+ All Categories
Home > Documents > AGFS_Part_5

AGFS_Part_5

Date post: 03-Apr-2018
Category:
Upload: ifyjoslyn
View: 214 times
Download: 0 times
Share this document with a friend

of 18

Transcript
  • 7/29/2019 AGFS_Part_5

    1/18

  • 7/29/2019 AGFS_Part_5

    2/18Articial Grass or Sport77

    3.13 Pitch Lay-out and Linemarking.Considerable thought needs to go into

    likely uture uses o your sporting space,

    so that the acility can be designed to

    capture the fexibility required.

    Activity spaces and their usage can be

    radically enhanced at the planning stage.

    Think about special events, school use,

    cross-eld activities, and associatedaccess, lighting, encing and goal

    storage requirements.

    It is important to get your dimensions

    right. Appropriate eld space,

    appropriately sized and sae run-o

    zones are mandatory. Think through the

    trade-o between multi-lined fexibility

    and line clarity, particularly where tennis

    is involved because tennis players

    need to make repeated, split-second

    decisions re: ball location and court

    lines.

    Lines placed on the eld can be either

    cut in (inlaid) or painted on. Inlaid lines

    are permanent and thereore signicantly

    reduce eld preparation time, but the

    use o painted lines or temporary

    requirements can also be eective.

    Most sportspeople are able to cope

    with multi-lined sports halls and sporting

    elds, and this process is aided by

    sticking to the recommended colour

    hierarchy the most requently playedsport should use white lines, the second

    most requently played in yellow,

    ollowed by blue and red. It is important

    to check with the relevant sport peak

    body in relation to their requirements.

    Top TipTo enhance and saeguard player

    ooting ensure that:

    - The run-o area should provide

    a similar gradient to the playing

    area (or the specied distance

    rom the eld).

    - The pitch or court run-o areas

    are suraced with the same type

    o carpet as the playing area.

    Painted yellow temporary lines

    3.14 Practice, Warm-up and Multi-Games AreasMany schools are developing smaller

    articial grass activity areas similar

    to what exists in some sporting club

    acilities. These smaller spaces (500

    - 3000m2) can be antastic attributes

    where usable activity space is limited,

    or where there is a desire to remove

    activity rom high-wear areas on the

    main sporting eld or court, or as a

    replacement o an underutilised existing

    activity area.

    The School Sports section (1.6.12,

    p35) highlights potential considerationsin developing these smaller projects.

    Wembley Primary School, Yarraville

  • 7/29/2019 AGFS_Part_5

    3/18Articial Grass or Sport 78

    The planning and development o a

    smaller articial grass activity area should

    ollow the same planning process and

    set o general considerations outlined inthis guide or large or ull court acilities.

    The key broad considerations are:

    Assess the likely or potential users

    o the space.

    Determine the priority order in which

    those activities or sports will be

    involved. This may help determine

    the shape o the required activity

    space, and the priority o line

    marking and line colour allocation.

    Develop a drat management

    plan or the space that includes

    anticipated use, programs, lines and

    ttings required or those programs,

    conceptual design/review o

    potential site/location, management

    options and other operational

    considerations (access, security,

    access to toilets/changing rooms, etc).

    Review the list o likely activities and

    determine whether a shock pad is

    appropriate. Where the space is

    to be used principally or activities

    such as soccer, hockey, athletics,

    netball, etc (remember that we

    are talking about a multi-use area

    here, not a specialised sporting

    eld), then a shock pad may be

    a valuable addition. I the principleactivities are to be tennis, mini tennis

    or basketball, then the need or a

    higher ball bounce might mitigate

    against the nomination o a shock

    pad.

    Other specic issues or consideration

    include:

    Site/location choice: (Reer to

    Section 3.1).

    Basework: (Reer to Section 3.3).

    In many school installations the

    emphasis may be on maximising thesize o the activity space, possibly at

    the expense o constructing a solid,

    long-term base. This likely to have

    implications or the liespan and

    quality o the acility.

    Footscray Hockey Centre

    Top TipFind the balance between inserting

    lines or high-use activities

    (including lines that will help

    casual users o the space) with

    minimising the number/length

    o potentially problematic extra

    seams being added to the acility.

    Large, lightly marked spaces can

    provide greater fexibility through

    the use o witches hats, cones,

    etc.

    Multi Use/Cricket Net Space

  • 7/29/2019 AGFS_Part_5

    4/18Articial Grass or Sport79

    Articial grass selection: (Reer to

    Section 3.4). Given the stability o

    sand-lled suraces, this type o

    articial grass surace is used in

    most cases where durability and

    long liespan are important.

    Line marking: (Reer to Section

    3.13).

    Fittings and goal storage (Reer to

    Section 3.15). Remember that the

    fexible use o spaces is enhanced

    by having both an open and

    unencumbered (ie. removable posts,

    nets, coaching aids etc) activity

    area, but is urther enhanced by

    having good adjacent storage space

    or these items.

    Recessed goals: These are a good

    idea on courts where small sided

    soccer is the main activity. They

    relate to enced areas where theences themselves incorporate

    rebound walls, and there are no

    external boundary lines. (Reer to

    photograph on page 73).

    Rebound walls: These acilities are

    a terric asset or individual practice

    (in particular or tennis, volleyball,

    soccer and hockey goal shooting,

    casual games such as handball,

    and so on). This is achieved via the

    painting o cricket stumps, targets

    and tennis nets on the wall (Reer to

    photograph Page 74).

    Fencing or divider nets: (Reer to

    Sections 3.10 and 3.11).

    Articial grass protection: Consider

    the importance o paved access to

    the practice area and the provision

    o shoe cleaning equipment

    (Sections 3.12, 3.18).

    Drainage: (Reer to Section 3.6)

    Concrete kerbs: Particularly eective

    or hockey hitting practice (Section

    3.7)

    Floodlights: (Reer to Section 3.9).

    Access points: (Reer to Section

    3.18).

    Signage: particularly i the space

    involved is small or enclosed,

    consider installing signage that

    establishes some basic protocols

    or the use o the space. Enhancing

    the saety o the users is a key

    consideration particularly in conned

    spaces.

    Top TipRemember that the platorm on

    which the articial grass surace/

    pad sits is ideally solid/stable

    enough to last the lietime o many

    surace carpets. Constructed

    properly the rst time, it can avoid

    repeated expensive base/sub-

    grade repairs every time that the

    surace system is replaced.

    3.15 Goal and Net StorageAt the design stage, thought needs to

    be given to the storage o goal posts

    and nets. Recessed areas in encing are

    oten a satisactory option, particularly in

    maintaining sae, clear perimeter run-os

    around the eld. In such cases ensure

    that the storage bay is level with the

    sporting eld, and that the bay is wide

    enough or adults to t either side o the

    goals being moved. Another satisactory

    option is the installation o old-away

    goals.

    Tennis net storage Koonung Secondary College

  • 7/29/2019 AGFS_Part_5

    5/18Articial Grass or Sport 80

    Off eld goal storage Kew Hockey Centre

    Top Tip

    Consider installing a high-tension

    wire and netting across the ront

    o the goal/tennis net storage area.

    This will prevent balls going into

    that space and becoming dicult

    to retrieve.

    3.16 Player and Umpire SheltersPlayer and umpire shelters are invariably

    built too small. Remember that there

    is generally an overlap where teams

    arrive or the ollowing timeslot and need

    to store their bags, and equipment,

    while the earlier timeslot teams are still

    competing. Space thereore needs to

    be allowed or our teams to all haveadequate space or their bags and

    equiptment, and possibly that o the

    umpires as well.

    Too oten the shelters cater or the

    coach and a ew interchange players (i.e.

    those involved on the sideline during a

    game) rather than the our ull squads

    that need storage beore, during and

    ater their game. Nearby taps or water

    ountains or players to access are also

    key considerations. Shelters Kew Hockey Centre

    3.17 Spectator Areas and FurnitureShelters like the one shown above also

    provide excellent weather protection

    or spectators at events where relatively

    small spectator numbers are the norm.

    These areas require some provision o

    seating, rubbish bins and ideally a water

    ountain or two.

    3.18 Access Points (including Ambulance Access)Consider what is the largest item that

    might need to be moved on or o your

    sporting acility (i.e. sets o goals) and

    plan your access routes and gate sizes

    accordingly. You may need to request

    gate-opening sizes (including lintel

    heights) dierent to standard provision.

    Also think about the size and weight o

    maintenance and repair vehicles that will

    need access at some stage, including

    sizeable trucks and equipment that

    are required intermittently or foodlight

    maintenance, pitch grooming andrepairs.

    It is particularly important that clear

    passage is always maintained or

    emergency services vehicles such as

    ambulances. Access gates Footscray Hockey Centre

  • 7/29/2019 AGFS_Part_5

    6/18Articial Grass or Sport81

    3.19 TreesWhile trees can provide both a

    welcomed screening rom the sun and

    the wind, their proximity to constructed

    sports acilities can be problematic.

    Root invasion underneath articial grass

    sporting suraces can lead to surace

    cracking and upheaval. Articial grass

    sporting areas should ideally be located

    one to two times the trees mature heightaway rom strong rooted trees, and in

    other cases where trees are adjacent to

    the synthetic surace the installation o a

    root barrier is strongly recommended.

    Overhanging branches can be a source

    o contamination with dripping lea sap,

    insect secretions and bird droppings, as

    well as the dropping o leaves and nuts.

    I not quickly removed, these elements

    can be crushed or broken down and

    will penetrate into the carpet surace

    and will potentially contaminate inll or

    lead to algal-type growth. Overhangingbranches should be pruned back

    regularly.

    3.20 Relationship to Changerooms and Car ParkingIssues relevant to this topic are

    mentioned in Section 3.1.1 (Site

    Selection). A close relationship o the

    carpark and changeroom to the playingsurace is preerable, ideally with wide

    pathways between all three elements.

    Players and spectators need to be kept

    on clean hard suraces so as not to

    bring contaminants onto the synthetic

    grass suraces.

    Note the reerence in Section 3.23 to the

    importance o using Universal Design

    Principles so that people o all abilities

    are appropriately provided or.

    Top TipIt is important that the clubroom

    and surrounding structures are not

    located such that they overshadow

    the synthetic surace or long

    periods which can lead to algae

    problems.

    3.21 Environmentally Sustainable DesignEconomic, environmental and social

    sustainability is now the logicalplanning ramework around which

    our communities are designed and

    maintained. Reducing negative impacts

    on the environment, repairing damage

    done, and nding more sustainable

    processes or the uture underpin our

    communities being prosperous and

    liveable in the uture.

    The Victorian State Government

    Department o Sustainability and

    Environment developed a publication,Environmentally Sustainable Design

    and Construction

    www.resourcesmart.vic.gov.au/documentsto help integrate environmental

    sustainability into the planning, design

    and construction processes or all new

    capital works.

    Providing a detailed methodology

    to ensure the integration o ESDC

    principles, these guidelines will help

    achieve the Governments vision o a

    uture in which all Victorians are living

    sustainably within their natural and built

    environments.

    3.22 SafetyDuring the design phase there are many

    elements to be considered that relate to

    the saety o acility users. Saety must

    rst be investigated during the Planning

    (Drat Management Plan Figure 2,

    page 57) phase via the development o

    a preliminary Risk Management Plan or

    the proposed acility. At this early stage

    the document would outline a broad

    policy position, and make reerence to

    a number o key issues to be explored

    during the design phase.

    These issues are:

    A sae location

    Ensure that the chosen location is

    sae in terms o visual sight lines.

    Players and spectators should be

    generally visible to site managers/

    supervisors and to passers-by.

    Ensure good lighting or the playing

    area, but also or access pathways,the car park and change room

    areas.

    The playing area has some shelter

    rom inclement weather (screen

    planting, ence screening, etc),

  • 7/29/2019 AGFS_Part_5

    7/18Articial Grass or Sport 82

    but more so the ancillary acilities

    (verandas or weather shelter, etc).

    The acility is easily accessible

    or ambulances and emergency

    vehicles.

    A sae pitch or court (reer to the

    regular saety check-list noted in

    Section 6 - Maintenance)

    The initially constructed pitch or

    court must meet the specied

    perormance criteria mandated by

    the sports governing body. These

    perormance standards must then

    be continued by rigorous application

    o ongoing maintenance and

    cleaning responsibilities.

    The pitch or courts are designed

    with the appropriately sized run-

    os, with these run-o areas built

    with the current contour to match

    that o the playing eld. The acility is

    checked daily to ensure it is clear o

    rubbish and obstructions.

    The run-o areas are carpeted with

    the same product as was used on

    the eld or court proper.

    Spread the wear and tear across the

    eld, thereby reducing worn areas.

    Select appropriate maintenance

    equipment, maintain it properlyand only let trained and approved

    personnel utilise it.

    Check that ttings such as goal

    posts and nets are sturdy, well

    secured, and appropriately located

    (particularly when they are not being

    ocially utilised).

    Check or and respond to gaps or

    bumps in seams (see Section 6).

    Check or and respond to algal

    growth on the eld or the presence

    o debris such as dirt and leaves,

    that usually precipitates the

    development o algal growth.

    Check the age and condition o the

    foodlight towers.Check that xtures that need saety

    padding have it installed.

    With wet elds, occasionally sanitize

    the eld (via irrigation and use o

    enzyme-based cleansers) to counter

    any potential bacterial, microbial

    or staph inections that could be

    present due to bodily fuids, bird

    droppings, etc.

    A sae player

    In addition to all o the above:

    Ensure that rst-aid equipment is

    always available (rst aid kit, ice,

    stretcher, etc).

    Ensure that essential emergency

    phone numbers are clearly on

    display.

    Ensure that a heat policy is known

    and observed.

    Ensure via your specication that

    your contractor produces an

    acceptable health and saety plan.

    Ensure guidance is provided and

    that ootwear and boot cleaning

    acilities are being used.

    Ensure that litter bins are provided.

    All sport and recreation building projects

    are to comply with the Disability

    Standards or Access to Premises.

    Please visit the ollowing website or

    copies o the Standards and incorporate

    them into your building planning:

    www.aph.gov.au

    Universal design is a philosophy that

    encourages building development

    beyond what is required by the DisabilityStandards or Access to Premises. The

    intent o universal design is to create

    environments to be usable by all people.

    To know more about Universal Design,

    go to: www.design.ncsu.edu

    3.23 Disability Standards for Access to

    Premises / Universal Design

    Top Tip

    Good access is essential or a

    variety o people be they the

    elderly, people with injuries or

    just parents with prams. As a

    mandatory part o your planning

    and design process ollow the

    nominated design principles

    reerred to in the access and

    inclusion publications available

    on Sport and Recreation Victorias

    website at: www.sport.vic.gov.au

  • 7/29/2019 AGFS_Part_5

    8/18Articial Grass or Sport83

    3.24 Designing to Minimise Maintenance

    The ollowing text is taken rom the

    English Hockey Boards October 2009

    paper Pitch Maintenance

    (www.englandhockey.co.uk)

    Many acets o good maintenance

    practice can be incorporated into the

    design and construction phase o theproject. Steps can be taken to keep

    the pitch and adjacent areas ree o

    litter, gravel, grit, mud, dirt, oil, and toxic

    materials including:

    Landscaping with non-lea-shedding

    trees and bushes.

    Installation o concrete or asphalt

    paths.

    Specication o static and rolling

    load limits.

    Control o access to minimize the

    possibility o vehicles entering the

    pitch area.

    Availability o articial grass practiceor warm-up areas.

    Provision o markings and extragoals or cross-pitch practice.

    Routing o player trac to minimisetracking o impurities.

    Installation o brushes, sluices and

    mats or cleaning boots and a

    requirement that boots are cleaned

    beore entering the pitch area.

    Setting up ood and beverageacilities well away rom the pitch.

    Strategic placement o rubbish binswith provision or regular emptying.

    Erection o prominent signsdesignating required positive actionsand prohibitions or everyone.

    Construction must be closely monitoredto ensure that specications are adheredto, that inspection is thorough, and thatany corrections have been satisactorilycompleted.

    Caroline Springs College (Springside Campus)

    Port Adelaide F.C. Indoor Training Venue

  • 7/29/2019 AGFS_Part_5

    9/18Articial Grass or Sport 84

    4.1 Project StagesThe key stages in project delivery are

    listed below. Many o these elements

    have been covered in previous sections:

    Project brie development

    Business case, preliminary designs

    and cost estimates, statutory

    planning issues, unding issues,

    engagement o project managementsupport, and determination o

    procurement route.

    Design development

    The development o detailed

    scheme proposals and supporting

    documentation.

    Construction procurement

    Preparation o contracts, selection

    o possible tenderers, putting the

    scheme to tender (or single partynegotiations), resolving tender

    queries, reporting on tenders

    submitted, conrming unding,

    letting the main construction

    contracts.

    Monitoring construction

    Monitoring the quality o work

    undertaken, contract administration

    (including arranging payments,

    evaluating variations and extension

    o time claims).

    Completing the project

    Ensure:

    That the acility meets specications.

    That you have obtained required

    certicates and endorsements.

    That contracts managing deect

    rectications are nalised.

    That appropriate maintenance

    arrangements are in place.

    4.2 Procurement RoutesThere are a range o project procurement

    methods. Common models operating in

    Australia include:

    Design and Documentation, Tender,

    Construction (traditional)

    Design and Construct (D and C)

    Construction Management (CM)

    Engineering, Procurement,

    Construction Management (EPCM)

    Alliancing/Private Public

    Partnerships (PPP)

    The two most commonly used options

    or articial grass sporting installation

    projects are:

    Design and Documentation

    Where a comprehensive

    specication is prepared, including

    detailed working drawings, a bill o

    quantities and supporting contract

    conditions. The project is thentendered or construction.

    Design and Construct

    Where perormance outcomes are

    specied (not design details).

    The project is then tendered or design

    and construction. Ater acceptance o

    the successul tender the detailed design

    and specication are prepared by the

    contractor and subsequently signed o

    by the client prior to commencement o

    construction.

    Top Tip

    More detailed inormation on

    procurement routes can be

    obtained rom the Sport England

    document: A Guide To The Design,

    Specication and Construction o

    Multi-Use Games Areas Including

    Multi-Sport Synthetic Tur Pitches

    Part 2: General Procurement and

    Contracts Guidance, 2004.

    Website: www.sportengland.org

    Top Tip

    You may wish to consider

    conducting an Expression o

    Interest (EOI) process, sometimes

    called a Registration o Interest

    process, prior to the design

    development/construction

    procurement phases. The EOI

    seeks preliminary nomination by

    interested parties, and enables

    the project manager(s) to develop

    a shortlist o best qualied

    companies which would then be

    invited to tender.

  • 7/29/2019 AGFS_Part_5

    10/18Articial Grass or Sport85

    Choosing the project procurement

    method most suitable to your project

    requires an assessment o the ollowing

    key issues:

    Project complexity and cost

    Design responsibility

    Level o cost certainty required

    Risk items (i.e. ground conditions

    and how to manage them, the risks

    o having to make changes on site)

    Saety hazards

    Whether sucient inormation

    can be supplied to potential

    contractors early enough to enable

    the contractor to reasonably assess

    risks

    How much fexibility and nancial

    control is required.

    4.3 Choosing the Most Suitable ProjectProcurement Method

    Top Tip

    The bottom line is that a

    procurement method needs to

    be determined that will deliver

    maximum value or money over

    the whole lie o the acility.

    4.4 Design and Documentation versusDesign and Construct

    Design Documentation(Detailed Specication)In relative terms articial grass sporting

    acility projects are small, although scale

    is relative to the nancial capacity o the

    project owner. For local government

    authorities, and more so local sporting

    clubs or school councils, articial grass

    projects are complex and high-cost, and

    thereore may warrant comprehensive

    specications and detailed drawing

    development in order to reduce risk andprovide certainty with respect to quality

    and cost.

    Documentation will typically include:

    Geotechnical investigation report.

    Detailed drawings or set out, levels

    and all construction elements.

    Specication.

    Bill o quantities.

    Supporting contract.

    This degree o project owner research

    and preparation is appropriate where

    there is a need to resolve complex site

    or interace issues.

    Design and Construct(Perormance Outcome)The potential strength o the design and

    construct project delivery method is that

    it allows bidding contractors to think

    creatively about options or delivering the

    required acility or service without being

    locked into just one specic design or

    construction resolution.

    Although these types o projects are

    ultimately about a contractor producinga acility that meets a perormance

    specication, the bidding companies

    (prior to the tender) should still receive:

    Existing Feature Survey.

    Comprehensive utility services

    survey and associated inormation.

    Geotechnical Investigation Report.

    Concept and preliminary layout.

    The perormance specication

    (including quality control and

    warranty requirements).

    Inormation relating to access to the

    site and any specic requirements

    needed eg. storage o materials,

    tipping o soil, etc.

    Supporting contract.

    When putting together this inormation

    package or the bidding companies,

    the project owner, employer or client

    should also tightly dene design

    and construction standards as well

    as provide a clear indication o any

    construction arrangement preerences.

    Top Tip

    The level o specic detail that is

    dened prior to this type o project

    being tendered leads to one o its

    greatest strengths the capacity

    or specic line-item bidding over

    exact quantities/methods and

    thereore allowing an apples with

    apples comparison o bids.

  • 7/29/2019 AGFS_Part_5

    11/18Articial Grass or Sport 86

    Accurate cost estimates are a key

    element in making sound decisions

    at each stage o the project. In the

    case o the design and documentation

    procurement method, cost estimates

    should be developed at the ollowing

    stages:

    Concept Development and Project1.

    Brieng.

    Preliminary Design.2.

    Pre-tender Documentation.3.

    Cost estimates and project budgets are

    typically established early in the projects

    lie when there is limited inormation and

    detail. I a budget or estimate has to

    be set at this stage, it should be done

    on the basis o a developed concept

    drawing, all available site inormation,

    independent industry rates, investigation

    and design (civil works and synthetic)

    and generous contingencies.

    As the level o inormation and detail

    increases with progress o the design

    process, the cost estimate can be

    rened and the contingency amounts

    reduced. In the case o a design

    and construct contract a similar

    process can be adopted, however the

    tenderers/bidding companies take onthe responsibility or developing and

    costing the detailed design elements.

    Cost estimates can be developed

    with the assistance o an independent

    consultant, i.e. quantity surveyor or

    engineer experienced in this work.

    4.5 Project Cost Estimation

    Top Tip

    Obtain independent costing

    advice. Be wary o cost estimates

    provided by just one individualsuracing contractor (particularly

    in the absence o a reasonable

    specication).

    Articial grass sporting acility

    installations generally require two key

    areas o work:

    The civil engineering and-

    construction tasks o clearing andpreparing the sub-grade, the design

    and preparation o the base, and

    associated works or drainage,

    irrigation, encing, etc.

    The articial grass installation,-

    involving the possible placement o

    a shock pad, the laying o articial

    grass carpet, the installation o

    lines into the carpet, and oten the

    application o inll products (such as

    sand, rubber granules, etc).

    Typically companies which regularly

    undertake this type o work are

    structured as one o the ollowing:

    Civil contractor with suracing

    supplier as subcontractor.

    Suracing supplier with civil

    contractor as subcontractor.

    Contractors who have both civil and

    suracing expertise in house.

    Alternatively some projects have

    been delivered with separate

    contracts:

    Civil contractor or civil works.-

    Suracing supplier or suracing-

    works.

    The trend in recent times is or the workto be lead by the synthetic suracingcompany with a civil contractor assubcontractor. The project owner/theirdelegate can have some infuence here

    in terms o speciying expectations andrequirements or contractors/tenderersin terms o:

    Expected lead contractor.

    Experience with similar hightolerance work.

    Subcontractor experience.

    Project management capability.

    Project resourcing.

    Program o works.

    Witness and hold points.

    Setting expectations and requirementswith respect to the lead contractor willbe based on the level o complexity othe project and the balance o worktypes, i.e. civil works versus syntheticsuracing works.

    4.6 Selecting Your Lead Contractor

    Top TipRegardless o the lead contractor

    arrangement chosen, it is essential

    that the project owner retains

    a suitably qualied engineer

    (expertise across both earth

    preparation and articial grass

    installation) to supervise all works

    and protect the clients interests.

  • 7/29/2019 AGFS_Part_5

    12/18Articial Grass or Sport87

    Top TipRegardless o the lead contractor

    arrangement chosen, it is essential

    that the selected company is

    able to accept sign-o on both

    the design/construction o the

    baseworks (whether they did

    that work themselves or not) and

    the supply and installation o the

    surace system. The door cannotbe let open, i base or suracing

    issues arise later, to complaints

    that the baseworks undertaken

    were inadequate.

    Top Tip

    Many companies are producing

    sports surace systems that are

    endorsed/licensed by peak bodies

    such as FIFA, FIH and ITF. Given

    that some companies on-sell

    their suracing systems to other

    providers or preerred contractors,

    it is important or the client to

    seek written assurance that the

    company actually holding the

    licence warrants the work o their

    contractor/sub-contractor in ull.

    There are a number o simple criteria by

    which decisions can be made as to who

    goes on your tender shortlist:

    The product being promoted by

    a particular contractor/supplier

    must have perormed satisactorily

    in independent laboratory testing

    or durability and other required

    characteristics (copies o relevant

    independent reports should be

    requested).

    The contractor/supplier should

    be able to demonstrate that they

    have previously constructed

    similar acilities, or have acquired

    or has a direct trading relationship

    with another company that has

    the experience (request that the

    contractor provide a list o similar

    projects completed not just under

    construction).

    There is no evidence o the

    perormance o the company, or

    oered product, being the subject

    o any outstanding dispute, or that

    they have previous customers that

    remain dissatised with the acility

    that they have had constructed.

    A useul process to help in collating

    preliminary inormation rom prospective

    contractors is to run an Expression o

    Interest process in which the need toattract interested, suitable contractors is

    advertised (along with the availability o a

    brie specication or project outline), and

    rom the response a short-list o best-t

    respondents is invited to tender.

    As has been said many times in this

    guide, through all o these phases it

    is highly recommended that your club

    or school has independent expert

    consulting advice available to assist in

    the decision making.

    4.7 Selecting a Tender List and Inviting Tenders

    Top TipPersonally inspect as many o the

    bidding companies previously-

    constructed acilities as is

    possible, particularly the oldest

    o the installations. Question the

    owners about the perormance

    o the surace, usage levels, the

    perormance o the seams, line

    creep, wear rates in high-use

    areas, maintenance needs and

    their opinion o the perormance othe contractor and subcontractors

    generally.

    4.8 Tender DocumentationDocumentation required with a tender

    release is partly dependant on the

    procurement route being ollowed (reer

    to Sections 4.2, 4.3 and 4.7 o this

    guide), but in broad principle tender

    documents should make reerence to:

    The role and responsibilities o the

    client/project owner.

    The role and responsibilities o the

    client/project owners consultants.

    General conditions o contract.

    Provide background inormationsuch as surveys, geo-technicaldata, planning permits (including anyconditions applicable), foodlighting

    specications, constructiondrawings (i applicable), bill oquantities, etc).

    Guarantees/warranties.

    Perormance standards andspecications.

  • 7/29/2019 AGFS_Part_5

    13/18Articial Grass or Sport 88

    O-site and on-site testing

    procedures.

    Associated works (encing, gates,

    etc).

    Equipment issues.

    Requirement or as built drawings

    (post-construction).

    Maintenance requirements.

    The process/methodology by which

    tenders will be assessed.

    It is extremely important that the tender

    documents also make strong reerence

    to:

    The need or a quality control

    process that denes key stages

    (hold points) where inspections

    o key phases o work are to be

    undertaken and approved.

    The provision, with the tender bids,

    o data sheets and specications

    and actual samples o the materials

    that are being oered in the

    tender carpet and shock pad,sand and/or rubber granule inll,

    glues, and a sample demonstrating

    the exact seaming technique to be

    used.

    Some examples o specications and

    bries are noted in Appendix 3.

    It is at this stage o the project that

    decisions made earlier in the process(i.e. procurement route ull design

    and documentation versus design and

    construct) can make evaluating tenders

    dicult.

    While providing opportunities or

    alternative ideas and approaches, the

    Design and Construct project delivery

    method can make it dicult to compare

    tender bids ie. apples with apples. Lack

    o clarity in this area not only makes the

    initial assessment process more dicult,

    but can also set up the possibility oadditional changes or variations as the

    project proceeds.

    With the ull documentation, drawings,

    and bill o quantities approach, all o the

    bids can be analysed on a detailed line-

    by-line basis which gives clear indication

    o the true and air cost or the particular

    item, and also highlights where a bidding

    contractor might not ully understand the

    issue or process in question. It should

    also help avoid circumstances where

    the client or their consultant is unawareo key issues or implications that may

    impact on their projects perormance.

    These issues can be claried as part o

    tender negotiations.

    For either procurement method (but

    particularly Design and Construct) it

    is recommended that you interview

    the two or three lowest conorming

    tenderers, going through their proposals

    in detail. This allows the ull exploration

    o the technical aspects o bids, moving

    beyond a simple ocus on price. At these

    interviews, contractors should be able to

    demonstrate:

    A detailed knowledge o the scope

    o work (Civil and Synthetic).

    What the specic materials or

    products will be.Precisely how they will be installed.

    Critical stages in the process.

    Not just how they do things, but

    why.

    A detailed program o works.

    A knowledge o the site and its

    ground conditions, existing and

    nished levels and services.

    A knowledge o who the

    subcontractors are and their

    experiences.

    To complete the tender review, check

    each bid or:

    Compliance with specications.

    The total value o the package.

    The companys experience.

    The companys reputation.

    Visit sites o relevant, nished productsand evaluate them or quality and

    perormance. For example, see how the

    surace/seams are wearing over time.

    4.9 Evaluation of Tenders

    Top TipObtain samples o the tendered

    suraces. Establish whether the

    samples provided exactly match

    the written product description/

    specication oered, and whether

    they are exactly the same as the

    product that would be laid. Thesecomparisons (via simple testing)

    should be made once the product

    arrives on-site or installation.

    Testing laboratories are listed in

    Appendix 6 o this guide.

  • 7/29/2019 AGFS_Part_5

    14/18Articial Grass or Sport89

    Prior to conrming acceptance o the

    tender rom the preerred contractor,

    a meeting should be held involving

    all project partners and the preerred

    contractor. Matters that should be

    discussed and agreed to include:

    Costs and provisional sums

    Specication and test samples

    Contract monitoring procedures

    Timescale and critical path analysis

    Site working procedure

    Subcontractors and supervision

    Maintenance schedule

    List o equipment

    Guarantee/warranty

    Specic questions related to

    the suracing products, their

    manuacture and their installation.

    4.10 Agree to Final Details With Preferred Contractor

    Top Tip

    Prior to signing o on the

    acceptance o a tender bid, go

    through the guarantee document

    in detail with the proposed

    contractor. Understand specically

    what is being oered, particularly

    extended warranty oers as these

    oten come with restrictions.

    Top TipAppendix 4 is a sample

    questionnaire used recently to help

    clariy tender submission issues

    with a proposed lead contractor.

    You may wish to undertake a

    similar process or your project.

    4.11 Awarding the JobOnce your decision has been made,

    send the contractor a letter o intent

    and ask or conrmation o their precise

    starting date on site. Promptly initiate

    the preparation o ormal written

    agreements, as ew contractors will

    agree to start work on-site beore the

    ormal contract has been received.

    The Sport England document A

    Guide to the Design, Specication

    and Construction o Multi-Use Games

    Areas (Website: www.sportengland.org)

    provides the ollowing advice regarding

    projects where it is intended that work

    will commence based on a letter o

    intent:

    I, due to time constraints, a construction

    contract is to be let initially on the basis

    o a letter o intent- a letter in which

    the employer instructs a contractor to

    proceed beore contract documents are

    executed particular care should be

    taken not to issue such a letter without

    agreement between the project owner

    and contractor o all contractual terms

    and conditions. To proceed on anyother basis potentially prejudices the

    negotiating strength o the project owner

    and can have unexpectedly adverse

    consequences or him/her.

    Depending on the orm o contract

    chosen and its content, bonds may

    need to be obtained and nancial audits

    undertaken.

    4.12 Establishing a Contract

    There are generally a range o contractoptions available. For works o this

    scale it is usual or work to be tendered

    on a xed lump sum basis which can

    include provisional sums, amounts and

    quantities i some elements o scope

    are not able to be qualied adequately.

    Other alternatives include a schedule

    o rates or construction management

    where the client eectively pays or the

    contractor on a rates basis or labour and

    materials with agreed overheads andprot components. There are a number

    o standard orms o contract that can

    be used and adopted or the chosen

    contract type. For example,Australian

    Standards AS 4000 General Conditions

    of Contract and AS 4300 GeneralConditions of contract for Design and

    Constructare good starting points.

    In determining which contract type is

    most appropriate to your project, the

    ollowing actors should be considered:

    Project complexity and cost.

    Design responsibility.

    Level o cost certainty required.

    Risk items such as ground

    conditions, and their management.

    The impact o weather.

    The risk o onsite changes.

    Saety hazardsHow much fexibility and nancialcontrol the project owner or clientwants.

  • 7/29/2019 AGFS_Part_5

    15/18Articial Grass or Sport 90

    Preparedness to deal with late

    variations or changes and the

    potential impact o same on

    proposed completion dates.

    The degree to which you want to

    leave design and construction risks

    with the contractor (could lead to

    construction problems and almost

    certainly higher tender prices).

    Eliminate all the unknowns about

    a project prior to the tender and

    pricing phase.

    Because the nal stages o an articial

    grass eld installation (laying the shock

    pad and carpet) can be criticallydependant on weather conditions, it is

    sensible to plan a projects timelines so

    that the construction phase is taking

    place during the drier or warmer months

    o the year.

    An indicative timeline (working back rom

    when the eld might become available

    or upgrade at the end o a winterplaying season say mid September) or

    a ull eld project might be similar to the

    ollowing:

    Top TipMinimise this transerred risk by providing potential tenderers with sucient

    ground investigation inormation.

    Top TipFor the scale o works associated with most articial grass projects you would

    generally go with a Fixed Lump Sum contract, whether or a ully-documented

    or design and construct project.

    4.13 Timing and Period of the Contract/Project

    1 May Advertise or Expressions o Interest (2 weeks). Finalise thespecication during this period.

    15 May Close EOI (3 weeks to review, ollowed by the selective releaseo tender).

    8 June Release tender documents (allow 4 weeks).

    8 July Close tenders (allow 4 weeks to decide/have approved).

    8 August Award contract (lead-in time 5 weeks rom awarding).

    15 September Field available, construction commences.

    22 December Field completed (14 weeks).

    Reer to Section 1.13 o this guide or

    inormation on Warranties.

    4.14 Terms and Warranties Offered

    Reer to Section 1.12 o this guide or

    inormation on Licensing.

    4.15 Manufacturer/Supplier Licensing

    In terms o interpreting product

    compliance along certication lines,

    Section 1.12 o this guide lists two

    reerences:

    Product certication: A product

    (synthetic tur system) that is

    approved by a sports parent body

    via early laboratory testing.

    Installed eld certication: The

    testing and approval o the synthetic

    grass eld or court ater it is

    installed. For some sports this is

    mandatory, and or some others it

    is only mandatory i you want to be

    able to bid or or host elite events.

    In many cases it is best to wait or

    several months worth o playing-in

    time (i.e. time or sand and rubber

    inll to settle) to lapse beore you

    conduct the post-installation testing.

    Product compliance can also reer to

    compliance in terms o perormance and

    checking processes during construction.

    This important quality check is discussed

    in Section 4.17 Monitor and Supervise

    Construction and the Contract.

    4.16 Product Compliance

  • 7/29/2019 AGFS_Part_5

    16/18Articial Grass or Sport91

    During the development o the project

    specication and contract, there needs

    to be appropriate reerence made

    to quality systems, particularly the

    importance o key hold-points involving

    constant checking o workmanship and

    materials. The SAPCA Code o Practice

    or the Construction and Maintenance o

    Synthetic Tur Sports Pitches 20 suggeststhe ollowing test items and timetable:

    4.17.1 WorkmanshipThe quality o the workmanship should

    be checked at various key stages during

    the construction process (against the

    specication or the works). These

    stages may include:

    At completion o the sub-grade,

    to check size, levels, gradients

    and strength - to compare to the

    geotechnical report, which willvalidate the design o the sub-base

    (thickness, etc).

    At completion o the construction o

    the drainage system, to ensure that

    all connections have been made

    and that the correct alls have been

    made in pipe work (and that they

    are clean many have been used

    as rubbish pits or have had waste

    concrete dumped in them!).

    At completion o the base to

    check that level and thicknessrequirements have been met and

    that the materials supplied are

    as per tender, eg. crushed rock,

    concrete, etc.

    At completion o the shock pad to-

    check thickness.

    At completion o the carpet surace-

    to ensure consistency o inll depth

    across the pitch. Also to ratiy lines,

    dimensions, and so on.

    4.17.2 MaterialsShock pad and carpet materials

    delivered to site should be checked

    (samples sent or analysis) against the

    reerence sample or:

    Shock pad:

    Tensile strength.

    Density.

    Thickness.

    Weight per unit area.

    Carpet:

    Fibre type and dtex.

    Pile length. This should match the

    nominal value to 1mm when tested

    using the appropriate method.

    Pile density in terms o tuts per

    square cm.

    Face pile weight per unit area.

    Total weight per unit area.

    Tut withdrawal orce.

    Quality o backing materials.Pile lling materials (size, shape,

    grading).

    4.17 Monitor and Supervise Construction & Contract

    Reer to Section 1.13 or extensive

    coverage o quality control issues.

    4.18 Quality Control

    Beore the acility is classied

    as Practically Complete, it is

    recommended that the client or theirconsultant project manager undertake

    or commission all necessary tests to

    ensure the compliance o the acility with

    your specication/standards. This step

    is normally linked to the retention o a

    certain percentage o the contract price.

    Checks may include:

    The colour o the pile

    The pile length

    The inll spread rate

    Any deviations in levels (beneath a 3

    metre straight edge and accordingto standard deviation nominated by

    sports code tolerances)

    Uniormity and acceptability o

    seams and joins

    A thorough visual examination

    and preparation o a photographic

    record o any distinctive eaturesThe ormal tests, such as:

    Ball rebound resilience-

    Ball rolling resistance and-

    deviation

    Berlin athlete impact response-

    (deormation)

    Peak acceleration (g) rom 1.0m-

    Limoux surace riction-

    Porosity.-

    This would also be the time at which

    the materials (carpet, shock pad,

    sand, rubber granules, adhesives, etc)are checked to see that they match

    those rst proered at the time when

    companies were making their

    tender bids.

    4.19 Check Final Completion with Consultantsand the Contractor

    20The Code o Practice or the Construction and Maintenance o Synthetic Tur Sports Pitches

    The Sports and Play Construction Association (2009)

  • 7/29/2019 AGFS_Part_5

    17/18Articial Grass or Sport 92

    Hopeully the monitoring and inspection

    process during construction has been

    suciently eective, and the nal check

    and testing has revealed no problems. In

    this case the ormal handover (the trigger

    or the nal payments, less retention

    monies to be retained) can occur.

    Should any deects be revealed,

    establish a rectication program and

    timetable with the contractor, and

    do not accept project handover until

    satised with the resolution. Depending

    on the extent o the remedial works

    required, it is possible that urther survey

    and testing work might be necessary.

    This is where a site supervisor and

    clients advisor are vital, with a very clear

    orm o contract spelling out the Quality

    Assurance, Quality Control and payment

    procedures, and the procedure or

    deects rectication and payment.

    Top TipWhile unlled articial grass carpets can be tested immediately at the completion o

    works, with lled/dressed carpets this is oten best done a month or two later ater

    the inll materials have settled properly into the carpet, and the redistribution o inll

    has been completed. With projects calling or lled/dressed carpets, you should

    consider advising bidding suppliers (in the tender specication) that nal payment

    will be held until the delayed testing is completed.

    4.20 Remedial Works and Re-Inspection

    I there were no deects identied

    ollowing practical completion (and the

    carrying-out o appropriate tests at that

    stage), then by now the acility will be

    ully operational. I remedial works were

    identied though, it may be necessary to

    re-test the surace.

    The appropriate testing issues and

    protocols are listed in Section 4.19 othis guide (Check Final Completion with

    Consultants and the Contractor).

    The stages at which eld compliance

    testing can or should occur are:

    When the carpet arrives on site.

    Send several samples (min. size

    350mm X 350mm) or analysis and

    comparison with the samples and

    specications provided originally

    with the tenderers bid and product

    specication.

    Check the thickness and

    composition o all layers in the base.

    Test the composition and depth o

    the shock pad beore the shock pad

    laying phase is completed.

    Check the perormance to

    standards or seam strength.

    Check the inll spread rate.

    Perormance testing on site

    immediately or soon ater practical

    completion.

    Perormance testing prior to the end

    o the deects liability period (usually

    12 months). Note: This may only be

    appropriate or high-end acilities,

    not community level.

    Perormance testing prior to the end

    o the warranty period - ve to seven

    years (also probably only relevant to

    high-end acilities. Adds cost to the

    project, but more importantly will

    place a stronger spotlight on usage

    levels, maintenance regimes, etc.

    Annual or biannual certication

    where required by the sports parent

    body. I so required, this needs to

    be made absolutely clear in the brieand contract details.

    At any time i you think that your

    surace is ailing to meet required

    playability and perormance.

    4.21 Field Testing

    Top Tip

    The ormal testing o an articial

    grass surace can be an expensive

    process, but the cost is minor

    compared with the overall

    investment in the project.

    Brisbane Hockey Centre

  • 7/29/2019 AGFS_Part_5

    18/18

    Guarantees on articial grass pitches

    are oten advertised as being or ve to

    seven years, but what do they actually

    cover? What acility users and nanciers

    need is a guarantee that the playing

    perormance o their pitch (to standards

    generally set by their sports parent

    body) is guaranteed or a set period

    o time. In many cases, the warranty

    provided may just relate to issues such

    as ultra-violet degradation or generalwear.

    Follow the trail back and you will oten

    nd that the warranties oered by

    suppliers or installers are likely to be

    underpinned by warranties provided

    by the yarn extruders. Note that these

    warranties are oten linked to things

    such as:

    hours o play (the general ceiling is

    1,500-1,600 hours per annum)

    number and age (size) o

    participants.

    Check Section 1.13 o this guideor important inormation related

    to establishing, understanding and

    implementing warranties.

    When the client or their representative

    consultants is satised that the acility

    is satisactorily nished (practical

    completion), the ormal handover can

    occur.

    At this point the contractor is entitled to

    receive the balance o their payment,

    less the usual retention amount that is

    held until the end o the deects liability

    period usually 12 months rom the

    date o the handover. Some owners may

    wish to again ormally test the acility

    prior to the end o the deects liability

    period.

    4.22 Handover and Defects Liability Period

    4.23 The Warranty or Guarantee Period

    Top TipMake sure that you are clear on the specics o the warranty. Does it cover

    minimum playability throughout the warranty period? I so, how is that

    measured? How does the warranty relate to the yarn, the carpet, the seams?

    Who is issuing the warranty?

    Top TipMost warranties will be linked to maintenance, both specialised and in-house,

    particularly any perormance warranty.

    Top Tip

    Warranties are generally paid on a pro-rata basis, not ull replacement. Forexample, i your carpet ails, the compensation ormula might revolve around

    the percentage o the warranty period that has elapsed and what percentage o

    the cost o the installation relates to the carpet.

    Top TipBeore the warranty period elapses, consider another batch o ormal testing i

    you think that your acility is ailing to meet the minimum playability standards

    specied.