+ All Categories
Home > Documents > Akron Children’s Hospital 2015 Gerry Haggerty Annual ......– Lean Design Principles Allowed...

Akron Children’s Hospital 2015 Gerry Haggerty Annual ......– Lean Design Principles Allowed...

Date post: 14-Jul-2020
Category:
Upload: others
View: 3 times
Download: 0 times
Share this document with a friend
49
Akron Children’s Hospital 2015 Gerry Haggerty Annual Leadership Institute The Power of Lean Construction Methodologies NEO HFMA Friday, May 15, 2015
Transcript
Page 1: Akron Children’s Hospital 2015 Gerry Haggerty Annual ......– Lean Design Principles Allowed Reduction in Service Line Build-outs by 34,000 SF or $12.2M – Reduction in Construction

Akron Children’s Hospital

2015 Gerry Haggerty Annual Leadership Institute

The Power of Lean Construction Methodologies

NEO HFMA

Friday, May 15, 2015

Page 2: Akron Children’s Hospital 2015 Gerry Haggerty Annual ......– Lean Design Principles Allowed Reduction in Service Line Build-outs by 34,000 SF or $12.2M – Reduction in Construction

2

AgendaMinutes Speaker

10 IntroductionDon Taylor, Welty

14Describe how lean techniques can be used in

healthcare construction projects to drive down costs

Sheryl Valentine,

ACH

15 Describe the Integrated Project Delivery modelTim Ziga, ACH

6 Implications on financing the project

Michael Trainer

Alicia

LaMancusa, ACH

10 The Contractor’s Point of ViewDon Taylor, Welty

5 Questions

Page 3: Akron Children’s Hospital 2015 Gerry Haggerty Annual ......– Lean Design Principles Allowed Reduction in Service Line Build-outs by 34,000 SF or $12.2M – Reduction in Construction

3

Integrated Project Delivery:

A contracting method that removes

traditional barriers to collaboration, by

forming durable partnerships, with a shared

profit amongst those partners, thereby

aligning the interests of all partners

Page 4: Akron Children’s Hospital 2015 Gerry Haggerty Annual ......– Lean Design Principles Allowed Reduction in Service Line Build-outs by 34,000 SF or $12.2M – Reduction in Construction

4

– Lean Design Principles Allowed Reduction in Service Line Build-outs by

34,000 SF or $12.2M

– Reduction in Construction Costs of $45M

• “Comparable Facility” Control Estimate : $160M

• TVM Budget : $115M

– Reduction in Overall Construction Schedule of 2 Months

• 24 Months to 22 Months in spite of 37.5 weather day delays

– Fully funded Incentive Compensation Layer of $5.2M

• Shared Amongst Owner, A/E, CM, Trade Partners

– Fully Funded Owner Profit Payment of $1M

Overall Results at Akron Children’s

Hospital

Page 5: Akron Children’s Hospital 2015 Gerry Haggerty Annual ......– Lean Design Principles Allowed Reduction in Service Line Build-outs by 34,000 SF or $12.2M – Reduction in Construction

5

Welty Building Company

• 1945 Henry D. Welty Co. is established – serving for

70 years strong

• 4 offices – Akron, Cleveland, Columbus, Houston

• Services offerings include Construction Management,

Lean, IPD, Design-Build, General Contracting, Facilities

Management

• Two subsidiaries: environments 4 business, inSITE

Advisory Group

Page 6: Akron Children’s Hospital 2015 Gerry Haggerty Annual ......– Lean Design Principles Allowed Reduction in Service Line Build-outs by 34,000 SF or $12.2M – Reduction in Construction

6

Akron Children’s Hospital

Kay Jewelers Pavilion

366,000 SF New Construction

$180M Target Cost

Delivery Method : Integrated Lean Project Delivery

Includes:• A 100-bed neonatal intensive care unit with private rooms for each of our tiniest

patients and their parents. The current Level III NICU is nationally ranked but has

outgrown its space.

• High-risk delivery area that includes labor, delivery and recovery rooms to keep at-risk

newborns close to the high-tech care they need.

• An emergency department with enough room to meet our current and future patient

volumes. Annual ER visits of more than 60,000 to the Akron campus strain the hospital’s

resources in a facility built to accommodate 44,000.

• A new outpatient surgery center designed to accommodate a more than doubling of

outpatient procedures in the past 20 years.

• An enclosed concourse that takes patients and staff from the new 1,250-space parking

garage to the new building and beyond into the existing hospital

Page 7: Akron Children’s Hospital 2015 Gerry Haggerty Annual ......– Lean Design Principles Allowed Reduction in Service Line Build-outs by 34,000 SF or $12.2M – Reduction in Construction

About Akron Children’s Hospital

Awards and RecognitionsRanked a Best Children’s Hospital by US News & WR

8th largest children’s hospital in the country*

Magnet Recognition for Nurse Excellence

Health Care’s Most Wired Hospital Award

Largest Pediatric Provider in Northeast Ohio2 hospital campuses

25+ primary care locations

80+ specialty locations

Nearly 5,200 employees

800+ medical staff with over 380 of them employed

Page 8: Akron Children’s Hospital 2015 Gerry Haggerty Annual ......– Lean Design Principles Allowed Reduction in Service Line Build-outs by 34,000 SF or $12.2M – Reduction in Construction

8

Page 9: Akron Children’s Hospital 2015 Gerry Haggerty Annual ......– Lean Design Principles Allowed Reduction in Service Line Build-outs by 34,000 SF or $12.2M – Reduction in Construction

Our Goal • An outpatient surgery center

• NICU with single patient rooms

• New Emergency Department

• Special Delivery Unit

Page 10: Akron Children’s Hospital 2015 Gerry Haggerty Annual ......– Lean Design Principles Allowed Reduction in Service Line Build-outs by 34,000 SF or $12.2M – Reduction in Construction

10

Page 11: Akron Children’s Hospital 2015 Gerry Haggerty Annual ......– Lean Design Principles Allowed Reduction in Service Line Build-outs by 34,000 SF or $12.2M – Reduction in Construction

11

Page 12: Akron Children’s Hospital 2015 Gerry Haggerty Annual ......– Lean Design Principles Allowed Reduction in Service Line Build-outs by 34,000 SF or $12.2M – Reduction in Construction

12

Page 13: Akron Children’s Hospital 2015 Gerry Haggerty Annual ......– Lean Design Principles Allowed Reduction in Service Line Build-outs by 34,000 SF or $12.2M – Reduction in Construction

13

Page 14: Akron Children’s Hospital 2015 Gerry Haggerty Annual ......– Lean Design Principles Allowed Reduction in Service Line Build-outs by 34,000 SF or $12.2M – Reduction in Construction

14

Page 15: Akron Children’s Hospital 2015 Gerry Haggerty Annual ......– Lean Design Principles Allowed Reduction in Service Line Build-outs by 34,000 SF or $12.2M – Reduction in Construction

What does our staff think about this

process?

Video here of Milo and Farid

Page 16: Akron Children’s Hospital 2015 Gerry Haggerty Annual ......– Lean Design Principles Allowed Reduction in Service Line Build-outs by 34,000 SF or $12.2M – Reduction in Construction

16

Page 17: Akron Children’s Hospital 2015 Gerry Haggerty Annual ......– Lean Design Principles Allowed Reduction in Service Line Build-outs by 34,000 SF or $12.2M – Reduction in Construction

5-Party Agreement

Owner

Children’s Hospital Medical Center of

Akron(Akron Children’s Hospital)

Architectural Team Construction Management

Team

Hasenstab Architects, Inc

Akron, OH

HKS, Inc.

Dallas, TX

Welty Building Company,

LTD, Akron, OH

The Boldt Company

Appleton, WI

17

Page 18: Akron Children’s Hospital 2015 Gerry Haggerty Annual ......– Lean Design Principles Allowed Reduction in Service Line Build-outs by 34,000 SF or $12.2M – Reduction in Construction

• Party commits to becoming a member of the IPD Team

• Party agrees to be bound by the contract documents

• Party agrees to participate fully and openly in all IPD Team

functions

• Party agrees to participate in the risk sharing and incentive

compensation plan if invited

• Party agrees to abide by determinations made by PLT

• Party agrees to adhere to the principles of collaboration based

on mutual trust, confidence, good faith and fair dealing

• Party agrees to utilize lean project principles and methods

Joining Agreements

18

Page 19: Akron Children’s Hospital 2015 Gerry Haggerty Annual ......– Lean Design Principles Allowed Reduction in Service Line Build-outs by 34,000 SF or $12.2M – Reduction in Construction

• SET - Senior Executive Team

ACH, Welty, Boldt, HAI, HKS

• PLT - Project Leadership Team

ACH, Welty, Boldt, HAI, HKS, KLMK

• PIT - Project Implementation/Innovation

Teams

Architects, Designers, Engineers, Trade-Partners

Project Leadership

19

Page 20: Akron Children’s Hospital 2015 Gerry Haggerty Annual ......– Lean Design Principles Allowed Reduction in Service Line Build-outs by 34,000 SF or $12.2M – Reduction in Construction

• Waive liability and claims against each other

• Indemnify each other against a limited number

of acts or omissions

• Have profit for Project fixed

• Place 100% of profit at risk

• Participate in the Incentive Compensation Plan,

if invited

• Are covered by a Project specific insurance

program

• Agree to a binding dispute resolution process

All IPD Team Members

20

Page 21: Akron Children’s Hospital 2015 Gerry Haggerty Annual ......– Lean Design Principles Allowed Reduction in Service Line Build-outs by 34,000 SF or $12.2M – Reduction in Construction

• Reimbursable Costs → Owner’s right to audit

• Project Contingency → Shared pool of funds

• Project Profit → Fixed and tied to Target Cost

Three Main Components

of the Project’s Target Cost

21

Page 22: Akron Children’s Hospital 2015 Gerry Haggerty Annual ......– Lean Design Principles Allowed Reduction in Service Line Build-outs by 34,000 SF or $12.2M – Reduction in Construction

[Expected Profit] x 1.5 = [Potential Reward]

e.g. $66.67 x 1.5 = $100.00

Potential Reward = Profit-at-Risk (60%) + Incentive

Compensation (40%)

e.g. $100.00 Potential Reward = $60.00 Profit-at-Risk +

$40.00 Incentive Compensation

Incentive Compensation Plan

Calculating Reward Components

22

Page 23: Akron Children’s Hospital 2015 Gerry Haggerty Annual ......– Lean Design Principles Allowed Reduction in Service Line Build-outs by 34,000 SF or $12.2M – Reduction in Construction

23

1. Safety2. Local Participation3. Energy Efficiency4. Team Performance5. Schedule6. Quality7. LEED8. Staff and Family

Satisfaction

Maximum points are 100.

Project Success Matrix

Page 24: Akron Children’s Hospital 2015 Gerry Haggerty Annual ......– Lean Design Principles Allowed Reduction in Service Line Build-outs by 34,000 SF or $12.2M – Reduction in Construction

Allocation of Savings

Incentive

Compensation

Component

Owner

$2,000,000 or less 50% 50%

More than $2,000,000 but

less than or equal to

$7,500,000

100% 0%

More than $7,500,000 10% 90%

If the total Reimbursable Costs plus the total Profit-at-Risk component

(the “Actual cost”) is less than the Target Cost, then a part of that

difference between the Target cost and the Actual cost (the “Savings”)

shall be used to fund the Incentive Compensation component of the

Project provided for in Section 8 of the IALPD. The Savings will be

allocated between the Owner and the Incentive Compensation component

as follows:

TABLE 1

Incentive Compensation Component

24

Page 25: Akron Children’s Hospital 2015 Gerry Haggerty Annual ......– Lean Design Principles Allowed Reduction in Service Line Build-outs by 34,000 SF or $12.2M – Reduction in Construction

Target Cost$180,000,000

Profit @ Risk$9,000,000

Contingency Pool$10,000,000

Reimbursable Costs Approx

$160,000,000

Incentive CompensationProfit @ Risk = $1,000,000

+Preserved Contingency

Total Profit

$10,000,000

25

Page 26: Akron Children’s Hospital 2015 Gerry Haggerty Annual ......– Lean Design Principles Allowed Reduction in Service Line Build-outs by 34,000 SF or $12.2M – Reduction in Construction

Target Cost$180,000,000

Profit @ Risk$9,000,000

Reimbursable Costs

$170,000,000

Incentive Compensation

$1,000,000

Scenario 1: Actual Cost equals

Target Cost

Incentive Compensation

Up to $2,000,000 – 50/50

$500,000 to Owner

$500,000 to Team

26

Page 27: Akron Children’s Hospital 2015 Gerry Haggerty Annual ......– Lean Design Principles Allowed Reduction in Service Line Build-outs by 34,000 SF or $12.2M – Reduction in Construction

Target Cost$180,000,000

Profit @ Risk$9,000,000

Reimbursable Costs

$162,500,000

Incentive Compensation

$8,500,000

Scenario 2: Actual Cost Below

Target Cost

Actual Cost = $171,500,000

Incentive Compensation up to

$2,000,000

• ACH 50% - $1,000,000

• Team 50% - $1,000,000

$2,000,000 to $7,500,000

• 100% to Team -- $5,500,000

Above $7,500,000

• ACH 90% - $900,000

• Team 10% - $100,000*All Incentive Compensation subject to meeting

Measures of Success

27

Page 28: Akron Children’s Hospital 2015 Gerry Haggerty Annual ......– Lean Design Principles Allowed Reduction in Service Line Build-outs by 34,000 SF or $12.2M – Reduction in Construction

Reimbursable Costs

$195,000,000

Scenario 3: Actual Cost Exceeds Target Cost

Actual Cost $195,000,000

-----------------------

•Owner Pays all Reimbursable Costs•All contingency used•No Profit-at-Risk Paid

- ICL Participants return any Milestone Distributions paid out by owner

•No Incentive Compensation Paid

ProfitIncentive

Compensation- 0 -

28

Target Cost$180,000,000

Page 29: Akron Children’s Hospital 2015 Gerry Haggerty Annual ......– Lean Design Principles Allowed Reduction in Service Line Build-outs by 34,000 SF or $12.2M – Reduction in Construction

29

Financing the Project

Prepared Children’s forecast of the

financial statements to see what can be

paid from equity versus financing

Determined our debt

capacity and implications

on our bond ratings

Engaged an experienced bond

underwriter and convince them of this

style of construction and develop the

timeline for selling the bonds

Page 30: Akron Children’s Hospital 2015 Gerry Haggerty Annual ......– Lean Design Principles Allowed Reduction in Service Line Build-outs by 34,000 SF or $12.2M – Reduction in Construction

30

Financing the Project Continued

Engaged the remainder of the bond

team

Obtained the approvals from the

Board of Directors/Committees

as necessary

Had weekly status calls

Page 31: Akron Children’s Hospital 2015 Gerry Haggerty Annual ......– Lean Design Principles Allowed Reduction in Service Line Build-outs by 34,000 SF or $12.2M – Reduction in Construction

31

Scheduled visits to our facility for rating

agencies

Monitored progress and watched

the markets

Sold the bonds

Financing the Project Continued

Page 32: Akron Children’s Hospital 2015 Gerry Haggerty Annual ......– Lean Design Principles Allowed Reduction in Service Line Build-outs by 34,000 SF or $12.2M – Reduction in Construction

Developed process for

reimbursement of invoices and

document retention

Closed out the project when asset is ready for

use and placed in service

32

Financing the Project Continued

Page 33: Akron Children’s Hospital 2015 Gerry Haggerty Annual ......– Lean Design Principles Allowed Reduction in Service Line Build-outs by 34,000 SF or $12.2M – Reduction in Construction

33

Our Industry Has A

Problem:

– Construction Costs

are Consistently

Rising

– This is a Major

Concern for Our

CustomersAnd Not All of This is Material Cost,

Which We Don’t Control…

Construction Labor-Force

Productivity is Decreasing

(Becoming Less Efficient) Data Courtesy of Bureau

of Labor & Statistics

Page 34: Akron Children’s Hospital 2015 Gerry Haggerty Annual ......– Lean Design Principles Allowed Reduction in Service Line Build-outs by 34,000 SF or $12.2M – Reduction in Construction

34

A Comprehensive Study of Hundreds of Projects

Nationwide Showed that Only 40% Of the Average

Construction Worker’s Day Was Value Added :

Lean Construction Institute

Page 35: Akron Children’s Hospital 2015 Gerry Haggerty Annual ......– Lean Design Principles Allowed Reduction in Service Line Build-outs by 34,000 SF or $12.2M – Reduction in Construction

35

There are 8 WASTES.

Once you know them, you’ll see them everywhere:

Defects - Do it right the first time

Overproduction - Make what you need...nothing more

Waiting - Create flow to eliminate waiting

Not Utilizing Human Resources - Use everyone’s talents To Their Fullest

Transportation – Minimize the amount and distance you and material travel

Inventory - Only stock what you need. Just in time deliveries.

Motion - Have what you need at your side

Excess Processing - Only do what is required...nothing more

Page 36: Akron Children’s Hospital 2015 Gerry Haggerty Annual ......– Lean Design Principles Allowed Reduction in Service Line Build-outs by 34,000 SF or $12.2M – Reduction in Construction

36

Productivity

Preserved

Contingency

Innovation

Lean Success

Page 37: Akron Children’s Hospital 2015 Gerry Haggerty Annual ......– Lean Design Principles Allowed Reduction in Service Line Build-outs by 34,000 SF or $12.2M – Reduction in Construction

37

Challenge Statement: At the onset of the project, the

structure team was challenged to reduce structure duration.

The team indicated that form tower placement was the

longest duration activity, and was moving as fast as the

crane allowed.

CASE STUDY: CONCRETE CYCLE

Page 38: Akron Children’s Hospital 2015 Gerry Haggerty Annual ......– Lean Design Principles Allowed Reduction in Service Line Build-outs by 34,000 SF or $12.2M – Reduction in Construction

38

Step 1: Game Tape Analysis

Our team utilized 2 GoPro cameras positioned at 2 locations to observe

the operation over a period of 4 hours.

It was observed that there were two unique operations:

1- Strip Tower and Prepare for Flying (On Lower Level)

2- Receive Tower and Set in Place (On Upper Level)

CASE STUDY: CONCRETE CYCLE

Page 39: Akron Children’s Hospital 2015 Gerry Haggerty Annual ......– Lean Design Principles Allowed Reduction in Service Line Build-outs by 34,000 SF or $12.2M – Reduction in Construction

39

Step 2: Workstream Mapping

A Field Engineer charted the operations of both operations to

establish a baseline, and to identify opportunities.

It was noted that the make-ready operation took much longer than

the placing operation (Waiting waste) and was highly variable.

CASE STUDY: CONCRETE CYCLE

Page 40: Akron Children’s Hospital 2015 Gerry Haggerty Annual ......– Lean Design Principles Allowed Reduction in Service Line Build-outs by 34,000 SF or $12.2M – Reduction in Construction

40

Step 3: Tradesman Kaizen

The shoring crew was brought in

for a lunch/review session. They

observed their work and brought

up several potential

improvements, especially to the

make-ready operation, and

suggestions that would improve

the consistency and safety of the

rigging operation. A revised

standard work was developed.

CASE STUDY: CONCRETE CYCLE

Page 41: Akron Children’s Hospital 2015 Gerry Haggerty Annual ......– Lean Design Principles Allowed Reduction in Service Line Build-outs by 34,000 SF or $12.2M – Reduction in Construction

41

Step 4: Check

1 Week Later, the

gametape analysis was

repeated after the

improvements had been

implemented.

While the safety

improvement to the rigging

step added on average 2.5

minutes to the operation,

other improvements

reduced time.

CASE STUDY: CONCRETE CYCLE

Page 42: Akron Children’s Hospital 2015 Gerry Haggerty Annual ......– Lean Design Principles Allowed Reduction in Service Line Build-outs by 34,000 SF or $12.2M – Reduction in Construction

42

Step 5: Sustain

The End result was a net

reduction of 2 minutes per

average crew cycle, a 15%

improvement.

This standard work was

sustained and improved

several more times.

CASE STUDY: CONCRETE CYCLE

Page 43: Akron Children’s Hospital 2015 Gerry Haggerty Annual ......– Lean Design Principles Allowed Reduction in Service Line Build-outs by 34,000 SF or $12.2M – Reduction in Construction

43

Results:

2 Minutes May not Sound Like a Big Improvement, but:

There are 1,440 Tower placements for every slab

X 6 Elevated decks completed after this study

= 8,640 cycles

X 2 minutes improved per cycle

= 288 Crew Hours or 36 Work Days

For this 6 person crew, that’s $95,000 in savings

PLUS

Schedule reductions and General Conditions Savings

CASE STUDY: CONCRETE CYCLE

Page 44: Akron Children’s Hospital 2015 Gerry Haggerty Annual ......– Lean Design Principles Allowed Reduction in Service Line Build-outs by 34,000 SF or $12.2M – Reduction in Construction

44

Other Tools

There are many other tools that we

implement to reduce waste, including:

– Target Value Design

– Built In Quality

– TAKT Planning

– Small Wins Program

–Innovation Teams

–Last Planner System

–Lean Delivery Rules

–Safety Awareness

Program

Page 45: Akron Children’s Hospital 2015 Gerry Haggerty Annual ......– Lean Design Principles Allowed Reduction in Service Line Build-outs by 34,000 SF or $12.2M – Reduction in Construction

45

IPD Success: Root Cause Analysis

People Ask Us What Allowed Our Team To Be Successful:

1. Visionary Owner Organization That Demands Better

Outcomes; Embraces Innovation

2. Design Firm With Leadership and Personnel that Can Work

Outside Their “Comfort Zone”; Put Owner’s Vision Before

Theirs

3. Construction Manager That Is Willing to Truly Invest In

Planning; Is Flexible; Can “Control With” (Vs. Control Over)

4. An Understanding From All Of These Parties That In Order

For the Project to Be Successful, ALL Parties must be

successful, and There is No Place for Blame on a High-

Performing Team

Page 46: Akron Children’s Hospital 2015 Gerry Haggerty Annual ......– Lean Design Principles Allowed Reduction in Service Line Build-outs by 34,000 SF or $12.2M – Reduction in Construction

46

To receive a copy of the

book compiled by the

ACH Kay Jewelers

Pavilion team, please

give your business card

to Don Taylor after the

session, or email him at

[email protected]

Page 47: Akron Children’s Hospital 2015 Gerry Haggerty Annual ......– Lean Design Principles Allowed Reduction in Service Line Build-outs by 34,000 SF or $12.2M – Reduction in Construction

47

Questions

Page 48: Akron Children’s Hospital 2015 Gerry Haggerty Annual ......– Lean Design Principles Allowed Reduction in Service Line Build-outs by 34,000 SF or $12.2M – Reduction in Construction

As you leave, please remember:

Lean and IPD will give you the maximum

return on your investment.

Page 49: Akron Children’s Hospital 2015 Gerry Haggerty Annual ......– Lean Design Principles Allowed Reduction in Service Line Build-outs by 34,000 SF or $12.2M – Reduction in Construction

49

Name Title Contact Information

Don Taylor President & CEO, Welty Building

Company

[email protected]

234-678-1114

Michael Trainer Chief Financial Officer,

Treasurer, Akron Children’s

Hospital

[email protected]

330-543-4251

Alicia LaMancusa Vice President Finance, Akron

Children’s Hospital

[email protected]

330-543-8171

Tim Ziga Associate General Counsel,

Akron Children’s Hospital

[email protected]

330-543-4960

Sheryl Valentine Deployment Leader, COE,

Akron Children’s Hospital

[email protected]

330-543-8923


Recommended