ALERT GOLF MANAGEMENT SERVICES
Transcript
Page 1: Alert Golf

ALERT GOLFMANAGEMENT

SERVICES

Page 2: Alert Golf

Working Style

Page 3: Alert Golf

Project Site, Pujan, Staking & Visit

Page 4: Alert Golf

Clearing and Grubbing Related Activities

Page 5: Alert Golf

Major Earthworks

Page 6: Alert Golf

Feature Construction

Page 7: Alert Golf

Sieving, Feature Construction

Page 8: Alert Golf

Grassing, Water Body, Lining Works

Page 9: Alert Golf

Ready for Soft Opening

Page 10: Alert Golf

TENTATIVE SCHEDULE FOR THE CONSTRUCTION OF GOLF COURSE    May-14 Jun-14 Jul-14 Aug-14 Sep-14 Oct-14 Nov-14 Dec-14 Jan-15

  ACTIVITY/WEEK 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36

1 Survey and Staking                                                                       

2 Site Clearaning                                                                       

3 Earthwork                                                                       

4 Rough Shaping                                                                       

5 Irrigation Works

6 Feature Construction                                                                        

7 Topsoil placement                                                                       

8 Final Shaping                                                                       

9 Fine Dressing                                                                       

10 Fumigation                                                                       

11 Fecing Work for Driving Range                                                                        

12 Grassing SCHEDULE WILL DEPEND ENTIRELY ON COMPLETION OF IRRIGATION SYSTEM

WORK CHART

Page 11: Alert Golf

Equipment List

Name of equipment Quantity

JCB Escorts 3D 2 nos.Tippers 6 nos.Pocklain/ Excavator 1 no.Dozer D-5K 1 no.Water Tanker 1 no.H. Trolley 1 no.Hand Roller 0.5 Ton 1 no.Mechanical Roller 1 no.Tractor 3 nos.Tractor attachment: Scraper 2 nos.Box grader, Tiling, Ploughing & Harrow 1 no.Total Station (Survey) 1 no.

Apart from above mentioned equipment there will be lot of small equipment that are

tailor made for golf course works. We will be getting the best and modern hand tools

to ensure proper working.

Page 12: Alert Golf

Formats for Records and Reporting

Page 13: Alert Golf

Request for Inspection

Project : Golf Course Construction

Contractor : ALERT GOLF MANAGEMENT SERVICE

RFI No.     

StructureIdentification      

Sr. No. Description of Activity LocationInspection

RemarkDate Time

           

           

           Not Approved 

Remark Approved

Contractor's representative

   

   

Weston Representative

Name   Name

Date   Date

Signature   Signature

Page 14: Alert Golf

S. No. Activity Location Remarks

1

2

3

4

5

6

DAILY PROGRESS REPORT

DAY: WEATHER: DATE:

Page 15: Alert Golf

SITE PROGRESS REPORTLocation: Date:

MANPOWER

S. No. CATEGORY NOS. REMARKS

1 SKILLED

2 SEMI SKILLED

3 UNSKILLED #

4 STAFF

TOTAL

MACHINERY DEPLOYED AT SITE

S.NO. EQUIPMENT NOS WORKING HOURS

TOTAL HOURS WORKED

HRS NOT WORKED REMARKS

FROM TO

1 Tipper ( A )

2 Tipper ( B )

3 Excavator

4 Dozer D-4

5 Tractor

Page 16: Alert Golf

THANK YOU

HAPPY GOLFING