Staff to return with recommended phasing of the Express Lanes segment in spring 2014

Prepared By: Murali Ramanujam, Casey Emoto, Joseph Smith and John Ristow

Memo No. 4191

4.3

Page 59: Agenda - Friday, September 27, 2013vtaorgcontent.s3-us-west-1.amazonaws.com/...packet.pdf · Title VI (codified at 42 U.S.C. §2000d et seq.)was enacted as part of the landmark Civil

4.3.a

Page 60: Agenda - Friday, September 27, 2013vtaorgcontent.s3-us-west-1.amazonaws.com/...packet.pdf · Title VI (codified at 42 U.S.C. §2000d et seq.)was enacted as part of the landmark Civil

1August 2013

Silicon Valley Express Lanes Program

Board Workshop

September 27, 2013

4.3.b

Page 61: Agenda - Friday, September 27, 2013vtaorgcontent.s3-us-west-1.amazonaws.com/...packet.pdf · Title VI (codified at 42 U.S.C. §2000d et seq.)was enacted as part of the landmark Civil

2

Agenda

Background on Silicon Valley Express Lanes

Funding

Next Steps

4.3.b

Page 62: Agenda - Friday, September 27, 2013vtaorgcontent.s3-us-west-1.amazonaws.com/...packet.pdf · Title VI (codified at 42 U.S.C. §2000d et seq.)was enacted as part of the landmark Civil

3

How we got here…

Legislative Approvals AB 2032 (2004)

AB 574 (2007)

AB 1105 (2011)

Equity Study (2004)

VTA Feasibility Study (2005)

External communication and outreach

4.3.b

Page 63: Agenda - Friday, September 27, 2013vtaorgcontent.s3-us-west-1.amazonaws.com/...packet.pdf · Title VI (codified at 42 U.S.C. §2000d et seq.)was enacted as part of the landmark Civil

4

Approved Silicon Valley Express

Lanes Program

2008 VTA Board

approval: Implementation of Express

Lanes on US 101/SR 85 and

SR 237 corridors

Directed staff to return with

funding options to complete

Express Lanes Program

4.3.b

Page 64: Agenda - Friday, September 27, 2013vtaorgcontent.s3-us-west-1.amazonaws.com/...packet.pdf · Title VI (codified at 42 U.S.C. §2000d et seq.)was enacted as part of the landmark Civil

5

4.3.b

Page 65: Agenda - Friday, September 27, 2013vtaorgcontent.s3-us-west-1.amazonaws.com/...packet.pdf · Title VI (codified at 42 U.S.C. §2000d et seq.)was enacted as part of the landmark Civil

6

Proceeded with incremental implementation

based on funding availability.

I-680 EL opened for tolling in September 2010

Proceeded to develop SR 237 EL using lessons

learned from I-680 EL

Opened SR 237 Express Lanes (Phase 1) for tolling

(March 2012)

Initiated environmental clearance process for:

– US 101/SR 85 Express Lanes (Spring 2009)

– SR 237 Express Lanes Phase 2 (Fall 2012)

Implementation Actions

(2008-2013)

4.3.b

Page 66: Agenda - Friday, September 27, 2013vtaorgcontent.s3-us-west-1.amazonaws.com/...packet.pdf · Title VI (codified at 42 U.S.C. §2000d et seq.)was enacted as part of the landmark Civil

7

Award winning SR 237

Express Lanes project

Project cost $11.8 million

FY 2013 gross revenue

$1.05 million

Travel time savings up to

15 minutes

Experience operating

Express Lanes

Where are we now?

4.3.b

Page 67: Agenda - Friday, September 27, 2013vtaorgcontent.s3-us-west-1.amazonaws.com/...packet.pdf · Title VI (codified at 42 U.S.C. §2000d et seq.)was enacted as part of the landmark Civil

8

Increased Traffic Congestion

in the Bay Area

I-280 - US 101 junction in downtown San Jose. (Mercury News)

San Jose area traffic

congestion increased

25% between April 2012

and April 2013.(Source: INRIX National Traffic

Scorecard)

4.3.b

Page 68: Agenda - Friday, September 27, 2013vtaorgcontent.s3-us-west-1.amazonaws.com/...packet.pdf · Title VI (codified at 42 U.S.C. §2000d et seq.)was enacted as part of the landmark Civil

9

Congestion Levels in Silicon Valley

AM Peak Hour PM Peak Hour

Source: Caltrans PeMs

Speed < 35 mph

4.3.b

Page 69: Agenda - Friday, September 27, 2013vtaorgcontent.s3-us-west-1.amazonaws.com/...packet.pdf · Title VI (codified at 42 U.S.C. §2000d et seq.)was enacted as part of the landmark Civil

10

Silicon Valley 2040 Forecasts

Population Jobs Freeway Capacity

Source: VTP 2040

4.3.b

Page 70: Agenda - Friday, September 27, 2013vtaorgcontent.s3-us-west-1.amazonaws.com/...packet.pdf · Title VI (codified at 42 U.S.C. §2000d et seq.)was enacted as part of the landmark Civil

11

Existing Challenges

Highly urbanized

corridor with limited

room to widen.

Increased employment

and population growth

will increase demand.

No dedicated local

funding for highways

similar to dedicated sales

tax for transit.

4.3.b

Page 71: Agenda - Friday, September 27, 2013vtaorgcontent.s3-us-west-1.amazonaws.com/...packet.pdf · Title VI (codified at 42 U.S.C. §2000d et seq.)was enacted as part of the landmark Civil

12

So why Express Lanes?

Essential tool to

manage traffic demand

Provides a reliable

commute option with

travel time reliability

Source of funding for

improvements

including transit

4.3.b

Page 72: Agenda - Friday, September 27, 2013vtaorgcontent.s3-us-west-1.amazonaws.com/...packet.pdf · Title VI (codified at 42 U.S.C. §2000d et seq.)was enacted as part of the landmark Civil

13

A Core Element of Long-Term

Countywide Plan

VTP 2040 identifies EL projects on

all highways in Santa Clara County

Near term:

SR 237, US 101, SR 85

Long term:

I-280, I-880, I-680, SR 87, SR 17

Revenues from Express Lanes to

support transit operations and capital

highway improvements

4.3.b

Page 73: Agenda - Friday, September 27, 2013vtaorgcontent.s3-us-west-1.amazonaws.com/...packet.pdf · Title VI (codified at 42 U.S.C. §2000d et seq.)was enacted as part of the landmark Civil

14

Potential Finance and Delivery

Options

Degree of Private Sector Involvement

Deg

ree o

f P

rivate

Secto

r R

isk

Design-Build

Contracting Out Operations / Maintenance

Design-Build Operate and/or Maintain

Design-Build-Finance-Operate – Availability Payments

Design-Build-Finance-Operate – Shadow Tolling/Fares

Design-Build-Finance-Operate – Real Toll/Fares

Conventional

Model

PPP Models

Alternative

Delivery

Public

Funding

Design-Bid-Build

4.3.b

Page 74: Agenda - Friday, September 27, 2013vtaorgcontent.s3-us-west-1.amazonaws.com/...packet.pdf · Title VI (codified at 42 U.S.C. §2000d et seq.)was enacted as part of the landmark Civil

15

Total SVEL miles - 66

US 101 - 34 miles

SR 85 - 24 miles

SR 237 (Phase 2) - 5 miles

Total Cost - $600 million

US 101 - $415 million

SR 85 - $170 million

SR 237 - $15 million

4.3.b

Page 75: Agenda - Friday, September 27, 2013vtaorgcontent.s3-us-west-1.amazonaws.com/...packet.pdf · Title VI (codified at 42 U.S.C. §2000d et seq.)was enacted as part of the landmark Civil

16

Funding Approach

Two-step funding approach

Step 1: Fund design/development of project

Step 2: Finance construction costs

4.3.b

Page 76: Agenda - Friday, September 27, 2013vtaorgcontent.s3-us-west-1.amazonaws.com/...packet.pdf · Title VI (codified at 42 U.S.C. §2000d et seq.)was enacted as part of the landmark Civil

17

Design/Development Funding

Purpose: Complete design and prepare

investment grade Traffic & Revenue study

needed for financing of construction.

Approach:

1. Program STIP funds to Measure A project

2. Use Measure A funds to advance design/development

VTA Risk Exposure: Potential that construction

does not occur

4.3.b

Page 77: Agenda - Friday, September 27, 2013vtaorgcontent.s3-us-west-1.amazonaws.com/...packet.pdf · Title VI (codified at 42 U.S.C. §2000d et seq.)was enacted as part of the landmark Civil

18

Purpose: Fund remaining design and construction,

capitalized interest, reserves.

Multiple Components

Senior Revenue Bonds – Long-term tax exempt revenue

bonds backed by forecast revenues from express lanes

Subordinated Debt – e.g., Federal TIFIA loan or public

market alternatives

Public Contributions – Federal, state, local grants and/or

loans

Construction Funding

4.3.b

Page 78: Agenda - Friday, September 27, 2013vtaorgcontent.s3-us-west-1.amazonaws.com/...packet.pdf · Title VI (codified at 42 U.S.C. §2000d et seq.)was enacted as part of the landmark Civil

19

Exact composition will depend on several factors:

Construction cost bids (design, technology and

construction environment)

Projected revenues from Traffic & Revenue Study

- Traffic volumes, toll rates, HOV-2+ vs. HOV-3+,

technology/violation levels

Bond market (interest rates, investor appetite)

VTA risk tolerance (debt structure, lower rating, etc.)

Construction Funding (Contd.)

4.3.b

Page 79: Agenda - Friday, September 27, 2013vtaorgcontent.s3-us-west-1.amazonaws.com/...packet.pdf · Title VI (codified at 42 U.S.C. §2000d et seq.)was enacted as part of the landmark Civil

20

Different Funding Approach

Funding approach for Express Lanes differs from VTA’s

traditional approach to financing transit projects

Sales Tax Bonds SVEL Financing

Issuing Entity VTA Special Purpose Vehicle

Security Existing revenues from broad

based sales tax

Projected revenues forecast

for express lanes

Rating AA to AAA ratings BBB category

Debt Structure Level Ascending/growth dependent

Risks Sales tax revenue declineConstruction; forecast

revenues do not materialize

Rate Covenant No Yes

Need for Interim Funding No Yes

Need for Equity/Sub. Debt No Yes

4.3.b

Page 80: Agenda - Friday, September 27, 2013vtaorgcontent.s3-us-west-1.amazonaws.com/...packet.pdf · Title VI (codified at 42 U.S.C. §2000d et seq.)was enacted as part of the landmark Civil

21

Sales Tax Bonds vs. Express Lanes Finance

0

50

100

150

200

250

300

350

2014

2015

2016

2017

2018

2019

2020

2021

2022

2023

2024

2025

2026

2027

2028

2029

2030

2031

2032

2033

2034

2035

2036

Millio

ns

Measure A Debt Service

0

50

100

150

200

250

300

350

2015

2016

2017

2018

2019

2020

2021

2022

2023

2024

2025

2026

2027

2028

2029

2030

2031

2032

2033

2034

2035

2036

2037

2038

2039

2040

2041

2042

2043

2044

Millio

ns

Express Lane Aggregate Debt Service

Projected Express Lane Net Revenue

Santa Clara VTA’s 2000 Measure A Sales Tax Revenue Bond Debt Profile

Projected Silicon Valley Express Lanes Debt Profile

Level debt service & demonstrated revenues

Level debt service over the

life of the bonds

Financing based upon

historical sales tax revenue

Minimum debt service

coverage exceeds 2.0x

Ascending debt service tracks

forecasted growth in revenue

Revenue projection based

upon T&R study forecast, no

track record

Minimum debt service

coverage at 1.5x or lower

While riskier, project financing is a

well accepted funding approach

for Express Lanes

4.3.b

Page 81: Agenda - Friday, September 27, 2013vtaorgcontent.s3-us-west-1.amazonaws.com/...packet.pdf · Title VI (codified at 42 U.S.C. §2000d et seq.)was enacted as part of the landmark Civil

22

Preliminary Financing Analysis

(US 101)

US 101 – HOV 2+ US 101 – HOV3+

Sources

Senior Debt (Toll Revenue Bonds) - CIBS1

$89,000,000

Senior Debt (Toll Revenue Bonds) - CABS2

$82,000,000

TIFIA $155,000,000

Third Party $50,000,000

Funding Gap $81,000,000

Total Sources $457,000,000

Uses

Capital Costs $415,000,000

Capitalized Interest $23,000,000

Debt Service Reserve Fund $17,500,000

Financing Costs and Reserves $1,500,000

Total Uses $457,000,000

Sources

Senior Debt (Toll Revenue Bonds) - CIBS1

$182,000,000

Senior Debt (Toll Revenue Bonds) - CABS2

$182,000,000

TIFIA $136,000,000

Funding Gap $0

Total Sources $500,000,000

Uses

Capital Costs $415,000,000

Capitalized Interest $45,500,000

Debt Service Reserve Fund $36,000,000

Financing Costs and Reserves $3,500,000

Total Uses $500,000,000

1 “CIBS” = Current Interest Bonds2 “CABS” = Capital Appreciation Bonds

Assumes capital costs as of July 2013, T&R projections as of August 2013 for HOV2+ and T&R projections as of March 2012 for HOV3+

4.3.b

Page 82: Agenda - Friday, September 27, 2013vtaorgcontent.s3-us-west-1.amazonaws.com/...packet.pdf · Title VI (codified at 42 U.S.C. §2000d et seq.)was enacted as part of the landmark Civil

23

Preliminary Financing Analysis

(SR 85)

Sources

Senior Debt (Toll Revenue Bonds) - CIBS1

$14,500,000

Senior Debt (Toll Revenue Bonds) - CABS2

$14,500,000

TIFIA $44,000,000

Third Party $50,000,000

Funding Gap $52,000,000

Total Sources $175,000,000

Uses

Capital Costs $170,000,000

Capitalized Interest $2,000,000

Debt Service Reserve Fund $2,800,000

Financing Costs and Reserves $200,000

Total Uses $175,000,000

Sources

Senior Debt (Toll Revenue Bonds) - CIBS1

$39,000,000

Senior Debt (Toll Revenue Bonds) - CABS2

$34,000,000

TIFIA $68,000,000

Third Party $44,000,000

Funding Gap $0

Total Sources $185,000,000

Uses

Capital Costs $170,000,000

Capitalized Interest $7,000,000

Debt Service Reserve Fund $7,500,000

Financing Costs and Reserves $500,000

Total Uses $185,000,000

SR 85 – HOV 2+ SR 85 – HOV3+

1 “CIBS” = Current Interest Bonds2 “CABS” = Capital Appreciation Bonds

Assumes capital costs as of August 2013 and T&R projections as of March 2012

4.3.b

Page 83: Agenda - Friday, September 27, 2013vtaorgcontent.s3-us-west-1.amazonaws.com/...packet.pdf · Title VI (codified at 42 U.S.C. §2000d et seq.)was enacted as part of the landmark Civil

24

Program $12.5 million of 2014 STIP to

Measure A project

Authorize use of $12.5 million Measure A

fund to advance design/development

Authorize $4.5 million from existing Local

Program Reserves to design/development

Proposed Funding Plan for

Design/Development

4.3.b

Page 84: Agenda - Friday, September 27, 2013vtaorgcontent.s3-us-west-1.amazonaws.com/...packet.pdf · Title VI (codified at 42 U.S.C. §2000d et seq.)was enacted as part of the landmark Civil

25

Estimated STIP & Measure A

Allocations

STIP CycleEstimated

Total Available

Amount to

Express Lanes

Development

Year

ProgrammedProject

2014 $19 M $12.5 M 18 / 19 SVSX

2016 $35 M $15 M 20 / 21 SVSX

2018 $40 M $20 M 22 / 23 SVSX

4.3.b

Page 85: Agenda - Friday, September 27, 2013vtaorgcontent.s3-us-west-1.amazonaws.com/...packet.pdf · Title VI (codified at 42 U.S.C. §2000d et seq.)was enacted as part of the landmark Civil

26

Advance Measure A funds and payback

using STIP Maintain control

Minimize external financing

Advance delivery of revenue generation projects

Build express lanes improvements

incrementally

Use design-bid-build project delivery

Proposed Project Delivery

Approach

4.3.b

Page 86: Agenda - Friday, September 27, 2013vtaorgcontent.s3-us-west-1.amazonaws.com/...packet.pdf · Title VI (codified at 42 U.S.C. §2000d et seq.)was enacted as part of the landmark Civil

27

November 2013:

Approve STIP programming for FY 2014

Approve Measure A swap funds for allocation of future STIP

funds to Measure A project

Approve Local Program Reserve fund for Express Lanes Program

Spring 2014: Approve recommended phasing of Express

Lanes segments

What is the timeline?

4.3.b

Page 87: Agenda - Friday, September 27, 2013vtaorgcontent.s3-us-west-1.amazonaws.com/...packet.pdf · Title VI (codified at 42 U.S.C. §2000d et seq.)was enacted as part of the landmark Civil

28

www.siliconvalleyexpresslanes.org

www.vta.org/expresslanes

Thank You!

4.3.b

Page 88: Agenda - Friday, September 27, 2013vtaorgcontent.s3-us-west-1.amazonaws.com/...packet.pdf · Title VI (codified at 42 U.S.C. §2000d et seq.)was enacted as part of the landmark Civil

Date: September 11, 2013

Current Meeting: September 27, 2013

Board Meeting: April 26, 2013

BOARD MEMORANDUM

TO: Santa Clara Valley Transportation Authority

Board of Directors

THROUGH: N/A

FROM: General Counsel Robert R Fabela

SUBJECT: Public Employee Pension Reform Act Update

3331 North First Street ∙ San Jose, CA 95134-1927 ∙ Administration 408.321.5555 ∙ Customer Service 408.321.2300

FOR INFORMATION ONLY

BACKGROUND:

On September 12, 2012, the Governor signed into law the Public Employee Pension Reform Act

(“PEPRA”). Intended to help in the state’s efforts to curb long term pension costs, PEPRA

generally restricts current pension provisions while mandating certain rules for

employee/employer cost sharing.

The law establishes new retirement formulas that cannot be exceeded by a public employer

offering a defined benefit pension plan, setting the maximum benefit allowable for employees

first hired on or after January 1, 2013. PEPRA also sets standards for pension plan contributions

by new employees, and limits the amount that public employers can contribute on behalf of their

new employees.

DISCUSSION:

Although charter cities and counties that do not participate in a retirement system governed by

state statute are exempt from PEPRA’s provisions, special districts and transit agencies like the

VTA are not. Thus, the VTA has been subject to PEPRA since its effective date of January 1,

2013.

The provisions of PEPRA are lengthy and complex. The manner in which the law should be

interpreted has been the subject of much discourse by public agencies and pension professionals.

In addition, the federal Department of Labor has delayed or blocked federal transit grants from

being distributed to transit agencies throughout California (including the VTA), asserting that

PEPRA infringes on transit employees’ collective bargaining rights.

5.1.a

Page 89: Agenda - Friday, September 27, 2013vtaorgcontent.s3-us-west-1.amazonaws.com/...packet.pdf · Title VI (codified at 42 U.S.C. §2000d et seq.)was enacted as part of the landmark Civil

Page 2 of 2

In light of the many questions surrounding PEPRA, the General Counsel and VTA staff will

present a verbal summary of PEPRA, the challenges it presents, and the latest legislative

developments intended to address some of these issues.

Prepared By: Robert Fabela

Memo No. 3809

5.1.a


Recommended