of 18
7/29/2019 AGFS_Part_5
1/18
7/29/2019 AGFS_Part_5
2/18Articial Grass or Sport77
3.13 Pitch Lay-out and Linemarking.Considerable thought needs to go into
likely uture uses o your sporting space,
so that the acility can be designed to
capture the fexibility required.
Activity spaces and their usage can be
radically enhanced at the planning stage.
Think about special events, school use,
cross-eld activities, and associatedaccess, lighting, encing and goal
storage requirements.
It is important to get your dimensions
right. Appropriate eld space,
appropriately sized and sae run-o
zones are mandatory. Think through the
trade-o between multi-lined fexibility
and line clarity, particularly where tennis
is involved because tennis players
need to make repeated, split-second
decisions re: ball location and court
lines.
Lines placed on the eld can be either
cut in (inlaid) or painted on. Inlaid lines
are permanent and thereore signicantly
reduce eld preparation time, but the
use o painted lines or temporary
requirements can also be eective.
Most sportspeople are able to cope
with multi-lined sports halls and sporting
elds, and this process is aided by
sticking to the recommended colour
hierarchy the most requently playedsport should use white lines, the second
most requently played in yellow,
ollowed by blue and red. It is important
to check with the relevant sport peak
body in relation to their requirements.
Top TipTo enhance and saeguard player
ooting ensure that:
- The run-o area should provide
a similar gradient to the playing
area (or the specied distance
rom the eld).
- The pitch or court run-o areas
are suraced with the same type
o carpet as the playing area.
Painted yellow temporary lines
3.14 Practice, Warm-up and Multi-Games AreasMany schools are developing smaller
articial grass activity areas similar
to what exists in some sporting club
acilities. These smaller spaces (500
- 3000m2) can be antastic attributes
where usable activity space is limited,
or where there is a desire to remove
activity rom high-wear areas on the
main sporting eld or court, or as a
replacement o an underutilised existing
activity area.
The School Sports section (1.6.12,
p35) highlights potential considerationsin developing these smaller projects.
Wembley Primary School, Yarraville
7/29/2019 AGFS_Part_5
3/18Articial Grass or Sport 78
The planning and development o a
smaller articial grass activity area should
ollow the same planning process and
set o general considerations outlined inthis guide or large or ull court acilities.
The key broad considerations are:
Assess the likely or potential users
o the space.
Determine the priority order in which
those activities or sports will be
involved. This may help determine
the shape o the required activity
space, and the priority o line
marking and line colour allocation.
Develop a drat management
plan or the space that includes
anticipated use, programs, lines and
ttings required or those programs,
conceptual design/review o
potential site/location, management
options and other operational
considerations (access, security,
access to toilets/changing rooms, etc).
Review the list o likely activities and
determine whether a shock pad is
appropriate. Where the space is
to be used principally or activities
such as soccer, hockey, athletics,
netball, etc (remember that we
are talking about a multi-use area
here, not a specialised sporting
eld), then a shock pad may be
a valuable addition. I the principleactivities are to be tennis, mini tennis
or basketball, then the need or a
higher ball bounce might mitigate
against the nomination o a shock
pad.
Other specic issues or consideration
include:
Site/location choice: (Reer to
Section 3.1).
Basework: (Reer to Section 3.3).
In many school installations the
emphasis may be on maximising thesize o the activity space, possibly at
the expense o constructing a solid,
long-term base. This likely to have
implications or the liespan and
quality o the acility.
Footscray Hockey Centre
Top TipFind the balance between inserting
lines or high-use activities
(including lines that will help
casual users o the space) with
minimising the number/length
o potentially problematic extra
seams being added to the acility.
Large, lightly marked spaces can
provide greater fexibility through
the use o witches hats, cones,
etc.
Multi Use/Cricket Net Space
7/29/2019 AGFS_Part_5
4/18Articial Grass or Sport79
Articial grass selection: (Reer to
Section 3.4). Given the stability o
sand-lled suraces, this type o
articial grass surace is used in
most cases where durability and
long liespan are important.
Line marking: (Reer to Section
3.13).
Fittings and goal storage (Reer to
Section 3.15). Remember that the
fexible use o spaces is enhanced
by having both an open and
unencumbered (ie. removable posts,
nets, coaching aids etc) activity
area, but is urther enhanced by
having good adjacent storage space
or these items.
Recessed goals: These are a good
idea on courts where small sided
soccer is the main activity. They
relate to enced areas where theences themselves incorporate
rebound walls, and there are no
external boundary lines. (Reer to
photograph on page 73).
Rebound walls: These acilities are
a terric asset or individual practice
(in particular or tennis, volleyball,
soccer and hockey goal shooting,
casual games such as handball,
and so on). This is achieved via the
painting o cricket stumps, targets
and tennis nets on the wall (Reer to
photograph Page 74).
Fencing or divider nets: (Reer to
Sections 3.10 and 3.11).
Articial grass protection: Consider
the importance o paved access to
the practice area and the provision
o shoe cleaning equipment
(Sections 3.12, 3.18).
Drainage: (Reer to Section 3.6)
Concrete kerbs: Particularly eective
or hockey hitting practice (Section
3.7)
Floodlights: (Reer to Section 3.9).
Access points: (Reer to Section
3.18).
Signage: particularly i the space
involved is small or enclosed,
consider installing signage that
establishes some basic protocols
or the use o the space. Enhancing
the saety o the users is a key
consideration particularly in conned
spaces.
Top TipRemember that the platorm on
which the articial grass surace/
pad sits is ideally solid/stable
enough to last the lietime o many
surace carpets. Constructed
properly the rst time, it can avoid
repeated expensive base/sub-
grade repairs every time that the
surace system is replaced.
3.15 Goal and Net StorageAt the design stage, thought needs to
be given to the storage o goal posts
and nets. Recessed areas in encing are
oten a satisactory option, particularly in
maintaining sae, clear perimeter run-os
around the eld. In such cases ensure
that the storage bay is level with the
sporting eld, and that the bay is wide
enough or adults to t either side o the
goals being moved. Another satisactory
option is the installation o old-away
goals.
Tennis net storage Koonung Secondary College
7/29/2019 AGFS_Part_5
5/18Articial Grass or Sport 80
Off eld goal storage Kew Hockey Centre
Top Tip
Consider installing a high-tension
wire and netting across the ront
o the goal/tennis net storage area.
This will prevent balls going into
that space and becoming dicult
to retrieve.
3.16 Player and Umpire SheltersPlayer and umpire shelters are invariably
built too small. Remember that there
is generally an overlap where teams
arrive or the ollowing timeslot and need
to store their bags, and equipment,
while the earlier timeslot teams are still
competing. Space thereore needs to
be allowed or our teams to all haveadequate space or their bags and
equiptment, and possibly that o the
umpires as well.
Too oten the shelters cater or the
coach and a ew interchange players (i.e.
those involved on the sideline during a
game) rather than the our ull squads
that need storage beore, during and
ater their game. Nearby taps or water
ountains or players to access are also
key considerations. Shelters Kew Hockey Centre
3.17 Spectator Areas and FurnitureShelters like the one shown above also
provide excellent weather protection
or spectators at events where relatively
small spectator numbers are the norm.
These areas require some provision o
seating, rubbish bins and ideally a water
ountain or two.
3.18 Access Points (including Ambulance Access)Consider what is the largest item that
might need to be moved on or o your
sporting acility (i.e. sets o goals) and
plan your access routes and gate sizes
accordingly. You may need to request
gate-opening sizes (including lintel
heights) dierent to standard provision.
Also think about the size and weight o
maintenance and repair vehicles that will
need access at some stage, including
sizeable trucks and equipment that
are required intermittently or foodlight
maintenance, pitch grooming andrepairs.
It is particularly important that clear
passage is always maintained or
emergency services vehicles such as
ambulances. Access gates Footscray Hockey Centre
7/29/2019 AGFS_Part_5
6/18Articial Grass or Sport81
3.19 TreesWhile trees can provide both a
welcomed screening rom the sun and
the wind, their proximity to constructed
sports acilities can be problematic.
Root invasion underneath articial grass
sporting suraces can lead to surace
cracking and upheaval. Articial grass
sporting areas should ideally be located
one to two times the trees mature heightaway rom strong rooted trees, and in
other cases where trees are adjacent to
the synthetic surace the installation o a
root barrier is strongly recommended.
Overhanging branches can be a source
o contamination with dripping lea sap,
insect secretions and bird droppings, as
well as the dropping o leaves and nuts.
I not quickly removed, these elements
can be crushed or broken down and
will penetrate into the carpet surace
and will potentially contaminate inll or
lead to algal-type growth. Overhangingbranches should be pruned back
regularly.
3.20 Relationship to Changerooms and Car ParkingIssues relevant to this topic are
mentioned in Section 3.1.1 (Site
Selection). A close relationship o the
carpark and changeroom to the playingsurace is preerable, ideally with wide
pathways between all three elements.
Players and spectators need to be kept
on clean hard suraces so as not to
bring contaminants onto the synthetic
grass suraces.
Note the reerence in Section 3.23 to the
importance o using Universal Design
Principles so that people o all abilities
are appropriately provided or.
Top TipIt is important that the clubroom
and surrounding structures are not
located such that they overshadow
the synthetic surace or long
periods which can lead to algae
problems.
3.21 Environmentally Sustainable DesignEconomic, environmental and social
sustainability is now the logicalplanning ramework around which
our communities are designed and
maintained. Reducing negative impacts
on the environment, repairing damage
done, and nding more sustainable
processes or the uture underpin our
communities being prosperous and
liveable in the uture.
The Victorian State Government
Department o Sustainability and
Environment developed a publication,Environmentally Sustainable Design
and Construction
www.resourcesmart.vic.gov.au/documentsto help integrate environmental
sustainability into the planning, design
and construction processes or all new
capital works.
Providing a detailed methodology
to ensure the integration o ESDC
principles, these guidelines will help
achieve the Governments vision o a
uture in which all Victorians are living
sustainably within their natural and built
environments.
3.22 SafetyDuring the design phase there are many
elements to be considered that relate to
the saety o acility users. Saety must
rst be investigated during the Planning
(Drat Management Plan Figure 2,
page 57) phase via the development o
a preliminary Risk Management Plan or
the proposed acility. At this early stage
the document would outline a broad
policy position, and make reerence to
a number o key issues to be explored
during the design phase.
These issues are:
A sae location
Ensure that the chosen location is
sae in terms o visual sight lines.
Players and spectators should be
generally visible to site managers/
supervisors and to passers-by.
Ensure good lighting or the playing
area, but also or access pathways,the car park and change room
areas.
The playing area has some shelter
rom inclement weather (screen
planting, ence screening, etc),
7/29/2019 AGFS_Part_5
7/18Articial Grass or Sport 82
but more so the ancillary acilities
(verandas or weather shelter, etc).
The acility is easily accessible
or ambulances and emergency
vehicles.
A sae pitch or court (reer to the
regular saety check-list noted in
Section 6 - Maintenance)
The initially constructed pitch or
court must meet the specied
perormance criteria mandated by
the sports governing body. These
perormance standards must then
be continued by rigorous application
o ongoing maintenance and
cleaning responsibilities.
The pitch or courts are designed
with the appropriately sized run-
os, with these run-o areas built
with the current contour to match
that o the playing eld. The acility is
checked daily to ensure it is clear o
rubbish and obstructions.
The run-o areas are carpeted with
the same product as was used on
the eld or court proper.
Spread the wear and tear across the
eld, thereby reducing worn areas.
Select appropriate maintenance
equipment, maintain it properlyand only let trained and approved
personnel utilise it.
Check that ttings such as goal
posts and nets are sturdy, well
secured, and appropriately located
(particularly when they are not being
ocially utilised).
Check or and respond to gaps or
bumps in seams (see Section 6).
Check or and respond to algal
growth on the eld or the presence
o debris such as dirt and leaves,
that usually precipitates the
development o algal growth.
Check the age and condition o the
foodlight towers.Check that xtures that need saety
padding have it installed.
With wet elds, occasionally sanitize
the eld (via irrigation and use o
enzyme-based cleansers) to counter
any potential bacterial, microbial
or staph inections that could be
present due to bodily fuids, bird
droppings, etc.
A sae player
In addition to all o the above:
Ensure that rst-aid equipment is
always available (rst aid kit, ice,
stretcher, etc).
Ensure that essential emergency
phone numbers are clearly on
display.
Ensure that a heat policy is known
and observed.
Ensure via your specication that
your contractor produces an
acceptable health and saety plan.
Ensure guidance is provided and
that ootwear and boot cleaning
acilities are being used.
Ensure that litter bins are provided.
All sport and recreation building projects
are to comply with the Disability
Standards or Access to Premises.
Please visit the ollowing website or
copies o the Standards and incorporate
them into your building planning:
www.aph.gov.au
Universal design is a philosophy that
encourages building development
beyond what is required by the DisabilityStandards or Access to Premises. The
intent o universal design is to create
environments to be usable by all people.
To know more about Universal Design,
go to: www.design.ncsu.edu
3.23 Disability Standards for Access to
Premises / Universal Design
Top Tip
Good access is essential or a
variety o people be they the
elderly, people with injuries or
just parents with prams. As a
mandatory part o your planning
and design process ollow the
nominated design principles
reerred to in the access and
inclusion publications available
on Sport and Recreation Victorias
website at: www.sport.vic.gov.au
7/29/2019 AGFS_Part_5
8/18Articial Grass or Sport83
3.24 Designing to Minimise Maintenance
The ollowing text is taken rom the
English Hockey Boards October 2009
paper Pitch Maintenance
(www.englandhockey.co.uk)
Many acets o good maintenance
practice can be incorporated into the
design and construction phase o theproject. Steps can be taken to keep
the pitch and adjacent areas ree o
litter, gravel, grit, mud, dirt, oil, and toxic
materials including:
Landscaping with non-lea-shedding
trees and bushes.
Installation o concrete or asphalt
paths.
Specication o static and rolling
load limits.
Control o access to minimize the
possibility o vehicles entering the
pitch area.
Availability o articial grass practiceor warm-up areas.
Provision o markings and extragoals or cross-pitch practice.
Routing o player trac to minimisetracking o impurities.
Installation o brushes, sluices and
mats or cleaning boots and a
requirement that boots are cleaned
beore entering the pitch area.
Setting up ood and beverageacilities well away rom the pitch.
Strategic placement o rubbish binswith provision or regular emptying.
Erection o prominent signsdesignating required positive actionsand prohibitions or everyone.
Construction must be closely monitoredto ensure that specications are adheredto, that inspection is thorough, and thatany corrections have been satisactorilycompleted.
Caroline Springs College (Springside Campus)
Port Adelaide F.C. Indoor Training Venue
7/29/2019 AGFS_Part_5
9/18Articial Grass or Sport 84
4.1 Project StagesThe key stages in project delivery are
listed below. Many o these elements
have been covered in previous sections:
Project brie development
Business case, preliminary designs
and cost estimates, statutory
planning issues, unding issues,
engagement o project managementsupport, and determination o
procurement route.
Design development
The development o detailed
scheme proposals and supporting
documentation.
Construction procurement
Preparation o contracts, selection
o possible tenderers, putting the
scheme to tender (or single partynegotiations), resolving tender
queries, reporting on tenders
submitted, conrming unding,
letting the main construction
contracts.
Monitoring construction
Monitoring the quality o work
undertaken, contract administration
(including arranging payments,
evaluating variations and extension
o time claims).
Completing the project
Ensure:
That the acility meets specications.
That you have obtained required
certicates and endorsements.
That contracts managing deect
rectications are nalised.
That appropriate maintenance
arrangements are in place.
4.2 Procurement RoutesThere are a range o project procurement
methods. Common models operating in
Australia include:
Design and Documentation, Tender,
Construction (traditional)
Design and Construct (D and C)
Construction Management (CM)
Engineering, Procurement,
Construction Management (EPCM)
Alliancing/Private Public
Partnerships (PPP)
The two most commonly used options
or articial grass sporting installation
projects are:
Design and Documentation
Where a comprehensive
specication is prepared, including
detailed working drawings, a bill o
quantities and supporting contract
conditions. The project is thentendered or construction.
Design and Construct
Where perormance outcomes are
specied (not design details).
The project is then tendered or design
and construction. Ater acceptance o
the successul tender the detailed design
and specication are prepared by the
contractor and subsequently signed o
by the client prior to commencement o
construction.
Top Tip
More detailed inormation on
procurement routes can be
obtained rom the Sport England
document: A Guide To The Design,
Specication and Construction o
Multi-Use Games Areas Including
Multi-Sport Synthetic Tur Pitches
Part 2: General Procurement and
Contracts Guidance, 2004.
Website: www.sportengland.org
Top Tip
You may wish to consider
conducting an Expression o
Interest (EOI) process, sometimes
called a Registration o Interest
process, prior to the design
development/construction
procurement phases. The EOI
seeks preliminary nomination by
interested parties, and enables
the project manager(s) to develop
a shortlist o best qualied
companies which would then be
invited to tender.
7/29/2019 AGFS_Part_5
10/18Articial Grass or Sport85
Choosing the project procurement
method most suitable to your project
requires an assessment o the ollowing
key issues:
Project complexity and cost
Design responsibility
Level o cost certainty required
Risk items (i.e. ground conditions
and how to manage them, the risks
o having to make changes on site)
Saety hazards
Whether sucient inormation
can be supplied to potential
contractors early enough to enable
the contractor to reasonably assess
risks
How much fexibility and nancial
control is required.
4.3 Choosing the Most Suitable ProjectProcurement Method
Top Tip
The bottom line is that a
procurement method needs to
be determined that will deliver
maximum value or money over
the whole lie o the acility.
4.4 Design and Documentation versusDesign and Construct
Design Documentation(Detailed Specication)In relative terms articial grass sporting
acility projects are small, although scale
is relative to the nancial capacity o the
project owner. For local government
authorities, and more so local sporting
clubs or school councils, articial grass
projects are complex and high-cost, and
thereore may warrant comprehensive
specications and detailed drawing
development in order to reduce risk andprovide certainty with respect to quality
and cost.
Documentation will typically include:
Geotechnical investigation report.
Detailed drawings or set out, levels
and all construction elements.
Specication.
Bill o quantities.
Supporting contract.
This degree o project owner research
and preparation is appropriate where
there is a need to resolve complex site
or interace issues.
Design and Construct(Perormance Outcome)The potential strength o the design and
construct project delivery method is that
it allows bidding contractors to think
creatively about options or delivering the
required acility or service without being
locked into just one specic design or
construction resolution.
Although these types o projects are
ultimately about a contractor producinga acility that meets a perormance
specication, the bidding companies
(prior to the tender) should still receive:
Existing Feature Survey.
Comprehensive utility services
survey and associated inormation.
Geotechnical Investigation Report.
Concept and preliminary layout.
The perormance specication
(including quality control and
warranty requirements).
Inormation relating to access to the
site and any specic requirements
needed eg. storage o materials,
tipping o soil, etc.
Supporting contract.
When putting together this inormation
package or the bidding companies,
the project owner, employer or client
should also tightly dene design
and construction standards as well
as provide a clear indication o any
construction arrangement preerences.
Top Tip
The level o specic detail that is
dened prior to this type o project
being tendered leads to one o its
greatest strengths the capacity
or specic line-item bidding over
exact quantities/methods and
thereore allowing an apples with
apples comparison o bids.
7/29/2019 AGFS_Part_5
11/18Articial Grass or Sport 86
Accurate cost estimates are a key
element in making sound decisions
at each stage o the project. In the
case o the design and documentation
procurement method, cost estimates
should be developed at the ollowing
stages:
Concept Development and Project1.
Brieng.
Preliminary Design.2.
Pre-tender Documentation.3.
Cost estimates and project budgets are
typically established early in the projects
lie when there is limited inormation and
detail. I a budget or estimate has to
be set at this stage, it should be done
on the basis o a developed concept
drawing, all available site inormation,
independent industry rates, investigation
and design (civil works and synthetic)
and generous contingencies.
As the level o inormation and detail
increases with progress o the design
process, the cost estimate can be
rened and the contingency amounts
reduced. In the case o a design
and construct contract a similar
process can be adopted, however the
tenderers/bidding companies take onthe responsibility or developing and
costing the detailed design elements.
Cost estimates can be developed
with the assistance o an independent
consultant, i.e. quantity surveyor or
engineer experienced in this work.
4.5 Project Cost Estimation
Top Tip
Obtain independent costing
advice. Be wary o cost estimates
provided by just one individualsuracing contractor (particularly
in the absence o a reasonable
specication).
Articial grass sporting acility
installations generally require two key
areas o work:
The civil engineering and-
construction tasks o clearing andpreparing the sub-grade, the design
and preparation o the base, and
associated works or drainage,
irrigation, encing, etc.
The articial grass installation,-
involving the possible placement o
a shock pad, the laying o articial
grass carpet, the installation o
lines into the carpet, and oten the
application o inll products (such as
sand, rubber granules, etc).
Typically companies which regularly
undertake this type o work are
structured as one o the ollowing:
Civil contractor with suracing
supplier as subcontractor.
Suracing supplier with civil
contractor as subcontractor.
Contractors who have both civil and
suracing expertise in house.
Alternatively some projects have
been delivered with separate
contracts:
Civil contractor or civil works.-
Suracing supplier or suracing-
works.
The trend in recent times is or the workto be lead by the synthetic suracingcompany with a civil contractor assubcontractor. The project owner/theirdelegate can have some infuence here
in terms o speciying expectations andrequirements or contractors/tenderersin terms o:
Expected lead contractor.
Experience with similar hightolerance work.
Subcontractor experience.
Project management capability.
Project resourcing.
Program o works.
Witness and hold points.
Setting expectations and requirementswith respect to the lead contractor willbe based on the level o complexity othe project and the balance o worktypes, i.e. civil works versus syntheticsuracing works.
4.6 Selecting Your Lead Contractor
Top TipRegardless o the lead contractor
arrangement chosen, it is essential
that the project owner retains
a suitably qualied engineer
(expertise across both earth
preparation and articial grass
installation) to supervise all works
and protect the clients interests.
7/29/2019 AGFS_Part_5
12/18Articial Grass or Sport87
Top TipRegardless o the lead contractor
arrangement chosen, it is essential
that the selected company is
able to accept sign-o on both
the design/construction o the
baseworks (whether they did
that work themselves or not) and
the supply and installation o the
surace system. The door cannotbe let open, i base or suracing
issues arise later, to complaints
that the baseworks undertaken
were inadequate.
Top Tip
Many companies are producing
sports surace systems that are
endorsed/licensed by peak bodies
such as FIFA, FIH and ITF. Given
that some companies on-sell
their suracing systems to other
providers or preerred contractors,
it is important or the client to
seek written assurance that the
company actually holding the
licence warrants the work o their
contractor/sub-contractor in ull.
There are a number o simple criteria by
which decisions can be made as to who
goes on your tender shortlist:
The product being promoted by
a particular contractor/supplier
must have perormed satisactorily
in independent laboratory testing
or durability and other required
characteristics (copies o relevant
independent reports should be
requested).
The contractor/supplier should
be able to demonstrate that they
have previously constructed
similar acilities, or have acquired
or has a direct trading relationship
with another company that has
the experience (request that the
contractor provide a list o similar
projects completed not just under
construction).
There is no evidence o the
perormance o the company, or
oered product, being the subject
o any outstanding dispute, or that
they have previous customers that
remain dissatised with the acility
that they have had constructed.
A useul process to help in collating
preliminary inormation rom prospective
contractors is to run an Expression o
Interest process in which the need toattract interested, suitable contractors is
advertised (along with the availability o a
brie specication or project outline), and
rom the response a short-list o best-t
respondents is invited to tender.
As has been said many times in this
guide, through all o these phases it
is highly recommended that your club
or school has independent expert
consulting advice available to assist in
the decision making.
4.7 Selecting a Tender List and Inviting Tenders
Top TipPersonally inspect as many o the
bidding companies previously-
constructed acilities as is
possible, particularly the oldest
o the installations. Question the
owners about the perormance
o the surace, usage levels, the
perormance o the seams, line
creep, wear rates in high-use
areas, maintenance needs and
their opinion o the perormance othe contractor and subcontractors
generally.
4.8 Tender DocumentationDocumentation required with a tender
release is partly dependant on the
procurement route being ollowed (reer
to Sections 4.2, 4.3 and 4.7 o this
guide), but in broad principle tender
documents should make reerence to:
The role and responsibilities o the
client/project owner.
The role and responsibilities o the
client/project owners consultants.
General conditions o contract.
Provide background inormationsuch as surveys, geo-technicaldata, planning permits (including anyconditions applicable), foodlighting
specications, constructiondrawings (i applicable), bill oquantities, etc).
Guarantees/warranties.
Perormance standards andspecications.
7/29/2019 AGFS_Part_5
13/18Articial Grass or Sport 88
O-site and on-site testing
procedures.
Associated works (encing, gates,
etc).
Equipment issues.
Requirement or as built drawings
(post-construction).
Maintenance requirements.
The process/methodology by which
tenders will be assessed.
It is extremely important that the tender
documents also make strong reerence
to:
The need or a quality control
process that denes key stages
(hold points) where inspections
o key phases o work are to be
undertaken and approved.
The provision, with the tender bids,
o data sheets and specications
and actual samples o the materials
that are being oered in the
tender carpet and shock pad,sand and/or rubber granule inll,
glues, and a sample demonstrating
the exact seaming technique to be
used.
Some examples o specications and
bries are noted in Appendix 3.
It is at this stage o the project that
decisions made earlier in the process(i.e. procurement route ull design
and documentation versus design and
construct) can make evaluating tenders
dicult.
While providing opportunities or
alternative ideas and approaches, the
Design and Construct project delivery
method can make it dicult to compare
tender bids ie. apples with apples. Lack
o clarity in this area not only makes the
initial assessment process more dicult,
but can also set up the possibility oadditional changes or variations as the
project proceeds.
With the ull documentation, drawings,
and bill o quantities approach, all o the
bids can be analysed on a detailed line-
by-line basis which gives clear indication
o the true and air cost or the particular
item, and also highlights where a bidding
contractor might not ully understand the
issue or process in question. It should
also help avoid circumstances where
the client or their consultant is unawareo key issues or implications that may
impact on their projects perormance.
These issues can be claried as part o
tender negotiations.
For either procurement method (but
particularly Design and Construct) it
is recommended that you interview
the two or three lowest conorming
tenderers, going through their proposals
in detail. This allows the ull exploration
o the technical aspects o bids, moving
beyond a simple ocus on price. At these
interviews, contractors should be able to
demonstrate:
A detailed knowledge o the scope
o work (Civil and Synthetic).
What the specic materials or
products will be.Precisely how they will be installed.
Critical stages in the process.
Not just how they do things, but
why.
A detailed program o works.
A knowledge o the site and its
ground conditions, existing and
nished levels and services.
A knowledge o who the
subcontractors are and their
experiences.
To complete the tender review, check
each bid or:
Compliance with specications.
The total value o the package.
The companys experience.
The companys reputation.
Visit sites o relevant, nished productsand evaluate them or quality and
perormance. For example, see how the
surace/seams are wearing over time.
4.9 Evaluation of Tenders
Top TipObtain samples o the tendered
suraces. Establish whether the
samples provided exactly match
the written product description/
specication oered, and whether
they are exactly the same as the
product that would be laid. Thesecomparisons (via simple testing)
should be made once the product
arrives on-site or installation.
Testing laboratories are listed in
Appendix 6 o this guide.
7/29/2019 AGFS_Part_5
14/18Articial Grass or Sport89
Prior to conrming acceptance o the
tender rom the preerred contractor,
a meeting should be held involving
all project partners and the preerred
contractor. Matters that should be
discussed and agreed to include:
Costs and provisional sums
Specication and test samples
Contract monitoring procedures
Timescale and critical path analysis
Site working procedure
Subcontractors and supervision
Maintenance schedule
List o equipment
Guarantee/warranty
Specic questions related to
the suracing products, their
manuacture and their installation.
4.10 Agree to Final Details With Preferred Contractor
Top Tip
Prior to signing o on the
acceptance o a tender bid, go
through the guarantee document
in detail with the proposed
contractor. Understand specically
what is being oered, particularly
extended warranty oers as these
oten come with restrictions.
Top TipAppendix 4 is a sample
questionnaire used recently to help
clariy tender submission issues
with a proposed lead contractor.
You may wish to undertake a
similar process or your project.
4.11 Awarding the JobOnce your decision has been made,
send the contractor a letter o intent
and ask or conrmation o their precise
starting date on site. Promptly initiate
the preparation o ormal written
agreements, as ew contractors will
agree to start work on-site beore the
ormal contract has been received.
The Sport England document A
Guide to the Design, Specication
and Construction o Multi-Use Games
Areas (Website: www.sportengland.org)
provides the ollowing advice regarding
projects where it is intended that work
will commence based on a letter o
intent:
I, due to time constraints, a construction
contract is to be let initially on the basis
o a letter o intent- a letter in which
the employer instructs a contractor to
proceed beore contract documents are
executed particular care should be
taken not to issue such a letter without
agreement between the project owner
and contractor o all contractual terms
and conditions. To proceed on anyother basis potentially prejudices the
negotiating strength o the project owner
and can have unexpectedly adverse
consequences or him/her.
Depending on the orm o contract
chosen and its content, bonds may
need to be obtained and nancial audits
undertaken.
4.12 Establishing a Contract
There are generally a range o contractoptions available. For works o this
scale it is usual or work to be tendered
on a xed lump sum basis which can
include provisional sums, amounts and
quantities i some elements o scope
are not able to be qualied adequately.
Other alternatives include a schedule
o rates or construction management
where the client eectively pays or the
contractor on a rates basis or labour and
materials with agreed overheads andprot components. There are a number
o standard orms o contract that can
be used and adopted or the chosen
contract type. For example,Australian
Standards AS 4000 General Conditions
of Contract and AS 4300 GeneralConditions of contract for Design and
Constructare good starting points.
In determining which contract type is
most appropriate to your project, the
ollowing actors should be considered:
Project complexity and cost.
Design responsibility.
Level o cost certainty required.
Risk items such as ground
conditions, and their management.
The impact o weather.
The risk o onsite changes.
Saety hazardsHow much fexibility and nancialcontrol the project owner or clientwants.
7/29/2019 AGFS_Part_5
15/18Articial Grass or Sport 90
Preparedness to deal with late
variations or changes and the
potential impact o same on
proposed completion dates.
The degree to which you want to
leave design and construction risks
with the contractor (could lead to
construction problems and almost
certainly higher tender prices).
Eliminate all the unknowns about
a project prior to the tender and
pricing phase.
Because the nal stages o an articial
grass eld installation (laying the shock
pad and carpet) can be criticallydependant on weather conditions, it is
sensible to plan a projects timelines so
that the construction phase is taking
place during the drier or warmer months
o the year.
An indicative timeline (working back rom
when the eld might become available
or upgrade at the end o a winterplaying season say mid September) or
a ull eld project might be similar to the
ollowing:
Top TipMinimise this transerred risk by providing potential tenderers with sucient
ground investigation inormation.
Top TipFor the scale o works associated with most articial grass projects you would
generally go with a Fixed Lump Sum contract, whether or a ully-documented
or design and construct project.
4.13 Timing and Period of the Contract/Project
1 May Advertise or Expressions o Interest (2 weeks). Finalise thespecication during this period.
15 May Close EOI (3 weeks to review, ollowed by the selective releaseo tender).
8 June Release tender documents (allow 4 weeks).
8 July Close tenders (allow 4 weeks to decide/have approved).
8 August Award contract (lead-in time 5 weeks rom awarding).
15 September Field available, construction commences.
22 December Field completed (14 weeks).
Reer to Section 1.13 o this guide or
inormation on Warranties.
4.14 Terms and Warranties Offered
Reer to Section 1.12 o this guide or
inormation on Licensing.
4.15 Manufacturer/Supplier Licensing
In terms o interpreting product
compliance along certication lines,
Section 1.12 o this guide lists two
reerences:
Product certication: A product
(synthetic tur system) that is
approved by a sports parent body
via early laboratory testing.
Installed eld certication: The
testing and approval o the synthetic
grass eld or court ater it is
installed. For some sports this is
mandatory, and or some others it
is only mandatory i you want to be
able to bid or or host elite events.
In many cases it is best to wait or
several months worth o playing-in
time (i.e. time or sand and rubber
inll to settle) to lapse beore you
conduct the post-installation testing.
Product compliance can also reer to
compliance in terms o perormance and
checking processes during construction.
This important quality check is discussed
in Section 4.17 Monitor and Supervise
Construction and the Contract.
4.16 Product Compliance
7/29/2019 AGFS_Part_5
16/18Articial Grass or Sport91
During the development o the project
specication and contract, there needs
to be appropriate reerence made
to quality systems, particularly the
importance o key hold-points involving
constant checking o workmanship and
materials. The SAPCA Code o Practice
or the Construction and Maintenance o
Synthetic Tur Sports Pitches 20 suggeststhe ollowing test items and timetable:
4.17.1 WorkmanshipThe quality o the workmanship should
be checked at various key stages during
the construction process (against the
specication or the works). These
stages may include:
At completion o the sub-grade,
to check size, levels, gradients
and strength - to compare to the
geotechnical report, which willvalidate the design o the sub-base
(thickness, etc).
At completion o the construction o
the drainage system, to ensure that
all connections have been made
and that the correct alls have been
made in pipe work (and that they
are clean many have been used
as rubbish pits or have had waste
concrete dumped in them!).
At completion o the base to
check that level and thicknessrequirements have been met and
that the materials supplied are
as per tender, eg. crushed rock,
concrete, etc.
At completion o the shock pad to-
check thickness.
At completion o the carpet surace-
to ensure consistency o inll depth
across the pitch. Also to ratiy lines,
dimensions, and so on.
4.17.2 MaterialsShock pad and carpet materials
delivered to site should be checked
(samples sent or analysis) against the
reerence sample or:
Shock pad:
Tensile strength.
Density.
Thickness.
Weight per unit area.
Carpet:
Fibre type and dtex.
Pile length. This should match the
nominal value to 1mm when tested
using the appropriate method.
Pile density in terms o tuts per
square cm.
Face pile weight per unit area.
Total weight per unit area.
Tut withdrawal orce.
Quality o backing materials.Pile lling materials (size, shape,
grading).
4.17 Monitor and Supervise Construction & Contract
Reer to Section 1.13 or extensive
coverage o quality control issues.
4.18 Quality Control
Beore the acility is classied
as Practically Complete, it is
recommended that the client or theirconsultant project manager undertake
or commission all necessary tests to
ensure the compliance o the acility with
your specication/standards. This step
is normally linked to the retention o a
certain percentage o the contract price.
Checks may include:
The colour o the pile
The pile length
The inll spread rate
Any deviations in levels (beneath a 3
metre straight edge and accordingto standard deviation nominated by
sports code tolerances)
Uniormity and acceptability o
seams and joins
A thorough visual examination
and preparation o a photographic
record o any distinctive eaturesThe ormal tests, such as:
Ball rebound resilience-
Ball rolling resistance and-
deviation
Berlin athlete impact response-
(deormation)
Peak acceleration (g) rom 1.0m-
Limoux surace riction-
Porosity.-
This would also be the time at which
the materials (carpet, shock pad,
sand, rubber granules, adhesives, etc)are checked to see that they match
those rst proered at the time when
companies were making their
tender bids.
4.19 Check Final Completion with Consultantsand the Contractor
20The Code o Practice or the Construction and Maintenance o Synthetic Tur Sports Pitches
The Sports and Play Construction Association (2009)
7/29/2019 AGFS_Part_5
17/18Articial Grass or Sport 92
Hopeully the monitoring and inspection
process during construction has been
suciently eective, and the nal check
and testing has revealed no problems. In
this case the ormal handover (the trigger
or the nal payments, less retention
monies to be retained) can occur.
Should any deects be revealed,
establish a rectication program and
timetable with the contractor, and
do not accept project handover until
satised with the resolution. Depending
on the extent o the remedial works
required, it is possible that urther survey
and testing work might be necessary.
This is where a site supervisor and
clients advisor are vital, with a very clear
orm o contract spelling out the Quality
Assurance, Quality Control and payment
procedures, and the procedure or
deects rectication and payment.
Top TipWhile unlled articial grass carpets can be tested immediately at the completion o
works, with lled/dressed carpets this is oten best done a month or two later ater
the inll materials have settled properly into the carpet, and the redistribution o inll
has been completed. With projects calling or lled/dressed carpets, you should
consider advising bidding suppliers (in the tender specication) that nal payment
will be held until the delayed testing is completed.
4.20 Remedial Works and Re-Inspection
I there were no deects identied
ollowing practical completion (and the
carrying-out o appropriate tests at that
stage), then by now the acility will be
ully operational. I remedial works were
identied though, it may be necessary to
re-test the surace.
The appropriate testing issues and
protocols are listed in Section 4.19 othis guide (Check Final Completion with
Consultants and the Contractor).
The stages at which eld compliance
testing can or should occur are:
When the carpet arrives on site.
Send several samples (min. size
350mm X 350mm) or analysis and
comparison with the samples and
specications provided originally
with the tenderers bid and product
specication.
Check the thickness and
composition o all layers in the base.
Test the composition and depth o
the shock pad beore the shock pad
laying phase is completed.
Check the perormance to
standards or seam strength.
Check the inll spread rate.
Perormance testing on site
immediately or soon ater practical
completion.
Perormance testing prior to the end
o the deects liability period (usually
12 months). Note: This may only be
appropriate or high-end acilities,
not community level.
Perormance testing prior to the end
o the warranty period - ve to seven
years (also probably only relevant to
high-end acilities. Adds cost to the
project, but more importantly will
place a stronger spotlight on usage
levels, maintenance regimes, etc.
Annual or biannual certication
where required by the sports parent
body. I so required, this needs to
be made absolutely clear in the brieand contract details.
At any time i you think that your
surace is ailing to meet required
playability and perormance.
4.21 Field Testing
Top Tip
The ormal testing o an articial
grass surace can be an expensive
process, but the cost is minor
compared with the overall
investment in the project.
Brisbane Hockey Centre
7/29/2019 AGFS_Part_5
18/18
Guarantees on articial grass pitches
are oten advertised as being or ve to
seven years, but what do they actually
cover? What acility users and nanciers
need is a guarantee that the playing
perormance o their pitch (to standards
generally set by their sports parent
body) is guaranteed or a set period
o time. In many cases, the warranty
provided may just relate to issues such
as ultra-violet degradation or generalwear.
Follow the trail back and you will oten
nd that the warranties oered by
suppliers or installers are likely to be
underpinned by warranties provided
by the yarn extruders. Note that these
warranties are oten linked to things
such as:
hours o play (the general ceiling is
1,500-1,600 hours per annum)
number and age (size) o
participants.
Check Section 1.13 o this guideor important inormation related
to establishing, understanding and
implementing warranties.
When the client or their representative
consultants is satised that the acility
is satisactorily nished (practical
completion), the ormal handover can
occur.
At this point the contractor is entitled to
receive the balance o their payment,
less the usual retention amount that is
held until the end o the deects liability
period usually 12 months rom the
date o the handover. Some owners may
wish to again ormally test the acility
prior to the end o the deects liability
period.
4.22 Handover and Defects Liability Period
4.23 The Warranty or Guarantee Period
Top TipMake sure that you are clear on the specics o the warranty. Does it cover
minimum playability throughout the warranty period? I so, how is that
measured? How does the warranty relate to the yarn, the carpet, the seams?
Who is issuing the warranty?
Top TipMost warranties will be linked to maintenance, both specialised and in-house,
particularly any perormance warranty.
Top Tip
Warranties are generally paid on a pro-rata basis, not ull replacement. Forexample, i your carpet ails, the compensation ormula might revolve around
the percentage o the warranty period that has elapsed and what percentage o
the cost o the installation relates to the carpet.
Top TipBeore the warranty period elapses, consider another batch o ormal testing i
you think that your acility is ailing to meet the minimum playability standards
specied.