Technical Paper M2 Aggregates Cornwall Council January 2012 N.B. This is a live document that will be updated 1
Transcript
  • Technical Paper M2 Aggregates

    Cornwall Council January 2012

    N.B. This is a live document that will be updated

    1

  • Technical Paper 2 Aggregates

    Contents 1. The geological background of aggregates. 2. Current production methods and reserves of aggregates 3. Markets, transport and use of aggregates. 4. Government planning policy and guidance for aggregates 5. Cornwall local policy development history for aggregates 6. Future needs and likely patterns of supply for aggregates 7. Safeguarding the resource and associated infrastructure for aggregates 8. Key issues for planning policy development for aggregates Figures Figure 1: Cornwall: Geology, currently worked and other permitted aggregate sites. Figure 2: Primary and Secondary Aggregate Production Table 1: Status of Primary Aggregate Quarries in Cornwall Table 2: Shipments of china clay aggregate from Par 2002 – 2004 Table 3: National and regional guidelines for aggregates provision in England, 2005 – 2020 (million tonnes) Appendices

    Appendix 1: Comments received from respondents concerning aggregates and related matters in the Cornwall Minerals Development Framework Core Strategy Revised Report on Preferred Options May 2008, Mineral Planning Authority considerations and officer recommendations.

    2

  • 1. The geological background of aggregates 1.1 The information set out below on geology is drawn from ‘Mineral

    Resource Information for Development Plans, Cornwall: Resources and Constraints. British Geological Survey (Technical Report WF/97/11, Mineral Resource Series), 1997.

    1.2 Igneous rock and sandstones are worked for aggregate in Cornwall:

    broad geological mapping information to accompany this section is included in section 2.

    Granites 1.3 Granites are the most extensive igneous rocks in Cornwall and

    occur as four large intrusions together with a number of smaller bodies. Granite accounts for the major proportion of the crushed rock output. The types of granite worked for aggregate use vary considerably in their texture and appearance, but most are coarse-grained biotite or biotite/muscovite granites, with some prominent large potassium feldspar crystals. Fine-grained granites are less common. The available technical data demonstrate that there is considerable variation in rock strength from one site to another, while resistance to polishing is relatively low. These data, together with data supplied by the Industry, suggest that the strength and Polished Stone Value (PSV) are independent of granite variety and texture, and instead, reflect local variations in weathering and secondary alteration.

    Basic igneous rocks 1.4 A wide variety of basic igneous rock occurs in Cornwall: basalt,

    dolerite, gabbro and picrite. They occur within the Devonian and Lower Carboniferous slate and sandstone sequences as variably sized bodies of extrusive (volcanic) material or intrusive (dolerite) sills and dykes. They tend to form positive features in the landscape, being harder than host rock.

    1.5 Considerable variation in lithology exists: the coarsely crystalline

    gabbros of the Lizard contrast with microcrystalline lavas of East Cornwall. They may be relatively unaltered (all show low grade metamorphism) or show extreme alteration.

    1.6 The technical properties of the basic igneous rocks also vary and

    therefore their suitability for use as an aggregate. 1.7 As the variations in basic igneous rocks are complex and may not

    be directly related to the perceived technical qualities, no differentiation is made on the resource map between intrusive and extrusive deposits. The resources shown on the map show wide variations in properties. Their potential can only be determined after detailed examination.

    3

  • Sandstone 1.8 Many of the sedimentary rocks in Cornwall contain sandstone. In

    some cases the sandstone is thickly bedded. Elsewhere it is interbedded with slate, shale or siltstone in variable proportions. Massive beds are found in the Later Carboniferous Bude Formation (North Cornwall) and parts of the early Devonian Staddon Grit.

    1.9 Thinner interbedded sandstones are found in late Carboniferous

    Bude & Crackington Formation (North Cornwall) and the late Devonian Porthscatho Formation. Most of the sandstones are technically Greywackes (i.e have a matrix of silt/clay). Individual sandstones vary in thickness, lateral persistence, grain size and strength, the latter depending on the degree of metamorphism and state of weathering. All these have a bearing on the aggregate potential of sandstone. Despite apparently extensive resources relatively little sandstone is produced in the County, reflecting the relatively high cost of working and competition from igneous rock.

    1.10 Very few technical data are available for the sandstones of

    Cornwall. Some high-specification sandstones, suitable for road surfacing occur in the late Carboniferous Culm Measures of north Cornwall. These have been shown to have considerable resistance to polishing (PSV >60) and to wear (

  • 2. Current production methods and reserves of aggregates. Figure 1: Cornwall: Geology, currently worked and other permitted aggregate sites.

    Table 1: Status of Primary Aggregate Quarries in Cornwall West Area

    Quarry Status Castle-an-Dinas Quarry Active Penlee Active (not

    working) Kessel Downs Quarry Active (not

    working) Dean Quarry Active (not

    working) West of England Quarry Active St Keverne Quarries Dormant Carnsew Quarry Active Chywoon Quarry Active Penventon Quarry Dormant

    Central Area Quarry Status Treworgans Quarry Dormant Tredinnick Quarry, Grampound Active (not

    working)

    5

  • Pentewan Beach Dormant Dairy Quarry Active (not

    working) Tregongeeves Dormant Luxulyan Quarry Active (not

    working) East Area

    Quarry Status Doublebois Quarry Dormant Carthuther Quarry Dormant Trewint Marsh Active (not

    working) Cansford Quarry Active (not

    working) Blackhill Quarry Active (not

    working) Hingston Down Quarry Active Greystone Quarry Active Pigsdon Quarry Active

    Primary aggregate. 2.1 In Cornwall the principal source of primary aggregate (aggregate

    extracted from in situ sources) is currently from some 7 actively worked aggregate quarries. A considerable amount of Cornwall’s demand for aggregate is serviced from secondary sources predominantly china clay waste (approximately 60% in 2008).

    2.2 Permitted reserves of primary and secondary aggregates in

    Cornwall greatly exceed demand (there is a “landbank” of more th93 million tonnes of crushed rock, or over 70 years of permittprimary reserves if production continues at the 2009 rates (of 1.1million tonnes) or 52 years if production follows the “sub-regional apportionment”

    an ed

    93

    .3 For aggregates a system of collecting data on sales and reserves is

    ators to

    1 levels of 1.786 million tonnes per annum). 2

    well established by a four yearly Aggregates Monitoring Survey carried out by mineral planning authorities on behalf of the Government. The mineral planning authority also asks opersupply data on production for intervening years so that a more accurate picture of the overall trend can be established.

    1 South West Regional Aggregates Working Party: Annual Report 2008

    http://www.communities.gov.uk/publications/planningandbuilding/swannualreport2008

    6

  • 2.4 In 2009 production of primary aggregates in Cornwall was around 1.193 million tonnes (cf 1.45 million tonnes in 2007). Due to commercial confidentiality it is not possible to break this figure down in to the amount of crushed rock and sand and gravel produced in the county.

    Secondary / Recycled Aggregates 2.5 By far the largest source of secondary aggregate in Cornwall is

    china clay waste. This can be used for a range of purposes including block making, concreting sand and bulk fill in highway schemes in the County and is frequently regarded as an equivalent material to quarried primary aggregate. In the case of concreting sand, in many areas there is no commercially available alternative. Slate waste is also sold for use as construction fill and sub-base material.

    2.6 There is potential for greater exploitation of the estimated 120

    million tonnes of useable secondary aggregate resources in the Hensbarrow (St Austell China Clay) Area (embedded in china clay waste tips). The introduction of the Aggregates Levy, payable on sales of primary aggregates, has resulted in greater use of this resource. The current rate is £2.00 per tonne.

    2.7 Sales of secondary aggregates during 2009 were approximately

    1.25 million tonnes compared with approximately 2.14 million tonnes in 2007. A large proportion (98.75%) of the secondary aggregate material sold was china clay waste, the remainder being slate waste.

    2.8 The graph below ‘Primary and Secondary Aggregate Production’

    shows the total sales of primary and secondary aggregates in Cornwall from 1990. This graph shows that the level of aggregate production has fallen after a period of relative stability. It can also be seen that the production of aggregate material sourced by secondary aggregates has risen since 1993.

    7

  • Figure 2: Primary and Secondary Aggregate Production

    2008 200620042002200019981996199419921990

    4000000

    3500000

    3000000

    2500000

    2000000

    1500000

    1000000

    500000

    0 Year

    Primary aggregate Secondary aggregate

    Primary aggregate reserves in Cornwall greatly exceed demand. 2008 levels of primary aggregate reserves stood at an estimated 93 million tonnes. (Active quarries = 67,971,970.44 tonnes Inactive quarries=24,866,260 tonnes) 3. Markets, transport and use of aggregates. 3.1 A wide range of aggregates are used by industry in the construction

    of domestic, commercial and other buildings and transport infrastructure such as roads, railways, ports and airports. Most aggregates produced in Cornwall are transported by road to local destinations. Some secondary aggregates are transported by rail and sea to destinations beyond Cornwall, and there is potential to expand these export markets in the future.

    High Specification Aggregates (HSA) A report titled ‘The sustainable use of high specification aggregates for skid resistant road surfacing in England’ was published in 20042. Some of the key points/findings from that report are as follows: • High Specification Aggregates used for the construction of skid

    resistant road surfaces are relatively rare and highly specialised aggregates which can only be obtained in limited areas

    • Resistance to polishing is the single most important characteristic of High Specification Aggregates although resistance to abrasion is important. Resistant to fragmentation and weathering are also relevant.

    2 The Sustainable Use of High Specification Aggregates for Skid-Resistance Road Surfacing in England 2004 Capita Symonds http://www.sustainableaggregates.com/library/docs/samp/l0057_samp_1_039.pdf

    8

    abroadLine

  • • The specific thresholds used to define HAS for the purpose of the study are: Polished stone Value > 58, Aggregate Abrasion Value < 16, Los Angeles Coefficient < 30 & magnesium sulphate value of > 25

    • When considering national and regional guideline figures, High Specification Aggregates should be seen as a national, strategic resource

    • It is recommended that Mineral Planning Authorities should differentiate between resources of High Specification Aggregates and those for other, more general applications, with separate landbanks being maintained for each.

    3.2 Only 2 sites in Cornwall, Blackhill Quarry and Lean Quarry, were

    identified in the Capita Symonds report as Category 1 (the highest quality for HSAs) i.e. operational sites with Polished Stone Value (PSV’s) above 58. These have subsequently closed. Other sites in Cornwall of lower quality or potential were identified:

    Quarry PSV

    Tredinnick (Grampound) Quarry (not operating)

    63

    Pigsdon Quarry Not identified

    Greystone Quarry 57

    Castle an Dinas Quarry 57

    Carnsew Quarry 57

    De Lank Quarry 54

    DeanQuarry (not operating) 54

    Hingston Down Quarry 53

    Penlee Quarry (not operating) 44 3.3 The geological formation most likely to contain higher quality HSA

    resources in Cornwall is the Cornwall Gramscatho group in Mid Cornwall.

    3.4 Use of different aggregate materials produced in Cornwall. Granites 3.5 Crushed rock and sand from granites are used for a range of

    aggregate uses including: asphalt, uncoated roadstone, in concrete, as armourstone, in an unbound state for as a building/mortar sand as armourstone and in constructional fill.

    3.6 The granite resources exploited in the County do not yield high grade

    material for use in skid resistant road surfacing with material from all sites having Polished Stone Value of less than 57. However some have sufficiently high polished stone values (low 50s) to be used in some of the less demanding road surfacing applications (but only on lightly trafficked low speed roads). The site at Castle and Dinas is

    9

  • notable in that aggregate from this site is typically has a PSV value of 57 (Capita Symonds Report table 7.7).

    3.7 China clay aggregates are worked as a by product of china clay

    production. They consist of sand (from the quartz fraction of granite that has been kaolinized) and crushed rock from unaltered granite fractions. China clay waste has already substantially replaced primary coarse aggregates from traditional Cornish granite quarries (being a very similar material but exempt from the aggregates levy. China clay sand also has a long tradition of being used instead of natural sand for concreting.

    Basic igneous rocks 3.8 Crushed rock from basic igneous deposits worked in Cornwall are

    used extensively in road surfacing applications (asphalt and uncoated roadstone). Some products are also used in concrete and other unbound aggregate uses. Some of the dolerites have notable Polished Stone values. For instance Blackhill Quarry (which is now closed) is recorded as having a PSV of 60 and Greystone a PSV of 57 3. In addition Blackhill Quarry is identified as a category (1) HAS source in England (Capita Symonds Report on High Specification Aggregates 2).

    Sandstones 3.9 The Sandstones of the Carboniferous Crackington and Bude

    Formations in north Cornwall and the Upper Devonian Porthscatho Formation are generally of very high quality with PSVs and other properties sufficient for use in the most demanding road surfacing applications, but the interbedded shales present major obstacles in terms of overall economic viability 4.

    3.10 Whereas the high PSV road surfacing aggregate can commend

    premium prices and therefore justify relatively long distance transportation, the bulk of the output from these sites can only be used to satisfy local, low grade requirements. The shales in particular can only be utilised as a bulk fill material, and for pipe bedding etc, and much of the production cannot be sold (especially when competing against secondary and recycled products that are exempt from the aggregates levy)3.

    3.11 Grampound Quarry is identified as a category (3) HAS source (in the

    Capita Symonds report on High Specification Aggregates) as is Pigsdon Quarry. However that classification reflects that fact that the quarry is only a ‘potential’ supplier of such material.

    3 The sustainable use of high specification aggregates for skid resistant road surfacing in England, Capita Symonds Ltd, November 2004 (report to the Office of the Deputy Prime Minister and the Mineral Industry Research Organisation). Appendix E. 4 Technical and strategic assessment of aggregates supply options in the south west region. Capita Symonds Ltd. June 2005.

    10

  • Markets 3.12 Cornwall produces sufficient amounts of aggregate to meet local

    demand for concreting aggregate, many grades of roadstone and other products. These markets are met by the primary and secondary (china clay) aggregate resource. However, very high grade road stone has been imported from other parts of the UK.

    3.13 China clay aggregate, transported by road, plays an important role in

    meeting the need for aggregate in Cornwall and is utilised from around Redruth in the west to Camelford in the North and Plymouth in the East (Para 4.20 3).

    3.14 Capita Symonds (3) considered that the Aggregates Levy at £1.60 (at

    the time the report was written in 2005) equates to about 10 miles of road transportation. This increases the radius of penetration into the local market by this amount and effectively means that most of the china clay workings become ‘coastal’ quarries with much easier access to port facilities at Par and Fowey.

    3.15 Small quantities of aggregate have for a number of years, been

    transported by sea from Par docks to ports such as Erith, Rye, Shoreham, Littlehampton, Southampton and Guernsey. The quantities involved have grown steadily peaking in 2003. Par Docks Closed in 2007 and subsequently some shipments of secondary aggregates have been transported from the Port of Fowey, and by rail.

    3.16 The table below shows the shipments of clay aggregate from Par in

    the past and confirm the south east focus of the domestic market (taken from Foy/Par Bulk Transport Study, MDS Transmodal Ltd, August 2009). The table also shows the decline in volumes of china clay waste exported to areas outside the South West.

    Table 2: Shipments of china clay aggregate from Par 2002 – 2004

    2002 2003 2004 Year 000 tonnes

    Vessels 000 tonnes

    Vessels 000 tonnes

    Vessels

    Total 137 107 95 71 42 26 of which into

    Thames 70 54 95 71 42 26 Portsmouth

    19 15 12 8 14 12

    Isle of Wight

    18 11 37 25 6 5

    Source: Fowey/Par Bulk Transport Study, MDS Transmodal, Aug 2009. 3.17 In terms of future markets for china clay waste MDS Transmodal

    conclude (para 4.5), having considered all the factors that “the market for china clay waste is relatively small. The South

    11

  • East/London regional market could grow to be in the region of 600,000 tonnes by 2060”. They go on to say that “Little information is available on overseas demand for secondary aggregates, though principal markets lie in the near continent and Channel Islands. Sales of china clay waste to these markets will be in competition with suppliers that are geographically closer and therefore at a transport cost advantage compared with the South West”.

    4. Government planning policy and guidance for aggregates. 4.1 Minerals Policy Statement 1 (MPS1): Planning and Minerals

    (CLG,2006) was published on 13 November 2006. This is the overarching planning policy document for all minerals in England, providing advice and guidance to planning authorities and the minerals industry. It is intended to ensure that the need by society and the economy for minerals is managed in an integrated and sustainable way against its impact on the environment and communities. It replaces Minerals Planning Guidance (MPG1) Note 1: General considerations and the development plan system.

    4.2 It sets out the generic national objectives for minerals, linked to

    policies for minerals concerning:

    • Exploration • Survey • Safeguarding • Protection of heritage and countryside • Supply • Bulk transportation • Environmental protection • Efficient Use • Restoration

    4.3 The following are extracts from national minerals policy:

    Safeguarding mineral resources policy • define Mineral Safeguarding Areas (MSAs) in LDDs, in order that

    proven resources are not needlessly sterilised by non-mineral development, although there is no presumption that resources defined in MSAs will be worked;

    • in unitary planning areas, define MSAs in LDDs to alert prospective applicants for non-minerals development to the existence of valuable mineral resources;

    Safeguarding sites for mineral infrastructure policy • safeguard existing, planned and potential rail heads, wharfage

    and associated storage, handling and processing facilities for the bulk transport by rail, sea or inland waterways of minerals, particularly coal and aggregates, including recycled, secondary and marine-dredged materials;

    Protection of Heritage and Countryside

    12

  • • do not normally grant planning permission for a proposed mineral development on land within or outside a Site of Special Scientific Interest (SSSI), if it is likely to have an adverse effect on a SSSI (either individually or in combination with other developments);

    • consider carefully mineral proposals within or likely to affect regional and local sites of biodiversity, geodiversity, landscape, historical and cultural heritage;

    Supply policy • identify at the regional level, those minerals which are of

    national and regional significance and include policies for them in RSS (now superseded);

    Bulk transportation policy • seek to promote and enable the bulk movement of minerals by

    rail, sea or inland waterways to reduce the environmental impact of their transportation;

    • promote facilities at ports and rail links that have good communications inland, so that bulk minerals can be landed by sea and distributed from ports, as far as is practicable, by rail or water;

    • safeguard and promote rail links to quarries where there is potential to move minerals by rail.

    Efficient use policy • maximise the potential for minerals waste to be used for

    recycling or in-site restoration, but if not required for these purposes and where practicable, identify a market for its potential use;

    Restoration policy • take account of the opportunities for enhancing the overall

    quality of the environment and the wider benefits that sites may offer, including nature and geological conservation and increased public accessibility, which may be achieved by sensitive design and appropriate and timely restoration;

    • consider the opportunities that sites may offer for the development of new woodland areas and for providing networks of habitats;

    4.4 The Planning and Minerals Practice Guide which accompanies MPS1

    offers examples and principles of good practice and background information.

    4.5 Paragraph 59 identifies and encourages the potential use of china

    clay waste for aggregate purposes. Minerals Policy Statement 1 Annex 1: Aggregates (CLG, 2006) 4.6 This annex sets out Government planning policy on the provision of

    construction aggregates in England. Aggregates here include land-won sand and gravel and crushed rock, marine-dredged sand and gravel and alternative, including recycled, materials supplied or used as aggregate

    13

  • • To encourage the use, where practicable, of alternative aggregates in preference to primary aggregate;

    • To encourage the supply of marine-dredged sand and gravel to the extent that environmentally acceptable sources can be identified and exploited, within the principles of sustainable development;

    • To make provision for the remainder of supply to be met from land-won sand and gravel and crushed rock.

    Minerals Policy Statement 1: Practice Guide (CLG, 2006) 4.7 The national and regional guidelines for aggregates provision in

    England for the period 2005 to 2020 (DCLG, 2009) provides guidance on the preparation and revision of minerals local development frameworks and regional spatial strategies. The guidelines aim to inform the provision of aggregates through the planning system.

    4.8 The guidance recommends that each mineral planning authority

    should calculate their “land banks” for primary aggregates (i.e. the size of their permitted reserves), and should also estimate how long those reserves are likely to last (based upon a prediction of the average annual production).5 Government advises that the minimum land banks should be 10 years for crushed rock aggregates and 7 years for sand and gravel. Where land banks are considered to be insufficient to provide an adequate supply for the whole of the plan period, the mineral planning authority should seek to make provision for new permissions by making appropriate allocations in the development plan.

    4.9 British Geological Survey “Minerals Resource Information for

    development plans Cornwall Resources and Constraints 1997”provides a map showing mineral resources within the county relevant to different uses including aggregates. A description of the various mineral resources relevant to primary aggregates is included in the beginning of the paper. A separate chapter on secondary aggregates provides information on resources from china clay waste, slate waste and metalliferous mining sites.

    Update

    4.10 n July 2011 the Government published the Draft National Planning

    Policy Framework. This includes a section on Minerals and makes specific reference to defining Mineral Safeguarding Areas for minerals of national and local importance, including kaolin. The Draft National Planning Policy Statement can be viewed at http://www.communities.gov.uk/planningandbuilding/planningsystem/planningpolicy/planningpolicyframework/

    5 Mineral Policy Statement 1: Planning and Minerals Annex 1. Aggregates http://webarchive.nationalarchives.gov.uk/+/http://www.communities.gov.uk/publications/p lanningandbuilding/mineralspolicystatement5

    14

    abroadLine

  • 4.11 In addition, the Localism Bill is progressing through Parliament. The aims of the new legislation include decentralising and strengthening local democracy, empowering communities and the introduction of neighbourhood planning. Information on the Localism Bill can be viewed at https://www.gov.uk/government/topics/local-government

    5. Cornwall Local Policy Development History for Aggregates Cornwall Minerals Local Plan 1997 5.1 This is a Countywide Plan setting out Local Policy in line with

    national and regional guidance covering all mineral sectors. 5.2 Chapter 9 deals specifically with aggregates and Policy A1 states

    that a landbank of permitted aggregate reserves will be maintained in accordance with Minerals Planning Guidance Note 6.

    5.3 Chapter 10 deals with the related topic of Secondary Aggregates

    explaining the council’s encouragement of the use of secondary aggregates, particularly, from the St Austell China Clay Area and including Policy SE1 which favours development for the recycling, handling and transfer of mineral waste for secondary aggregates subject to exceptions.

    Cornwall Structure Plan 5.4 The policies of the Cornwall Structure Plan 2004 have been saved

    and will remain extant until replaced by Cornwall Local Development Framework. It is less specific than the earlier Structure Plan of 1997 concerning aggregates and minerals because the Cornwall Minerals Local Plan had been adopted in the intervening period.

    5.5 Policy 5 states that “Mineral resources should be conserved and

    managed to provide a steady supply of minerals to meet needs subject to environmental and social considerations and the need for high standards in restoration and aftercare. Development should ensure:

    • the conservation of the mineral resources; • a steady supply of minerals is available; • impacts on the environment are minimised and

    encouragement is given to the use of secondary or recycled aggregates;

    • an increased use in non road based transport; • the improvement of operational standards at all mineral

    workings; • that high standards of restoration and aftercare are secured

    on a progressive basis; • that adequate overall capacity for mineral wastes arising in

    Cornwall is provided for during the Plan period.

    15

  • Cornwall Minerals Development Framework 5.6 The policy for aggregates set out in the Revised Report on Preferred

    Options 2008 was broadly as follows: 5.7 Local needs for crushed stone and sand aggregates will be met

    predominantly from primary and secondary resource areas within Cornwall, located outside the Cornwall Area of Outstanding Natural Beauty and the Cornwall and West Devon Mining Landscape World Heritage Site, mainly in the Carnmenellis and Hensbarrow Granite, the North Cornwall Sandstone and the East Cornwall Dolerite Areas, (An exception will be made for existing operational sites outside these areas)

    5.8 Demand for crushed rock and sand to meet the needs of more

    distant markets within the UK and beyond will be met predominantly from secondary resources from China Clay Waste in the Hensbarrow Area.

    5.9 Following the reform to the development plan system work began

    on the Cornwall Minerals Development Framework, with an issues and options consultation taking place in 2004 and subsequent preferred options consultation in December 2006. A revised preferred options report was published for consultation in 2008, following changes to guidance on Core Strategies. A summary of the consultee responses to the Cornwall Minerals Core Strategy Revised Preferred Options Report concerning building stone is included at Appendix 1.

    5.10 Following creation of the unitary authority for Cornwall in April 2009, minerals planning policy is now being prepared for inclusion in the Cornwall Local Development Framework Core Strategy, although it is anticipated that a specific Minerals Development Plan Document will be prepared following adoption of the Core Strategy.

    6. Future needs and likely patterns of supply for aggregates Primary Aggregates 6.1 Regional guideline figures for aggregates are set out in ‘National

    and regional guidelines for aggregates provision in England, 2005 – 2020’. These are shown in the table below.

    Table 3: National and regional guidelines for aggregates provision in England, 2005 – 2020 (million tonnes) Land-won

    Sand & Gravel

    Land-won Crushed Rock

    Marine Sand & Gravel

    Alternative Materials

    Net Imports to England

    South West

    85 412 12 142 5

    England 1028 1492 259 993 136

    16

  • 6.2 Cornwall can easily meet the Sub-Regional Apportionment set by central government and the South West Aggregate Working Party for Primary Crushed Rock aggregates of 26.94 million tonnes up to 2020. However the timeframe of the Core Strategy runs until 2030 and it is important to gauge likely demand up until that time. Given that permitted reserves of primary aggregates are estimated to amount to an estimated 91 million tonnes there is more than sufficient permitted reserve to meet the needs of Cornwall over the plan period and for some time beyond.

    6.3 In addition there are in excess of 120 million tonnes of secondary

    aggregates embodied in china clay waste tips in Cornwall. Reserves of China clay amount are estimated to exceed 60 million tonnes. It is estimated that some 8.3 million tonnes of secondary aggregate will be generated annually from china clay waste. (If china clay production continues at current rates (at 1.1968 million tpa) “live” production of secondary aggregate in Cornwall will be around 200,000 tonnes per annum.

    6.4 A study undertaken by Capita Symonds (The Sustainable Use of

    High Specification Aggregates for Skid-Resistance Road Surfacing in England 2004) recommended that mineral planning authorities should identify separate land banks for High Specification Aggregate and mainstream primary aggregates, and that sites for new High Specification Aggregate reserves should be allocated in development plans as a high priority. This is a matter which should be addressed in the Local Development Plan. (Further assessments will be completed prior to publication to take into account the results of a survey of operators which is currently underway).

    7. Safeguarding the resource and associated infrastructure for aggregates 7.1 There are a large number of aggregate quarries with extant

    planning permissions for extraction. At present, only those which are currently or were recently worked (predominantly those with larger reserves) are safeguarded.

    7.2 In addition, a level of safeguarding is afforded to secondary

    aggregate reserves within existing china clay waste tips, by virtue of the fact that they fall within the extensive St Austell China Clay Mineral Consultation Area.

    7.3 Further investigations are required, working with the aggregate

    operators, to review the aggregate mineral consultation areas. 7.4 Government guidance requires mineral planning authorities to

    safeguard existing, planned and potential rail heads, wharfage and associated storage, handling and processing facilities for the bulk transport by rail, sea or inland waterways of minerals, particularly coal and aggregates, including recycled, secondary and marine-dredged materials. Currently, land at the ports of Par and Fowey

    17

  • are safeguarded. Whilst both ports have exported aggregates in the past, the port of Par is now closed.

    8. Key considerations for planning policy development for aggregates 8.1 Consideration 1 - New Sites There are sufficient permitted reserves of primary aggregates in Cornwall to meet estimated needs for “mainstream” crushed rock over the Plan period. Consequently it would appear that there is no need to identify new sites for mainstream crushed rock primary aggregate over the plan period. 8.2 Consideration 2 - Provision for particular grades of material. There is a need to explore the possibility of identifying a potential site (or sites) for High Specification Aggregates for road stone uses (potentially for safeguarding or allocation within the Local Development Framework. 8.3 Consideration 3 - Restoration The considerable level of permitted reserves of primary and secondary aggregate (china clay waste) has resulted in a situation where potential supply from permitted reserves vastly exceeds existing and likely future demand. Consequently many quarries work sporadically, are mothballed or are defined as dormant. Consideration should be given to the future of quarries which lie unworked or dormant. Should guidance be prepared to promote interim restoration where it is not intended to preclude working in the future? 8.4 Consideration 4 - China clay waste opportunities. There are vast reserves of secondary aggregate within existing tips in the Hensbarrow China Clay Area. In addition this resource is being added to as clay production proceeds. There is the potential to increase secondary aggregate production to serve markets in the South East and other markets outside Cornwall. (Even with an increase in production for export there is likely to be sufficient reserves to meet needs until the end of the plan period). Consideration should be given to the promotion of increased use (and export) of china clay waste as a substitute for primary aggregate through the Local Development Framework. Sites relating to the bulk transport of secondary aggregates should be safeguarded and new or extended sites could be allocated in the Local Development Framework.

    18

  • Appendix 1

    Comments received from respondents concerning AGGREGATES and related matters in the Cornwall Minerals Development Framework Core Strategy Revised Report on Preferred Options May 2008, Mineral Planning Authority considerations and officer recommendations.

    Since the reform of the planning system (as required by the Planning and Compulsory Purchase Act 2004), work has been undertaken to replace the Cornwall Minerals Local Plan. Initially, Cornwall County Council was working towards the production of a separate Cornwall Mineral Development Framework. However, since the amalgamation of the former County and District/Borough Councils for Cornwall to form the unitary Cornwall Council minerals policy for Cornwall will be included in the Cornwall Local Development Framework.

    To progress this work consultations/ stakeholder participation has been undertaken to date on the following publications:

    Cornwall Minerals Development Framework: Report on Issues and Options October 2004

    Cornwall Minerals Development Framework: Report on Preferred Options November/December 2006

    Cornwall Minerals Development Framework: Core Strategy Revised Report on Preferred Options May 2008

    Following the consultation on the Cornwall Minerals Development Framework: Core Strategy Revised Report on Preferred Options, 2008, a report detailing the comments received, Mineral Planning Authority considerations and officer recommendations was considered by Cornwall Council’s Cabinet, Planning Policy Advisory Panel in November 2009. http://democracy.cornwall.gov.uk/Published/C00000663/M00002120/$$ADocPackPublic.pdf

    Comments received from key AGGREGATES stakeholders and others about AGGREGATES and related issues have been transcribed in detail in this Appendix.

    Key matters raised were:

    • Support for the option of increasing exports of secondaryaggregates from china clay waste.

    19

  • • Support for the use of secondary and recycled aggregates and the use of demolition waste.

    • The Port of Par was no longer viable and should not be safeguarded

    as infrastructure for exporting china clay and secondary aggregates.

    • Transport assessments will be needed for new applications.

    • Advice should be sought from the industry regarding the likely

    future viability of primary aggregates sites (in respect of decisions about safeguarding).

    Transcription of aggregates comments received, MPA considerations and officer recommendations 8.1 Spatial Strategy Aggregate Industries Comments Section 8.1.5 bullet point 2 discusses aggregates that are suitable for use in wearing course roads. It identifies two quarries as having high specification i.e. a higher PSV value. In section 8.2.7 >60 PSV is referred to. Greystone Quarry produces consistent 57 PSV stone utilised across the whole of Cornwall for wearing course. This quarry should be included within the text of bullet point two. By identifying specific quarry's the supporting text for policy 1 favours these quarry's. Either include all quarry's that produce material suitable for wearing course in Cornwall or none. Suggested amendments Include Greystone Quarry within bullet point two. MPA considerations Agree that Greystone Quarry should be included in bullet point two of 8.1.5 for consistency. Officer recommendations Incorporate suggested change in Cornwall Minerals Development Framework Core Strategy or related evidence base. Aggregate Industries Comments Policy 1, paragraph 3 does not make sense. In its current format there is a presumption against primary aggregate sites unless "where no net gain of mineral tonnage would be achieved"? i.e. you can apply for a quarry or extension where there is no mineral! Suggested amendments Strike "where no net gain of mineral tonnage would be achieved".

    20

  • MPA considerations The purpose of this clause is to facilitate the enhanced operational circumstances at an existing aggregates quarry by allowing an extension where environmental advantages have been demonstrated, whilst limiting the permitted reserves (mineral tonnage) at that site to an equivalent of the current permitted reserves. (Essentially a "swap" of the permitted area or depth of working). This would normally be achieved through the revocation/modification of that part of the existing planning permission which is operationally or environmentally problematic (such as a that which is close to a residential area). The MPA will seek to clarify the syntax whilst retaining the principle of this part of the policy Officer recommendations This element of the policy will be clarified within the planned consolidation of the Cornwall Minerals Development Framework policies. Cornwall AONB Partnership Comments Para 8.1.3 - To provide clarity need to be more specific about environmental and social costs. Para 8.1.5 - bullet point one - Recognition of the challenge regarding the relationship between the source of aggregate and the Cornwall AONB is welcomed. Option 3 and policy 1 are supported in the context of the considerations outlined in para 8.1.6. Suggested amendments None. MPA considerations The support of the Area of Outstanding Natural Beauty Office is noted regarding 8.1.5, Option 3 and Policy 1. More information about the environmental and social costs will provided in the evidence base. Officer recommendations Provide full information about the social and environmental costs in the evidence base. Quarry Products Association Limited (now Mineral Products Association) Comments 8.1.6 'Exceptional circumstances' can only be judged at the time a proposal comes forward. Therefore it is not appropriate to state that there are 'no exceptional circumstances relating to non-specialist aggregates' prior to a proposal coming forward. Suggested amendments None. MPA considerations

    21

  • Noted. The text should be amended. Officer recommendations The Phrase "There are no exceptional circumstances relating to non- specialist aggregates which would appear to be relevant in Cornwall, so" should be deleted from 8.1.7. 8.2 Safeguarding Imerys Minerals Ltd Comments Strategies, Activities and Actions - Safeguarding - Paragraph 8.2.5 - Page 60: Unsound - Tests 7 and 9 (Revised PPS 12 tests - Justified and effective) This paragraph is not justified on the up to date evidence as summarised below and is not the most appropriate approach to safeguarding facilities. It is unlikely to be effective because it lacks flexibility. This paragraph advises that the mineral planning authority must safeguard facilities for the bulk of transportation of minerals by rail and sea. It is suggested that the mineral planning authority should consider the foreseeable economic viability of facilities when considering safeguarding particular infrastructure rather than the implied blanket safeguarding of all bulk transport facilities. It is important to stress that not every facility for the bulk transportation of minerals by rail and sea need be safeguarded in particular when it is not viable, needed or has become obsolete through various factors. Suggested amendments Replace the words 'must safeguard' with the wording 'may consider safeguarding facilities.' MPA considerations Mineral Planning Guidance 1 Planning and Minerals sets out national policies for mineral planning, which include advice to safeguard existing, planned and potential facilities for the bulk transport and handling, processing and handling of minerals. The proposed change does not reflect the national policy. However, a slight adaptation of the current wording is proposed. Officer recommendations Additional wording should be inserted into the current text of 8.2.5 to highlight aspects of the national guidance: Insert "follow national guidance to" after "the mineral planning authority" and before "safeguard”, and insert “(particularly in Cornwall for china clay and secondary aggregates)" after "the bulk transportation of minerals". Policy 1 Preferred Spatial Strategy for aggregates in Cornwall The Kaolin and Ball Clay Association (UK) Comments

    22

  • Preferred Spatial Strategy for aggregates in Cornwall Section 8.1: Spatial Strategy - Policy 1; page 46 Comments The Association finds the policy as sound and supports the statement in relation to the general presumption in favour of a significant expansion of extraction of secondary aggregates from the china clay waste resources in the Hensbarrow Area. Suggested amendments None. MPA considerations The Kaolin and Ball Clay Association's support for the policy and statement is welcomed. Officer recommendations The principle of this Policy should be retained within the Cornwall Minerals Development Framework Core Strategy. Cornish Chamber of Mines and Minerals Comments The Chamber in general supports the Core Strategy document, subject to its further comments below. However the Chamber considers that some of the wording comes across as being negative against mineral development. In the Chambers opinion the mineral resource within Cornwall is an extremely important economic asset for the county. Therefore the principal objective of the Core Strategy should be to protect the strategic importance of this resource and to provide guidance and preferred directives that assist future mineral working. Whilst it is important to negate against the potential adverse effects of mineral development the Core Strategy should place greater emphasise against sterilisation of mineral resources by non-mineral related development. One particular example of this is Section 8.1.15 on page 51 of the Core Strategy where we would argue that urban regeneration within areas of potential future mineral working has to make allowance for the requirement to resume such working should viable economic market conditions arise. Therefore we would propose re-word the last paragraph in this section to read `urban regeneration has to work around areas of potential future mining’. We would like to point out also that the photograph on page 119 is Levant Mine (not Botallack). Suggested amendments Therefore we would propose re-word the last paragraph in this section to read `urban regeneration has to work around areas of potential future mining’. MPA considerations The general support of the Cornish Chamber of Mines and Minerals is welcomed and the mineral planning authority agrees that Cornwall's minerals resources are an important economic asset which the Minerals Development seeks to safeguard. Section 8.1.15 is correct in indicating the potential conflicts of reactivation of mining with the urban regeneration of traditional mining areas. It would be appropriate to add

    23

  • to the next section, "How the above factors have influenced the spatial strategy for metals" to address the concern raised by the Chamber of Mines, by emphasising the importance of working closely with the urban regeneration teams to ensure the protection of safeguarded mineral areas. Officer recommendations Correct name of photograph on page 119 to read Levant Mine. Incorporate the principle of the suggested change within the Cornwall Minerals Development Framework Core Strategy or related evidence base. Goonvean Ltd Comments Goonvean Ltd finds the policy as sound and supports the statement in relation to the general presumption in favour of a significant expansion of extraction of secondary aggregates from the china clay waste resources in the Hensbarrow Area. Suggested amendments None. MPA considerations The support of Goonvean Ltd for this policy and statement is welcomed. Officer recommendations The principle of this Policy should be retained within the Cornwall Minerals Development Framework Core Strategy. South West Councils Comments Has a sufficient landbank of primary aggregates. We welcome that the Core Strategy also recognises the increased importance of Secondary aggregates. We also note that the Council's Preferred Spatial Strategy Option 3 for aggregates envisages an increased export of secondary aggregates, serving markets in the UK and beyond. It will be critical however to demonstrate that a continued supply of secondary aggregates can be ensured from the China Clay reserves over the plan period. We find this option and Policy 1 however to be in general conformity with draft RSS, and here in particular with Policy RE12, and it is also in line with draft RSS para. 7.3.32. It will be important however, if required, to identify sites for key additional infrastructure/facilities in the Core Strategy, with the capacity to promote the delivery and bulk transport of minerals. Suggested amendments None. MPA considerations The mineral planning authority will commission an expert study concerning the bulk transport potential for exporting minerals and particularly secondary aggregates from the ports of Fowey and Par which

    24

  • will also consider other bulk transport modes. This and further consultations with the china clay and secondary aggregate industries will be used as a further evidence base. Officer recommendations A demonstration should be given, within the evidence base to the Core Strategy that a continued supply of secondary aggregates can be ensured over the Plan Period. Future sites for additional key infrastructure and facilities for the bulk transport of secondary aggregates should be identified within the Core Strategy Imerys Minerals Ltd Comments Strategies, Activities and Actions - aggregates - Preferred Spatial Strategy for aggregates in Cornwall Policy 1 Unsound - tests 7 & 9 (Revised PPS 12 tests - Justified and effective) This paragraph is not justified on the up to date evidence as summarised below and Par Docks is too constrained; it is therefore not the most appropriate strategy. It is unlikely to be effective because is probably not deliverable and lacks flexibility. Support is given by Imerys to Preferred Spatial Strategy for aggregates in Cornwall - Policy 1. However it should be noted that in accordance with Imerys' other representations relating to Par Docks it is unlikely that secondary aggregates would be shipped from Par by sea due to economies of scale. Fowey has the capacity to handle secondary aggregates and would be the commercially favoured facility which is under the control of Imerys. Suggested amendments Delete the indicated key reference to Par Docks on the diagram accompanying aggregates - Option 3. MPA considerations Up to date evidence will be gathered through the independent expert study to assess the potential for the use of the Ports of Fowey and Par for the bulk transfer of minerals (see "outcome" relating to comment 221), which (in association with further discussions with Imerys and other stakeholders) will inform the decision whether or not to delete the reference to Par Docks. Officer recommendations The findings of the independent expert study on the Bulk Transport Potential of the Ports of Fowey and Par and the outcome of ensuing discussions with Imerys and key stakeholders should be used to determine whether or not to reference Par docks in the diagram accompanying aggregates Option 3. Restormel Borough Council Comments Policy 1 Preferred Spatial Strategy for aggregates in Cornwall. All options envisage that primary aggregates will continue to supply local markets by road from resource areas mainly in the Carnmenellis and Hensbarrow

    25

  • Granite Areas, the North Cornwall Sandstone Areas and the East Cornwall Dolerite areas. The plan supports the increased export of secondary aggregates. Given that the permitted reserves of primary and secondary aggregates in Cornwall greatly exceed demand this approach would help support the economy whilst areas of industry such as china clay continue to change. Suggested amendments None. MPA considerations None. Officer recommendations None. Quarry Products Association Limited (now Mineral Products Association) Comments The paragraph is unclear and there needs to be justification of why there will be a presumption against primary aggregate sites. There is no clear mechanism to ensure this policy is effective and therefore fails soundness test 8. Suggested amendments None. MPA considerations The policy has evolved from the main challenges and opportunities set out within 8.1.5. It is accepted that further justification of the policy within the text and evidence base is needed. In particular further information should be given concerning Cornwall's existing land bank of primary aggregate reserves which exceeds Cornwall's regional apportionment. Officer recommendations Expand the explanatory text and include appropriate information within the evidence base to justify the policy and to explain why there is a presumption against additional primary aggregate sites. North Cornwall District Council Comments Observations It is recommended that the spatial strategy for aggregates be supported but every effort is made to avoiding possible conflicts with regeneration objectives. Suggested amendments None. MPA considerations

    26

  • The support for the spatial strategy for aggregates is noted. The development management policies relating to the safeguarding of mineral resources and mineral related infrastructure do make provision for exception from safeguarding in cases of overriding need. Officer recommendations None. Government Office for the South West (GOSW) Comments Whilst we do not disagree with the general approach set out in this policy, we are concerned about appropriateness of the terminology adopted. We would advise that terms such as "general presumption against/in favour" should be avoided as being vague, imprecise and potentially contrary to the evidence based approach. Suggested amendments None. MPA considerations Noted. The policy should be reviewed and its precision should be enhanced. e.g. ‘There is a general presumption against additional primary aggregate sites’ could be replaced with ‘Planning permission will not be granted for new aggregate sites’. Officer recommendations The policy should be reviewed to eliminate terms such as ‘there will be a general presumption against/in favour of..’. Policy 2 Preferred Spatial Strategy for Building, Roofing and Ornamental Stone for Cornwall South West Councils Comments Policy 2 Building, Roofing and Ornamental Stone for Cornwall Spatial Strategy Option 2 for Building, Roofing and Ornamental Stone in Cornwall is supported. With regard to building stone quarries we would only like to suggest liaising with Natural England and English Heritage to discuss the prospect of future working of sites, as required by MPS1. When planning for new sites the proximity principle should be taken into account, and travel distances minimised when materials are to be transported to the point of use. Concerning the use of aggregates extracted from building stone quarries, we agree that in some cases it might prove difficult to distinguish between a stone quarry and an aggregate quarry. However, MPS1 para. 3.13 needs to be taken into account to ensure that the nature of the operation is not changed into an aggregates quarry. Suggested amendments None.

    27

  • MPA considerations The support for Option 2 is welcomed. Natural England and English Heritage have been consulted about the Report on Preferred Options and will be consulted when a development proposal is made which affects an old building stone source to provide an opportunity for its significance to be assessed. The policy on sustainable transport of minerals should include provision for the minimisation of travel distances where local markets are being served. Policy 5 on the sustainable and efficient supply and use of minerals includes a section that important mineral resources of limited distribution should not be used for needs which can be met from more common mineral resources or from the recycling and re-use of materials or from secondary aggregates including china clay waste. Officer recommendations "and where possible, travel distances should be minimised where extraction is serving local markets" should be added to Policy 6 on the Sustainable Transport of Minerals. Paragraph 8.1.13 which deals with the use of waste rock at building, roofing and ornamental stone quarries for aggregates should cross refer to the policy on the sustainable and efficient supply and use of minerals. Policy 20 Development Management Policy: Ancillary and secondary development at a mineral extraction facility Aggregate Industries Comments Section 8.3.38 distinguishes between ancillary and secondary development, however it does not define the two operations sufficiently to eliminate any confusion. Ancillary is defined within the glossary yet secondary is not. In Cornwall secondary predominantly relates to secondary aggregates and this will lead to confusion. Section 8.3.39 tells us that secondary plant is required to manufacture a new product normally in conjunction with other materials. However, Section 8.3.38 tells us that plant such as asphalt and concrete blocks is ancillary yet these plants operate in conjunction with other materials. Plant, machinery and structures are for primary production of material, offices, weighbridges are associated infrastructure and equipment such as Asphalt plants, concrete batching plants and concrete block plants are added value plants. Suggested amendments Strike sections 8.3.38, 8.3.39 and 8.3.40 or define each activity to remove the confusion. MPA considerations Clarify and include appropriate definitions of ancillary and secondary development. Officer recommendations Retain the separate references to ancillary and secondary development within the Cornwall Minerals Development Framework Core

    28

  • Strategy/evidence base but seek to clarify further. Include definition of secondary development within the glossary. Reconsider the comments made/phrasing in the Sustainability Appraisal Summary which in making special references to the processing of secondary aggregates may have introduced some confusion. Aggregate Industries Comments Policy 20 is a reproduction of the GPDO 1995 and is therefore reproducing higher level national policy which is unnecessary. Suggested amendments Strike Policy 20. MPA considerations Disagree, not all ancillary or secondary development at or near a mineral extraction facility will fall within the terms of the General Permitted Development Order. In addition Policy 20 part i. seeks to avoid unrelated or loosely development of plant and structures at mineral extraction sites. Officer recommendations The principle of this policy should be retained within the Cornwall Minerals Development Framework Core Strategy. Aggregate Industries Comments Policy 20 i states the imported ratio of 2:3. Across other Counties in England the accepted percentage of imported material is 49%. If the ancillary plant is using 51% in situ material it falls within Parts 19 A or B of the GPDO 1995. Suggested amendments Strike policy 20 or amend the text to reflect the standard 51% in situ and 49% imported. MPA considerations The 2:3 ratio has been used in Cornwall and is considered to be appropriate to this County where the majority of mineral sites are reliant upon road haulage, often along narrow roads. It appropriate to seek to minimise the generation of heavy traffic to and from mineral sites. Officer recommendations The principle of this policy, and the reference to the 2:3 (imported:in situ) should be retained in the Cornwall Minerals Development Framework. Policy 22 Development Management Policy: Reclamation Natural England Comments

    29

  • Reclamation 8.3.42 p112 Object Advise that in addition to reflecting targets for the BAP and LCA, site reclamation should also address Cornwall Geodiversity Action Plan (GAP) targets (N.B. a National GAP is currently being produced) - see also comment below re SA. Suggested amendments None. MPA considerations Agreed. Officer recommendations "the Geodiversity Action Plan" should be added after "Biodiversity Action Plan" in paragraph 8.3.42. Policy 23 Development Management Policy: New applications to work aggregates within the Area of Outstanding Natural Beauty and World Heritage Site Cornwall AONB Partnership Comments Paragraph 8.3.45 - last line - the word "favourably should be deleted. Need further clarification if policy 23 is to be consistent with policy 1 - preferred spatial strategy for aggregates. This complies with the national policy, as outlined in para 8.1.6, that "major mineral developments should not be permitted in the AONB except in exceptional circumstances". Clause 1 should be considered in the context of this requirement, and in the context of its relationship with clause (iii). Suggested amendments None. MPA considerations Substitute "permitted" for "considered favourably" to avoid any doubt. There is not considered to be any inherent inconsistency between Policy 1 and Policy 23. Tensions between different policies or aspects of one policy may need to be balanced when determining planning applications. Officer recommendations Seek to combine Policies 1 and 23 with a view to clarifying the issues raised. Highways Agency Comments The Agency supports the need for all minerals development proposals to include a comprehensive assessment of potential impacts on the local and strategic highway network. Therefore it is important that policies 23 to 27 covering different types of mineral extraction and processing should include criteria to ensure that negative impacts on these networks are avoided.

    30

  • Suggested amendments None. MPA considerations Noted. The need for site-specific applications to include comprehensive assessments of the potential impacts on the local and strategic highway networks is critical and is fully accepted. However, this matter will be addressed elsewhere in the Cornwall Minerals Development Framework Core Strategy policies and in the "Design, Operation and Reclamation of Mineral Sites in Cornwall" Supplementary Planning Document. It is not necessary, therefore, to re-iterate the policy relating to the sustainable transport of minerals within other policies of the Cornwall Minerals Development Framework. (In relation to any proposed development, the Policies of the Development Framework, and complementary regional and national policies should be considered as a whole, where each policy must be balanced in the context of all other policies). Officer recommendations The need for minerals development proposals to include transport assessments, and where appropriate, travel plans, together with information about the criteria to avoid negative impacts on the networks, should be addressed elsewhere in the Cornwall Minerals Development Framework Core Strategy and in the "Design, Operation and Reclamation of Mineral Sites in Cornwall" Supplementary Planning Document. English Heritage Comments We welcome this policy. Suggested amendments None. MPA considerations The support is welcomed. Officer recommendations No changes are required in relation to this comment. Historic Environment Service, Environment and Heritage Comments We welcome the inclusion of DPM Policy 23 'New Applications within the area of Outstanding Beauty and World Heritage Site' Suggested amendments None MPA considerations The support for this policy is welcomed.

    31

  • Officer recommendations The principles of this policy should be retained within an amalgamated policy for aggregates. Government Office for the South West (GOSW) Comments Policy 23 These policies contain the wording 'where it can be demonstrated that'. The word 'where' should remain but the rest of the wording should be deleted. Suggested amendments None. MPA considerations It is accepted that "it is demonstrated that" should be removed from the policy, but additional text should be provided making it clear that the applicant should supply appropriate information within the impact assessment accompanying the application. Officer recommendations "It is demonstrated that" should be removed from part v. of the policy and text should be added to paragraph 8.3.45 to explain that applications in these circumstances should be accompanied by information to explain how the application and any mitigation measures meet the criteria of the policy. Policy 24 Development Management Policy: New aggregate quarries Highways Agency Comments The Agency supports the need for all minerals development proposals to include a comprehensive assessment of potential impacts on the local and strategic highway network. Therefore it is important that policies 23 to 27 covering different types of mineral extraction and processing should include criteria to ensure that negative impacts on these networks are avoided. Suggested amendments None. MPA considerations Noted. The need for site-specific applications to include comprehensive assessments of the potential impacts on the local and strategic highway networks is critical and is fully accepted. However, this matter will be addressed elsewhere in the Cornwall Minerals Development Framework Core Strategy policies and in the "Design, Operation and Reclamation of Mineral Sites in Cornwall" Supplementary Planning Document. It is not necessary, therefore, to re-iterate the policy relating to the sustainable transport of minerals within other policies of the Cornwall Minerals

    32

  • Development Framework. (In relation to any proposed development, the Policies of the Development Framework, and complementary regional and national policies should be considered as a whole, where each policy must be balanced in the context of all other policies). Officer recommendations The need for minerals development proposals to include transport assessments, and where appropriate, travel plans, together with information about the criteria to avoid negative impacts on the networks, should be addressed elsewhere in the Cornwall Minerals Development Framework Core Strategy and in the "Design, Operation and Reclamation of Mineral Sites in Cornwall" Supplementary Planning Document. Mr Langdon Comments If disturbance of bedrock is entailed it should on no account be permitted. Suggested amendments None. MPA considerations The comment is unreasonable, as this would mean that the mineral planning authority would be unable to secure adequate and steady supplies of aggregates to meet the needs of society and the economy, particularly for specialist aggregates which cannot be met through the use of recycled and secondary aggregates. Officer recommendations No change arising from Mr Langdon's suggestion. However, an amalgamated policy should be formulated which strengthens and gives greater prominence to the prudent, efficient and sustainable use and supply and minerals. Quarry Products Association Limited (now Mineral Products Association) Comments Policy 24 In Policy 24 no justification is given to why planning permission for quarrying aggregates will only be permitted in the circumstances listed. Suggested amendments None. MPA considerations A justification is given in paragraph 8.3.46 which is overleaf, on the previous page. Further clarification of the explanatory text will be undertaken, which should be located alongside the Policy in the Core Strategy. Officer recommendations

    33

  • The explanatory text such be clarified and located alongside the Policy in the Cornwall Minerals Development Framework Core Strategy. Policy 26 Development Management Policy: Working metals in the Area of Outstanding Natural Beauty/World Heritage Site Policy 4 Preferred Spatial Strategy for China Clay South West Councils Comments Policy 4 Preferred Spatial Strategy for China Clay Access to China Clay reserves should be safeguarded through policies in the Core Strategy. We agree that options for either dispersed or concentrated working of china clay would lead to unsustainable development and in case of the latter, to early exhaustion of reserves. In turn, Option 2 also provides the opportunity to ensure a continuous market supply of secondary aggregates, and making use of sustainable modes of transport. We therefore support this option in the light of draft RSS policies RE10 and RE12, and also welcome the preparation of the Mid Restormel Action Plan to maintain a co-ordinated approach to mineral and other forms of development. Suggested amendments None. MPA considerations The china clay industry has proposed an adapted Option 3 which is a concentrated pattern of multisized operations in the Hensbarrow Area. This is less restricted than the original Option 3 in the Revised Report on Preferred Options, and the MPA accepts this Option as it is based upon industry forecasts of markets and the industry investment programme. Officer recommendations A revised version of Option 3 with a concentrated pattern of multisized operations in the Hensbarrow Area should be accepted as the Preferred Option for the Core Strategy. Policy 5 Core Policy: Sustainable and efficient supply and use of minerals Kaolin and Ball Clay Association (UK) Comments Policy 5 Core Policy: Sustainable and efficient supply and use of minerals page 81 Unsound “tests 4B & 7 The Core Policy is not justifiable and lacks flexibility Comments In view of the different reasoning within the safeguarding options at Section 8.2, the policy should not qualify the nature of the minerals to be safeguarded, in the manner proposed. As presently drafted this Policy would not appear inclusive of some of the proposed safeguarded minerals, such as secondary aggregates and mica.

    34

  • This comment is also relevant to Core Policy 7, where it is repeated. The Association would suggest that i) is re-worded. In addition, for clarity and to be consistent with MPS1 reference should be made to ‘an adequate and steady supply to meet the needs of society and the economy.’ Suggested amendments Amend i) to read:- ‘safeguarding minerals of economic importance and where necessary, conserving scarce and important minerals as far as possible, whilst ensuring an adequate and steady supply to meet the needs of society and the economy,’ The proposed change would make the policy consistent with national policy and effective. MPA considerations The proposed change enhances Policy 5 and is acceptable in principle. Officer recommendations Incorporate the suggested change in the Cornwall Minerals Development Framework Core Strategy with the exception of retaining the word appropriate: (“safeguarding minerals of economic importance and where appropriate, conserving scarce and important minerals as far as possible, whilst ensuring an adequate and steady supply to meet the needs of society and the economy, The proposed change would make the policy consistent with national policy and effective"). Goonvean Ltd Comments Policy 5 Core Policy: Sustainable and efficient supply and use of minerals page 81 Unsound - tests 4B & 7 The Core Policy is not justifiable and lacks flexibility In view of the different reasoning with the safeguarding options at Section 8.2, the policy should avoid qualifying the nature of the minerals to be safeguarded. As presently drafted this Policy would not appear inclusive of some of the proposed safeguarded minerals, such as secondary aggregates and mica. Goonvean Ltd would suggest that i) is re-worded. In addition, for clarity and to be consistent with MPS1 reference should be made to 'an adequate and steady supply to meet the needs of society and the economy'. Suggested amendments Amend i) to read:- ''safeguarding minerals of economic importance and where necessary, conserving scarce and important minerals as far as possible, whilst ensuring an adequate and steady supply to meet the needs of society and the economy''. MPA considerations The proposed change enhances Policy 5 and is acceptable in principle. Officer recommendations Incorporate the suggested change in the Cornwall Minerals Development Framework Core Strategy with the exception of retaining the word appropriate (''safeguarding minerals of economic importance and where appropriate, conserving scarce and important minerals as far as possible,

    35

  • whilst ensuring an adequate and steady supply to meet the needs of society and the economy''). Highways Agency Comments The Agency supports in principle the encouragement of recycling and re-use of secondary aggregates as it has the potential to reduce transportation of minerals within Cornwall and thereby alleviate pressure on the SRN. However, there are issues regarding transportation of secondary aggregates around the County and to other destinations to be considered in terms of impacts on the SRN. We therefore urge the Council to include guidance within this policy regarding the promotion of sustainable transportation of minerals and secondary aggregates. Suggested amendments Noted. MPA considerations In relation to any proposed development, the Policies of the Development Framework, and complementary regional and national policies should be considered as a whole, where each policy must be balanced in the context of all other policies. It is not necessary, therefore, to re-iterate the policy relating to the sustainable transport of minerals within other policies of the Cornwall Minerals Development Framework. Officer recommendations No change should be made to the policy in respect of this comment, although the complementary nature of the Policies of the Cornwall Minerals Development Framework, national and regional policies should be clearly explained in the Core Strategy and related evidence base. Policy 7 Core Policy: Safeguarding Kaolin and Ball Clay Association (UK) Comments Mineral Safeguarding Areas page 85 Unsound “tests 7 & 9 The proposal is unjustified and lacks flexibility Comments The reference only to MSAs including china clay resources that may warrant future working reinforces our concern as to the intentions in respect of identifying MSAs. It would seem to suggest that existing workings may be excluded, although the options for safeguarding refer to the BGS map. The wording of the first bullet point should be amended to include existing workings and a criterion of quality, to those areas to be included in MSAs. The fifth bullet point should be amended to give flexibility to the identification of mica dams for any safeguarding provision. Suggested amendments The first bullet point to read: ‘Existing china clay workings and china clay resources which are of sufficient size and quality to warrant, potentially, future working and in a location reasonable well linked to transport

    36

  • infrastructure.’ Fifth bullet point to read: ‘Potential reserves of secondary aggregates and some micaceous residue dams.....’ The proposed changes would make the reasoning justified and effective. MPA considerations The term resources was intended to include permitted reserves as well as other resources. Accept the points made by the Kaolin and Ball Clay Association. Officer recommendations The suggested changes such be incorporated in principle in the Cornwall Minerals Development Framework Core Strategy and related evidence base. Goonvean Ltd Comments Policy 7 Core Policy: Safeguarding page 84 Unsound - tests 4B, 7 & 8 The policy is inflexible and not the most appropriate policy in the light of the safeguarding options. In view of the different reasoning within the safeguarding options at Section 8.2, the policy should avoid qualifying the nature of the minerals to be safeguarded. As presently drafted this Policy is not, arguably, inclusive of some of the proposed safeguarded minerals, such as secondary aggregates or mica dams, which are not scarce. It relies heavily on the interpretation of 'scarce and important'. Metalliferous minerals, for instance, are stated at paragraph 8.2.43 as 'not scarce nationally'; paragraph 8.1.5 states that aggregates are 'generally not scarce' and paragraph 8.2.16 states that china clay waste is not considered a scarce resource' when considering secondary aggregates. The options may, therefore, become superfluous if the policy is used to guide the minerals to be included in Mineral Safeguarding Areas. A more positive note needs to be given to avoiding potentially conflicting uses, within and in the proximity to Mineral Safeguarding Areas (MSA) and existing permitted sites. We assume that the preference to 'existing permitted sites' is only necessary because there will be some existing mineral operations that will not benefit from a MSA. Suggested amendments Core Policy: Safeguarding "The Mineral Planning Authority will safeguard mineral deposits of economic importance and infrastructure through the identification of Mineral Safeguarding Areas. The Mineral Planning Authority will seek to avoid potentially conflicting uses, within and in the proximity of Mineral Safeguarding Areas and/or existing permitted mineral sites''. MPA considerations The points made are broadly accepted, although reference to existing permitted sites should not be necessary, as any permitted sites considered to be of economic importance should already be included as Mineral Safeguarding Areas. Officer recommendations

    37

  • The Cornwall Minerals Development Framework should include a Safeguarding Policy which is revised along the lines suggested. Goonvean Ltd Comments Mineral Safeguarding Areas: Page 85 Unsound Tests 7 & 9 The reference only to MSAs including China clay resources that may warrant future working reinforces our concern as to the intentions in respect of identifying MSA's. It would seem to suggest that existing workings may be excluded. Goonvean Ltd suggests that the wording of the first bullet point should be amended to include existing workings and a criterion of quality, to those areas to be included in Mineral Safeguarding Areas. The fifth bullet point should be amended to give flexibility to the identification of mica dams for any safeguarding provision. Suggested amendments The first bullet point to read: Existing china clay workings and china clay resources which are of sufficient size and quality to warrant, potentially, future working and in a location reasonable well linked to transport infrastructure.’’ Fifth bullet point to read: “Potential reserves of secondary aggregates and some micaceous residue dams....” MPA considerations The term resources was intended to include permitted reserves as well as other resources. Accept the points made by Goonvean Ltd. Officer recommendations The suggested changes such be incorporated in principle in the Cornwall Minerals Development Framework Core Strategy and related evidence base. Quarry Products Association Limited (now Mineral Products Association) Comments Policy 7 Mineral safeguarding Minerals resources should be safeguarded by defining Mineral Safeguarding Areas (MSA's). However 'infrastructure' associated with minerals development should be safeguarded by defining Mineral Consultation Areas (MCA's) Resources which may be of economic importance in the future should be safeguarded, not just scarce and important resources. For those reasons this policy is not in accordance with national policy (MPS1), Para. 13) and therefore fails soundness test 4. Suggested amendments None. MPA considerations The position regarding the safeguarding of infrastructure serving the minerals industry, such as existing, planned and potential wharves,

    38

  • railway sidings and associated land and facilities, as well as existing planned and potential sites including rail and water served, for concrete batching, the manufacture of coated materials, other concrete products etc. is unclear. Whilst Mineral Planning Statement 1: Planning and Minerals indicates that they should be safeguarded, it is noted that the British Geological Survey "guide to mineral safeguarding in England" states that "Mineral Safeguarding Areas are only to be defined to protect the resource itself." (p 11 paragraph 5 is reproduced here in full "MCAs also give an additional measure of safeguarding to sites related to mineral infrastructure, such as wharves and railway sidings, that cannot be protected by MSAs. MSAs are only to be defined to protect the resource itself. Appropriate safeguarding policies should appear in the DPDs of MPAs, and can be reflected in those produced by district councils. MCAs can be updated more easily than MSAs as their statutory basis is outside that of the development framework. The can therefore be more responsive to the latest information on geology. "Cornwall Council, as unitary authority, is not eligible for the use of statutory Mineral Consultation Areas. However, the principles of consultations with the Natural Resources Team by the area development management teams on minerals policy issues in mineral consultation areas will continue on an informal basis. It is therefore proposed to introduce, together with associated policy to ensure a satisfactory level of safeguarding. Officer recommendations A new designation of Minerals Infrastructure Safeguarding Areas and associated policy should be introduced to ensure that infrastructure serving the minerals industry, such as existing, planned and potential wharves, railway sidings and associated land and facilities, as well as existing planned and potential sites including rail and water served, for concrete batching, the manufacture of coated materials, other concrete products and the handling, processing and distribution of substitute, recycled and secondary aggregate material. Table 6.1a Issues, Problems and Challenges to be considered in developing the Core Strategy for Minerals in Cornwall CPR Regeneration Comments Table 6.1a: Issues Problems and Challenges to be considered. Issues and challenges: the conflict with regeneration objectives is not identified as an issue; neither are the challenges relating to the need to balance economic, environmental and social regeneration benefits with the need to safeguard minerals from sterilisation. Problems: Bullet Points 1 and 4 - A 'Mineral Resource' is generally regarded as a concentration or occurrence of material of intrinsic economic interest in or on the Earth's crust in such form, quality and quantity that there are reasonable prospects for eventual economic extraction. The term 'reasonable prospects for eventual economic extraction' implies a judgment (albeit preliminary) by a Competent Person or Authority in respect of the technical and economic factors likely to influence the prospect of economic extraction, including the approximate mining parameters. In other words, a Mineral Resource

    39

  • is not an inventory of mineralisation which, under assumed and justifiable technical and economic conditions, might, in whole or in part, become economically extractable The above representations relate to compliance with legal requirements (preparation in accordance generally with the Regional Spatial Strategy. 'Justified' test - need to ensure the most appropriate strategy when considered against the reasonable alternatives. Paragraph 6.03 A Summary of the challenges for mineral planning in Cornwall and paragraph 6.05 list of strategies - see above representations regarding the need to identify further challenges. Challenges Bullet points 1 and 4 The word 'appropriate' is insufficiently well defined. Regional policy requires that MPA'S should seek to make provision for the supply of aggregate and other minerals to meet the South West's contribution to national requirements. MPA'S and LPAs will identify and collaborate in safeguarding mineral resources of economic importance from sterilisation by other forms of development'. The test for 'appropriate' in this case would suggest that the level of supply should be sufficient to meet the South West's contribution to demand in the case of aggregates and that only those mineral resources of economic importance are safeguarded. What criteria are to be used for the determination of appropriateness? Suggested amendments Insert Issues: Mineral Extraction may present conflict with the objectives of economic, environmental and social regeneration objectives. Problems: Uncertainty over development of new mining proposals and safeguarding of existing resources may sterilise regeneration options discouraging investment and the promotion of a strong and sustainable economy. Challenges: To ensure that mineral resources have been adequately, objectively and professionally assessed in terms of location, continuity, mining dimension and prospects for economic recovery and to establish clear criteria to ensure that the most appropriate minerals are safeguarded from sterilisation. To establish clear criteria upon which judgments can be made weighing proposals against the reasonable alternatives and varied interests arising in relation to the objectives of economic, environmental and social regeneration. To determine the need for metalliferous minerals and to resolve conflicting issues in a reasonable timescale which does not sterilise land for other beneficial uses. Add: Para 6.03 No 6 'against other varied interests and the benefits of regeneration objectives are balanced against the need to safeguard mineral resources. Amend Paragraph 6.05 Camborne Pool Redruth Regeneration objectives as set out in masterplans and technical strategies. The above representations relate to compliance with legal requirements (preparation in accordance generally with the Regional Spatial Strategy) (RSS) and sustainable community strategy. 'Justified' test - need to ensure the most appropriate strategy when considered against the reasonable alternatives. MPA considerations Accept amendments to Issues Problems and Challenges which should be inserted in Table 6.1e, addition to paragraph 6.03 6# and paragraph 6.05. Officer recommendations

    40

  • The proposed amendments should be incorporated within the evidence base for the Cornwall Minerals Development Framework Core Strategy. Table 6.1d Issues, Problems and Challenges to be considered in developing the Core Strategy for Minerals in Cornwall Imerys Minerals Ltd Comments Table 6.1d - Issues, Problems and Challenges Issues, Problems and Challenges to be considered in developing the Core Strategy for Minerals in Cornwall - Cornwall: transport states, ''The ports of Fowey and Par are important strategic ports of the export of china clay and secondary aggregate''. This should read ''Fowey is now the principal strategic port of the export of china clay and secondary aggregate''. Similarly, within the same table, under Problems' the statement, ''The ports of Fowey and Par face increasing pressure from other development.’’ Reference to Fowey should be deleted as such pressures are not apparent to Imerys. With regard to Par ''pressure from other development'' may be viewed as being an opportunity to assist in safeguarding a commercial wharf use through associated investment. Suggested amendments None. MPA considerations The suggested amendments to 6.1d are acceptable. The opportunity for other development to assist in safeguarding a commercial wharf use at the Port of Par through associated investment should be fully considered in the analysis of safeguarding. Officer recommendations The suggested amendments should be incorporated in Table 6.1d. Table 8.1 Kaolin and Ball Clay Association (UK) Comments Preferred Spatial Strategy for Aggregates in Cornwall Section 8.1: Spatial Strategy - Table 8.1; Option 3; page 44 Comments The Association finds the Preferred Option as sound and supports Option 3. Suggested amendments None. MPA considerations KaBCA's support for Option 3 is noted. Officer recommendations The Preferred Option for the Spatial Strategy for Aggregates should be incorporated within the Cornwall Minerals Development Framework.

    41

  • Goonvean Ltd Comments Goonvean Ltd finds the Preferred Option as sound and supports Option 3. Suggested amendments None. MPA considerations The support of Goonvean Ltd is welcomed. Officer recommendations The Preferred Option for the Spatial Strategy for Aggregates should be incorporated within the Cornwall Minerals Development Framework. CPR Regeneration Comments Option 3 is generally supported as providing the greatest potential benefit to the cou